Jeddah Tower cements region’s status as global high rise capital

2 October 2024

 

> This package also includes: Contractor appointed to complete world's tallest tower


The appointment of Saudi Binladin Group (SBG) on 2 October to complete the 1,000-metre-plus-tall Jeddah Tower in Saudi Arabia will cement the region's status as the global high-rise capital. Dubai's Burj Khalifa has been the world's tallest tower since 2009, and the completion of Jeddah Tower will mean the region's run as home to the world's tallest building will continue for many more years. Here is a list of the region's tallest buildings:

1. Burj Khalifa, UAE

The construction of the world’s tallest skyscraper, Burj Khalifa, began in 2006 and reached its pinnacle in 2009.

The 829.8-metre-tall tower was developed by Dubai’s Emaar Properties and designed by US-based Skidmore Owings & Merrill.

Construction was led by a consortium of South Korea’s Samsung C&T, the local/Belgian Bel Hasa Six Construct and the local Arabtec Construction. The $875m main construction contract was awarded in December 2004.

The 163-storey tower took 22 million man-hours to build. Overall, the project cost about $1.5bn to complete. 

2. Mecca Royal Clock Tower, Saudi Arabia

The 601-metre-tall Mecca Royal Clock Tower is the landmark feature of the Abraj al-Bayt complex.

The development comprises seven towers overlooking the holy site of Kaaba, with a total built-up area of more than 1.4 million square metres and 15,000 apartments.

Saudi Binladin Group was the main contractor for the project.

The $800m contract for the clock tower was awarded in 2003 and the complex completed in 2012.

3. Marina 101, UAE

Marina 101 is the second-tallest building in Dubai.

Construction began in 2007 when Turkish contractor TAV was awarded the estimated AED800m ($218m) main contract.

The project involved building a 101-floor tower with a height of 425 metres and a total built-up area of 144,000 sq m.

The project has witnessed several setbacks over the years and remains unoccupied. The construction works were partially completed in 2017.

4. Princess Tower, UAE

Princess Tower is the second-tallest residential building in the world.

The 107-storey tower stands 413 metres tall and is located in Dubai Marina.

The project was announced in 2005 and the foundation works were completed in 2007.

The main contractor for the project was the Lebanese Arabian Construction Company.

The Princess Tower was the world’s tallest residential building from 2012 to 2015, when it was overtaken by 432 Park Avenue in New York City.

5. Al-Hamra Tower, Kuwait

The 80-floor Al-Hamra Tower is the tallest building in Kuwait and the 36th tallest in the world, at 412 metres. It was built by the local Ahmadiah Contracting & Trading Company. Construction works started in 2005 and were completed in 2011. The project was designed by US-based architectural firms Skidmore, Owings & Merrill, Callison and the local Al-Jazirah Engineers & Consultants. 

6. 23 Marina, UAE

The 392-metre-tall 23 Marina is the fourth-tallest building in the UAE and the 40th tallest in the world. Dubai Civil Engineering constructed the 88-floor tower. The construction works started in 2005 and the project was completed in 2012. US-based KEO International and Indian Architect Hafeez Contractor designed the tower. 

Jeddah Tower restart is watershed moment

7. PIF Tower, Saudi Arabia

The Public Investment Fund (PIF) Tower is located within Riyadh’s King Abdullah Financial District. US-based HOK Architects, Canadian WSP, Hyder Consulting and the local Omrania Associates designed the 385-metre-tall, 80-storey tower. The construction works began in 2009 and were finally completed in 2022. Saudi Binladin Group was the main project contractor.

8. Iconic Tower, Egypt

The 385-metre-tall Iconic Tower is the centrepiece among the 20 buildings of the Central Business District in Egypt’s New Administrative Capital. The construction of this 80-storey tower started in 2019 when China State Construction Engineering Corporation was appointed as the main contractor. The construction works on Africa’s tallest skyscraper were completed in 2022. Lebanese engineering company Dar al-Handasah was the project consultant. 

9. Burj Mohammed bin Rashid, UAE

Completed in 2014, Abu Dhabi’s tallest building measures 381 metres and consists of 88 floors. The tower, part of the Abu Dhabi World Trade Centre, was announced in 2004. The construction works started in 2007 under the government’s redevelopment plan. The consultants involved in the development included Arup, Mott MacDonald, Foster & Partners, AtkinsRealis and Callison. Lebanese contractor Arabian Construction Company undertook the construction works.

10. Elite Residence, UAE

Dubai Marina’s Elite Residence, a 91-storey residential building, is the sixth-tallest building in the UAE. The 380-metre-tall tower was announced in 2006 and designed by Lebanese Khatib & Alami. The construction works began in 2007 when Arabian Construction Company was awarded the main construction contract. The tower has been operational since 2012.

