Jordan water project enters critical phase

11 January 2024

Commentary
Jennifer Aguinaldo
Energy & technology editor

Jordan’s national water carrier programme, previously known as the Aqaba-Amman water desalination and conveyance project, achieved a major milestone in December when a developer consortium submitted a bid to develop the project.

It is a much-anticipated water infrastructure project to alleviate the kingdom’s gaping water scarcity issue.

Jordan has only 97 cubic metres of water available per capita annually, less than one-fifth of the absolute water scarcity threshold of 500 cu m/capita a year, according to the World Bank.

The project has so far received pledges in the form of loans and grants from financial institutions such as the European Investment Bank, the EU and the World Bank’s International Finance Corporation.

These total roughly $730m in loans and $107m in grants, far smaller than the total investment the project requires.

Notably, in 2022, the heads of Jordan’s Planning Ministry and Water Ministry confirmed that the pledges and commitments at the time reached a total of $2.2bn, although a breakdown was not published.

A source close to the project says there are no legal obstacles to awarding the contract to the single bidder, “provided the client finds the price acceptable”.

The bidding team comprises Paris-headquartered Meridiam, a shareholder in Suez, Vinci, also of France, and Egypt’s Orascom.

The proposed levelised water cost for the project has not been disclosed.

Some prequalified bidders have told MEED they did not bid for the contract due to potential challenges in obtaining financing for the project, which is estimated to cost between $2bn and $3.5bn depending on its final configuration.

The build-operate-transfer project is Jordan’s single largest planned infrastructure scheme to date. It will pipe water from the southern coast to the country’s northern regions.

The desalination component of the project will have the capacity to treat 835,000 cubic metres a day (cm/d) of water, of which 250,000 cm/d to 300,000 cm/d are expected to be transported to the capital Amman.

The conveyance segment of the project includes the construction of a seawater intake pump station, reservoir, pipeline, booster pump stations and freshwater collection pipes.

The project is expected to use clean energy in line with the government’s commitment to reduce greenhouse gas emissions.

An estimated 1.6 million people, roughly a 10th of the kingdom’s population, are expected to benefit from improved water services through the project. 

It is not the only project planned to alleviate Jordan’s worsening water woes, which result from population growth, the influx of refugees, and leaking, ageing pipes.

In June, the World Bank approved a $250m financing to improve and rehabilitate Jordan’s water distribution network. An estimated 50 per cent of Jordan’s municipal water is considered non-revenue water (NRW), meaning it either leaks from pipes or is not paid for by the consumer.

Water levels in the country’s 14 major dams are also understood to sit at about 43 million cubic metres – roughly a 10th of their total capacity of 336.4 million cubic metres.

Jordan’s treaty with Syria to import water has fallen through, with Syria rejecting the latest request to import 30 million cubic metres of water.

Its only other water source is Israel, with whom it signed a peace treaty in 1994. Under this deal, Israel agreed to provide Jordan with 55 million cubic metres of water a year. In 2021, Israel agreed to supply Jordan with an additional 50 million cubic metres of water outside the framework of the 1994 treaty.

In late 2022, Jordan and Israel signed a water-for-energy deal brokered by the UAE and US. Under the plan, Jordan will build a 600MW solar power plant and export the capacity to Israel. In return, Israel will provide Jordan with 200 million cubic metres of desalinated water.

The project appeared to be advancing in 2023 before the Israel/Hamas conflict began on 7 October.  

Jordan said in November that it would not sign the deal, which leaves Jordan’s water problem unsolved until the water national carrier project is completed – assuming it is successfully awarded, financed and developed – in three or four years’ time. 

https://image.digitalinsightresearch.in/uploads/NewsArticle/11429011/main.jpg
Jennifer Aguinaldo
Related Articles
  • Aramco Stadium races towards completion

    12 November 2025

     

    The Aramco Stadium in Khobar is moving forward at an impressive pace as the fast-track project races towards completion in 2026

    The 47,000-seat stadium will be the new home for the Aramco-owned Al-Qadsiah Club and a key venue for the 2027 AFC Asian Cup and the 2034 Fifa World Cup. 

    The project’s progress stems from detailed planning and an accelerated delivery strategy. The project was conceived in May 2023, with the design process, managed by Aramco, commencing shortly thereafter. 

    “We completed the design within six months,” said Mohammed Subhi, the Aramco Stadium’s project manager.


    The project advanced quickly due to thorough planning and a fast-track delivery approach. Initiated in May 2023, the design phase—overseen by Aramco—was completed within six months


    An early engagement approach with the main contractor – a joint venture of Besix and Al-Bawani – was instrumental in maintaining momentum. This partnership began early in 2024, allowing for collaborative input on critical construction elements. 

    This upfront collaboration minimised pre-construction time, ensuring a rapid transition to site work.

