Iraq power projects make headway

9 May 2023

 

The inefficiency of Iraq’s electricity generation and transmission and distribution (T&D) infrastructure is well documented and ironic, given that the country is the second-largest Opec crude oil producer and home to the world’s largest crude oil reserves.

Decades-long protracted armed conflicts have routinely targeted Iraq’s substations, while economic and political upheavals have deterred further investments within the sector.

Over the past few months, however, there have been positive indications that the tide could be turning in favour of Iraq’s plans to improve the sector’s performance and output and reduce its carbon intensity.

In February, US-headquartered GE and Iraq’s Ministry of Electricity (MoE) agreed to pursue new projects to boost the country’s electricity infrastructure.

The parties signed principles of cooperation (PoC) to explore several projects, including establishing new power plants, expanding capacity at existing facilities, and building new substations to relieve grid congestion across a range of directorates.

This is on top of the power generation and T&D projects that the US firm has delivered in Iraq since 2011.

MOE also signed five-year service agreements with Germany’s Siemens Energy for three power plants with a combined total capacity of 1GW in March. Further cooperation is expected to be finalised for conventional and renewable generation capacity of up to 11GW.

In addition, Iraq has an estimated $10bn-worth of greenfield and brownfield thermal power generation projects in various planning and procurement stages, along with some $5bn of solar photovoltaic (PV) power plants, data from regional projects tracker MEED Projects reveals.

France’s TotalEnergies is in advanced talks to develop a 1GW solar power project catering to the southern Basra region as part of its $27bn Iraq energy programme.

“Talks are … progressing positively with the government. There are discussions about contracts and doing development activities,” a source close to the project tells MEED.

Power links

Similarly, plans to link Iraq to the regional GCC, Saudi Arabia and Jordan electricity grids have made good progress in recent months.

In February, the GCC Interconnection Authority (GCCIA) confirmed the award of five contracts worth $220m for the construction of infrastructure linking the region’s electricity grid with Iraq’s.

The project involves the construction of a double circuit 400-kilovolt (kV) transmission line from the Wafra station in Kuwait to the Al-Faw station in south Iraq with a total transmission capacity of 1,800MW and a length of 295 kilometres.

To be completed within 24 months, the project’s first stage is expected to supply Iraq with 500MW of electricity.

Work on the first 150MW phase of the Iraq-Jordan power link is also understood to start this month, following the award of the contract to GE.

A third power transmission link is planned by Saudi Electricity Company and Iraq’s MoE, between Arar in northern Saudi Arabia and Yousifiyah, a township in Iraq’s Baghdad Governorate.

These projects will help alleviate Iraq’s worsening power deficit, especially in the summer months when its existing infrastructure cannot cope with demand spikes.

It could also reduce dependence on Iran, from which Iraq imports an average of 1,200MW of electricity annually to augment supply.

It is understood Baghdad accrued a debt of $1.6bn for its Iranian gas and electricity purchases between 2019 and 2021, although most of the debt, if not all, was reportedly settled in October 2022.

Setbacks

As expected in Iraq, there have been some setbacks despite the encouraging developments.

Norwegian utility developer and investor Scatec has exited the deals it signed in 2021 to develop two solar independent power projects (IPPs) with a total combined capacity of 525MW in Karbala and Iskandariya.

Reports cite that difficulties and delays in negotiations led to the firm’s decision to exit the projects, for which power-purchase agreements (PPAs) are understood to have not yet been signed.

Scatec’s partners for the project, Egypt’s Orascom and the local firm Iraqi al-Bilal, may go ahead with implementing the projects, according to an industry source. 

The start of construction work has also been delayed for the first phase of a planned 1,400MW thermal power plant in Karbala due to the lack of a financial agreement between the developer and the Iraqi government.

Baghdad-based Harlow International was selected to develop the project in February 2021. During the intervening period, it acquired land, signed a power-purchase agreement and appointed China’s Citic Construction to build the first and second phases of the planned power plant. 

Citic has agreed to co-finance the project along with Harlow International.

Decarbonisation route

In addition to an estimated 5.5GW of solar PV projects in various stages of negotiations, other plans are under way to reduce the carbon intensity of Iraq’s energy sector.

