Jeddah plans $31bn airport expansion

29 May 2023

 

Register for MEED’s guest programme 

Jeddah Airports Company (Jedco) plans to transform King Abdulaziz International airport (KAIA) into one of the world’s largest airports with a SR115bn ($31bn) expansion plan that will increase its capacity to 114 million passengers a year.

The largest components of the plan cover the design and expansion of Terminal 1 and the construction of a new passenger terminal to be called Terminal 2.

The expected completion date for the expansion project is 2031.

Terminal plans

The Terminal 1 project comprises basic infrastructure and enabling works, the installation of new gates, air bridges and parking aprons, the extension of the automatic people mover, new baggage conveyor systems and lounges, with the goal of increasing annual passenger capacity by 15 million.

Work on the multibillion-dollar scheme is scheduled to start this year, with completion targeted for 2026.

The Terminal 2 project aims to increase the airport’s total capacity to 114 million passengers a year, almost tripling the airport’s 40 million limit today.

Due to start in 2026 and end by 2031, the project will involve constructing a completely new terminal building with dozens of gates, new taxiways, aprons, roads, utilities, and baggage handling and other software systems. It is likely to be worth in excess of $10bn to build.

Jedco is also planning to construct a fourth runway starting in 2025 and completing by 2029 to cope with the increased traffic. Due to space limitations, the new runway will require substantive infrastructure relocation work to accommodate it.

Passenger traffic-focused developments are not the only element of the plan. As part of growing the airport’s commercial proposition, the client is also due to start developing a new logistics area later this year.

Covering more than 3 square kilometres, the facility will house new customs and service buildings as well as several leasable warehouses for the private sector. Construction of the facilities will be implemented in phases with an ultimate scheduled completion date of 2029.

Concurrently, Jedco is building a new Hajj and Umrah terminal. Pilgrims comprise a large portion of passenger traffic, and the new arrivals and departures hall for budget airlines will be able to handle 15 million passengers a year. The project is expected to be completed by 2025.

Another project starting this year is the construction of a new baggage handling facility to expand the airport’s existing capacity. The building will be located next to Terminal 1 and will be integrated with the existing conveyor belt systems.

Passenger demand

The project investment programme is a result of Jedco’s forecast that annual demand will reach 114 million passengers by 2030. Of this figure, the authority estimates 51 million will come from Saudi Arabian Airlines, 21 million from international airlines, and 13 million and 12 million from budget airlines Flynas and Flyadeal, respectively.

The forecast and plans were created in conjunction with key drivers of future passenger demand in the Mecca and Jeddah region, including gigaproject real estate developers Roshn and Uptown Jeddah, air cargo handler Saudi Logistics Services (SAL), and the General Civil Aviation Authority (Gaca) with its subsidiary Matarat Holding. Engineering firms Atkins, Mace and DGJ also inputted into the process. The three companies are the consultants on the capital projects investment plan.

KAIA has three operational terminals. Opened in 2018, Terminal 1 is one of the world’s largest passenger terminals, and caters primarily for the state carrier and domestic flights. The North Terminal handles international airlines, while the Hajj Terminal is dedicated to pilgrim traffic.

Construction work on KAIA has been a key driver of airport-building activity in Saudi Arabia in the past. In 2010, there were over $7bn of contract awards for work at the airport, marking the most active year for airport construction activity on record, according to regional projects tracker MEED Projects.

There are other major airport projects planned in Saudi Arabia. In November, Saudi Arabia’s Crown Prince Mohammed bin Salman bin Abdulaziz al-Saud announced the masterplan for King Salman International airport in Riyadh. If completed on time in 2030, it will become the largest airport in the world in terms of passenger capacity.

The airport aims to accommodate up to 120 million passengers by 2030 and 185 million by 2050. For cargo, the goal is to process 3.5 million tonnes a year by 2050.

Neom airport

Another major airport is planned for Neom. US firm Aecom confirmed on 22 March that it had been awarded a contract to provide project management consultancy (PMC) services for the new airport project.

The airport will be inland, close to the Tabuk end of the 170-kilometre-long Line development. Neom International airport is separate from the Neom Bay airport, which started receiving commercial flights in 2019.

Although not confirmed, it is understood that the first phase of the airport will have the capacity to handle 25 million passengers a year. A second phase could take the capacity up to 50 million passengers a year. There is an aspiration for the airport to become the largest in the world, with a capacity of 100 million passengers a year. 

