Local firms rise in GCC Power Developer Ranking
24 September 2024
Two Saudi Arabia-headquartered firms have joined Acwa Power in the top 10 of MEED’s 2024 GCC Power Developer Ranking.
Aljomaih Energy & Water Company and Ajlan & Bros have entered the list, occupying the sixth and ninth spots, respectively.
The latest developer ranking included a survey of 109 privately owned and financed power generation plants in the six GCC states, including those with attached water desalination facilities. These plants have a collective gross electricity generation capacity of approximately 112,400MW.
These projects include seven solar, two wind and two gas-fired plants, as well as one industrial steam and cogeneration facility, with a total combined gross capacity of 19,635MW, for which contracts were awarded between September 2023 and August 2024.
Of the total capacity awarded during the 12-month period, solar photovoltaic (PV) and wind capacity accounted for 58%, or 11,400MW. Three solar PV contracts with a total capacity of 5,500MW, directly negotiated between Saudi Arabia’s Public Investment Fund (PIF) and a team led by Riyadh-headquartered Acwa Power, comprised nearly half of the awarded renewable IPP capacity.
These three contracts, along with a fourth for the development and operation of the 3,800MW Taiba 1 and Qassim 1 combined-cycle gas turbine (CCGT) IPP, helped boost Acwa Power’s dominance over its competitors.
Acwa Power's 35.1% stake in the 2,000MW Haden, the 2,000MW Muwayh and 1,500MW Al-Khushaybi solar PV projects, and its 40% share in Taiba 1 and Qassim 1, increased the company's total net capacity by 3,200MW, up 23% from last year’s 13,340MW. This figure takes into account the dilution of its shares in Rabigh Arabian Water & Electricity Company. As a result of the contracts it won, Acwa Power’s gross capacity also rose by 8,800MW to reach a total of 45,150MW.
Acwa Power has occupied the top spot in MEED’s GCC Power Developer Ranking in terms of net capacity since 2021, but it overtook its main rival, French utility developer and investor Engie, in terms of gross capacity only the following year.
Excluding the capacity of the directly negotiated solar IPP contracts that Acwa Power secured with the PIF in the past
three years does not change the company’s dominant position in the ranking, although it decreases its net and gross capacities by 25% and 24%, respectively.
Contenders
With no new contracts won, Engie still managed to retain second place in the ranking, with a net capacity of close to 8,000MW.
The successful bids of a team comprising Japan’s Marubeni Corporation and Ajlan & Bros for the contracts to develop and operate the 600MW Al-Ghat and 500MW Waad Al-Shamal wind schemes in Saudi Arabia increased Marubeni’s net capacity to 4,257MW, up 555MW compared to the previous year.
As with Engie, Japan’s Mitsui did not win any new contracts but retained its fourth place in the ranking, just above EDF, which climbed two positions to claim this year’s fifth spot and registered a net capacity that nearly doubled to reach 2,047MW.
EDF’s impressive performance accrued from its equities in three contracts: the 1,100MW Hinakiyah solar PV and the 3,960MW Taiba 2 and Qassim 2 CCGT projects in Saudi Arabia, and Abu Dhabi’s 1,500MW Al-Ajban solar PV scheme.
EDF knocked Japanese developer Sumitomo down the ranking; it landed in the seventh spot this year. Saudi Arabia’s Aljomaih Energy & Water Company – which was not part of the top 10 last year – rose past Sumitomo to claim sixth position.
Aljomaih’s 30% shareholding in the Taiba 2 and Qassim 2 IPP increased its net capacity by close to 1,200MW from just 775MW in the previous 12-month period.
Previously ranked sixth, Japan’s Jera fell to eighth place, despite having won the contract to develop the Najim cogeneration plant catering to Saudi Arabia’s Amiral petrochemicals complex, which it secured along with Abu Dhabi National Energy Company (Taqa).
