Local firms rise in GCC Power Developer Ranking

24 September 2024

 

Two Saudi Arabia-headquartered firms have joined Acwa Power in the top 10 of MEED’s 2024 GCC Power Developer Ranking.

Aljomaih Energy & Water Company and Ajlan & Bros have entered the list, occupying the sixth and ninth spots, respectively.

The latest developer ranking included a survey of 109 privately owned and financed power generation plants in the six GCC states, including those with attached water desalination facilities. These plants have a collective gross electricity generation capacity of approximately 112,400MW.

These projects include seven solar, two wind and two gas-fired plants, as well as one industrial steam and cogeneration facility, with a total combined gross capacity of 19,635MW, for which contracts were awarded between September 2023 and August 2024.

Of the total capacity awarded during the 12-month period, solar photovoltaic (PV) and wind capacity accounted for 58%, or 11,400MW. Three solar PV contracts with a total capacity of 5,500MW, directly negotiated between Saudi Arabia’s Public Investment Fund (PIF) and a team led by Riyadh-headquartered Acwa Power, comprised nearly half of the awarded renewable IPP capacity.

These three contracts, along with a fourth for the development and operation of the 3,800MW Taiba 1 and Qassim 1 combined-cycle gas turbine (CCGT) IPP, helped boost Acwa Power’s dominance over its competitors.

Acwa Power's 35.1% stake in the 2,000MW Haden, the 2,000MW Muwayh and 1,500MW Al-Khushaybi solar PV projects, and its 40% share in Taiba 1 and Qassim 1, increased the company's total net capacity by 3,200MW, up 23% from last year’s 13,340MW. This figure takes into account the dilution of its shares in Rabigh Arabian Water & Electricity Company. As a result of the contracts it won, Acwa Power’s gross capacity also rose by 8,800MW to reach a total of 45,150MW.

Acwa Power has occupied the top spot in MEED’s GCC Power Developer Ranking in terms of net capacity since 2021, but it overtook its main rival, French utility developer and investor Engie, in terms of gross capacity only the following year.

Excluding the capacity of the directly negotiated solar IPP contracts that Acwa Power secured with the PIF in the past
three years does not change the company’s dominant position in the ranking, although it decreases its net and gross capacities by 25% and 24%, respectively.

Contenders

With no new contracts won, Engie still managed to retain second place in the ranking, with a net capacity of close to 8,000MW.

The successful bids of a team comprising Japan’s Marubeni Corporation and Ajlan & Bros for the contracts to develop and operate the 600MW Al-Ghat and 500MW Waad Al-Shamal wind schemes in Saudi Arabia increased Marubeni’s net capacity to 4,257MW, up 555MW compared to the previous year.

As with Engie, Japan’s Mitsui did not win any new contracts but retained its fourth place in the ranking, just above EDF, which climbed two positions to claim this year’s fifth spot and registered a net capacity that nearly doubled to reach 2,047MW.

EDF’s impressive performance accrued from its equities in three contracts: the 1,100MW Hinakiyah solar PV and the 3,960MW Taiba 2 and Qassim 2 CCGT projects in Saudi Arabia, and Abu Dhabi’s 1,500MW Al-Ajban solar PV scheme.

EDF knocked Japanese developer Sumitomo down the ranking; it landed in the seventh spot this year. Saudi Arabia’s Aljomaih Energy & Water Company – which was not part of the top 10 last year – rose past Sumitomo to claim sixth position.

Aljomaih’s 30% shareholding in the Taiba 2 and Qassim 2 IPP increased its net capacity by close to 1,200MW from just 775MW in the previous 12-month period.

Previously ranked sixth, Japan’s Jera fell to eighth place, despite having won the contract to develop the Najim cogeneration plant catering to Saudi Arabia’s Amiral petrochemicals complex, which it secured along with Abu Dhabi National Energy Company (Taqa).

Below Jera in the ranking is Ajlan & Bros, which is Marubeni’s partner for the contract to develop the Al-Ghat and Waad Al-Shamal wind IPPs. Ajlan is also understood to have taken a 30% stake in the consortium that won the contract to develop the Taiba 2 and Qassim 2 CCGT project.

