Iraq power projects make headway

9 May 2023

 

The inefficiency of Iraq’s electricity generation and transmission and distribution (T&D) infrastructure is well documented and ironic, given that the country is the second-largest Opec crude oil producer and home to the world’s largest crude oil reserves.

Decades-long protracted armed conflicts have routinely targeted Iraq’s substations, while economic and political upheavals have deterred further investments within the sector.

Over the past few months, however, there have been positive indications that the tide could be turning in favour of Iraq’s plans to improve the sector’s performance and output and reduce its carbon intensity.

In February, US-headquartered GE and Iraq’s Ministry of Electricity (MoE) agreed to pursue new projects to boost the country’s electricity infrastructure.

The parties signed principles of cooperation (PoC) to explore several projects, including establishing new power plants, expanding capacity at existing facilities, and building new substations to relieve grid congestion across a range of directorates.

This is on top of the power generation and T&D projects that the US firm has delivered in Iraq since 2011.

MOE also signed five-year service agreements with Germany’s Siemens Energy for three power plants with a combined total capacity of 1GW in March. Further cooperation is expected to be finalised for conventional and renewable generation capacity of up to 11GW.

In addition, Iraq has an estimated $10bn-worth of greenfield and brownfield thermal power generation projects in various planning and procurement stages, along with some $5bn of solar photovoltaic (PV) power plants, data from regional projects tracker MEED Projects reveals.

France’s TotalEnergies is in advanced talks to develop a 1GW solar power project catering to the southern Basra region as part of its $27bn Iraq energy programme.

“Talks are … progressing positively with the government. There are discussions about contracts and doing development activities,” a source close to the project tells MEED.

Power links

Similarly, plans to link Iraq to the regional GCC, Saudi Arabia and Jordan electricity grids have made good progress in recent months.

In February, the GCC Interconnection Authority (GCCIA) confirmed the award of five contracts worth $220m for the construction of infrastructure linking the region’s electricity grid with Iraq’s.

The project involves the construction of a double circuit 400-kilovolt (kV) transmission line from the Wafra station in Kuwait to the Al-Faw station in south Iraq with a total transmission capacity of 1,800MW and a length of 295 kilometres.

To be completed within 24 months, the project’s first stage is expected to supply Iraq with 500MW of electricity.

Work on the first 150MW phase of the Iraq-Jordan power link is also understood to start this month, following the award of the contract to GE.

A third power transmission link is planned by Saudi Electricity Company and Iraq’s MoE, between Arar in northern Saudi Arabia and Yousifiyah, a township in Iraq’s Baghdad Governorate.

These projects will help alleviate Iraq’s worsening power deficit, especially in the summer months when its existing infrastructure cannot cope with demand spikes.

It could also reduce dependence on Iran, from which Iraq imports an average of 1,200MW of electricity annually to augment supply.

It is understood Baghdad accrued a debt of $1.6bn for its Iranian gas and electricity purchases between 2019 and 2021, although most of the debt, if not all, was reportedly settled in October 2022.

Setbacks

As expected in Iraq, there have been some setbacks despite the encouraging developments.

Norwegian utility developer and investor Scatec has exited the deals it signed in 2021 to develop two solar independent power projects (IPPs) with a total combined capacity of 525MW in Karbala and Iskandariya.

Reports cite that difficulties and delays in negotiations led to the firm’s decision to exit the projects, for which power-purchase agreements (PPAs) are understood to have not yet been signed.

Scatec’s partners for the project, Egypt’s Orascom and the local firm Iraqi al-Bilal, may go ahead with implementing the projects, according to an industry source. 

The start of construction work has also been delayed for the first phase of a planned 1,400MW thermal power plant in Karbala due to the lack of a financial agreement between the developer and the Iraqi government.

Baghdad-based Harlow International was selected to develop the project in February 2021. During the intervening period, it acquired land, signed a power-purchase agreement and appointed China’s Citic Construction to build the first and second phases of the planned power plant. 

