Local firms rise in GCC Power Developer Ranking

24 September 2024

 

Two Saudi Arabia-headquartered firms have joined Acwa Power in the top 10 of MEED’s 2024 GCC Power Developer Ranking.

Aljomaih Energy & Water Company and Ajlan & Bros have entered the list, occupying the sixth and ninth spots, respectively.

The latest developer ranking included a survey of 109 privately owned and financed power generation plants in the six GCC states, including those with attached water desalination facilities. These plants have a collective gross electricity generation capacity of approximately 112,400MW.

These projects include seven solar, two wind and two gas-fired plants, as well as one industrial steam and cogeneration facility, with a total combined gross capacity of 19,635MW, for which contracts were awarded between September 2023 and August 2024.

Of the total capacity awarded during the 12-month period, solar photovoltaic (PV) and wind capacity accounted for 58%, or 11,400MW. Three solar PV contracts with a total capacity of 5,500MW, directly negotiated between Saudi Arabia’s Public Investment Fund (PIF) and a team led by Riyadh-headquartered Acwa Power, comprised nearly half of the awarded renewable IPP capacity.

These three contracts, along with a fourth for the development and operation of the 3,800MW Taiba 1 and Qassim 1 combined-cycle gas turbine (CCGT) IPP, helped boost Acwa Power’s dominance over its competitors.

Acwa Power's 35.1% stake in the 2,000MW Haden, the 2,000MW Muwayh and 1,500MW Al-Khushaybi solar PV projects, and its 40% share in Taiba 1 and Qassim 1, increased the company's total net capacity by 3,200MW, up 23% from last year’s 13,340MW. This figure takes into account the dilution of its shares in Rabigh Arabian Water & Electricity Company. As a result of the contracts it won, Acwa Power’s gross capacity also rose by 8,800MW to reach a total of 45,150MW.

Acwa Power has occupied the top spot in MEED’s GCC Power Developer Ranking in terms of net capacity since 2021, but it overtook its main rival, French utility developer and investor Engie, in terms of gross capacity only the following year.

Excluding the capacity of the directly negotiated solar IPP contracts that Acwa Power secured with the PIF in the past
three years does not change the company’s dominant position in the ranking, although it decreases its net and gross capacities by 25% and 24%, respectively.

Contenders

With no new contracts won, Engie still managed to retain second place in the ranking, with a net capacity of close to 8,000MW.

The successful bids of a team comprising Japan’s Marubeni Corporation and Ajlan & Bros for the contracts to develop and operate the 600MW Al-Ghat and 500MW Waad Al-Shamal wind schemes in Saudi Arabia increased Marubeni’s net capacity to 4,257MW, up 555MW compared to the previous year.

As with Engie, Japan’s Mitsui did not win any new contracts but retained its fourth place in the ranking, just above EDF, which climbed two positions to claim this year’s fifth spot and registered a net capacity that nearly doubled to reach 2,047MW.

EDF’s impressive performance accrued from its equities in three contracts: the 1,100MW Hinakiyah solar PV and the 3,960MW Taiba 2 and Qassim 2 CCGT projects in Saudi Arabia, and Abu Dhabi’s 1,500MW Al-Ajban solar PV scheme.

EDF knocked Japanese developer Sumitomo down the ranking; it landed in the seventh spot this year. Saudi Arabia’s Aljomaih Energy & Water Company – which was not part of the top 10 last year – rose past Sumitomo to claim sixth position.

Aljomaih’s 30% shareholding in the Taiba 2 and Qassim 2 IPP increased its net capacity by close to 1,200MW from just 775MW in the previous 12-month period.

Previously ranked sixth, Japan’s Jera fell to eighth place, despite having won the contract to develop the Najim cogeneration plant catering to Saudi Arabia’s Amiral petrochemicals complex, which it secured along with Abu Dhabi National Energy Company (Taqa).

Below Jera in the ranking is Ajlan & Bros, which is Marubeni’s partner for the contract to develop the Al-Ghat and Waad Al-Shamal wind IPPs. Ajlan is also understood to have taken a 30% stake in the consortium that won the contract to develop the Taiba 2 and Qassim 2 CCGT project.

