Local firms rise in GCC Power Developer Ranking

24 September 2024

 

Two Saudi Arabia-headquartered firms have joined Acwa Power in the top 10 of MEED’s 2024 GCC Power Developer Ranking.

Aljomaih Energy & Water Company and Ajlan & Bros have entered the list, occupying the sixth and ninth spots, respectively.

The latest developer ranking included a survey of 109 privately owned and financed power generation plants in the six GCC states, including those with attached water desalination facilities. These plants have a collective gross electricity generation capacity of approximately 112,400MW.

These projects include seven solar, two wind and two gas-fired plants, as well as one industrial steam and cogeneration facility, with a total combined gross capacity of 19,635MW, for which contracts were awarded between September 2023 and August 2024.

Of the total capacity awarded during the 12-month period, solar photovoltaic (PV) and wind capacity accounted for 58%, or 11,400MW. Three solar PV contracts with a total capacity of 5,500MW, directly negotiated between Saudi Arabia’s Public Investment Fund (PIF) and a team led by Riyadh-headquartered Acwa Power, comprised nearly half of the awarded renewable IPP capacity.

These three contracts, along with a fourth for the development and operation of the 3,800MW Taiba 1 and Qassim 1 combined-cycle gas turbine (CCGT) IPP, helped boost Acwa Power’s dominance over its competitors.

Acwa Power's 35.1% stake in the 2,000MW Haden, the 2,000MW Muwayh and 1,500MW Al-Khushaybi solar PV projects, and its 40% share in Taiba 1 and Qassim 1, increased the company's total net capacity by 3,200MW, up 23% from last year’s 13,340MW. This figure takes into account the dilution of its shares in Rabigh Arabian Water & Electricity Company. As a result of the contracts it won, Acwa Power’s gross capacity also rose by 8,800MW to reach a total of 45,150MW.

Acwa Power has occupied the top spot in MEED’s GCC Power Developer Ranking in terms of net capacity since 2021, but it overtook its main rival, French utility developer and investor Engie, in terms of gross capacity only the following year.

Excluding the capacity of the directly negotiated solar IPP contracts that Acwa Power secured with the PIF in the past
three years does not change the company’s dominant position in the ranking, although it decreases its net and gross capacities by 25% and 24%, respectively.

Contenders

With no new contracts won, Engie still managed to retain second place in the ranking, with a net capacity of close to 8,000MW.

The successful bids of a team comprising Japan’s Marubeni Corporation and Ajlan & Bros for the contracts to develop and operate the 600MW Al-Ghat and 500MW Waad Al-Shamal wind schemes in Saudi Arabia increased Marubeni’s net capacity to 4,257MW, up 555MW compared to the previous year.

As with Engie, Japan’s Mitsui did not win any new contracts but retained its fourth place in the ranking, just above EDF, which climbed two positions to claim this year’s fifth spot and registered a net capacity that nearly doubled to reach 2,047MW.

EDF’s impressive performance accrued from its equities in three contracts: the 1,100MW Hinakiyah solar PV and the 3,960MW Taiba 2 and Qassim 2 CCGT projects in Saudi Arabia, and Abu Dhabi’s 1,500MW Al-Ajban solar PV scheme.

EDF knocked Japanese developer Sumitomo down the ranking; it landed in the seventh spot this year. Saudi Arabia’s Aljomaih Energy & Water Company – which was not part of the top 10 last year – rose past Sumitomo to claim sixth position.

Aljomaih’s 30% shareholding in the Taiba 2 and Qassim 2 IPP increased its net capacity by close to 1,200MW from just 775MW in the previous 12-month period.

Previously ranked sixth, Japan’s Jera fell to eighth place, despite having won the contract to develop the Najim cogeneration plant catering to Saudi Arabia’s Amiral petrochemicals complex, which it secured along with Abu Dhabi National Energy Company (Taqa).

Below Jera in the ranking is Ajlan & Bros, which is Marubeni’s partner for the contract to develop the Al-Ghat and Waad Al-Shamal wind IPPs. Ajlan is also understood to have taken a 30% stake in the consortium that won the contract to develop the Taiba 2 and Qassim 2 CCGT project.

China’s Jinko Power rounded out the top 10. It led the team that won the contract to develop the 400MW Tubarjal solar IPP in Saudi Arabia in November last year.

