Jeddah plans $31bn airport expansion
29 May 2023

Register for MEED’s guest programme
Jeddah Airports Company (Jedco) plans to transform King Abdulaziz International airport (KAIA) into one of the world’s largest airports with a SR115bn ($31bn) expansion plan that will increase its capacity to 114 million passengers a year.
The largest components of the plan cover the design and expansion of Terminal 1 and the construction of a new passenger terminal to be called Terminal 2.
The expected completion date for the expansion project is 2031.
Terminal plans
The Terminal 1 project comprises basic infrastructure and enabling works, the installation of new gates, air bridges and parking aprons, the extension of the automatic people mover, new baggage conveyor systems and lounges, with the goal of increasing annual passenger capacity by 15 million.
Work on the multibillion-dollar scheme is scheduled to start this year, with completion targeted for 2026.
The Terminal 2 project aims to increase the airport’s total capacity to 114 million passengers a year, almost tripling the airport’s 40 million limit today.
Due to start in 2026 and end by 2031, the project will involve constructing a completely new terminal building with dozens of gates, new taxiways, aprons, roads, utilities, and baggage handling and other software systems. It is likely to be worth in excess of $10bn to build.
Jedco is also planning to construct a fourth runway starting in 2025 and completing by 2029 to cope with the increased traffic. Due to space limitations, the new runway will require substantive infrastructure relocation work to accommodate it.
Passenger traffic-focused developments are not the only element of the plan. As part of growing the airport’s commercial proposition, the client is also due to start developing a new logistics area later this year.
Covering more than 3 square kilometres, the facility will house new customs and service buildings as well as several leasable warehouses for the private sector. Construction of the facilities will be implemented in phases with an ultimate scheduled completion date of 2029.
Concurrently, Jedco is building a new Hajj and Umrah terminal. Pilgrims comprise a large portion of passenger traffic, and the new arrivals and departures hall for budget airlines will be able to handle 15 million passengers a year. The project is expected to be completed by 2025.
Another project starting this year is the construction of a new baggage handling facility to expand the airport’s existing capacity. The building will be located next to Terminal 1 and will be integrated with the existing conveyor belt systems.
Passenger demand
The project investment programme is a result of Jedco’s forecast that annual demand will reach 114 million passengers by 2030. Of this figure, the authority estimates 51 million will come from Saudi Arabian Airlines, 21 million from international airlines, and 13 million and 12 million from budget airlines Flynas and Flyadeal, respectively.
The forecast and plans were created in conjunction with key drivers of future passenger demand in the Mecca and Jeddah region, including gigaproject real estate developers Roshn and Uptown Jeddah, air cargo handler Saudi Logistics Services (SAL), and the General Civil Aviation Authority (Gaca) with its subsidiary Matarat Holding. Engineering firms Atkins, Mace and DGJ also inputted into the process. The three companies are the consultants on the capital projects investment plan.
KAIA has three operational terminals. Opened in 2018, Terminal 1 is one of the world’s largest passenger terminals, and caters primarily for the state carrier and domestic flights. The North Terminal handles international airlines, while the Hajj Terminal is dedicated to pilgrim traffic.
Construction work on KAIA has been a key driver of airport-building activity in Saudi Arabia in the past. In 2010, there were over $7bn of contract awards for work at the airport, marking the most active year for airport construction activity on record, according to regional projects tracker MEED Projects.
There are other major airport projects planned in Saudi Arabia. In November, Saudi Arabia’s Crown Prince Mohammed bin Salman bin Abdulaziz al-Saud announced the masterplan for King Salman International airport in Riyadh. If completed on time in 2030, it will become the largest airport in the world in terms of passenger capacity.
The airport aims to accommodate up to 120 million passengers by 2030 and 185 million by 2050. For cargo, the goal is to process 3.5 million tonnes a year by 2050.
Neom airport
Another major airport is planned for Neom. US firm Aecom confirmed on 22 March that it had been awarded a contract to provide project management consultancy (PMC) services for the new airport project.
The airport will be inland, close to the Tabuk end of the 170-kilometre-long Line development. Neom International airport is separate from the Neom Bay airport, which started receiving commercial flights in 2019.
Although not confirmed, it is understood that the first phase of the airport will have the capacity to handle 25 million passengers a year. A second phase could take the capacity up to 50 million passengers a year. There is an aspiration for the airport to become the largest in the world, with a capacity of 100 million passengers a year.
Regional airports
Smaller domestic airports are also being developed. In March, Matarat signed a three-year contract with France’s Egis Group to provide technical support and project management services for 26 regional airports.