China’s Jinko Power rounded out the top 10. It led the team that won the contract to develop the 400MW Tubarjal solar IPP in Saudi Arabia in November last year.

Local developers

The rise of Aljomaih and Ajlan & Bros, which led to South Korea’s Korea Electric Power Corporation (Kepco) and Singapore’s Sembcorp dropping out of the power developer ranking’s top 10 this year, confirms the improving profile of regional utility developers.

The resurgence of gas-fired power generation IPPs – in part due to Saudi Arabia’s liquid fuel displacement programme and the overall demand for baseload to address rising renewable energy capacity – is helping local developers to strengthen their footing.

“The reduced interest from European and Japanese contractors in bidding for gas-fired power generation projects could present an opportunity for local developers and investors,” says a senior executive with an international developer.

“As these firms are less constrained by their 2040-50 net-zero targets, they might focus on efficiency and quick deployment rather than on adhering to decarbonisation timelines, allowing for more flexibility in CCGT projects.”

The fact that only two teams submitted bids for the contracts to develop the next pair of CCGT IPPs in Saudi Arabia supports this observation. Similarly, Qatar’s General Electricity & Water Corporation (Kahramaa) received only one bid from a team led by Sumitomo for the contract to develop the Facility E independent water and power producer (IWPP) project earlier this year.

Conscious of its own net-zero targets, and those of its partners, Abu Dhabi state utility Emirates Water & Electricity Company (Ewec) is adopting a slightly different approach for its next CCGT project in Taweelah by announcing that a carbon-capture facility will be installed as part of the project once such solutions become commercially viable.

In addition, the power-purchase agreement (PPA) for Taweelah C is expected to expire by 2049, making it several years shorter than previous PPAs and in line with the UAE's plan to reach net-zero carbon emissions by 2050.

So far, the market has responded positively, with nine companies having met Ewec’s prequalification requirements for Taweelah C.

However, the scale and volume of gas and renewable energy projects planned by Saudi Arabia, which has said it could procure up to 20GW of renewable energy capacity annually starting this year, is expected to continue to boost the net capacity of local developers and their less net-zero-constrained counterparts for the foreseeable future.

There is also an expectation that the exclusion of Acwa Power from the latest round of tenders for Saudi Arabia’s National Renewable Energy Programme (NREP) could further open up opportunities for other companies, regardless of their origin and net-zero targets.   

Tariffs

There are mixed expectations in terms of how levelised electricity costs (LCOE) will behave over the next 12 months. Compared to the preceding decade, when unsubsidised renewable energy production costs consistently and sharply declined, tariffs have become less predictable since 2022.

In the region, solar PV tariffs in particular have trended upward since Acwa Power offered to develop the Shuaibah 1 solar IPP scheme for $cents 1.04 a kilowatt-hour (kWh) in 2020-21.

These tariffs have remained highly competitive relative to those seen in other, less renewable energy-intense regions, however, disincentivising some developers that felt they could not compete on price.

The next six to 12 months could prove decisive, according to one industry expert.

“It is possible that the surge in renewable projects could limit the availability of competent engineering, procurement and construction (EPC) contractors. The combination of aggressive national targets and competition for EPC services may drive up prices and slow project timelines,” the Dubai-based executive tells MEED.

“With raw materials and commodity prices trending downward, it's feasible that renewable energy tariffs could remain low in the short term. However, sustained record-low tariffs will also depend on the availability of financing, local regulations and grid integration costs.”

The LCOE trend for gas-fired power generation schemes seems more predictable.

According to the executive, the limited capacity of original equipment manufacturers, particularly for turbines and other key components of CCGT plants, will likely push tariffs up over the next 12 months.

“Limited availability of high-efficiency equipment will increase procurement costs and construction timelines, influencing the overall project cost.”

This extends to CCGTs incorporating carbon capture, where the LCOE will likely increase due to additional capital and operational expenses. “Whether these costs are absorbed through renegotiation or passed on to the state offtaker will depend on the power-purchase agreement structure,” he says.

