Iraq power projects make headway
9 May 2023

The inefficiency of Iraq’s electricity generation and transmission and distribution (T&D) infrastructure is well documented and ironic, given that the country is the second-largest Opec crude oil producer and home to the world’s largest crude oil reserves.
Decades-long protracted armed conflicts have routinely targeted Iraq’s substations, while economic and political upheavals have deterred further investments within the sector.
Over the past few months, however, there have been positive indications that the tide could be turning in favour of Iraq’s plans to improve the sector’s performance and output and reduce its carbon intensity.
In February, US-headquartered GE and Iraq’s Ministry of Electricity (MoE) agreed to pursue new projects to boost the country’s electricity infrastructure.
The parties signed principles of cooperation (PoC) to explore several projects, including establishing new power plants, expanding capacity at existing facilities, and building new substations to relieve grid congestion across a range of directorates.
This is on top of the power generation and T&D projects that the US firm has delivered in Iraq since 2011.
MOE also signed five-year service agreements with Germany’s Siemens Energy for three power plants with a combined total capacity of 1GW in March. Further cooperation is expected to be finalised for conventional and renewable generation capacity of up to 11GW.
In addition, Iraq has an estimated $10bn-worth of greenfield and brownfield thermal power generation projects in various planning and procurement stages, along with some $5bn of solar photovoltaic (PV) power plants, data from regional projects tracker MEED Projects reveals.
France’s TotalEnergies is in advanced talks to develop a 1GW solar power project catering to the southern Basra region as part of its $27bn Iraq energy programme.
“Talks are … progressing positively with the government. There are discussions about contracts and doing development activities,” a source close to the project tells MEED.
Power links
Similarly, plans to link Iraq to the regional GCC, Saudi Arabia and Jordan electricity grids have made good progress in recent months.
In February, the GCC Interconnection Authority (GCCIA) confirmed the award of five contracts worth $220m for the construction of infrastructure linking the region’s electricity grid with Iraq’s.
The project involves the construction of a double circuit 400-kilovolt (kV) transmission line from the Wafra station in Kuwait to the Al-Faw station in south Iraq with a total transmission capacity of 1,800MW and a length of 295 kilometres.
To be completed within 24 months, the project’s first stage is expected to supply Iraq with 500MW of electricity.
Work on the first 150MW phase of the Iraq-Jordan power link is also understood to start this month, following the award of the contract to GE.
A third power transmission link is planned by Saudi Electricity Company and Iraq’s MoE, between Arar in northern Saudi Arabia and Yousifiyah, a township in Iraq’s Baghdad Governorate.
These projects will help alleviate Iraq’s worsening power deficit, especially in the summer months when its existing infrastructure cannot cope with demand spikes.
It could also reduce dependence on Iran, from which Iraq imports an average of 1,200MW of electricity annually to augment supply.
It is understood Baghdad accrued a debt of $1.6bn for its Iranian gas and electricity purchases between 2019 and 2021, although most of the debt, if not all, was reportedly settled in October 2022.
Setbacks
As expected in Iraq, there have been some setbacks despite the encouraging developments.
Norwegian utility developer and investor Scatec has exited the deals it signed in 2021 to develop two solar independent power projects (IPPs) with a total combined capacity of 525MW in Karbala and Iskandariya.
Reports cite that difficulties and delays in negotiations led to the firm’s decision to exit the projects, for which power-purchase agreements (PPAs) are understood to have not yet been signed.
Scatec’s partners for the project, Egypt’s Orascom and the local firm Iraqi al-Bilal, may go ahead with implementing the projects, according to an industry source.
The start of construction work has also been delayed for the first phase of a planned 1,400MW thermal power plant in Karbala due to the lack of a financial agreement between the developer and the Iraqi government.
Baghdad-based Harlow International was selected to develop the project in February 2021. During the intervening period, it acquired land, signed a power-purchase agreement and appointed China’s Citic Construction to build the first and second phases of the planned power plant.
Citic has agreed to co-finance the project along with Harlow International.
Decarbonisation route
In addition to an estimated 5.5GW of solar PV projects in various stages of negotiations, other plans are under way to reduce the carbon intensity of Iraq’s energy sector.
For example, the recent PoC that the Electricity Ministry signed with GE includes a proposed 10-point strategy to accelerate Iraq’s energy transition.
The plan includes a flare gas-to-power project so that Iraq can utilise gas that is currently flared to produce electricity. Maintenance, upgrades and rehabilitation of the traditional fuel fleet are also planned.
It additionally includes a combined-cycle conversion programme, which is expected to “enhance efficiency, leading to significant fuel savings and decreasing greenhouse gas (GHG) emissions intensity”.
Notably, Iraq has tendered and awarded several plant conversion projects in recent years. In February, MOE awarded a team of China’s Dongfang Electric and China State Construction Engineering Corporation a contract to convert a simple-cycle power generation plant in Al-Zubair into a combined-cycle gas turbine (CCGT) facility.
Similar projects are in the procurement and execution stages. These include converting three power plants in Baghdad and two in Quds.
