Iraq power projects make headway
9 May 2023

The inefficiency of Iraq’s electricity generation and transmission and distribution (T&D) infrastructure is well documented and ironic, given that the country is the second-largest Opec crude oil producer and home to the world’s largest crude oil reserves.
Decades-long protracted armed conflicts have routinely targeted Iraq’s substations, while economic and political upheavals have deterred further investments within the sector.
Over the past few months, however, there have been positive indications that the tide could be turning in favour of Iraq’s plans to improve the sector’s performance and output and reduce its carbon intensity.
In February, US-headquartered GE and Iraq’s Ministry of Electricity (MoE) agreed to pursue new projects to boost the country’s electricity infrastructure.
The parties signed principles of cooperation (PoC) to explore several projects, including establishing new power plants, expanding capacity at existing facilities, and building new substations to relieve grid congestion across a range of directorates.
This is on top of the power generation and T&D projects that the US firm has delivered in Iraq since 2011.
MOE also signed five-year service agreements with Germany’s Siemens Energy for three power plants with a combined total capacity of 1GW in March. Further cooperation is expected to be finalised for conventional and renewable generation capacity of up to 11GW.
In addition, Iraq has an estimated $10bn-worth of greenfield and brownfield thermal power generation projects in various planning and procurement stages, along with some $5bn of solar photovoltaic (PV) power plants, data from regional projects tracker MEED Projects reveals.
France’s TotalEnergies is in advanced talks to develop a 1GW solar power project catering to the southern Basra region as part of its $27bn Iraq energy programme.
“Talks are … progressing positively with the government. There are discussions about contracts and doing development activities,” a source close to the project tells MEED.
Power links
Similarly, plans to link Iraq to the regional GCC, Saudi Arabia and Jordan electricity grids have made good progress in recent months.
In February, the GCC Interconnection Authority (GCCIA) confirmed the award of five contracts worth $220m for the construction of infrastructure linking the region’s electricity grid with Iraq’s.
The project involves the construction of a double circuit 400-kilovolt (kV) transmission line from the Wafra station in Kuwait to the Al-Faw station in south Iraq with a total transmission capacity of 1,800MW and a length of 295 kilometres.
To be completed within 24 months, the project’s first stage is expected to supply Iraq with 500MW of electricity.
Work on the first 150MW phase of the Iraq-Jordan power link is also understood to start this month, following the award of the contract to GE.
A third power transmission link is planned by Saudi Electricity Company and Iraq’s MoE, between Arar in northern Saudi Arabia and Yousifiyah, a township in Iraq’s Baghdad Governorate.
These projects will help alleviate Iraq’s worsening power deficit, especially in the summer months when its existing infrastructure cannot cope with demand spikes.
It could also reduce dependence on Iran, from which Iraq imports an average of 1,200MW of electricity annually to augment supply.
It is understood Baghdad accrued a debt of $1.6bn for its Iranian gas and electricity purchases between 2019 and 2021, although most of the debt, if not all, was reportedly settled in October 2022.
Setbacks
As expected in Iraq, there have been some setbacks despite the encouraging developments.
Norwegian utility developer and investor Scatec has exited the deals it signed in 2021 to develop two solar independent power projects (IPPs) with a total combined capacity of 525MW in Karbala and Iskandariya.
Reports cite that difficulties and delays in negotiations led to the firm’s decision to exit the projects, for which power-purchase agreements (PPAs) are understood to have not yet been signed.
Scatec’s partners for the project, Egypt’s Orascom and the local firm Iraqi al-Bilal, may go ahead with implementing the projects, according to an industry source.
The start of construction work has also been delayed for the first phase of a planned 1,400MW thermal power plant in Karbala due to the lack of a financial agreement between the developer and the Iraqi government.
Baghdad-based Harlow International was selected to develop the project in February 2021. During the intervening period, it acquired land, signed a power-purchase agreement and appointed China’s Citic Construction to build the first and second phases of the planned power plant.
Citic has agreed to co-finance the project along with Harlow International.
Decarbonisation route
In addition to an estimated 5.5GW of solar PV projects in various stages of negotiations, other plans are under way to reduce the carbon intensity of Iraq’s energy sector.
For example, the recent PoC that the Electricity Ministry signed with GE includes a proposed 10-point strategy to accelerate Iraq’s energy transition.
The plan includes a flare gas-to-power project so that Iraq can utilise gas that is currently flared to produce electricity. Maintenance, upgrades and rehabilitation of the traditional fuel fleet are also planned.
It additionally includes a combined-cycle conversion programme, which is expected to “enhance efficiency, leading to significant fuel savings and decreasing greenhouse gas (GHG) emissions intensity”.