SOON TO JOIN

GCC countries’ quest to build tall towers is not over yet. Several upcoming developments are likely to overthrow some of the tall towers on our list. These schemes include:

  • The North Pole, 2kms (Saudi Arabia)
  • Burj Azizi, 725 metres (UAE)
  • Pentominium Tower, 516 metres (UAE)
  • Burj Binghatti, 500+ metres (UAE)

Tallest towers in the world

Jeddah Tower image (top): Jeddah Economic Company

https://image.digitalinsightresearch.in/uploads/NewsArticle/12641934/main.gif
Yasir Iqbal
Related Articles
  • Firms seek to prequalify for Oman waste-to energy project

    10 November 2025

    Oman’s state offtaker Nama Power and Water Procurement (Nama PWP) has received 18 submissions for qualification from international and local companies for the planned waste-to-energy (WTE) project in Barka, South Al-Batinah governorate.

    The project will be Oman’s first large-scale waste-to-energy facility with a generation capacity of 95–100MW.

    According to Nama PWP, the facility will be developed on a 190,000-square-metre site and is scheduled to reach commercial operation in the fourth quarter of 2030.

    The project is expected to contribute 757GWh of renewable energy annually and reduce carbon dioxide emissions by about 302,000 tonnes per year. 

    It will process up to 3,000 tonnes of municipal solid waste per day using grate incineration technology.

    The following companies submitted statements of qualifications:

    • Acwa Power (Saudi Arabia)
    • Al Ramooz National (Oman)
    • Al Tasnim Enterprise (Oman)
    • ASPEC for Contracting & Environmental Consultancy (Oman)
    • China Communications Construction (China)
    • China Everbright Environment Group (China)
    • China Tianying (China)
    • Eco Vision (Oman)
    • Emirates Waste to Energy (UAE)
    • Eternal Industrial Investment (China)
    • FCC Medioambiente Internacional (Spain)
    • Future Vision Engineering Services (Oman)
    • Horsol Switz Engineering Asia Pte (Singapore)
    • Hunan Junxin (China)
    • Itochu Corporation (Japan)
    • Kanadevia Inova AG (Switzerland)
    • Keppel Seghers Engineering Co. (Singapore)
    • Mohammed Abdulmohsin Al-Kharafi & Sons (Kuwait)
    • N.V. Besix (Belgium/UAE)
    • Oman National Engineering & Investment (Oman)
    • Paprec Group (France)
    • Satarem America (US)
    • Seven Seas Petroleum (Oman)
    • Shanghai Environment Group (China)
    • Shanghai SUS Environment (China)
    • Shenzhen Energy Group (China)
    • Sinoma Energy Conservation (China)
    • Suez International SAS (France/Oman branch)
    • Veolia Middle East (France)
    • Urbaser (Spain)

    In August, MEED reported that Oman had finally moved to the prequalification phase following attempts to start work on the project to develop a waste-to-energy facility for a few years.

    Nama PWP is understood to have started the process to appoint consultants for the project, based on an independent power producer (IPP) model, in 2019, when it was known as Oman Power & Water Procurement Company (OPWP).

    It later put the project on hold, only to revive the prequalification and procurement process, along with Oman Environmental Services Holding Company (Beah), in 2023.

    Beah will supply the waste feedstock for the project, which is part of a long-term plan to convert municipal waste into energy and reduce landfill dependency, supporting Oman’s net-zero emissions target for 2050.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15058075/main.jpg
    Mark Dowdall
  • WEBINAR: Saudi gigaprojects 2026 and beyond

    7 November 2025

    Webinar: Saudi Gigaprojects 2026 & Beyond
    Tuesday 25 November 2025 | 11:00 GST  |  Register now


    Agenda:

    • Latest update to November 2025 on the gigaprojects programme and the Saudi projects market in general, with full data analysis for 2025 year-to-date
    • Latest assessment on the reprioritisation of the programme and views on which of the gigaprojects are being prioritised
    • Summary of key recent project developments and announcements 
    • Analysis of key contracts awarded this year to date
    • Highlights of key contracts to be tendered and awarded over the next six months
    • Key drivers and challenges going forward plus MEED’s outlook for the future short and long-term prospects of the gigaprojects programme
    • In-depth look at the recently announced King Salman Gate gigaproject and other planned, but unannounced PIF developments
    • Life beyond the gigaprojects – what other key project programmes are being implemented in the kingdom 
    • Q&A session

    Hosted by: Edward James, head of content and analysis at MEED

    A well-known and respected thought leader in Mena affairs, Edward James has been with MEED for more than 19 years, working as a researcher, consultant and content director. Today he heads up all content and research produced by the MEED group. His specific areas of expertise are construction, hydrocarbons, power and water, and the petrochemicals market. He is considered one of the world’s foremost experts on the Mena projects market. He is a regular guest commentator on Middle East issues for news channels such as the BBC, CNN and ABC News and is a regular speaker at events in the region. 