In 2021, MOE prequalified companies to bid for the contracts to convert two simple-cycle power plants in Diwaniya and Haidariya into CCGT facilities. Other similar projects include an existing power plant in Karbala, which has 10 units of GE’s F9E gas turbines, and another power plant in Najaf, which runs on two GE F9E units.
Exclusive from Meed
-
Delivery unlocks gigaproject investment29 September 2026
-
Giga developers absorb supply chain shocks29 September 2026
-
KBR seeks renewable energy contracts in Libya29 September 2026
-
Sharakat receives bids for Riyadh East sewage treatment plant29 September 2026
-
Egypt firm wins Al-Dabaa desalination O&M contract29 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Delivery unlocks gigaproject investment29 September 2026

Register for MEED’s 14-day trial access
Completed infrastructure and open assets are making it easier to attract private developers and foreign investors to Saudi Arabia’s gigaprojects, said speakers at MEED’s Shaping Mega Projects conference in Riyadh on 28 September.
Dale Chadwick, acting CEO of King Salman Park Foundation, said investor appetite had grown as construction advanced. The foundation has received 23 expressions of interest from private developers, and Chadwick said that number was increasing.
“What the private sector is looking for in terms of investment is surety of what we’re doing,” he said. “As soon as a private developer comes in and sees what we’re doing, they’re blown away. The closer we get to completion, the greater the appetite.”
He said interest from foreign direct investors was also rising, and that a deal the foundation expects to award soon involves foreign investment.
The foundation times its private asset awards to follow infrastructure and landscaping works. “They don’t have to take the leap of faith that we are going to execute on our side of the equation,” said Chadwick. “They can see it.”
Partnership model
Mohamed Saad, president of DevCo at Diriyah Company, said investors wanted a relationship rather than a transaction.
“The first thing they’re looking for is partners,” he said. "They’re looking for master developers who act as true partners to them.”
Saad said master developers acted as the catalyst, investing in infrastructure and anchor assets before the private sector joins. He said investors also wanted healthy supply and demand, and a market able to absorb commercial assets in phases.
He said Diriyah had prioritised delivery over publicity. “People want to see to believe,” said Saad. “We are delivering on the ground, and when people come and visit, they’re pleasantly surprised.”
Chadwick said developers also wanted flexibility, with some seeking more height or a different mix of uses. “We ourselves have a plan, but in order to make that more attractive, we have to be prepared to make adjustments as well,” he said.
Ben Edwards, group head of cost, commercial and procurement at Red Sea Global, said the operating track record of The Red Sea and Amaala was now its strongest pitch to investors.
"We’ve gone past the field of dreams approach of ‘if you build it, they will come',” he said. "We’ve built it now. The tourists are coming.”
Edwards said Red Sea Global was at various stages of negotiation on several joint venture opportunities for future projects.
The developer’s utilities public-private partnership (PPP) at The Red Sea is fully operational. Its Amaala equivalent is in final testing and commissioning and is due to be operational before the end of the year. Edwards expects the model to spread.
"I’m sure the PPP market will continue to expand into the different infrastructure sectors here, and then lead into other sectors, from schools to hospitals,” he said.
He added that Red Sea Global’s environmental credentials were a selling point for investors.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20084647/main.jpeg -
KBR seeks renewable energy contracts in Libya29 September 2026

The US-headquartered technology and engineering company KBR is seeking renewable energy project contracts in Libya.
Representatives from KBR met with Abdussalam Elansari, chairman of the Renewable Energy Authority of Libya, earlier this month to discuss project opportunities, sources said.
The meeting with Elansari followed KBR’s opening of a new branch in Libya and its securing of several contract awards in the oil and gas sector.
In March, KBR announced that it had been awarded a contract by Zallaf Exploration, Production & Refining of Oil & Gas Company to provide project management and technical services for the South Refinery Project in Libya’s southern city of Ubari.
Under the terms of the contract, KBR will provide contract management, project management and supporting technical services throughout the engineering, procurement and construction (EPC) phases of the project, according to a company statement.
The EPC work is expected to be executed over a 50-month period.
KBR is also carrying out work to re-evaluate the front-end engineering and design (feed) for the project to develop Libya’s J6 North Gialo field.
In January, KBR signed a memorandum of understanding (MoU) with the state-owned Libyan Post, Telecommunications & Information Technology Company.
Under the MoU, KBR agreed to support efforts to develop and improve Libya’s communications infrastructure and enhance fifth-generation (5G) mobile networks in the country.
KBR has previously provided engineering services for major national projects in Libya, but was forced to shut down its office in the country several times amid political instability and security issues.
When the company was known as Brown & Root, it worked on the Great Man-Made River Project in Libya, which is widely recognised as the largest irrigation project in the world.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20081880/main.jpg -
Giga developers absorb supply chain shocks29 September 2026

Register for MEED’s 14-day trial access
Saudi Arabia’s gigaproject developers are rerouting shipments and absorbing higher freight costs as regional geopolitical tensions disrupt supply chains. Executives discussed the impact at MEED’s Shaping Mega Projects conference in Riyadh on 28 September.
Mohamed Saad, president of DevCo at Diriyah Company, said supply chain disruption was one of several challenges facing the developer. He said it required the company to be adaptive and quick in its decision-making.