Brisk pace of IPP awards set to continue

https://image.digitalinsightresearch.in/uploads/NewsArticle/12556220/main.gif
Jennifer Aguinaldo
Related Articles
  • Mitsubishi Power to supply Rumah 1 and Nairiyah 1 turbines

    21 November 2024

    The developer and engineering, procurement and construction (EPC) teams that will develop and build the Rumah 1 and Nairiyah 1 combined-cycle gas turbine (CCGT) schemes in Saudi Arabia are understood to have partnered with Tokyo-headquartered Mitsubishi Power for the gas turbines to power the plants.

    The Rumah 1 and Nairiyah 1 independent power projects (IPPs) will each have a capacity of 1,800MW.

    The principal buyer, Saudi Power Procurement Company (SPPC), previously indicated that the power plants would operate using natural gas combined-cycle technology with a carbon-capture unit readiness provision.

    A consortium comprising Saudi Electricity Company (SEC), Riyadh-based utility developer Acwa Power and South Korea’s Korea Electric Power Corporation (Kepco) won the contract to develop the two CCGT independent power projects (IPP).

    The consortium signed the power-purchase agreements (PPAs) for the two projects with the SPPC on 18 November.

    China’s Sepco 3 and South Korea’s Doosan Enerbility will undertake the EPC contract for the projects, as MEED reported.

    The SEC, Acwa Power and Kepco team offered a levelised electricity cost (LCOE) of $cents 4.5859 a kilowatt-hour (kWh) for Rumah 1, and $cents 4.6114/kWh for Nairiyah 1.

    Acwa Power said that the two IPPs will require a combined investment of approximately SR15bn ($4bn). The IPPs are expected to reach commercial operations in Q2 2008. 

    Rumah 1 is located in the Central Region in Riyadh and is part of the previously planned Riyadh Power Plant 15 (PP15). Nairiyah 1 is located in the Eastern Region.

    SPPC received bids for the contracts for four thermal IPPs – the other two being the similarly configured Rumah 2 and Nairiyah 2 – on 21 August.

    The four power generation facilities will be developed using a build-own-operate (BOO) model over 25 years. 

    SPPC’s transaction advisory team for the Rumah 1 and 2 and Al-Nairiyah 1 and 2 IPP projects comprises US/India-based Synergy Consulting, Germany’s Fichtner and US-headquartered Baker McKenzie. 

    Najm and Mitsubishi Power

    The Rumah and Nairiyah 2 orders will be the second one this year for Mitsubishi Power, which in August confirmed receiving an order from South Korea's Samsung C&T Corporation to provide its M501JAC hydrogen-ready CCGT for the Najim industrial steam and electricity cogeneration plant in Jubail in the Eastern Province of Saudi Arabia.

    The M501JAC gas turbine will enable the new cogeneration plant to generate up to 475MW of power and approximately 452 tonnes an hour of steam.

    Samsung C&T is the engineering, procurement and construction (EPC) contractor for the project, which is being developed by a team comprising Abu Dhabi National Energy Company (Taqa) and Japanese power generation company Jera, the same team that won the contract to develop and operate the Rumah 2 and Nairiyah 2 CCGT contracts.

    Photo credit: Mitsubishi Power (for illustrative purposes only)

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12964755/main.jpg
    Jennifer Aguinaldo
  • Shanghai Electric to build 2GW Al-Sadawi solar project

    21 November 2024

    A developer team that includes Abu Dhabi Future Energy Company (Masdar), South Korea's Korea Electric Power Corporation (Kepco) and China's GD Power Development has tapped a Chinese firm to undertake the engineering, procurement and construction (EPC) contract for a 2GW solar project in Saudi Arabia.

    According to an industry source, Shanghai Electric will undertake the EPC work for the 2,000MW Al-Sadawi solar independent power project (IPP).

    The winning developer consortium signed the power-purchase agreement (PPA) with the principal buyer, Saudi Power Procurement Company (SPPC), for the project on 18 November.

    It offered a levelised cost of electricity of hals 4.847 ($c1.29) a kilowatt-hour (kWh) for the contract to develop the scheme, which is located in the Eastern Province.