The contract aims to establish phased project management portals, update airport project management policies and procedures, and provide technical support for planning and designing.
The contract also involves following up on the implementation of capital projects with Matarat subsidiaries, including Riyadh Airports Company, Jeddah Airports, Dammam Airports and Cluster2.
Exclusive from Meed
-
Saudi Arabia battery storage awards provide fresh lift24 August 2026
-
Qatar receives bids for major power grid expansion24 August 2026
-
Maaden closes $1bn term loan and credit facility24 August 2026
-
Dubai inflation slows to 5.3% in July24 August 2026
-
Libya oil project on track for 2027 completion24 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Saudi Arabia battery storage awards provide fresh lift24 August 2026
Commentary
Mark Dowdall
Power & water editorThe latest battery storage awards provide a welcome injection of investment into Saudi Arabia’s power market, which has seen a sharp slowdown in contract awards this year.
Saudi Power Procurement Company’s four Group 1 storage service agreements, announced last week, are worth more than $1.16bn and cover 2,000MW of capacity.
That is significant against the wider market. According to regional project tracker MEED Projects, Saudi Arabia recorded $19.7bn in power sector contract awards in the first seven months of 2025, compared with just $2.5bn in new awards in the same period this year.
The battery energy storage system (bess) awards therefore account for a sizeable share of the activity recorded so far this year and provide a much-needed source of new contracting activity.
Importantly, this is not a one-off. SPPC issued the request for proposal (RFP) for its second group of bess projects in July, covering six projects with a combined capacity of 3,000MW and 12,000MWh.
With the Group 1 tender taking around 18 months from RFP to contract award, it is reasonable to expect Group 2 contracts to be signed in 2027.
At the same time, the awards for six independent renewable plants under Round 7 of Saudi Arabia’s National Renewable Energy Programme (NREP), with a combined capacity of 5,300MW, are also likely to move into next year, with the latest bid deadlines now extending into September.
Although a substantial pipeline remains in procurement, it is only once these projects move from tender to award and into construction that this pipeline translates into market activity.
It is important that these tenders continue to progress at the pace established by the early rounds of Saudi Arabia’s renewable energy programme and now also SPPC’s independent storage provider bess scheme.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18962923/main.jpg -
Qatar receives bids for major power grid expansion24 August 2026

Qatar General Electricity & Water Corporation (Kahramaa) has received bids for several packages under a major power transmission expansion project tendered in April.
The project covers new substations at multiple voltage levels, as well as the supply and installation of 400kV extra-high-voltage power cables. The overall scheme is estimated to cost $650m.
It is being tendered as part of Kahramaa’s 2026 procurement plan, which includes 198 tenders with a total estimated value of QR21.4bn ($5.9bn).
According to sources, bids were submitted for the following packages on 20 August:
- Substation packages S1 and S2, covering new 132/11kV substations (estimated cost: $200m)
- Package S3, covering new 66/11kV substations ($50m)
- Package S4, including a new 400/220/132kV substation, as well as upgrades and modifications to existing 400kV and 220kV substations ($200m)
- Package S5, covering new 132/11kV substations and upgrades to existing 132kV and 66kV substations ($100m)
- Cable packages C1 and C2, covering 400kV cables ($100m)
Kahramaa previously stated that foreign companies not registered in Qatar would be allowed to participate in the bidding, subject to meeting specified conditions, including registration and certification requirements.
In June, the electricity and water utility awarded contracts worth more than QR2.2bn ($604m) to expand the electricity transmission network in the country’s western region.
The engineering, procurement and construction (EPC) works will support the integration of the 2GW Dukhan solar power project into Qatar’s national electricity grid. The scope includes new and upgraded substations, as well as the installation of underground cables and overhead transmission lines.
Kahramaa said contracts were awarded to local firm Voltage Engineering, Turkiye’s Best & Betas Consortium, India’s Larsen & Toubro and South Korea’s LS Cable.
Of Kahramaa’s 2026 procurement plan, electricity transmission projects account for QR8.9bn ($2.4bn) and include the construction of new 400/132kV substations in Al-Wukair and Al-Mashaf, as well as the expansion of 400kV substations at Ras Laffan.
These also cover the installation of 132kV underground cables between Al-Sailiya and Al-Rayyan over a 24-kilometre route, as well as upgrades to the 400kV and 220kV networks.
Additionally, there are 64 planned electricity distribution projects managed by the Electricity Distribution Department that cover the medium-voltage and low-voltage networks throughout Doha and the regional municipalities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18962223/main.jpg -
Maaden closes $1bn term loan and credit facility24 August 2026
Saudi Arabian Mining Company (Maaden) has announced the closing of its inaugural international syndicated term loan and revolving credit facilities, worth a total of $1bn.
