Jeddah plans $31bn airport expansion

29 May 2023

 

Register for MEED’s guest programme 

Jeddah Airports Company (Jedco) plans to transform King Abdulaziz International airport (KAIA) into one of the world’s largest airports with a SR115bn ($31bn) expansion plan that will increase its capacity to 114 million passengers a year.

The largest components of the plan cover the design and expansion of Terminal 1 and the construction of a new passenger terminal to be called Terminal 2.

The expected completion date for the expansion project is 2031.

Terminal plans

The Terminal 1 project comprises basic infrastructure and enabling works, the installation of new gates, air bridges and parking aprons, the extension of the automatic people mover, new baggage conveyor systems and lounges, with the goal of increasing annual passenger capacity by 15 million.

Work on the multibillion-dollar scheme is scheduled to start this year, with completion targeted for 2026.

The Terminal 2 project aims to increase the airport’s total capacity to 114 million passengers a year, almost tripling the airport’s 40 million limit today.

Due to start in 2026 and end by 2031, the project will involve constructing a completely new terminal building with dozens of gates, new taxiways, aprons, roads, utilities, and baggage handling and other software systems. It is likely to be worth in excess of $10bn to build.

Jedco is also planning to construct a fourth runway starting in 2025 and completing by 2029 to cope with the increased traffic. Due to space limitations, the new runway will require substantive infrastructure relocation work to accommodate it.

Passenger traffic-focused developments are not the only element of the plan. As part of growing the airport’s commercial proposition, the client is also due to start developing a new logistics area later this year.

Covering more than 3 square kilometres, the facility will house new customs and service buildings as well as several leasable warehouses for the private sector. Construction of the facilities will be implemented in phases with an ultimate scheduled completion date of 2029.

Concurrently, Jedco is building a new Hajj and Umrah terminal. Pilgrims comprise a large portion of passenger traffic, and the new arrivals and departures hall for budget airlines will be able to handle 15 million passengers a year. The project is expected to be completed by 2025.

Another project starting this year is the construction of a new baggage handling facility to expand the airport’s existing capacity. The building will be located next to Terminal 1 and will be integrated with the existing conveyor belt systems.

Passenger demand

The project investment programme is a result of Jedco’s forecast that annual demand will reach 114 million passengers by 2030. Of this figure, the authority estimates 51 million will come from Saudi Arabian Airlines, 21 million from international airlines, and 13 million and 12 million from budget airlines Flynas and Flyadeal, respectively.

The forecast and plans were created in conjunction with key drivers of future passenger demand in the Mecca and Jeddah region, including gigaproject real estate developers Roshn and Uptown Jeddah, air cargo handler Saudi Logistics Services (SAL), and the General Civil Aviation Authority (Gaca) with its subsidiary Matarat Holding. Engineering firms Atkins, Mace and DGJ also inputted into the process. The three companies are the consultants on the capital projects investment plan.

KAIA has three operational terminals. Opened in 2018, Terminal 1 is one of the world’s largest passenger terminals, and caters primarily for the state carrier and domestic flights. The North Terminal handles international airlines, while the Hajj Terminal is dedicated to pilgrim traffic.

Construction work on KAIA has been a key driver of airport-building activity in Saudi Arabia in the past. In 2010, there were over $7bn of contract awards for work at the airport, marking the most active year for airport construction activity on record, according to regional projects tracker MEED Projects.

There are other major airport projects planned in Saudi Arabia. In November, Saudi Arabia’s Crown Prince Mohammed bin Salman bin Abdulaziz al-Saud announced the masterplan for King Salman International airport in Riyadh. If completed on time in 2030, it will become the largest airport in the world in terms of passenger capacity.

The airport aims to accommodate up to 120 million passengers by 2030 and 185 million by 2050. For cargo, the goal is to process 3.5 million tonnes a year by 2050.

Neom airport

Another major airport is planned for Neom. US firm Aecom confirmed on 22 March that it had been awarded a contract to provide project management consultancy (PMC) services for the new airport project.

