Jordan sustains utility infrastructure progress

6 June 2023

This package on Jordan’s power and water sector also includes:

Jordan extends $2bn water scheme bid deadline
> Masdar inaugurates 200MW Jordan solar plant
> Jordan signs Ghabawi wastewater plant deal
> Jordan signs $99m solar funding

 

Jordan reached a new level of electricity peak load on the evening of 1 February, recorded at 4,060MW by state utility National Electric Power Company (Nepco).

This was slightly higher than the previous peak registered in January 2022 of 4,010MW.

With a total generation installed capacity of over 6,400MW, the kingdom is comfortable dealing with such demand peaks.

However, with the share of total generation capacity accounted for by solar and wind sources estimated at a substantial 2,371MW, Jordan could benefit from battery energy storage systems (BESS), as well as grid interconnection with its neighbours. 

As it is, Iraq stands to benefit from Jordan’s substantial production surplus, with construction reaching the final stage for the Jordan-Iraq electricity interconnection project.

US-based GE is implementing the project. It comprises a 288-kilometre overhead line from Jordan to Iraq’s Qaim area.

Another project to connect the electricity grid of Jordan to Saudi Arabia is in the tendering process. The estimated $1bn package is expected to enable the daily exchange of 500MW of electricity in its initial phase and up to 1,000MW in a later phase. 

Region plans vital big grid connections

Renewable energy lead

Jordan is anticipated to sustain its renewable energy leadership in the Middle East and North Africa (Mena) region.  

In February this year, Baynouna Solar Energy Company (BSCE) formally inaugurated the 200MW Baynouna solar park. BSCE is a joint venture of the UAE-based clean energy firm Masdar and the Finnish investment and asset management group Taaleri.

The project is Masdar’s second renewable energy asset in Jordan after the 117MW Tafila wind farm, which was completed in 2015.

The inauguration came on the heels of the signing in November 2022 of a memorandum of understanding (MoU) between Masdar and the Jordanian Energy & Mineral Resources Ministry (MEMR) to explore the development of a further 2GW of renewable energy projects in the country.

In addition to utility-scale power and wind projects, Jordan is also making progress with its small-scale solar distribution network.

In February this year, Amman-based Future Sun Renewable Energy Systems and Safwa Islamic finalised a loan agreement for a JD70m ($98.7m) project to install solar power plants at industrial enterprises.

The bank agreed to provide Future Sun with JD70m to fund a 100MW solar power project at 84 industrial enterprises that are Future Sun shareholders. The project is expected to cut electricity costs by JD15m, and each beneficiary will have a solar PV system with a maximum capacity of 2MW.

Water projects

There are growing opportunities for water infrastructure contractors in Jordan as well. A 200MW hydropower plant in Al-Mujib and a water desalination conveyance system in Hisban are planned. The Water Authority of Jordan (WAJ) is planning several wastewater collection and network projects and a desalination plant.

In February, the Water & Irrigation Ministry and the local firm Arab Towers Contracting Company signed an agreement worth 79.5m ($84.7m) to design and implement a wastewater treatment plant in the Ghabawi region.

The European Bank for Reconstruction & Development (EBRD) will provide a 41.3m loan, while the EU has agreed to provide a 30m grant for the project.

Engicon and CDM Smith Europe have signed a $1.2m supervision contract for the project, funded by an EBRD grant.

Under the two agreements, the water authority will build a treatment plant with a capacity of 24,750 cubic metres a day, with sewage tanks instead of the primary type of treatment plant equipment in the Ain Ghazal region.

The project will help to improve the area’s environmental conditions and reduce the biological load on the Khirbet Samra treatment plant.

The country’s largest, single water infrastructure project to date continues to face delays, however. Tendered in March 2022, bids are due this month for the estimated $2bn Aqaba-Amman water desalination and conveyance project.

The build-operate-transfer (BOT) project will pipe water from the southern coast to the country’s northern regions.

The first phase will involve the construction of 280,000 cubic metres a day (cm/d) of capacity for desalination and 80,000 cm/d of groundwater. A planned second phase will raise the plant’s overall production to 600,000 cm/d.

The conveyance segment of the project includes the construction of a seawater intake pump station, reservoir, pipeline, booster pump stations and freshwater collection pipes.

The project is expected to use clean energy in line with the government’s commitment to reduce greenhouse gas emissions.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10909813/main.jpg
Jennifer Aguinaldo
Related Articles
  • French contractor begins work on Morocco’s Noor Atlas project

    24 March 2026

     

    France-headquartered Eiffage is carrying out construction works on phase one of Morocco’s 305MW Noor Atlas solar photovoltaic (PV) programme, according to sources close to the project.

    Morocco’s National Office of Electricity & Drinking Water (Onee) and the Moroccan Agency for Sustainable Energy (Masen) recently signed power purchase agreements (PPAs) for the programme covering the development, financing, construction, and operation of six solar PV power plants.

    The plants were tendered in two lots in 2022, covering the eastern and southern parts of the country.