Notably, Iraq has tendered and awarded several plant conversion projects in recent years. In February, MOE awarded a team of China’s Dongfang Electric and China State Construction Engineering Corporation a contract to convert a simple-cycle power generation plant in Al-Zubair into a combined-cycle gas turbine (CCGT) facility.
Similar projects are in the procurement and execution stages. These include converting three power plants in Baghdad and two in Quds.
In 2021, MOE prequalified companies to bid for the contracts to convert two simple-cycle power plants in Diwaniya and Haidariya into CCGT facilities. Other similar projects include an existing power plant in Karbala, which has 10 units of GE’s F9E gas turbines, and another power plant in Najaf, which runs on two GE F9E units.
Exclusive from Meed
-
Saudi Arabia battery storage awards provide fresh lift24 August 2026
-
Qatar receives bids for major power grid expansion24 August 2026
-
Maaden closes $1bn term loan and credit facility24 August 2026
-
Dubai inflation slows to 5.3% in July24 August 2026
-
Libya oil project on track for 2027 completion24 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Saudi Arabia battery storage awards provide fresh lift24 August 2026
Commentary
Mark Dowdall
Power & water editorThe latest battery storage awards provide a welcome injection of investment into Saudi Arabia’s power market, which has seen a sharp slowdown in contract awards this year.
Saudi Power Procurement Company’s four Group 1 storage service agreements, announced last week, are worth more than $1.16bn and cover 2,000MW of capacity.
That is significant against the wider market. According to regional project tracker MEED Projects, Saudi Arabia recorded $19.7bn in power sector contract awards in the first seven months of 2025, compared with just $2.5bn in new awards in the same period this year.
The battery energy storage system (bess) awards therefore account for a sizeable share of the activity recorded so far this year and provide a much-needed source of new contracting activity.
Importantly, this is not a one-off. SPPC issued the request for proposal (RFP) for its second group of bess projects in July, covering six projects with a combined capacity of 3,000MW and 12,000MWh.
With the Group 1 tender taking around 18 months from RFP to contract award, it is reasonable to expect Group 2 contracts to be signed in 2027.
At the same time, the awards for six independent renewable plants under Round 7 of Saudi Arabia’s National Renewable Energy Programme (NREP), with a combined capacity of 5,300MW, are also likely to move into next year, with the latest bid deadlines now extending into September.
Although a substantial pipeline remains in procurement, it is only once these projects move from tender to award and into construction that this pipeline translates into market activity.
It is important that these tenders continue to progress at the pace established by the early rounds of Saudi Arabia’s renewable energy programme and now also SPPC’s independent storage provider bess scheme.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18962923/main.jpg -
Qatar receives bids for major power grid expansion24 August 2026

Qatar General Electricity & Water Corporation (Kahramaa) has received bids for several packages under a major power transmission expansion project tendered in April.
The project covers new substations at multiple voltage levels, as well as the supply and installation of 400kV extra-high-voltage power cables. The overall scheme is estimated to cost $650m.
It is being tendered as part of Kahramaa’s 2026 procurement plan, which includes 198 tenders with a total estimated value of QR21.4bn ($5.9bn).
According to sources, bids were submitted for the following packages on 20 August:
- Substation packages S1 and S2, covering new 132/11kV substations (estimated cost: $200m)
- Package S3, covering new 66/11kV substations ($50m)
- Package S4, including a new 400/220/132kV substation, as well as upgrades and modifications to existing 400kV and 220kV substations ($200m)
- Package S5, covering new 132/11kV substations and upgrades to existing 132kV and 66kV substations ($100m)
- Cable packages C1 and C2, covering 400kV cables ($100m)
Kahramaa previously stated that foreign companies not registered in Qatar would be allowed to participate in the bidding, subject to meeting specified conditions, including registration and certification requirements.
In June, the electricity and water utility awarded contracts worth more than QR2.2bn ($604m) to expand the electricity transmission network in the country’s western region.
The engineering, procurement and construction (EPC) works will support the integration of the 2GW Dukhan solar power project into Qatar’s national electricity grid. The scope includes new and upgraded substations, as well as the installation of underground cables and overhead transmission lines.
Kahramaa said contracts were awarded to local firm Voltage Engineering, Turkiye’s Best & Betas Consortium, India’s Larsen & Toubro and South Korea’s LS Cable.
Of Kahramaa’s 2026 procurement plan, electricity transmission projects account for QR8.9bn ($2.4bn) and include the construction of new 400/132kV substations in Al-Wukair and Al-Mashaf, as well as the expansion of 400kV substations at Ras Laffan.
These also cover the installation of 132kV underground cables between Al-Sailiya and Al-Rayyan over a 24-kilometre route, as well as upgrades to the 400kV and 220kV networks.
