Local firms rise in GCC Power Developer Ranking

24 September 2024

 

Two Saudi Arabia-headquartered firms have joined Acwa Power in the top 10 of MEED’s 2024 GCC Power Developer Ranking.

Aljomaih Energy & Water Company and Ajlan & Bros have entered the list, occupying the sixth and ninth spots, respectively.

The latest developer ranking included a survey of 109 privately owned and financed power generation plants in the six GCC states, including those with attached water desalination facilities. These plants have a collective gross electricity generation capacity of approximately 112,400MW.

These projects include seven solar, two wind and two gas-fired plants, as well as one industrial steam and cogeneration facility, with a total combined gross capacity of 19,635MW, for which contracts were awarded between September 2023 and August 2024.

Of the total capacity awarded during the 12-month period, solar photovoltaic (PV) and wind capacity accounted for 58%, or 11,400MW. Three solar PV contracts with a total capacity of 5,500MW, directly negotiated between Saudi Arabia’s Public Investment Fund (PIF) and a team led by Riyadh-headquartered Acwa Power, comprised nearly half of the awarded renewable IPP capacity.

These three contracts, along with a fourth for the development and operation of the 3,800MW Taiba 1 and Qassim 1 combined-cycle gas turbine (CCGT) IPP, helped boost Acwa Power’s dominance over its competitors.

Acwa Power's 35.1% stake in the 2,000MW Haden, the 2,000MW Muwayh and 1,500MW Al-Khushaybi solar PV projects, and its 40% share in Taiba 1 and Qassim 1, increased the company's total net capacity by 3,200MW, up 23% from last year’s 13,340MW. This figure takes into account the dilution of its shares in Rabigh Arabian Water & Electricity Company. As a result of the contracts it won, Acwa Power’s gross capacity also rose by 8,800MW to reach a total of 45,150MW.

Acwa Power has occupied the top spot in MEED’s GCC Power Developer Ranking in terms of net capacity since 2021, but it overtook its main rival, French utility developer and investor Engie, in terms of gross capacity only the following year.

Excluding the capacity of the directly negotiated solar IPP contracts that Acwa Power secured with the PIF in the past
three years does not change the company’s dominant position in the ranking, although it decreases its net and gross capacities by 25% and 24%, respectively.

Contenders

With no new contracts won, Engie still managed to retain second place in the ranking, with a net capacity of close to 8,000MW.

The successful bids of a team comprising Japan’s Marubeni Corporation and Ajlan & Bros for the contracts to develop and operate the 600MW Al-Ghat and 500MW Waad Al-Shamal wind schemes in Saudi Arabia increased Marubeni’s net capacity to 4,257MW, up 555MW compared to the previous year.

As with Engie, Japan’s Mitsui did not win any new contracts but retained its fourth place in the ranking, just above EDF, which climbed two positions to claim this year’s fifth spot and registered a net capacity that nearly doubled to reach 2,047MW.

EDF’s impressive performance accrued from its equities in three contracts: the 1,100MW Hinakiyah solar PV and the 3,960MW Taiba 2 and Qassim 2 CCGT projects in Saudi Arabia, and Abu Dhabi’s 1,500MW Al-Ajban solar PV scheme.

EDF knocked Japanese developer Sumitomo down the ranking; it landed in the seventh spot this year. Saudi Arabia’s Aljomaih Energy & Water Company – which was not part of the top 10 last year – rose past Sumitomo to claim sixth position.

Aljomaih’s 30% shareholding in the Taiba 2 and Qassim 2 IPP increased its net capacity by close to 1,200MW from just 775MW in the previous 12-month period.

Previously ranked sixth, Japan’s Jera fell to eighth place, despite having won the contract to develop the Najim cogeneration plant catering to Saudi Arabia’s Amiral petrochemicals complex, which it secured along with Abu Dhabi National Energy Company (Taqa).

Below Jera in the ranking is Ajlan & Bros, which is Marubeni’s partner for the contract to develop the Al-Ghat and Waad Al-Shamal wind IPPs. Ajlan is also understood to have taken a 30% stake in the consortium that won the contract to develop the Taiba 2 and Qassim 2 CCGT project.

China’s Jinko Power rounded out the top 10. It led the team that won the contract to develop the 400MW Tubarjal solar IPP in Saudi Arabia in November last year.

Local developers

The rise of Aljomaih and Ajlan & Bros, which led to South Korea’s Korea Electric Power Corporation (Kepco) and Singapore’s Sembcorp dropping out of the power developer ranking’s top 10 this year, confirms the improving profile of regional utility developers.

