Kuwait aims to award revegetation deal in late 2023

18 May 2023

State-owned upstream operator Kuwait Oil Company (KOC) is aiming to award contracts for planned revegetation works as part of the multibillion-dollar Kuwait Environmental Remediation Programme (Kerp) in late 2023 or early 2024, according to Muthanna al-Mumin, a team leader for remediation projects at the company.

In an interview with MEED, he said: “The company is working diligently in collaboration with the various committees to roll out the revegetation tender and we target the award of the revegetation works in late 2023 or early 2024 at the latest.

“The upcoming election will have no bearing on our drive to achieve our targets and we have full support from Kuwait’s leadership in moving forward with our programme.

“The award of the revegetation contracts will be a statement to the international community of Kuwait’s and Kuwait Oil Company’s commitment to the environment.”

Earlier this year, KOC extended the bid deadlines for the recently tendered revegetation contracts, increasing expectations that the scheme would be significantly delayed.

Bids for the contracts are currently due to be submitted by 18 June 2023. Previously, the deadline for the bids was 16 April.

The project is expected to be divided into four separate packages with a combined value of about $675m.

The four revegetation contracts being tendered by KOC are expected to be awarded to four separate contractors and include a wide range of work activities, according to internal documents that were obtained by MEED in March.

These have been divided into enabling works and revegetation works.

The required enabling works include:

  • Health, safety and environmental studies
  • Topographical surveys
  • Constructing roads
  • Installing temporary site offices
  • Assessing risks posed by unexploded ordnance
  • Carrying out geophysical surveys for unexploded ordnance and unexploded ordnance clearance
  • Installing fencing
  • Groundwater monitoring well installation
  • Designing, constructing, operating and maintaining an on-site seeding nursery
  • Designing and constructing permanent offices
  • Designing, constructing and commissioning a water pipeline and associated tankage
  • Designing, constructing and commissioning a permanent water treatment system and accessories
  • Water well infrastructure and connection

The required revegetation works include:

  • Plant procurement and delivery
  • Planting procedures and layout
  • Irrigation
  • Aftercare and maintenance

The winners of the contracts will use the soil that is currently being processed to remove oil pollution in ongoing remediation projects. This soil will be distributed in multiple areas and seeded with native plants.

A total of 10 different species of grass and shrub have been approved for the project, as well as two different tree species.

After the contract award, there will be an “establishment period” of 180 days before the contract formally commences.

This will be followed by a “performance period” of 2,000 days.

According to the original project schedule, plant installation will be complete by the end of March 2027, and the whole project is scheduled to be finished by the end of July 2029. 

Due to the delays to the tendering schedule, the targets for project completion may now be pushed back.

Each contractor will be required to plant several million plants as part of their contract, over a period of three years.

The contractors will only be permitted to plant seasonally, from 1 September to 31 March.

The project is the last to be tendered as part of Kerp.

Kerp is the largest environmental remediation project in the world and was established by the UN Compensation Commission to allow Kuwait to address the ecological damage resulting from the 1990-91 Gulf War.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10861190/main.jpg
Wil Crisp
Related Articles
  • Iraq boosts oil exports after talks with Iran

    7 September 2026

    Iraq has boosted its oil export capacity to more than 3 million barrels a day (b/d) after holding talks with Iran, according to Oil Minister Basim Mohammed Khudair.

    In a video statement released on 5 September, he said the country has been able to ship more than 3 million b/d since the start of this month.

    He also said: “The government plans to raise export capacity to 5 million b/d after completing the strategic pipelines extending towards Fishakhpur and Banias, as well as the export outlets in the Strait of Hormuz.”

    Iraq’s oil exports rose to around 2.34 million b/d in August, according ⁠to ⁠officials.

    The increase came after Iran granted special permission for a number of Iraqi oil tankers to pass through the Strait of Hormuz in August, following repeated requests from Baghdad.

    On 22 August, Iraqi President Nizar Amidi said Iran had facilitated the passage of “some ships carrying Iraqi oil in the strait” in recent days, and Baghdad had discussed exporting Iraqi oil through Hormuz with Iranian officials.

    The details of Iraq’s agreement have not been released by officials, but Amidi said that his government “will not accept Iraqi territory being used to launch attacks against any other country”.

    The Iraqi president said attacks launched from inside Iraq against countries in the region “have no justification”.

    Prior to the deal being announced, Iraqi exports had been dramatically reduced amid fallout from the regional war that started when the US and Israel attacked Iran on 28 February 2026.

    The regional war has led to significant disruption to shipping through the Strait of Hormuz, which is a key export route for Iraqi oil.

