Kuwait opens Al-Zour North 2 & 3 financial envelopes

6 May 2025

Kuwait's Ministry of Electricity, Water & Renewable Energy (MEWRE), through the Kuwait Authority for Partnership Projects (Kapp), has opened the financial envelopes submitted by the lone bidder for the contract to develop and operate the state's second independent water and power producer (IWPP) project.

Phases two and three of the the Al-Zour North project will have a power generation capacity of 2,700MW and a desalination capacity of 120 million imperial gallons a day (MIGD).

A utility developer team comprising Saudi Arabia's Acwa Power and the local Gulf Investment Company (GIC) submitted an annual equivalent payment (AEP) value, the yearly payment to the developer over the project's lifetime, Kapp announced on 5 May.

The procurement authority said it opened the financial envelopes in the presence of qualified investors that had previously obtained the project's proposal request.

Based on an uploaded picture on the Kapp website, the AEP value is about KD522.38m ($1.7bn).

The signing of the power and water purchase agreement by the Acwa Power team and MEWRE is expected to take place at a later date, according to an industry source.

The project company will sign a 25-year energy conversion and water purchase agreement with MEWRE starting from the project’s commercial operation date.

It is understood that Al-Zour North 2 & 3 will use liquefied natural gas and high-pressure natural gas, with gas oil as a backup fuel, and will connect to the national grid via a 400-kilovolt transmission substation.

Unlike in most GCC states, where bidders submit separate levelised electricity and water costs – expressed in $cents a kilowatt-hour and per cubic metre – for IWPP tenders, Kuwait has two bid evaluation parameters.

The AEP value is a combination of average power and water costs within a year, while the SHP, or equivalent share price, is the amount of equity divided by the number of shares.

Separate tariffs for the power and water desalination plants may have been submitted but will not likely be disclosed publicly, one of the sources said.

Located about 100 kilometres south of Kuwait City, the Al-Zour North 2 & 3 IWPP will be adjacent to the western border of the first Al-Zour North facility for electric power generation and water desalination, which is currently in operation, and on the northern border of the Al-Zour South station.

The project struggled to take off partly due to stakeholder indecision, with the government undergoing several changes and transitions in the past few years.

The plan to develop Kuwait's second IWPP was first announced in 2016-17, following the commissioning of its first IWPP, Al-Zour North 1, in late 2016.

Following a series of delays and scope changes, Kapp finally tendered the contract to develop the Al-Zour North 2 & 3 IWPP in March last year. The tender took place three years after Kapp had selected a team comprising three UK-headquartered firms – EY, Atkins and Addleshaw Goddard – as transaction advisers for this project, along with another planned IWPP in Al-Khiran, in April 2021.

First IWPP

Kuwait's erstwhile Partnerships Technical Bureau selected the winning consortium of UK/French company GDF Suez, now Engie; Japan's Sumitomo; and Kuwait's AH Sagar & Brothers Group as the preferred bidder for the Al-Zour North 1 IWPP in February 2012.

However, the project stalled when Kuwait's National Assembly voted to scrap the scheme in June that year.

According to MEED archives, the successful consortium submitted the lowest bid to build the project with an AEP value of KD127.1m ($453m) at the time.

The project company, Shamal Az-Zour Al-Oula, awarded South Korea’s Hyundai Heavy Industries and France’s Sidem the engineering, procurement and construction contract to build the plant.

The power generation plant is a combined-cycle power plant that utilises gas and steam turbines to produce up to 50% more electricity than a traditional simple-cycle plant.

It produces 1,539.2MW in net contracted power capacity from five General Electric GTG 9F-3 turbines generating 225.8MW each, and two General Electric STG D1 turbines generating 251MW each.

The integrated facility has a multiple-effect distillation unit capable of producing 107 MIGD, the equivalent of 486,400 cubic metres a day of desalinated water.

Shamal Az-Zour Al-Oula began trading shares on the Kuwait stock exchange in 2020, after Kapp distributed 50% of its total shares to individual Kuwaiti investors in the last quarter of 2019.

Several public and private entities own the remaining 50% of the company's shares. They are:

  • Azour North One Holding Company, owned by a consortium comprising Engie, Sumitomo Corporation and Abdullah Hama Al-Sagar & Brothers (40%);
  • Kuwait Investment Authority (5%); 
  • Public Institution for Social Security (5%).