Below Jera in the ranking is Ajlan & Bros, which is Marubeni’s partner for the contract to develop the Al-Ghat and Waad Al-Shamal wind IPPs. Ajlan is also understood to have taken a 30% stake in the consortium that won the contract to develop the Taiba 2 and Qassim 2 CCGT project.
China’s Jinko Power rounded out the top 10. It led the team that won the contract to develop the 400MW Tubarjal solar IPP in Saudi Arabia in November last year.
Local developers
The rise of Aljomaih and Ajlan & Bros, which led to South Korea’s Korea Electric Power Corporation (Kepco) and Singapore’s Sembcorp dropping out of the power developer ranking’s top 10 this year, confirms the improving profile of regional utility developers.
The resurgence of gas-fired power generation IPPs – in part due to Saudi Arabia’s liquid fuel displacement programme and the overall demand for baseload to address rising renewable energy capacity – is helping local developers to strengthen their footing.
“The reduced interest from European and Japanese contractors in bidding for gas-fired power generation projects could present an opportunity for local developers and investors,” says a senior executive with an international developer.
“As these firms are less constrained by their 2040-50 net-zero targets, they might focus on efficiency and quick deployment rather than on adhering to decarbonisation timelines, allowing for more flexibility in CCGT projects.”
The fact that only two teams submitted bids for the contracts to develop the next pair of CCGT IPPs in Saudi Arabia supports this observation. Similarly, Qatar’s General Electricity & Water Corporation (Kahramaa) received only one bid from a team led by Sumitomo for the contract to develop the Facility E independent water and power producer (IWPP) project earlier this year.
Conscious of its own net-zero targets, and those of its partners, Abu Dhabi state utility Emirates Water & Electricity Company (Ewec) is adopting a slightly different approach for its next CCGT project in Taweelah by announcing that a carbon-capture facility will be installed as part of the project once such solutions become commercially viable.
In addition, the power-purchase agreement (PPA) for Taweelah C is expected to expire by 2049, making it several years shorter than previous PPAs and in line with the UAE's plan to reach net-zero carbon emissions by 2050.
So far, the market has responded positively, with nine companies having met Ewec’s prequalification requirements for Taweelah C.
However, the scale and volume of gas and renewable energy projects planned by Saudi Arabia, which has said it could procure up to 20GW of renewable energy capacity annually starting this year, is expected to continue to boost the net capacity of local developers and their less net-zero-constrained counterparts for the foreseeable future.
There is also an expectation that the exclusion of Acwa Power from the latest round of tenders for Saudi Arabia’s National Renewable Energy Programme (NREP) could further open up opportunities for other companies, regardless of their origin and net-zero targets.
Tariffs
There are mixed expectations in terms of how levelised electricity costs (LCOE) will behave over the next 12 months. Compared to the preceding decade, when unsubsidised renewable energy production costs consistently and sharply declined, tariffs have become less predictable since 2022.
In the region, solar PV tariffs in particular have trended upward since Acwa Power offered to develop the Shuaibah 1 solar IPP scheme for $cents 1.04 a kilowatt-hour (kWh) in 2020-21.
These tariffs have remained highly competitive relative to those seen in other, less renewable energy-intense regions, however, disincentivising some developers that felt they could not compete on price.
The next six to 12 months could prove decisive, according to one industry expert.
“It is possible that the surge in renewable projects could limit the availability of competent engineering, procurement and construction (EPC) contractors. The combination of aggressive national targets and competition for EPC services may drive up prices and slow project timelines,” the Dubai-based executive tells MEED.
“With raw materials and commodity prices trending downward, it's feasible that renewable energy tariffs could remain low in the short term. However, sustained record-low tariffs will also depend on the availability of financing, local regulations and grid integration costs.”
The LCOE trend for gas-fired power generation schemes seems more predictable.
According to the executive, the limited capacity of original equipment manufacturers, particularly for turbines and other key components of CCGT plants, will likely push tariffs up over the next 12 months.