The $500m international term loan facility will support Maaden’s growth agenda and general corporate purposes, including funding growth projects across its portfolio.
The $500m international revolving credit facility, which is expected to remain undrawn, provides additional committed funding capacity “as Maaden continues to scale its business and execute its long-term growth strategy”.
The transaction “was met with strong support from the international banking market, attracting participation from a diverse group of leading international banks across key global financial markets”, including the US, Canada, Europe, China and Japan. The facilities were oversubscribed, Maaden said.
ALSO READ: Maaden and Aramco sign deal to create joint venture
“The level of demand reflects the global banking community’s confidence in Maaden’s financial strength, strategic direction and ambitious growth plans,” the Saudi state miner said in its statement.
“The facilities mark another significant milestone in Maaden’s funding journey – further diversifying its sources of funding and broadening its access to global capital providers as the company continues to advance its long-term growth ambitions.
“Maaden continues to make significant progress across its growth pipeline, expanding production, advancing major projects and accelerating exploration as it builds a world-class mining company at the heart of Saudi Arabia’s economic transformation.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/18962086/main4516.jpg -
Dubai inflation slows to 5.3% in July24 August 2026
Dubai’s annual inflation rate slowed to 5.3% in July, down from 5.7% in June, as a decline in transport costs eased pressure on consumer prices, according to Emirates NBD.
The bank said the slowdown supported its view that price growth peaked at mid-year, and it expects inflation to continue easing through the rest of 2026. Monthly price growth slowed to 0.1% in July, from 0.4% in June, the weakest pace since February.
Transport was the clearest sign of the moderation. Annual price growth in the category slowed to 11.9% in July, from 18.1% in June, as transport costs fell 3.7% over the month. Fuel and lubricant inflation eased to 24.1% year on year, from 48.3%, tracking a decline in local petrol prices.
Petrol remains the main swing factor in the emirate’s inflation. Transport contributed 1.1 percentage points to headline inflation in July, down from 1.7 percentage points in June. Emirates NBD said the relief may prove temporary, with Super 98 petrol prices climbing 5.9% in August to leave them 33.8% higher than a year earlier. The bank expects headline inflation to edge higher in the August figures before easing again later in the year.
The UAE deregulated petrol and diesel prices in 2015 and reviews them monthly against global prices, meaning changes in global fuel costs pass through to consumers quickly. Transport, which includes fuel, accounts for 9% of Dubai’s consumer price index basket.
Housing remained the largest contributor to inflation even as its impulse faded. Housing and utilities, which account for about two-fifths of the basket, added 2.8 percentage points to headline inflation. Annual price growth in the category slowed to 7.0%, from 7.4% in January.
Food inflation edged up to 7.8% year on year, from 7.6% in June, which the bank attributed to lingering supply-chain disruption from the regional conflict. Inflation in restaurants and hotels accelerated to 4.5% year on year, from 1.7% in June.
Emirates NBD forecasts inflation of 2.9% by year-end but said risks to that projection were tilted to the upside, given lingering pressures in food and housing.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18961735/main1839.jpg -
Libya oil project on track for 2027 completion24 August 2026

The project to develop a workers’ camp at Libya’s Erawin oil field is on track for completion next year, according to industry sources.
The project, estimated to be worth about $50m, is being executed by the Libyan oil services company Al-Saraya Al-Hamara, headquartered in the city of Sebha.
The Libyan company was awarded the contract in February 2025.
The scope of the project includes:
- Construction of an accommodation camp
- Construction of the camp maintenance warehouse
- Construction of the camp office
- Construction of a fire brigade shelter
- Construction of a kitchen and mess hall
- Construction of a mosque
- Construction of a laundry room
- Construction of a clinic
- Construction of parking facilities
- Installation of a fire and gas system
- Installation of a power generator
- Construction of associated facilities
The client on the project is Zallaf Libya Oil & Gas Exploration & Production Company.
Zallaf Libya Oil & Gas Exploration & Production Company was established in Libya in 2013 and is wholly owned by Libya’s state-owned National Oil Corporation.
The Erawin field development project is located about 800 kilometres south of Tripoli and 100km southwest of the El-Sharara field.
Libya shipped its first cargo of crude from the Erawin oil field in November 2023.
The shipment departed from Libya’s Zawiyah port and consisted of 600,000 barrels of crude.
Australia-based Worley Parsons was appointed as the front-end engineering and design (feed) contractor for the early production facility project in 2019.