Iraq power projects make headway
9 May 2023

The inefficiency of Iraq’s electricity generation and transmission and distribution (T&D) infrastructure is well documented and ironic, given that the country is the second-largest Opec crude oil producer and home to the world’s largest crude oil reserves.
Decades-long protracted armed conflicts have routinely targeted Iraq’s substations, while economic and political upheavals have deterred further investments within the sector.
Over the past few months, however, there have been positive indications that the tide could be turning in favour of Iraq’s plans to improve the sector’s performance and output and reduce its carbon intensity.
In February, US-headquartered GE and Iraq’s Ministry of Electricity (MoE) agreed to pursue new projects to boost the country’s electricity infrastructure.
The parties signed principles of cooperation (PoC) to explore several projects, including establishing new power plants, expanding capacity at existing facilities, and building new substations to relieve grid congestion across a range of directorates.
This is on top of the power generation and T&D projects that the US firm has delivered in Iraq since 2011.
MOE also signed five-year service agreements with Germany’s Siemens Energy for three power plants with a combined total capacity of 1GW in March. Further cooperation is expected to be finalised for conventional and renewable generation capacity of up to 11GW.
In addition, Iraq has an estimated $10bn-worth of greenfield and brownfield thermal power generation projects in various planning and procurement stages, along with some $5bn of solar photovoltaic (PV) power plants, data from regional projects tracker MEED Projects reveals.
France’s TotalEnergies is in advanced talks to develop a 1GW solar power project catering to the southern Basra region as part of its $27bn Iraq energy programme.
“Talks are … progressing positively with the government. There are discussions about contracts and doing development activities,” a source close to the project tells MEED.
Power links
Similarly, plans to link Iraq to the regional GCC, Saudi Arabia and Jordan electricity grids have made good progress in recent months.
In February, the GCC Interconnection Authority (GCCIA) confirmed the award of five contracts worth $220m for the construction of infrastructure linking the region’s electricity grid with Iraq’s.
The project involves the construction of a double circuit 400-kilovolt (kV) transmission line from the Wafra station in Kuwait to the Al-Faw station in south Iraq with a total transmission capacity of 1,800MW and a length of 295 kilometres.
To be completed within 24 months, the project’s first stage is expected to supply Iraq with 500MW of electricity.
Work on the first 150MW phase of the Iraq-Jordan power link is also understood to start this month, following the award of the contract to GE.
A third power transmission link is planned by Saudi Electricity Company and Iraq’s MoE, between Arar in northern Saudi Arabia and Yousifiyah, a township in Iraq’s Baghdad Governorate.
These projects will help alleviate Iraq’s worsening power deficit, especially in the summer months when its existing infrastructure cannot cope with demand spikes.
It could also reduce dependence on Iran, from which Iraq imports an average of 1,200MW of electricity annually to augment supply.
It is understood Baghdad accrued a debt of $1.6bn for its Iranian gas and electricity purchases between 2019 and 2021, although most of the debt, if not all, was reportedly settled in October 2022.
Setbacks
As expected in Iraq, there have been some setbacks despite the encouraging developments.
Norwegian utility developer and investor Scatec has exited the deals it signed in 2021 to develop two solar independent power projects (IPPs) with a total combined capacity of 525MW in Karbala and Iskandariya.
Reports cite that difficulties and delays in negotiations led to the firm’s decision to exit the projects, for which power-purchase agreements (PPAs) are understood to have not yet been signed.
Scatec’s partners for the project, Egypt’s Orascom and the local firm Iraqi al-Bilal, may go ahead with implementing the projects, according to an industry source.
The start of construction work has also been delayed for the first phase of a planned 1,400MW thermal power plant in Karbala due to the lack of a financial agreement between the developer and the Iraqi government.
Baghdad-based Harlow International was selected to develop the project in February 2021. During the intervening period, it acquired land, signed a power-purchase agreement and appointed China’s Citic Construction to build the first and second phases of the planned power plant.
Citic has agreed to co-finance the project along with Harlow International.
