Local firms rise in GCC Power Developer Ranking

24 September 2024

 

Two Saudi Arabia-headquartered firms have joined Acwa Power in the top 10 of MEED’s 2024 GCC Power Developer Ranking.

Aljomaih Energy & Water Company and Ajlan & Bros have entered the list, occupying the sixth and ninth spots, respectively.

The latest developer ranking included a survey of 109 privately owned and financed power generation plants in the six GCC states, including those with attached water desalination facilities. These plants have a collective gross electricity generation capacity of approximately 112,400MW.

These projects include seven solar, two wind and two gas-fired plants, as well as one industrial steam and cogeneration facility, with a total combined gross capacity of 19,635MW, for which contracts were awarded between September 2023 and August 2024.

Of the total capacity awarded during the 12-month period, solar photovoltaic (PV) and wind capacity accounted for 58%, or 11,400MW. Three solar PV contracts with a total capacity of 5,500MW, directly negotiated between Saudi Arabia’s Public Investment Fund (PIF) and a team led by Riyadh-headquartered Acwa Power, comprised nearly half of the awarded renewable IPP capacity.

These three contracts, along with a fourth for the development and operation of the 3,800MW Taiba 1 and Qassim 1 combined-cycle gas turbine (CCGT) IPP, helped boost Acwa Power’s dominance over its competitors.

Acwa Power's 35.1% stake in the 2,000MW Haden, the 2,000MW Muwayh and 1,500MW Al-Khushaybi solar PV projects, and its 40% share in Taiba 1 and Qassim 1, increased the company's total net capacity by 3,200MW, up 23% from last year’s 13,340MW. This figure takes into account the dilution of its shares in Rabigh Arabian Water & Electricity Company. As a result of the contracts it won, Acwa Power’s gross capacity also rose by 8,800MW to reach a total of 45,150MW.

Acwa Power has occupied the top spot in MEED’s GCC Power Developer Ranking in terms of net capacity since 2021, but it overtook its main rival, French utility developer and investor Engie, in terms of gross capacity only the following year.

Excluding the capacity of the directly negotiated solar IPP contracts that Acwa Power secured with the PIF in the past
three years does not change the company’s dominant position in the ranking, although it decreases its net and gross capacities by 25% and 24%, respectively.

Contenders

With no new contracts won, Engie still managed to retain second place in the ranking, with a net capacity of close to 8,000MW.

The successful bids of a team comprising Japan’s Marubeni Corporation and Ajlan & Bros for the contracts to develop and operate the 600MW Al-Ghat and 500MW Waad Al-Shamal wind schemes in Saudi Arabia increased Marubeni’s net capacity to 4,257MW, up 555MW compared to the previous year.

As with Engie, Japan’s Mitsui did not win any new contracts but retained its fourth place in the ranking, just above EDF, which climbed two positions to claim this year’s fifth spot and registered a net capacity that nearly doubled to reach 2,047MW.

EDF’s impressive performance accrued from its equities in three contracts: the 1,100MW Hinakiyah solar PV and the 3,960MW Taiba 2 and Qassim 2 CCGT projects in Saudi Arabia, and Abu Dhabi’s 1,500MW Al-Ajban solar PV scheme.

EDF knocked Japanese developer Sumitomo down the ranking; it landed in the seventh spot this year. Saudi Arabia’s Aljomaih Energy & Water Company – which was not part of the top 10 last year – rose past Sumitomo to claim sixth position.

Aljomaih’s 30% shareholding in the Taiba 2 and Qassim 2 IPP increased its net capacity by close to 1,200MW from just 775MW in the previous 12-month period.

Previously ranked sixth, Japan’s Jera fell to eighth place, despite having won the contract to develop the Najim cogeneration plant catering to Saudi Arabia’s Amiral petrochemicals complex, which it secured along with Abu Dhabi National Energy Company (Taqa).

Below Jera in the ranking is Ajlan & Bros, which is Marubeni’s partner for the contract to develop the Al-Ghat and Waad Al-Shamal wind IPPs. Ajlan is also understood to have taken a 30% stake in the consortium that won the contract to develop the Taiba 2 and Qassim 2 CCGT project.

China’s Jinko Power rounded out the top 10. It led the team that won the contract to develop the 400MW Tubarjal solar IPP in Saudi Arabia in November last year.

