Lessons learnt from a power plant decommissioning

26 February 2026

 

Al-Kamil power plant, a 280MW, gas-fired power plant in the Sharqiya region of Oman, was recently decommissioned following nearly 20 years of operations as the country’s second independent power plant.

The plant reached commercial operation in 2002, at which time it started to supply electricity to Nama Power & Water Procurement Company under a 15-year power purchase agreement that was later extended to the end of 2021. No further extension was granted so, in 2022, the decommissioning process was initiated.

Al-Kamil power plant was one of the first privately owned power plants in Oman to be decommissioned. The entire process took significantly longer than planned – three years compared to an initial target of 12 months. This was not unexpected, however, as there were not yet any standard processes to follow. Everything was being done for the first time, and proper procedures had to be established.

Starting decommissioning 

The decommissioning of a power plant is a complex process and can take as much time to complete as it takes to build a plant. It involves environmental considerations, health and safety protocols, detailed surveys, de-energisation, dismantling, demolition, waste management and the segregation and storage of secondary valuables. 

Careful planning and management are essential to ensure that decommissioning is accomplished safely, cost-effectively and in accordance with all government environmental standards.

Consulting on the decommissioning of Al-Kamil were Dubai’s Golden Sands Marketing Consulting (GSMC), appointed in 2021, alongside Abu Dhabi’s Sustainable Water & Power Company (SWPC) and Dubai’s Tractebel Engineering Company (TEC).

One of the first steps that GSMC undertook was to prepare a master plan covering the entire decommissioning process (see right).

A site investigation was undertaken by GSMC and SWPC early in the process to determine the condition of the power assets and the overall site. 

The Al-Kamil power plant was found to have been well maintained, with no major health, safety, security and environment (HSSE) issues.

SWPC prepared the dismantling guidelines covering all plant equipment, and these were reviewed by TEC. The guidelines covered three main phases: the shut down and isolation of all assets; the de-
energisation process; and the dismantling of the plant equipment, its removal from site and the demolition of all remaining civil works.

GSMC designed a sales strategy for the plant equipment, taking into consideration the secondary market for power-related equipment, as well as the scrap market in Oman. A competitive procurement process was also followed in an effort to maximise sales revenues from plant equipment.

A separate tender was issued to appoint a demolition contractor to remove the remaining civil works, and once this work was complete, a local environmental engineering company undertook a final environmental report to demonstrate that the site was properly cleared and ready for handover to the original owner, the Housing & Urban Planning Ministry.

Final results

The decommissioning project went well in terms of HSSE considerations, with no fatalities, no lost-time injuries and no first aid injuries over the more than 243,000 total workhours at the site. 

There were no material environmental spills or incidents to report, and all above- and below-ground structures were demolished and safely removed from the site in accordance with local requirements. 

The final environmental report, completed just before handover, showed that the site was effectively in the same condition as it was when originally taken over at the start of construction.

The decommissioning was also successful from a financial perspective, as revenues from the sale of plant equipment and diesel fuel were beyond what was required to cover the costs associated with the decommissioning process. 

Lessons learnt 

Many lessons were learnt during the process that can benefit future power plant decommissioning efforts in the region.

> Notify key stakeholders early: Key stakeholders are those that have a vested interest in the project, either through ownership of certain assets on site, such as grid connection assets, or via regulation, such as the environmental authority. Many of these stakeholders take time to respond, so notifying key stakeholders early in the process can ensure that unnecessary delays are avoided.

> Prioritise HSSE: For any future decommissioning project, HSSE must be a top priority, and this should be the focus throughout the entire decommissioning process – at all levels of work and management. 

The site manager at Al-Kamil installed a 24/7 closed-circuit television camera, which proved to be extremely effective in terms of monitoring progress and identifying potential HSSE issues before they became an incident. This simple and cost-effective practice should be replicated for all future decommissioning projects.

> Appoint the environmental consultant early in the process: It is advisable to appoint an environmental consultant early in the process. The consultant is needed to coordinate activities with the local environmental authority and obtain a no-objection letter or certificate, complete an environmental management report and an update of the environmental impact assessment, which includes an environmental baseline.

