Jordan water project enters critical phase
11 January 2024
Commentary
Jennifer Aguinaldo
Energy & technology editor
Jordan’s national water carrier programme, previously known as the Aqaba-Amman water desalination and conveyance project, achieved a major milestone in December when a developer consortium submitted a bid to develop the project.
It is a much-anticipated water infrastructure project to alleviate the kingdom’s gaping water scarcity issue.
Jordan has only 97 cubic metres of water available per capita annually, less than one-fifth of the absolute water scarcity threshold of 500 cu m/capita a year, according to the World Bank.
The project has so far received pledges in the form of loans and grants from financial institutions such as the European Investment Bank, the EU and the World Bank’s International Finance Corporation.
These total roughly $730m in loans and $107m in grants, far smaller than the total investment the project requires.
Notably, in 2022, the heads of Jordan’s Planning Ministry and Water Ministry confirmed that the pledges and commitments at the time reached a total of $2.2bn, although a breakdown was not published.
A source close to the project says there are no legal obstacles to awarding the contract to the single bidder, “provided the client finds the price acceptable”.
The bidding team comprises Paris-headquartered Meridiam, a shareholder in Suez, Vinci, also of France, and Egypt’s Orascom.
The proposed levelised water cost for the project has not been disclosed.
Some prequalified bidders have told MEED they did not bid for the contract due to potential challenges in obtaining financing for the project, which is estimated to cost between $2bn and $3.5bn depending on its final configuration.
The build-operate-transfer project is Jordan’s single largest planned infrastructure scheme to date. It will pipe water from the southern coast to the country’s northern regions.
The desalination component of the project will have the capacity to treat 835,000 cubic metres a day (cm/d) of water, of which 250,000 cm/d to 300,000 cm/d are expected to be transported to the capital Amman.
The conveyance segment of the project includes the construction of a seawater intake pump station, reservoir, pipeline, booster pump stations and freshwater collection pipes.
The project is expected to use clean energy in line with the government’s commitment to reduce greenhouse gas emissions.
An estimated 1.6 million people, roughly a 10th of the kingdom’s population, are expected to benefit from improved water services through the project.
It is not the only project planned to alleviate Jordan’s worsening water woes, which result from population growth, the influx of refugees, and leaking, ageing pipes.
In June, the World Bank approved a $250m financing to improve and rehabilitate Jordan’s water distribution network. An estimated 50 per cent of Jordan’s municipal water is considered non-revenue water (NRW), meaning it either leaks from pipes or is not paid for by the consumer.
Water levels in the country’s 14 major dams are also understood to sit at about 43 million cubic metres – roughly a 10th of their total capacity of 336.4 million cubic metres.
Jordan’s treaty with Syria to import water has fallen through, with Syria rejecting the latest request to import 30 million cubic metres of water.
Its only other water source is Israel, with whom it signed a peace treaty in 1994. Under this deal, Israel agreed to provide Jordan with 55 million cubic metres of water a year. In 2021, Israel agreed to supply Jordan with an additional 50 million cubic metres of water outside the framework of the 1994 treaty.
In late 2022, Jordan and Israel signed a water-for-energy deal brokered by the UAE and US. Under the plan, Jordan will build a 600MW solar power plant and export the capacity to Israel. In return, Israel will provide Jordan with 200 million cubic metres of desalinated water.
The project appeared to be advancing in 2023 before the Israel/Hamas conflict began on 7 October.
Jordan said in November that it would not sign the deal, which leaves Jordan’s water problem unsolved until the water national carrier project is completed – assuming it is successfully awarded, financed and developed – in three or four years’ time.
Exclusive from Meed
-
Meraas confirms $517m The Acres villas contract award26 November 2025
-
December deadline for Riyadh airport fourth runway26 November 2025
-
Chinese contractor appointed for Algerian refinery project26 November 2025
-
Egypt seeks to accelerate progress on chemicals facility26 November 2025
-
Bahrain extends deadline for Hawar Island water station25 November 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Meraas confirms $517m The Acres villas contract award26 November 2025
Dubai-based real estate developer Meraas, now part of Dubai Holding Group, has confirmed that it has awarded a AED1.9bn ($517m) contract to build 642 three-, four- and five-bedroom villas as part of the first phase of its residential community, The Acres, in Dubailand.