For example, the recent PoC that the Electricity Ministry signed with GE includes a proposed 10-point strategy to accelerate Iraq’s energy transition.

The plan includes a flare gas-to-power project so that Iraq can utilise gas that is currently flared to produce electricity. Maintenance, upgrades and rehabilitation of the traditional fuel fleet are also planned.

It additionally includes a combined-cycle conversion programme, which is expected to “enhance efficiency, leading to significant fuel savings and decreasing greenhouse gas (GHG) emissions intensity”.

Notably, Iraq has tendered and awarded several plant conversion projects in recent years. In February, MOE awarded a team of China’s Dongfang Electric and China State Construction Engineering Corporation a contract to convert a simple-cycle power generation plant in Al-Zubair into a combined-cycle gas turbine (CCGT) facility.

Similar projects are in the procurement and execution stages. These include converting three power plants in Baghdad and two in Quds.

In 2021, MOE prequalified companies to bid for the contracts to convert two simple-cycle power plants in Diwaniya and Haidariya into CCGT facilities. Other similar projects include an existing power plant in Karbala, which has 10 units of GE’s F9E gas turbines, and another power plant in Najaf, which runs on two GE F9E units.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10822122/main.gif
Jennifer Aguinaldo
Related Articles
  • Contractor appointed for Oman power plants

    13 May 2026

     

    A consortium of China-headquartered Shandong Electric Power Construction No. 3 Company (Sepco 3) and South Korea’s Doosan Enerbility has been appointed as the main contractor on the Misfah and Duqm combined-cycle gas turbine power plants in Oman.

    The contracts cover the construction of two independent power producer (IPP) projects, with work scheduled to begin in the third quarter of 2026.

    State offtaker Nama Power & Water Procurement (Nama PWP) had previously signed power-purchase agreements (PPAs) for the development and operation of the plants.

    The developer’s contract was awarded to a consortium comprising Korea Western Power (Kowepo), Qatar’s Nebras Power, the UAE’s Etihad Water & Electricity (EtihadWE) and Oman’s Bhawan Infrastructure Services.

    The Misfah IPP will be led by Nebras Power and located in Wilayat Bousher in Muscat Governorate, with a planned capacity of 1,600MW.

    The Duqm IPP will be led by Kowepo and located in Wilayat Duqm in Al-Wusta Governorate, with a capacity of 800MW.

    According to Nama PWP, the total investment for the two projects is estimated at approximately RO1bn ($2.6bn).

    MEED reported last October that Nama PWP had received three bids for the development and operation of the gas-fired IPPs.

    The other bids included a consortium comprising China’s Shenzhen Energy Group and Oman National Engineering & Investment Company, and a lone bid from Saudi Arabia’s Acwa Power.

    Synergy Consulting is the financial adviser and lead adviser to Nama PWP for these projects.

    In November, Oman’s OQ Gas Networks received final investment approval to proceed with gas supply connections for the facilities.

    The Misfah IPP will receive 8.5 million cubic metres a day (cm/d) of natural gas. The Duqm IPP will be supplied with 4.5 million cm/d of natural gas.

    In March 2025, the same Sepco 3 and Doosan Enerbility consortium signed an engineering, procurement and construction contract with Saudi Electricity Company for the expansion of the Riyadh Power Plant 12 (PP12).

    Located about 150 kilometres northwest of Riyadh, the 1,863MW power plant is expected to be completed in 2028.

    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16816237/main.jpg
    Mark Dowdall
  • Financial challenge tests Iraq’s resolve

    13 May 2026

     

    On 21 April, as a fragile ceasefire held between the US and Iran, the Trump administration halted a $500m shipment in cash headed for Iraq, as it sought to clamp down on Iranian-backed Shia militias in the country. 

    That cash, derived from Iraqi oil exports and routed via the US Federal Reserve to the Central Bank of Iraq (CBI), is a vital cog in Iraq’s financial arteries, enabling it to cover foreign exchange demand.

    This was not the first time that Iraq’s financial system has felt the US’s warm breath on its neck.

    Back in February 2025, the US Treasury Department blacklisted five Iraqi banks from participating in dollar transactions, citing concerns about their role in illicit financial flows that benefited Iran’s Islamic Revolutionary Guards Corps.

