Iraq power projects make headway
9 May 2023

The inefficiency of Iraq’s electricity generation and transmission and distribution (T&D) infrastructure is well documented and ironic, given that the country is the second-largest Opec crude oil producer and home to the world’s largest crude oil reserves.
Decades-long protracted armed conflicts have routinely targeted Iraq’s substations, while economic and political upheavals have deterred further investments within the sector.
Over the past few months, however, there have been positive indications that the tide could be turning in favour of Iraq’s plans to improve the sector’s performance and output and reduce its carbon intensity.
In February, US-headquartered GE and Iraq’s Ministry of Electricity (MoE) agreed to pursue new projects to boost the country’s electricity infrastructure.
The parties signed principles of cooperation (PoC) to explore several projects, including establishing new power plants, expanding capacity at existing facilities, and building new substations to relieve grid congestion across a range of directorates.
This is on top of the power generation and T&D projects that the US firm has delivered in Iraq since 2011.
MOE also signed five-year service agreements with Germany’s Siemens Energy for three power plants with a combined total capacity of 1GW in March. Further cooperation is expected to be finalised for conventional and renewable generation capacity of up to 11GW.
In addition, Iraq has an estimated $10bn-worth of greenfield and brownfield thermal power generation projects in various planning and procurement stages, along with some $5bn of solar photovoltaic (PV) power plants, data from regional projects tracker MEED Projects reveals.
France’s TotalEnergies is in advanced talks to develop a 1GW solar power project catering to the southern Basra region as part of its $27bn Iraq energy programme.
“Talks are … progressing positively with the government. There are discussions about contracts and doing development activities,” a source close to the project tells MEED.
Power links
Similarly, plans to link Iraq to the regional GCC, Saudi Arabia and Jordan electricity grids have made good progress in recent months.
In February, the GCC Interconnection Authority (GCCIA) confirmed the award of five contracts worth $220m for the construction of infrastructure linking the region’s electricity grid with Iraq’s.
The project involves the construction of a double circuit 400-kilovolt (kV) transmission line from the Wafra station in Kuwait to the Al-Faw station in south Iraq with a total transmission capacity of 1,800MW and a length of 295 kilometres.
To be completed within 24 months, the project’s first stage is expected to supply Iraq with 500MW of electricity.
Work on the first 150MW phase of the Iraq-Jordan power link is also understood to start this month, following the award of the contract to GE.
A third power transmission link is planned by Saudi Electricity Company and Iraq’s MoE, between Arar in northern Saudi Arabia and Yousifiyah, a township in Iraq’s Baghdad Governorate.
These projects will help alleviate Iraq’s worsening power deficit, especially in the summer months when its existing infrastructure cannot cope with demand spikes.
It could also reduce dependence on Iran, from which Iraq imports an average of 1,200MW of electricity annually to augment supply.
It is understood Baghdad accrued a debt of $1.6bn for its Iranian gas and electricity purchases between 2019 and 2021, although most of the debt, if not all, was reportedly settled in October 2022.
Setbacks
As expected in Iraq, there have been some setbacks despite the encouraging developments.
Norwegian utility developer and investor Scatec has exited the deals it signed in 2021 to develop two solar independent power projects (IPPs) with a total combined capacity of 525MW in Karbala and Iskandariya.
Reports cite that difficulties and delays in negotiations led to the firm’s decision to exit the projects, for which power-purchase agreements (PPAs) are understood to have not yet been signed.
Scatec’s partners for the project, Egypt’s Orascom and the local firm Iraqi al-Bilal, may go ahead with implementing the projects, according to an industry source.
The start of construction work has also been delayed for the first phase of a planned 1,400MW thermal power plant in Karbala due to the lack of a financial agreement between the developer and the Iraqi government.
Baghdad-based Harlow International was selected to develop the project in February 2021. During the intervening period, it acquired land, signed a power-purchase agreement and appointed China’s Citic Construction to build the first and second phases of the planned power plant.
Citic has agreed to co-finance the project along with Harlow International.
Decarbonisation route
In addition to an estimated 5.5GW of solar PV projects in various stages of negotiations, other plans are under way to reduce the carbon intensity of Iraq’s energy sector.
For example, the recent PoC that the Electricity Ministry signed with GE includes a proposed 10-point strategy to accelerate Iraq’s energy transition.
The plan includes a flare gas-to-power project so that Iraq can utilise gas that is currently flared to produce electricity. Maintenance, upgrades and rehabilitation of the traditional fuel fleet are also planned.
It additionally includes a combined-cycle conversion programme, which is expected to “enhance efficiency, leading to significant fuel savings and decreasing greenhouse gas (GHG) emissions intensity”.
Notably, Iraq has tendered and awarded several plant conversion projects in recent years. In February, MOE awarded a team of China’s Dongfang Electric and China State Construction Engineering Corporation a contract to convert a simple-cycle power generation plant in Al-Zubair into a combined-cycle gas turbine (CCGT) facility.
Similar projects are in the procurement and execution stages. These include converting three power plants in Baghdad and two in Quds.