Photo credit: Kapp

https://image.digitalinsightresearch.in/uploads/NewsArticle/13817267/main0307.jpg
Jennifer Aguinaldo
Related Articles
  • Dubai seeks consultants to develop drainage strategy

    18 March 2026

    Dubai Municipality has issued a request for qualifications (RFQ) for a study to develop a sustainable urban drainage systems (Suds) strategy across the emirate.

    The bid submission deadline is 9 April.

    The tender, issued through the Sewerage and Recycled Water Projects Department, covers the development of a strategy and conceptual implementation plan for Suds in Dubai.

    It follows a separate RFQ issued by the municipality in March for consultancy services to study the emirate’s sewage treatment strategy.

    The Suds project, designated TF-23-D1, aims to support the emirate’s flood protection and drainage infrastructure by promoting a more sustainable approach to stormwater management.

    The scope of work includes a review of international best practices in Suds and their applicability to Dubai. It also involves undertaking a Suds opportunity study and carrying out catchment-scale modelling and financial evaluation for a pilot study area.

    Consultants will be required to develop Suds design guidelines, specifications and standard drawings. The project also includes establishing a strategy, policy, legal and regulatory framework to support a Suds implementation roadmap.

    Dubai Municipality said the initiative represents “a significant step towards a more resilient, sustainable and forward-looking stormwater management approach for Dubai.”

    The study forms part of a broader review of Dubai’s water and wastewater infrastructure. Earlier this month, the municipality issued a separate consultancy tender (P115-D1) to assess the emirate’s sewage treatment and recycled water distribution strategy. 

    The study will focus on infrastructure requirements to support future population growth. 

    This includes identifying locations for potential future facilities such as treatment plants and pumping stations.

    The bid submission deadline is 23 March.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16027434/main.jpg
    Mark Dowdall
  • Oman awards power purchase agreements

    18 March 2026

    Oman’s Nama Power & Water Procurement Company (PWP) has issued letters of award (LoA) for new power purchase agreements (PPAs) to three independent power producers (IPPs), according to regulatory filings.

    The new PPAs will extend the operating life of existing gas-fired power plants beyond the expiry of their current contracts.

    The projects have a combined capacity of about 3,500MW.

    The agreements have been awarded to Phoenix Power Company, Al-Batinah Power Company and Al-Suwadi Power Company.

    Phoenix Power Company operates the 2,000MW Sur IPP.  It is owned by a consortium of international and regional investors, including Japan’s Marubeni Corporation and Chubu Electric Power, Qatar’s Nebras Power, Qatar Electricity & Water Company and Multitech of Oman’s Bahwan Engineering Company.

    Al-Batinah Power Company and Al-Suwadi Power Company operate the 750MW Sohar 2 IPP and the 750MW Barka 3 IPP, respectively.

    According to regional projects tracker MEED Projects, Nama PWP signed the original PPA for the Barka 3 project in 2010 with a consortium led by Gaz de France (GDF) Suez under a special purpose vehicle (SPC) called Al-Suwadi Power Company.

    The shareholders comprised GDF Suez (46%), Bahwan Engineering Company (22%), Shikoku Electric Power Corporation (11%), Sojitz Corporation (11%)  and the Public Authority for Social Insurance (10%).

    In 2015, GDF Suez was rebranded as Engie following a strategic shift towards low-carbon energy and utilities.

    All three companies said the new PPAs will run for 15 years under agreed commercial terms. Acceptance of the LOAs has been requested by 18 March 2026.

    The new agreements for Sohar 2 and Barka 3 will take effect on 1 April 2028 and run until 31 March 2043. The agreement for the Sur IPP will commence on 1 April 2029 and run until 31 March 2044.

    The awards form part of Nama PWP’s 2028-29 procurement programme. The programme aims to secure firm generation capacity from existing assets whose current PPAs are due to expire during that period.

    In Oman, IPP projects are developed under a build-own-operate model. This allows plant operators to continue running assets beyond the initial PPA term, either through contract extensions or by selling power into a future electricity market.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16027001/main.jpg
    Mark Dowdall
  • DP World awards Jafza warehouse construction deal

    18 March 2026

    Dubai-based ports operator DP World has awarded a contract to build a multi-tenant warehouse development at Jebel Ali Freezone in Dubai, UAE.

    The contract was awarded to local firm Group Amana.

