Lowest bidder emerges for Kuwait’s Doha desalination plant

19 August 2025

Kuwait-based Heavy Engineering Industries & Shipbuilding Company has submitted the lowest bid for a tender to supply, install, operate and maintain the second phase of the Doha seawater reverse osmosis (SWRO) desalination plant in Kuwait.

The project scope includes the installation of reverse osmosis desalination facilities, along with alkalinisation equipment for the treated water.

The bidders and their prices are:

  • Heavy Engineering Industries & Shipbuilding Company: KD114.28m ($373.2m)
  • Cox Water SL: KD164.80m ($538.1m)
  • Orascom Construction: KD174.13m ($568.4m)

The tender was issued by Kuwait’s Ministry of Electricity, Water & Renewable Energy, and the deadline closed on 5 August 2025.

The Doha SWRO desalination plant is part of Kuwait’s broader programme to expand water production capacity and reduce reliance on thermal desalination methods.

In April, MEED reported that Kuwait had retendered the contract for the facility.

The ministry had previously cancelled the initial tender in June last year. 

When it was first tendered, the Doha SWRO phase two project was expected to have a capacity of 60 million imperial gallons a day (MIGD).

The Ministry of Electricity & Water awarded South Korea’s Doosan Heavy Industries & Construction – now known as Doosan Enerbility – a $422m contract in May 2016 to build the 60 MIGD Doha 1 SWRO plant.

https://image.digitalinsightresearch.in/uploads/NewsArticle/14495721/main.gif
Mark Dowdall
Related Articles
  • Aramco plans to execute 85 projects in next three years

    8 September 2025

    Saudi Aramco plans to execute 85 projects over the next three years, most of which are currently in the planning phase.

    These new, expansion and upgrade projects span multiple business domains at Aramco – from core oil and gas production to pipeline networks and civil infrastructure – the company announced at the ongoing Future Projects Forum in Saudi Arabia’s capital Riyadh.

    “Award of these projects will translate into hundreds of contract packages located within different regions of the Kingdom of Saudi Arabia,” Sara Alkhonaiz, contracts adviser at Aramco’s Project Management Office Department/Market Research Unit, said at the conference.

    In the oil, gas and petrochemicals sector, Aramco plans to execute 20 projects.

    Of these, 17 projects involve oil, gas and refining facilities – specifically upgrades to sulphur recovery units, gas field compression systems and refining units.

    Two major petrochemicals projects have been earmarked for development: the Sasref+ project, part of the large-scale liquids-to-chemicals programme, and an integrated refining and petrochemicals complex that Alkhonaiz did not elaborate on.

    In the offshore domain, Aramco has identified six major projects involving the expansion or upgrade of offshore oil and gas platforms, as well as maintaining offshore potential.

    Additionally, 12 projects are planned in the pipeline division “to support our operations and distribution network”, Alkhonaiz said. These involve upgrades to trunklines and flowlines, pipeline replacements and maintaining onshore potential.

    Separately, the Saudi energy giant intends to advance 53 projects across civil infrastructure, marine and other related business lines, she added. Of these, 15 projects cover infrastructure development, expansion of residential facilities and upgrades to utilities systems.

    Project procurement demand

    Executing these planned projects will generate significant demand for products, equipment and long-lead items, requiring Aramco to launch a large-scale procurement drive, Alkhonaiz said.

    Materials required for these projects include:

    • 21,000 kilometres of carbon steel pipes
    • 2.2 million tonnes of structural steel
    • 41,000km of cables
    • 1,700km of transmission lines
    • 6,000 transformers
    • 24,000 switchgears
    • 113 million cubic metres of fill and compact
    • 3.3 million cubic metres of concrete

    Aramco had earlier announced a capital investment guidance in the range of $52bn to $58bn for 2025, excluding around $4bn of project financing.

    The state enterprise’s capital expenditure (capex) for Q2 2025 stood at $12.3bn –  a marginal year-on-year increase of 1.46%. For the first half of the year, the firm recorded capex of $24.85bn – a 9.5% increase compared to the same period last year.

    “We continue to invest in various initiatives, such as new energies and digital innovation with a focus on AI – aiming to leverage our scale, low cost and technological advancements for long-term success,” said Amin Nasser, Aramco’s president and CEO, in comments on the company’s second-quarter and first-half financial results.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14625866/main.jpeg
    Edward James
  • Saudi Water Authority awards transmission contract

    8 September 2025

     

    Saudi Services for Electro Mechanic Works has been appointed as the main contractor for package B of phase one of the Riyadh Northern Ring water transmission system. The contract is valued at $146m.

    The scope of work includes laying water pipelines, constructing pumping stations, building water diversion structures, carrying out infrastructure works and constructing associated facilities.

    The Riyadh Northern Ring water transmission system is being developed by Saudi Water Authority (SWA) as part of a $266m masterplan to expand the capital’s water supply capacity.

    Phase 1 involves the construction of multiple large reservoirs, ranging in size from 60,000 to 170,000 cubic metres, as well as pumping stations and transmission pipelines.

