King Salman inaugurates Riyadh Metro

27 November 2024

Register for MEED's 14-day trial access 

King Salman Bin Abdulaziz Al-Saud inaugurated the Riyadh Metro on 27 November.

The network spans 176 kilometres across six lines and 85 stations. Four of the stations are iconic stations designed by signature architects.

The metro is part of the Riyadh Public Transport Project, which includes the metro and bus systems. The project aims to relieve traffic congestion. Currently, 90% of trips within the Saudi capital rely on cars.

The $23bn project was scheduled to open six years ago, in 2018, but construction activity on the project slowed in recent years due to disputes over prolongation and the disruption caused by the Covid-19 pandemic.

Arriyadh Development Authority, now the Royal Commission for Riyadh City (RCRC), awarded the main construction packages for the scheme on 28 July 2013.

Completion works

In November 2022, MEED reported that the three contracting consortiums working on the Riyadh Metro scheme had struck deals with the RCRC regarding the completion of the works.

The development was divided into five major design-and-build packages, with lines one and two as a combined package, and the other lines as single packages. Each package also includes the supply of rolling stock.

Spanish firm FCC heads up the consortium known as Fast, while US firm Bechtel leads the BACS consortium. Italian firm Ansaldo STS is the leader of the Arriyadh New Mobility group.

The Fast consortium won lines four, five and six, which are reported to be valued at $7.82bn. The BACS consortium picked up lines one and two for $9.45bn, while Arriyadh New Mobility secured line three for $5.21bn.

More lines

There are plans to expand the metro network. In September, MEED reported that the RCRC was preparing to award the contract for the Riyadh Metro Line 2 extension. 

The Line 2 extension is 8.4 kilometres (km), of which 1.3km is elevated and 7.1km is underground. It includes five stations – two elevated and three underground.

It will run from where Line 2 currently ends at King Saud University (KSU) and then travel onward to new stations, namely KSU Medical City, KSU West, Diriyah East, Diriyah Central (where it interchanges with the planned Line 7), and then finally to Diriyah South.

Also in September, the RCRC issued the request for proposal notice to selected firms to design and build Line 7 of the Riyadh Metro project.

The RCRC has given consortiums six months to prepare the bids. The submission deadline is 10 March 2025.

According to sources close to the project, the consortiums planning to bid for the project include:

  • Alstom (France) / FCC (Spain) / Freysinnet Contracting (local) / WeBuild (Italy) / Nesma (local) 
  • Siemens (Germany) / Samsung C+T (South Korea) / Acciona (Spain) / Alayuni (local)
  • Hitachi Rail (Japan) / OHLA (Spain) / Daewoo (South Korea) / Hyundai E&C (South Korea) / Almabani (local) / Albawani (local)
  • CRRC (China) / Mapa (Turkiye) / Limak (Turkiye)

Spanish consulting firms Typsa and Ayesa, along with US-based Aecom, are the design consultants for the Alstom-led consortium.

Spain-headquartered Idom, South Korea’s Dowha and Switzerland’s Pini are the designers for the Siemens-led team.

Spanish engineering firm Sener is the design consultant for the Hitachi Rail-led group.

The project involves constructing a metro line linking Qiddiya Entertainment City, King Abdullah International Gardens, King Salman Park, Misk City and Diriyah Gate. The total length of the line will be about 65km, of which 47km will be underground and 19km will be elevated.

The line will have 19 stations, 14 of which will be built underground and five overground. 

The consultants working on the scheme are France’s Egis and Lebanon-based Dar Al-Handasah, according to regional projects tracker MEED Projects.

In June 2020, a joint venture led by French consultancy Systra won the preliminary design contract for the second phase of Saudi Arabia’s Riyadh Metro.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13013642/main.png
Colin Foreman
Related Articles
  • Algeria tenders 310km Tamanrasset railway

    16 October 2026

     

    Algeria’s state railway project developer, Agence Nationale d’Etudes et de Suivi de la Realisation des Investissements Ferroviaires (Anesrif), has invited national and international contractors to bid for the construction of a 310-kilometre (km) railway line between Hotel Station and Moulay Lahcen Station. 

