Iraq power projects make headway

9 May 2023

 

The inefficiency of Iraq’s electricity generation and transmission and distribution (T&D) infrastructure is well documented and ironic, given that the country is the second-largest Opec crude oil producer and home to the world’s largest crude oil reserves.

Decades-long protracted armed conflicts have routinely targeted Iraq’s substations, while economic and political upheavals have deterred further investments within the sector.

Over the past few months, however, there have been positive indications that the tide could be turning in favour of Iraq’s plans to improve the sector’s performance and output and reduce its carbon intensity.

In February, US-headquartered GE and Iraq’s Ministry of Electricity (MoE) agreed to pursue new projects to boost the country’s electricity infrastructure.

The parties signed principles of cooperation (PoC) to explore several projects, including establishing new power plants, expanding capacity at existing facilities, and building new substations to relieve grid congestion across a range of directorates.

This is on top of the power generation and T&D projects that the US firm has delivered in Iraq since 2011.

MOE also signed five-year service agreements with Germany’s Siemens Energy for three power plants with a combined total capacity of 1GW in March. Further cooperation is expected to be finalised for conventional and renewable generation capacity of up to 11GW.

In addition, Iraq has an estimated $10bn-worth of greenfield and brownfield thermal power generation projects in various planning and procurement stages, along with some $5bn of solar photovoltaic (PV) power plants, data from regional projects tracker MEED Projects reveals.

France’s TotalEnergies is in advanced talks to develop a 1GW solar power project catering to the southern Basra region as part of its $27bn Iraq energy programme.

“Talks are … progressing positively with the government. There are discussions about contracts and doing development activities,” a source close to the project tells MEED.

Power links

Similarly, plans to link Iraq to the regional GCC, Saudi Arabia and Jordan electricity grids have made good progress in recent months.

In February, the GCC Interconnection Authority (GCCIA) confirmed the award of five contracts worth $220m for the construction of infrastructure linking the region’s electricity grid with Iraq’s.

The project involves the construction of a double circuit 400-kilovolt (kV) transmission line from the Wafra station in Kuwait to the Al-Faw station in south Iraq with a total transmission capacity of 1,800MW and a length of 295 kilometres.

To be completed within 24 months, the project’s first stage is expected to supply Iraq with 500MW of electricity.

Work on the first 150MW phase of the Iraq-Jordan power link is also understood to start this month, following the award of the contract to GE.

A third power transmission link is planned by Saudi Electricity Company and Iraq’s MoE, between Arar in northern Saudi Arabia and Yousifiyah, a township in Iraq’s Baghdad Governorate.

These projects will help alleviate Iraq’s worsening power deficit, especially in the summer months when its existing infrastructure cannot cope with demand spikes.

It could also reduce dependence on Iran, from which Iraq imports an average of 1,200MW of electricity annually to augment supply.

It is understood Baghdad accrued a debt of $1.6bn for its Iranian gas and electricity purchases between 2019 and 2021, although most of the debt, if not all, was reportedly settled in October 2022.

Setbacks

As expected in Iraq, there have been some setbacks despite the encouraging developments.

Norwegian utility developer and investor Scatec has exited the deals it signed in 2021 to develop two solar independent power projects (IPPs) with a total combined capacity of 525MW in Karbala and Iskandariya.

Reports cite that difficulties and delays in negotiations led to the firm’s decision to exit the projects, for which power-purchase agreements (PPAs) are understood to have not yet been signed.

Scatec’s partners for the project, Egypt’s Orascom and the local firm Iraqi al-Bilal, may go ahead with implementing the projects, according to an industry source. 

The start of construction work has also been delayed for the first phase of a planned 1,400MW thermal power plant in Karbala due to the lack of a financial agreement between the developer and the Iraqi government.

Baghdad-based Harlow International was selected to develop the project in February 2021. During the intervening period, it acquired land, signed a power-purchase agreement and appointed China’s Citic Construction to build the first and second phases of the planned power plant. 