Ideally, these reports and environmental authority approvals should be completed well before any work is under way at the site. This information is also useful to potential bidders for the sale of equipment, or to contractors involved in the dismantling and demolition process.

> Submit an environmental management plan for approval: It is unlikely that any environmental authority will provide a no-objection letter or certificate without reviewing the environmental plan. It is therefore necessary to complete the plan early, prior to informing the environmental authority. This can minimise potential delays in starting the decommissioning process. 

As a general practice, an environmental consultant should be brought on board early in the process, ideally once the overall master plan is approved by the company.

> Establish a proactive steering committee: This was done at Al-Kamil and proved to be effective when it came to overseeing project progress and dealing with issues as they arose. Certain members of the steering committee visited the site regularly and undertook spot HSSE inspections.

At Al-Kamil, the overall decommissioning was relatively straightforward as the plant was in a remote area. However, decommissioning a power plant in a busier location, or when part of the power plant remains in operation, is more challenging. Under these circumstances, a steering committee is vital. 

> Set realistic delivery and completion timelines: Decommissioning a power plant is a complex process. The initial timeline to complete the process for Al-Kamil was one year, which was the best estimate at the time as there were no benchmarks or references in Oman. However, the actual completion time turned out to be three years – longer than the approximately 2.5 years it took to build the plant, from the start of construction in early 2001 to full commercial operation in July 2003.

Realistic delivery dates should be set for contractors, suppliers and others involved in the decommissioning process. This is likely to result in better pricing, as bidders tend to factor in higher contingencies with shorter or fast-track delivery dates. More realistic delivery dates also help management to allocate staff resources and manage the decommissioning budget. 

Finally, realistic delivery dates help to manage owner and shareholder expectations regarding project completion.

Given the experience with Al-Kamil, a reasonable decommissioning timeline for a power plant is probably close to the actual construction timeline for the plant involved.

> Allow time to maximise revenues from the sale of assets: The market value for Al-Kamil’s power assets was estimated at a value significantly higher than the prevailing scrap value. This was based in part on the value of similar gas turbine units, after adjusting for age, usage and other factors that affect the net market value. However, the company realised a much lower value, even after retendering the equipment sales in an effort to get a better price.

It appears that prices close to the market rate are only achievable if there is time to find a suitable buyer. This can take many months or even years – typically a longer time than the owners of power plants wish to take. 

Moreover, as renewables continue to penetrate the market, there is less worldwide demand for used gas turbine units. Prevailing market supply and demand conditions also have a bearing on the sale price for secondary equipment, and this factor needs to be considered.

If time is of the essence, then power plant owners need to accept the fact that the expected revenues will likely be on the low side, although still higher than the scrap value of the assets. 


Main image: Picture 1: Al-Kamil power plant as constructed; Picture 2: Post decommissioning 


https://image.digitalinsightresearch.in/uploads/NewsArticle/15780944/main.gif
Related Articles
  • Kuwait tenders oil manifold project

    24 June 2026

    State-owned upstream operator Kuwait Oil Company (KOC) has tendered a contract to construct remote header manifolds and associated works in the southern and eastern regions of Kuwait.

    A meeting with prospective contractors has been scheduled for 21 July 2026, and bids are due to be submitted ahead of a deadline on 20 September 2026.

    Manifolds are devices used in the oil sector to divide the flow of liquids from a single source to several outlets, or to collect liquids, or vice versa.

    Previously, a project with a similar scope in the same region was awarded to the Kuwaiti contractor Al-Ghanim International General Trading & Contracting.

    In 2016, it signed a contract worth $435m to construct remote header manifolds and associated works in the south and east Kuwait areas.

    The scope of that contract included design, procurement, construction and commissioning of 25 remote manifold stations and associated pipelines in south and east Kuwait using multi-phase pumps to deliver liquids to gathering centres.

    Kuwait’s oil fields are connected to more than 25 gathering centres, which serve as collection points for crude oil produced by several wells connected by flowlines, providing initial treatment by separating associated gas and removing salt.


    READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDF

    GCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.

    Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17409564/main.jpg
    Wil Crisp
  • Contractors win deals for Saudi Energy transmission projects

    23 June 2026

     

    Saudi Arabia-based Haif Company has won contracts for two separate substation projects in Saudi Arabia, according to sources.

    The first involves the construction of a 132/33/13.8kV substation for Saudi Energy, formerly Saudi Electricity Company, which will replace the existing Tabuk substation 2 in Tabuk, northwestern Saudi Arabia.

    The works include the construction of a new substation, along with GIS, transformers, switchgear, capacitor banks, MV/LV cable systems and protection infrastructure.

    Ten firms submitted bids for the project last December. The bidders included:

    • Al-Babtain Contracting (Saudi Arabia)
    • Alfanar Projects (Saudi Arabia)
    • Al-Gihaz Holding (Saudi Arabia) 
    • Al-Osais International Holding (Saudi Arabia)
    • Danway Electrical & Mechanical Engineering (UAE)
    • Haif Company (Saudi Arabia)
    • Mohammed Al-Ojaimi Group (Saudi Arabia)
    • Nesma Infrastructure & Technology (Saudi Arabia)
    • Saudi Services for Electro Mechanic Works (Saudi Arabia)
    • Tareg Al-Jaafari Contracting Est (Saudi Arabia)

    In addition to Tabuk, Saudi Energy is planning several power transmission projects in Al-Jouf, Medina and the Eastern Province as part of the kingdom’s push to upgrade its electricity transmission and distribution infrastructure

    The second Haif contract involves a 132/33kV substation project at Hail to support the integration of solar generation from the Al-Kahfah photovoltaic facility into the network. Together, the projects are valued at about $90m.

    Elsewhere, the local Trading & Development Partnership has been appointed to build a 132/33kV substation at Al-Jouf, in Al-Jouf Province.

    The facility will deliver a transmission capacity of about 168 MVA to the Al-Busitaa agricultural site, supporting the Liquid Fuel Displacement Programme, which aims to reduce reliance on diesel generators and fuel oil for power generation.

    Nine bids were submitted for the project last year.

    According to MEED Projects, Saudi Energy has almost $2.3bn-worth of projects currently under bid evaluation, including the 500kV overhead transmission line, approximately 466km long, for the Eastern Operating Area and the Central Operating Area in the Eastern Province. The main contract is expected to be awarded later in 2026.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17397346/main.jpg
    Mark Dowdall
  • Morocco approves Khalladi wind farm expansion

    23 June 2026

    Acwa Maroc, a subsidiary of Saudi developer Acwa, has secured approval to expand the Khalladi wind independent power project (IPP) in northern Morocco by 40MW.

    The extension will increase the project’s total installed capacity from 120MW to 160MW. The Khalladi wind farm is located at Djebel Sendouq, about 50 kilometres from Tangier. The existing facility comprises 40 wind turbines rated at 3MW each.

    The project operates under Morocco’s Law 13.09 renewable energy framework, which allows private renewable energy firms to develop generation assets and supply electricity directly to industrial consumers.

    According to Acwa’s website, the facility entered commercial operation in 2018 and supplies electricity to Morocco’s state-owned utility Onee and large industrial customers under a 20-year power-purchase agreement.

    Acwa holds a 51% stake in the project alongside Participation Khalladi SA (24%) and ARIF North Africa Investment SARL, an infrastructure investment fund managed by France’s Amundi (25%).

    The engineering, procurement and construction contract was executed by Denmark’s Vestas, France’s Cegelec and Morocco’s Stam and AGTT.

    Morocco is targeting renewables to account for 52% of its installed power generation capacity by 2030.

    The operational wind farm generates about 397GWh of electricity a year. It is understood that the expansion project has already entered the development phase.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17394999/main5046.jpg
    Mark Dowdall
  • Libya plans to distribute oil budget in July

    23 June 2026

     

    Libya’s National Oil Corporation (NOC) has communicated to contractors in the country that it is expecting funds from the country’s budget to be distributed to state-owned oil companies in July, according to industry sources.