The resurgence of gas-fired power generation IPPs – in part due to Saudi Arabia’s liquid fuel displacement programme and the overall demand for baseload to address rising renewable energy capacity – is helping local developers to strengthen their footing.

“The reduced interest from European and Japanese contractors in bidding for gas-fired power generation projects could present an opportunity for local developers and investors,” says a senior executive with an international developer.

“As these firms are less constrained by their 2040-50 net-zero targets, they might focus on efficiency and quick deployment rather than on adhering to decarbonisation timelines, allowing for more flexibility in CCGT projects.”

The fact that only two teams submitted bids for the contracts to develop the next pair of CCGT IPPs in Saudi Arabia supports this observation. Similarly, Qatar’s General Electricity & Water Corporation (Kahramaa) received only one bid from a team led by Sumitomo for the contract to develop the Facility E independent water and power producer (IWPP) project earlier this year.

Conscious of its own net-zero targets, and those of its partners, Abu Dhabi state utility Emirates Water & Electricity Company (Ewec) is adopting a slightly different approach for its next CCGT project in Taweelah by announcing that a carbon-capture facility will be installed as part of the project once such solutions become commercially viable.

In addition, the power-purchase agreement (PPA) for Taweelah C is expected to expire by 2049, making it several years shorter than previous PPAs and in line with the UAE's plan to reach net-zero carbon emissions by 2050.

So far, the market has responded positively, with nine companies having met Ewec’s prequalification requirements for Taweelah C.

However, the scale and volume of gas and renewable energy projects planned by Saudi Arabia, which has said it could procure up to 20GW of renewable energy capacity annually starting this year, is expected to continue to boost the net capacity of local developers and their less net-zero-constrained counterparts for the foreseeable future.

There is also an expectation that the exclusion of Acwa Power from the latest round of tenders for Saudi Arabia’s National Renewable Energy Programme (NREP) could further open up opportunities for other companies, regardless of their origin and net-zero targets.   

Tariffs

There are mixed expectations in terms of how levelised electricity costs (LCOE) will behave over the next 12 months. Compared to the preceding decade, when unsubsidised renewable energy production costs consistently and sharply declined, tariffs have become less predictable since 2022.

In the region, solar PV tariffs in particular have trended upward since Acwa Power offered to develop the Shuaibah 1 solar IPP scheme for $cents 1.04 a kilowatt-hour (kWh) in 2020-21.

These tariffs have remained highly competitive relative to those seen in other, less renewable energy-intense regions, however, disincentivising some developers that felt they could not compete on price.

The next six to 12 months could prove decisive, according to one industry expert.

“It is possible that the surge in renewable projects could limit the availability of competent engineering, procurement and construction (EPC) contractors. The combination of aggressive national targets and competition for EPC services may drive up prices and slow project timelines,” the Dubai-based executive tells MEED.

“With raw materials and commodity prices trending downward, it's feasible that renewable energy tariffs could remain low in the short term. However, sustained record-low tariffs will also depend on the availability of financing, local regulations and grid integration costs.”

The LCOE trend for gas-fired power generation schemes seems more predictable.

According to the executive, the limited capacity of original equipment manufacturers, particularly for turbines and other key components of CCGT plants, will likely push tariffs up over the next 12 months.

“Limited availability of high-efficiency equipment will increase procurement costs and construction timelines, influencing the overall project cost.”

This extends to CCGTs incorporating carbon capture, where the LCOE will likely increase due to additional capital and operational expenses. “Whether these costs are absorbed through renegotiation or passed on to the state offtaker will depend on the power-purchase agreement structure,” he says.

Brisk pace of IPP awards set to continue

https://image.digitalinsightresearch.in/uploads/NewsArticle/12556220/main.gif
Jennifer Aguinaldo
Related Articles
  • Acwa signs Mauritania gas IPP agreements

    2 July 2026

    Saudi Arabia's Acwa has announced it has signed the public-private partnership (PPP) and power purchase agreement (PPA) for the 230MW N'diago combined-cycle gas turbine (CCGT) power plant in Nouakchott, Mauritania.

    The agreements cover the development, financing, construction and operation of the project. They were signed in Nouakchott  in the presence of senior officials from the Mauritanian government and Acwa chairman Mohammad Abunayyan.

