Iraq power projects make headway
9 May 2023

The inefficiency of Iraq’s electricity generation and transmission and distribution (T&D) infrastructure is well documented and ironic, given that the country is the second-largest Opec crude oil producer and home to the world’s largest crude oil reserves.
Decades-long protracted armed conflicts have routinely targeted Iraq’s substations, while economic and political upheavals have deterred further investments within the sector.
Over the past few months, however, there have been positive indications that the tide could be turning in favour of Iraq’s plans to improve the sector’s performance and output and reduce its carbon intensity.
In February, US-headquartered GE and Iraq’s Ministry of Electricity (MoE) agreed to pursue new projects to boost the country’s electricity infrastructure.
The parties signed principles of cooperation (PoC) to explore several projects, including establishing new power plants, expanding capacity at existing facilities, and building new substations to relieve grid congestion across a range of directorates.
This is on top of the power generation and T&D projects that the US firm has delivered in Iraq since 2011.
MOE also signed five-year service agreements with Germany’s Siemens Energy for three power plants with a combined total capacity of 1GW in March. Further cooperation is expected to be finalised for conventional and renewable generation capacity of up to 11GW.
In addition, Iraq has an estimated $10bn-worth of greenfield and brownfield thermal power generation projects in various planning and procurement stages, along with some $5bn of solar photovoltaic (PV) power plants, data from regional projects tracker MEED Projects reveals.
France’s TotalEnergies is in advanced talks to develop a 1GW solar power project catering to the southern Basra region as part of its $27bn Iraq energy programme.
“Talks are … progressing positively with the government. There are discussions about contracts and doing development activities,” a source close to the project tells MEED.
Power links
Similarly, plans to link Iraq to the regional GCC, Saudi Arabia and Jordan electricity grids have made good progress in recent months.
In February, the GCC Interconnection Authority (GCCIA) confirmed the award of five contracts worth $220m for the construction of infrastructure linking the region’s electricity grid with Iraq’s.
The project involves the construction of a double circuit 400-kilovolt (kV) transmission line from the Wafra station in Kuwait to the Al-Faw station in south Iraq with a total transmission capacity of 1,800MW and a length of 295 kilometres.
To be completed within 24 months, the project’s first stage is expected to supply Iraq with 500MW of electricity.
Work on the first 150MW phase of the Iraq-Jordan power link is also understood to start this month, following the award of the contract to GE.
A third power transmission link is planned by Saudi Electricity Company and Iraq’s MoE, between Arar in northern Saudi Arabia and Yousifiyah, a township in Iraq’s Baghdad Governorate.
These projects will help alleviate Iraq’s worsening power deficit, especially in the summer months when its existing infrastructure cannot cope with demand spikes.
It could also reduce dependence on Iran, from which Iraq imports an average of 1,200MW of electricity annually to augment supply.
It is understood Baghdad accrued a debt of $1.6bn for its Iranian gas and electricity purchases between 2019 and 2021, although most of the debt, if not all, was reportedly settled in October 2022.
Setbacks
As expected in Iraq, there have been some setbacks despite the encouraging developments.
Norwegian utility developer and investor Scatec has exited the deals it signed in 2021 to develop two solar independent power projects (IPPs) with a total combined capacity of 525MW in Karbala and Iskandariya.
Reports cite that difficulties and delays in negotiations led to the firm’s decision to exit the projects, for which power-purchase agreements (PPAs) are understood to have not yet been signed.
Scatec’s partners for the project, Egypt’s Orascom and the local firm Iraqi al-Bilal, may go ahead with implementing the projects, according to an industry source.
The start of construction work has also been delayed for the first phase of a planned 1,400MW thermal power plant in Karbala due to the lack of a financial agreement between the developer and the Iraqi government.
Baghdad-based Harlow International was selected to develop the project in February 2021. During the intervening period, it acquired land, signed a power-purchase agreement and appointed China’s Citic Construction to build the first and second phases of the planned power plant.
Citic has agreed to co-finance the project along with Harlow International.
Decarbonisation route
In addition to an estimated 5.5GW of solar PV projects in various stages of negotiations, other plans are under way to reduce the carbon intensity of Iraq’s energy sector.