    Iraq has also itself often circumscribed dollar use within its own financial system.

    In July 2023, the CBI banned 14 banks from conducting dollar transactions in a crackdown on dollar smuggling. In February 2024, it banned a further eight banks from dollar transactions as part of a crackdown on fraud and money laundering.

    Dollar pressure

    The recent halt in US dollar cash shipments has nevertheless added pressure to Iraq’s parallel currency market gap, says Lucila Bonilla, lead emerging market economist at Oxford Economics.  

    “The gap between the parallel exchange rate has widened noticeably against the official peg, to around 20%,” she says.

    “Dollar demand has risen as citizens and traders seek to hedge uncertainty – dollar deposits are up, and there are reports of a notable shift in the composition of cash holdings toward dollars.”

    Ratings agencies see the US move on Iraqi dollar use as a challenge, but one that might not prove too onerous.

    “Iraq can overcome a short-term war as it has $100bn of reserves and its debt profile is bearable,” says Gilbert Hobeika, a director at Fitch Ratings.

    “But a longer-term conflict will hurt Iraq as the economy is reliant on oil revenues and government involvement, while facing at the same time risk from the US stopping delivery of US dollars.”

    How persistent the pressure proves will depend largely on the duration of the Hormuz shock and how the relationship with the US evolves.

    “Forming a new government that is palatable to the US could ease the pressure, though Iraq’s protracted government formation process adds uncertainty to that timeline,” says Bonilla.

    The US-Iran war is putting even more pressure on banks.

    “There are uncertainties with regard to depositors,” says Hobeika. “The public sector banks have weak management and governance structures. Financial reporting is weak, and that puts pressure on asset quality and capitalisation.”

    If the conflict lasts a long time, the government will start withdrawing funds to pay salaries and contractors.

    “That will affect deposits at the public sector banks in the near term,” says Hobeika.

    State-heavy system

    Iraq’s banking system is dominated by a handful of state-owned banks with a market share of 75%-80%, and then 60-plus private banks competing for the remaining 20%-25% of the pie. 

    “Private banks have struggled to compete in a market with limited opportunities, small deposit bases and a narrow range of products, often focusing on very basic activities,” says Lea Hanna, an analyst at Moody’s.

    “In 2019, we had a wave of Islamic banks getting bans on dealing with US dollars – reducing what had been a primary source of business.”

    A few private banks have benefitted since then, namely those with majority ownership by foreign banks such as National Bank of Iraq, a subsidiary of Capital Bank of Jordan, and Bank of Baghdad, a subsidiary of Jordan Kuwait Bank.

    “Supported by their affiliates, these banks are relatively well run compared to domestic peers and have ample capital buffers,” says Hanna.

    “They have captured a large market share of US dollar transfers thanks to their strong US correspondent banking relationships that allow them easier access to US dollars. They have seen a surge in their profitability and an increase in their deposit base.”

    Financial reform

    The CBI has attempted to introduce reforms to the banking system, as part of a wider effort to enable it to channel funding to the private sector.

    In early 2025, it increased the minimum issued and paid-up capital requirement to ID400bn ($305m), along with a requirement to establish correspondent banking relationships for foreign-currency trading. The plan was to increase these in ID50bn increments every six months, to hasten sector consolidation.

    However, of Fitch’s rated banks, just two – state-owned Trade Bank of Iraq and Mansour Bank, a subsidiary of Qatar National Bank – met the full capital requirement.

    “While a lot of banks managed to increase their capital, a number of them didn’t and have been struggling to improve their systems and compliance with anti-terrorism and anti-money laundering regulations,” says Hobeika.

    “These systems take a long time to improve, and it costs the banks too. For that reason, they have agreed with the central bank to postpone implementation to 2027/28.”

    The expectation is that the number of private Iraqi banks will shrink from 60 to about half that number by 2028.

    “Iraq’s banking sector is undergoing a significant overhaul, with the Central Bank pushing through higher capital requirements, improved anti-money-laundering compliance, and a shift towards commercial banks managing their own international correspondent relationships. These moves are welcomed,” says Bonilla.

