Iraq steps up post-war revival
13 May 2024
Latest news from Iraq’s construction and transport sectors:
> Iraq taps international consultant for Europe road
> Iraq to award metro projects by May
> Countries sign Iraq to Europe road agreement
> AD Ports signs agreement with Iraqi ports operator
> Iraq remains tough to sell
> Iraq approves new airport and steel plant projects
> Iraq confirms consultants for metro schemes

Recent signs of infrastructure project progress in Iraq have generated a renewed sense of optimism that certain major schemes may finally move ahead under the country’s post-war building initiatives.
Contract awards in Iraq’s construction and transport projects market reached $5bn in 2023, the highest value in the sector since 2012 and well above the average of $2.9bn over the past decade. The 2023 awards value was also a much-needed rebound from the disappointing value of just $1.4bn-worth of awards in the sector in 2022.
The sector has more generally been headed on a clear upward path, with awards averaging $3.4bn a year in the past five years (2019-23) compared to $2.4bn a year in the five years prior to that (2014-18).
Benefitting from higher oil prices and a period of relatively stable governance, Baghdad has shifted its focus to reconstructing and modernising Iraq’s deteriorating infrastructure.
The positive sentiment in the sector has been particularly buoyed by the robust 2023 budget, which outlined plans for substantial investments into transport, social infrastructure and housing initiatives.
Key infrastructure priorities for the country include advancing transport plans to capitalise on the expanding Al-Faw Port, including through the delivery of a north-to-south high-speed rail system—a proposal that has been under discussion for more than two decades.
Transport
As part of its 2023 budget, Baghdad approved 16 new projects, with an estimated value of nearly $17bn, for the development and construction of roads, bridges and overpasses in the capital.
The schemes are part of the first package of the master plan revealed in December that included 150 projects intended to modernise and expand infrastructure, address congestion, and improve access and security in central Baghdad and inside the Green Zone.
One of the first contracts to be awarded was the $55m contract to build the Al Zafaraniyah Bridge project, which the Ministry of Construction & Housing awarded to Lebanese contractor Setraco in August 2023.
In a strong positive sign for market activity, Iraq floated tender notices in February 2024 for a combined $4bn-worth of contracts to develop the Baghdad and Najaf-Karbala metro projects on a design, build, operate, maintain, finance and transfer basis.
In April 2024, the country further advanced its infrastructure plans by signing a memorandum of understanding (MoU) with Turkiye, Qatar and the UAE to establish a framework for implementing a 1,200km-long Development Road project from Al-Faw Port to Turkiye.
While previous false starts on ambitious transport schemes such as these have eroded investor confidence in the country, there appears to be some hope that Iraq may have reached a tipping point leading to the most recent revival of projects.
One smaller, but still strategically important, transport scheme in the works is the $200m project to rehabilitate and expand Baghdad International airport, which is due to be awarded in 2025. In February, Baghdad also approved the construction of the $800m Diwaniyah International airport.
As the $5.8bn Al-Faw Grand Port masterplan – one of Iraq’s most significant ongoing projects – nears completion in 2025 after a decade of delays, it is also especially critical that new projects proceed to market.
Housing initiatives
Despite past efforts to boost supply, the housing shortfall in Iraq remains critical, with three million homes needed urgently and presenting a supply gap that is increasingly problematic for the government.
Between 2016 and 2020, Iraq reported 971 reconstruction projects, of which 718 were completed.
Most recently, Iraq broke ground on the estimated $2bn Al-Jawahiri residential city project in Abu Ghraib, west of Baghdad. It selected East China Engineering Science & Technology Company and China National Chemical Engineering Company, in collaboration with the local Shams Al Binaa, as the main contractors for the project.
The Jawahiri project is part of a programme to construct five cities across Iraq, including Babil, Karbala, Nineveh and Anbar, to fill the country's housing shortages.
Continuing the Iraq Housing Programme, which aims to build 3 million residential units in the form of low-rise buildings and townhouses nationwide, also remains pivotal for driving future construction activity.
Projects pipeline
Iraq has a total of around $86bn-worth of project work in planning and pre-execution across its construction and transport sectors. This is split roughly evenly between the sectors, at $43bn each.
It is hard to estimate how much of this value consists of work that will likely go ahead soon. Much of the value is still at an early stage, though $30bn-worth of construction projects and $41bn-worth of projects in the transport sector have on paper proceeded past study.
The immediate outlook for transport projects seems optimistic as the government continues to focus on economic revitalisation through expansive infrastructure initiatives.
These projects hold the potential to attract investors, stimulate local employment opportunities and generate significant revenues. The specific allocation of funds for vital metro and airport projects will also likely boost investor confidence.
