Iraq power projects make headway

9 May 2023

 

The inefficiency of Iraq’s electricity generation and transmission and distribution (T&D) infrastructure is well documented and ironic, given that the country is the second-largest Opec crude oil producer and home to the world’s largest crude oil reserves.

Decades-long protracted armed conflicts have routinely targeted Iraq’s substations, while economic and political upheavals have deterred further investments within the sector.

Over the past few months, however, there have been positive indications that the tide could be turning in favour of Iraq’s plans to improve the sector’s performance and output and reduce its carbon intensity.

In February, US-headquartered GE and Iraq’s Ministry of Electricity (MoE) agreed to pursue new projects to boost the country’s electricity infrastructure.

The parties signed principles of cooperation (PoC) to explore several projects, including establishing new power plants, expanding capacity at existing facilities, and building new substations to relieve grid congestion across a range of directorates.

This is on top of the power generation and T&D projects that the US firm has delivered in Iraq since 2011.

MOE also signed five-year service agreements with Germany’s Siemens Energy for three power plants with a combined total capacity of 1GW in March. Further cooperation is expected to be finalised for conventional and renewable generation capacity of up to 11GW.

In addition, Iraq has an estimated $10bn-worth of greenfield and brownfield thermal power generation projects in various planning and procurement stages, along with some $5bn of solar photovoltaic (PV) power plants, data from regional projects tracker MEED Projects reveals.

France’s TotalEnergies is in advanced talks to develop a 1GW solar power project catering to the southern Basra region as part of its $27bn Iraq energy programme.

“Talks are … progressing positively with the government. There are discussions about contracts and doing development activities,” a source close to the project tells MEED.

Power links

Similarly, plans to link Iraq to the regional GCC, Saudi Arabia and Jordan electricity grids have made good progress in recent months.

In February, the GCC Interconnection Authority (GCCIA) confirmed the award of five contracts worth $220m for the construction of infrastructure linking the region’s electricity grid with Iraq’s.

The project involves the construction of a double circuit 400-kilovolt (kV) transmission line from the Wafra station in Kuwait to the Al-Faw station in south Iraq with a total transmission capacity of 1,800MW and a length of 295 kilometres.

To be completed within 24 months, the project’s first stage is expected to supply Iraq with 500MW of electricity.

Work on the first 150MW phase of the Iraq-Jordan power link is also understood to start this month, following the award of the contract to GE.

A third power transmission link is planned by Saudi Electricity Company and Iraq’s MoE, between Arar in northern Saudi Arabia and Yousifiyah, a township in Iraq’s Baghdad Governorate.

These projects will help alleviate Iraq’s worsening power deficit, especially in the summer months when its existing infrastructure cannot cope with demand spikes.

It could also reduce dependence on Iran, from which Iraq imports an average of 1,200MW of electricity annually to augment supply.

It is understood Baghdad accrued a debt of $1.6bn for its Iranian gas and electricity purchases between 2019 and 2021, although most of the debt, if not all, was reportedly settled in October 2022.

Setbacks

As expected in Iraq, there have been some setbacks despite the encouraging developments.

Norwegian utility developer and investor Scatec has exited the deals it signed in 2021 to develop two solar independent power projects (IPPs) with a total combined capacity of 525MW in Karbala and Iskandariya.

Reports cite that difficulties and delays in negotiations led to the firm’s decision to exit the projects, for which power-purchase agreements (PPAs) are understood to have not yet been signed.

Scatec’s partners for the project, Egypt’s Orascom and the local firm Iraqi al-Bilal, may go ahead with implementing the projects, according to an industry source. 

The start of construction work has also been delayed for the first phase of a planned 1,400MW thermal power plant in Karbala due to the lack of a financial agreement between the developer and the Iraqi government.

Baghdad-based Harlow International was selected to develop the project in February 2021. During the intervening period, it acquired land, signed a power-purchase agreement and appointed China’s Citic Construction to build the first and second phases of the planned power plant. 

Citic has agreed to co-finance the project along with Harlow International.

Decarbonisation route

In addition to an estimated 5.5GW of solar PV projects in various stages of negotiations, other plans are under way to reduce the carbon intensity of Iraq’s energy sector.

For example, the recent PoC that the Electricity Ministry signed with GE includes a proposed 10-point strategy to accelerate Iraq’s energy transition.

The plan includes a flare gas-to-power project so that Iraq can utilise gas that is currently flared to produce electricity. Maintenance, upgrades and rehabilitation of the traditional fuel fleet are also planned.

It additionally includes a combined-cycle conversion programme, which is expected to “enhance efficiency, leading to significant fuel savings and decreasing greenhouse gas (GHG) emissions intensity”.

