Lessons learnt from a power plant decommissioning
26 February 2026

Al-Kamil power plant, a 280MW, gas-fired power plant in the Sharqiya region of Oman, was recently decommissioned following nearly 20 years of operations as the country’s second independent power plant.
The plant reached commercial operation in 2002, at which time it started to supply electricity to Nama Power & Water Procurement Company under a 15-year power purchase agreement that was later extended to the end of 2021. No further extension was granted so, in 2022, the decommissioning process was initiated.
Al-Kamil power plant was one of the first privately owned power plants in Oman to be decommissioned. The entire process took significantly longer than planned – three years compared to an initial target of 12 months. This was not unexpected, however, as there were not yet any standard processes to follow. Everything was being done for the first time, and proper procedures had to be established.
Starting decommissioning
The decommissioning of a power plant is a complex process and can take as much time to complete as it takes to build a plant. It involves environmental considerations, health and safety protocols, detailed surveys, de-energisation, dismantling, demolition, waste management and the segregation and storage of secondary valuables.
Careful planning and management are essential to ensure that decommissioning is accomplished safely, cost-effectively and in accordance with all government environmental standards.
Consulting on the decommissioning of Al-Kamil were Dubai’s Golden Sands Marketing Consulting (GSMC), appointed in 2021, alongside Abu Dhabi’s Sustainable Water & Power Company (SWPC) and Dubai’s Tractebel Engineering Company (TEC).
One of the first steps that GSMC undertook was to prepare a master plan covering the entire decommissioning process (see right).
A site investigation was undertaken by GSMC and SWPC early in the process to determine the condition of the power assets and the overall site.
The Al-Kamil power plant was found to have been well maintained, with no major health, safety, security and environment (HSSE) issues.
SWPC prepared the dismantling guidelines covering all plant equipment, and these were reviewed by TEC. The guidelines covered three main phases: the shut down and isolation of all assets; the de-
energisation process; and the dismantling of the plant equipment, its removal from site and the demolition of all remaining civil works.
GSMC designed a sales strategy for the plant equipment, taking into consideration the secondary market for power-related equipment, as well as the scrap market in Oman. A competitive procurement process was also followed in an effort to maximise sales revenues from plant equipment.
A separate tender was issued to appoint a demolition contractor to remove the remaining civil works, and once this work was complete, a local environmental engineering company undertook a final environmental report to demonstrate that the site was properly cleared and ready for handover to the original owner, the Housing & Urban Planning Ministry.
Final results
The decommissioning project went well in terms of HSSE considerations, with no fatalities, no lost-time injuries and no first aid injuries over the more than 243,000 total workhours at the site.
There were no material environmental spills or incidents to report, and all above- and below-ground structures were demolished and safely removed from the site in accordance with local requirements.
The final environmental report, completed just before handover, showed that the site was effectively in the same condition as it was when originally taken over at the start of construction.
The decommissioning was also successful from a financial perspective, as revenues from the sale of plant equipment and diesel fuel were beyond what was required to cover the costs associated with the decommissioning process.
Lessons learnt
Many lessons were learnt during the process that can benefit future power plant decommissioning efforts in the region.
> Notify key stakeholders early: Key stakeholders are those that have a vested interest in the project, either through ownership of certain assets on site, such as grid connection assets, or via regulation, such as the environmental authority. Many of these stakeholders take time to respond, so notifying key stakeholders early in the process can ensure that unnecessary delays are avoided.
> Prioritise HSSE: For any future decommissioning project, HSSE must be a top priority, and this should be the focus throughout the entire decommissioning process – at all levels of work and management.
The site manager at Al-Kamil installed a 24/7 closed-circuit television camera, which proved to be extremely effective in terms of monitoring progress and identifying potential HSSE issues before they became an incident. This simple and cost-effective practice should be replicated for all future decommissioning projects.
> Appoint the environmental consultant early in the process: It is advisable to appoint an environmental consultant early in the process. The consultant is needed to coordinate activities with the local environmental authority and obtain a no-objection letter or certificate, complete an environmental management report and an update of the environmental impact assessment, which includes an environmental baseline.
Ideally, these reports and environmental authority approvals should be completed well before any work is under way at the site. This information is also useful to potential bidders for the sale of equipment, or to contractors involved in the dismantling and demolition process.
> Submit an environmental management plan for approval: It is unlikely that any environmental authority will provide a no-objection letter or certificate without reviewing the environmental plan. It is therefore necessary to complete the plan early, prior to informing the environmental authority. This can minimise potential delays in starting the decommissioning process.
As a general practice, an environmental consultant should be brought on board early in the process, ideally once the overall master plan is approved by the company.
