Kuwait aims to award revegetation deal in late 2023

18 May 2023

State-owned upstream operator Kuwait Oil Company (KOC) is aiming to award contracts for planned revegetation works as part of the multibillion-dollar Kuwait Environmental Remediation Programme (Kerp) in late 2023 or early 2024, according to Muthanna al-Mumin, a team leader for remediation projects at the company.

In an interview with MEED, he said: “The company is working diligently in collaboration with the various committees to roll out the revegetation tender and we target the award of the revegetation works in late 2023 or early 2024 at the latest.

“The upcoming election will have no bearing on our drive to achieve our targets and we have full support from Kuwait’s leadership in moving forward with our programme.

“The award of the revegetation contracts will be a statement to the international community of Kuwait’s and Kuwait Oil Company’s commitment to the environment.”

Earlier this year, KOC extended the bid deadlines for the recently tendered revegetation contracts, increasing expectations that the scheme would be significantly delayed.

Bids for the contracts are currently due to be submitted by 18 June 2023. Previously, the deadline for the bids was 16 April.

The project is expected to be divided into four separate packages with a combined value of about $675m.

The four revegetation contracts being tendered by KOC are expected to be awarded to four separate contractors and include a wide range of work activities, according to internal documents that were obtained by MEED in March.

These have been divided into enabling works and revegetation works.

The required enabling works include:

  • Health, safety and environmental studies
  • Topographical surveys
  • Constructing roads
  • Installing temporary site offices
  • Assessing risks posed by unexploded ordnance
  • Carrying out geophysical surveys for unexploded ordnance and unexploded ordnance clearance
  • Installing fencing
  • Groundwater monitoring well installation
  • Designing, constructing, operating and maintaining an on-site seeding nursery
  • Designing and constructing permanent offices
  • Designing, constructing and commissioning a water pipeline and associated tankage
  • Designing, constructing and commissioning a permanent water treatment system and accessories
  • Water well infrastructure and connection

The required revegetation works include:

  • Plant procurement and delivery
  • Planting procedures and layout
  • Irrigation
  • Aftercare and maintenance

The winners of the contracts will use the soil that is currently being processed to remove oil pollution in ongoing remediation projects. This soil will be distributed in multiple areas and seeded with native plants.

A total of 10 different species of grass and shrub have been approved for the project, as well as two different tree species.

After the contract award, there will be an “establishment period” of 180 days before the contract formally commences.

This will be followed by a “performance period” of 2,000 days.

According to the original project schedule, plant installation will be complete by the end of March 2027, and the whole project is scheduled to be finished by the end of July 2029. 

Due to the delays to the tendering schedule, the targets for project completion may now be pushed back.

Each contractor will be required to plant several million plants as part of their contract, over a period of three years.

The contractors will only be permitted to plant seasonally, from 1 September to 31 March.

The project is the last to be tendered as part of Kerp.

Kerp is the largest environmental remediation project in the world and was established by the UN Compensation Commission to allow Kuwait to address the ecological damage resulting from the 1990-91 Gulf War.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10861190/main.jpg
Wil Crisp
Related Articles
  • Oman 500MW solar project secures financing

    8 December 2023

    Oman's Manah 1 solar photovoltaic (PV) independent power producer (IPP) project has signed financing deals worth $302m with France's Societe Generale, the Export-Import Bank of Korea (Korea Eximbank) and Bank Muscat.

    The Manah 1 IPP developers and investors, comprising Korea Western Power Company (Kowepo) and France's EDF Renewables, signed the deal on 6 December.

    According to a local media report citing a Kowepo statement, the Korea Eximbank plans to provide $170m in project financing.  

    A team comprising EDF Renewables and Kowepo started mobilising to construct the 500MW Manah 1 solar IPP project in Oman, as MEED reported in September.

    The solar power plant will span over 7.8 square kilometres in Oman’s Al-Dakhiliyah governorate. 

    The developer intends to deploy over 1 million bifacial photovoltaic (PV) modules mounted on a single-axis tracker system for the plant.

    A project company, Wadi Noor Solar Power Company, has been formed to deliver and operate the project for 20 years.

    The company will work with Australia-headquartered Worley, which has recently been appointed as the owner engineer for the project.

    Oman Power & Water Procurement Company (OPWP) signed the 20-year power-purchase agreements (PPA) for the Manah 1 and Manah 2 solar IPP projects in March this year.

    Both plants are expected to be operational by 2025.

    A team of Singapore’s Sembcorp Industries (Sembcorp) and China-headquartered Jinko Power Technology was awarded the 500MW Manah 2 solar PV IPP contract.

    Manah 1 and 2 were previously named Solar IPP 2022 and 2023.