Citic has agreed to co-finance the project along with Harlow International.

Decarbonisation route

In addition to an estimated 5.5GW of solar PV projects in various stages of negotiations, other plans are under way to reduce the carbon intensity of Iraq’s energy sector.

For example, the recent PoC that the Electricity Ministry signed with GE includes a proposed 10-point strategy to accelerate Iraq’s energy transition.

The plan includes a flare gas-to-power project so that Iraq can utilise gas that is currently flared to produce electricity. Maintenance, upgrades and rehabilitation of the traditional fuel fleet are also planned.

It additionally includes a combined-cycle conversion programme, which is expected to “enhance efficiency, leading to significant fuel savings and decreasing greenhouse gas (GHG) emissions intensity”.

Notably, Iraq has tendered and awarded several plant conversion projects in recent years. In February, MOE awarded a team of China’s Dongfang Electric and China State Construction Engineering Corporation a contract to convert a simple-cycle power generation plant in Al-Zubair into a combined-cycle gas turbine (CCGT) facility.

Similar projects are in the procurement and execution stages. These include converting three power plants in Baghdad and two in Quds.

In 2021, MOE prequalified companies to bid for the contracts to convert two simple-cycle power plants in Diwaniya and Haidariya into CCGT facilities. Other similar projects include an existing power plant in Karbala, which has 10 units of GE’s F9E gas turbines, and another power plant in Najaf, which runs on two GE F9E units.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10822122/main.gif
Jennifer Aguinaldo
Related Articles
  • Contractors submit interest for Riyadh expo substructure

    24 July 2026

     

    Contractors have submitted expressions of interest on 23 July for a contract to deliver the early works and substructure works for several assets at the Expo 2030 Riyadh site.

    Expo 2030 Riyadh Company (ERC) is tasked with delivering the Expo 2030 Riyadh venue. Saudi sovereign wealth vehicle, the Public Investment Fund, launched ERC – a wholly owned subsidiary – in June 2025 to build and operate facilities for the event.

    The assets include the Icon; the convention centre; and thematic pavilions, including the Culture of Wisdom, Place & Planet and Adaptation & Innovation pavilions.

    The Icon will be located at the entrance of the Expo 2030 Riyadh site, within the Collaboration Precinct.

    The structure will be connected to the metro station and will serve as a gateway to the event.

    It will be 66 metres tall and will comprise an observation platform, food and beverage (F&B) outlets and other features.

    The convention centre will cover about 22,000 square metres. It will be the first point of arrival for visitors to the expo.

    The Culture of Wisdom pavilion will be a 25-metre-tall building that will feature exhibition galleries, innovation laboratories and conference and learning spaces.

    The Place & Planet building will also be 25 metres tall, and will include indoor and outdoor exhibition spaces, F&B and retail facilities and support areas.

    The Adaptation & Innovation pavilion will be located within the Loop of Nations precinct and will comprise a 29-metre-tall building.

    Construction progress

    The tendering of the pavilion structures followed progress on the site’s infrastructure development works.

    In April, ERC awarded two contracts for the next phase of infrastructure works at the site to local firm Al-Yamama Company.

    The scope covered the construction of road networks and infrastructure for water, sewage, electricity, telecommunications and electric vehicle charging.

    These awards followed ERC’s January award of an estimated SR1bn ($267m) contract for initial infrastructure works at the site to local firm Nesma & Partners. That scope covered about 50 kilometres of integrated infrastructure networks, including internal roads and essential utilities such as water, sewage, electrical and communications systems, and electric vehicle charging stations.

    The overall infrastructure works – covering the construction of main utilities and civil works at Expo 2030 Riyadh – are split into three packages:

    • Lot 1 covers the main utilities corridor;
    • Lot 2 includes the northern cluster of the Nature Corridor;
    • Lot 3 comprises the southern cluster of the Nature Corridor. 

    The masterplan encompasses an area of 6 square kilometres, making it one of the largest sites ever designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport and will provide direct access to landmarks within Riyadh.


    READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Stress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.

    Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17739044/main.jpg
    Yasir Iqbal
  • Oil price rises above $100 a barrel after Red Sea attacks

    24 July 2026

    Oil prices rose to their highest level in nearly two months on 23 July after the latest escalation in the US-Iran conflict threatened severe new disruptions to global energy supplies.

    Global benchmark Brent crude closed 7% higher, at $100.69 a barrel on 23 July. Earlier in the trading day, it rose as high as $102 a barrel. That is its highest level in eight weeks, since the end of May.

    Brent was trading at over $100 a barrel in the early hours of 24 July, but later pared gains to settle around $99.63 a barrel as of 11am Gulf Standard Time (GST).

    The surge in the Brent price came after Iran-backed Houthi rebels claimed attacks on two Saudi oil tankers in the Red Sea following their announcement of a naval blockade on Saudi Arabia.

    It appeared to be the first time since the regional war began that attacks on oil tankers and other commercial ships had extended beyond the Strait of Hormuz, opening up a new front in the volatile conflict.

    The Houthi threat is unsettling to oil markets because millions of barrels a day pass through the Bab El-Mandeb Strait to reach global markets.

    ALSO READ: Opec+ holds the line on unwinding of production cuts

    About 12%-15% of global maritime trade, worth more than $1tn, transits the waterway every year.

    It has also served as an alternative to the Strait of Hormuz, where traffic remains largely at a standstill, with ship crossings falling to single digits on 21 July.

    Since the start of July, oil prices have risen about 35%. Those prices are more than 60% higher than at the start of the year. This has erased much of the progress made in bringing prices down after the US and Iran signed a memorandum of understanding in mid-June.

    The interim peace deal has now collapsed, with US President Donald Trump threatening on 22 July to blow up an Iranian bridge or power plant for every vessel Tehran attacks.

    This was followed by the Houthi claim to have hit two tankers in the Red Sea.

    The UK’s Maritime Trade Office reported a tanker “struck by an unknown projectile” north of the Bab El-Mandeb Strait, and state-run Saudi Press Agency (Spa) reported that a vessel named Encelia was set ablaze by an attack while it was sailing overnight in the Red Sea, citing an unidentified source from the General Authority of Transport. Spa did not mention the other vessel, which is understood to be called Layla.


    READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Stress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.

    Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17739553/main4051.jpg
    Indrajit Sen
  • Qiddiya tenders Dragon Ball theme park package

    24 July 2026

     

    Qiddiya Investment Company (QIC) has tendered a contract to undertake the back-of-house works on the Dragon Ball theme park in Qiddiya, Saudi Arabia.

    The scope covers the construction of plant rooms, facilities management buildings, workshops, storage warehouses and central processing kitchens.

    It also includes a monorail service depot, a fire station, parking, utilities and other associated infrastructure.

    The bid submission deadline is 13 September.

    The Dragon Ball theme park will cover more than 500,000 square metres and will have seven themed zones inspired by the Japanese media franchise, including Kame House, Capsule Corporation and Beerus’ Planet.

    The park will offer more than 30 rides with five main attractions, including a rollercoaster that passes through a 70-metre landmark based on the series’ wish-granting dragon Shenron. 

    The development will also include themed hotels.

    In September 2024, US-based firm Falcon’s Creative Group announced that it is undertaking the masterplan and attraction design and is the creative lead for the theme park.

    QIC formally launched the Dragon Ball theme park in March 2024.

    The announcement came after QIC signed an agreement with Japanese firm Toei Animation, the producer of the Dragon Ball anime series.

    The Dragon Ball theme park is one of several major projects within the wider Qiddiya development. Other projects include an e-games arena, Prince Mohammed Bin Salman Stadium, a horse racing venue, a performing arts centre, the Speed Park and Six Flags theme parks and Aquarabia waterpark.

