Iraq power projects make headway

9 May 2023

 

The inefficiency of Iraq’s electricity generation and transmission and distribution (T&D) infrastructure is well documented and ironic, given that the country is the second-largest Opec crude oil producer and home to the world’s largest crude oil reserves.

Decades-long protracted armed conflicts have routinely targeted Iraq’s substations, while economic and political upheavals have deterred further investments within the sector.

Over the past few months, however, there have been positive indications that the tide could be turning in favour of Iraq’s plans to improve the sector’s performance and output and reduce its carbon intensity.

In February, US-headquartered GE and Iraq’s Ministry of Electricity (MoE) agreed to pursue new projects to boost the country’s electricity infrastructure.

The parties signed principles of cooperation (PoC) to explore several projects, including establishing new power plants, expanding capacity at existing facilities, and building new substations to relieve grid congestion across a range of directorates.

This is on top of the power generation and T&D projects that the US firm has delivered in Iraq since 2011.

MOE also signed five-year service agreements with Germany’s Siemens Energy for three power plants with a combined total capacity of 1GW in March. Further cooperation is expected to be finalised for conventional and renewable generation capacity of up to 11GW.

In addition, Iraq has an estimated $10bn-worth of greenfield and brownfield thermal power generation projects in various planning and procurement stages, along with some $5bn of solar photovoltaic (PV) power plants, data from regional projects tracker MEED Projects reveals.

France’s TotalEnergies is in advanced talks to develop a 1GW solar power project catering to the southern Basra region as part of its $27bn Iraq energy programme.

“Talks are … progressing positively with the government. There are discussions about contracts and doing development activities,” a source close to the project tells MEED.

Power links

Similarly, plans to link Iraq to the regional GCC, Saudi Arabia and Jordan electricity grids have made good progress in recent months.

In February, the GCC Interconnection Authority (GCCIA) confirmed the award of five contracts worth $220m for the construction of infrastructure linking the region’s electricity grid with Iraq’s.

The project involves the construction of a double circuit 400-kilovolt (kV) transmission line from the Wafra station in Kuwait to the Al-Faw station in south Iraq with a total transmission capacity of 1,800MW and a length of 295 kilometres.

To be completed within 24 months, the project’s first stage is expected to supply Iraq with 500MW of electricity.

Work on the first 150MW phase of the Iraq-Jordan power link is also understood to start this month, following the award of the contract to GE.

A third power transmission link is planned by Saudi Electricity Company and Iraq’s MoE, between Arar in northern Saudi Arabia and Yousifiyah, a township in Iraq’s Baghdad Governorate.

These projects will help alleviate Iraq’s worsening power deficit, especially in the summer months when its existing infrastructure cannot cope with demand spikes.

It could also reduce dependence on Iran, from which Iraq imports an average of 1,200MW of electricity annually to augment supply.

It is understood Baghdad accrued a debt of $1.6bn for its Iranian gas and electricity purchases between 2019 and 2021, although most of the debt, if not all, was reportedly settled in October 2022.

Setbacks

As expected in Iraq, there have been some setbacks despite the encouraging developments.

Norwegian utility developer and investor Scatec has exited the deals it signed in 2021 to develop two solar independent power projects (IPPs) with a total combined capacity of 525MW in Karbala and Iskandariya.

Reports cite that difficulties and delays in negotiations led to the firm’s decision to exit the projects, for which power-purchase agreements (PPAs) are understood to have not yet been signed.

Scatec’s partners for the project, Egypt’s Orascom and the local firm Iraqi al-Bilal, may go ahead with implementing the projects, according to an industry source. 

The start of construction work has also been delayed for the first phase of a planned 1,400MW thermal power plant in Karbala due to the lack of a financial agreement between the developer and the Iraqi government.

Baghdad-based Harlow International was selected to develop the project in February 2021. During the intervening period, it acquired land, signed a power-purchase agreement and appointed China’s Citic Construction to build the first and second phases of the planned power plant. 

Citic has agreed to co-finance the project along with Harlow International.

Decarbonisation route

In addition to an estimated 5.5GW of solar PV projects in various stages of negotiations, other plans are under way to reduce the carbon intensity of Iraq’s energy sector.

For example, the recent PoC that the Electricity Ministry signed with GE includes a proposed 10-point strategy to accelerate Iraq’s energy transition.

The plan includes a flare gas-to-power project so that Iraq can utilise gas that is currently flared to produce electricity. Maintenance, upgrades and rehabilitation of the traditional fuel fleet are also planned.

It additionally includes a combined-cycle conversion programme, which is expected to “enhance efficiency, leading to significant fuel savings and decreasing greenhouse gas (GHG) emissions intensity”.