The airport will be inland, close to the Tabuk end of the 170-kilometre-long Line development. Neom International airport is separate from the Neom Bay airport, which started receiving commercial flights in 2019.

Although not confirmed, it is understood that the first phase of the airport will have the capacity to handle 25 million passengers a year. A second phase could take the capacity up to 50 million passengers a year. There is an aspiration for the airport to become the largest in the world, with a capacity of 100 million passengers a year. 

Regional airports

Smaller domestic airports are also being developed. In March, Matarat signed a three-year contract with France’s Egis Group to provide technical support and project management services for 26 regional airports.

The contract aims to establish phased project management portals, update airport project management policies and procedures, and provide technical support for planning and designing.

The contract also involves following up on the implementation of capital projects with Matarat subsidiaries, including Riyadh Airports Company, Jeddah Airports, Dammam Airports and Cluster2. 

https://image.digitalinsightresearch.in/uploads/NewsArticle/10893610/main4549.jpg
Edward James
Related Articles
  • UAE firm acquires majority stake in African power producer

    31 August 2026

    Abu Dhabi-based ePointZero has announced a deal to acquire a 90% stake in pan-African independent power producer Azura Power Holdings.

    The transaction will give the subsidiary of UAE investment group 2PointZero control of 752MW of operating power generation capacity across Nigeria, Senegal and Mozambique.

    The company will acquire the respective stakes held by existing shareholders Actis and Africa50 through an acquisition vehicle established with Amaya Capital, an Africa-focused investment firm based in London.

    Amaya Capital founded Azuro Power in 2010 and will retain a 10% minority stake in the company, which also has a development pipeline of more than 1.5GW of planned power projects.

    The pipeline includes expansions at existing sites, as well as new gas and renewable energy projects and battery energy storage systems.

    Azuro Power’s operating portfolio comprises the 461MW Azura-Edo power plant in Nigeria, the 116MW Tobene power plant in Senegal and the 175MW Central Termica de Ressano Garcia plant in Mozambique. The company’s operating assets generate around 10% of each country’s grid baseload power, the statement said.

    The company’s projects have received financing and support from development finance institutions including the World Bank, British International Investment, German Investment & Development Company, the US International Development Finance Corporation, the Dutch entrepreneurial development bank, the International Finance Corporation, the Multilateral Investment Guarantee Agency and France’s Proparco.

    The deal, subject to regulatory approvals and other customary closing conditions, marks ePointZero’s entry into African power generation and follows the acquisition of a 20% stake in Egypt’s Elsewedy Electric in 2024.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19171095/main.jpg
    Mark Dowdall
  • Contract award nears for Saudi Landbridge Riyadh section

    31 August 2026

     

    Saudi Arabia Railways (SAR) is preparing to award the main construction contract for the design-and-build of the Riyadh Rail Link, a new north-to-south railway line across the capital.

    MEED understands that the commercial proposals were opened two weeks ago, with a decision expected imminently.

    SAR began the post-tender clarifications with bidders in July, as MEED reported.

    The bidders include:

    • China Civil Engineering Construction Corporation / Al-Ayuni Investment & Contracting (China/local)
    • Nesma & Partners / China Harbour Engineering Company (local/China)
    • Al-Rashid Trading & Contracting / IC Ictas Construction / Saipem (local/Turkiye/Spain)
    • Saudi Binladin Group (local)

    In June, MEED exclusively reported that contractors submitted their commercial proposals on the 30th of that month.

    The scope includes a 35-kilometre double-track line connecting SAR’s North-South Railway to the Eastern Railway network.

    Issued on 29 January, the tender also covers the procurement, construction and installation of associated infrastructure, including viaducts, civil works, utility diversions/installations, signalling systems and other related works.

    Once delivered, the Riyadh Rail Link is expected to become a key component of the Saudi Landbridge railway.

    In January, SAR said it would deliver the Saudi Landbridge project through a “new mechanism” by 2034, after failing to reach an agreement with a Chinese consortium to construct it, as MEED reported.