    Click here to register

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15045990/main.gif
    Edward James
  • Bahrain advances utility reform

    7 November 2025

     

    In September, Bahrain’s government referred a draft law to parliament to restructure the kingdom’s electricity and water sector.

    This proposes dissolving the Electricity & Water Authority (Ewa) and transferring its assets and functions to a newly established National Electricity & Water Company, which will operate under the oversight of the Electricity & Water Regulatory Authority. 

    The reform marks the first full structural overhaul of Bahrain’s utilities sector in nearly two decades and signals a shift towards a more commercially driven model. 

    Regulatory and operational roles would be separated for the first time, allowing private sector participation under transparent licensing and tariff systems, aligning Bahrain with utility reforms seen in Saudi Arabia, Oman and the UAE.

    It comes amid a relatively subdued year for new contracts that broadly falls in line with 2024’s performance. Most significantly, Bahrain continues to move towards its two upcoming utility public-private partnership (PPP) schemes, the Sitra independent water and power project (IWPP) and the Al-Hidd independent water project (IWP).

    In August, a developer tender was issued for the main works package for the Sitra IWPP. This followed the prequalification of seven companies and consortiums, reflecting a wide range of international interest.

    The planned Sitra IWPP replaces the previously planned Al-Dur 3 and will be the first IWPP project to be awarded since the 1,500MW Al-Dur 2 IWPP was completed in 2021.

    The combined-cycle gas turbine (CCGT) plant is expected to have a production capacity of about 1,200MW of electricity, while the project’s seawater reverse osmosis (SWRO) desalination unit will have a production capacity of 30 million imperial gallons a day (MIGD) of potable water. The main contract is expected to be awarded by the end of the year, with commercial operations set for 2029. 

    A developer tender was also recently launched for Bahrain’s first independent, standalone SWRO plant following a prequalification process that shortlisted nine companies and consortiums.

    The Al-Hidd IWP is expected to have a production capacity of about 60MIGD of potable water and be completed in 2028. It is likely to be the last IWPP for Bahrain, which aims to reach net-zero carbon emissions by 2060.

    The imminent launch of the two projects boosts Bahrain’s projects pipeline, which has experienced muted growth in the aftermath of the Covid-19 pandemic, carried by relatively small-scale projects.

    Solar PV projects

    The creation of the National Electricity & Water Company as Bahrain’s new operational entity could also support the rollout of future renewable energy schemes. 

    As a corporatised offtaker, the company will be able to enter long-term power purchase agreements (PPAs) with private developers under a more bankable framework. Currently, these are negotiated by Ewa on a case-by-case basis.

    The government recently signed a 123MWp solar PPA with the UAE’s Yellow Door Energy, highlighting growing private sector interest in the market. The project includes the world’s largest single-site rooftop solar installation and will be developed at Foulath Holding’s industrial complex in Salman Industrial City.

    Bahrain has already set a target to source 20% of its energy from renewables by 2035 and reach net-zero emissions by 2060.

    In October, Ewa also issued a tender for the development of the Bilaj Al-Jazayer solar independent power project (IPP). The planned 100MW project will be developed on a build-own-operate basis with a 25-year contract term.

    In parallel, Bahrain is broadening its long-term energy strategy beyond solar. In July, the kingdom signed a cooperation agreement with the US on the peaceful use of nuclear energy, aimed at advancing research and potential deployment of small modular reactor (SMR) technology.

    For countries like Bahrain, which has limited land availability and high energy demand growth, SMRs could offer a way to produce low-carbon, reliable baseload power without requiring vast areas of land for solar or wind farms. 

    Officials have indicated that SMRs, along with floating solar solutions, are being studied as part of a broader push to diversify energy sources and expand renewable generation capacity.

    Water and waste

    Bids for four Ewa-owned projects are currently being evaluated. This includes the construction of a new SWRO desalination plant on Hawar Island and rehabilitation works for the Ras Abu Jarjur water treatment plant in Askar. Contracts for both projects are expected to be awarded this year.

    Bahrain’s Ministry of Works (MoW) is the other client for the island-state’s power and water infrastructure-related projects. It has awarded three smaller sewage-related contracts this year.

    It is also preparing to tender the construction of a $130m sewage treatment plant in Khalifa City, which will be developed in two phases. Meanwhile, the construction of MoW’s sewerage scheme phase 2 network in Bahrain remains in the early design stage with no further updates.