There nevertheless remains a pressing need for major investments across other project sectors, including energy, utilities, construction and transport, to fully address infrastructural requirements and spur economic growth.
MEED's June 2024 market focus on Iraq also includes:
> Al Sudani struggles to maintain Iraq’s political stability
> Iraq economic revival faces headwinds
> Iraq electricity sector makes slow progress
Exclusive from Meed
-
Saudi Arabia battery storage awards provide fresh lift24 August 2026
-
Qatar receives bids for major power grid expansion24 August 2026
-
Maaden closes $1bn term loan and credit facility24 August 2026
-
Dubai inflation slows to 5.3% in July24 August 2026
-
Libya oil project on track for 2027 completion24 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Saudi Arabia battery storage awards provide fresh lift24 August 2026
Commentary
Mark Dowdall
Power & water editorThe latest battery storage awards provide a welcome injection of investment into Saudi Arabia’s power market, which has seen a sharp slowdown in contract awards this year.
Saudi Power Procurement Company’s four Group 1 storage service agreements, announced last week, are worth more than $1.16bn and cover 2,000MW of capacity.
That is significant against the wider market. According to regional project tracker MEED Projects, Saudi Arabia recorded $19.7bn in power sector contract awards in the first seven months of 2025, compared with just $2.5bn in new awards in the same period this year.
The battery energy storage system (bess) awards therefore account for a sizeable share of the activity recorded so far this year and provide a much-needed source of new contracting activity.
Importantly, this is not a one-off. SPPC issued the request for proposal (RFP) for its second group of bess projects in July, covering six projects with a combined capacity of 3,000MW and 12,000MWh.
With the Group 1 tender taking around 18 months from RFP to contract award, it is reasonable to expect Group 2 contracts to be signed in 2027.
At the same time, the awards for six independent renewable plants under Round 7 of Saudi Arabia’s National Renewable Energy Programme (NREP), with a combined capacity of 5,300MW, are also likely to move into next year, with the latest bid deadlines now extending into September.
Although a substantial pipeline remains in procurement, it is only once these projects move from tender to award and into construction that this pipeline translates into market activity.
It is important that these tenders continue to progress at the pace established by the early rounds of Saudi Arabia’s renewable energy programme and now also SPPC’s independent storage provider bess scheme.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18962923/main.jpg -
Qatar receives bids for major power grid expansion24 August 2026

Qatar General Electricity & Water Corporation (Kahramaa) has received bids for several packages under a major power transmission expansion project tendered in April.
The project covers new substations at multiple voltage levels, as well as the supply and installation of 400kV extra-high-voltage power cables. The overall scheme is estimated to cost $650m.
It is being tendered as part of Kahramaa’s 2026 procurement plan, which includes 198 tenders with a total estimated value of QR21.4bn ($5.9bn).
According to sources, bids were submitted for the following packages on 20 August:
- Substation packages S1 and S2, covering new 132/11kV substations (estimated cost: $200m)
- Package S3, covering new 66/11kV substations ($50m)
- Package S4, including a new 400/220/132kV substation, as well as upgrades and modifications to existing 400kV and 220kV substations ($200m)
- Package S5, covering new 132/11kV substations and upgrades to existing 132kV and 66kV substations ($100m)
- Cable packages C1 and C2, covering 400kV cables ($100m)
Kahramaa previously stated that foreign companies not registered in Qatar would be allowed to participate in the bidding, subject to meeting specified conditions, including registration and certification requirements.
In June, the electricity and water utility awarded contracts worth more than QR2.2bn ($604m) to expand the electricity transmission network in the country’s western region.
The engineering, procurement and construction (EPC) works will support the integration of the 2GW Dukhan solar power project into Qatar’s national electricity grid. The scope includes new and upgraded substations, as well as the installation of underground cables and overhead transmission lines.
Kahramaa said contracts were awarded to local firm Voltage Engineering, Turkiye’s Best & Betas Consortium, India’s Larsen & Toubro and South Korea’s LS Cable.
Of Kahramaa’s 2026 procurement plan, electricity transmission projects account for QR8.9bn ($2.4bn) and include the construction of new 400/132kV substations in Al-Wukair and Al-Mashaf, as well as the expansion of 400kV substations at Ras Laffan.
These also cover the installation of 132kV underground cables between Al-Sailiya and Al-Rayyan over a 24-kilometre route, as well as upgrades to the 400kV and 220kV networks.
Additionally, there are 64 planned electricity distribution projects managed by the Electricity Distribution Department that cover the medium-voltage and low-voltage networks throughout Doha and the regional municipalities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18962223/main.jpg -
Maaden closes $1bn term loan and credit facility24 August 2026
Saudi Arabian Mining Company (Maaden) has announced the closing of its inaugural international syndicated term loan and revolving credit facilities, worth a total of $1bn.