Notably, Iraq has tendered and awarded several plant conversion projects in recent years. In February, MOE awarded a team of China’s Dongfang Electric and China State Construction Engineering Corporation a contract to convert a simple-cycle power generation plant in Al-Zubair into a combined-cycle gas turbine (CCGT) facility.

Similar projects are in the procurement and execution stages. These include converting three power plants in Baghdad and two in Quds.

In 2021, MOE prequalified companies to bid for the contracts to convert two simple-cycle power plants in Diwaniya and Haidariya into CCGT facilities. Other similar projects include an existing power plant in Karbala, which has 10 units of GE’s F9E gas turbines, and another power plant in Najaf, which runs on two GE F9E units.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10822122/main.gif
Jennifer Aguinaldo
Related Articles
  • Neom requests revised Gayal wind proposals

    6 September 2024

     

    Neom’s energy, water and hydrogen subsidiary Enowa has requested that the final bidders submit updated proposals for a contract to build a 1,200MW wind farm catering to the gigaproject in Saudi Arabia.

    This development follows the introduction of an addendum to the tender after companies submitted their best and final offers (bafos) for the contract to build the 1,200MW Gayal wind farm project in June, a source close to the project tells MEED.

    MEED reported on 9 July that Neom is progressing towards awarding the engineering, procurement and construction (EPC) contract to the selected bidder following receipt of the bafos.

    Enowa received the initial bids for the contract on 4 March.

    It is understood that PowerChina and Egyptian contractor Orascom are among the firms invited to bid for the Gayal wind farm EPC contract.

    The wind farm project site is approximately 35 kilometres northwest of the former town of Gayal.

    The project will have an estimated plot area of 164 square kilometres. The project duration is 31 months from the start of construction.

    The scope of work for the EPC contractors bidding for the scheme includes the design, supply and installation of wind turbine generators and foundations, three 380kV substations and control systems, meteorological towers, site roads, hard stands, crane pads and associated infrastructure.

    Enowa received bids for another renewable energy project, the 800MW Shiqri solar farm, in March. The client is conducting commercial clarifications for the solar project, MEED reported in May.

    Neom aims to be powered 100% by renewable energy by 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12465111/main0411.jpg
    Jennifer Aguinaldo
  • Wabag confirms $317m Saudi water deal

    6 September 2024

    India-headquartered VA Tech Wabag has confirmed winning a contract to build a 300 cubic-metres-a-day (cm/d) seawater reverse osmosis (SWRO) plant project in Yanbu, Saudi Arabia.

    The value of the contract for the Yanbu 5 SWRO plant is $317m, the Bombay Stock Exchange-listed company said in a statement on 6 September.

    The engineering, procurement, construction and commissioning contract covers the design, engineering, supply, construction and commissioning of the desalination plant.

    According to Wabag, the plant will operate using dual media filters followed by a two-pass reverse osmosis process and re-mineralisation to produce clean potable water, which will be further distributed by Saudi Water Authority (SWA). 

    The plant is located on the west coast of Saudi Arabia, south of the Red Sea-facing Yanbu Al-Bahr, and is scheduled to be completed within 30 months of the contract award.

    MEED reported in July that Wabag submitted a lower bid for the contract.

    Saudi Arabia's main producer of desalinated water, SWA – formerly Saline Water Conversion Company (SWCC) – received two bids in May for the contract to build the Yanbu 5 SWRO project.

    The other bidder is understood to comprise a local contractor team and an overseas-based partner.  

    The bid evaluation process is ongoing for a second project, the Shuaiba 6 SWRO plant, which has a capacity of 545,000 cm/d.

    Two other projects, the Jubail and Ras Al-Khair SWRO projects, are in the bidding stage. They will each have the capacity to treat 600,000 cm/d of seawater.

    The four contracts are being procured using an EPC model, in contrast to the SWRO facilities being procured on a public-private partnership basis by state offtaker Saudi Water Partnership Company.

    SWA is the world's largest producer of desalinated water, with a capacity of at least 6.6 million cm/d. Plants utilising older and more energy-intensive techniques such as multi-stage flash technology account for the majority of the current capacity.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12464222/main3634.gif
    Jennifer Aguinaldo
  • Chinese companies win 95% of all Iraqi energy projects

    6 September 2024

    Commentary
    Wil Crisp
    Oil & gas reporter

    Companies headquartered in China have won 95% of all major project contracts awarded in Iraq’s oil, gas, chemicals and power sectors so far this year, as they increase their dominance in the market.

    A total of $12.1bn in energy project contracts were won by Chinese companies during the first eight months of 2024, according to data gathered by regional project tracker MEED Projects.