> Establish a proactive steering committee: This was done at Al-Kamil and proved to be effective when it came to overseeing project progress and dealing with issues as they arose. Certain members of the steering committee visited the site regularly and undertook spot HSSE inspections.
At Al-Kamil, the overall decommissioning was relatively straightforward as the plant was in a remote area. However, decommissioning a power plant in a busier location, or when part of the power plant remains in operation, is more challenging. Under these circumstances, a steering committee is vital.
> Set realistic delivery and completion timelines: Decommissioning a power plant is a complex process. The initial timeline to complete the process for Al-Kamil was one year, which was the best estimate at the time as there were no benchmarks or references in Oman. However, the actual completion time turned out to be three years – longer than the approximately 2.5 years it took to build the plant, from the start of construction in early 2001 to full commercial operation in July 2003.
Realistic delivery dates should be set for contractors, suppliers and others involved in the decommissioning process. This is likely to result in better pricing, as bidders tend to factor in higher contingencies with shorter or fast-track delivery dates. More realistic delivery dates also help management to allocate staff resources and manage the decommissioning budget.
Finally, realistic delivery dates help to manage owner and shareholder expectations regarding project completion.
Given the experience with Al-Kamil, a reasonable decommissioning timeline for a power plant is probably close to the actual construction timeline for the plant involved.
> Allow time to maximise revenues from the sale of assets: The market value for Al-Kamil’s power assets was estimated at a value significantly higher than the prevailing scrap value. This was based in part on the value of similar gas turbine units, after adjusting for age, usage and other factors that affect the net market value. However, the company realised a much lower value, even after retendering the equipment sales in an effort to get a better price.
It appears that prices close to the market rate are only achievable if there is time to find a suitable buyer. This can take many months or even years – typically a longer time than the owners of power plants wish to take.
Moreover, as renewables continue to penetrate the market, there is less worldwide demand for used gas turbine units. Prevailing market supply and demand conditions also have a bearing on the sale price for secondary equipment, and this factor needs to be considered.
If time is of the essence, then power plant owners need to accept the fact that the expected revenues will likely be on the low side, although still higher than the scrap value of the assets.
Main image: Picture 1: Al-Kamil power plant as constructed; Picture 2: Post decommissioning
Exclusive from Meed
-
KBR re-evaluates design for Libya oil project10 July 2026
-
Qiddiya to tender high-speed rail in September10 July 2026
-
-
Contractor appointed for Dubai’s One B Tower9 July 2026
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
KBR re-evaluates design for Libya oil project10 July 2026

US-headquartered KBR is responsible for re-evaluating the front-end engineering and design (feed) for the project to develop the J6 North Gialo field in Libya, according to industry sources.
In June, MEED reported that Libya’s Waha Oil Company (WOC), a subsidiary of the state-owned National Oil Corporation (NOC), had launched a review into the tender process for the J6 North Gialo oil field development project, and that this would include re-evaluating the feed work.
The Waha concessions are held by a consortium of Libya’s NOC, which holds 59.16%; TotalEnergies, holding 20.42%; and US-based ConocoPhillips, with 20.42%.
They are operated by WOC, which is 100% owned by NOC.
KBR has previously provided engineering services for major national projects in Libya, such as the Great Man-Made River project, which is widely recognised as the largest irrigation project in the world.
In March, KBR was awarded a contract by Zallaf Exploration, Production & Refining of Oil & Gas Company to provide project management and technical services for the South Refinery project in Libya’s southern city of Ubari.
Under the terms of the contract, KBR will provide contract management, project management and supporting technical services throughout the engineering, procurement and construction (EPC) phases of the project.
The EPC work is expected to be executed over a 50-month period.
In its statement, KBR said that the project is aligned with its “long-standing commitment to advancing vital oil and gas infrastructure in Libya”.
In March, MEED reported that South Korea’s Daewoo had pulled out of the tender process for Libya’s J6 North Gialo oil field development project.
Daewoo had formed a partnership with Egypt’s Petrojet to participate in the tender process.
The only other company to submit a bid for the project was UK-based Petrofac, which filed for administration in October last year.
In January, TotalEnergies signed an agreement extending the Waha concessions agreement up to 31 December 2050.
This agreement set new fiscal terms, allowing an increase in the production of these concessions that were, at the time, producing about 370,000 barrels of oil equivalent a day (boe/d).
In January, TotalEnergies said that the deal paved the way for “a new phase of investments, including the development of the North Gialo field, which is expected to add 100,000 boe/d of production”.
The J6 North Gialo project is the first of three field development projects that WOC has prioritised.
The other two are known as NC98 and Gialo 3.