    But the harder work remains, argues Bonilla: state-owned banks still carry high levels of non-performing loans, weak governance and a history of politically directed lending, while private sector credit remains among the lowest in the region.

    “The stakes are high as the IMF estimates that a comprehensive reform of the financial sector, alongside broader governance and regulatory changes, could double Iraq’s non-oil growth potential over the medium term, adding around 4 percentage points to GDP,” says Bonilla.

    “For now, the reforms address the plumbing. The structural transformation of a banking system to serve the private sector is still largely ahead.”

    Clouded outlook

    So far, Iraq’s financial system seems to have averted a worst-case scenario of large-scale deposit withdrawals related to the Iran conflict.

    Any deposit withdrawals seem to be more related to the introduction of a digital custom system ASYCUDA (Automated System for Customs Data) aimed at helping the government collect revenues, which saw a lot of traders trying to bypass the custom charges.

    “This drove some exporters or traders to source US dollars outside the banking system, in the parallel market, to avoid stricter requirements and up-front payment of customs duties. That has now eased,” says Hanna.

    Looking ahead, Fitch anticipates that most government financing is likely to come from the CBI through indirect purchases of government securities.

    The central bank’s total claims on the central government represented about 52% of the domestic debt stock and 25% of the total debt stock at end-2024, notes the agency.

    It envisages that a smaller portion will come from the government’s cash deposits, anticipated to fall to an average 12% by 2027.

    Fitch says the CBI’s balance sheet limits refinancing risks, while the FX reserves are large enough to absorb the expansion of that balance sheet without putting pressure on the exchange-rate peg with the US dollar.

    Surging foreign direct investment comes as a source of comfort, with annual inflows rising from around $2bn in 2022 to $5bn-$7bn from 2023 onwards. 

    Reform of the financial system will remain at the top of the new government’s in-tray.

    The regional environment is unconducive to this mammoth task, and it can only hope that an end to the conflict would support ongoing Iraqi efforts to build a financial system comparable to that of some of its Gulf neighbours.


    MEED’s June 2026 report on Iraq also includes:

    > OVERVIEW: Iraq enters era of resilience, reform and rising risks
    > OIL & GAS: Iraqi oil and gas sector in crisis
    > POWER & WATER: Focus shifts to delivery of Iraq utilities expansion
    > CONSTRUCTION: Momentum builds in Iraq’s post-war construction sector

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16799540/main.gif
    James Gavin
  • JinkoSolar signs 2GW deal for Abu Dhabi solar project

    13 May 2026

    China’s JinkoSolar has signed an agreement with Abu Dhabi Future Energy Company (Masdar) to supply 2GW of photovoltaic (PV) modules for the round-the-clock renewable energy project in Abu Dhabi.

    The agreement covers the supply of JinkoSolar’s Tiger Neo series modules for the project, which is being developed by Masdar in collaboration with Emirates Water & Electricity Company (Ewec).

    The landmark $6bn project combines a 5.2GW solar PV plant with a 19 gigawatt-hour battery energy storage system (bess).

    It entered construction in October 2025 with India’s Larsen & Toubro and Power China working as contractors. It is known as the world’s first gigascale round-the-clock renewable energy project.

    Masdar had earlier selected JinkoSolar and JA Solar as preferred suppliers for solar PV modules, and CATL (Contemporary Amperex Technology) as preferred supplier for the bess segment.

    The project is designed to provide baseload renewable power and address intermittency challenges associated with solar generation. The developers said the scheme will serve as a model for similar projects internationally.

    JinkoSolar said the Tiger Neo modules supplied for the project are based on N-type TOPCon technology and have been adapted to meet the technical requirements of the development.

    Senior executives from both companies attended the signing ceremony in Abu Dhabi, including Mohamed Jameel Al-Ramahi, CEO of Masdar, and Charlie Cao, CEO of JinkoSolar.

    Jinko has won several major contracts in recent years, including a contract to supply solar PV modules with a capacity of 3GW for Saudi Arabia’s Haden and Al-Khushaybi solar projects.

    It also recently announced the signing of a 2GW solar PV module supply agreement with China Energy Engineering Corporation (CEEC) for Saudi Arabia’s Phase Six Khurais PV project.