    The planned line is a key segment of the proposed railway corridor connecting El-Menea, In-Salah and Tamanrasset across the southern wilayas of In-Salah and Tamanrasset.

    The tender notice was issued on 12 October, with bids due by 10 November.

    The tender is open to single contractors and consortiums. To qualify, single firms must have executed at least 200km of new railway lines or track-doubling works since 2010, with accepted project certificates covering sections of at least 100km, along with a cumulative 800 metres of railway bridges with individual spans exceeding 30 metres.

    Bidders must also provide at least two rail-tamping machines, two ballast regulators, and a project director with an engineering degree and at least five years of railway construction management experience.

    From a commercial and classification perspective, single bidders and consortium leaders must hold a category-nine (IX) professional qualification in public works.

    Bidders must also demonstrate an average annual turnover in construction of at least DZ260bn ($1.96bn) across the 2023-2025 financial period.

    For joint ventures, the cumulative turnover of all members must meet the $1.96bn threshold, with the consortium leader accounting for at least $1.3bn.

    Offers must be accompanied by a bid bond exceeding 1% of the total bid value for submissions exceeding $7.4m, with proposals remaining valid for 90 days beyond the submission date.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20665591/main.jpg
    Yasir Iqbal
  • Joint venture wins $246m RCRC bridges contract

    16 October 2026

     

    A joint venture of local contractor Mofarreh Group and Turkey-based Gulsan Holding has won an estimated SR923m ($246m) contract from the Royal Commission for Riyadh City (RCRC) to construct a series of grade-separated steel flyovers across the capital.

    The contract, known as Package 2 (Groups 2 and 3), is part of RCRC’s urgent bridges programme under the wider project to build steel bridges at 10 junctions across Riyadh.

    The works have a 12-month execution timeline to fast-track traffic decongestion across major arterial corridors.

    The joint venture’s scope covers the engineering and construction of grade-separated steel bridge interchanges across seven key intersections:

    • IC04: Al-Khair Road and King Salman Bin Abdulaziz Road
    • IC05: Prince Turki Road and Imam Saud Road
    • IC06: Al-Takhassosi Road and Saeed Al-Sulami Road
    • IC07: Khurais Road and Al-Hareth Bin Abdullah Road
    • IC08: Khurais Road and Ash-Sharq Road
    • IC09: Khurais Road and Marmar Road
    • IC10: Al-Kharj Road and Al-Hilla Road

    The total length of the flyovers is 8.86 kilometres, excluding Junction IC10.

    In addition to the structural steel superstructures, concrete bridge foundations, decks and approach ramps, the contract includes retaining walls, utility diversions, temporary phased traffic arrangements, associated roadworks, drainage networks, roadway lighting, intelligent transportation systems and landscaping.

    The client received commercial proposals from several local and international contractors. Other bidders included:

    • Masco
    • Nesma & Partners
    • Al-Omaier Trading & Contracting Company 
    • Yuksel Saudia 
    • Batco 
    • Modern Building Leaders
    • Sapac

    The urgent bridges initiative is part of Riyadh’s rapid transport infrastructure programme to improve traffic throughput, enhance safety and ease vehicular congestion across central and ring-road corridors ahead of major events, including Expo 2030 and the 2034 Fifa World Cup.

    In July, Mofarreh Group and Turkiye’s Gulsan Holding formed a joint venture to bid for and deliver transport infrastructure projects in Riyadh for RCRC.

    The joint venture said it will target road, bridge, viaduct and interchange projects.

    Mofarreh will provide local market access and operational capacity, while Gulsan will contribute international experience in large-scale transport projects.

    The companies said the new venture will support knowledge transfer and localisation, and promote the use of international engineering and construction standards aligned with Saudi Arabia’s Vision 2030 infrastructure and sustainability goals.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20663255/main.png
    Yasir Iqbal
  • Humain tenders 100MW Riyadh AI data centre

    16 October 2026

     

    Register for MEED’s 14-day trial access 

    Saudi artificial intelligence infrastructure developer Humain has issued a request for proposals for an engineering, procurement and construction (EPC) contract to deliver a 100MW artificial intelligence (AI) data centre facility in Riyadh’s Al-Saad area.