    In an interview with local media, SAR CEO Bashar Bin Khalid Al-Malik said the consortium failed to meet local content requirements, and that the project would instead be delivered in several phases under a different procurement model.

    Negotiations have been under way between Saudi Arabia and China-backed investors interested in developing the scheme through a public-private partnership (PPP). Al-Malik put the project cost at about SR100bn ($26.6bn).

    Overall, it comprises more than 1,500km of new track. A core element is a 900km railway between Riyadh and Jeddah, providing the capital with direct freight access to King Abdullah Port on the Red Sea.

    Other key elements include upgrading the existing Riyadh-Dammam line, a bypass around the capital known as the Riyadh Link, and a connection between King Abdullah Port and Yanbu.

    The Saudi Landbridge is one of the kingdom’s most anticipated project programmes. First announced in 2004, it was put on hold in 2010 before being revived a year later. Rights-of-way issues, route alignment and the high cost have been among the main stumbling blocks.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19161887/main.gif
    Yasir Iqbal
  • Prequalification begins for Dammam suburb boulevard PPP

    31 August 2026

    Saudi Arabia’s Ministry of Municipalities & Housing, in collaboration with Ashraq Development Company and the National Centre for Privatisation & PPP, has issued a request for qualification (RFQ) notice for the development of the King Fahd suburb boulevard project in Dammam.

    The notice was issued on 27 August, with a submission deadline of 22 October.

    The public-private partnership (PPP) project will be delivered using a design, build, finance, operate, maintain and transfer model, with a 43-year contract term.

    The project is located in Al-Bayda Governorate and features a 4 kilometre (km) mixed-use zone along a central boulevard, forming part of a larger 7.3km corridor.

    The project will be developed in two phases and span about 1 million square metres.

    According to a statement: “The private sector partner will be responsible for developing and operating the boulevard, which includes leisure and recreational facilities, public parks, entertainment venues, retail outlets, office spaces, hospitality zones, pedestrian walkways and road networks.”

    The project is the latest addition to the growing number of PPP projects in the kingdom. 

    In January, Saudi Arabia launched a national privatisation strategy aimed at mobilising $64bn in private sector capital by 2030.

    Building on the privatisation programme first introduced in 2018, the strategy focuses on unlocking state-owned assets for private investment and privatising selected government services.

    In a statement, NCP said the strategy comprises 147 opportunities drawn from a broader pipeline of more than 500 projects across 18 sectors.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19160560/main.jpg
    Yasir Iqbal
  • Contractors submit bids for Kuwait power transmission works

    31 August 2026

     

    Kuwait’s Public Authority for Housing Welfare (PAHW) has received bids for two tenders covering power transmission works at the South Saad Al-Abdullah residential development.

    The first tender covers the supply, installation and maintenance of 10 main 132/11kV transformer substations for the third phase of the development. 

    According to sources, five contractors submitted bids on 26 August. The local Sayed Hamid Behbehani & Sons made the lowest offer of $104.2m.

    The bids include:

    • Sayed Hamid Behbehani & Sons: $104.2m (Kuwait)
    • Industrial Electrical Projects (IEP): $111.5m (Kuwait)
    • Larsen & Toubro: $114m (India)
    • Oman National Engineering & Investment: $118m (Oman)
    • National Contracting Company: $126m (Saudi Arabia)

    The second PAHW tender covers the supply, installation and maintenance of 10 main 132/11kV transformer substations for the fourth phase of the project. 

    According to sources, five contractors also submitted bids on 26 August, with A-Ahleia Switchgear making the lowest offer of $103.3m.

    The bids include:

    • Al-Ahleia Switchgear: $103.3m (Kuwait)
    • Industrial Electrical Projects (IEP): $111.7m (Kuwait)
    • Larsen & Toubro: $114m (India)
    • Oman National Engineering & Investment: $118.3m (Oman)
    • National Contracting Company: $126m (Saudi Arabia)

    Both projects were initially tendered in May. As reported by MEED, PAHW previously issued addendums for both substation tenders, revising the qualification requirements for bidders.