In 2021, MOE prequalified companies to bid for the contracts to convert two simple-cycle power plants in Diwaniya and Haidariya into CCGT facilities. Other similar projects include an existing power plant in Karbala, which has 10 units of GE’s F9E gas turbines, and another power plant in Najaf, which runs on two GE F9E units.
Exclusive from Meed
-
Oman begins procurement for truck road PPP2 July 2026
-
Acwa signs Mauritania gas IPP agreements2 July 2026
-
Saudi water sector awaits next catalyst2 July 2026
-
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Oman begins procurement for truck road PPP2 July 2026

Oman’s Ministry of Transport, Communications & Information Technology (MTCIT) has tendered a contract for the sultanate’s second public-private partnership (PPP) road scheme.
The project spans 66 kilometres between Al-Buraimi and Al-Dhahirah governorates, starting at the Al-Khatm border crossing in Mahdah and ending at the Al-Fath area in Dhank.
Under the scheme, the winning bidder will design, build, finance and transfer the project, which is specially designed for heavy vehicles.
MTCIT issued the tender on 30 June. The deadline to purchase tender documents is 11 August, and the clarification period will run from 11 to 18 August.
The bid submission deadline is 30 January 2027.
In August 2023, Oman shortlisted five of the eight prequalified teams to compete for the Salalah-Thumrait truck road (STTR) project, the sultanate’s first PPP road project.
The project failed to materialise beyond that point.
In January, MEED reported that Oman is planning to establish a new commercial railway line to transport essential supplies between Salalah and Thumrait – an initiative understood to have preceded the STTR project. The railway is planned to be implemented as a PPP.
The scheme comprises the construction of a railway line approximately 150-170km long. Two main stations are planned: Salalah Station, near the port and food storage facilities, and Thumrait Station, which will serve as a distribution hub for the surrounding areas.
Trains are expected to be equipped with refrigerated and dry containers. The scheme aims to reduce transport costs between the two areas by 20%-30%, and Oman plans to pitch the project to major food companies to secure long-term transport contracts.
The proposed project timeline is:
- 2025: Conduct economic, technical and environmental feasibility studies
- 2026: Launch the project for investment on a PPP basis
- 2027-30: Construction of the railway line
- 2031: Trial operations
- 2032: Full commercial operations
The project is touted as a key initiative under Oman Vision 2040, which aims to transform the sultanate into a global logistics hub.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17525698/main.jpg -
Acwa signs Mauritania gas IPP agreements2 July 2026
Saudi Arabia’s Acwa has announced it has signed the public-private partnership (PPP) and power-purchase agreements for the 230MW N’diago combined-cycle gas turbine (CCGT) power plant in Nouakchott, Mauritania.
The agreements cover the development, financing, construction and operation of the project. They were signed in Nouakchott in the presence of senior officials from the Mauritanian government and Acwa chairman Mohammad Abunayyan.
The project is Mauritania’s first large-scale gas-fired independent power project (IPP). It is also expected to be the country’s first major gas-fired power plant procured through a PPP structure.
The CCGT plant will provide 230MW of baseload generation capacity. It will use Mauritania’s domestic natural gas resources to supply the national grid.
Separately, Mauritanian Electricity Company (Somelec) has been advancing procurement for the construction of a 50MW solar power and battery energy storage system IPP project. It issued an expression of interest request in May.
Mauritania currently has several wind and solar power projects in the early study stages, according to regional project tracker MEED Projects.
There are also plans to build a 1,200MW wind power plant near Port Etienne in the Bay Province of Nouadhibou, for which China Energy Engineering was appointed as the main contractor in 2024.
Meanwhile, Acwa’s portfolio comprises 111 assets that are operational, under construction or in advanced development. These represent investments of SR468.9bn ($125bn).
According to the company, it has a power generation capacity of 98GW, including 52.3GW of renewable energy, and manages 9.7 million cubic metres a day of desalinated water globally.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17525605/main.jpg -
Saudi water sector awaits next catalyst2 July 2026
Commentary
Mark Dowdall
Power & water editorSaudi Arabia’s water sector is entering a critical period as developers and investors wait for the next signal that the kingdom’s project pipeline is moving forward.
Seven months have passed since preferred bidders were announced for the Arana and Hadda independent sewage treatment plant (ISTP) projects, which together will provide 350,000 cubic metres a day (cm/d) of treatment capacity. The projects had been expected to reach financial close in the second quarter of this year, but have yet to do so.
In parallel, Saudi Arabia’s Vision Invest was selected as preferred bidder last December for the estimated $2bn Riyadh-Qassim independent water transmission pipeline (IWTP) project. It was reported at the time that the company had submitted a levelised tariff of SR2.627 ($0.70) a cubic metre, almost 20% below the next nearest bid. The project, which will comprise an 859-kilometre pipeline with transmission capacity of 685,000 cm/d, had been tipped to reach financial close this quarter.
The uncertainty extends beyond projects awaiting financial close. The developer tender bid deadline was recently pushed back again for the $150m Riyadh East ISTP. Meanwhile, Saudi Arabia’s Water Transmission Company (WTCO) is understood to be reviewing the delivery model for the Jubail-Buraidah and Ras Mohaisen-Baha-Mecca independent water transmission system (IWTS) projects.
