Iraq electricity sector makes slow progress
9 May 2024
Latest news from Iraq's power and water sectors:
> Iraq plans new Baiji power plant
> Decision imminent on Iraq waste-to-energy project
> Iraq discusses nuclear projects with global watchdog
> Siemens Energy and SLB sign Iraq flare gas-to-power deal
> PowerChina in talks for Basra desalination plant
> US seeks firms for Baghdad power plant package
> Iraq plans green hydrogen project at refinery
> Iraq approves long-term grid expansion

In late March, Iraq’s Electricity Ministry struck a five-year gas supply deal with National Iranian Gas Company for up to 50 million cubic metres a day (cm/d), contingent on the needs of Iraqi power stations, in exchange for oil and gasoline.
The deal offers a lifeline to Iraq’s deteriorating electricity sector and replaces an existing agreement whereby contractual volumes were theoretically set at 70 million cm/d for summer and 45 million cm/d for winter.
The two countries signed the deal following nearly three months of longer-than-usual power outages in Iraq, and after Baghdad settled part of the multibillion-dollar debt it owes Iran. The power cuts occurred due to a drastic reduction in Irani gas supply, which dipped to 10 million cm/d and wiped out 4GW from Iraq’s grid.
The deal is a compromise for both countries. It allows Iraq some breathing space to implement projects to reduce its dependence on Iran’s gas exports – a long-running and elusive objective among Iraq’s policymakers and its allies in the GCC states and the US.
The crisis should prompt Iraq to push ahead with projects to boost domestic gas production and build solar power plants, according to the Electricity Ministry.
Supply and demand mismatch
There has been a persistent mismatch between supply and demand in Iraq’s electricity sector, with peak demand during the summer months outstripping available capacity by a sizeable margin.
In recent years, the deficit has returned during the winter when heating requirements rise.
With a few exceptions, however, the procurement process or negotiations for additional generation capacity have been proceeding slowly, leaving a gap that is typically addressed by diesel generators.
Iraq aspires to build 12,000MW of solar capacity by the end of the decade, which is nearly half its known available capacity today.
The Electricity Ministry has signed deals with several companies to develop sizeable solar photovoltaic (PV) capacity over the past two to three years in line with this objective. Yet, despite regular pronouncements that the construction phase for these projects is about to start, none have reached final investment decisions (FIDs) or the construction phase so far.
The Electricity Ministry remains the dominant client for these projects, although the National Investment Commission (NIC) has been an active participant, particularly in bilateral or public-private partnership projects.
For example, the UAE’s Masdar signed a deal to develop 2GW of solar capacity in Iraq with the NIC. The commission is also procuring a contract to develop the country’s first waste-to-energy (WTE) project in coordination with the Municipality of Baghdad, the Electricity Ministry and the Environment Ministry.
Located in the Al Nahrawan area of Baghdad Governorate, the planned WTE project will have the capacity to treat 3,000 tonnes of waste a day and generate nearly 80 megawatt-hours (MWh) of electricity.
Other companies that have committed to develop solar PV projects in Iraq include Power China, which has pledged to develop solar PV projects with a combined total capacity of 2GW, and France’s Total Energies, which has committed to build a 1,000MW solar farm in Artawi.
The solar project in Artawi is a small part of a $27bn package that TotalEnergies is developing in partnership with QatarEnergy. The package involves the development of a common seawater supply project and oil and gas fields in Iraq.
Awarded projects
As earlier cited, there are some exceptions to the endemic start-stop mode for Iraq’s power generation and distribution projects.
For example, Germany’s Siemens Energy and the US-based GE have ongoing projects that include retrofitting or upgrading existing gas turbine power stations or building new substations as part of agreements to help rebuild Iraq and support its goal of reducing carbon emissions.
Earlier this month, the Electricity Ministry signed a preliminary agreement with Germany’s Siemens Energy and US firm SLB, formerly Schlumberger, to explore the development of a power generation plant using flare gas.
According to Siemens Energy Middle East managing director Dietmar Siersdorfer, the planned flare gas-to-power project in southern Iraq will help reduce carbon dioxide emissions and capture value from gas that would otherwise be wasted.
The planned flare gas-to-power plant could have a generation capacity of up to 2,000MW.
In January this year, China-based Oriental International is understood to have signed a contract to convert a single-cycle unit at the Baghdad South power plant complex into a combined-cycle power plant.