Local developers

The rise of Aljomaih and Ajlan & Bros, which led to South Korea’s Korea Electric Power Corporation (Kepco) and Singapore’s Sembcorp dropping out of the power developer ranking’s top 10 this year, confirms the improving profile of regional utility developers.

The resurgence of gas-fired power generation IPPs – in part due to Saudi Arabia’s liquid fuel displacement programme and the overall demand for baseload to address rising renewable energy capacity – is helping local developers to strengthen their footing.

“The reduced interest from European and Japanese contractors in bidding for gas-fired power generation projects could present an opportunity for local developers and investors,” says a senior executive with an international developer.

“As these firms are less constrained by their 2040-50 net-zero targets, they might focus on efficiency and quick deployment rather than on adhering to decarbonisation timelines, allowing for more flexibility in CCGT projects.”

The fact that only two teams submitted bids for the contracts to develop the next pair of CCGT IPPs in Saudi Arabia supports this observation. Similarly, Qatar’s General Electricity & Water Corporation (Kahramaa) received only one bid from a team led by Sumitomo for the contract to develop the Facility E independent water and power producer (IWPP) project earlier this year.

Conscious of its own net-zero targets, and those of its partners, Abu Dhabi state utility Emirates Water & Electricity Company (Ewec) is adopting a slightly different approach for its next CCGT project in Taweelah by announcing that a carbon-capture facility will be installed as part of the project once such solutions become commercially viable.

In addition, the power-purchase agreement (PPA) for Taweelah C is expected to expire by 2049, making it several years shorter than previous PPAs and in line with the UAE's plan to reach net-zero carbon emissions by 2050.

So far, the market has responded positively, with nine companies having met Ewec’s prequalification requirements for Taweelah C.

However, the scale and volume of gas and renewable energy projects planned by Saudi Arabia, which has said it could procure up to 20GW of renewable energy capacity annually starting this year, is expected to continue to boost the net capacity of local developers and their less net-zero-constrained counterparts for the foreseeable future.

There is also an expectation that the exclusion of Acwa Power from the latest round of tenders for Saudi Arabia’s National Renewable Energy Programme (NREP) could further open up opportunities for other companies, regardless of their origin and net-zero targets.   

Tariffs

There are mixed expectations in terms of how levelised electricity costs (LCOE) will behave over the next 12 months. Compared to the preceding decade, when unsubsidised renewable energy production costs consistently and sharply declined, tariffs have become less predictable since 2022.

In the region, solar PV tariffs in particular have trended upward since Acwa Power offered to develop the Shuaibah 1 solar IPP scheme for $cents 1.04 a kilowatt-hour (kWh) in 2020-21.

These tariffs have remained highly competitive relative to those seen in other, less renewable energy-intense regions, however, disincentivising some developers that felt they could not compete on price.

The next six to 12 months could prove decisive, according to one industry expert.

“It is possible that the surge in renewable projects could limit the availability of competent engineering, procurement and construction (EPC) contractors. The combination of aggressive national targets and competition for EPC services may drive up prices and slow project timelines,” the Dubai-based executive tells MEED.

“With raw materials and commodity prices trending downward, it's feasible that renewable energy tariffs could remain low in the short term. However, sustained record-low tariffs will also depend on the availability of financing, local regulations and grid integration costs.”

The LCOE trend for gas-fired power generation schemes seems more predictable.

According to the executive, the limited capacity of original equipment manufacturers, particularly for turbines and other key components of CCGT plants, will likely push tariffs up over the next 12 months.

“Limited availability of high-efficiency equipment will increase procurement costs and construction timelines, influencing the overall project cost.”

This extends to CCGTs incorporating carbon capture, where the LCOE will likely increase due to additional capital and operational expenses. “Whether these costs are absorbed through renegotiation or passed on to the state offtaker will depend on the power-purchase agreement structure,” he says.

Brisk pace of IPP awards set to continue

https://image.digitalinsightresearch.in/uploads/NewsArticle/12556220/main.gif
Jennifer Aguinaldo
Related Articles
  • Jordan’s Nepco obtains $70m finance for grid

    21 February 2025

    The European Bank for Reconstruction & Development (EBRD) and the EU have approved a €67.1m ($70.2m) financing package for Jordan's state-owned utility, National Electric Power Company (Nepco).