China’s Jinko Power rounded out the top 10. It led the team that won the contract to develop the 400MW Tubarjal solar IPP in Saudi Arabia in November last year.

Local developers

The rise of Aljomaih and Ajlan & Bros, which led to South Korea’s Korea Electric Power Corporation (Kepco) and Singapore’s Sembcorp dropping out of the power developer ranking’s top 10 this year, confirms the improving profile of regional utility developers.

The resurgence of gas-fired power generation IPPs – in part due to Saudi Arabia’s liquid fuel displacement programme and the overall demand for baseload to address rising renewable energy capacity – is helping local developers to strengthen their footing.

“The reduced interest from European and Japanese contractors in bidding for gas-fired power generation projects could present an opportunity for local developers and investors,” says a senior executive with an international developer.

“As these firms are less constrained by their 2040-50 net-zero targets, they might focus on efficiency and quick deployment rather than on adhering to decarbonisation timelines, allowing for more flexibility in CCGT projects.”

The fact that only two teams submitted bids for the contracts to develop the next pair of CCGT IPPs in Saudi Arabia supports this observation. Similarly, Qatar’s General Electricity & Water Corporation (Kahramaa) received only one bid from a team led by Sumitomo for the contract to develop the Facility E independent water and power producer (IWPP) project earlier this year.

Conscious of its own net-zero targets, and those of its partners, Abu Dhabi state utility Emirates Water & Electricity Company (Ewec) is adopting a slightly different approach for its next CCGT project in Taweelah by announcing that a carbon-capture facility will be installed as part of the project once such solutions become commercially viable.

In addition, the power-purchase agreement (PPA) for Taweelah C is expected to expire by 2049, making it several years shorter than previous PPAs and in line with the UAE's plan to reach net-zero carbon emissions by 2050.

So far, the market has responded positively, with nine companies having met Ewec’s prequalification requirements for Taweelah C.

However, the scale and volume of gas and renewable energy projects planned by Saudi Arabia, which has said it could procure up to 20GW of renewable energy capacity annually starting this year, is expected to continue to boost the net capacity of local developers and their less net-zero-constrained counterparts for the foreseeable future.

There is also an expectation that the exclusion of Acwa Power from the latest round of tenders for Saudi Arabia’s National Renewable Energy Programme (NREP) could further open up opportunities for other companies, regardless of their origin and net-zero targets.   

Tariffs

There are mixed expectations in terms of how levelised electricity costs (LCOE) will behave over the next 12 months. Compared to the preceding decade, when unsubsidised renewable energy production costs consistently and sharply declined, tariffs have become less predictable since 2022.

In the region, solar PV tariffs in particular have trended upward since Acwa Power offered to develop the Shuaibah 1 solar IPP scheme for $cents 1.04 a kilowatt-hour (kWh) in 2020-21.

These tariffs have remained highly competitive relative to those seen in other, less renewable energy-intense regions, however, disincentivising some developers that felt they could not compete on price.

The next six to 12 months could prove decisive, according to one industry expert.

“It is possible that the surge in renewable projects could limit the availability of competent engineering, procurement and construction (EPC) contractors. The combination of aggressive national targets and competition for EPC services may drive up prices and slow project timelines,” the Dubai-based executive tells MEED.

“With raw materials and commodity prices trending downward, it's feasible that renewable energy tariffs could remain low in the short term. However, sustained record-low tariffs will also depend on the availability of financing, local regulations and grid integration costs.”

The LCOE trend for gas-fired power generation schemes seems more predictable.

According to the executive, the limited capacity of original equipment manufacturers, particularly for turbines and other key components of CCGT plants, will likely push tariffs up over the next 12 months.

“Limited availability of high-efficiency equipment will increase procurement costs and construction timelines, influencing the overall project cost.”

This extends to CCGTs incorporating carbon capture, where the LCOE will likely increase due to additional capital and operational expenses. “Whether these costs are absorbed through renegotiation or passed on to the state offtaker will depend on the power-purchase agreement structure,” he says.