    The second-lowest bidder is a team that includes China's SPIC Huanghe Hydropower Development and France's EDF Renewables, which offered to develop the project for $c1.31/kWh.

    SPPC received six proposals from companies for the contracts to develop and operate four solar photovoltaic (PV) IPP projects under the fifth procurement round of the kingdom's National Renewable Energy Programme (NREP) in August.

    According to SPPC, the lowest and second-lowest bidders in the remaining schemes under round five of the NREP are:

    Al-Masaa solar IPP (Hail): 1,000MW

    • L1: SPIC/EDF Renewables (France): $c1.36/kWh
    • L2: AlJomaih Energy & Water (local) / TotalEnergies Renewables (France): $c1.40/kWh

    Al-Hinakiyah 2 solar IPP (Medina): 400MW

    • L1: SPIC/EDF: $c1.51/kWh
    • L2: Masdar/Kepco/Nesma:  $c1.57/kWh

    Rabigh 2 solar IPP (Mecca): 300MW

    • L1: AlJomaih Energy & Water / TotalEnergies Renewables: $c1.78/kWh
    • L2: Masdar/Kepco/Nesma: $c1.89/kWh

    Saudi utility developer Acwa Power is not among the 23 companies that were prequalified to bid for the fifth round of NREP projects.

    US/India-based Synergy Consulting is providing financial advisory services to SPPC for the NREP fifth-round tender. Germany's Fichtner Consulting is providing technical consultancy services.

    The round five solar PV IPPs take the total capacity of publicly tendered renewable energy projects in Saudi Arabia to over 10,300MW. Solar PV IPPs account for 79%, or about 8,100MW, of the total capacity.

    Four wind IPPs, one of which has yet to be awarded, account for the remaining capacity.

    SPPC is procuring 30% of the kingdom's target renewable energy by 2030. Saudi sovereign wealth vehicle the Public Investment Fund (PIF) is procuring the rest through the Price Discovery Scheme. The PIF has appointed Acwa Power, which it partly owns, as principal partner for these projects.

    The Saudi Energy Ministry recently said that the kingdom plans to procure 20,000MW of renewable energy capacity annually, starting this year and until 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12964642/main.gif
    Jennifer Aguinaldo
  • Chinese firm wins 2.6GW Saudi inverter deals

    21 November 2024

    The engineering, procurement and construction (EPC) contractors implementing two of Saudi Arabia Public Investment Fund's (PIF) cluster-four solar photovoltaic (PV) projects have awarded contracts for the supply of inverters to China's Sineng Electric.

    The Jiangsu-headquartered company secured an order for 1GW of inverters from China Energy Engineering Group Consortium for the Haden solar PV project and 1GW from Indian contracting firm Larsen & Toubro for the Al-Khushaybi solar PV project.

    Sineng will provide its 8.8MW MV turnkey stations, each comprising 2 units of 4.4MW central inverter, a transformer and a ring main unit (RMU) for the solar projects.

    Designed to "withstand extreme temperatures [of] up to 51ºC… and strong sand-laden winds", the 8.8MW MV turnkey stations are expected to deliver consistent and reliable performance throughout the solar PV plants' operational lifespan.

    The PIF awarded the contracts to develop three cluster-four solar PV projects to a consortium led by Saudi utility developer Acwa Power earlier this year.

    The developer consortium, which includes PIF-backed Water & Electricity Holding Company (Badeel) and Saudi Aramco Power Company (Sapco), reached financial close for the three projects, which have a total combined capacity of  5,500MW, in September.

    The solar PV projects and their capacities are:

    • Haden solar PV (Mecca): 2,000MW
    • Muwayh (Mecca): 2,000MW
    • Al-Khushaybi (Qassim): 1,500MW

    The respective project companies that have been formed for the three projects are Buraiq Renewable Energy Company, Moya Renewable Energy Company and Nabah Renewable Energy Company.

    Acwa Power’s effective shareholding in each of the three projects is 35.1%. Badeel owns 34.9% and Sapco, a subsidiary of state majority-owned oil giant Saudi Aramco, owns the remaining shares.

    The project companies signed financing documents amounting to SR9.7bn ($2.6bn), Acwa Power previously announced. The financing duration is 27.3 years.