Citic has agreed to co-finance the project along with Harlow International.

Decarbonisation route

In addition to an estimated 5.5GW of solar PV projects in various stages of negotiations, other plans are under way to reduce the carbon intensity of Iraq’s energy sector.

For example, the recent PoC that the Electricity Ministry signed with GE includes a proposed 10-point strategy to accelerate Iraq’s energy transition.

The plan includes a flare gas-to-power project so that Iraq can utilise gas that is currently flared to produce electricity. Maintenance, upgrades and rehabilitation of the traditional fuel fleet are also planned.

It additionally includes a combined-cycle conversion programme, which is expected to “enhance efficiency, leading to significant fuel savings and decreasing greenhouse gas (GHG) emissions intensity”.

Notably, Iraq has tendered and awarded several plant conversion projects in recent years. In February, MOE awarded a team of China’s Dongfang Electric and China State Construction Engineering Corporation a contract to convert a simple-cycle power generation plant in Al-Zubair into a combined-cycle gas turbine (CCGT) facility.

Similar projects are in the procurement and execution stages. These include converting three power plants in Baghdad and two in Quds.

In 2021, MOE prequalified companies to bid for the contracts to convert two simple-cycle power plants in Diwaniya and Haidariya into CCGT facilities. Other similar projects include an existing power plant in Karbala, which has 10 units of GE’s F9E gas turbines, and another power plant in Najaf, which runs on two GE F9E units.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10822122/main.gif
Jennifer Aguinaldo
Related Articles
  • Kuwait receives bids for Al-Khairan phase one IWPP

    2 June 2026

     

    Two developer consortiums have submitted bids for the first phase of Kuwait’s Al-Khairan independent water and power producer (IWPP) project, according to a source.

    Bids were received by the Kuwait Authority for Partnership Projects (Kapp) on 1 June.

    The facility will have a capacity of 1,800MW and 150,000 cubic metres a day of desalinated water. It will be located in Al-Khairan, adjacent to the Al-Zour South thermal plant. 

    The bidders include:

    • Abu Dhabi National Energy Company (Taqa) / A H Al-Sagar & Brothers (Saudi Arabia) 
    • Acwa (Saudi Arabia) / Gulf Investment Corporation (Kuwait)

    The Al-Khairan IWPP is being procured by Kapp in partnership with the Ministry of Electricity, Water & Renewable Energy (MEWRE).

    The main contract was tendered last September. Three consortiums and two individual companies were previously prequalified to participate in the tender.

    Ernst & Young, BNP Paribas, AtkinsRealis and Addleshaw Goddard are financial advisers on the project. Chadbourne & Parke is acting as legal adviser.

    The winning bidder will sign a set of public-private partnership agreements covering financing, design, construction, operation and transfer of the project. The energy conversion and water-purchase agreement is expected to cover a 25-year supply period.

    Future phases

    The Al-Khairan IWPP project is expected to run on low-sulphur fuel oil as the primary fuel and to accommodate crude oil, gas oil and natural gas as backup fuels. Future phases will further expand capacity.

    It is understood that the estimated $750m second phase of the Al-Khairan IWPP project will add a further 1,800MW of generation capacity through a combined-cycle gas-fired power plant.

    The project, first mooted over a decade ago, remains in the early development stages, with no plans currently to advance to procurement in 2026, a source said.

    According to the source, the immediate focus is on advancing plans for the 3,600MW Nuwaiseeb power and water desalination IWPP project.

    The Nuwaiseeb IWPP plant will have a desalination capacity of 75 million imperial gallons a day.

    Kapp plans to release a transaction advisory tender for the project by the end of the year.


    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17072685/main.jpg
    Mark Dowdall
  • Doosan confirms Saudi Jafurah 2 cogen contract

    2 June 2026

    South Korea’s Doosan Enerbility has confirmed it has signed an engineering, procurement and construction (EPC) contract worth about $556m for the second phase of the Jafurah combined heat and power (CHP) plant in Saudi Arabia.