He said the wider situation had also weighed on end-user demand. “The appetite to buy residential units or lease retail or commercial office spaces has softened,” he said. “We also see opportunity, and developers who believe in the future and invest and develop in these times will catch the opportunity.”
Rerouted shipments
Dale Chadwick, acting CEO of King Salman Park Foundation, said the park had been fortunate because much of its supply chain was already in place.
Some bespoke construction materials sourced from India have been affected, forcing suppliers to change routes. The foundation has also been unable to import some trees from China, because extended delivery times meant they would spend too long at sea.
“It is a genuine challenge, and it’s on a case-by-case basis,” said Chadwick. “We make the call, then we pivot and start trying to secure the material from elsewhere.”
He said one alternative was sourcing from Europe through a different supply route into the kingdom’s west coast. Chadwick said the impact had so far been manageable, with no significant effect on the park linked to the geopolitical situation. He added that contractors were facing the same pressures and suggested some might be seeking higher margins as a result.
Local content
Ben Edwards, group head of cost, commercial and procurement at Red Sea Global, said the developer had been shielded by the stage its projects had reached. The high proportion of local content in its procurement had also helped.
Red Sea Global set up a landscape nursery to bring plants in early and acclimatise them. Edwards said the nursery, the largest in the region, had doubled in size to about 200 hectares.
Freight costs have still risen sharply. “Container prices have doubled, and you have to just face that,” he said. “Where you haven’t got any other route to bring things in, and you’ve got to pay double, and you need the stuff, then you have to be flexible and deal with it accordingly with the supply chain.”
Edwards said the local supply chain had strengthened since the peak of gigaproject construction activity.
“The capability was here in Saudi, but the capacity wasn’t necessarily here at the time that everybody needed it three or four years ago,” he said. “Everybody needed all the same stuff all at the same time.”
He said support from the Ministry of Investment and government programmes to build supplier capability was starting to pay off. Supplier quality was improving as capacity grew.
Saad said the contracting market was also maturing. A correction was allowing contractors to be more selective about the work they pursue.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20082381/main.jpg -
Sharakat receives bids for Riyadh East sewage treatment plant29 September 2026
Saudi Arabia’s state water offtaker Sharakat has received bids for the contract to develop the $150m Riyadh East independent sewage treatment plant (ISTP).
Bids were submitted on 28 September.
The plant will have a treatment capacity of 200,000 cubic metres a day (cm/d) in its first phase, expanding to 500,000 cm/d in the second phase.
Five consortiums made offers, including:
- EtihadWE (UAE) / Metito (UAE) / Thrustboring Construction Company (TCC, Saudi Arabia)
- GS Inima (Spain) / Alkhorayef (Saudi Arabia)
- Lamar (Bahrain) / China Harbour Engineering Company (CHEC)
- Miahona (Saudi Arabia) / Marafiq (Saudi Arabia) / Bin Omairah Holding (Saudi Arabia)
- Suez (France) / Civil Works Company (Saudi Arabia) / Alwael (Saudi Arabia)
In May, MEED exclusively reported that groups had begun to form for the project, which will be developed under a build‑own‑operate‑transfer model with a 25‑year concession term.
It is understood that at least two other potential consortiums weighed up making an offer for the contract, but did not bid.
In 2024, Sharakat prequalified 53 companies that could bid for the Riyadh East ISTP, part of seven planned ISTP projects it said it would procure between 2024 and 2026. The request for proposals was issued last October.
WSP is the technical adviser, and KPMG Middle East is the lead and financial adviser.
The targeted commercial operation date for the facility is 2029.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20066914/main.jpg -
Egypt firm wins Al-Dabaa desalination O&M contract29 September 2026
Elsewedy Utilities has been awarded a three-year operation and maintenance (O&M) contract for a seawater desalination plant in Al-Dabaa on Egypt’s north coast.
The plant has a production capacity of 40,000 cubic metres a day (cm/d), and the contract runs for three years.
The award reflects Egypt’s increased focus on involving local private sector companies in operating and maintaining existing seawater desalination plants.
In March, Egypt’s Ministry of Housing, Utilities & Urban Communities directed that a number of existing desalination plants with capacities of more than 10,000 cm/d be offered to specialised local private sector companies for O&M. The plants include facilities in Al-Dabaa, Matrouh and El-Alamein, as well as sites in the Red Sea region and North and South Sinai.
The government said the move is intended to improve operating efficiency, strengthen maintenance systems and make greater use of specialised technical expertise. The contract value was not disclosed.
Elsewedy Utilities is the utilities and facilities management arm of Elsewedy Electric, with activities spanning engineering, procurement and construction, O&M and utility management.
As MEED understands, the contract is separate from the South Med desalination project at Al-Dabaa, which is being developed for the Engineering Authority of the Armed Forces’ Water Management Department.
Elsewedy Electric Infrastructure previously announced it is the main engineering, procurement and construction contractor for the planned 160,000-cubic-metre-a-day seawater reverse-osmosis plant.
Cairo-headquartered Engineering Experience Group also won a design and engineering services contract for the project in June.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20066727/main41574303.jpg