    Engineering challenges

    The stadium’s architectural design, inspired by the natural whirlpools of the Gulf and featuring interwoven transparent sails, presents significant engineering challenges, particularly in the structural steel and façade work. For spectator comfort, the stadium is equipped with full cooling systems and designed to the highest international standards.

    Logistics management is another crucial facet of the project, which is located in central Khobar. With thousands of workers on site, the movement of materials is tightly controlled to minimise community disruption. 

    “We control how many trucks can enter the site and at what time. For example, we cannot cast concrete during the day. It has to be after 6pm, up until the early morning,” said Subhi.

    A key priority on site is health and safety, an area where the organisation’s legacy from its oil and gas operations is clearly visible. Subhi explains that the principle of health and safety is part of the company’s DNA and is embodied in the deployment of advanced technology and rigorous standards, which have collectively resulted in over 10 million safe working hours to date.

    The project employs a sophisticated Smart Safety Command Centre (SCC), which utilises artificial intelligence-based monitoring and 24/7 surveillance. One key feature of the centre is the crane collision prevention system – a key technological advancement in heavy machinery coordination and a first for the region. 

    “We have tower cranes and crawler cranes talking to each other. The anti-collision system means cranes talk to each other without human interference, and they automatically shut down when they are too close to each other,” said Subhi.


    A key technological advancement is the crane collision prevention system, which means the cranes talk to each other and shut down if they become too close


    In addition to ground operations, the project is leveraging aerial technology to mitigate risk in high-altitude work.

    “We have used drones for the inspection of the cranes and inspection of the steel structure itself to minimise the risk of working at height,” said Subhi.


    Drones have been adopted on-site to mitigate the risk of working at height


    Worker welfare

    The project’s commitment extends beyond mere regulatory compliance to comprehensive worker welfare, establishing a high standard for construction sites in the region. 

    With current staffing reaching approximately 11,000 direct and indirect workers, welfare provisions are a core priority, linking directly back to Aramco’s corporate standards.

    In a region where extreme heat is a constant challenge, the project has implemented advanced heat stress management protocols. This includes the installation of heat sensors with alarm systems, mandatory work stoppage during peak heat hours and regular briefings on heat exhaustion symptoms. Fully air-conditioned rest areas are provided for breaks and meals.

    Aramco is also committed to developing national talent. A significant proportion of the staff are young, and about 20% of the team are women.

    The relationship with the joint-venture contractor is defined by collaboration rather than traditional client-contractor hierarchy. “We are one team, working together,” said Subhi. This approach has fostered a cooperative environment that is accelerating the on-site progress towards the 2026 completion goal. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15073939/main.gif
    Colin Foreman
  • Oman signs PPA for 125MW Dhofar 2 wind project

    12 November 2025

    Singapore's Sembcorp Utilities and local firm OQ Alternative Energy (OQAE) have won a contract to develop the 125MW Dhofar 2 wind independent power project in Oman.

    The contract was awarded by state offtaker Nama Power & Water Procurement Company (Nama PWP) under a 20-year power purchase agreement (PPA).

    Under the PPA, Sembcorp and OQAE will form a joint venture to build, own and operate the wind farm, which will supply power to Nama PWP once operational.

    The equity split will give Sembcorp 75% and OQAE 25%, a source close to the project told MEED.

    Nama PWP said that it will allocate a portion of contracted works for the Dhofar 2 project to Omani small and medium-sized enterprises under its in-country value programme.

    The project is expected to begin commercial operations in the third quarter of 2027.

    The facility, valued at about OR43m ($112m), will be located on a 12-square-kilometre site in Dhofar Governorate.

    The project comprises 20 Windey WD200 turbines, each with a 6.25MW capacity. Each turbine stands 215 metres tall and will be connected to the national grid via a 400kV substation.

    The development will provide clean electricity to more than 18,000 homes and will cut carbon dioxide emissions by about 158,000 tonnes a year.

    It is also expected to generate about 396,754 megawatt-hours and free up around 76 million cubic metres of natural gas annually.

    Sembcorp has over 1.1GW of energy assets in Oman. In September, the firm signed a new 10-year power and water purchase agreement with Nama PWP for its Salalah independent water and power plant.

    According to Nama PWP, the offtaker has contracted 26 water and desalination plants, exceeding $11bn in investment, over the past 15 years.

    Chief energy transition officer at Nama PWP, Abdullah Bin Rashid Al-Sawafi, said the company "plans to attract a further $5bn over the next five years, mainly in renewable energy and storage technologies".

    This includes an extra 9GW of renewable energy capacity by 2030, representing 60% of total contracted capacity.

    Oman aims to have 30% of its electricity generation from renewable sources by the same year.