    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16813268/main1816.jpg
    Mark Dowdall
  • Dubai opens prequalification for Jebel Ali STP expansion

    13 May 2026

     

    Dubai Municipality has issued a request for qualifications for the Jebel Ali sewerage treatment plant (STP) expansion – phase 3 project.

    The DS150/3 project will be delivered under a public-private partnership (PPP) model on a design, build, finance, own, operate and transfer basis.

    The project involves the development of a new water resource recovery facility with an ultimate treatment capacity of up to 1 million cubic metres a day (cm/d).

    It is being procured through Dubai Municipality’s Sewerage and Recycled Water Projects Department and will be delivered through a two-stage operational approach over a 30-year concession period.

    The bid submission deadline is 18 June.

    UK-headquartered Deloitte is acting as financial adviser, Aecom as technical adviser and CMS as legal adviser.

    Dubai Municipality said the project will also include additional land uses and community-focused amenities as part of broader sustainability and urban integration objectives.

    Phase one and two expansion

    In April, the deadline was extended for contractors to submit bids for an engineering, procurement and construction (EPC) contract covering the expansion of the Jebel Ali STP phases one and two.

    Located on a 670-hectare site in Jebel Ali, the original wastewater facility has a treatment capacity of about 675,000 cm/d following the completion of phase two in 2019, combining approximately 300,000 cm/d from phase one and 375,000 cm/d from phase two.

    The upgraded facility will be capable of treating an additional sewage flow of 100,000 cm/d, with the expansion estimated to cost $300m.

    The new bid submission deadline is 11 June.

    UK-headquartered KPMG and UAE-based Tribe Infrastructure are serving as financial advisers on the project.

    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16812872/main.jpg
    Mark Dowdall
  • Iraq LNG project delayed until next year

    13 May 2026

    Register for MEED’s 14-day trial access 

    Iraq’s first liquefied natural gas (LNG) import terminal, which has an estimated project value of $450m, is now expected to become operational in 2027 due to delays caused by the regional war and disruption to shipping through the Strait of Hormuz.

    Work on jetty reinforcement and fixed terminal infrastructure at the Port of Khor Al-Zubair has been delayed, according to a statement from US-based Excelerate Energy, which is contracted to develop the facility.

    In its statement, the company said: “We are revising our full-year guidance to reflect the delayed startup of our Iraq terminal due to the ongoing conflict in the Middle East.”

    It added: “The Iraq project fundamentals remain unchanged. Looking ahead, we continue to have confidence in our sequenced earnings growth through 2028.”

    In October 2025, Excelerate signed a definitive commercial agreement with a subsidiary of Iraq’s Ministry of Electricity for the development of the country’s first LNG import terminal.

    The integrated project includes a five-year agreement for regasification services and LNG supply, with extension options, and a minimum contracted offtake of 250 million standard cubic feet a day (cf/d).

    Excelerate said: “Jetty reinforcement and construction of the fixed terminal infrastructure have been delayed temporarily due to the conflict in the Middle East and the terminal is no longer expected to commence operations in the third quarter of 2026 as previously disclosed.

    “Project startup is now expected in 2027. The long-term fundamentals supporting the project remain unchanged, driven by chronic power shortages and limited domestic gas processing capacity in Iraq.

    “Current conditions further reinforce the country’s need for reliable and scalable LNG import infrastructure and construction will resume as conditions allow.”

    Earlier this year, Iraq’s Ministry of Electricity said that the terminal was on track to come online on 1 June, ahead of expected gas shortages during the summer months.

    Then, in late April, the ministry said the project had been delayed by several months and was expected to come online in August at the earliest.

    Although Iraq is Opec’s second-largest oil producer after Saudi Arabia, it is a net natural gas importer because its lack of infrastructure investment has meant that, until 2023, it flared roughly half of the estimated 3.12 billion cf/d of gas produced in association with crude oil.

    Iraq’s reliance on flaring associated gas instead of gathering and processing it has prevented the country from fully realising its potential as a gas producer and forced the Iraqi government to rely on costly gas and electricity imports from Iran.


    READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Global energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.

    Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16803348/main.jpg
    Wil Crisp