    The financing package consists of a sovereign-guaranteed EBRD loan of up to $56.5m and an EU investment grant of up to €12.4m.

    These funds will finance the construction of a new high-voltage electricity substation in northern Jordan to improve the grid’s capacity, enabling it to handle existing and new generation in the north of the country, said EBRD

    The new substation will not only improve the grid’s ability to handle additional generation capacity, but also facilitate cross-border interconnections, as well as reduce transmission losses by optimising power flows across the national grid.

    The project to be financed will include the construction of four new overhead transmission lines: two 400-kilovolt (kV) lines providing connections to the existing Samra and Amman West substations, and two 132kV lines connected to the Hasan Industrial and Jerash substations.

    These projects support Jordan's ambitious renewable energy targets for 2030.

    The financing will be complemented by a comprehensive technical cooperation package. An EU-funded technical cooperation grant of €2.2m will also be provided to appoint a project implementation consultant for Nepco.

    Nepco is the owner and operator of Jordan’s transmission system, as well as the single buyer of electricity.

    Since the start of its operations in Jordan in 2012, the EBRD has invested almost €2.3bn across 74 projects, providing more than €815m to projects in the country’s energy sector through 14 loans.

    In February 2023, Jordan's Water & Irrigation Ministry and the local firm Arab Towers Contracting Company signed an agreement worth €79.5m ($84.7m) for the design and implementation of a wastewater treatment plant in the Ghabawi region. EBRD provided a €41.3m loan while the EU agreed to provide a €30m grant for the project.

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13414961/main.jpg
    Jennifer Aguinaldo
  • Saudi Arabia capacity buildout enters busiest period

    21 February 2025

    Saudi Arabia has entered what could be the busiest period for power generation capacity buildout in its entire history.

    According to data from regional projects tracker MEED Projects and MEED, a total of 53GW of power generation capacity is under construction or about to start construction following the formal award of contracts or the selection of bidders.

    Generation and cogeneration plants powered by natural gas account for two-thirds, or 66.7%, of the total capacity under construction, with renewable plants, mainly solar, accounting for the rest.

    Solar and wind power plants, however, dominate the pre-execution pipeline, accounting for roughly 94% of the capacity that is currently under bid or prequalification.

    Inclusive of projects in the study and design phase, the total thermal and renewable generation capacity being planned and tendered in Saudi Arabia stood at around 80GW as of February 2025.

    The major capacity buildout is in line with the kingdom's liquid displacement programme as well as its target for renewable energy sources to account for half its electricity production by 2030.

    According to the Energy Institute, Saudi Arabia's total electricity generation in 2023 reached 422.9 terawatt-hours (TWh). Oil accounted for 152.1 TWh, or about 36%, of the total, with natural gas accounting for 265TWh, or 63%, and renewables, 5.8TWh or 1%.

    CCGT plants

    The urgency of displacing its oil-fired fleets underpins the successive contract awards for combined-cycle gas turbine (CCGT) power generation plants, which are being developed as independent power projects (IPPs) or via engineering, procurement and construction (EPC) contracts.

    Roughly 47% of the 35.8GW of gas-fired capacity under construction is being built via an EPC or design and build model, mainly by the Saudi  Electricity Company (SEC), while the rest are being built using an IPP model.

    Of the total thermal capacity under construction, about 45% will be generated by greenfield power plants that are being built as an expansion to existing power generation facilities across the kingdom.

    Chinese contractors such as Sepco 3 and China Energy Engineering Corporation, among others, are constructing 10 of the 19 gas-fired power generation and cogeneration plants that are under execution in Saudi Arabia. An eleventh plant is being constructed by Sepco 3 in partnership with Doosan Enerbility, of South Korea. The 11 plants equate to a capacity of roughly 21GW.

    South Korean contractors, mainly Doosan and Samsung C&T are in four of the 19 projects.

    "I think the Chinese EPC contractors are already at capacity, so SEC has started tapping Egyptian and Spanish EPC contractors," an industry source tells MEED, in reference to Tecnicas Reunidas, Orascom and Elsewedy, which have been selected to undertake the EPC contracts for several CCGT plants last year.