    To be located 150 kilometres southwest of Muscat, the Manah 1 and 2 solar projects comprise the second utility-scale renewable energy projects to be tendered by OPWP, after Ibri 2, which has been operational since 2021.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11358677/main.jpg
    Jennifer Aguinaldo
  • Masdar and OMV sign green hydrogen agreement

    8 December 2023

    Abu Dhabi Future Energy Company (Masdar) and Austrian energy and chemicals firm OMV have signed a preliminary agreement to partner in the production of green hydrogen for the decarbonisation of industrial processes in OMV’s refineries.

    The non-binding heads of terms (HoT) agreement forms the basis of a joint agreement to develop an industrial large-scale electrolysis plant, which will be powered by renewable energy, Masdar said in a statement on 8 December.

    The statement added that the partners will collaborate to develop the project and plan to make a final investment decision in the second half of 2024.

    The HoT signing follows an initial memorandum of understanding (MoU), which the two parties signed in Abu Dhabi earlier this year.

    The agreement with OMV is a step in the right direction towards building a robust hydrogen value chain and supports Masdar's ongoing aim of 1 million tonnes of green hydrogen per annum globally by 2030, according to Masdar's chief green hydrogen officer, Mohammad Abdelqader el-Ramahi.

    Green hydrogen oasis

    According to MEED data, there are at least 12 known and planned green hydrogen projects in the UAE, with a budget of at least $12bn.

    In addition to the planned $5bn green hydrogen hub planned by Masdar and French utility developer and investor Engie, the other major planned green hydrogen projects in Abu Dhabi involve its largest industrial firms, including Abu Dhabi National Energy Company (Taqa), Emirates Steel, Fertiglobe and Brooge.

    One of these projects, the 150MW green hydrogen-based ammonia production facility planned in Ruwais, is expected to reach a financial investment decision (FID) shortly.

    The UAE's Green Hydrogen Strategy envisages the production of 1.4 million tonnes a year (t/y) of hydrogen by 2031, with green hydrogen accounting for 70 per cent of the target.

    This is expected to increase to 7.5 million t/y by 2040 and 15 million t/y by 2050. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11358471/main.jpg
    Jennifer Aguinaldo
  • Sheikh Mohammed inaugurates Dubai CSP plant

    7 December 2023

    Sheikh Mohammed bin Rashid al-Maktoum, UAE Vice President and Prime Minister and Ruler of Dubai, has inaugurated the fourth phase of the Mohammed bin Rashid al-Maktoum (MBR) Solar Park in Dubai.

    The 950MW fourth phase of the MBR solar park required an investment of AED15.78bn ($4.34bn).

    It uses hybrid technologies: 600MW from a parabolic basin complex, 100MW from the CSP tower, and 250MW from solar photovoltaic (PV) panels.

    The independent power producer (IPP) project features the tallest solar tower in the world, at 263.126 metres, and a thermal energy storage facility with a capacity of 5,907 megawatt-hours (MWh), the world's largest according to the Guinness World Records.

    The project covers an area of 44 square kilometres. It features 70,000 heliostats that track the sun’s movement. The molten salt receiver (MSR) on top of the solar power tower is the core and the most important part of the CSP plant. It receives solar radiation and turns it into thermal energy.

    The MSR contains over 1,000 thin tubes that enable the absorption of sun rays and their transfer to the molten salt within these tubes.

    The project can power approximately 320,000 residences with clean and sustainable energy. It will reduce carbon emissions by about 1.6 million tonnes annually.

    The completion of the project's fourth phase brings the total capacity of the MBR solar park to 2,863MW so far. The phases and their capacities are:

    • 13MW solar PV phase one: Completed in 2013
    • 200MW solar PV phase two: Commissioned in 2017
    • 800MW solar PV phase three: Commissioned in 2020
    • 950MW hybrid CSP/solar PV phase four: Inaugurated in 2023
    • 900MW solar PV phase five: Commissioned in 2023

    Dewa is aiming for the MBR development to reach 5,000MW of capacity by 2030. It recently awarded the UAE-based Masdar the contract to develop the solar park's sixth phase, which has capacity of 1,800MW.

    Project background

    Dubai Electricity & Water Authority (Dewa) awarded a consortium of Saudi Arabia’s Acwa Power and China's Silk Road Fund the contract to develop a 700MW CSP plant with storage for the fourth phase scheme in November 2017. Since then, the project has been expanded to include a 250MW solar PV component.

    Acwa Power then awarded Shanghai Electric the $3.8bn EPC contract for the hybrid CSP/PV plant in early 2018.

    The project reached financial closure in March 2019. The cost will be met through $2.9bn of debt and $1.5bn of equity.