    Iraq’s crude exports fell from more than 3.3 million b/d before the war to a low of about 330,000 b/d in April, while exports from its southern terminals were temporarily halted altogether in March.

    Tensions still remain high in the region, and some shipping is still being disrupted by the ongoing conflict.

    On 2 September, Saudi Arabia condemned an Iranian attack on an oil tanker owned by its national shipping company that resulted in the deaths of two citizens of the Philippines.

    In a statement, Saudi Arabia’s Foreign Ministry said Iran targeted the Sidr tanker, owned by national carrier Bahri, while it was transiting the Strait of Hormuz two days earlier.

    It said: “The kingdom stressed the necessity of halting escalations and respecting international maritime safety and the security of global energy supplies.”

    Kuwait and Qatar’s foreign ministries said the attack violated international law and freedom of maritime navigation.

    Qatar called the attack a “flagrant violation of the rules of international law and freedom of maritime navigation”. Doha further rejected the use of the Strait of Hormuz as a “bargaining chip”.

    Iran has repeatedly attacked and threatened tankers attempting to sail through the strategic waterway without authorisation, impeding energy exports from neighbouring oil-rich Gulf countries.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19424826/main.jpg
    Wil Crisp
  • Customs clearance delays Iraqi oil field development

    7 September 2026

     

    Problems getting critical equipment through customs are delaying a key part of Iraq’s $27bn Gas Growth Integrated Project (GGIP), according to industry sources.

    Phase one of the GGIP is expected to be worth about $10bn. France’s TotalEnergies holds a 45% stake in the project, while Iraq’s Basra Oil Company (BOC) and QatarEnergy hold 30% and 25% respectively.

    The specific part of the project that is being delayed by customs issues is known as Ratawi phase 1.

    It is focused on developing Iraq’s Ratawi oil and gas field as part of the wider GGIP.

    Previously, this project was expected to come online before the end of June this year.

    Speaking on 23 July 2026, TotalEnergies CEO Patrick Pouyanne said that Ratawi phase 1 was being delayed due to issues related to the conflict with Iran, but he still expected it to start up before the end of September 2026.

    Although recent complications are expected to delay the project further, it is on track to come online in mid-to-late October at the earliest, according to industry sources.

    One source said: “Right now, the main issue causing delays to the project isn’t the crisis in the Strait of Hormuz; it’s Iraqi customs clearance.

    “TotalEnergies is having trouble getting critical equipment released.”

    TotalEnergies did not respond to a request to comment on the progress of Ratawi phase 1.

    In November last year, the French company said that phase 1 aimed to increase production to 120,000 barrels a day (b/d).

    At the time, it also said that it was expected to come on stream “by early 2026”.

    It also said that the launch of phase 2 of the project, which would be considered “full field development”, would enable the company to increase production to 210,000 b/d starting in 2028.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19424624/main.png
    Wil Crisp
  • Firms prepare bids for NWC sewage treatment package 14

    4 September 2026

     

    At least three contractors are preparing to make offers for package 14 of Saudi Arabia’s long-term operations and maintenance (LTOM) sewage treatment programme, according to sources.

    Known as Eastern A Cluster (LTOM14), the package was tendered by the state-owned National Water Company (NWC) in April, with a bid submission deadline of 30 September.

    The contract covers the upgrade of six existing sewage treatment plants (STPs), with a capacity expansion of 30,000 cubic metres a day (cm/d) at the Al-Jarodia STP.

    This will increase total treatment capacity from about 263,000 cm/d to approximately 293,000 cm/d, with an estimated cost of $180m.

    According to sources, the firms preparing to submit bids include:

    • Alkhorayef Water & Power Technologies (Saudi Arabia)
    • Civil Works Company (Saudi Arabia)
    • Miahona (Saudi Arabia)

    The latest phase follows the formal signing of a $347m contract between NWC and a Saudi-Chinese consortium for Northern Cluster Sewage Treatment Plants Package 10 (LTOM10) on 2 September.

    The same consortium led by United Water (China) is not planning to bid for LTOM14 and is expected to formally sign a contract for LTOM11 in the coming months, a source said.

    In April, MEED exclusively reported that the group had won the contract for package 11, which will have a combined capacity of about 440,000 cm/d.

    It is also understood that Beijing Enterprises, a bidder for North Western B Cluster (LTOM12), is not preparing to bid for package 14.

    In the meantime, the contract for LTOM12 is moving towards award, with bids currently under evaluation.

    The contract covers the construction and upgrade of seven STPs with a combined capacity of about 162,000 cm/d. As previously reported, NWC opened financial bids for the project in April.