In April, the Electricity Ministry awarded another Chinese company, China Machinery Engineering Corporation (CMEC), a second year of operation and maintenance contracts for the Salah Al Din gas-fired power plant.
CMEC was awarded the estimated $1bn contract to build the power plant in northern Iraq in 2011. After a series of delays and challenges, including the Isis uprising, the two 630MW capacity units began operating last year.
In December last year, Siemens Energy also signed a contract to deliver five high-voltage substations on a turnkey basis in Iraq. The 400-kilovolt substations, each with a capacity of 1,500MW, will be installed in Baghdad, Diyala, Najaf, Karbala and Basra.
Similarly, the US’s preoccupation with helping wean Iraq off Iran’s gas and electricity imports has spurred projects to interconnect Iraq’s grid with its neighbour Saudi Arabia through the GCC grid and Jordan.
In October last year, the governor of Saudi Arabia’s Eastern Province, Prince Saud Bin Naif Bin Abdulaziz, inaugurated the GCC grid's Iraq connection, which had been under development for several years. The 295-kilometre power transmission network will have a total transmission capacity of 1,800MW, with an initial phase expected to supply 500MW of electricity to Iraq.
Future projects
In February this year, Electricity Ministry spokesperson Ahmed Mousa said the government had approved funds for the long-term plans to expand the country’s power transmission and distribution network with Siemens Energy’s help.
Mousa said the ministry “received funds for long-term plans to develop the electricity sector in 2023 … the three-year budget approved in 2023 also includes funds this year and in 2025”.
In early May, it was reported that the Electricity Ministry held discussions with Qatar’s UCC Holding to develop a 2,100MW gas-fired power plant in Baiji. The plant will replace a power station that was damaged during the war.
It is unclear if the project is part of a previous agreement between UCC Holding and NIC to develop two power plants with a capacity of 2,400MW in Iraq.
A new 2,000MW gas-fired power plant is also being proposed in Basra, which is expected to receive gas from the nearby West Qurna 1 and West Qurna 2 oil fields.
As it is, several projects are waiting for final approvals, such as the gas-fired 2,800MW Khairat independent power producer, which has yet to reach FID over two years after the contract was awarded.
Going nuclear
Project delays and indecision in Iraq do not appear to narrow down the options for future power generation expansion.
In March, it was reported that senior Iraq and International Atomic Energy Agency (IAEA) officials had discussed Iraq’s plans for a possible nuclear energy programme, including small modular reactors.
According to the nuclear watchdog, discussions included maintaining strict adherence to non-proliferation norms.
IAEA director general Rafael Mariano Grossi said his agency has committed to supporting the foundations of what should be an entirely peaceful programme in Iraq.
Iraq, for its part, is considering nuclear energy to enable greater energy security and for water desalination projects as part of the country’s plans for a more sustainable future.
Exclusive from Meed
-
-
Bidders compete for new Dubai Metro line project14 May 2026
-
Local firm wins $100m Kuwait substation contract14 May 2026
-
Al-Ain breaks ground on Four Seasons Saadiyat14 May 2026
-
Aldar acquires Dubai Studio City development14 May 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Consortiums prepare bids for Al-Khairan phase one IWPP14 May 2026

Two developer consortiums are finalising bids for the first phase of Kuwait’s Al-Khairan independent water and power producer (IWPP) project, the deadline for which has been extended to 1 June.
The facility will have a capacity of 1,800MW and 150,000 cubic metres a day of desalinated water. It will be located in Al-Khairan, adjacent to the Al-Zour South thermal plant.
The project is expected to run on Low Sulphur Fuel Oil (LSFO) as the primary fuel and to accommodate crude oil, gas oil, and natural gas as backup fuels. Later phases will further expand capacity.
The main contract was tendered last September. Three consortiums and two individual companies were previously prequalified to participate, with the following groups currently preparing offers:
- Abu Dhabi National Energy Company (Taqa) / A H Al-Sagar & Brothers (Saudi Arabia)
- Acwa (Saudi Arabia) / Gulf Investment Corporation (Kuwait)
The two individual companies, Sumitomo Corporation (Japan) and Nebras Power (Qatar), are now “unlikely” to submit a bid, according to a source close to the project.
It is also understood that the third consortium of China Power, Malakoff International (Malaysia) and Abdul Aziz Al-Ajlan Sons (Saudi Arabia) is no longer bidding for the contract.
The project is being procured by the Kuwait Authority for Partnership Projects (Kapp) and the Ministry of Electricity, Water & Renewable Energy (MEWRE).
