Jeddah Tower restart is watershed moment

15 September 2023

Commentary
Colin Foreman
Editor

The issue of the tender to complete the world’s tallest tower is a watershed moment for the Jeddah Tower and broader Saudi construction sector.

Construction in the kingdom has had a rough ride. The 2014 drop in oil prices ushered in a decade of stalled projects and spending cuts for the industry. While gigaproject announcements have pointed to a brighter future, financial concerns have stubbornly remained.

As the world’s tallest tower, the 1,000-metre-plus-tall Jeddah Tower symbolised the challenges of the past 10 years more than anything else in Saudi Arabia. As the tower restarts, the construction sector will want to finally consign the stress of the past 10 years to the history books.

While getting paid remains essential, the focus is shifting to other areas with issues such as logistics and recruitment, and for projects such as Jeddah Tower, engineering challenges are now a primary concern.

Building tall towers and other record-breaking projects are serious undertakings, but unlike chasing payments, they are challenges the construction sector should relish.

Images: Jeddah Economic Company; Dar al-Handasah

https://image.digitalinsightresearch.in/uploads/NewsArticle/11149979/main.gif
Colin Foreman
Related Articles
  • Dubai seeks contractors for Metro Gold Line

    20 May 2026

     

    Register for MEED’s 14-day trial access 

    Dubai's Roads & Transport Authority (RTA) has invited contractors to express interest in a contract to build the new Gold Line, as part of its expansion of the Dubai Metro network.

    The notice was issued in mid-May with a submission deadline of 13 June.

    Dubai officially announced the launch of the new Gold Line in April.

    In a post on social media site X, Sheikh Mohammed Bin Rashid Al-Maktoum, UAE Vice President and Prime Minister and Ruler of Dubai, said the project will cost about AED34bn ($9.2bn).

    The Gold Line will increase the total length of the Dubai Metro network by 35%.

    The project is scheduled for completion in September 2032.

    The Gold Line will be a fully underground network covering more than 42 kilometres, with 18 stations.

    It will pass through 15 areas in Dubai, benefiting 1.5 million residents.

    The project is expected to provide connectivity to over 55 under-construction real estate development projects.

    The Gold Line will start at Al-Ghubaiba in Bur Dubai and end at Jumeirah Golf Estates.

    It will be connected to Dubai Metro’s existing Red and Green lines and will integrate with the Etihad Rail passenger line.

    The contractor will be responsible for the design and build of all civil works, electromechanical equipment, rolling stock and rail systems.

    The selected contractor will also be required to assist in the systems maintenance and operations during an initial three-year period.

    In October last year, MEED exclusively reported that the RTA had selected US-based engineering firm Aecom to provide consultancy services for the Dubai Metro Gold Line project.

    Stage one covers concept design, stage two covers preliminary design, stage three covers the preparation of tender documents, stage four encompasses construction supervision and stage five covers the defects and liability period.


    MEED’s May 2026 report on the UAE includes:

    > COMMENT: Conflict tests UAE diversification
    > GVT &: ECONOMY: UAE economy absorbs multi-sector shock

    > BANKING: UAE banks ready to weather the storm
    > ATTACKS: UAE counts energy infrastructure costs

    > UPSTREAM: Adnoc builds long-term oil and gas production potential
    > DOWNSTREAM: Adnoc Gas to rally UAE downstream project spending
    > POWER: Large-scale IPPs drive UAE power market
    > WATER: UAE water investment broadens beyond desalination
    > CONSTRUCTION: War casts shadow over UAE construction boom
    > TRANSPORT: UAE rail momentum grows as trade routes face strain

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16919605/main.png
    Yasir Iqbal
  • Construction advances on Riyadh King Salman airport

    19 May 2026

    King Salman International Airport (KSIA) is advancing airside infrastructure works under its long-term expansion programme in Riyadh, including the delivery of a third runway and new private aviation facilities.

    Construction activity on the central runway programme is progressing across several operational zones, with works covering excavation, grading, site preparation and taxiway-enabling infrastructure to support upcoming phases.

    The third runway is intended to increase airfield capacity and cater to the airport’s future operational requirements.

    In a separate development, KSIA has completed initial landside works for the private aviation apron, marking a milestone in the rollout of its executive aviation infrastructure.

    The completed scope includes pavement markings, waterproofing systems, firefighting infrastructure chambers and final operational inspections to support readiness for the next stages.

    KSIA has also secured General Authority of Civil Aviation (GACA) approval for phase one airside works, which includes the planned connection of Taxiway Alpha to the private aviation facilities, strengthening operational integration between executive aviation assets and airfield movement areas.

    The packages form part of the wider KSIA masterplan, which covers about 57 square kilometres and supports Saudi Arabia’s objective of positioning Riyadh as a global aviation and logistics hub.

    The airport aims to accommodate up to 100 million passengers by 2030.