Regional airports

Smaller domestic airports are also being developed. In March, Matarat signed a three-year contract with France’s Egis Group to provide technical support and project management services for 26 regional airports.

The contract aims to establish phased project management portals, update airport project management policies and procedures, and provide technical support for planning and designing.

The contract also involves following up on the implementation of capital projects with Matarat subsidiaries, including Riyadh Airports Company, Jeddah Airports, Dammam Airports and Cluster2. 

https://image.digitalinsightresearch.in/uploads/NewsArticle/10893610/main4549.jpg
Edward James
Related Articles
  • Joint venture wins $246m RCRC bridges contract

    16 October 2026

     

    A joint venture of local contractor Mofarreh Group and Turkey-based Gulsan Holding has won an estimated SR923m ($246m) contract from the Royal Commission for Riyadh City (RCRC) to construct a series of grade-separated steel flyovers across the capital.

    The contract, known as Package 2 (Groups 2 and 3), is part of RCRC’s urgent bridges programme under the wider project to build steel bridges at 10 junctions across Riyadh.

    The works have a 12-month execution timeline to fast-track traffic decongestion across major arterial corridors.

    The joint venture’s scope covers the engineering and construction of grade-separated steel bridge interchanges across seven key intersections:

    • IC04: Al-Khair Road and King Salman Bin Abdulaziz Road
    • IC05: Prince Turki Road and Imam Saud Road
    • IC06: Al-Takhassosi Road and Saeed Al-Sulami Road
    • IC07: Khurais Road and Al-Hareth Bin Abdullah Road
    • IC08: Khurais Road and Ash-Sharq Road
    • IC09: Khurais Road and Marmar Road
    • IC10: Al-Kharj Road and Al-Hilla Road

    The total length of the flyovers is 8.86 kilometres, excluding Junction IC10.

    In addition to the structural steel superstructures, concrete bridge foundations, decks and approach ramps, the contract includes retaining walls, utility diversions, temporary phased traffic arrangements, associated roadworks, drainage networks, roadway lighting, intelligent transportation systems and landscaping.

    The client received commercial proposals from several local and international contractors. Other bidders included:

    • Masco
    • Nesma & Partners
    • Al-Omaier Trading & Contracting Company 
    • Yuksel Saudia 
    • Batco 
    • Modern Building Leaders
    • Sapac

    The urgent bridges initiative is part of Riyadh’s rapid transport infrastructure programme to improve traffic throughput, enhance safety and ease vehicular congestion across central and ring-road corridors ahead of major events, including Expo 2030 and the 2034 Fifa World Cup.

    In July, Mofarreh Group and Turkiye’s Gulsan Holding formed a joint venture to bid for and deliver transport infrastructure projects in Riyadh for RCRC.

    The joint venture said it will target road, bridge, viaduct and interchange projects.

    Mofarreh will provide local market access and operational capacity, while Gulsan will contribute international experience in large-scale transport projects.

    The companies said the new venture will support knowledge transfer and localisation, and promote the use of international engineering and construction standards aligned with Saudi Arabia’s Vision 2030 infrastructure and sustainability goals.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20663255/main.png
    Yasir Iqbal
  • Humain tenders 100MW Riyadh AI data centre

    16 October 2026

    Saudi artificial intelligence infrastructure developer Humain has issued a request for proposals for an engineering, procurement and construction (EPC) contract to deliver a 100MW artificial intelligence (AI) data centre facility in Riyadh’s Al-Saad area.

    The tender was issued on 17 September, with bids due by 8 November.

    The contract includes core-and-shell works; civil works; mechanical, electrical and plumbing installation; testing and commissioning; and site infrastructure across a 350,200-square-metre plot.

    The project also includes an optional expansion phase that could raise total site capacity to 200MW.

    The initial 100MW development is split into two equal 50MW phases, structured across two single-storey IT buildings housing four 25MW data halls.

    Phase one targets a ready-for-service date by October 2028, followed by phase two in January 2029.

    Under the optional phase three, an additional 100MW facility would be brought online by July 2029.

    The data centre will be designed to support high-density graphics processing unit clusters and AI-compute workloads, with rack densities of 240kW to 250kW.

    The facility will be built to Uptime Institute Tier III topology and LEED Silver standards as a baseline, targeting LEED Gold.

    The operational design targets an annualised power usage effectiveness below 1.35.

    Power will be delivered through four 33kV connections supplied by Saudi Electricity Company from two separate high-voltage/medium-voltage primary substations. The scope requires 15 transformers, 15 static 2,250kW IT uninterruptible power supply (UPS) units, and 450kW mechanical UPS systems with lithium-ion battery storage for each 25MW block. 