    Earlier this year, the country’s rival legislative bodies approved a unified state budget for the first time in more than 13 years.

    The Central Bank of Libya confirmed on 11 April that both chambers had endorsed the budget, calling it a key step towards restoring financial stability after prolonged division.

    The total budget was valued at LD190bn ($29.95bn), and LD12bn ($1.9bn) was allocated to the country’s NOC.

    An additional LD40bn ($6.3bn) was allocated for “development projects”.

    At the time, Libya stated that a joint committee had been formed to help prioritise development projects, and the projects had been listed in the budget.

    Over the past decade, the country has had two rival governments; the last time the country operated under a single national budget was in 2013.

    The country’s two legislatures are the eastern-based House of Representatives and the Tripoli-based High Council of State.

    As a result of the US and Israel’s war with Israel, there has been significant disruption to shipping through the Strait of Hormuz, which normally transports around 20% of the world’s oil and gas exports.

    This has driven global energy prices higher, with Brent hitting more than $114 a barrel in May this year.

    The price of Brent remains 10% higher than prior to the US and Israel attacking Iran on 28 February.

    Libya is well-positioned to capitalise on the ongoing uncertainty around exports via the Strait of Hormuz, as energy-importing nations seek reliable oil and gas supplies.

    The North African country is located near Europe, with several large oil and gas export ports and a pipeline that transports gas to Italy.

    Libya has the largest oil reserves in Africa, but has struggled to implement projects to develop them over recent years due to political infighting and security problems.


    READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDF

    GCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.

    Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17389246/main2010.jpg
    Wil Crisp
  • Contractors prepare bids for Jafurah fifth expansion phase

    23 June 2026

     

    Contractors are preparing to submit bids to Saudi Aramco for a major project representing the fifth expansion phase of the Jafurah unconventional gas development programme in Saudi Arabia.

    The main scope of work on the Jafurah fifth expansion phase project involves the engineering, procurement and construction (EPC) of three gas compression plants at the giant gas basin in the kingdom’s Eastern Province. Each plant will be capable of processing up to 200 million cubic feet a day (cf/d).

    Aramco is said to have issued the main EPC tender for the project during the first quarter of the year. The current deadline for contractors to submit bids is 12 July, according to sources.

    Aramco issued a solicitation of interest (SoI) for the Jafurah fifth expansion phase project in mid-November, with contractors submitting responses by 30 November, MEED previously reported.

    UK-headquartered Wood Group has carried out the front-end engineering and design (feed) for the Jafurah fifth expansion phase project.

    The Jafurah basin is the largest liquid-rich shale gas play in the Middle East, spanning around 17,000 square kilometres. The reserve is estimated to contain 229 trillion cubic feet of gas and 75 billion stock-tank barrels of condensate.

    Aramco recently brought the greenfield Jafurah gas processing plant online, with a production capacity of 450 million cf/d, marking the commissioning of the first phase of its $100bn capital expenditure programme to produce gas from the unconventional resource base.

    The Saudi energy giant had earlier stated it expected to start gas production at Jafurah in 2025, with the intention of progressively ramping up to 2 billion cf/d of sales gas, 420 million cf/d of ethane and 630,000 barrels a day (b/d) of high-value liquids by 2030.

    Aramco has said that its unconventional gas programme, at peak production, is expected to generate electricity equivalent to displacing 500,000 b/d of oil.

    Jafurah gas development phases

    Along with overseeing the main tending exercise for EPC works on the fifth expansion phase project at Jafurah, Aramco also recently kicked off EPC works on the fourth expansion phase.

    MEED reported in April that Aramco had selected Indian contractor Larsen & Toubro Energy Hydrocarbon (L&TEH) as the main contractor for the Jafurah fourth expansion phase, which sources estimate could be valued at around $1.5bn.

    The main scope of work on the Jafurah fourth expansion phase project involves the EPC of two gas compression trains at the giant gas basin in the kingdom’s Eastern Province. Each plant will be able to process up to 200 million cubic feet a day (cf/d).