Additionally, there are 64 planned electricity distribution projects managed by the Electricity Distribution Department that cover the medium-voltage and low-voltage networks throughout Doha and the regional municipalities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18962223/main.jpg -
Maaden closes $1bn term loan and credit facility24 August 2026
Saudi Arabian Mining Company (Maaden) has announced the closing of its inaugural international syndicated term loan and revolving credit facilities, worth a total of $1bn.
The $500m international term loan facility will support Maaden’s growth agenda and general corporate purposes, including funding growth projects across its portfolio.
The $500m international revolving credit facility, which is expected to remain undrawn, provides additional committed funding capacity “as Maaden continues to scale its business and execute its long-term growth strategy”.
The transaction “was met with strong support from the international banking market, attracting participation from a diverse group of leading international banks across key global financial markets”, including the US, Canada, Europe, China and Japan. The facilities were oversubscribed, Maaden said.
ALSO READ: Maaden and Aramco sign deal to create joint venture
“The level of demand reflects the global banking community’s confidence in Maaden’s financial strength, strategic direction and ambitious growth plans,” the Saudi state miner said in its statement.
“The facilities mark another significant milestone in Maaden’s funding journey – further diversifying its sources of funding and broadening its access to global capital providers as the company continues to advance its long-term growth ambitions.
“Maaden continues to make significant progress across its growth pipeline, expanding production, advancing major projects and accelerating exploration as it builds a world-class mining company at the heart of Saudi Arabia’s economic transformation.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/18962086/main4516.jpg -
Dubai inflation slows to 5.3% in July24 August 2026
Dubai’s annual inflation rate slowed to 5.3% in July, down from 5.7% in June, as a decline in transport costs eased pressure on consumer prices, according to Emirates NBD.
The bank said the slowdown supported its view that price growth peaked at mid-year, and it expects inflation to continue easing through the rest of 2026. Monthly price growth slowed to 0.1% in July, from 0.4% in June, the weakest pace since February.
Transport was the clearest sign of the moderation. Annual price growth in the category slowed to 11.9% in July, from 18.1% in June, as transport costs fell 3.7% over the month. Fuel and lubricant inflation eased to 24.1% year on year, from 48.3%, tracking a decline in local petrol prices.
Petrol remains the main swing factor in the emirate’s inflation. Transport contributed 1.1 percentage points to headline inflation in July, down from 1.7 percentage points in June. Emirates NBD said the relief may prove temporary, with Super 98 petrol prices climbing 5.9% in August to leave them 33.8% higher than a year earlier. The bank expects headline inflation to edge higher in the August figures before easing again later in the year.
The UAE deregulated petrol and diesel prices in 2015 and reviews them monthly against global prices, meaning changes in global fuel costs pass through to consumers quickly. Transport, which includes fuel, accounts for 9% of Dubai’s consumer price index basket.
Housing remained the largest contributor to inflation even as its impulse faded. Housing and utilities, which account for about two-fifths of the basket, added 2.8 percentage points to headline inflation. Annual price growth in the category slowed to 7.0%, from 7.4% in January.
Food inflation edged up to 7.8% year on year, from 7.6% in June, which the bank attributed to lingering supply-chain disruption from the regional conflict. Inflation in restaurants and hotels accelerated to 4.5% year on year, from 1.7% in June.
Emirates NBD forecasts inflation of 2.9% by year-end but said risks to that projection were tilted to the upside, given lingering pressures in food and housing.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18961735/main1839.jpg -
Libya oil project on track for 2027 completion24 August 2026

The project to develop a workers’ camp at Libya’s Erawin oil field is on track for completion next year, according to industry sources.
The project, estimated to be worth about $50m, is being executed by the Libyan oil services company Al-Saraya Al-Hamara, headquartered in the city of Sebha.
The Libyan company was awarded the contract in February 2025.
The scope of the project includes:
- Construction of an accommodation camp
- Construction of the camp maintenance warehouse
- Construction of the camp office
- Construction of a fire brigade shelter
- Construction of a kitchen and mess hall
- Construction of a mosque
- Construction of a laundry room
- Construction of a clinic
- Construction of parking facilities
- Installation of a fire and gas system
- Installation of a power generator
- Construction of associated facilities
The client on the project is Zallaf Libya Oil & Gas Exploration & Production Company.
Zallaf Libya Oil & Gas Exploration & Production Company was established in Libya in 2013 and is wholly owned by Libya’s state-owned National Oil Corporation.
The Erawin field development project is located about 800 kilometres south of Tripoli and 100km southwest of the El-Sharara field.
Libya shipped its first cargo of crude from the Erawin oil field in November 2023.
The shipment departed from Libya’s Zawiyah port and consisted of 600,000 barrels of crude.
Australia-based Worley Parsons was appointed as the front-end engineering and design (feed) contractor for the early production facility project in 2019.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18953632/main.jpg