    The development spans 141,916 square metres (sq m) and comprises 187 units across seven blocks.

    These comprise warehouses, light industrial units, a retail shop, a mosque and other associated infrastructure.

    The new contract builds on their existing partnership to deliver the logistics park at Jeddah Islamic Port in Saudi Arabia.

    In February last year, MEED exclusively reported that Dubai’s DP World and the Saudi Ports Authority (Mawani) had awarded a SR347m ($92m) design-and-build contract to Group Amana for the project.

    The scope of the contract covers construction work on the buildings under package two of the project’s first phase.

    Earlier this week, MEED reported that DP World has kept its 2026 capital expenditure budget at nearly $3bn, focusing on two domestic assets and four overseas projects.

    The company said in a statement that the priority developments include Jebel Ali and Drydocks World in Dubai.

    Earlier this month, the group announced record financial results for 2025, with revenue up 22% to $24.4bn and adjusted earnings before interest, taxes, depreciation and amortisation (Ebitda) up 18% to $6.4bn, delivering a 26.3% margin.

    DP World said this performance was driven by strong momentum across its ports and terminals and logistics business.

    The group’s gross throughput rose 5.8% to 93.4 million 20-foot equivalent units.

    Profit for the year increased 32.2% to $1.96bn, and operating cash flow grew 14% to $6.3bn.

    Return on capital employed increased to 9.9% in 2025, up from 8.9% in 2024, reflecting stronger earnings despite ongoing geopolitical and trade uncertainty.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16026660/main.png
    Yasir Iqbal
  • Egyptian firm starts building Sal’s Riyadh logistics centre

    18 March 2026

    Egyptian contractor Rowad Modern Engineering, a subsidiary of the Elsewedy Electric Group, has begun construction on the expansion of Saudi Logistics Services Company (Sal) facilities at King Khalid International airport in Riyadh.

    The scope of work includes the rehabilitation and upgrade of existing infrastructure, as well as the construction of new supporting facilities and services.

    Sal started the tendering process for its SR4.2bn ($1bn) logistics zone in the north of Riyadh in September last year, as MEED reported.

    UAE-based Global Engineering Consultants is the project consultant.

    The logistics hub aims to meet the demand for customised warehouses located near King Khalid International airport and the Riyadh Metro.

    The project is in line with Vision 2030 and the National Transport & Logistics Strategy, which aims to support the kingdom’s logistics sector and enhance Saudi Arabia’s position as a global logistics hub.

    Sal and Sela signed an agreement to develop the project in March last year.

    This was followed by another lease agreement for the project, which will span about 1.57 million square metres. 

    According to an official statement: “The lease will extend for 30 years, which is further extendable to an additional 15 years upon agreement of both parties.”

    GlobalData expects the kingdom’s construction industry to record an annual average growth rate of 5.2% in 2025-28, supported by investments in transport, electricity, housing and tourism infrastructure projects, as well as the $850bn-plus gigaprojects programme.

    Growth will also be supported by government investments in rail, dams, industrial and road infrastructure projects. 

    The industrial sector is estimated to grow by 3.3% in 2025-28, supported by investments in the development of manufacturing, logistics, chemicals and pharmaceuticals plants.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16026154/main.gif
    Yasir Iqbal
  • Jabal Omar plans next phase of its Mecca development

    18 March 2026

    Saudi Arabian developer Jabal Omar Development Company is carrying out planning for phase seven of its Jabal Omar master development in Mecca, according to a fourth-quarter 2025 financial presentation.

    The company said phase seven will be a mixed-use scheme comprising hotels, retail and residential components, but did not disclose a breakdown of the project elements.

    Jabal Omar plans to use a development partnership model for the phase to minimise capital expenditure.

    Separately, the developer said it is targeting the delivery of 1,346 hotel keys and more than 20,000 square metres of gross leasing area in phase four by 2027.

    Rotana Jabal Omar Makkah, comprising 655 keys, is due to be fully operational in the first quarter of 2026, after 450 keys began operating in the final week of December 2025.

    The 1,141-key Sofitel is scheduled to become operational in the fourth quarter of 2026, while the 20,000 square metres of gross leasable area is expected to be ready in 2027.

    Jabal Omar estimates its 2026 capital expenditure at SR1.1bn ($293m), with spending expected to fall once the phase four hotels are completed.