Decarbonisation route
In addition to an estimated 5.5GW of solar PV projects in various stages of negotiations, other plans are under way to reduce the carbon intensity of Iraq’s energy sector.
For example, the recent PoC that the Electricity Ministry signed with GE includes a proposed 10-point strategy to accelerate Iraq’s energy transition.
The plan includes a flare gas-to-power project so that Iraq can utilise gas that is currently flared to produce electricity. Maintenance, upgrades and rehabilitation of the traditional fuel fleet are also planned.
It additionally includes a combined-cycle conversion programme, which is expected to “enhance efficiency, leading to significant fuel savings and decreasing greenhouse gas (GHG) emissions intensity”.
Notably, Iraq has tendered and awarded several plant conversion projects in recent years. In February, MOE awarded a team of China’s Dongfang Electric and China State Construction Engineering Corporation a contract to convert a simple-cycle power generation plant in Al-Zubair into a combined-cycle gas turbine (CCGT) facility.
Similar projects are in the procurement and execution stages. These include converting three power plants in Baghdad and two in Quds.
In 2021, MOE prequalified companies to bid for the contracts to convert two simple-cycle power plants in Diwaniya and Haidariya into CCGT facilities. Other similar projects include an existing power plant in Karbala, which has 10 units of GE’s F9E gas turbines, and another power plant in Najaf, which runs on two GE F9E units.
Exclusive from Meed
-
-
Iraq LNG project delayed until next year13 May 2026
-
-
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Dubai opens prequalification for Jebel Ali STP expansion13 May 2026

Dubai Municipality has issued a request for qualifications for the Jebel Ali sewerage treatment plant (STP) expansion – phase 3 project.
The DS150/3 project will be delivered under a public-private partnership (PPP) model on a design, build, finance, own, operate and transfer basis.
The project involves the development of a new water resource recovery facility with an ultimate treatment capacity of up to 1 million cubic metres a day (cm/d).
It is being procured through Dubai Municipality’s Sewerage and Recycled Water Projects Department and will be delivered through a two-stage operational approach over a 30-year concession period.
The bid submission deadline is 18 June.
UK-headquartered Deloitte is acting as financial adviser, Aecom as technical adviser and CMS as legal adviser.
Dubai Municipality said the project will also include additional land uses and community-focused amenities as part of broader sustainability and urban integration objectives.
Phase one and two expansion
In April, the deadline was extended for contractors to submit bids for an engineering, procurement and construction (EPC) contract covering the expansion of the Jebel Ali STP phases one and two.
Located on a 670-hectare site in Jebel Ali, the original wastewater facility has a treatment capacity of about 675,000 cm/d following the completion of phase two in 2019, combining approximately 300,000 cm/d from phase one and 375,000 cm/d from phase two.
The upgraded facility will be capable of treating an additional sewage flow of 100,000 cm/d, with the expansion estimated to cost $300m.
The new bid submission deadline is 11 June.
UK-headquartered KPMG and UAE-based Tribe Infrastructure are serving as financial advisers on the project.
> Be recognised among the best in the industry at the MEED Projects Awards 2026 …
https://image.digitalinsightresearch.in/uploads/NewsArticle/16812872/main.jpg -
Iraq LNG project delayed until next year13 May 2026
Register for MEED’s 14-day trial access
Iraq’s first liquefied natural gas (LNG) import terminal, which has an estimated project value of $450m, is now expected to become operational in 2027 due to delays caused by the regional war and disruption to shipping through the Strait of Hormuz.
Work on jetty reinforcement and fixed terminal infrastructure at the Port of Khor Al-Zubair has been delayed, according to a statement from US-based Excelerate Energy, which is contracted to develop the facility.
In its statement, the company said: “We are revising our full-year guidance to reflect the delayed startup of our Iraq terminal due to the ongoing conflict in the Middle East.”
It added: “The Iraq project fundamentals remain unchanged. Looking ahead, we continue to have confidence in our sequenced earnings growth through 2028.”
In October 2025, Excelerate signed a definitive commercial agreement with a subsidiary of Iraq’s Ministry of Electricity for the development of the country’s first LNG import terminal.