    The project is being developed by Korea Electric Power Corporation (Kepco) in partnership with Saudi Aramco.

    Doosan said the contract covers design, equipment supply, installation, construction and commissioning of the facility.

    The Jafurah CHP phase 2 project will be built near the Jafurah gas field, about 400 kilometres east of Riyadh. Once operational, it will generate 330MW of electricity and produce 465 tonnes of steam an hour for the nearby gas field.

    According to the firm, the project’s main steam turbine will be supplied by Doosan Skoda Power, a subsidiary of Doosan Enerbility.

    WSP is acting as the project management consultant for the project, which is scheduled for completion in 2029.

    The Jafurah gas development is part of Aramco’s $3.2bn unconventional resources programme, which aims to develop shale gas in three areas. Jafurah lies southeast of Ghawar, the world’s largest conventional oil field.

    The programme is part of Riyadh’s plans under Vision 20230 to ensure the kingdom remains self-sufficient in gas supply amid rising demand from the residential and industrial power sectors.

    Jafurah phase one

    In February 2025, MEED exclusively reported that talks were under way to expand the capacity of the $500m Jafurah cogeneration independent steam and power plant (ISPP).

    Construction works were completed on the facility last November.

    At the time of its procurement, the plant’s first phase was to have a power capacity of 270-320MW, and a low-pressure (LP) steam demand of 77-166 thousand pounds an hour (klb/hr) and high-pressure (HP) steam demand of 29-126 klb/hour by 2023.

    The LP and HP steam demand will increase to 283-373 klb/hr and 66-321 klb/hr by 2027, respectively.

    The oil giant issued the letter of award to Kepco for the contract to develop the Jafurah ISPP scheme in July 2022.

    Kepco subsequently awarded South Korea’s Doosan Heavy Industries & Construction the project’s EPC contract.

    US/India-based Synergy Consulting provided financial advisory services to Kepco on its bid.

    Sumitomo Mitsui Banking Corporation (SMBC) served as the client’s financial adviser for the project. Germany’s Fichtner Consulting Engineers is technical consultant, while the UK’s Wood Group is project management consultant.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17072199/main.jpg
    Mark Dowdall
  • Al-Mabanee submits lowest bids for Kuwait infrastructure

    2 June 2026

    Kuwait’s Public Authority for Housing Welfare (PAHW) has opened commercial bids for two major infrastructure and public buildings packages at South Al-Mutlaa Residential City.

    Local firm Al-Mabanee United Company has emerged as the lowest bidder for both contracts, submitting combined offers worth KD44m. Both packages entail the construction, completion and maintenance of services, infrastructure works and public buildings for different district centres within the city.

    The first contract covers the infrastructure and public buildings for the N3 District Centre. PAHW received proposals from eight bidders, with Al-Mabanee United Company submitting the lowest price at KD20.9m. The second-lowest offer was submitted by The Contractor General Trading & Contracting Company at KD22.4m, followed by Golden Engineering Group for General Trading & Contracting at KD22.7m, though Golden Engineering Group was flagged for not providing a bid bond.

    Al-Khonaini General Trading & Contracting Company, operating as Inshat Al-Khonaini, ranked fourth with a bid of KD22.7m, followed closely by Kuwait Industrial Centre Company at KD22.8m. Combined Group Contracting Company submitted a bid of KD23.8m, Al-Dar Engineering & Construction Company bid KD25.7m, and China’s Sichuan Road & Bridge Group Corporation submitted the highest active proposal at KD29m. 

    The second contract is for identical infrastructure and public building works at the N1 District Centre. Al-Mabanee United Company submitted the lowest bid of KD22.8m. Its closest competitor was The Contractor General Trading & Contracting Company, which submitted an offer of KD23.9m.