For example, the recent PoC that the Electricity Ministry signed with GE includes a proposed 10-point strategy to accelerate Iraq’s energy transition.
The plan includes a flare gas-to-power project so that Iraq can utilise gas that is currently flared to produce electricity. Maintenance, upgrades and rehabilitation of the traditional fuel fleet are also planned.
It additionally includes a combined-cycle conversion programme, which is expected to “enhance efficiency, leading to significant fuel savings and decreasing greenhouse gas (GHG) emissions intensity”.
Notably, Iraq has tendered and awarded several plant conversion projects in recent years. In February, MOE awarded a team of China’s Dongfang Electric and China State Construction Engineering Corporation a contract to convert a simple-cycle power generation plant in Al-Zubair into a combined-cycle gas turbine (CCGT) facility.
Similar projects are in the procurement and execution stages. These include converting three power plants in Baghdad and two in Quds.
In 2021, MOE prequalified companies to bid for the contracts to convert two simple-cycle power plants in Diwaniya and Haidariya into CCGT facilities. Other similar projects include an existing power plant in Karbala, which has 10 units of GE’s F9E gas turbines, and another power plant in Najaf, which runs on two GE F9E units.
Exclusive from Meed
-
Neom cancels The Line tunnels contracts16 March 2026
-
-
Modon launches Tara Park on Abu Dhabi’s Reem Island16 March 2026
-
Jordan begins prequalification for Amman water project16 March 2026
-
Saudi Arabia allows Hail airport bidders more time16 March 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Neom cancels The Line tunnels contracts16 March 2026

Register for MEED’s 14-day trial access
Neom has cancelled the contracts related to the construction of the tunnel sections of The Line in northwest Saudi Arabia.
In a stock exchange announcement filed on 13 March, South Korean contractor Hyundai E&C said that Neom cancelled its contract on 29 December last year.
Hyundai E&C was executing the drill-and-blast section of The Line’s tunnels in a joint venture with Greece’s Archirodon and South Korean counterpart Samsung C&T.
The firm said its share of the joint venture was about 35%, amounting to $483m.
Neom awarded contracts for constructing the mountain tunnel sections of The Line in June 2022.
The drill-and-blast works were split into four packages, with two contracting teams winning two packages each.
The other joint-venture team comprised Spain’s FCC, the local Shibh Al-Jazira Contracting Company (Sajco) and Beijing-based China State Construction Engineering Corporation.
The tunnels formed part of the infrastructure backbone of Neom’s 170-kilometre The Line development, launched in January 2021.
What began as Crown Prince Mohammed Bin Salman’s defining symbol of a post-oil Saudi Arabia unravelled with quiet finality over roughly two years. By April 2024, planners were reportedly being forced to cut the initial phase to just 2.4km by 2030.
By July last year, with the sovereign wealth fund facing tightening liquidity, the kingdom was reported to have conducted a “strategic review” to determine whether The Line was feasible – a process described as a “recalibration” of Vision 2030.
Resources are now being directed to projects essential for the Fifa World Cup 2034, Expo 2030, and critical housing, healthcare and education targets.
According to media reports, the government has pivoted towards repositioning what remains of Neom as an industrial and data centre hub, leveraging the Red Sea coastline’s access to seawater cooling for artificial intelligence (AI) infrastructure.
READ THE MARCH 2026 MEED BUSINESS REVIEW – click here to view PDFRiyadh urges private sector to take greater role; Chemical players look to spend rationally; Economic uptick lends confidence to Cairo’s reforms.
Distributed to senior decision-makers in the region and around the world, the March 2026 edition of MEED Business Review includes:
> RAMADAN: Data disproves the Ramadan slowdown story> INDUSTRY REPORT: Chemicals producers look to cut spending> INDUSTRY REPORT: Global petrochemical project capex set to rise until 2030> MARKET FOCUS: Egypt’s crisis mode gives way to cautious revival> LEADERSHIP: Delivering Saudi Arabia’s next phase of rail growth> INTERVIEW: Abu Dhabi’s Enersol charts acquisitions pathTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15995688/main.gif -
Bidders get more time for Riyadh East sewage treatment plant16 March 2026

State water offtaker Sharakat, formerly Saudi Water Partnership Company (SWPC), has extended the bid submission deadline for the Riyadh East independent sewage treatment plant (ISTP).