    The tender was issued on 17 September, with bids due by 8 November.

    The contract includes core-and-shell works; civil works; mechanical, electrical and plumbing installation; testing and commissioning; and site infrastructure across a 350,200-square-metre plot.

    The project also includes an optional expansion phase that could raise total site capacity to 200MW.

    The initial 100MW development is split into two equal 50MW phases, structured across two single-storey IT buildings housing four 25MW data halls.

    Phase one targets a ready-for-service date by October 2028, followed by phase two in January 2029.

    Under the optional phase three, an additional 100MW facility would be brought online by July 2029.

    The data centre will be designed to support high-density graphics processing unit clusters and AI-compute workloads, with rack densities of 240kW to 250kW.

    The facility will be built to Uptime Institute Tier III topology and LEED Silver standards as a baseline, targeting LEED Gold.

    The operational design targets an annualised power usage effectiveness below 1.35.

    Power will be delivered through four 33kV connections supplied by Saudi Electricity Company from two separate high-voltage/medium-voltage primary substations. The scope requires 15 transformers, 15 static 2,250kW IT uninterruptible power supply (UPS) units, and 450kW mechanical UPS systems with lithium-ion battery storage for each 25MW block. 

    Backup emergency diesel generators will be provided on an owner-furnished, contractor-installed basis, with the EPC contractor handling their installation, connection and testing. Fuel storage will provide 24 hours of autonomous run-time, split between on-site underground bulk tanks and generator belly tanks.

    Thermal management combines air and liquid cooling. High-density server racks will be equipped with direct-to-chip liquid cooling loops using coolant distribution units and technical water distribution, paired with air-cooled chillers operating in dual high- and low-temperature loops, alongside fan-wall units.

    The total construction timeline is capped at 25 months from site handover or contract signing, with pre-execution early mobilisation scheduled to start in January 2027.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20661045/main.jpg
    Yasir Iqbal
  • Adnoc Onshore seeks bids for Bu Hasa field EOR project

    16 October 2026

     

    Register for MEED’s 14-day trial access 

    The onshore oil and gas business of Abu Dhabi National Oil Company (Adnoc Onshore) has sought bids from contractors for a key project to increase the oil production capacity of the Bu Hasa oil field, primarily through enhanced oil recovery (EOR) techniques.

    The main objective of the Bu Hasa-Shuaiba EOR Unit 1 (Phase 1) project is to achieve a targeted 70% increase in oil production, extend the Bu Hasa field development’s production plateau and maximise the field’s potential in an economical manner.

    The project aims to confirm and validate the optimum EOR technology for the top-ranked reservoirs/units; assess incremental recovery on top of the improved oil recovery (IOR) wedge; extend the field plateau for as long as is economically feasible; and achieve an ultimate recovery factor of 70% from the Shuaiba reservoir. It will evaluate and execute the recommended EOR option through pattern phasing for any technology proven by Adnoc.

    Adnoc Onshore is understood to have issued the tender for the project on 20 September, with an initial technical bid submission deadline of 8 October, according to sources. The client later extended the technical bid submission deadline to 17 October, sources told MEED.

    The chosen contractor will execute the project under a hybrid contracting strategy comprising:

    • A lump sum (turnkey) EPC scope covering the complete pipeline system from East Hub to the separation plant
    • A call-out-based scope for execution of all WAG injector and WSW tie-in works

    Unless otherwise specified, all activities defined under the contractor’s scope will be deemed included within the lump-sum contract price. This will cover engineering, procurement, construction, testing, pre-commissioning and support to commissioning for a complete and operable system.

    At the Bu Hasa field development, three remote degassing stations (RDS-1/2/3) and two satellite stations, Bida Al-Qemzan and Huwaila, are currently in operation. Production from oil wells completed in Shuaiba, Thamama B, Thamama F, Bida Al-Qemzan and Huwaila is routed via individual flowlines to the three remote degassing stations and the Bida Al-Qemzan and Huwaila stations across different parts of the field.

    Combined production from the wells at each of these stations is routed to the central degassing stations (CDS) via transfer lines ranging from 16 inches to 24 inches in diameter. In addition, some wells in the central part of the field are connected directly to the CDS.