    The only major award so far this year that was not won by a company or partnership that was 100% Chinese, was the contract to rehabilitate the Baiji 2 gas-fired power station, which is estimated to be worth $1.3bn by MEED Projects.

    This contract was awarded to a consortium of Beijing-headquartered China State Construction Engineering Corporation (CSCEC) and German technology conglomerate Siemens.

    Commenting on the figures, one industry source said: “China has been a dominant force in Iraq’s energy sector for a long time and this is only increasing as time passes.

    “The huge presence that China has in the country’s energy sector is a source of concern for Iraq’s leadership, which doesn’t want to cede control of so many important infrastructure projects to companies from any single country.”

    “The problem is, other countries are reluctant to take on the risks of doing business in Iraq and at the same offer the competitive prices that Chinese contractors can offer.”

    The biggest energy project contract won by a Chinese contractor so far this year is the agreement for the development of the Al-Faw Investment Refinery project.

    The client on the project, state-owned Southern Refineries Company, signed a contract with CSCEC in May this year.

    The refinery will have a capacity of 300,000 barrels a day and will produce oil derivatives for both domestic and international markets.

    The project will be carried out in two stages. The first phase will involve refining operations, while the second will involve constructing a petrochemicals complex with a capacity of 3 million tonnes a year.

    The wider project also includes the construction of a 2,000MW power plant and the establishment of the Al-Faw Academy for Refinery Technology, to train 5,000 Iraqi workers that will eventually work at the facility.

    Hualu, a subsidiary of China National Chemical Engineering Company (CNCEC), signed a preliminary principles agreement for the project in December 2021.

    At the time, Iraq’s Oil Ministry said that the project would have an investment value of $7bn-$8bn.

    MEED Projects has estimated that the contract value of the deal signed with CSCEC in May for the refinery project is about $4bn.

    Other energy project contracts won by Chinese companies during the first eight months of this year included the contract for the Artawi 1,000MW photovoltaic solar power plant in Basra.

    This contract, estimated to be worth $1bn, was awarded to China Energy Engineering International Group.

    Chengdu-based DongFang Electric Corporation was awarded the main contract for a project to convert the Baghdad South power plant into a combined-cycle gas turbine power plant.

    The project is estimated to be worth $85m and will increase the capacity of the power plant by 125MW-625MW.

    Also this year, a subsidiary of PetroChina, the listed arm of state-owned China National Petroleum Corporation, signed an agreement to develop Iraq’s Nahr Bin Umar onshore gas field.

    The subsidiary, PetroChina Halfaya, was awarded the build-own-operate-transfer contract, which is estimated to be worth about $400m.

    Iraq’s Oil Ministry said that the field will have an initial output capacity of 150 million cubic feet a day.

    The project is expected to be completed within 36 months and will include the construction of gas-gathering facilities, storage tanks and pipeline networks to supply gas to power stations.

    Strong performance

    Chinese contractors also performed well in Iraq’s energy sector in terms of the value of contract awards in 2023.

    Last year, Chinese contractors won $2.3bn in Iraqi energy sector contracts, almost half of the $4.8bn that was awarded.

    Looking at the data for 2023 and the first eight months of 2024 together, Chinese companies won $14.5bn in contracts, 82% of the $17.6bn in energy project contracts awarded over the period.

    The second closest competitors were companies from Germany, which won just over $1bn in contracts, 6% of all awards.

    Iraqi companies were third, winning $816m in contracts, according to the data compiled by MEED Projects.

    Contracts were also won by companies from Italy, the Netherlands and Turkiye.

    Iraq is currently in the midst of a push to try and increase the volume of work being carried out by US companies in the country’s energy sector.

    Earlier this month, Iraq announced that it was planning to offer about 10 gas exploration blocks to international companies in a new licensing round that will be launched during a visit to the US by Iraqi Oil Minister Hayan Abdel-Ghani.

    Abdel-Ghani said that he will be specifically targeting US companies in the upcoming round.

    Earlier this year, the US international oil and gas company ExxonMobil completed its exit from Iraq’s West Qurna-1 oil field, handing over operatorship to PetroChina.

    Exxon’s plan to exit the West Qurna-1 oil field was first announced in April 2021, when Iraq’s Oil Ministry said the US-based oil company was considering selling its 32.7% stake.

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12460160/main3355.jpg
    Wil Crisp
  • Region plugs in to electric future

    5 September 2024

    Commentary
    Colin Foreman
    Editor

    Read the September 2024 issue of MEED Business Review

    Saudi Arabia is well known as one of the world’s largest oil exporters. What is less known is that the kingdom is also one of the world’s most significant consumers of oil. 

    According to the US-based Energy Information Agency (EIA), Saudi Arabia consumed 3.65 million barrels a day (b/d) in 2022, making it the fifth-largest consumer globally, with a 4% share of the global total. 