    READ THE NOVEMBER 2025 MEED BUSINESS REVIEW – click here to view PDF

    Mena players up the ante in global LNG production race; Investment takes UAE non-oil economy from strength to strength; Project finance activity draws international lenders back to market

    Distributed to senior decision-makers in the region and around the world, the November 2025 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15073043/main.jpg
    Mark Dowdall
  • Hitachi wins Alexandria Raml tram systems deal

    12 November 2025

    Register for MEED’s 14-day trial access 

    Hitachi Rail has announced that it has won a contract related to the modernisation and upgrade of the Alexandria Raml tram network in Egypt.

    Hitachi Rail said it will deliver advanced signalling and communications systems, an operational control centre and supervisory control and data acquisition, security systems with CCTV cameras and access control, passenger information and on-board equipment.

    The contract was awarded by a joint venture of Hassan Allam and Arab Contractors.

    The project scope includes rehabilitating a 13.2-kilometre tram line, constructing a maintenance depot, developing elevated viaducts and upgrading 24 stations.

    The project will reduce journey times from 60 to 35 minutes by increasing the operational speed on the line from 11 kilometres an hour (km/h) to 21km/h. The project will also increase the hourly capacity from 4,700 to 13,800 passengers in each direction. 

    UK analytics firm GlobalData expects the Egyptian construction industry to grow by 6.5% in real terms in 2025, supported by investments in oil and gas, industrial and housing construction projects. According to the Central Bank of Egypt, the country’s average construction production index grew by 5.8% year-on-year in the first 10 months of 2024.

    GlobalData says the construction industry's output is expected to register an annual average growth rate of 8% in 2026-29, supported by investments in commercial, renewable energy and transport infrastructure projects, coupled with the government’s target of developing 10GW of renewable energy projects by 2028 under the Nexus of Water, Food and Energy Programme.

    The infrastructure construction sector is expected to expand by 4.4% in real terms in 2025 and record an annual average growth rate of 7% in 2026-29, supported by government plans to continue its spending on transport infrastructure, ports and terminals.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15073050/main.jpg
    Yasir Iqbal
  • Contract award nears for Al-Ula tram works

    12 November 2025

     

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s Royal Commission for Al-Ula (RCU) is preparing to award the contract to build infrastructure for the tramway at the Al-Ula development.

    MEED understands that bid evaluation has reached advanced stages and the contract award is imminent.

    Contractors submitted revised bids for the scheme in August, as MEED reported.

    It is understood that consortiums were asked to propose self-funded financing arrangements for the project.

    The first phase of the tram scheme is a 22.4-kilometre-long line with 17 stations, operated by 20 trams. It will link Al-Ula International airport to five of the area’s historical regions.

    The scope of work includes the design and construction of a tram depot, tram tracks, technical buildings, station buildings and other associated infrastructure.

    In June, MEED exclusively reported that the RCU had asked firms to submit their final offers for a contract to build tramway infrastructure at the Al-Ula development.

    The RCU issued a request for proposals in June last year and received commercial bids for the project on 10 November.

    France’s Systra is the consultant.

    In October 2023, the RCU announced that France’s Alstom will supply rolling stock and systems for the Al-Ula tram scheme.

    The RCU unveiled an investment plan worth SR57bn ($15bn) to regenerate Al-Ula in April 2021. About $3.2bn has been allocated for infrastructure development, including the tram and renewable power generation.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15072614/main.jpg
    Yasir Iqbal
  • Contractors submit bids for $1.4bn Kuwait oil pipeline

    12 November 2025

    Register for MEED’s 14-day trial access 

    A low bid of KD419m ($1.4bn) has been submitted on an oil pipeline project in Kuwait, according to figures published by the country’s Central Agency for Public Tenders (Capt).

    The bid was submitted by local contractor Alghanim International General Trading & Contracting.

    The contract was tendered by state-owned upstream operator Kuwait Oil Company (KOC) and covers the construction of crude oil pipelines and associated works.

    The full list of bidders and prices is:

    • Alghanim International General Trading & Contracting – KD419m ($1.4bn)
    • Mechanical Engineering & Construction Company – KD422.5m
    • Al-Dar Engineering & Construction Company – KD425.7m
    • Combined Group Contracting Company – KD502m
    • Heisco – KD506.1m
    • Sayed Hameed Behbehani & Sons – KD674m

    Kuwait is trying to boost project activity in its upstream sector.

    The country’s national oil company, Kuwait Petroleum Corporation, is aiming to increase oil production capacity to 4 million barrels a day (b/d) by 2035.

    In August, Kuwait announced that it was producing 3.2 million b/d.

    Earlier this month, KOC said it was planning to spend KD1.2bn ($3.92bn) on its exploration drilling programme through 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15072150/main.jpg
    Wil Crisp