    Al-Khonaini General Trading & Contracting Company came in third with a bid of KD24.2m, followed by Kuwait Industrial Centre Company at KD24.4m and Golden Engineering Group for General Trading & Contracting at KD24.4m. Combined Group Contracting Company placed a bid of KD26m, Al-Dar Engineering & Construction Company bid KD26.5m, and United Construction Company, known as Al-Inshat Al-Muttahida, submitted an offer of KD 30.9m. Al-Ghanim International General Trading & Contracting filed the highest bid at KD344m and was also noted for lacking a bid bond.

    South Mutlaa Residential City is a large-scale planned development designed to accommodate around 400,000 residents in a modern, fully serviced urban environment. Once completed, it will offer contemporary housing alongside extensive logistical services and a wide range of public and commercial areas, including hospitals, schools and other social services.

    The project also includes major infrastructure works such as approximately 150 kilometres of roads and related structures, lighting and other public works, as well as integrated systems for water distribution, rainwater collection and sewage. In addition, it will provide the civil infrastructure needed for electricity distribution, telecommunications networks and traffic control to support a well-connected, functional city.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17071938/main.gif
    Colin Foreman
  • Local developer secures finance for three Riyadh projects

    2 June 2026

    Qimam Noshoz for Real Estate Development Company, a subsidiary of Saudi Arabia’s Banan Real Estate Company, has signed a sharia-compliant credit facility agreement worth SR84m ($22.4m) with Riyad Bank to fund three commercial, hospitality and sports developments in the kingdom.

    The financing agreement is split into two distinct tranches to align with the projects’ development timelines. The first tranche consists of SR49m with a maturity duration of seven years, while the remaining SR35m has been secured for an eight-year term.

    Qimam Noshoz will utilise the capital to fund construction works for the Al-Rahmaniyah Gem and Al-Wadi District Gem projects. Both of these projects are already leased to the fitness operator Armah Sports Company. The other project is an independent hotel located within the Al-Wadi District.

    The Al-Wadi development is designed as an integrated commercial complex spanning approximately 7,818.5 square metres of land, with a built-up area of about 975 square metres. It includes a men’s gym, a women’s gym and a hotel building.

    The Al-Rahmaniyah project is an integrated commercial development combining fitness facilities with retail. The asset features men’s and women’s gyms operating alongside an independent commercial zone.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17071628/main.jpg
    Colin Foreman
  • SLB wins $385m contract for Kuwait oil research centre

    2 June 2026

    Schlumberger Oilfield Eastern, a unit of the US-headquartered oilfield services company SLB, has been awarded a KD118m ($385m) contract to develop an oil and gas research centre in Kuwait.

    The contract was awarded by the state-owned upstream operator Kuwait Oil Company (KOC), according to a report by Kuwait’s Al-Rai newspaper.

    The Ahmadi Innovation Valley (AIV) project is planned as an advanced research and innovation hub equipped with specialised facilities and technical teams focused on applied research for Kuwait’s oil and gas sector.

    The contract was awarded after the Higher Purchase Committee (HPC) of Kuwait’s national oil and gas company Kuwait Petroleum Corporation (KPC) determined the bid to be compliant with the project’s technical and commercial requirements.

    In February 2025, KOC signed memorandums of understanding (MoUs) with five international oilfield service companies to support the development of the AIV initiative.

    These companies were:

    • SLB (US)
    • Baker Hughes (US)
    • Weatherford (US)
    • Halliburton (US)
    • National Energy Services Reunited (US)

    Under the preliminary agreements, each of the five companies agreed to establish a world-class research and development centre at the project site, focused on helping KOC meet challenges in the upstream sector.

    KOC’s CEO Ahmad Jaber Al-Eidan had said in February 2025 that the project will enable Kuwait to keep pace with global transformations while investing in advanced technologies to ensure the sector’s sustainability and achieve operational excellence.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17063475/main.gif
    Wil Crisp