Local developers

The rise of Aljomaih and Ajlan & Bros, which led to South Korea’s Korea Electric Power Corporation (Kepco) and Singapore’s Sembcorp dropping out of the power developer ranking’s top 10 this year, confirms the improving profile of regional utility developers.

The resurgence of gas-fired power generation IPPs – in part due to Saudi Arabia’s liquid fuel displacement programme and the overall demand for baseload to address rising renewable energy capacity – is helping local developers to strengthen their footing.

“The reduced interest from European and Japanese contractors in bidding for gas-fired power generation projects could present an opportunity for local developers and investors,” says a senior executive with an international developer.

“As these firms are less constrained by their 2040-50 net-zero targets, they might focus on efficiency and quick deployment rather than on adhering to decarbonisation timelines, allowing for more flexibility in CCGT projects.”

The fact that only two teams submitted bids for the contracts to develop the next pair of CCGT IPPs in Saudi Arabia supports this observation. Similarly, Qatar’s General Electricity & Water Corporation (Kahramaa) received only one bid from a team led by Sumitomo for the contract to develop the Facility E independent water and power producer (IWPP) project earlier this year.

Conscious of its own net-zero targets, and those of its partners, Abu Dhabi state utility Emirates Water & Electricity Company (Ewec) is adopting a slightly different approach for its next CCGT project in Taweelah by announcing that a carbon-capture facility will be installed as part of the project once such solutions become commercially viable.

In addition, the power-purchase agreement (PPA) for Taweelah C is expected to expire by 2049, making it several years shorter than previous PPAs and in line with the UAE's plan to reach net-zero carbon emissions by 2050.

So far, the market has responded positively, with nine companies having met Ewec’s prequalification requirements for Taweelah C.

However, the scale and volume of gas and renewable energy projects planned by Saudi Arabia, which has said it could procure up to 20GW of renewable energy capacity annually starting this year, is expected to continue to boost the net capacity of local developers and their less net-zero-constrained counterparts for the foreseeable future.

There is also an expectation that the exclusion of Acwa Power from the latest round of tenders for Saudi Arabia’s National Renewable Energy Programme (NREP) could further open up opportunities for other companies, regardless of their origin and net-zero targets.   

Tariffs

There are mixed expectations in terms of how levelised electricity costs (LCOE) will behave over the next 12 months. Compared to the preceding decade, when unsubsidised renewable energy production costs consistently and sharply declined, tariffs have become less predictable since 2022.

In the region, solar PV tariffs in particular have trended upward since Acwa Power offered to develop the Shuaibah 1 solar IPP scheme for $cents 1.04 a kilowatt-hour (kWh) in 2020-21.

These tariffs have remained highly competitive relative to those seen in other, less renewable energy-intense regions, however, disincentivising some developers that felt they could not compete on price.

The next six to 12 months could prove decisive, according to one industry expert.

“It is possible that the surge in renewable projects could limit the availability of competent engineering, procurement and construction (EPC) contractors. The combination of aggressive national targets and competition for EPC services may drive up prices and slow project timelines,” the Dubai-based executive tells MEED.

“With raw materials and commodity prices trending downward, it's feasible that renewable energy tariffs could remain low in the short term. However, sustained record-low tariffs will also depend on the availability of financing, local regulations and grid integration costs.”

The LCOE trend for gas-fired power generation schemes seems more predictable.

According to the executive, the limited capacity of original equipment manufacturers, particularly for turbines and other key components of CCGT plants, will likely push tariffs up over the next 12 months.

“Limited availability of high-efficiency equipment will increase procurement costs and construction timelines, influencing the overall project cost.”

This extends to CCGTs incorporating carbon capture, where the LCOE will likely increase due to additional capital and operational expenses. “Whether these costs are absorbed through renegotiation or passed on to the state offtaker will depend on the power-purchase agreement structure,” he says.

Brisk pace of IPP awards set to continue

https://image.digitalinsightresearch.in/uploads/NewsArticle/12556220/main.gif
Jennifer Aguinaldo
Related Articles
  • Kuwait awards $381m oil project

    23 September 2026

    Register for MEED’s 14-day trial access 

    State-owned upstream operator Kuwait Oil Company (KOC) has awarded an oil project contract worth KD117m ($381m) to India’s Megha Engineering & Infrastructure (Meil).

    The Supreme Purchasing Committee for Kuwait Petroleum Corporation (KPC) approved the contract last month, paving the way for the official award.