The $500m international term loan facility will support Maaden’s growth agenda and general corporate purposes, including funding growth projects across its portfolio.
The $500m international revolving credit facility, which is expected to remain undrawn, provides additional committed funding capacity “as Maaden continues to scale its business and execute its long-term growth strategy”.
The transaction “was met with strong support from the international banking market, attracting participation from a diverse group of leading international banks across key global financial markets”, including the US, Canada, Europe, China and Japan. The facilities were oversubscribed, Maaden said.
ALSO READ: Maaden and Aramco sign deal to create joint venture
“The level of demand reflects the global banking community’s confidence in Maaden’s financial strength, strategic direction and ambitious growth plans,” the Saudi state miner said in its statement.
“The facilities mark another significant milestone in Maaden’s funding journey – further diversifying its sources of funding and broadening its access to global capital providers as the company continues to advance its long-term growth ambitions.
“Maaden continues to make significant progress across its growth pipeline, expanding production, advancing major projects and accelerating exploration as it builds a world-class mining company at the heart of Saudi Arabia’s economic transformation.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/18962086/main4516.jpg -
Dubai inflation slows to 5.3% in July24 August 2026
Dubai’s annual inflation rate slowed to 5.3% in July, down from 5.7% in June, as a decline in transport costs eased pressure on consumer prices, according to Emirates NBD.
The bank said the slowdown supported its view that price growth peaked at mid-year, and it expects inflation to continue easing through the rest of 2026. Monthly price growth slowed to 0.1% in July, from 0.4% in June, the weakest pace since February.
Transport was the clearest sign of the moderation. Annual price growth in the category slowed to 11.9% in July, from 18.1% in June, as transport costs fell 3.7% over the month. Fuel and lubricant inflation eased to 24.1% year on year, from 48.3%, tracking a decline in local petrol prices.
Petrol remains the main swing factor in the emirate’s inflation. Transport contributed 1.1 percentage points to headline inflation in July, down from 1.7 percentage points in June. Emirates NBD said the relief may prove temporary, with Super 98 petrol prices climbing 5.9% in August to leave them 33.8% higher than a year earlier. The bank expects headline inflation to edge higher in the August figures before easing again later in the year.
The UAE deregulated petrol and diesel prices in 2015 and reviews them monthly against global prices, meaning changes in global fuel costs pass through to consumers quickly. Transport, which includes fuel, accounts for 9% of Dubai’s consumer price index basket.
Housing remained the largest contributor to inflation even as its impulse faded. Housing and utilities, which account for about two-fifths of the basket, added 2.8 percentage points to headline inflation. Annual price growth in the category slowed to 7.0%, from 7.4% in January.
Food inflation edged up to 7.8% year on year, from 7.6% in June, which the bank attributed to lingering supply-chain disruption from the regional conflict. Inflation in restaurants and hotels accelerated to 4.5% year on year, from 1.7% in June.
Emirates NBD forecasts inflation of 2.9% by year-end but said risks to that projection were tilted to the upside, given lingering pressures in food and housing.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18961735/main1839.jpg -
Libya oil project on track for 2027 completion24 August 2026

The project to develop a workers’ camp at Libya’s Erawin oil field is on track for completion next year, according to industry sources.
The project, estimated to be worth about $50m, is being executed by the Libyan oil services company Al-Saraya Al-Hamara, headquartered in the city of Sebha.
The Libyan company was awarded the contract in February 2025.
The scope of the project includes:
- Construction of an accommodation camp
- Construction of the camp maintenance warehouse
- Construction of the camp office
- Construction of a fire brigade shelter
- Construction of a kitchen and mess hall
- Construction of a mosque
- Construction of a laundry room
- Construction of a clinic
- Construction of parking facilities
- Installation of a fire and gas system
- Installation of a power generator
- Construction of associated facilities
The client on the project is Zallaf Libya Oil & Gas Exploration & Production Company.
Zallaf Libya Oil & Gas Exploration & Production Company was established in Libya in 2013 and is wholly owned by Libya’s state-owned National Oil Corporation.
The Erawin field development project is located about 800 kilometres south of Tripoli and 100km southwest of the El-Sharara field.
Libya shipped its first cargo of crude from the Erawin oil field in November 2023.
The shipment departed from Libya’s Zawiyah port and consisted of 600,000 barrels of crude.
Australia-based Worley Parsons was appointed as the front-end engineering and design (feed) contractor for the early production facility project in 2019.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18953632/main.jpg