The new deadline is 30 June. The original deadline was 2 April.
The project will be developed under a build‑own‑operate‑transfer (BOOT) model with a 25‑year concession term.
The plant will have a treatment capacity of 200,000 cubic metres a day (cm/d) in its first phase, expanding to 500,000 cm/d in the second phase.
It includes the development of a treated sewage effluent transmission pipeline, forming part of the kingdom’s wider programme to expand wastewater treatment capacity through public-private partnerships.
The request for proposals (RFP) was issued last October.
In 2024, Sharakat prequalified 53 companies that could bid for the Riyadh East ISTP, part of seven planned ISTP projects it said it would procure between 2024 and 2026
WSP is the technical adviser and KPMG Middle East is the lead and financial adviser on the project.
The targeted commercial operation date for the facility is 2029.
ISTP plans
Sharakat’s current ISTP portfolio includes 10 large plants that are operational, under construction or under tendering, with a combined initial treatment capacity of 1.79 million cm/d.
These projects include North Taif, Jeddah Airport, West Dammam, Madinah 3, Buraydah 2, Tabuk 2, Al-Haer, Arana, Hadda and Riyadh East.
In December, two consortiums were selected for contracts to develop and operate the Hadda and Arana ISTP projects in Mecca province.
That same month, Sharakat prequalified 63 developers for upcoming ISTP projects under a revised prequalification process.
According to Sharakat’s newly released seven-year statement, it has identified six additional large ISTPs in the development pipeline.
These include:
- Kharj (75,000 cm/d)
- Abu Arish (50,000)
- Hafar Al-Batin (100,000)
- Riyadh North (TBD)
- Najran South (50,000)
- Khamis Mushait (50,000)
The company is also pursuing a nationwide small sewage treatment plant programme covering about 139 smaller ISTPs grouped into seven clusters.
These are designed to add roughly 521,450 cm/d of additional treatment capacity across the kingdom.
READ THE MARCH 2026 MEED BUSINESS REVIEW – click here to view PDFRiyadh urges private sector to take greater role; Chemical players look to spend rationally; Economic uptick lends confidence to Cairo’s reforms.
Distributed to senior decision-makers in the region and around the world, the March 2026 edition of MEED Business Review includes:
> RAMADAN: Data disproves the Ramadan slowdown story> INDUSTRY REPORT: Chemicals producers look to cut spending> INDUSTRY REPORT: Global petrochemical project capex set to rise until 2030> MARKET FOCUS: Egypt’s crisis mode gives way to cautious revival> LEADERSHIP: Delivering Saudi Arabia’s next phase of rail growth> INTERVIEW: Abu Dhabi’s Enersol charts acquisitions pathTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15993509/main.jpg -
Modon launches Tara Park on Abu Dhabi’s Reem Island16 March 2026
Abu Dhabi-based Modon Holding has launched the Tara Park residential project in the Reem Island area.
The project comprises two residential towers with a total of 340 residential units.
The development includes a 527-metre jogging track.
The latest project launch follows Modon Holding’s launch of the Bashayer residential waterfront community on Hudayriyat Island.
The project will comprise 157 four- and five-bedroom villas centred around a clubhouse with a rooftop infinity pool, and 330 one- to four-bedroom apartments across two low-rise buildings.
The development comprises a 3.5-kilometre waterfront promenade and a park.
In October last year, Modon Holding launched the Maysan residential development on Abu Dhabi’s Reem Island.
This development covers an area of about 600,000 square metres.
Maysan is being developed in several phases. The project’s first phase involves developing two districts: Mayar and Thoraya.
The first district, Mayar, consists of 132 mansions. The four-storey mansions will be located within a gated community featuring a central park and walking trails.
The second district, Thoraya, features 184 townhouses. It will include gardens, play areas, a gym and other associated facilities.
READ THE MARCH 2026 MEED BUSINESS REVIEW – click here to view PDFRiyadh urges private sector to take greater role; Chemical players look to spend rationally; Economic uptick lends confidence to Cairo’s reforms.