    Backup emergency diesel generators will be provided on an owner-furnished, contractor-installed basis, with the EPC contractor handling their installation, connection and testing. Fuel storage will provide 24 hours of autonomous run-time, split between on-site underground bulk tanks and generator belly tanks.

    Thermal management combines air and liquid cooling. High-density server racks will be equipped with direct-to-chip liquid cooling loops using coolant distribution units and technical water distribution, paired with air-cooled chillers operating in dual high- and low-temperature loops, alongside fan-wall units.

    The total construction timeline is capped at 25 months from site handover or contract signing, with pre-execution early mobilisation scheduled to start in January 2027.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20661045/main.jpg
    Yasir Iqbal
  • Construction progresses at Iraq oil refinery

    16 October 2026

     

    Construction is progressing on Iraq’s $800m Al-Diwaniyah oil refinery expansion project, according to industry sources.

    The project’s main contract was awarded to Iraq’s Al-Barham Group in January 2025 under an engineering, procurement, construction and commissioning model.

    The scope has been split into two phases.

    Phase one focuses on the development of:

    • A crude distillation unit (CDU)
    • A liquid petroleum gas complex
    • Utilities
    • Offsites and gantry systems

    Phase two focuses on the development of:

    • A naphtha hydrotreater
    • An isomerisation unit
    • A fixed bed platforming (FBP) unit, licensed from Honeywell UOP

    An FBP unit is a type of catalytic reforming unit used in refineries to convert low-octane naphtha into high-octane reformate that can be blended into gasoline.

    The client on the project is state-owned Midland Refineries Company and Iraq’s Ministry of Oil.

    The CDU will have the capacity to process 70,000 barrels a day (b/d), while the gasoline complex will have the capacity to process 18,000 b/d.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20636740/main.jpg
    Wil Crisp
  • Adnoc steps up crude expansion

    15 October 2026

     

    Abu Dhabi National Oil Company (Adnoc Group) is entering a new phase of upstream investment as the UAE’s withdrawal from Opec opens the way for greater oil production flexibility. After spending an estimated $37bn on upstream projects in 2023 and 2024, the state-owned energy company continues to invest heavily in expanding crude production capacity and developing domestic gas supplies.

    The investment programme supports two key targets: raising crude production capacity to 5 million barrels a day (b/d) by 2027 and achieving gas self-sufficiency by the end of the decade.

    Following the UAE’s withdrawal from Opec in May 2026, Adnoc Group has nearly matched its 2024 upstream project spending level so far this year and is on course to surpass it by a significant margin.

    The UAE had invested billions of dollars in expanding crude production capacity, but output quotas under the Opec+ framework had constrained its ability to translate that capacity into higher production and additional oil revenues in a high-price environment.

    The UAE’s exit from Opec gives Adnoc greater flexibility to utilise its spare capacity, accelerate progress towards its 5 million b/d target and potentially exceed it. The company is positioning itself to capitalise on rising oil demand while retaining the flexibility to respond to market conditions.

    Robust offshore spending

    So far this year, Adnoc Offshore has awarded major contracts for projects involving the Satah Al-Razboot (Sarb) deep gas development, the expansion of the Nasr oil field and an increase in the Upper Zakum oil field’s output capacity to 1.5 million b/d.

    Adnoc reached a final investment decision (FID) on the Sarb project in January and awarded the main engineering, procurement and construction (EPC) contract to US-based McDermott International. The contract is estimated to be worth around $500m, sources told MEED.

    The project is expected to deliver 200 million cubic feet a day (cf/d) of gas by the end of the decade – enough to power more than 300,000 homes.

    The scope includes the EPC of an offshore wellhead tower with four gas production wells, which will be connected to Das Island for processing through Adnoc Gas facilities. The works also include the installation of pipelines and intra-field connections linking the Sarb field to Das Island.

    Also in January, Adnoc Offshore awarded McDermott a $942m contract for the Nasr-115 project, which will increase production capacity at the Nasr offshore field to 115,000 b/d. The field is located about 130 kilometres northwest of Abu Dhabi.

    McDermott’s scope covers engineering, procurement, construction and installation services for two topside structures, a new manifold tower, a jacket, a bridge, associated pipelines, subsea cables and brownfield modifications.