    US/India-based Synergy Consulting is Financial Advisor to NWC for the full LTOM programme.

    Future phases

    In total, the LTOM programme comprises 19 packages split into two phases. In May 2024, NWC announced it had awarded $2.5bn-worth of contracts in the first phase. Phase two of the programme includes 10 packages covering 117 treatment plants.

    In April, MEED exclusively reported that NWC had held several discussions regarding changes in scope details and potential expansions to upcoming projects. This involved “grouping some upcoming projects”.

    The request for proposals for LTOM13 was subsequently put on hold and it is now understood that this tender has likely been merged with other packages in the programme.

    According to a source, Eastern B Cluster (LTOM15) has also been cancelled and has likely been merged. LTOM15 had comprised two STPs with a total capacity of 152,000 cm/d.

    The next contract to be tendered will be Central Cluster (LTOM16), potentially in November, a source added.

    Under the original scope, LTOM16 covers the construction of 14 STPs with a total capacity of 153,000 cm/d.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19358188/main.jpg
    Mark Dowdall
  • Egyptian contractor wins Abu Dhabi Ramhan Island deal

    4 September 2026

    Egypt-headquartered contractor Rowad Modern Engineering has been awarded the main works contract for the Marina Apartments project on Ramhan Island, Abu Dhabi.

    The contract was awarded by the local firm Eagle Hills, which is led by Mohamed Alabbar, the founder and chairman of Emaar Properties.

    Rowad’s scope includes structural and architectural works, finishing, and mechanical, electrical and plumbing systems.

    The company will also deliver infrastructure works, including utility connections to external networks, testing and commissioning.

    The development comprises two residential towers offering 187 residential units.

    The works will be carried out under the consultancy supervision of local engineering firm Mirage Leisure & Development.

    The latest contract award follows Eagle Hills awarding the local firm Arabian Construction Company (ACC) an estimated AED2.5bn ($680m) construction contract to build about 500 villas at the Ramhan Island development, as reported by MEED previously.

    Located off the coast of Abu Dhabi, the Ramhan Island development spans an area of over 4 million square metres.

    The overall development includes the construction of 1,800 villas, 900 residences, a hotel and retail facilities.

    Mohamed Alabbar launched the Ramhan Island development in May 2024.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19355437/main.jpg
    Yasir Iqbal
  • Dubai sets deadline for Jebel Ali waste-to-energy PPP

    4 September 2026

     

    Register for MEED’s 14-day trial access 

    Dubai Municipality has set a 27 September deadline for developers to submit expressions of interest (EOIs) for its planned Jebel Ali waste-to-energy (WTE) public-private partnership (PPP), according to a source.

    The greenfield facility is planned to treat up to 6,000 tonnes of municipal solid waste a day.

    The municipality is seeking international and local developers to develop, finance and operate the facility. It is planning to prequalify developers later this year before issuing a request for proposals (RFP) in the first quarter of next year, a source said.

    The Jebel Ali facility is intended to support Dubai’s waste-management strategy and its target of reducing reliance on landfill.

    Dubai Municipality is being advised by a team led by Abu Dhabi’s Tribe Infrastructure Group, with UK-headquartered Ashurst and Germany’s Fichtner also involved.

    It was confirmed to MEED that the project is separate from the planned second phase of the Warsan WTE facility, for which Dubai Municipality issued a consultancy tender in February.

    That facility will be located in Warsan 2, next to the Al-Aweer sewage treatment plant. The expansion is expected to increase waste-conversion capacity at the existing Warsan site with an estimated budget of $500m. The consultancy contract has a duration of six years.

    The original Warsan WTE plant, Dubai’s first major WTE public-private partnership (PPP) project, reached full commercial operations in 2024.

    Located in the Warsan area, the AED4bn ($1.1bn) facility treats 1.9 million tonnes of municipal solid waste annually, generating up to 220MW of thermal energy that is fed into the local grid.

    In February 2023, state utility Dubai Electricity & Water Authority (Dewa) and Dubai Waste Management Company signed the power-purchase agreement (PPA) for the project.

    Dubai Waste Management Company, the special-purpose vehicle implementing the scheme, reached financial close in June 2021 for the project.

    The Warsan project was developed under a 35-year PPP concession by a consortium comprising Dubai Holding, Dubai Aluminium, Tech Group and Itochu Corporation. 

    The main contractor was a joint venture of Belgium’s Besix Group and Hitachi Zosen Inova of Switzerland.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19354502/main.jpg
    Mark Dowdall