The contract was awarded to the local firm United Engineering Construction Company.
MEED exclusively reported in August that Meraas had awarded the contract for the project.
The Acres project is designed by local architectural practice U+A Architects.
The masterplan includes 1,200 villas ranging from three to seven bedrooms.
It also features a nursery, school, clinic, mosques, clubhouses, a retail zone, a 2,000-square-metre garden, walking and biking trails, an outdoor gym, children’s playgrounds, swimming pools and sports facilities.
The latest announcement follows Meraas awarding a AED440m ($120m) contract for the construction of the Northline residential project in the Al-Wasl area of Dubai.
The contract was awarded to the local GCC Contracting Company.
The project includes the construction of three residential buildings. Construction work is expected to begin shortly, and the project is slated for completion by 2027.
Meraas’ latest project contract awards in Dubai are backed by heightened real estate activity in the UAE’s construction market. Schemes worth over $323bn are in the execution or planning stages, according to UK analytics firm GlobalData.
The company forecasts that the output of the UAE’s construction sector will grow by 4.2% in real terms in 2025, supported by developments in infrastructure, energy and utilities, as well as residential construction projects.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15158561/main.jpg -
December deadline for Riyadh airport fourth runway26 November 2025

King Salman International Airport Development Company (KSIADC) has allowed firms until 3 December to bid for the design-and-build contract for the fourth runway at King Salman International airport (KSIA) in Riyadh.
The tender was first floated on 17 April. The previous bid submission deadline was 28 October.
It is understood that the third and fourth runways will add to the two existing runways at Riyadh’s King Khalid International airport, which will eventually become part of KSIA.
KSIADC, which is backed by Saudi Arabia’s Public Investment Fund, prequalified firms in September last year for the main engineering, procurement and construction packages; early and enabling works; specialist systems and integration; specialist systems, materials and equipment; engineering and design; professional services; health, safety, security, environment and wellbeing services; modular installation and prefabrication; local content; and environmental, social, governance and other services.
The entire scheme is divided into eight assets. These are:
- Iconic Terminal
- Terminal 6
- Private aviation terminal
- Central runway and temporary apron
- Hangars
- Landside transport
- Cargo buildings
- Real estate
In August last year, KSIADC confirmed it had signed up several architectural and design firms for the various elements of the project.
US-based firm Bechtel Corporation will manage the delivery of three new terminals, including the terminal for commercial carriers, Terminal 6 for low-cost carriers and a new private aviation terminal with hangars.
Parsons, also of the US, was chosen as the delivery partner for two packages. One covers the airside infrastructure, including the runways, taxiways, air traffic control towers, fuel farms and fire stations. The other involves the infrastructure connecting the airport to the rest of the city, including utilities and roads.
UK-based Foster+Partners will design the airport’s masterplan, including the terminals, six runways and a multi-asset real estate area.
US-based engineering firm Jacobs will provide specialist consultancy services for the masterplan and the design of the new runways.
UK-based engineering firm Mace was appointed as the project’s delivery partner and local firm Nera was awarded the airspace design consultancy contract.
Project scale
The project covers an area of about 57 square kilometres (sq km), allowing for six parallel runways, and will include the existing terminals at King Khalid International airport. It will also include 12 sq km of airport support facilities, residential and recreational facilities, retail outlets and other logistics real estate.
If the project is completed on time in 2030, it will become the world’s largest operating airport in terms of passenger capacity, according to UK analytics firm GlobalData.
The airport aims to accommodate up to 120 million passengers by 2030 and 185 million by 2050. The goal for cargo is to process 3.5 million tonnes a year by 2050.
Saudi Arabia plans to invest $100bn in its aviation sector. Riyadh’s Saudi Aviation Strategy, announced by the General Authority of Civil Aviation (Gaca), aims to triple Saudi Arabia’s annual passenger traffic to 330 million travellers by 2030.