    Aramco has, however, only issued a draft letter of award for the project to L&TEH, based on which the contractor has started EPC works. The official contract award and final investment decision (FID) are pending, according to sources.

    Progress on the fourth and fifth expansion phases of the Jafurah unconventional gas development programme continues, as EPC work on the third phase advances.

    In July 2024, Aramco issued a non-binding letter of intent to a consortium of Tecnicas Reunidas and Sinopec Group for the EPC contract for the Jafurah third expansion phase. The value of the contract is estimated to be $2.24bn.

    The objective of the third expansion phase of Jafurah is similar to that of the fourth phase of development. The main scope of work involves the EPC of three gas compression plants, each with a capacity of 200 million cf/d.

    The third phase’s scope of work also includes building a 230kV substation to power the new gas compression plants and installing other utilities units, piping systems and safety equipment.

    The selection of contractors for the third expansion phase of the Jafurah development came within weeks of Aramco officially awarding EPC contracts for the second expansion phase, which aims to raise its processing potential to up to 2 billion cf/d of raw gas produced from the Jafurah field.

    Aramco awarded 16 contracts, worth a combined total of about $12.4bn, for the second expansion phase on 30 June 2024.

    The EPC scope of work on the project involves the construction of gas compression facilities and associated pipelines and the expansion of the Jafurah gas plant, including the construction of gas processing trains, utilities, sulphur and export facilities, Aramco said in a statement.

    The main EPC packages of the Jafurah second expansion phase project, their estimated values and the selected contractors are:

    • Package 1 – gas processing plant and main process units – $2.9bn: Larsen & Toubro Energy Hydrocarbon (India)
    • Package 2 – utilities and offsites – $2.4bn: Hyundai Engineering (South Korea)
    • Package 3 – gas compression units – $1bn: Larsen & Toubro Energy Hydrocarbon
    • Riyas natural gas liquids (NGL) package 1 – NGL fractionation trains – $1bn: Tecnicas Reunidas / Refining & Chemical Engineering Group (part of China’s Sinopec Group)
    • Riyas NGL package 2 – utilities, storage and export facilities – $2.2bn: Tecnicas Reunidas/Refining & Chemical Engineering Group
    • Riyas NGL package 6 – site preparation works – $107mMofarreh Alharbi & Partners (Saudi Arabia)
    • Riyas NGL package 9 – temporary construction facilities – $80mMofarreh Alharbi & Partners

    Aramco kickstarted EPC works on the first phase of the programme in November 2021 by awarding $10bn-worth of subsurface and EPC contracts.

    In February 2020, Aramco received a capital expenditure grant of $110bn from the Saudi government for the long-term phased development of the Jafurah unconventional gas resource base.

    The Jafurah unconventional gas development programme is central to Aramco’s goal of increasing gas production capacity. The target has recently been raised to 80%, with 2021 as the baseline, up from 60%, to meet rising domestic and global demand. The company expects life-cycle investment in Jafurah to exceed $100bn.

    Prior to the commissioning of the Jafurah gas plant in the last quarter of this year, Aramco completed an $11bn lease-and-leaseback deal in late October for gas processing facilities at the Jafurah unconventional gas reserve with a consortium led by funds managed by Global Infrastructure Partners (GIP), part of US asset manager BlackRock.

    Under the transaction, which Aramco started in August, a newly formed subsidiary – Jafurah Midstream Gas Company (JMGC) – will lease development and usage rights to the Jafurah field gas processing plant and the Riyas natural gas liquids (NGL) fractionation facility.

    After 20 years, JMGC will lease the assets back to Aramco. JMGC will collect a tariff payable by Aramco in exchange for granting Aramco the exclusive right to receive, process and treat raw gas from the Jafurah resource base.

    Aramco will hold a 51% majority stake in JMGC, while the GIP-led consortium will hold the remaining 49%. Investors participating in the GIP-led consortium include Hassana Investment Company, The Arab Energy Fund (TAEF) and Aberdeen Investcorp Infrastructure Partners, as well as other institutional investors from North and Southeast Asia and the Middle East.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17385386/main5205.jpg
    Indrajit Sen