    Package B focuses on the transmission pipeline and related works. In parallel, package C, valued at $120m, covers the construction of strategic reservoirs in Shaqra, Ghanman, Majmaah and Alghat. Al-Rawaf Trading & Contracting won this contract and began construction work earlier this year.

    SWA, formerly Saline Water Conversion Corporation (SWCC), also recently awarded the contract to supply power to the Saad water station in Riyadh.

    This will establish a main transformer station at 132/33 kV to supply Saad Station 1 and Saad Station 2 with a combined load of 128 megavolt-amperes, replacing existing diesel generators.


    READ THE SEPTEMBER 2025 MEED BUSINESS REVIEW – click here to view PDF

    Doha’s Olympic bid; Kuwait’s progress on crucial reforms reinforces sentiment; Downstream petrochemicals investments take centre stage

    Distributed to senior decision-makers in the region and around the world, the September 2025 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/14624458/main.gif
    Mark Dowdall
  • Dubai selects Chinese contractor for Al-Safa Street upgrade

    8 September 2025

     

    Dubai’s Roads & Transport Authority (RTA) has selected Beijing-headquartered China Civil Engineering Construction Corporation for a contract to deliver the Al-Safa Street improvement project in Dubai.

    The project extends 1,500 metres from the junction of Al-Safa Street with Sheikh Zayed Road to the junction with Al-Wasl Street.

    The project involves the construction of two bridges and two tunnels with a total length of 3.1 kilometres (km), the widening of surface roads, and upgrades to intersections and traffic signal systems.

    The project will reduce the travel time on Al-Safa Street from 12 minutes to just three minutes, and double the street’s capacity from 6,000 to 12,000 vehicles an hour in both directions.

    It will serve as a gateway to some of Dubai’s key landmarks, including City Walk and the Coca-Cola Arena.

    US-based engineering firm CDM Smith is the project consultant.

    In June, MEED exclusively reported that the RTA had started the survey and soil testing for the Al-Safa Street improvement project.

    The early works are being undertaken by the local Al-Mawazeen Soil Testing & Surveying Company.

    Planning for growth

    In March 2021, the government launched the Dubai 2040 Urban Master Plan. Its launch referenced studies indicating that the emirate’s population will reach 5.8 million by 2040, up from 3.3 million in 2020. The daytime population is set to increase from 4.5 million in 2020 to 7.8 million in 2040.

    In December 2022, Sheikh Mohammed Bin Rashid Al-Maktoum, Vice President and Prime Minister of the UAE and Ruler of Dubai, approved the 20-Minute City Policy as part of the second phase of the Dubai 2040 Urban Master Plan. 

    In addition to the road projects, the RTA’s Dubai Metro Blue Line extension forms part of Dubai’s plans to improve residents’ quality of life by cutting journey times, as outlined in the policy.

    The policy aims for residents to be able to meet 80% of their daily requirements within a 20-minute journey time, either on foot or by bicycle. This goal will be achieved by developing integrated service centres with all the necessary facilities and increasing the population density around mass transit stations.


    READ THE SEPTEMBER 2025 MEED BUSINESS REVIEW – click here to view PDF

    Doha’s Olympic bid; Kuwait’s progress on crucial reforms reinforces sentiment; Downstream petrochemicals investments take centre stage

    Distributed to senior decision-makers in the region and around the world, the September 2025 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/14624644/main.jpg
    Yasir Iqbal
  • Iraq signs Oman oil agreements

    8 September 2025

    Iraq’s State Oil Marketing Organisation (Somo) has signed two agreements with Oman’s OQ group, including one to develop an oil storage facility with a capacity of 10 million barrels.

    The memorandums of understanding (MoUs) were signed during the official visit of Iraqi Prime Minister Mohammed Shia Al-Sudani to Oman.

    They mark a new chapter in Oman-Iraq energy relations and reinforce the role of both nations as “key hubs in global crude markets”, OQ said in a statement.

    Under the terms of the first MoU, the OQ subsidiary Oman Tank Terminal Company (OTTCO), which operates a major crude oil storage terminal at Ras Markaz near Duqm, will collaborate with Somo on the development of an integrated crude oil project at Ras Markaz.

    The company said that, in its initial phases, the project will include storage, loading and unloading facilities, with a starting capacity of 10 million barrels, expandable in the future.

    OQ said: “The first memorandum establishes a large-scale crude storage project at Ras Markaz with an initial capacity of 10 million barrels, creating modern infrastructure to support global distribution.”

    OTTCO said: “This strategic partnership reflects the strong relations between the Sultanate of Oman and the Republic of Iraq, and underscores OTTCO’s ambitious vision to position Duqm as a regional energy hub while opening new horizons for growth and economic integration.”

    The large-scale crude storage project is expected to support the global distribution of Iraqi oil.

    Under the terms of the second MoU, OQ Trading, the commodities trading arm of OQ Group, agreed to collaborate with Somo on the international marketing of Iraqi crude.

    OQ said: “Together, these memoranda extend beyond trade. They embody a shared commitment to building sustainable economic ties, exchanging knowledge and advancing OQ’s ambition to grow as a trusted global partner in energy investment and trade.”