    Saudi Arabia plans to invest $100bn in its aviation sector. The Saudi Aviation Strategy, announced by GACA, aims to triple annual passenger traffic to 330 million travellers by 2030. It also targets air cargo growth to 4.5 million tonnes and an increase in total air connections to more than 250 destinations.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16906496/main.jpeg
    Yasir Iqbal
  • Aldar launches Al-Ghadeer Gardens project

    19 May 2026

    Abu Dhabi-based real estate developer Aldar Properties has launched the Al-Ghadeer Gardens project, located on the Abu Dhabi-Dubai border.

    The new residential development will feature 437 villas and townhouses, offering two-, three- and four-bedroom homes.

    Al-Ghadeer Gardens will include more than 30,000 square metres of landscaped open space, supporting a pedestrian-friendly layout and outdoor-focused living.

    As part of its sustainability and wellbeing approach, the project is targeting Estidama Pearl 2 and Fitwel 2-star certifications.

    Earlier this month, Aldar announced its Q1 financial results, reporting a 20% year-on-year increase in net profit after tax to AED2.3bn ($626m).

    Aldar Development recorded a 14% year-on-year rise in revenue to $1.7bn, while earnings before interest, taxes, depreciation and amortisation (Ebitda) increased 23% to $599m.

    UAE revenue backlog rose to $17bn at the end of March from $16.6bn at the end of December, with an average duration of 29 months.

    The group attributed its performance to revenue from its development backlog and steady income from its investment properties.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16906154/main.jpg
    Yasir Iqbal
  • Iraq trucks oil from the south to Kurdish pipeline

    19 May 2026

     

    Iraq is trucking crude from Basra to the north of the country to be exported via the Iraq-Turkiye Pipeline (ITP), according to industry sources.

    The oil is being loaded into trucks at fields in Basra before being driven to the north, where it is injected into the pipeline network at Khurmala Dome, in the northern section of the Kirkuk field.

    Once it has entered the network at Khurmala Dome, it is transported to the main ITP export pipeline and eventually to the port of Ceyhan in Turkiye, where it can be loaded onto ships.

    The volumes of crude being transported using trucks have surged in Iraq since the US and Israel attacked Iran on 28 February, starting a regional conflict that has disrupted shipping through the Strait of Hormuz.

    One source said: “Most of the crude that is being trucked out of Iraqi oil fields at the moment is going to Syria, but some is being trucked to the north where it is being funnelled through the pipeline.”

    Even with the additional volumes being trucked from the south, Iraq is struggling to boost exports using the ITP.

    At the end of March, Amer Khalil, the director-general of Iraq’s state-run North Oil Company, said that Iraq was exporting 200,000 barrels a day (b/d) through the ITP.

    At the time, he said that the pipeline, which runs from Kirkuk in Iraqi Kurdistan to the port of Ceyhan in Turkiye, was expected to start transporting 300,000 b/d “in the near future”.

    As of early May, the pipeline was still exporting about 200,000 b/d, despite having a nameplate capacity of 1.4 million b/d.

    One of the factors said to be stopping increased volumes from being shipped through the pipeline is that several key oil fields in northern Iraq evacuated staff and stopped production after the US and Israel started their war with Iran.

    Another factor is that Iraq has not invested in domestic pipeline infrastructure to pipe production from Basra to Kurdistan, where it could be exported via the Kurdish ITP route.


    READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Global energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.

    Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16902345/main1824.jpg
    Wil Crisp
  • Kuwaiti oil services company secures credit facility

    19 May 2026

    The Kuwaiti drilling and oilfield services provider Action Energy Company (AEC) has secured a new credit facility and renewed and expanded an existing facility in order to support the company’s rig fleet expansion.

    The new facility and the expansion were obtained from two Kuwaiti banks and had a combined value of KD40.9m ($132.8m).

    In its statement, AEC said that the facilities support the financing and deployment of new rigs linked to contract awards previously announced with the state-owned upstream operator Kuwait Oil Company (KOC).

    The company added: “They further reinforce AEC’s financing structure and strengthen its ability to execute its contracted fleet expansion plan through 2026 and beyond, while maintaining a disciplined approach to capital allocation.”

    The new credit facility was obtained from Kuwait International Bank (KIB).

    It is worth KD7.3m ($23.7m) and will finance two new 750-horsepower (HP) rigs.

    The renewal and expansion of the existing facility is worth KD33.6m ($109.1m) and was obtained from Commercial Bank of Kuwait (CBK) to finance four new 1,500 HP rigs and one 1,000 HP rig, in addition to the renewal of the existing facilities.

    AEC announced its financial and operational performance for the first quarter earlier this month.

    The company reported a net profit of KD2.2m ($7.1m).

    The company’s revenue grew by 69.2% year-on-year, primarily driven by the expansion of the operating rig fleet from 13 rigs in the first quarter of 2025 to 20 rigs in the first quarter of 2026, including the full-quarter contribution of 10 new rigs deployed during 2025.

    The company is benefitting from a substantial multi-year contracted backlog with KOC.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16902234/main.jpg
    Wil Crisp