Notably, Iraq has tendered and awarded several plant conversion projects in recent years. In February, MOE awarded a team of China’s Dongfang Electric and China State Construction Engineering Corporation a contract to convert a simple-cycle power generation plant in Al-Zubair into a combined-cycle gas turbine (CCGT) facility.

Similar projects are in the procurement and execution stages. These include converting three power plants in Baghdad and two in Quds.

In 2021, MOE prequalified companies to bid for the contracts to convert two simple-cycle power plants in Diwaniya and Haidariya into CCGT facilities. Other similar projects include an existing power plant in Karbala, which has 10 units of GE’s F9E gas turbines, and another power plant in Najaf, which runs on two GE F9E units.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10822122/main.gif
Jennifer Aguinaldo
Related Articles
  • Public Investment Fund backs Neom

    16 April 2026

    Commentary
    Colin Foreman
    Editor

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s Public Investment Fund (PIF) has backed Neom by including it as one of six strategic ecosystems in its newly approved 2026-30 strategy.

    The future of the $500bn gigaproject had been thrown into doubt following the postponement of the 2029 Asian Winter Games at the Trojena mountain resort, the cancellation of construction contracts – such as the $5bn deal with Italian contractor Webuild for dam works at Trojena – and the slowdown of development at The Line, where tunnelling contracts were cancelled and staff left the project.

    The backing comes as Neom’s operational focus appears to be evolving in response to shifting regional dynamics and global economic conditions. For example, on 15 April Neom posted on its official X account about a new Europe-Egypt-Neom-GCC corridor, describing it as a faster route for time-sensitive goods. It said the corridor combines trucking and ferry services to move goods quickly into the Gulf, adding that importers from several European markets are already using it to reach the UAE, Kuwait, Iraq, Oman and beyond.

    Powered by Pan Marine, DFDS and regional RoPax services, the initiative is positioned as a way to add flexibility and resilience to regional supply chains. This emphasis on logistics and immediate trade utility suggests a shift away from the more speculative architectural announcements that characterised Neom’s early years, towards activity more directly tied to current market realities.

    PIF’s broader 2026-30 strategy places heavy emphasis on “delivering competitive domestic ecosystems to connect sectors, unlock the full potential of strategic assets, maximise long-term returns and continue to drive the economic transformation of Saudi Arabia”.

    The inclusion of Neom as a standalone ecosystem within the Vision Portfolio suggests that while the project remains part of the kingdom’s Vision 2030 goals, it will be subject to the fund's focus on working with the private sector.

    That means the long-term success of Neom will increasingly depend on its ability to attract external investment and function as a viable economic hub rather than just a state-funded construction site.


    MEED’s April 2026 report on Saudi Arabia includes:

    > COMMENT: Risk accelerates Saudi spending shift
    > GVT &: ECONOMY: Riyadh navigates a changed landscape
    > BANKING: Testing times for Saudi banks
    > UPSTREAM: Offshore oil and gas projects to dominate Aramco capex in 2026
    > DOWNSTREAM: Saudi downstream projects market enters lean period
    > POWER: Wind power gathers pace in Saudi Arabia

    > WATER: Sharakat plan signals next phase of Saudi water expansion
    > CONSTRUCTION: Saudi construction enters a period of strategic readjustment
    > TRANSPORT: Rail expansion powers Saudi Arabia’s infrastructure push

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16417262/main.jpeg
    Colin Foreman
  • Kuwait gas project worth $3.3bn put on hold

    16 April 2026

     

    State-owned Kuwait Gulf Oil Company’s (KGOC’s) planned tender for the development of an onshore gas plant next to the Al-Zour refinery has been put on hold due to uncertainty created by the US and Israel’s war with Iran, according to industry sources.

    The project budget is estimated to be $3.3bn, and the last meeting with contractors to discuss the project took place in Kuwait on 10 February.

    Previously, it was expected to be tendered in late March, but the tendering process was delayed due to the regional conflict and disruption to shipping through the Strait of Hormuz.

    One source said: “This tender is now effectively on hold while KGOC waits for increased stability in the region before it invites companies to bid for the contract.”

    Under current plans, the plant will have the capacity to process up to 632 million cubic feet a day of gas and 88.9 million barrels a day of condensates from the Dorra offshore field, located in Gulf waters in the Saudi-Kuwait Neutral Zone.

    Ownership of the field is disputed by Iran, which refers to the field as Arash.

    Iran claims the field partially extends into Iranian territory and asserts that Tehran should be a stakeholder in its development.

    It is believed that the Dorra field’s close proximity to Iran will make development difficult due to the current security environment.

    The offshore elements of the project are expected to be especially difficult to protect from attacks from Iran.