Together, the three projects are expected to double Waha’s production from about 300,000 barrels a day (b/d) of oil to 600,000 b/d.
The Waha concession covers 13 million acres.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17621475/main.jpg -
Qiddiya to tender high-speed rail in September10 July 2026

Saudi Arabia’s Royal Commission for Riyadh City, in collaboration with Qiddiya Investment Company and the National Centre for Privatisation & PPP, are expected to float the tender in September for the Qiddiya high-speed rail project in Riyadh.
MEED understands that the clarification process is ongoing for the engineering, procurement, construction and financing (EPCF), as well as the public-private partnership (PPP) packages.
The Qiddiya high-speed rail project, also known as Q-Express, will cover 84 kilometres, connecting King Salman International airport and King Abdullah Financial District with Qiddiya City.
In April, MEED exclusively reported that the clients had received prequalification statements from firms for the EPCF package of the project.
MEED also reported in May that firms were forming joint ventures for the PPP package of the project.
The line will operate at speeds of up to 250 kilometres an hour, reaching Qiddiya in 30 minutes.
There are five stations planned: Qiddiya Grand Central Station, Qiddiya Uptown Station, King Abdullah Financial District, Terminal 6 King Salman International airport (KSIA) and Iconic Terminal at KSIA.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17621301/main.jpg -
Middle East construction cost inflation to hit 5.1% by 20279 July 2026
Construction cost inflation in the Middle East is forecast to reach 5.1% in 2027, the second-highest of any region worldwide, as global demand for data centres tightens contractor capacity and deepens shortages of skilled labour.
The projection comes from the Global Construction Market Intelligence report, published by UK programme manager Turner & Townsend. The report draws on data from 112 markets across 44 countries, gathered between 2 March and 20 March 2026.
Only Africa is expected to see steeper cost escalation, at 7%. Australia and New Zealand follow the Middle East at 4.9%, while the EU records the lowest figure at 2.8%. Globally, construction cost inflation is set to rise from 4.2% in 2025 to 4.5% in 2026 before flattening in 2027.
The report identifies a two-speed market. Data centres are now the most in-demand construction sector globally, followed by industrial and logistics. More than 70% of the 112 markets surveyed report tightening or overstretched contractor capacity in the data centre sector. By contrast, more than 79% of markets show balanced or spare capacity across hospitality and leisure, residential and commercial development.
Skills shortage
Labour availability has displaced material costs as the primary driver of cost escalation. About 71% of markets report labour shortages. Skills deficits are most acute in mechanical, electrical and plumbing (MEP) trades, with 87% of markets reporting MEP shortages. These trades are central to data centre delivery.
The findings carry weight for the GCC, where sovereign programmes in Saudi Arabia and the UAE are competing for the same contractor pools that artificial intelligence (AI) infrastructure now draws on. Regional governments have announced large data centre commitments alongside gigaprojects, housing and transport schemes, placing further strain on an already stretched supply chain.
Turner & Townsend says that construction input costs have stabilised over the past year, with supply chain resilience built since the pandemic limiting the impact of recent volatility. Cost drivers are becoming more localised and sector-specific rather than the product of international shocks.
Energy market exposure introduces a separate risk. The report cites oil prices, higher transport and freight costs, and volatility in petrochemicals inputs as significant challenges. Disruption to shipping routes lengthens lead times and adds supply chain volatility.
Conflict assumptions
The baseline scenario assumes a relatively short-lived conflict in the Middle East and a moderate rise in energy commodity prices in 2026. A prolonged or escalating conflict would produce more pronounced effects on inflation, supply chains and construction costs.
New York remains the world's most expensive construction market at $7,938 a square metre, followed by San Francisco at $7,883 and Geneva at $6,985. London ranks fifth at $6,032.
North America carries the highest regional labour costs, with an average hourly wage of $79.5, ahead of the EU at $75.6 and Australia and New Zealand at $68.
Digital adoption remains uneven, though momentum is building. Sixty-six percent of markets report that AI capability now carries more weight in tendering and client discussions than it did 12 months ago.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17606750/main.gif -
Contractor appointed for Dubai’s One B Tower9 July 2026

Dubai-based construction firm Naresco Contracting has been awarded a contract to build One B Tower, located on Dubai's Sheikh Zayed Road.
Local real estate developer Wasl Group awarded the contract.
It covers a 47-storey high-rise tower offering a mix of one- to four-bedroom residential units.
The project is also known as One Billion Meals Endowment Tower.
The enabling works were undertaken by local firm APCC Building Contracting.
Netherlands-headquartered UN Studio is the project architect.
Dubai-based firm Studio International Engineering Consultants is the project consultant.