    The peak for new gas-fired contract awards may have passed, however.

    MEED Projects data indicate that four cogeneration plants with a combined capacity of around 1.5GW  are in the pre-execution stage. And, only at least two gas-fired IPP schemes - Shoaiba and Al-Shuqaiq - are currently under study, each with a planned capacity of 2.6GW.

    However, a "surprise"  new project, such as the 3GW expansion of the Qurayyah IPP, announced on 20 February, cannot be ruled out. 

    Renewables  

    A reverse trend could be seen for renewable solar power generation capacity.

    As of February 2025, nearly all renewable energy capacity under construction in Saudi Arabia is being developed as IPPs.

    Around 43% of these IPPs are publicly tendered by the principal buyer, Saudi Power Procurement Company (SPPC), while the rest are directly negotiated between the Saudi sovereign vehicle, Public Investment Fund (PIF), and the dominant local utility developer, Acwa Power.

    The pre-execution pipeline for solar and wind energy projects, which will be procured by SEC and gigaproject developer Neom, is staggering, especially given a directive by the Energy Ministry to procure up to 20GW of renewable energy capacity annually until 2030 subject to demand growth.

    "It is a massive pipeline," notes a Dubai-based senior transaction adviser.

    However, he also notes that a re-scoping process is under way especially for renewable energy projects designed to cater to Neom, the $500bn development in northwestern Saudi Arabia, which aims to be powered 100% by renewables by 2030.

    Issues related to land allocation may also become an issue if it has not yet, notes another industry expert.

    Deployment of additional renewable energy capacity will also require a major battery energy storage system buildout, which started last year, to ensure the flexibility of the electricity grid. 

    "The question is how much batteries they will need and how much batteries will be available to support that ambition," the consultant said.    

    Data centres

    In addition to the liquid displacement programme and the 50% renewable energy production target by 2030, Saudi Arabia has been seeing a major uptick in data centre construction projects in line with a plan to become a major artificial intelligence (AI) hub.

    Hyperscalers such as Amazon Web Services, Google and Microsoft plan to expand their digital or cloud infrastructure in Saudi Arabia in line with this strategy. These and other AI  players, as well as local firms such as DataVolt, Ezditek, Alfanar and the UAE-based Gulf Data Hub, among others, pledged around $15bn of investments in such infrastructure during the recently concluded Leap technology conference in Riyadh, with more investments expected to be announced over the coming months or years.

    These projects, assuming they all come to fruition, will significantly increase computing, cooling and overall electricity demand. The need to make these advanced data centres as sustainable as possible will also further incentivise the kingdom's national renewable energy programme.

     

     

       

     

     

      

     

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13414408/main.gif
    Jennifer Aguinaldo
  • Hyundai E&C wins $389m Saudi grid contracts

    21 February 2025

    South Korea’s Hyundai Engineering & Construction (E&C) has won two power transmission line contracts worth approximately $389m in Saudi Arabia.

    The transmission lines will be built in Saudi Arabia's Medina and Jeddah regions, the firm said.

    The 380-kilovolt (kV) Humaiji transmission network will extend 311 kilometres and transfer power from a solar power plant in Humaiji to a substation in the Medina area.

    The 380kV Kulais transmission network will extend 180 kilometres and transmit power from a solar facility planned for construction in the coastal Kulais area to an existing transmission network in Jeddah.

    The project owner is Saudi Electricity Company, which conducted a competitive bidding process among a selected number of engineering, procurement and construction (EPC) companies, said Hyundai E&C.

    In November, Hyundai E&C won a KRW1tn ($725m) contract to build a high-voltage direct current (HVDC) network project in Saudi Arabia.

    The contract forms part of a 1,089-kilometre (km), 500-kilovolt (kV) HVDC transmission line connecting Riyadh Power Plant 14 (PP14) to the Kudmi substation in southwest Saudi Arabia.

    The company signed the contract to build the transmission line's first package, which extends over 369km, with National Grid, the power transmission unit of state utility Saudi Electricity Company (SEC).

    The lump sum turnkey project is expected to be completed by January 2027.

    Photo credit: Hyundai E&C

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13413980/main.jpeg
    Jennifer Aguinaldo
  • Sojitz-backed Capella eyes Middle East PPPs

    20 February 2025

     

    Public-private partnership (PPP) projects across the Middle East will be a key focus for Sydney-headquartered infrastructure developer and investor Capella Capital, according to two sources familiar with the matter.