Brisk pace of IPP awards set to continue

https://image.digitalinsightresearch.in/uploads/NewsArticle/12556220/main.gif
Jennifer Aguinaldo
Related Articles
  • Chinese firm announces $1.9bn Abu Dhabi renewables contract

    23 March 2026

    China Power Construction Corporation (PowerChina) has announced details of a contract signed for the engineering, procurement and construction (EPC) works on part of Abu Dhabi’s $6bn round-the-clock solar and battery storage project.

    The independent power project (IPP) will combine 5.2GW of solar photovoltaic (PV) capacity with 19GWh of battery storage. Last October, Emirates Water & Electricity Company (Ewec) and Abu Dhabi Future Energy Company (Masdar) broke ground on what will be the world’s largest combined solar and battery energy storage system (bess), designed to supply 1GW of round-the-clock power.

    India’s Larsen & Toubro and Beijing-headquartered PowerChina were awarded the EPC contract for the project last year, with PwC Middle East advising Ewec on financial structuring.

    According to the Chinese firm, the full project has been divided into two blocks, north and south, indicating at least two major packages. 

    PowerChina’s contract, valued at about $1.9bn, covers the northern block of the project, which includes 2.1GW of DC-side PV installations and a 7.75GWh bess. The scope includes the design, procurement and construction of substations, PV facilities and battery energy storage systems.

    Located in the Mshayrif area of Abu Dhabi, the wider project is designed to supply steady delivery of power between April and October each year, the UAE’s peak electricity demand season due to cooling loads.

    This includes serving large energy users that require 24/7 clean electricity, such as fast-growing data centre operators and technology firms driving artificial intelligence deployment in the region.

    Ewec will act as the offtaker under a long-term power purchase agreement.

    MEED previously reported that China’s CATL (Contemporary Amperex Technology Co), Jinko Solar and JA Solar will supply the bess and PV modules, with Jinko and JA each providing 2.6GW of modules. 

    The project will avoid 5.7 million tonnes of CO₂ emissions annually and provide enough clean energy to power nearly half a million homes.

    Construction is expected to be completed in 2028.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16083288/main.jpg
    Mark Dowdall
  • Kuwait tenders major infrastructure packages

    23 March 2026

     

    Kuwait’s Ministry of Public Works (MPW) has tendered several contracts for infrastructure works across various parts of the country.

    The first tender covers the construction of rainwater drainage systems in the Sabah Al-Ahmad South, Sabah Al-Ahmad, Al-Khairan and Al-Wafra residential areas.

    The second tender includes the construction of a treated water system in Kuwait’s southern region.

    The third tender covers the construction of a treated water system in Kuwait’s northern region.

    The final tender covers the construction of roads, bridges, stormwater drainage, sewage and other services for a section of the Kabd-Sulaibiya Road, as well as a section of the Kabd-Sulaibiya industrial road link.

    MPW issued all of these tenders on 22 March, with a bid submission deadline of 21 April.

    UK analytics firm GlobalData expects Kuwait’s construction industry to grow by 5.1% in 2026-29, supported by government investment in the oil and gas sector aimed at raising production, as well as investment in the infrastructure sector.

    In the short term, growth will be boosted by planned expenditure under the 2025-26 budget, which was approved in March 2025.

    The construction industry in Kuwait is expected to record an annual average growth rate of 4.9% in 2026-29, supported by investments in renewable energy, transport, and oil and gas projects.

    The commercial construction sector is expected to grow by 4.8% in 2026-29, supported by public and private sector investment in the construction of hotels, retail outlets and office buildings.


    READ THE MARCH 2026 MEED BUSINESS REVIEW – click here to view PDF

    Riyadh urges private sector to take greater role; Chemical players look to spend rationally; Economic uptick lends confidence to Cairo’s reforms.

    Distributed to senior decision-makers in the region and around the world, the March 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16083252/main.jpg
    Yasir Iqbal
  • Qiddiya tenders new infrastructure package

    23 March 2026

     

    Saudi Arabian gigaproject developer Qiddiya Investment Company (QIC) has tendered a contract inviting firms to bid for new infrastructure works in Qiddiya Entertainment City.