    UZ 1.5MMBD project

    Located 84km offshore Abu Dhabi, Upper Zakum is the world’s second-largest offshore oil field and fourth-largest oil field overall. The UZ 1.5MMBD project is Adnoc Offshore’s latest crude production expansion scheme at the Upper Zakum field.

    The project scope is divided into three packages. The first EPC package covers surface facilities required on the field’s existing artificial islands, including integrated gas-lift compressors, produced-water reinjection units, water treatment plants, pre-assembled manifolds and related facilities.

    The second package covers offshore facilities and comprises several segments of subsea pipelines and subsea cables.

    The third package covers work on Adnoc’s existing Zirku Island and will require additional oil tanks, a water treatment unit, an export gas compressor, a condensate treatment unit, and associated power and utilities facilities.

    Adnoc Offshore awarded the first and third EPC packages of the UZ 1.5MMBD project to Spanish contractor Tecnicas Reunidas, while Abu Dhabi-based NMDC Energy won the second package. The overall scheme is estimated to be worth more than $10bn.

    Umm Shaif Gas Cap

    Gas production has also been a key capex area this year, with Adnoc and its foreign partners reaching a $6.2bn FID in July for a major project to produce up to 600 million cf/d of natural gas by developing the Umm Shaif Gas Cap in Abu Dhabi.

    The Umm Shaif Gas Cap reserve lies within the offshore Umm Shaif and Nasr hydrocarbons concession, in which Adnoc is the majority stakeholder. Other stakeholders in the concession are Italy’s Eni, France’s TotalEnergies and China National Petroleum Corporation.

    Adnoc said the FID includes three EPC packages totalling $5.1bn for large-scale offshore infrastructure, awarded to the following contractors:

    • First offshore package – fabrication of a 30,000-tonne gas compression system: Larsen & Toubro Energy Hydrocarbon (India) / Lamprell (Saudi Arabia/UAE)
    • Second offshore package – fabrication of another 30,000-tonne gas compression system: McDermott (US)
    • Onshore package – EPC of gas inlet and processing systems on Das Island: China Petroleum Engineering & Construction Company (CPECC)

    As part of the FID, Adnoc also awarded a $365m contract to its subsidiary Adnoc Drilling for a 14-well drilling and integrated drilling services scope, to be delivered over 18 months using three existing rigs.

    Separate from the Umm Shaif Gas Cap development, Adnoc Offshore is preparing to issue the main tender for the next expansion phase of the Umm Shaif oil and gas field offshore Abu Dhabi.

    Contractors expressed interest to Adnoc Offshore in June in participating in the main tendering exercise for the Umm Shaif long-term development plan 2.1 (LTDP-2.1) project.

    The project’s primary objective is to maintain Umm Shaif’s oil production capacity at approximately 390,000 b/d, while enabling peak output of up to 430,000 b/d.

    The project includes constructing a new combined artificial island at Umm Shaif, equipped with drilling, processing, utilities and supporting infrastructure. It also includes installation of an optimised crude-stabilisation train at Adnoc’s existing Das Island facilities.

    Located about 150km northwest of Abu Dhabi city, Umm Shaif is one of Adnoc’s oldest offshore oil-producing assets. In 2022, the company marked the 60th anniversary of the UAE’s first export of Umm Shaif crude, which took place in July 1962.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20634497/main.gif
    Indrajit Sen
  • Joint venture wins Oman desalination contract

    15 October 2026

    Bahwan Veolia Water, a joint venture of France’s Veolia and Oman’s Bahwan Engineering Company, has signed a five-year operations and maintenance (O&M) contract for the Al-Asilah desalination plant in the sultanate.

    The Al-Asilah plant has a production capacity of 80,000 cubic metres a day and helps supply drinking water to about 600,000 residents across South Al-Sharqiyah governorate. It also has an on-site solar farm to support lower-carbon water production.

    The plant entered commercial operation in January 2022 under a build-own-operate arrangement. A consortium of Bahwan Engineering and Japan-headquartered JGC Corporation developed it.

    South Korea’s Doosan Heavy Industries & Construction, now known as Doosan Enerbility, carried out the engineering, procurement and construction (EPC) works.

    Oman’s first independent water project (IWP), the Sur IWP, also serves residents in Al-Sharqiyah governorate.

    The main contract for the project was awarded in 2007, with Veolia carrying out EPC works and acting as shareholder in Sharqiyah Desalination Company, which owns the plant.

    Bahwan Veolia Water signed a 22-year O&M agreement for the project that same year.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20631273/main.jpg
    Mark Dowdall