    The project is Mauritania's first large-scale gas-fired independent power project (IPP). It is also expected to be the country's first major gas-fired power plant procured through a PPP structure.

    The CCGT plant will provide 230MW of baseload generation capacity. It will use Mauritania's domestic natural gas resources to supply the national grid.

    Sepaarately, the Mauritanian Electricity Company (Somelec) has been advancing procurment for the construction of a 50MW solar power and battery enery storage systems (Bess) IPP project. In May, it issued an expression of interest (EoI) request.  

    Mauritania currently has several wind and solar power projects in the early study stages, according to regional project tracker MEED Projects.

    There are also plans to build a 1,200MW wind power plant near port Etienne in the bay province of Nouadhibou, for which, China Energy Engineering was appointed as the main contractor in 2024. 

    Meanwhile, Acwa's portfolio comprises 111 assets that are operational, under construction or in advanced development. These represent investments of SR468.9bn ($125bn).

    According to the company, it has a power generation capacity of 98GW, including 52.3GW of renewable energy, and manages 9.7 million cubic metres a day of desalinated water globally.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17525605/main.jpg
    Mark Dowdall
  • Saudi water sector awaits next catalyst

    2 July 2026

    Commentary
    Mark Dowdall
    Power & water editor

    Saudi Arabia’s water sector is entering a critical period as developers and investors wait for the next signal that the kingdom’s project pipeline is moving forward.

    Seven months have passed since preferred bidders were announced for the Arana and Hadda independent sewage treatment plant (ISTP) projects, which together will provide 350,000 cubic metres a day (cm/d) of treatment capacity. The projects had been expected to reach financial close in the second quarter of this year, but have yet to do so.

    In parallel, Saudi Arabia’s Vision Invest was selected as preferred bidder last December for the estimated $2bn Riyadh-Qassim independent water transmission pipeline (IWTP) project. It was reported at the time that the company had submitted a levelised tariff of SR2.627 ($0.70) a cubic metre, almost 20% below the next nearest bid. The project, which will comprise an 859-kilometre pipeline with transmission capacity of 685,000 cm/d, had been tipped to reach financial close this quarter.

    The uncertainty extends beyond projects awaiting financial close. The developer tender bid deadline was recently pushed back again for the $150m Riyadh East ISTP. Meanwhile, Saudi Arabia’s Water Transmission Company (WTCO) is understood to be reviewing the delivery model for the Jubail-Buraidah and Ras Mohaisen-Baha-Mecca independent water transmission system (IWTS) projects.

    According to sources familiar with the plans, WTCO is considering establishing a special purpose vehicle that would take equity stakes in both schemes. This could further delay procurement for a project that has already seen multiple deadline extensions. Sharakat’s next wave of independent water projects (IWPs) is also in the pipeline. The first of these is not expected to be tendered until early 2027.

    According to regional project tracker MEED Projects, Saudi Arabia’s water infrastructure sector recorded $3.14bn-worth of awards in the first half of this year, substantially lower than the $7.58bn recorded during the same period in 2025.

    While activity has slowed, the longer-term outlook remains unchanged. Population growth and industrial expansion continue to drive demand for desalination, wastewater treatment and water transmission infrastructure. In the meantime, key stakeholders are looking for the next clear signal that the project pipeline is regaining momentum.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17510220/main.jpg
    Mark Dowdall
  • Contractor wins Jeddah road expansion deal in Riyadh

    2 July 2026

     

    The Royal Commission for Riyadh City (RCRC) has awarded a contract for the Jeddah Road Development Project in Riyadh.

    Local construction firm Saudi Pan Kingdom (Sapac) won the contract.

    Spanning 29 kilometres, the scheme includes 14 bridges and five lanes.

    Designed to handle up to 353,000 vehicles a day, the road is expected to be completed by 2028, with mobilisation works already under way.

    The project forms part of the third package of the RCRC’s Riyadh Main and Ring Road Axes Development Programme, which was announced in January.

    The other schemes include:

    > Taif Road Development Project: The project stretches 15km and includes four bridges, each with four lanes. It also features two tunnels. It will have a capacity of up to 200,000 vehicles a day and will enhance connectivity between Riyadh’s southern and western districts and the city centre.

    Thumamah Road Development Project: The eastern section of the project will span 8km and include three bridges and three tunnels, linking the northern and eastern parts of Riyadh. The project will have a daily capacity of up to 200,000 vehicles.

    King Abdulaziz Road Development Project: The northern section of the project stretches 4.7km and will include four bridges, four lanes and one tunnel, with a capacity of up to 450,000 vehicles per day.