    "The Middle East … is one of the potential markets to expand the business portfolio of Capella," one of the sources said.

    MEED understands that the region is included in Capella's medium- to long-term growth strategy.

    This development follows the acquisition of the company by Japanese infrastructure investor Sojitz in January this year.

    Valued at AUD470m ($300m), the acquisition is targeted for completion in June this year.

    Sojitz says the acquisition is in line with its efforts to "strengthen its large-scale infrastructure development capability in the energy, social and transportation infrastructure fields" in Australia, as well as in global markets.

    It will also support Sojitz's transformation into an "integrated business model that manages projects from initial formation to asset management".

    Capella will likely follow the entry into the Middle East PPP market of fellow Australian infrastructure investor, Plenary Group.

    Abu Dhabi holding company ADQ acquired a 49% stake in Plenary in April 2024, including all shares owned at the time by the Canadian pension fund Caisse de Depot et Placement du Quebec.

    In a statement issued in September last year, ADQ said the two firms plan to establish a co-investment platform, which will focus on public and social infrastructure opportunities "in high-growth geographies including the GCC region, the Middle East and Central Asia".

    In August last year, the Abu Dhabi Investment Office (Adio) appointed a team of Plenary, Belgian firm Besix and the local Mazrui International for a contract to develop and operate a 3,250-bed student accommodation complex and associated facilities at Khalifa University in Abu Dhabi. 

    Plenary is also part of a consortium that is understood to be planning to bid for the first two packages of the $22bn Dubai Strategic Sewerage Tunnels project.  

    In April 2023, Saudi Arabia launched a pipeline of 200 PPP projects in 17 sectors. Adio is responsible for coordinating PPP projects in Abu Dhabi, while Oman's Finance Ministry oversees the sultanate's planned PPP projects. 

    Photo credit: Pixabay (for illustrative purposes only)


    READ THE FEBRUARY MEED BUSINESS REVIEW

    Trump unleashes tech opportunities; Doha achieves diplomatic prowess and economic resilience; GCC water developers eye uptick in award activity in 2025.

    Published on 1 February 2025 and distributed to senior decision-makers in the region and around the world, the February MEED Business Review includes:

    > WATER & WASTEWATER: Water projects require innovation
    https://image.digitalinsightresearch.in/uploads/NewsArticle/13411316/main5649.jpg
    Jennifer Aguinaldo
  • SEC and Acwa Power sign Qurayyah IPP expansion deal

    20 February 2025

    Register for MEED’s 14-day trial access 

    Riyadh-based utility firm Saudi Electricity Company (SEC) and Acwa Power have signed a power-purchase agreement with the principal buyer, Saudi Power Procurement Company, for the expansion of the Qurayyah independent power project (IPP) in Saudi Arabia.

    The Qurayyah IPP expansion project will have a generation capacity of 3,010MW and is expected to be carbon capture-ready, the two firms said in separate bourse filings on 20 February.

    SEC and Acwa Power will each have an effective shareholding of 40% in the project, which is valued at SR13.4bn ($3.57bn).

    Hajj Abdullah Alireza & Company (Haaco) will own the remaining 20%. 

    The three firms will develop, finance, build, own and operate the combined-cycle gas turbine plant.

    The project also includes the development, financing, construction and transfer of a 380-kilovolt (kV) electrical substation.

    The project duration is 25 years from the plant commercial operation date.

    Acwa Power, South Korea's Samsung C&T, Mena Infrastructure Fund and SEC own Hajr Electricity Production Company, the development company behind the existing 3.9GW Qurayyah 1 & 2 IPP in Saudi Arabia.

    The Qurayyah 1 & 2 IPP reached commercial operations in 2015.

    The expansion of the Qurayyah IPP is not to be confused with a separate engineering, procurement and construction (EPC) project with the same name.

    Egyptian contractor Orascom is understood to be undertaking the EPC contract for the 3.6GW Qurayyah EPC project.

    MEED reported in September 2024 that Orascom had received limited notice to proceed on the project from SEC.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13411202/main4001.gif
    Jennifer Aguinaldo