    According to the project structure, Dewa is to provide $750m, or half of the project equity. Project developers Acwa Power and the Silk Road Fund will provide 51 per cent and 49 per cent, respectively, of the remaining equity.

    The fourth phase project achieved a tariff of 7.3 $cents a kilowatt hour ($c/kWh) for the CSP component and 2.4$c/kWh for the PV capacity, two of the lowest tariffs for CSP and PV solar technology in the world at the time of award.

    Dewa holds a 51 per cent stake in the project company, Noor Energy 1, set up to develop the plant, with Acwa Power and the Silk Road Fund holding the remaining stake. The developer consortium has signed a 35-year power-purchase agreement to supply power to Dubai’s grid.

    Photo: Wam

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11354147/main.jpg
    Jennifer Aguinaldo
  • Firms win Saudi Landbridge

    7 December 2023

     

    Register for MEED’s guest programme 

    The team of US-based Hill International, Italy’s Italferr and Spain’s Sener has been awarded the contract to provide project management services for the estimated $7bn Saudi Landbridge project.

    The Landbridge is a rail project that will connect the Red Sea coast of Saudi Arabia in the west and the Gulf coast in the east. It is one of the largest infrastructure projects planned in Saudi Arabia. The scheme is being implemented by the Saudi Railway Company (SAR).

    Project scope

    The project comprises six lines. The first line involves upgrading the Jubail Industrial City internal network, which is currently under construction. It will require 10 kilometres (km) of track to be built.

    The second is the upgrade of the Jubail to Dammam railway line, which is also currently under construction. It will require 35km of track to be built.

    The third line involves the upgrade of the Dammam to Riyadh railway line, with 87km of track to be built. 

    The fourth line, known as the Riyadh bypass, is from the existing network in the north of the city to the south. It is split into two packages: the first has 67km of track, and the second has 35km.

    The fifth line is a link from Riyadh to Jeddah and then on to King Abdullah Port with three stations at Jamuma, Moya and Al-Doadmi. The Riyadh to Jeddah line will have 920km of track, and the Jeddah to King Abdullah Port link will have 146km of track.

    The sixth line is a new 172km line from King Abdullah Port to Yanbu Industrial City.

    There will also be seven logistics centres: Jubail Industrial City Logistics Centre, Damman Logistics Dry Port, a relocated Riyadh Dry Port, King Khalid Airport Logistics Centre in Riyadh, Jeddah Logistics Dry Port, King Abdullah Port Logistics Centre and Yanbu Industrial City Logistics Centre.

    Contractor negotiations

    MEED reported in November that negotiations with the Saudi China Landbridge Consortium that will build the rail link are in the final stages.

    The consortium signed a memorandum of understanding to implement the project on a public-private partnership basis in October 2018. It was formed by SAR and China Civil Engineering Construction Company.

    Al-Ayuni Contracting was named as the local partner for the consortium. Other members include French firms Systra and Thales; Canada’s WSP; Aldhabaan & Partners, the local partner of UK legal consultancy Eversheds & Sutherland; ALG Infrastructure; and Calx Consultancy.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11354086/main.jpg
    Colin Foreman
  • Siemens Energy wins five Iraq substation contracts

    6 December 2023

    Register for MEED's guest programme 

    Iraq's Electricity Ministry has awarded Germany-headquartered Siemens Energy a contract to deliver five high-voltage substations on a turnkey basis in Iraq.

    The 400-kilovolt (kV) substations will be installed in Baghdad, Diyala, Najaf, Karbala and Basra.

    Each substation will have a capacity of 1,500MW. Work on the substation projects is expected to commence in early 2024.

    German export credit agency Allianz Trade Trust, formerly Euler Hermes, will provide most of the project financing in collaboration with Iraq's Finance Ministry.

    MEED understands the substations address the increasing demand for power transmission in Iraq, providing power to around 2.5 million homes.

    On 5 December, a consortium led by K&K Group, which includes Siemens Energy, announced that it is moving ahead with a detailed study for an electricity corridor, known as Green Vein, whose initial stage will have the capacity to transmit up to 3GW of clean electricity from Egypt to Italy.

    Italian companies Cesi and Prysmian Group comprise the rest of the consortium planning to develop the Green Vein project.

    It entails the installation of a submarine high-voltage, direct current (HVDC) cable, which extends approximately 2,800 kilometres and reaches sea depths of up to 3,000 metres.

    The cable will connect the West Sohag area in Egypt to the Dolo substation near the Mestre Industrial Area in Italy.

    The project's initial capacity of 3GW equates to approximately 5 per cent of Italy's peak electricity demand.

    Image: Pixabay

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11352608/main.jpg
    Jennifer Aguinaldo