“Limited availability of high-efficiency equipment will increase procurement costs and construction timelines, influencing the overall project cost.”
This extends to CCGTs incorporating carbon capture, where the LCOE will likely increase due to additional capital and operational expenses. “Whether these costs are absorbed through renegotiation or passed on to the state offtaker will depend on the power-purchase agreement structure,” he says.
Exclusive from Meed
-
Kuwait retenders Doha desalination package
30 April 2025
-
Kuwait tenders 900MW Subiya plant contract
30 April 2025
-
Read the May 2025 MEED Business Review
30 April 2025
-
Oman seeks firms for geothermal plant study
30 April 2025
-
Kurdistan plant to deploy GE Vernova technology
30 April 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends

Related Articles
-
Kuwait retenders Doha desalination package
30 April 2025
Kuwait’s Electricity, Water and Renewable Energy Ministry (MEWRE) has retendered a contract to design and build the planned second phase of a seawater reverse osmosis (SWRO) plant in Doha.
The Doha SWRO phase two project was expected to have a capacity of 60 million imperial gallons a day (MIGD) when it was first tendered.
The tender closing date for the retendered contract is 27 May.
The scope of work entails the supply, installation, operation and maintenance of phase 2 of the Doha SWRO plant, inclusive of alkalinisation equipment for produced water.
The ministry cancelled the tender for the contract in June last year.
Contractors submitted bids for the contract in September 2022. At the time, the MEW did not disclose the engineering, procurement and contracting firms that were invited to bid for the contract.
The MEW awarded South Korea’s Doosan Heavy Industries & Construction, now known as Doosan Enerbility, the $422m contract to build the 60MIGD Doha 1 SWRO in May 2016.
https://image.digitalinsightresearch.in/uploads/NewsArticle/13784666/main.gif -
Kuwait tenders 900MW Subiya plant contract
30 April 2025
Kuwait’s Electricity, Water & Renewable Energy Ministry (MEWRE) has reissued the tender for a contract to build a combined-cycle gas turbine (CCGT) plant in Subiya.
The fourth phase of the Subiya power and water complex is expected to have a capacity of 900MW.
The ministry issued the tender on 27 April and expects to receive bids by 27 May.
The ministry announced earlier this month that the Kuwait Central Authority for Public Tenders has approved issuing the tender for the 36-month contract.
MEWRE first tendered the contract to design and build the 900MW Subiya phase 4 CCGT in 2022.
According to MEED Projects data, the bidders and their offers were:
- Al-Ghanim International General Trading & Contracting (local): $837.3m
- Al-Zain United General Trading & Contracting (local): $866.17m
MEED understands that Al-Ghanim International emerged as the preferred bidder after agreeing to a revised contract value of $662m.
The planned project, along with a scheme to convert an existing 250MW simple-cycle plant into a CCGT plant, aims to boost the generation capacity at the Subiya power complex by 1,150MW.
https://image.digitalinsightresearch.in/uploads/NewsArticle/13784621/main5321.gif -
Read the May 2025 MEED Business Review
30 April 2025
Download / Subscribe / 14-day trial access Global stock markets suffered some of their worst days on record following US President Donald Trump's announcement of his 'Liberation Day' tariffs on 2 April. Although a 90-day pause was quickly announced for most trading partners, the 10% baseline import duty and levies on aluminium and industrial metals led to selloffs across regional indices. Oil prices also took a hit, as Brent crude dropped to under $60 a barrel for the first time since 2021.
The GCC is well positioned to survive the trade wars, however. Oil, energy and various petrochemicals products remain exempt from US tariffs, and with low regulatory barriers and the capacity to engage in manufacturing-intensive activities, the region's economies pride themselves on being trade-friendly. By building on the strong relations that regional leaders enjoy with the Trump administration, GCC states can hope to emerge from the assault relatively unscathed.