The project is slated for completion by 2028.
This is the second major contract to have been awarded by Wasl Group this year for a residential development.
In January, the firm awarded an estimated $250m deal to build the Avenue Park Towers project in Dubai to South Korean contractor Ssangyong Engineering & Construction.
The development comprises two mixed-use buildings offering residential and commercial facilities. One of the towers will have 43 floors while the other will have 37.
The project is slated for completion by 2028.
Wasl Group's latest contract award in the UAE market is backed by heightened real estate activity in the construction sector, with schemes worth over $323bn in the execution or planning stages, according to UK analytics firm GlobalData.
The company forecasts that output from the UAE’s residential construction sector will grow by 3% in real terms in 2026-29, supported by infrastructure, energy and utilities developments, as well as residential construction projects.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17605135/main.jpg -
Iran and US break peace deal and resume Gulf attacks9 July 2026
Iran and the US have once again traded attacks in the Gulf region, in the worst exchange of fire since the two nations signed an interim peace deal in June.
US Central Command (CentCom) said on 7 July that it had launched strikes in response to attacks on three oil tankers in the Strait of Hormuz, hitting more than 80 targets including air defence systems, coastal radar and fast boats.
In retaliatory attacks on 8 July, Iran said it had targeted US military sites in Bahrain and Kuwait.
Oil prices have spiked following the strikes, with global benchmark Brent crude trading at $77.32 a barrel as of 1pm Gulf Standard Time.
UK Maritime Trade Operations (UKMTO) said a tanker travelling through the strait had reported a fire after an unknown projectile hit an engine room on 6 July.
In two separate incidents on 7 July, a tanker reported it had been hit as it exited the strait but was able to proceed to its next port of call, while another tanker reported sustaining minor structural damage after being struck, UKMTO said.
Qatar and Saudi Arabia have denounced the attacks, each saying a tanker from its country had been hit while transiting in or near the strait, and blaming Iran.
A spokesperson for Qatar's foreign ministry, Majed Al-Ansari, said it held Iran fully responsible for an apparently targeted attack on a vessel called Al-Rekayyat as it transited near the Strait of Hormuz.
Saudi Arabia's foreign ministry said Iran had targeted the Saudi tanker Wedyan as it crossed the strait. The owner of the very large crude carrier, the kingdom’s national shipping company Bahri, confirmed the attack on the vessel in a statement on 7 July, adding that “all crew members are safe and accounted for, and the cargo remains secure”.
“The vessel remains in a seaworthy condition. The company promptly informed all relevant authorities and continues to work closely with them and other maritime stakeholders, while maintaining continuous communication with the vessel's crew and closely monitoring the situation,” Bahri said.
“Bahri continues to closely monitor developments in the region and has implemented appropriate precautionary measures to support the safety of its people, vessels and operations,” it added.
Breakdown of peace deal
Separately, the US also said it had revoked its temporary suspension of sanctions on Iranian oil sales. Iran's speaker Mohammad Bagher Ghalibaf accused the US of breaching their memorandum of understanding (MoU) on this issue, and others, including the attacks in southern Iran and "violating Iranian adjustments in the strait".
Missiles and drones were launched at "85 key US military facilities", including a US Navy headquarters and an air base in Kuwait, the Islamic Revolutionary Guard Corps (IRGC) said.
Iranian state media agency Irna also reported the death of an IRGC guard in the US strikes, “after being struck by shrapnel from a projectile".
Kuwait has responded to the Iranian strikes on its country, lambasting the "repeated attacks".
Talks on reaching a permanent peace deal have been on hold due to the state funeral in Iran for the late Supreme Leader Ayatollah Ali Khamenei, who was killed on 28 February – the first day of US-Israeli strikes on Iran.
Early on 7 July, Iran's deputy foreign minister described the US attacks as a violation of the US-Iran MoU signed on 14 June, and warned Tehran would "take decisive measures".
The US had said there would be consequences for what it called the "wholly unacceptable" attacks on the three tankers.
CentCom said that in addition to 60 small boats, it had struck Iranian missile launch sites and command centres. It did not give the locations of its targets.
It said the strikes were "to impose heavy costs for targeting and attacking commercial shipping crewed by innocent individuals in an international waterway".
Before the strikes, the US Treasury revoked a waiver that had temporarily lifted oil sanctions on Iran and was part of the MoU signed by Washington and Tehran in June.
Iran's foreign ministry called the move a breach of the MoU and said it proved the "bad faith, inconsistency and unreliability" of the US government.
It added that Tehran "will take whatever measures it considers necessary to safeguard its national interests and national security".
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17605530/main5658.jpg