    The project focuses on a water separation unit at the Al-Rawdatain facility in Kuwait.

    The water separation facility will be developed at Gathering Centre 25 (GC-25), along with a pumping facility at GC-30.

    The project will deliver a wide-ranging upgrade of processing and utility infrastructure, including new low-pressure separation and gas-handling equipment such as a three-phase wet separator package, a gas knock-out drum and associated low-pressure gas pipelines, as well as a high-integrity pressure protection system and a high-pressure flare.

    Meil will develop the new three-phase low-pressure wet separation facility at GC-25.

    The main process equipment will include two wet separator packages, each with a capacity of 150,000 barrels of liquid a day, and a low-pressure gas knock-out drum with a capacity of 53 million standard cubic feet a day, together with associated gas-handling facilities.

    The facility will also incorporate an effluent water treatment and transfer system, including an effluent water balance tank equipped with microbubble flotation and induced gas flotation systems, as well as transfer pumps.

    Additional GC-25 facilities will include fuel gas treatment, chemical injection, oil recovery and flare connections, along with firewater and deluge systems.

    The scope also covers control and safety systems, substations, and associated civil, structural, mechanical, electrical and instrumentation works.

    At GC-30, the project will focus on treated-water filtration and high-pressure injection infrastructure.

    The scope includes nutshell filters and associated feed pumps with a combined capacity of approximately 500,000 barrels of water a day.

    Booster and injection pumps will transfer treated effluent water to designated injection wells.

    Additional facilities at GC-30 will include fuel gas treatment, sludge collection and disposal systems, oil recovery systems, control and safety systems, substations, laboratory and workshop facilities, and associated civil, structural, piping, mechanical, electrical and instrumentation works.

    The project also includes transfer pipelines connecting GC-25, GC-15 and GC-30.

    Meil will carry out modifications to existing tanks at GC-30, as well as process and utility tie-ins, electrical and instrumentation modifications and other infrastructure required to integrate the new facilities with KOC’s existing assets.

    Meil’s responsibilities cover the project lifecycle from design and engineering through procurement, construction, testing, pre-commissioning, commissioning, start-up and performance testing.

    The contract also includes operation, maintenance, repair and insurance responsibilities for the designated facilities during the applicable operations and maintenance period.

    Seven companies submitted bids for the project last November.

    The full list of bids was:

    • Meil (India) – KD117m ($381m)
    • Mechanical Engineering & Contracting Company (Kuwait) – KD130m
    • Spetco (Kuwait) – KD158m
    • Al-Kharafi (Kuwait) – KD164m
    • China Oil HBP Science & Technology (China) – KD169m
    • Alghanim International (Kuwait) – KD169m
    • Jereh Oil & Gas Engineering (China) – KD191m

    In October last year, KOC awarded Meil a separate contract for a project to develop a gas sweetening and recovery facility in west Kuwait.

    Meil submitted the lowest bid for that tender, at KD69.2m ($225.5m), in February 2025.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19911322/main.jpg
    Wil Crisp
  • Kuwait refinery project on track for year-end completion

    23 September 2026

     

    A $65m project to replace a substation at the Mina Al-Ahmadi (MAA) refinery is on schedule to be mechanically complete before the end of the year, according to industry sources.

    The project is being executed by India’s Larsen & Toubro (L&T), which was awarded the contract in October 2024.

    One source said: “This project is approaching completion and is currently on schedule to be completed before the end of the year, although it could still see delays related to the ongoing regional conflict.”

    The client is state-owned downstream operator Kuwait National Petroleum Company (KNPC).

    Kuwait’s Ministry of Electricity, Water & Renewable Energy (MEW) is also involved in the project and will provide final approvals and sign-off.

    The scope of the project includes:

    • Construction of a substation
    • Installation of transformers
    • Installation of medium-voltage switchgear
    • Installation of low-voltage auxiliary systems
    • Installation of network protection systems
    • Installation of disconnecting switches
    • Installation of surge arrestors
    • Installation of feeder breakers and cubicles
    • Installation of low-voltage A/C and D/C equipment
    • Installation of battery banks and battery chargers
    • Installation of related relay and control panel boards
    • Installation of fire alarm and fire protection equipment
    • Installation of a SCADA system
    • Installation of cables
    • Civil works
    • Associated facilities

    The current project to replace a substation at the MAA refinery closely resembles another project tendered by KNPC more than a decade ago, which L&T also won.