In the May edition of MEED Business Review, we take an in-depth look at how regional governments hope to avoid the worst of the hits from US tariffs, examine the impact of the tariff regime on Gulf stock markets and assess the additional damage that falling prices will cause for oil exporters across the Middle East and North Africa region.
MEED's latest issue also includes a 17-page market report on the UAE, which explores how solid fiscal and macroeconomic fundamentals will help the country ride out the global uncertainty caused by the imposition of US tariffs. UAE financial institutions remain on a strong growth heading, and an expected increase in oil production, continued chemicals sector growth, expansionary government spending on infrastructure and renewed investment in real estate will all help the UAE to weather the storm.
In addition, this month's issue features MEED's 2025 GCC Contractor Ranking, which reveals an increase in orders across the region in the past year. While the GCC’s most active contractor is Saudi Arabia’s Nesma & Partners, with $13.9bn of work at the execution stage, Beijing-based China State Construction Engineering Corporation has continued to grow strongly to secure second place this year, just $300m behind Nesma with $13.5bn.
This issue is also packed with analysis. We examine the steps that are being taken by Damascus to reassure regional partners and lay the groundwork for the reconstruction of war-torn Syria; look at what Saudi Arabia and Oman are doing to attract local and international miners; and learn how UAE sovereign wealth fund Mubadala is investing in a low-carbon future.
In the May issue, the team also speaks exclusively to Walter Simpson, the former managing director of CC Energy Development (CCED), about the oil producer’s plans for growth in Oman; and Iain McBride, head of commercial for gigaproject multi-asset developer Roshn Group, who lays out the procurement strategy that is enabling the company to navigate the challenges presented by Saudi Arabia’s construction boom.
We hope our valued subscribers enjoy the May 2025 issue of MEED Business Review.
Must-read sections in the May 2025 issue of MEED Business Review include:
> AGENDA:
> GCC shelters from the trade wars
> Gulf markets slide as US tariff shockwaves hit
> Lower oil prices raise Gulf’s fiscal pressure> CURRENT AFFAIRS:
> Syria makes progress towards reunificationINDUSTRY REPORT:
2025 GCC contractor ranking
> Contractors take on more work in 2025> MINERALS: Saudi Arabia and Oman open up their minerals potential
> INTERVIEWS:
> CCED seeks growth in Oman’s hydrocarbons sector
> A case study in procurement> LEADERSHIP: Rethinking investments for a lower-carbon future
> UAE MARKET REPORT:
> COMMENT: UAE is poised to weather the storm
> GOVERNMENT & ECONOMY: UAE looks to economic longevity
> BANKING: UAE banks dig in for new era
> UPSTREAM: Adnoc in cruise control with oil and gas targets
> DOWNSTREAM: Abu Dhabi chemicals sector sees relentless growth
> POWER: AI accelerates UAE power generation projects sector
> CONSTRUCTION: Dubai construction continues to lead region
> TRANSPORT: UAE accelerates its $60bn transport push
> DATABANK: UAE growth prospects head north> MEED COMMENTS:
> Opec+ shows defiance in the face of sliding oil prices
> Corruption may hinder Iraqi oil pipeline reopening
> Mall of the Emirates sets trends again with $1.4bn revamp
> Abu Dhabi infrastructure entity will help forge partnerships> GULF PROJECTS INDEX: Gulf projects index inches upwards
> MARCH 2025 CONTRACTS: Region records $70.3bn of deal signings in first quarter of 2025
> ECONOMIC DATA: Data drives regional projects
> OPINION: Trump’s new world order
> BUSINESS OUTLOOK: Finance, oil and gas, construction, power and water contracts
To see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/13755806/main.gif -
Oman seeks firms for geothermal plant study
30 April 2025
Oman’s Nama Power & Water Procurement Company (PWP) has invited companies to bid for a contract to provide technical and economic consultancy services for the sultanate’s first planned geothermal power plant project.