    The scope covers two infrastructure development packages in District 0 of Qiddiya Entertainment City, including the construction of four event park-and-ride facilities.

    The tender was issued on 11 March, with a bid submission deadline of 22 April.

    Lebanese firm Dar Al-Handasah and Saudi-based Sets International are serving as project consultants.

    QIC is accelerating plans to develop additional assets at Qiddiya City. Earlier this month, the company set a 16 April deadline for firms to submit prequalification statements for the Qiddiya high-speed rail project in Riyadh.

    Previously, MEED reported that QIC had received bids from contractors on 23 February for a SR980m ($261m) contract covering the construction of staff accommodation at Qiddiya Entertainment City.

    The project will cover an area of more than 105,000 square metres (sq m).

    Last month, QIC started the main construction works on its performing arts centre at Qiddiya Entertainment City.

    The Qiddiya City performing arts centre is one of several major projects within the greater Qiddiya development. Other projects include an e-games arena, Prince Mohammed Bin Salman Stadium, a motorsports track, the Dragon Ball and Six Flags theme parks, and Aquarabia.

    In December last year, QIC officially opened the Six Flags theme park to the public.

    The theme park covers an area of 320,000 sq m and features 28 rides and attractions, 10 of which are thrill rides and 18 designed for families and young children.

    The Qiddiya project is a key part of Riyadh’s strategy to boost leisure tourism in the kingdom. According to UK analytics firm GlobalData, leisure tourism in Saudi Arabia has experienced significant growth in recent years.

    The kingdom’s tourism sector posted record-breaking numbers last year, with over 130 million domestic and international visitors entering the kingdom, representing a 6% increase over 2024.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16083013/main.jpg
    Yasir Iqbal
  • Kuwait’s Mina Al-Ahmadi refinery attacked

    23 March 2026

    Register for MEED’s 14-day trial access 

    Several units were shut down at Kuwait’s largest oil refinery after it was hit by drones as Iran targeted energy infrastructure across the Gulf, according to a statement from state-owned Kuwait Petroleum Corporation (KPC).

    Fires broke out across multiple units at the Mina Al-Ahmadi refinery in the morning of 20 March 2026 following the attack.

    The refinery normally processes about 730,000 barrels of oil a day.

    There were no casualties as a result of the attack, according to KPC.

    Kuwait’s oil and gas sector has been severely disrupted by the ongoing regional conflict.

    On 10 March, MEED revealed that the state-owned upstream operator Kuwait Oil Company (KOC) was operating with just 30% of its total workforce in their normal workplaces.

    Earlier in the month, KPC also declared force majeure due to difficulties transporting oil and gas through the Strait of Hormuz caused by the conflict.

    Force majeure, a French term meaning “superior force”, is a clause included in many international commercial contracts. It allows companies to suspend contractual obligations when extraordinary events occur beyond their control.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16067425/main.gif
    Wil Crisp
  • Iraq declares force majeure on foreign-operated oil fields

    23 March 2026

    Register for MEED’s 14-day trial access 

    Iraq has declared force majeure on all oil fields developed by foreign oil companies as the US and Israel’s war with Iran disrupts navigation through the Strait of Hormuz.

    The initial attack and Iran’s response have slashed Iraq’s exports.

    Prior to the war starting on 28 February, Iraq was exporting between 3.3 and 3.5 million barrels a day of crude oil.

    Oil sales account for nearly 90% of Iraq’s government revenues.

    Earlier this month, two drone strikes hit infrastructure at Iraq’s Majnoon oil field, increasing security concerns in the country’s energy sector.

    One of the drones hit a communications tower, and the other hit the office of the US engineering company KBR.

    There were no casualties as a result of the attacks.

    Foreign workers were evacuated from the site days after the US and Israel’s war with Iran started, and only Iraqi staff are currently working at the site.

    Shortly before the war started, KBR announced that it had been awarded a “major contract” by Iraq’s state-owned Basra Oil Company to provide integrated field management services for the Majnoon oil field.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16067302/main.png
    Wil Crisp