    The project is a key part of Riyadh’s strategy to boost leisure tourism in the kingdom. According to UK analytics firm GlobalData, leisure tourism in Saudi Arabia has experienced significant growth in recent years.


    READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Stress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.

    Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17738622/main.jpg
    Yasir Iqbal
  • Saudi Arabia appoints developer for hybrid power plant

    24 July 2026

     

    Saudi Arabia-based Lamar Holding has signed a contract to develop a hybrid power plant at the Empty Quarter (Rub Al-Khali) land port in Saudi Arabia, according to a source.

    The public-private partnership (PPP) project aims to reduce diesel fuel use with renewable energy and ensure a long-term power supply at the Empty Quarter land port. It includes the construction of 15MW of total hybrid installed capacity, installation of a 7 megawatt-peak solar photovoltaic system and eight 1MW internal combustion engines.

    In March, MEED exclusively reported that Lamar had been given preferred bidder status and was in advanced discussions with Saudi Arabia’s Zakat, Tax & Customs Authority (Zatca) for the contract.

    MEED understands that the proposed plant will have the capacity to produce 25 gigawatt-hours of electricity annually. It will be implemented under a design, build, finance, operate, maintain and transfer contract model for 25 years, excluding the construction period.

    US/India-based Synergy Consulting is acting as financial advisor to Lamar on the project. Egyptian firm Eternal Consultation Engineering Services is acting as the technical support consultant and Dubai-headquartered Aktech is the technical consultant for the project.

    Lamar Holding and Dubai’s SirajPower submitted bids for the Empty Quarter hybrid power plant project in July 2025, as previously reported by MEED.

    Zatca, in collaboration with the National Centre for Privatisation & PPP, had previously prequalified the following four companies to bid for the contract in October 2024:

    • Alfanar Company (Saudi Arabia)
    • Lamar Holding (Saudi Arabia)
    • Olayan Energy (Saudi Arabia) / Enerwhere Sustainable Energy (UAE)
    • Siraj Power for Renewable Energy (UAE)

    Prior to that, in July 2024, 12 Saudi companies and local branches of international companies, along with 11 overseas-based companies, submitted statements of qualifications for the contract.

    In addition to building and operating the power plant, the project scope includes ensuring the facility operates to defined requirements and output specifications. It also involves managing power generation and the connection to the Zatca interface point for the entire project term.


    READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Stress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.

    Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17733327/main.jpg
    Mark Dowdall
  • Saudi Downtown awards Al-Khobar substation contract

    23 July 2026

    Saudi Downtown Company (SDC), a wholly owned subsidiary of sovereign wealth vehicle the Public Investment Fund (PIF), has awarded the local Al-Ojaimi Contracting a contract to design and construct a primary electrical substation for its Downtown Al-Khobar project.

    It is understood that the facility will be the main electricity supply point for the wider development. The scope also includes the design and implementation of the associated electrical infrastructure.

    SDC was launched in 2022 by Saudi Crown Prince and Prime Minister Mohammed Bin Salman Bin Abdulaziz Al-Saud, who also serves as chairman of the PIF.

    The company is developing downtown districts in 12 cities in Saudi Arabia: Al-Khobar, Medina, Al-Ahsa, Buraidah, Najran, Jizan, Hail, Al-Baha, Arar, Taif, Dumat Al-Jandal and Tabuk.

    Earlier in July, MEED reported that SDC had awarded a contract for infrastructure works in downtown Al-Khobar to Saudi-based contractor Ansab General Contracting Company. The deal covers the design and development of the project's infrastructure, road networks and street lighting.

    SDC's mandate is to develop more than 10 million square metres (sq m) of land across its projects, supporting the objectives of Saudi Vision 2030.

    The Al-Khobar project covers approximately 829,103 sq m of land and is designed as a mixed-use hub offering residential units, retail spaces, entertainment, hospitality and integrated public amenities.

    Local firm Omrania & Associates was recently appointed as the main consultant on the project.


    READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Stress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.

    Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17732450/main.jpg
    Mark Dowdall