According to sources familiar with the plans, WTCO is considering establishing a special purpose vehicle that would take equity stakes in both schemes. This could further delay procurement for a project that has already seen multiple deadline extensions. Sharakat’s next wave of independent water projects (IWPs) is also in the pipeline. The first of these is not expected to be tendered until early 2027.
According to regional project tracker MEED Projects, Saudi Arabia’s water infrastructure sector recorded $3.14bn-worth of awards in the first half of this year, substantially lower than the $7.58bn recorded during the same period in 2025.
While activity has slowed, the longer-term outlook remains unchanged. Population growth and industrial expansion continue to drive demand for desalination, wastewater treatment and water transmission infrastructure. In the meantime, key stakeholders are looking for the next clear signal that the project pipeline is regaining momentum.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17510220/main.jpg -
Contractor wins Jeddah road expansion deal in Riyadh2 July 2026

The Royal Commission for Riyadh City (RCRC) has awarded a contract for the Jeddah Road Development Project in Riyadh.
Local construction firm Saudi Pan Kingdom (Sapac) won the contract.
Spanning 29 kilometres, the scheme includes 14 bridges and five lanes.
Designed to handle up to 353,000 vehicles a day, the road is expected to be completed by 2028, with mobilisation works already under way.
The project forms part of the third package of the RCRC’s Riyadh Main and Ring Road Axes Development Programme, which was announced in January.
The other schemes include:
> Taif Road Development Project: The project stretches 15km and includes four bridges, each with four lanes. It also features two tunnels. It will have a capacity of up to 200,000 vehicles a day and will enhance connectivity between Riyadh’s southern and western districts and the city centre.
> Thumamah Road Development Project: The eastern section of the project will span 8km and include three bridges and three tunnels, linking the northern and eastern parts of Riyadh. The project will have a daily capacity of up to 200,000 vehicles.
> King Abdulaziz Road Development Project: The northern section of the project stretches 4.7km and will include four bridges, four lanes and one tunnel, with a capacity of up to 450,000 vehicles per day.
> Othman Bin Affan Road Development Project: The northern section will span 4.3km and include seven bridges and other related upgrades to enhance traffic flow across northern Riyadh. The project will have a daily capacity of up to 500,000 vehicles.
> Second phase of engineering enhancements for congested areas: This project targets eight locations across the city’s road network, where advanced engineering solutions will be applied to reduce congestion and improve intersection performance, increasing traffic capacity by 40% to 60%.
The contract for the Jeddah Road Development Project is the latest of several high-profile deals awarded by the RCRC recently. In May, it awarded an estimated SR5bn ($1.3bn) contract to construct the Sheikh Jaber Al-Sabah Road project in Riyadh.
That contract went to a joint venture of Riyadh-based Al-Rashid Trading & Contracting Company (RTCC) and Turkiye’s IC Ictas.
Stretching 12km, the project runs from Khurais Road to Al-Thumama Road and is a key component of the Second Eastern Ring Road scheme.
Works include five interchanges: Prince Bandar, King Abdullah, Imam Abdullah, Dammam Road and Al-Thumama.
In 2021, Saudi Arabia’s Crown Prince Mohammed Bin Salman Bin Abdulaziz Al-Saud said the population of Riyadh would double to 15-20 million people by 2030.
He directed government entities to work closely with the RCRC to prepare the city’s development strategy.
The RCRC’s major projects include Riyadh Metro, Riyadh Art, Sports Boulevard, King Salman International Park, Green Riyadh and several road development projects in the capital.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17523376/main.jpg -
Dubai announces First Al-Khail road development project2 July 2026
Register for MEED’s 14-day trial access
Dubai’s Executive Council has announced the First Al-Khail Street Development project, which will run parallel to Sheikh Zayed Road.
The scheme comprises a 15-kilometre elevated carriageway with three lanes in each direction.
According to a Dubai Media Office statement, “The project will provide access to areas including Al-Barsha, Al-Quoz, Business Bay and Meydan.”
“It is expected to serve more than 2.6 million people and reduce travel time on Sheikh Zayed Road by 51% during peak hours,” the statement added.
Designed to accommodate more than 9,000 vehicles an hour, construction is expected to begin in the third quarter of 2027, with completion targeted for 2030.
The development forms part of a wider AED18bn ($5bn) programme covering initiatives related to culture, trade, infrastructure, Emiratisation, finance, investment, urban planning and the city’s population census.
Projects approved by The Executive Council:
– Dubai Cultural Strategy
– Dubai Customs Strategy
– First Al Khail Street Development Plan
– ‘Dubai Population Now’ Real-Time Population Census and Growth Monitoring Initiative
– Emirati Talents Strategy in Private Education
– Dubai… pic.twitter.com/665ARlV3cK— Dubai Media Office (@DXBMediaOffice) July 1, 2026
https://image.digitalinsightresearch.in/uploads/NewsArticle/17523587/main.jpg