    The first lot comprises the following four projects:

    • Ain Beni Mathar: 121MW
    • Enjil: 42MW
    • Boudnib: 33MW
    • Buonane: 29MW

    The second lot comprises two solar PV projects in Tan-Tan and Tata, with each having a planned capacity of 40MW.

    Eiffage, through its subsidiary Clemessy Maroc, previously carried out electrical works on Morocco’s Noor Tafilalt solar programme.

    However, it is understood that the contract for lot one is the company’s first role as full engineering, procurement and construction contractor for a solar project in the region.

    Local media reports previously said plants under the programme will be developed by consortiums comprising Moroccan and European companies.

    Contractor details for phase two of the project have not been disclosed. However, it is understood that construction work has begun, with the project scheduled to begin delivering electricity by July 2027.

    In 2025, Masen established a dedicated subsidiary (Noor Atlas Energy Company) to oversee the project’s implementation.

    Germany’s development bank KfW and the European Investment Bank (EIB) are providing concessional financing, while Bank of Africa is providing commercial financing (local) for the project.

    US/India-based Synergy Consulting is acting as consultant on the project.

    In May 2025, Onee obtained EIB financing of €170m and KfW financing of €130m to expand the national grid by 731  kilometres and increase its evacuation capacity by 1,850 MVA.

    EIB previously announced in 2018 that it is providing concessional financing of €129m under the ELM guarantee for Noor Atlas, against a total project cost of €272m.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16100781/main.jpg
    Mark Dowdall
  • Kuwait contractor wins Shagaya power grid deal

    24 March 2026

    Kuwait-based contractor Power Grid Company has won a KD48.6m ($158.7m) contract to build a 400kV overhead transmission line linking the Shagaya solar energy generation station with Wafra in southern Kuwait.

    The contract was awarded by Kuwait’s Ministry of Electricity, Water & Renewable Energy (MEWRE).

    Power Grid was one of three firms that submitted bids last year, according to regional projects tracker MEED Projects.

    The other bidders included India’s Larsen & Toubro, with an offer of $135m, and Kuwait’s National Contracting Company, with a bid of $140m.

    The transmission line will connect Shagaya to the Wafra (Z) transformer station. The project forms part of the wider Shagaya masterplan, which is being developed as a key component of Kuwait’s renewable energy strategy, including the Shagaya renewable energy complex.

    The Kuwait Authority for Partnership Projects (Kapp) is currently procuring a 500MW solar photovoltaic (PV) independent power project (IPP) in partnership with MEWRE.

    As MEED exclusively reported, the deadline to bid for a contract to develop the plant was recently pushed back to the end of April.

    The plant is being developed under zone two of the third phase of the Al-Dibdibah power and Al-Shagaya renewable energy project.

    In January, three consortiums submitted bids for a contract to develop Kuwait’s first utility-scale solar PV plant.

    The Al-Dibdibah power and Al-Shagaya renewable energy phase three, zone one IPP will have a total power generating capacity of 1,100MW.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16097432/main.jpg
    Mark Dowdall
  • Prequalification begins for Cairo Metro Line 2 upgrade

    24 March 2026

     

    Egypt’s National Authority for Tunnels (NAT) has issued a request for prequalification (RFQ) notice inviting firms to prequalify for a contract to rehabilitate and upgrade the Cairo Metro’s Line 2 network.

    The notice was issued in mid-March. The prequalification submission deadline is 30 April.

    According to the official notice, the scope of the works includes the design, execution, supply, installation, testing and commissioning of major system upgrades across the Cairo Metro Line 2 infrastructure and stations, along with integration into existing operational systems.

    The project aims to refurbish and modernise the metro line systems and enhance onboard communications across the current rolling stock fleet, to extend the metro system’s operational lifespan by at least 25 years.

    The contract duration is five years.

    The project is receiving a financing grant of €250m ($263m) from the European Bank for Reconstruction and Development (EBRD), €240m ($252m) from the European Investment Bank (EIB) and €60m ($63m) from the Egyptian government.

    Cairo Metro Line 2 has been operational since 1996. The line runs from Shubra El-Kheima to El-Mounib, spanning about 21.5 kilometres (km) with 20 stations.

    The route includes 12 underground stations, six at-grade stations and two elevated stations.

    The track infrastructure is built around two primary track configurations.

    The line carries about 1.8 million passengers a day.

    The project is part of NAT’s key planned railway projects in the country. According to NAT’s official website, eight key projects, including metro lines, high-speed rail and light rail transit, are currently in the pipeline.

    According to GlobalData, the Egyptian construction industry is expected to grow by 6.4% in 2026, supported by rising foreign direct investment in the country, coupled with the government’s investment in energy and industrial construction projects.

    The industry’s expansion in the forecasted period will be supported by investments outlined in Egypt’s financial year 2025-26 budget, approved in June 2025. The budget includes a total government spending of E£4.6tn ($91.3bn).

    The infrastructure construction sector is expected to expand by 6.9% from 2026 to 2029, supported by investments in road, rail and port infrastructure projects.