The integrated project includes a five-year agreement for regasification services and LNG supply, with extension options, and a minimum contracted offtake of 250 million standard cubic feet a day (cf/d).
Excelerate said: “Jetty reinforcement and construction of the fixed terminal infrastructure have been delayed temporarily due to the conflict in the Middle East and the terminal is no longer expected to commence operations in the third quarter of 2026 as previously disclosed.
“Project startup is now expected in 2027. The long-term fundamentals supporting the project remain unchanged, driven by chronic power shortages and limited domestic gas processing capacity in Iraq.
“Current conditions further reinforce the country’s need for reliable and scalable LNG import infrastructure and construction will resume as conditions allow.”
Earlier this year, Iraq’s Ministry of Electricity said that the terminal was on track to come online on 1 June, ahead of expected gas shortages during the summer months.
Then, in late April, the ministry said the project had been delayed by several months and was expected to come online in August at the earliest.
Although Iraq is Opec’s second-largest oil producer after Saudi Arabia, it is a net natural gas importer because its lack of infrastructure investment has meant that, until 2023, it flared roughly half of the estimated 3.12 billion cf/d of gas produced in association with crude oil.
Iraq’s reliance on flaring associated gas instead of gathering and processing it has prevented the country from fully realising its potential as a gas producer and forced the Iraqi government to rely on costly gas and electricity imports from Iran.
READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDFGlobal energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.
Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:
> REGIONAL LNG: War undermines business case for Middle East LNG> CAPITAL MARKETS: Damage avoidance frames debt issuance> MARKET FOCUS: Conflict tests UAE diversificationTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16803348/main.jpg -
Algeria turns the GCC oil crisis into an economic opportunity13 May 2026
Commentary
Wil Crisp
Oil & gas reporterAlgeria’s state-owned oil and gas company, Sonatrach, is taking advantage of concerns about global gas and crude supplies to sign deals and push ahead with major upstream projects.
In recent weeks, the country has launched an oil and gas licensing round, taken steps to boost crude production in the short term and awarded a $1.1bn oil and gas field development project.
This comes as shipping remains disrupted through the Strait of Hormuz, a key global oil and gas supply route. The disruption began after the US and Israel attacked Iran on 28 February 2026, triggering a regional war.
Algeria’s ramp-up in activity puts it in a stronger position to benefit from higher global energy prices than neighbouring Libya, despite Libya holding Africa’s largest proven oil reserves.
Libya challenges
In Libya, officials have sought to advance oil and gas projects, but the business environment remains challenging due to recurring violence and deep political divisions.
Last month, Libya’s rival legislative bodies approved a unified state budget for the first time in more than 13 years. The Central Bank of Libya confirmed on 11 April that both chambers had endorsed the budget, calling it a key step towards restoring financial stability after prolonged division.
Contractors expected the agreement to accelerate project activity, but so far the deal has yet to translate into meaningful progress on the ground. Earlier this month, MEED reported that Libya’s state-owned National Oil Corporation (NOC) had not yet provided subsidiaries with details of their funding allocations under the new budget.
Libya’s downstream sector was also disrupted this month by a fresh outbreak of violence. On 8 May, military clashes damaged buildings and vehicles, and forced the country’s largest operating refinery and a nearby oil port to shut for two days. On 10 May, Azzawiya Oil Refining Company, operator of the Zawiya facility, said it had lifted the state of emergency, allowing work to resume.
Algeria momentum
While Libya has struggled to capitalise on the current period of higher oil and gas prices, Algeria has significantly increased activity across its hydrocarbons sector.
Last month, Algeria launched a new bid round offering seven exploration blocks to international companies. The round was launched by the National Agency for the Valorisation of Hydrocarbon Resources (Alnaft), which regulates the upstream sector. The blocks are located in Ouargla, Illizi, Touggourt and El-Bayadh.
In parallel, Algeria is implementing short-term measures to raise output. On 3 May, the Ministry of Oil & Gas said the country plans to increase average production by 6,000 barrels a day in June.
Algeria is also pursuing regional export opportunities. Earlier this month, officials signed a framework agreement to enable crude supplies from Algeria to Egypt.