    The three projects are being procured under the National Renewable Energy Programme's (NREP) Price Discovery Scheme, which is being implemented by the PIF.

    Under this scheme, the projects are directly negotiated with Acwa Power and its selected partners.

    The three new solar PV facilities have a combined value of SR12.3bn ($3.3bn) and are expected to become operational in the first half of 2027.

    The PIF and its partners are currently developing several solar PV projects with a total capacity of 13.6GW, involving over $9bn in investments. These joint projects – including Sudair, Shuaibah 2, Ar Rass 2, Al-Kahfah and Saad 2 – are intended to enable and support the local private sector through domestic supply-chain participation.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12963512/main.jpg
    Jennifer Aguinaldo
  • Marubeni-led team reaches 1.1GW wind financial close

    21 November 2024

    A developer consortium led by Japan's Marubeni Corporation has reached financial close with a team of lenders for the contracts to develop two wind independent power producer (IPP) projects in Saudi Arabia.

    Marubeni and the local Ajlan & Bros won the contracts to develop the first two wind schemes of the kingdom's National Renewable Energy Programme (NREP) round four, the 600MW Al-Ghat and the 500MW Waad Al-Shamal wind IPPs, in May this year.

    According to an industry source, the following lenders will provide financing for the two projects:

    • Japan Bank for International Cooperation (Jbic)
    • Standard Chartered Bank (UK)
    • Sumitomo Mitsui Trust Bank (Japan)
    • Commercial Bank of Dubai (UAE)

    The consortium agreed to develop and operate the 600MW Al-Ghat wind IPP project with a new world-record-low levelised electricity cost (LCOE) from wind power of $cents 1.56558 a kilowatt-hour (kWh), or about 5.87094 halalas/kWh.

    The 500MW Waad Al-Shamal project has also achieved a second world-record-low tariff for wind power of $cents 1.70187/kWh or 6.38201 halalas/kWh, the energy ministry announced in May.

    The tariff achieved for Al-Ghat is almost 22% lower compared to the LCOE agreed for Saudi Arabia's first wind IPP, the 400MW Dumat Al-Jandal scheme, which a team comprising the UAE's Abu Dhabi Future Energy (Masdar) and France's EDF Renewables won in 2019.

    Marubeni will own 51% while Ajlan will maintain a 49% stake in the project company that will implement the projects.

    The Japanese-local team has appointed Power Construction Corporation of China (Power China) and Sepco 3 to undertake the wind projects' engineering, procurement and construction (EPC) contract.

    MEED previously reported that the same developer team is expected to win the contract to develop and operate the third wind scheme of NREP round four, the 700MW Yanbu wind IPP.

    The contract could be awarded before the year-end, according to a source.

    It is understood that other teams, separately led by local utility developer Acwa Power, France's Engie and EDF Renewables, submitted proposals for the contract to develop the Yanbu wind IPP scheme.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12959899/main.jpg
    Jennifer Aguinaldo
  • L&T signs $400m Riyadh-Kudmi transmission contract

    20 November 2024

    India-headquartered contracting firm Larsen & Toubro (L&T) has signed a contract with state utility Saudi Electricity Company (SEC) for the construction of a new 500-kilovolt (kV) high-voltage direct current (HVDC) project in Saudi Arabia.

    The contract is valued at SR1.51bn ($400m).

    The project involves constructing a section of the HVDC transmission lines from the Riyadh Power Plant 14 (PP14) in the capital to the southwest coastal region of Kudmi.

    MEED understands that the contract was awarded on a lump-sum turnkey basis.

    The other two sections of the HVDC transmission project, which has a total length of 1,089-kilometres (km), have been awarded to South Korea's Hyundai Engineering & Construction Company and Saudi Services for Electro Mechanic Works (SSEM).

    Earlier this month,  Hyundai E&C announced winning a KRW1tn ($725m) contract as part of the PP14-Kudmi HVDC network project. Hyundai E&C's portion of the total package extends over 369km, and is expected to be completed by January 2027.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12955076/main.jpg
    Jennifer Aguinaldo