    Previous studies have identified carbon dioxide (CO2) flooding as a promising tertiary recovery mechanism in the Shuaiba reservoir, delivering incremental recovery on top of the IOR wedge (P5 project), extending the field plateau as long as economically feasible, and achieving an ultimate recovery factor of 70% from the Bu Hasa Shuaiba units.

    Located 200 kilometres south of Abu Dhabi city, Bu Hasa is Adnoc Onshore’s westernmost producing field. It is one of Abu Dhabi's biggest onshore assets, with crude oil production capacity of 650,000 b/d. It is also one of the Adnoc Group’s oldest oil fields, having been discovered in 1962 and in production since May 1965.

    As part of the ongoing Bu Hasa Integrated Field Development Project (BUIFDP), 13 new well pads and two pad hubs have been added to the field. Oil, gas and water produced at these sites will be collected at a central gathering facility, then sent through production headers and transfer lines to the CDS for processing.

    Adnoc Onshore is the Adnoc Group’s largest oil-producing subsidiary, accounting for 2 million b/d of oil and about 7 billion cubic feet a day of associated gas production from four main onshore field developments in Abu Dhabi: Bab, Bu Hasa, North East Bab and South East.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20639750/main0548.jpg
    Indrajit Sen
  • OTTCO issues tender for Oman oil storage park expansion

    16 October 2026

     

    Register for MEED’s 14-day trial access 

    Oman Tank Terminal Company (OTTCO) has issued the main tender for a major project related to the expansion of the Ras Markaz crude oil storage complex at Duqm, on the sultanate’s Arabian Sea coast.

    The project, titled Trade Bridge, involves the engineering, procurement and construction (EPC) of eight large storage tanks, each with a capacity of 650,000 barrels. This will increase the Ras Markaz terminal’s total storage capacity by 5.2 million barrels.

    The project represents the next expansion phase (phase 1.4) of the Ras Markaz oil storage terminal within the Special Economic Zone at Duqm (Sezad).

    State-owned OTTCO issued the prequalification notice for the project on 28 July, with contractors submitting initial responses by 4 August and final responses by 19 August, MEED previously reported.

    According to sources, OTTCO issued the main tender for EPC works on Project Trade Bridge in the weeks following completion of the prequalification exercise.

    The following contractors, among others, are understood to have been prequalified by OTTCO to bid for Project Trade Bridge:

    • China Petroleum Pipeline Engineering Company (China)
    • China Tianchen Engineering Corporation (China)
    • Daqing Oilfield Construction Group Company (China)
    • Enppi Muscat (local branch of Egypt-based Enppi)
    • Gulf Petrochemical Services & Trading (Oman)
    • Hualu Engineering & Technology Company (China)
    • Rotary Engineering (Singapore)
    • Sinopec Ningbo Engineering Company (China)

    OTTCO commissioned the first phase of the Ras Markaz crude oil storage park, covering 10 square kilometres and with a capacity of 26.7 million barrels, in December 2022.

    The storage facility has two parts. The first is a marine services area, which includes a floating station for crude imports and exports. This zone is about 7 kilometres offshore and is connected via two 42-inch pipelines and associated facilities.

    In water depths of up to 42 metres, the floating station can accommodate very large crude carriers. It is linked to four main pumps that transfer crude oil to the storage area, which is located more than 120 metres above sea level. OTTCO could add pumps at a later stage to keep pace with future demand for oil storage.

    The second part of the storage facility features oil pumping systems, water treatment facilities, reservoirs, power station networks and other associated systems.

    Region’s largest oil storage park

    OTTCO will build the Ras Markaz oil storage facility in five phases over several years across an area of about 40 square kilometres, for which it signed a land agreement with Sezad in July 2017.

    It will be able to hold 200 million barrels of crude a year. Total investment in the scheme is understood to be $5.2bn.

    The storage terminal in the first phase of the Ras Markaz facility is connected to the estimated $7bn Duqm refinery and other oil-derivatives production plants at Sezad via a pipeline that will supply crude feedstock to the refinery when required.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20638090/main0749.jpg
    Indrajit Sen