    In July last year, MEED reported that KGOC had initiated the project by launching an early engagement process with contractors for the main engineering, procurement and construction tender.

    France-based Technip Energies completed the contract for the front-end engineering and design.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16413221/main.png
    Wil Crisp
  • Iraq pushes to revive oil pipeline through Saudi Arabia

    16 April 2026

    Iraq is pushing to revive an oil pipeline that passes through Saudi Arabia, allowing it to diversify export routes.

    Saheb Bazoun, a spokesman for Iraq’s Oil Ministry, said the pipeline would help to insulate Iraq from any future blockades of the Strait of Hormuz, which has been largely closed since 28 February.

    The original pipeline through Saudi Arabia has not been used for more than 30 years and would need work to be done in order to bring it online.

    It is 1,568km long, extending from the city of Zubair in Iraq to the Saudi port of Yanbu on the Red Sea.

    The pipeline was built in two phases during the 1980s. The first phase stretches between Zubair and Khurais, while the second extends to Yanbu. The pipeline’s operating capacity reached over 1.6 million barrels a day (b/d).

    Following the Gulf War, the pipeline was shut down in August 1990. It has remained out of operation for decades, despite Iraq’s several attempts to restart it.

    The original pipeline project cost over $2.6bn, including storage tanks and loading terminals.

    In the wake of the US and Israel attacking Iran on 28 February, global markets have lost 11 million barrels a day (b/d) of oil supply due to the effective closure of the Strait of Hormuz.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16413290/main.jpg
    Wil Crisp
  • Algeria opens bidding for water treatment plant

    15 April 2026

     

    State-owned Cosider Pipelines, part of Algeria’s public infrastructure group Cosider, has issued a tender for the construction of a demineralisation plant in In Salah in Algeria.

    The contract covers the design, supply, installation, testing and commissioning of a plant with a treatment capacity of 62,000 cubic metres a day (cm/d).

    The tender is open to local and international companies specialising in the design and construction of demineralisation and reverse osmosis desalination plants.

    The bid submission deadline is 26 April.

    The project will be located at In Salah, a key industrial area in southern Algeria, where treated water supply is important for both municipal and industrial use.

    Cosider said that individual bidders must demonstrate that they have completed at least one reverse osmosis demineralisation or desalination plant with a capacity of 20,000 cubic metres a day or more.

    They must also show an average annual turnover of at least AD1bn ($7.7m) for their five best years over the past decade.

    For consortium bids, all partners must share full responsibility for the contract, while the lead company must meet the technical and financial requirements.

    Recent projects

    In 2023, MEED reported that Riyadh-based water utility developer Wetico had won two contracts to develop water desalination plants in Algeria.

    Societe Algerienne de Realisation de Projects Industriels (Sarpi) awarded the contract for the El-Tarf desalination plant, while Entreprise Nationale de Canalisations (Enac) is the client for the Bejaja facility.

    Both plants were commissioned in 2025, each with a production capacity of 300,000 cm/d.

    Separately, Wetico was the main contractor on a third plant commissioned last year. The Cap Dijinet 2 seawater desalination plant in Boumerdes province covers 18 hectares and also has a capacity of 300,000 cm/d.

    Like many countries, Algeria is facing pressure on resources due to longer and more frequent droughts. Seawater desalination is seen as a key driver of the government’s strategy to guarantee drinking water supply.

    According to previous reports, the government is planning to build up to six additional plants by 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16404325/main.jpg
    Mark Dowdall
  • WEBINAR: UAE Projects Market 2026

    15 April 2026

    Webinar: UAE Projects Market 2026
    Tuesday, 28 April 2026 | 11:00 GST  |  Register now


    Agenda:

    • Overview of the UAE projects market landscape
    • 2025 projects market performance
    • Value of work awarded 2026 YTD
    • Impact of the Iran conflict on the projects market and real estate, assessing supply chain disruptions, material cost inflation and war risk premiums
    • Key drivers, challenges and opportunities
    • Size of future pipeline by sector and status
    • Ranking of the top contractors and clients
    • Summary of key current and future projects
    • Short and long-term market outlook
    • Audience Q&A

    Hosted by: Colin Foreman, editor of MEED 

    Colin Foreman is editor and a specialist construction journalist for news and analysis on MEED.com and the MEED Business Review magazine. He has been reporting on the region since 2003, specialising in the construction sector and its impact on the broader economy. He has reported exclusively on a wide range of projects across the region including Dubai Metro, the Burj Khalifa, Jeddah Airport, Doha Metro, Hamad International airport and Yas Island. Before joining MEED, Colin reported on the construction sector in Hong Kong.

    Click here to register

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16401868/main.gif
    Colin Foreman