    Othman Bin Affan Road Development Project: The northern section will span 4.3km and include seven bridges and other related upgrades to enhance traffic flow across northern Riyadh. The project will have a daily capacity of up to 500,000 vehicles.

    Second phase of engineering enhancements for congested areas: This project targets eight locations across the city’s road network, where advanced engineering solutions will be applied to reduce congestion and improve intersection performance, increasing traffic capacity by 40% to 60%.

    The contract for the Jeddah Road Development Project is the latest of several high-profile deals awarded by the RCRC recently. In May, it awarded an estimated SR5bn ($1.3bn) contract to construct the Sheikh Jaber Al-Sabah Road project in Riyadh.

    That contract went to a joint venture of Riyadh-based Al-Rashid Trading & Contracting Company (RTCC) and Turkiye’s IC Ictas.

    Stretching 12km, the project runs from Khurais Road to Al-Thumama Road and is a key component of the Second Eastern Ring Road scheme.

    Works include five interchanges: Prince Bandar, King Abdullah, Imam Abdullah, Dammam Road and Al-Thumama.

    In 2021, Saudi Arabia’s Crown Prince Mohammed Bin Salman Bin Abdulaziz Al-Saud said the population of Riyadh would double to 15-20 million people by 2030. 

    He directed government entities to work closely with the RCRC to prepare the city’s development strategy.

    The RCRC’s major projects include Riyadh Metro, Riyadh Art, Sports Boulevard, King Salman International Park, Green Riyadh and several road development projects in the capital.


    READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Stress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.

    Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17523376/main.jpg
    Yasir Iqbal
  • Dubai announces First Al-Khail road development project

    2 July 2026

    Register for MEED’s 14-day trial access 

    Dubai’s Executive Council has announced the First Al-Khail Street Development project, which will run parallel to Sheikh Zayed Road.

    The scheme comprises a 15-kilometre elevated carriageway with three lanes in each direction.

    According to a Dubai Media Office statement, “The project will provide access to areas including Al-Barsha, Al-Quoz, Business Bay and Meydan.”

    “It is expected to serve more than 2.6 million people and reduce travel time on Sheikh Zayed Road by 51% during peak hours,” the statement added.

    Designed to accommodate more than 9,000 vehicles an hour, construction is expected to begin in the third quarter of 2027, with completion targeted for 2030.

    The development forms part of a wider AED18bn ($5bn) programme covering initiatives related to culture, trade, infrastructure, Emiratisation, finance, investment, urban planning and the city’s population census.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17523587/main.jpg
    Yasir Iqbal
  • Contractors submit Saudi Landbridge Riyadh section bids

    2 July 2026

     

    Contractors submitted proposals on 30 June for a design-and-build contract to construct the Riyadh Rail Link, a new north-to-south railway line across the capital.

    The scope includes a 35-kilometre double-track line connecting SAR’s North-South Railway to the Eastern Railway network.

    Issued on 29 January, the tender also covers the procurement, construction and installation of associated infrastructure, including viaducts, civil works, utility diversions/installations, signalling systems and other related works.

    Once delivered, the Riyadh Rail Link is expected to become a key component of the Saudi Landbridge railway.

    In January, SAR said it would deliver the Saudi Landbridge project through a “new mechanism” by 2034, after failing to reach an agreement with a Chinese consortium to construct it, as MEED reported.

    In an interview with local media, SAR CEO Bashar Bin Khalid Al-Malik said the consortium failed to meet local content requirements, and that the project would instead be delivered in several phases under a different procurement model.

    Negotiations have been under way between Saudi Arabia and China-backed investors interested in developing the scheme through a public-private partnership (PPP). Al-Malik put the project cost at about SR100bn ($26.6bn).

    Overall, it comprises more than 1,500km of new track. A core element is a 900km railway between Riyadh and Jeddah, providing the capital with direct freight access to King Abdullah Port on the Red Sea.

    Other key elements include upgrading the existing Riyadh-Dammam line, a bypass around the capital known as the Riyadh Link, and a connection between King Abdullah Port and Yanbu.

    The Saudi Landbridge is one of the kingdom’s most anticipated project programmes. First announced in 2004, it was put on hold in 2010 before being revived a year later. Rights-of-way issues, route alignment and the high cost have been among the main stumbling blocks.


    READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Stress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.

    Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17522174/main.jpg
    Yasir Iqbal