Known as the Hot Springs geothermal project, the site being considered for the project’s first phase is the area between Wilayat Fanja and Al-Ansab in Wilayat Bausher in Muscat.
PWP expects to receive bids from technical and financial consultancy firms by 22 May.
The selected bidder will conduct a feasibility assessment of geothermal energy potential within the specified sites.
The project supports Oman Vision 2040 and renewable energy targets as well as its net-zero committed target.
The tender proceedings are under way for several renewable energy projects in Oman.
In February, PWP received four bids for the contract to develop and operate the Ibri 3 solar independent power producer (IPP) project.
The 500MW scheme is Oman’s fourth utility-scale solar power plant project.
The bidding process is also under way for two wind IPPs in Oman.
The Jalan Bani Bu Ali wind IPP will cater to the Main Interconnection System (MIS), while the Dhofar 2 wind IPP will cater to the smaller Dhofar Power System (DPS).
The Jalan Bani Bu Ali wind IPP, located in South Sharqiyah Governorate, will have a capacity of 91MW-105MW and has a commercial operation target of Q1 2027.
Adjacent to the existing Dhofar Wind 1 IPP in Shaleem and Al-Hallaniyat Islands in Dhofar Governorate, the Dhofar 2 wind plant will have a capacity of 114MW-132MW and will be operational in Q2 2027.
Photo credit: Pixabay, for illustrative purposes only
https://image.digitalinsightresearch.in/uploads/NewsArticle/13784148/main.jpg -
Kurdistan plant to deploy GE Vernova technology
30 April 2025
The 1,250 MW Bazyan power plant in the Iraqi Kurdistan region will deploy the US-based GE Vernova's first upgrade of its Advanced Gas Proven (AGP) technology that runs on its 9E.03 gas turbine fleet.
Known as AGP Xpand, the technology can increase their 9E.03 gas turbines' output by up to approximately 7%, with an approximately 1% incremental efficiency, GE Vernova said.
Taurus Energy, a portfolio company of Onex Group, operated the Bazyan power plant. Onex Group is a private energy group with a portfolio of power generation, utilities, energy trading, shipping and refining companies.
Qubad Talabani, deputy prime minister of the Kurdistan Regional Government, Kamal Mohammad Salih Khalil, Minister of Electricity in the Kurdistan Regional Government and Steven Bitner, consul general at the US Consulate General Erbil, along with other senior government officials and local business leaders witnessed the signing of the agreement held in Sulaymaniyah.
In addition to increasing the gas turbines' efficiency, the technology enables exhaust energy to increase by up to 2.6% to produce more steam or power, for combined heat and power (CHP) plants or combined cycle plants, like the Bazyan power plant.
Taurus is welcoming this technology, which could modernize its
The Bazyan power plant is powered by
Four GE Vernova 9E.03 and two 9F.04 gas turbines power the Basyan power plant, which uses natural gas as the primary fuel source and light fuel oil as backup fuel.
Taurus designed and engineered the power plant for baseload operations with an expected lifetime of 25-30 years.
The AGP XPAND upgrade is expected to enhance the current capacity and deliver additional, much-needed electricity to the Kurdistan Region as well as nearby cities and governorates such as Mosul and Salahaddin.
In addition, GE Vernova and Taurus Energy signed a new 17-year long-term service agreement covering four GE Vernova’s 9E units with the first 9E rotor life extension package in Iraq.
“By utilising Kurdistan Region’s natural gas resources and power generation capacity, we are laying the foundation to create an energy hub," said Saad Tayeb Hasan, Onex founder and chairman.
"Through projects like Bazyan, we can contribute to the efforts to meet local energy needs as well as transmit additional power to other parts of the country."
According to GE Vernova, it has added more than 19GW of power capacity in Iraq since 2011, built and energised more than 30 substations since 2015, and mobilised over $3bn in financing for energy projects since 2015.
https://image.digitalinsightresearch.in/uploads/NewsArticle/13783196/main.jpg