Turkiye has also announced plans to renew and expand its liquefied natural gas (LNG) agreement with Algeria. Turkiye’s Energy and Natural Resources Minister Alparslan Bayraktar said on 8 May that annual volumes could rise to 6.5 billion cubic metres, up from the current 4.4 billion cubic metres a year. The existing agreement is due to expire in September 2027.
Another sign of momentum is the award of a $1.1bn contract for phase two of the Hassi Bir Rekaiz oil and gas field development. The contract was signed by Egypt’s Petrojet and Italian engineering and contracting company Arkad. Petrojet’s share is estimated at about $600m and Arkad’s at about $500m. The client is Groupement HBR, a joint venture of Sonatrach and Thailand’s PTTEP.
Overall, while Libya continues to face obstacles to building sustained momentum in its oil and gas sector, Algeria is pursuing multiple initiatives that are likely to deliver economic benefits in the short, medium and long term.
READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDFGlobal energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.
Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:
> REGIONAL LNG: War undermines business case for Middle East LNG> CAPITAL MARKETS: Damage avoidance frames debt issuance> MARKET FOCUS: Conflict tests UAE diversificationTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16803345/main4150.jpg -
Chinese-Saudi joint venture to build $566m copper plant12 May 2026
Register for MEED’s 14-day trial access
Saudi Arabia-based industrial investment company Rawas and China’s Zhejiang Hailiang Company have signed a joint-venture agreement to establish a copper products manufacturing plant in the kingdom.
The joint venture, in which Zhejiang Hailiang will hold 51% and Rawas 49%, plans to invest about $566m in the facility, which will be built near Dammam port in Saudi Arabia’s Eastern Province.
The factory will be developed in two phases, with total production capacity projected at 150,000 tonnes a year (t/y). This includes 30,000 t/y of copper tubes, 20,000 t/y of copper busbars, 50,000 t/y of refined recycled copper and 50,000 t/y of copper foil.
“The project will fully leverage Saudi Arabia’s local copper ore resources, energy cost advantages and regional policy incentives to serve markets across the Middle East, Europe and Africa,” the partners said in their statement.
Shenzhen Stock Exchange-listed Zhejiang Hailiang is a subsidiary of Hailiang Group, one of the world’s largest copper pipe manufacturers and exporters.
Rawas is based in Riyadh. Obeikan Investment Group and Al-Khorayef Group are among its founding shareholders, while other investors include Al-Muhaidib Group and Mohammed Abunayyan Investment Group.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16799512/main.jpg -
Dubai Holding increases its shareholding in Emaar12 May 2026
Register for MEED’s 14-day trial access
Dubai Holding and the Investment Corporation of Dubai (ICD) have completed a transaction under which Dubai Holding acquired a 22.27% equity stake in the private real estate developer Emaar Properties from ICD.
Following the transaction, Dubai Holding’s total shareholding in Emaar Properties has risen to 29.73%, making it the company’s largest shareholder.
Listed on the Dubai Financial Market, Emaar Properties is among the region’s leading real estate developers, with a portfolio spanning residential, commercial, hospitality and retail assets. The firm has a presence across the Middle East, North Africa, Asia and Europe.
In a statement, Dubai Holding said that the acquisition is a strategic investment that underscores Dubai Holding’s confidence in Emaar Properties’ market position, asset quality and long-term growth outlook, as well as the resilience of Dubai’s economy and real estate sector.
Dubai Holding’s latest investment follows the incorporation of local real estate bodies Nakheel and Meydan into the Dubai Holding Group in 2024.
Since its establishment in 2004, Dubai Holding Group has created a portfolio of companies, including Jumeirah Group, Dubai Properties and Tecom Group. Tecom Group owns and operates several clusters in Dubai, including Dubai Internet City and Dubai Media City.
Nakheel and Meydan are among Dubai’s major real estate developers, with developments including Palm Jumeirah, Palm Jebel Ali, Meydan One, Tilal Al-Furjan, Mohammed Bin Rashid City and Dubai Islands.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16799031/main.jpg