Distributed to senior decision-makers in the region and around the world, the March 2026 edition of MEED Business Review includes:
> RAMADAN: Data disproves the Ramadan slowdown story> INDUSTRY REPORT: Chemicals producers look to cut spending> INDUSTRY REPORT: Global petrochemical project capex set to rise until 2030> MARKET FOCUS: Egypt’s crisis mode gives way to cautious revival> LEADERSHIP: Delivering Saudi Arabia’s next phase of rail growth> INTERVIEW: Abu Dhabi’s Enersol charts acquisitions pathTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15993317/main.jpg -
Jordan begins prequalification for Amman water project16 March 2026
Jordan’s Ministry of Investment has issued a request for qualifications (RFQ) for a non-revenue water (NRW) reduction project in the southern and southeastern areas of Amman.
The project will be delivered under a public-private partnership (PPP) model using a design, build, finance, operate and maintain structure. It aims to reduce water losses and improve the efficiency of water distribution networks in the targeted areas.
The initiative is being led by the Ministry of Investment through its PPP unit in collaboration with the Ministry of Water & Irrigation, the Water Authority of Jordan and Miyahuna.
The procurement is expected to attract international water operators, engineering contractors and infrastructure investors with experience in NRW reduction programmes.
The bid submission deadline is 23 April.
Jordan has prioritised reducing NRW as part of efforts to improve the efficiency of its water sector. The country is among the most water-scarce in the world, and losses from distribution networks are estimated to account for about 45% of water supplied.
NRW reduction programmes typically involve measures such as network rehabilitation, leak detection, pressure management and improved metering to reduce physical and commercial losses across water systems.
Jordan is also advancing its $6bn Aqaba-Amman water desalination and conveyance project that aims to meet about 40% of Jordan’s municipal water demand by 2040.
As MEED recently reported, the project is nearing financial close. Once complete, it will supply about 300 million cubic metres of potable water a year from the Red Sea to Amman and other regions.
In February, the Water Authority of Jordan signed a four-year performance-based management contract with France’s Veolia to support water and wastewater services in the country’s northern governorates.
Under the contract, Veolia will provide operations, maintenance and management services to Yarmouk Water Company, the public utility responsible for water supply and wastewater services in the region.
READ THE MARCH 2026 MEED BUSINESS REVIEW – click here to view PDFRiyadh urges private sector to take greater role; Chemical players look to spend rationally; Economic uptick lends confidence to Cairo’s reforms.
Distributed to senior decision-makers in the region and around the world, the March 2026 edition of MEED Business Review includes:
> RAMADAN: Data disproves the Ramadan slowdown story> INDUSTRY REPORT: Chemicals producers look to cut spending> INDUSTRY REPORT: Global petrochemical project capex set to rise until 2030> MARKET FOCUS: Egypt’s crisis mode gives way to cautious revival> LEADERSHIP: Delivering Saudi Arabia’s next phase of rail growth> INTERVIEW: Abu Dhabi’s Enersol charts acquisitions pathTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15993071/main.jpg -
Saudi Arabia allows Hail airport bidders more time16 March 2026

Saudi Arabia’s Cluster2 Company, which operates under the state-owned Matarat Holding, has extended the bid deadline to 29 March for a contract to expand Hail airport.
The notice was issued in early January. The previous deadline was 1 March.
The scope of work covers the upgrade and expansion of the terminal infrastructure, including departures and arrivals areas, enhanced baggage handling facilities and other associated works.
The terminal expansion works include the south expansion, which encompasses the construction of a new building covering 5,600 square metres. This building will connect to the existing terminal from the southern side.
The expansion will increase the airport’s capacity to about 1.7 million passengers a year by 2030.
Cluster2 Company operates and manages 22 airports in Saudi Arabia, both domestic and international. It was established in 2022 as part of Matarat Holding to modernise and improve airport operations and the passenger experience.
Cluster2 Company aims to improve service quality, safety and operational efficiency while supporting traffic growth and local economic development. Through standardised processes, technology adoption and infrastructure upgrades, the company contributes to Matarat’s broader goals of enhancing connectivity, enabling tourism and business travel, and aligning airport performance with Saudi Vision 2030.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15993068/main.jpg
.gif)