    Iraq is also considering building a pipeline to export crude oil to Oman – a move that would help the country market its crude globally and keep the planned storage facility in the sultanate well supplied, according to Somo.

    Somo has said that there is already an “agreement in principle” and that discussions on the pipeline’s route and capacity will be part of future contract negotiations.

    The Ras Markaz terminal currently supplies the Duqm refinery via an 80-kilometre pipeline, transporting crude oil directly from Ras Markaz to the refinery.

    Its storage facilities comprise eight large oil tanks, floating platforms for import and export operations, seven kilometres of subsea pipelines for receiving and dispatching oil, and a pumping station connected to the storage tanks.

    In April, OTTCO signed an agreement with Royal Vopak of the Netherlands to support the development of an integrated hub at the Special Economic Zone at Duqm (Sezad) for the storage and handling of hydrocarbons, chemicals and low-carbon products. The collaboration also focuses on building industrial and energy terminal infrastructure, including storage solutions for oil, chemicals, liquefied petroleum gas, liquefied natural gas, hydrogen, ammonia and carbon dioxide.


    READ THE SEPTEMBER 2025 MEED BUSINESS REVIEW – click here to view PDF

    Doha’s Olympic bid; Kuwait’s progress on crucial reforms reinforces sentiment; Downstream petrochemicals investments take centre stage

    Distributed to senior decision-makers in the region and around the world, the September 2025 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/14623472/main.jpg
    Wil Crisp
  • Kuwait awards remediation contract

    8 September 2025

     

    Kuwaiti contractor Khalid Ali Al-Kharafi & Brothers Company has been awarded a remediation contract at Kuwait’s Wafra oil field and the contract has been signed, according to industry sources.

    The client on the project is Kuwait Gulf Oil Company (KGOC).

    Under the terms of the contract, Kharafi will process oil sludge at the oil field, reducing contamination levels.

    The contract was awarded directly without an open tender due to Kharafi’s performance on other remediation projects in Kuwait, sources said.

    Under the terms of the contract, payment will be based on the volumes of polluted soil that are treated.

    The minimum value of the contract has been set at $10m over a time period of one year.

    Under the scope of the project, there are around 700,000 cubic metres of sludge available to be processed.

    Sources close to the project understand that Kharafi could process between 100,000 and 200,000 cubic metres of sludge during the time period.

    If Kharafi processes 100,000 cubic metres, it will receive a payment of $100m, sources said. This sum will be doubled if it processes 200,000 cubic metres.

    Environmental projects

    Over recent years, Kharafi has gained significant experience working on remediation projects.

    The company is executing two major oil clean-up contracts with state-owned upstream operator Kuwait Oil Company (KOC).

    The contracts are part of the multibillion-dollar project known as the Kuwait Environmental Remediation Programme (Kerp).

    Khalid Ali Al-Kharafi & Brothers is executing its Kerp projects in partnership with Lamor Corporation, a Finland-based company specialising in oil spill response, waste management and water treatment.

    KOC awarded the two companies the two major oil remediation contracts in June 2021. Each package involves remediating 2.6 million cubic metres of soil

    One of the packages, the North Kuwait Excavation, Transportation and Remediation Project-2A (NKETR-2A), has a value of $194m.

    The second contract, worth $197m, is known as the South Kuwait Excavation, Transportation and Remediation Project-2A (SKETR-2A).

    Kerp is the largest environmental remediation project in the world and was established by the UN Compensation Commission to allow Kuwait to address the ecological damage resulting from the 1990-91 Gulf War.

    The new contract focused on the Wafra field is not part of Kerp.

    The Wafra field is located in the Partitioned Zone between Kuwait and Saudi Arabia.

    Both countries equally share the natural resources contained in this region.

    The area is operated jointly by KGOC, which represents Kuwait, and Saudi Arabian Chevron, which represents Saudi Arabia.

    In 2024, Kuwait Petroleum Corporation (KPC) chief executive Sheikh Nawaf Al-Sabah reiterated that his company plans to increase its oil production capacity to 4 million barrels a day by 2035.

    About 90% of Kuwait’s oil production comes from KOC, which also plans to achieve a daily gas production capacity of 1.5 trillion cubic feet by 2040

    Kuwait is estimated to have 100 billion barrels of oil reserves.

    Under KPC’s 2040 strategy, it plans to invest $410bn, which will come from its cash flow, debt and joint ventures with other businesses.

    Out of the $410bn, KPC and its subsidiaries intend to invest $110bn to accomplish the group’s energy transition targets.


    MEED’s September 2025 report on Kuwait includes:

    > GOVERNMENT: Kuwait looks to capitalise on consolidation of power
    > ECONOMY: Kuwait aims for investment to revive economy
    > BANKING: Change is coming for Kuwait’s banks
    > OIL & GAS: Kuwaiti oil activity rising after parliament suspension
    > POWER & WATER: Signs of project progress for Kuwait's power and water sector
    > CONSTRUCTION: Momentum builds in Kuwait construction

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/14623400/main.gif
    Wil Crisp