    According to the revised requirements, contractors must be approved by Kuwait’s Ministry of Electricity, Water & Renewable Energy and have experience supplying and installing at least 10 132kV substations in Kuwait.

    The addendums also introduced requirements related to transformer and gas-insulated switchgear manufacturing approvals, as well as operational performance records for installed equipment.

    Sabah Al-Ahmad residential city

    Meanwhile, bids remain under evaluation for two 132kV underground cable tenders for the South Sabah Al-Ahmad residential development, tendered by PAHW in May.

    The first cable tender covers the supply, extension and maintenance of 132kV underground cables feeding eight main transformer substations serving the N1, N6 and N11 districts in the project’s fourth phase. 

    MEED previously reported that Egytech Cables, a subsidiary of Egypt’s Elsewedy Electric, was the lowest bidder with an offer of $42.37m.

    The second cable tender covers the supply, extension and maintenance of 132kV underground cables linked to substations serving the N5, N6, N8 and N10 districts in the project’s third phase. 

    Egytech Cables submitted the lowest offer of $39.95m. TBEA Shandong Luneng Taishan Cable submitted a bid of $41.89m, along with Riyadh Cables ($42.05m) and The Contractor General Trading & Contracting ($44.97m).

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19151780/main.jpg
    Mark Dowdall
  • Eni plans to drill 230 oil and gas wells in Egypt

    31 August 2026

    Italy’s Eni is planning to drill 230 new oil and gas wells in Egypt, according to a statement from the country’s Ministry of Petroleum & Mineral Resources.

    Eni’s chief executive, Claudio Descalzi, discussed his plans for exploration and development in Egypt on 25 August during a meeting with Egypt’s Prime Minister Mostafa Madbouly and the Minister of Petroleum and Mineral Resources Karim Badawi.

    During the meeting, Descalzi said that the company has plans to drill 30 exploration wells in addition to 200 development wells.

    Descalzi said his company plans to intensify its exploration and development programmes, especially in the Mediterranean and Western Sahara regions, to increase production of natural gas and crude oil.

    He said that his company plans to use the latest seismic imaging and artificial intelligence technologies as a key part of its exploration and development plans.

    In a separate statement, Eni also said that it is working with UK-headquartered BP and state-owned Egyptian General Petroleum Corporation (EGPC) to reach a final investment decision (FID) for a project to develop the major gas discovery of Denise West in Egypt’s Temsah concession.

    Eni made the discovery in February and says it holds about 2 trillion cubic feet of gas and 130,000 barrels of condensate.

    It is targeting first gas in less than two years and expects to reach FID “in the next few months”, according to its statement.

    Eni’s total investments in Egypt have reached a value of $8.5bn, according to the statement from Egypt’s Ministry of Petroleum & Mineral Resources.

    During the meeting on 25 August, Descalzi also stressed the importance of linking Cyprus’ Cronos gas field to Egyptian export infrastructure.

    In July, Eni reached the FID to develop the Cronos project in deep waters offshore Cyprus, targeting the first Cypriot gas to market in 2028.

    Production is expected to reach a plateau of 500 million standard cubic feet a day.

    In October last year, Egypt and Cyprus signed provisional agreements to connect Cyprus’ Cronos gas field to Egypt’s gas infrastructure.

    The agreements were signed by parties including Egypt’s Ministry of Petroleum and Mineral Resources, Eni, and the French oil and gas company TotalEnergies.

    Connecting the Cronos field to Egypt is expected to involve the tendering of a major subsea pipeline project.

    This will allow gas to be transported and processed in existing Zohr facilities in Egypt, then transferred and liquefied at the Damietta LNG plant for export as LNG to international markets, primarily Europe.

    At the meeting on 25 August, Descalzi said the planned project to connect the Cronos field to Egypt will be considered a model for regional cooperation in the gas sector and will enhance Egypt’s status as a regional gas hub.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19079059/main.jpg
    Wil Crisp