    According to MEED Projects, Egypt has been the most active market for the rail sector in the Mena region, with contracts worth over $34bn awarded in the past decade.


    MEED’s March 2026 report on Egypt includes:

    > COMMENT: Egypt’s crisis mode gives way to cautious revival
    > GOVERNMENT: Egypt adapts its foreign policy approach

    > ECONOMY & BANKING: Egypt nears return to economic stability
    > OIL & GAS: Egypt’s oil and gas sector shows bright spots
    > POWER & WATER: Egypt utility contracts hit $5bn decade peak
    > CONSTRUCTION: Coastal destinations are a boon to Egyptian construction

    To see previous issues of MEED Business Review, please click here

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16097414/main.jpg
    Yasir Iqbal
  • Contractors submit bids for Safaniya onshore facilities project

    24 March 2026

     

    Contractors have submitted bids to Saudi Aramco for a project to build onshore surface facilities to boost productivity at the Safaniya offshore oil field development in Saudi Arabia.

    The Safaniya field is the world’s largest offshore oil field, with a production capacity of nearly 1.2 million barrels a day (b/d). Discovered in 1951, the field is located in the Gulf waters, approximately 265 kilometres north of Aramco’s headquarters in Dhahran.

    Contractors submitted bids for the Safaniya onshore surface facilities project by the deadline of 17 March, according to sources.

    Aramco issued the main tender for engineering, procurement and construction (EPC) works on the Safaniya onshore surface facilities project on 9 July last year.

    Contractors were initially given deadlines of 24 October and 7 November to submit technical and commercial bids for the project, MEED previously reported. Aramco later merged the technical and commercial bid submission requirements and extended the techno-commercial proposal submission deadline until 31 January.

    Prior to that, Aramco is understood to have issued the solicitation of interest document for the Safaniya field onshore surface facilities project in May, with contractors submitting responses by 28 May.

    The EPC scope of work has been divided into two packages:

    • Package 1 – Water treatment and injection plant:
      • Building new water injection units
      • Expansion of gas-oil separation plant one
      • Building storage tanks, transfer pumps and substation
      • A central processing facility at the Zuluf field development, including water transfer pumps, chemical injection skids and other components
         
    • Package 2 – Produced water utilities:
      • Fire water system
      • Potable water units
      • Utilities
      • Nitrogen generation system
      • Site buildings
      • Electrical infrastructure
      • Security systems
      • Telecommunications networks

    In addition to pursuing the onshore facilities project to boost Safaniya’s productivity, MEED also previously reported that Aramco had issued three key offshore tenders last year for the field’s next expansion phase.

    Contractors in Aramco’s Long-Term Agreement pool of offshore service providers submitted bids for the three tenders – Contracts Release and Purchase Order (CRPO) numbers 154, 155 and 156 – by 31 August.

    Aramco awarded Italian contractor Saipem the EPCI contract for CRPO 156, valued at an estimated $500m, in February. The scope of work on the contract covers the EPCI of a 48-inch trunkline, comprising approximately 65 kilometres offshore and 12km onshore, as well as associated subsea facilities at the Safaniya oil field.

    The Saudi energy giant is evaluating bids for the other two tenders for the Safaniya offshore field expansion project and is expected to award contracts within the first quarter.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16097410/main1828.jpg
    Indrajit Sen
  • Local firm wins Al-Ras Dubai Walk masterplan deal

    24 March 2026

     

    Abu Dhabi-based firm Western Bainona Group has won a contract from Dubai’s Roads & Transport Authority (RTA) to develop the first phase of the Dubai Walk masterplan in the Al-Ras area.

    The project’s first phase focuses on developing the historic Al-Ras walkway, including 12 kilometres (km) of pedestrian paths and 5km of cycling tracks, along with the rehabilitation of 10 artistic spaces.

    The Al-Ras walkway project will link pedestrian routes with 11 metro stations, bus stops and marine transport points to improve first- and last-mile access.

    The RTA said that the works include upgrades to internal pedestrian paths and the waterfront promenade, using straightforward urban design interventions that will maintain the area’s historic identity.

    Planned improvements include wider sidewalks, added shade elements, more seating, increased greenery and heritage-sensitive wayfinding signage.

    The overall masterplan includes extending a connected pedestrian network across 160 locations, with plans to build and upgrade around 6,000km of walkways throughout the emirate by 2040.

    It also includes developing 110 pedestrian bridges and underpasses to improve links between districts, supporting a shift in walking and other low-impact mobility from 16% of trips in 2025 to 25% by 2040.

    Proposed highlights include a bridge on Al-Ittihad Street between Al-Nahda and Al-Mamzar; another on Tripoli Street linking Al-Warqa with Mirdif; a crossing on Al-Khawaneej Street connecting Mushrif and Al-Khawaneej; and a bridge on Dubai-Al-Ain Road tying Dubai Silicon Oasis to Dubailand.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16097076/main.jpeg
    Yasir Iqbal