    On 18 May 2015, KNPC signed a contract with L&T to build a new 240MW substation at the MAA refinery, valued at KD21.866m.

    The new substation, known as M20, was designed to replace an existing substation that was considered old and obsolete.

    Mohammed Al-Mutairi, who was KNPC’s chief executive at the time, said the substation building would be explosion-proof and use state-of-the-art control systems.

    He said the station’s capacity would increase from 180MW to 240MW, supplying most of the refinery’s electricity needs.

    Given the similarities between the two projects, L&T has been able to reuse some designs, creating efficiencies, according to industry sources.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19911319/main.jpg
    Wil Crisp
  • Contractor wins $208m Almoosa hospital MEP contract

    23 September 2026

    Register for MEED’s 14-day trial access 

    Riyadh-based construction firm BEC Arabia has won a SR781m ($208m) contract for the mechanical, electrical and plumbing (MEP) works at Almoosa Hospital in Al-Khobar.

    Saudi Arabia’s Almoosa Health Company awarded the contract.

    The hospital complex consists of two towers: a 24-storey in-patient tower with 380 beds, and an 11-storey tower with 224 clinics and 113 additional treatment spaces.

    It will be built on a 45,000-square-metre site.

    A podium spanning the ninth and 10th floors will connect the two towers.

    The hospital will also include parking for 1,700 cars.

    BEC Arabia won the SR656m ($175m) main construction contract for the hospital in November last year.

    In August 2025, MEED reported that Almoosa Health Company had announced it had secured a sharia-compliant credit facility worth SR650m ($173m) from Banque Saudi Fransi.

    In a statement published on the Saudi stock exchange (Tadawul), the company said the seven-year facility would be used to support its expansion and growth strategy.

    Lebanon’s Dar, US-based Perkins&Will and French design firm Pierre-Yves Rochon designed the project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19910889/main.jpg
    Yasir Iqbal
  • UAE to develop integrated waste-to-resource pilot

    23 September 2026

    Emirates Biotech and United Arab Emirates University (UAEU) have launched a pilot project in Al-Ain that could provide a model for larger waste-to-resource facilities.

    The project involves developing the UAE’s first integrated organic-waste valorisation pilot plant, which will test whether food waste and compostable packaging can be processed together to recover resources and reduce waste sent to landfill.

    Located near the UAEU campus, the 40kg-a-day facility will process organic waste to produce renewable biogas and nutrient-rich compost. The project is intended to generate technical and operating data that could support the development of larger-scale facilities.

    Emirates Biotech and UAEU will design, build and operate the pilot plant as part of a two-year research project running from August 2026 to August 2028. Installation and commissioning are expected to be completed by August 2027.

    The plant will combine anaerobic digestion and composting. Anaerobic digestion will convert the organic waste into renewable biogas, while the resulting digestate will be composted to produce nutrient-rich compost.

    A laboratory-scale assessment will also examine the potential to convert the biogas into renewable hydrogen.

    Food waste accounts for nearly 40% of daily municipal solid waste in the UAE, according to Emirates Biotech, and much of it is currently disposed of in landfills.

    The pilot will therefore assess the technical and operational feasibility of recovering value from two waste streams through a single integrated process.

    If successfully scaled, Emirates Biotech says an integrated organic-waste valorisation plant could reduce CO₂ emissions by 89% compared with landfilling.

    The project is expected to provide a scalable and modular model for converting food waste and compostable packaging into renewable biogas and compost, with the findings intended to inform the development of larger waste-to-resource facilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19908972/main.jpg
    Mark Dowdall
  • Contractors prepare Oxagon Highway 55 bids

    23 September 2026

     

    Contractors are preparing to submit bids on 28 September for a design-and-build contract for permanent upgrade works on Highway 55 in the kingdom’s Oxagon region.

    The first phase of the project includes constructing 14 kilometres of road, with two lanes in each direction. It also includes one bridge and three interchanges.

    The project duration is 22 months.

    Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.

    MEED reported exclusively in August 2025 that contractors had submitted responses to an expression of interest notice that Neom had issued earlier that month.

    The project is expected to support cargo movement from Duba Port to other parts of the kingdom and the wider region.

    Last year, Neom tested a pilot initiative by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.

    In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”

    The Port of Neom is located on the Red Sea near the Arar border, a key entry point into Iraq.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19907876/main.jpg
    Yasir Iqbal