It also aims to increase air cargo traffic to 4.5 million tonnes and raise the country’s total air connections to more than 250 destinations.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15158546/main.jpg -
Chinese contractor appointed for Algerian refinery project26 November 2025
China’s Sinopec Guangzhou Engineering Company has signed a contract for the construction of a heavy naphtha catalytic processing unit at the Arzew refinery in Algeria.
The contract was signed with the Algerian national oil and gas company Sonatrach.
The contract uses the engineering, procurement, construction and operation model.
Under the terms of the contract, Sinopec Guangzhou Engineering Company will handle the entire project lifecycle, from initial design to long-term management and operation.
The project will be completed over 30 months, according to a statement from the Algerian Ministry of Hydrocarbons & Mines.
The unit will have an annual capacity of 738,000 tonnes of heavy naphtha and will enable the refinery to increase gasoline production from 550,000 tonnes to 1.2 million tonnes a year.
Algeria’s Ministry of Hydrocarbons & Mines said this represented “a significant step” that will strengthen the national capacity for gasoline production and help meet demand across various regions, particularly in the west and southwest of the country.
Sinopec Guangzhou Engineering Company is a subsidiary of China Petroleum & Chemical Corporation (Sinopec), which is listed on stock exchanges in Hong Kong, Shanghai and New York.
The project is part of Sonatrach’s wider programme to modernise and expand national refining capacities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15157814/main.jpg -
Egypt seeks to accelerate progress on chemicals facility26 November 2025
Egypt’s government is attempting to accelerate progress on the country’s $680m project to develop a new soda ash production facility.
The country’s cabinet has granted state-owned Egyptian Soda Ash Company a so-called “golden licence” to develop the plant, which will also produce derivatives of soda ash.
The golden licence is a single approval given by the cabinet that consolidates multiple permits into one, in an effort to speed up project progress.
The golden licence includes permits relating to land allocation, construction, operation and management of the project.
In February this year, China National Chemical Corporation was appointed as the main contractor for the project.
The plant is set to produce 600,000 tonnes of soda ash and derivatives annually, making it one of the largest industrial projects of its kind in the region.
The project is being developed on a 1.12 million-square-metre plot in the industrial zone of New Alamein City.
It will create 600 direct jobs and 2,000 indirect jobs, according to a statement from the cabinet.
The factory is expected to be completed by mid-2027, with an investment cost exceeding $680m.
Soda ash is a basic, alkaline industrial chemical used in large volumes worldwide.
The project aims to meet local market demand for soda ash and to expand related industries, such as glass, detergents, paper, metals and pharmaceuticals.
The local component of production inputs will be no less than 50% per tonne of the finished product, in terms of both value and quantity.
Egyptian Soda Ash Company is a subsidiary of Egyptian Petrochemicals Holding Company (Echem), which was established in 2002 to develop, manage and expand the North African country’s petrochemicals sector.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15157812/main.jpg -
Bahrain extends deadline for Hawar Island water station25 November 2025
Bahrain’s Electricity & Water Authority (Ewa) has extended the bid submission deadline for the main contract to build a new water distribution station on Hawar Island.
The deadline, initially set for 23 November, has been moved to 7 December.
The $15m project covers the construction of two steel ground storage tanks with a capacity of one million gallons each, pumping stations, motors, pipelines and associated facilities.
The scheme forms a key part of Bahrain’s wider plans to develop Hawar Island, which currently has limited utility infrastructure and relies on water transported from the mainland.
The government is advancing tourism-led investment on the island, including eco-resorts and hospitality developments that require reliable potable water supplies.
The tender is linked to Ewa’s ongoing procurement for a new seawater reverse osmosis (SWRO) desalination plant on Hawar.
The engineering, procurement and construction contract for the SWRO facility, designed to produce one million imperial gallons a day, is currently out to tender, with bids due on 30 November.
According to Ewa, the desalination plant will connect with two related contracts.
One of these covers the construction of the new water distribution station, while the second covers offshore seawater intake and outfall systems.
The main desalination contractor will be required to ensure its design and construction align with these works so that all three components function together as one integrated system.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15149229/main.jpg