    Much of Saudi Arabia’s oil consumption comes from the power sector, although this is changing as Riyadh embarks on an ambitious renewable energy programme. Another major contributor is combustion engines in automobiles. 

    Anyone who has experienced Riyadh’s traffic congestion in recent years will attest to the fact that Saudi Arabia has a lot of cars. 

    In the coming years, the plan is for the cars on Saudi Arabia’s streets to be electric rather than gasoline-powered.  

    This aim is supported by key initiatives involving establishing electric vehicle (EV) assembly plants in the kingdom and plants that will produce key components, most notably batteries.  

    For Saudi Arabia’s efforts and similar endeavours across the region to be successful, other factors will also need to be considered. Shifting from gasoline to electric will require upgrading infrastructure with charging points installed at service stations and in residential areas. 

    Overhauling infrastructure in existing urban areas is complicated and costly, but the region’s governments have demonstrated a clear commitment to making EVs work. Initial success is within reach as the region plays catch up with other geographies that have shown higher EV ownership rates are achievable. 

    Looking further ahead, if the region can successfully shift to EVs, it will prove that even the most oil-dependent economies can embrace change and lead the charge towards a cleaner and greener future.


    Must-read sections in the September 2024 issue of MEED Business Review include:

    AGENDA: 
    GCC ponders electric future
    Region on the cusp of EV production boom

    > CURRENT AFFAIRS:
    Outlook uncertain for Iraq gas expansion project
    Security concerns threaten outlook for Libyan oil sector

    INDUSTRY REPORT:
    Analysis of the outlook for the downstream sector
    > Global LNG demand set for steady growth
    Region advances LNG projects with pace

    > SAUDI GIGAPROJECTS: Communication gaps hinder Saudi gigaprojects

    > INTERVIEW: Legacy building at Diriyah

    > SAUDI STADIUMS: Top 15 Saudi stadium projects

    LEADERSHIP: Navigating the impact of digital currencies on forex markets

    > KUWAIT MARKET REPORT: 

    > COMMENT: Kuwait’s prospects take positive turn
    > GOVERNMENT: Kuwait navigates unchartered political territory
    > ECONOMY: Fiscal deficit pushes Kuwait towards reforms
    > BANKING: Kuwaiti banks hunt for growth 
    > OIL & GAS: 
    Kuwait oil project activity doubles
    > POWER & WATER: Kuwait utilities battle uncertainty
    > CONSTRUCTION: Kuwait construction sector turns corner

    MEED COMMENTS: 
    > Saudi World Cup bid bucks global trend for sporting events
    > Finance deals reflect China’s role in delivering Vision 2030

    Harris-Walz portents shift in US policy on Gaza
    Aramco increases spending despite drop in profits

    > GULF PROJECTS INDEX: UAE leads slight dip in market

    > JULY 2024 CONTRACTS: Saudi Arabia boosts regional total again

    > ECONOMIC DATA: Data drives regional projects

    > OPINIONThe beginning of the end

    BUSINESS OUTLOOK: Finance, oil and gas, construction, power and water contracts

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/12460011/main.gif
    Colin Foreman
  • PIF and Hyundai award car plant construction deal

    5 September 2024

    Register for MEED's 14-day trial access 

    Saudi Arabia's sovereign wealth vehicle, the Public Investment Fund (PIF), and South Korea's Hyundai Motor Company have awarded the contract to build a vehicle manufacturing plant in Saudi Arabia.

    According to media reports, the firms awarded an estimated $248m contract to Seoul-headquartered Hyundai Engineering & Contracting.

    Construction of the plant is expected to start in 2024, and vehicle production in 2026.

    The facility will have a production capacity of 50,000 vehicles a year, including both conventional vehicles and electric vehicles (EVs).

    MEED reported in November last year that Hyundai Motor Company had appointed Seoul-headquartered Heerim Architects as the design consultant for its vehicle manufacturing plant in Saudi Arabia.

    PIF and Hyundai Motor Company signed a joint venture agreement to set up a vehicle manufacturing plant in the country in October last year.

    The PIF will hold a 70% share in the joint venture, with Hyundai holding the remaining 30% stake. The total investment for the project is estimated to be about $500m.

    In December 2022, Saudi Arabia's Industry & Mineral Resources Ministry signed a memorandum of understanding with Hyundai Motor Company to establish a car production plant in the kingdom. 

    The PIF is keen to invest in the kingdom's automotive sector. Last year, it launched the National Automotive & Mobility Investment Company (Tasaru Mobility Investments) to develop the local supply chain capabilities for the automotive and mobility industry in Saudi Arabia.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12457629/main.gif
    Yasir Iqbal