    As Bahrain moves ahead with these projects, the new electricity and water law could define how future investments are structured, regulated and financed. This could reshape the kingdom’s utilities landscape for decades to come.


    MEED's December special report on Bahrain also includes:

    > ECONOMY: Bahrain’s cautious economic evolution
    > BANKING: Mergers loom over Bahrain’s banking system
    > OIL & GAS: Bahrain remains in pursuit of hydrocarbon resources
    > CONSTRUCTION: Bahrain construction faces major slowdown
    > TRANSPORT: Bahrain signs game-changer aviation deal with Air Asia

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15044915/main.gif
    Mark Dowdall
  • Masdar and OMV sign 140MW green hydrogen plant deal

    7 November 2025

    Register for MEED’s 14-day trial access 

    Abu Dhabi Future Energy Company (Masdar) has signed a binding agreement with Austrian energy company OMV to develop and operate a major green hydrogen production plant in Austria.

    The 140MW green hydrogen electrolyser plant will be Europe's fifth-largest hydrogen plant, according to Masdar chairman, Sultan Ahmed Al-Jaber.

    It will be built in Bruck an der Leitha, about 40 kilometres southeast of Vienna.

    The facility will be developed under a newly established joint venture, in which Masdar owns 49% and OMV holds the majority 51% stake.

    The agreement was signed at the Abu Dhabi International Petroleum Exhibition and Conference (Adipec), in the presence of Al-Jaber; Austria’s Federal Minister of Economy, Energy and Tourism, Wolfgang Hattmannsdorfer; OMV CEO Alfred Stern; and Masdar CEO Mohamed Jameel Al-Ramahi.

    It is expected that the project will reach financial close in early 2026, subject to final documentation, shareholder consent and regulatory approvals.

    Construction began in September, with operations scheduled to start in 2027.

    OMV, which already operates a 10MW electrolyser in Schwechat, will procure renewable electricity for hydrogen production and retain ownership of the output.

    Several large-scale hydrogen facilities across Europe are currently under construction.

    In 2024, Germany's Siemens Energy signed a deal with German utility EWE to build a 280MW green hydrogen electrolysis plant. This is expected to begin operations in 2027.

    Masdar and OMV previously signed a letter of intent to cooperate on green hydrogen, synthetic sustainable aviation fuels (e-SAF) and synthetic chemicals in both the UAE and central and northern Europe.


    READ THE NOVEMBER 2025 MEED BUSINESS REVIEW – click here to view PDF

    Mena players up the ante in global LNG production race; Investment takes UAE non-oil economy from strength to strength; Project finance activity draws international lenders back to market

    Distributed to senior decision-makers in the region and around the world, the November 2025 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15040802/main0933.jpg
    Mark Dowdall
  • Syria signs deal for 5GW power projects

    7 November 2025

    Register for MEED’s 14-day trial access 

    The Syrian Ministry of Energy has signed final concession agreements with an international consortium led by Qatar’s Urbacon (UCC) Holding to build and operate eight power plants with a total capacity of 5GW.

    The consortium includes Urbacon Concessions Investment (a subsidiary of UCC Holding), Kalyon GIS Energy (Turkiye), Cengiz Energy (Turkiye) and Power International (US).

    UCC Holding and Power International USA are both subsidiaries of Qatar’s Power International Holding. The US-based subsidiary was likely created to ease transactions and imports to Syria under the new General Licence 25 (GL 25) US sanctions exemptions for Syria.

    The final contracts cover the construction and operation of the following four natural gas-fired combined-cycle plants:

    • North Aleppo (1,200MW)
    • Deir Ezzor (1,000MW)
    • Zayzoun (1,000MW)
    • Mehardeh (800MW)

    It also includes four solar projects totalling 1,000MW across Widian Al-Rabee, Deir Ezzor, Aleppo and Homs.

    The agreements were signed in Damascus by Energy Minister Mohammad Al-Bashir and UCC Holding president Ramez Al-Khayyat, in the presence of consortium representatives and senior Syrian energy officials.

    The deal represents Syria’s first integrated public-private partnership model in the energy sector and marks the start of the implementation phase of Syria’s national energy rehabilitation programme. 

    The projects also form part of a wider Qatari investment package in Syria.

    In May, the ministry signed a $7bn memorandum of understanding that set the framework for strategic energy cooperation.

    Preparatory engineering and technical works, including site surveys and feasibility studies, have since been completed.

    Completion is expected within three years for the gas plants and two years for the solar plants, with the projects doubling the country’s output.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15040717/main.jpg
    Mark Dowdall