The Al-Khairan IWPP project is part of Kuwait’s long-term plan to expand power and water production capacity through public-private partnerships (PPPs).
The winning bidder will sign a set of PPP agreements covering financing, design, construction, operation and transfer of the project.
The energy conversion and water purchase agreement is expected to cover a 25-year supply period.
Upcoming awards
Kuwait is also preparing to offer a contract to develop zone one of the third phase of the Al-Dibdibah power and Al-Shagaya renewable energy project.
In January, three consortiums submitted bids for a contract to develop Kuwait’s first utility-scale solar photovoltaic (PV) plant.
The Al-Dibdibah power and Al-Shagaya renewable energy phase three, zone one independent power project (IPP) will have a total power-generating capacity of 1,100MW.
MEED understands that the preferred bidder announcement will happen after the bid closes for zone two of the third phase of the Al-Dibdibah power and Al-Shagaya renewable energy project.
The PPP authority is procuring the 500MW solar photovoltaic IPP in partnership with the ministry.
The bid deadline for this project was recently extended to 31 May.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16835649/main.jpg -
Bidders compete for new Dubai Metro line project14 May 2026

Register for MEED’s 14-day trial access
Dubai’s Roads & Transport Authority (RTA) has held a pre-bid meeting for the Dubai Metro Airport Express Line with consultants understood to be competing for work on the project.
It is understood that the RTA has requested firms to form joint ventures for the project. The firms that attended the meeting include:
- Aecom (US)
- Arup (UK)
- ARX (Switzerland)
- AtkinsRealis (Canada)
- DB (Germany)
- Egis (France)
- Jacobs (US)
- Mott Macdonald (UK)
- Parsons (US)
- Sener (Spain)
- Surbana Jurong (Singapore)
- Systra (France)
- WSP (Canada)
The consultancy contract covers the study and design of the Airport Express Line, which will extend from the Al-Garhoud area of the city to Al-Maktoum International airport (DWC) in the Jebel Ali area. The proposed line will stretch about 55 kilometres (km) and include five stations, providing passengers with facilities such as remote airline check-in, baggage drop-off and security screening.
Consultants have been allowed until June to submit their proposals.
The new line will run from the Red Line metro station at Dubai International airport through Al-Jaddaf, along Al-Khail Road to a new station at Jumeirah Village Circle (JVC) before continuing on to DWC.
There will be two spur lines. The first will run from the new JVC station to the Al-Fardan Exchange metro station at Emirates Golf Club, while the second will branch out towards Business Bay, where another station will be built.
The new line appears to follow a similar route to the Etihad Rail high-speed railway project, which is now under construction and due to be completed by 2030.
Route 2020 extension
The Airport Express Line scheme is the latest metro project to be tendered by the RTA this year. Tendering activity is already ongoing for the Route 2020 extension, which will start from the Expo 2020 metro station and connect to DWC’s West Terminal.
In April, MEED exclusively reported that consultants had submitted bids for the project.
The extension to the line will run for about 3km and will feature two stations.
The existing Route 2020 metro link is a 15km-long line that branches off the Red Line at Jebel Ali metro station. The line comprises 11.8km of elevated tracks and 3.2km of tunnels, and has five elevated stations and two underground stations.
The RTA awarded the AED10.6bn ($2.9bn) design-and-build contract for the project to a consortium of Spain’s Acciona, Turkiye’s Gulermak and France’s Alstom in 2016.
Gold Line
Dubai’s plans for its metro network do not stop with connecting the extension of the Route 2020 metro line to DWC. There are long-term plans for further extensions.
In October last year, MEED exclusively reported that the RTA had selected US-based engineering firm Aecom to provide consultancy services for the upcoming Dubai Metro Gold Line project, also known as Metro Line 4.
The Gold Line will start at Al-Ghubaiba in Bur Dubai. It will run parallel to – and alleviate pressure on – the existing Red Line, before heading inland to Business Bay, Meydan, Global Village and residential developments in Dubailand.
The existing network includes the Red and Green lines of the Dubai Metro and the Dubai Tram, which connects Al-Sufouh and Dubai Marina to the metro network. The last rail project to start operations in Dubai was the Red Line extension that opened for Expo 2020.
There are also existing and planned rail lines connecting Dubai to other emirates that are being developed and operated by Abu Dhabi-based Etihad Rail. These include passenger and freight services, as well as a high-speed rail connection.
Blue Line
In December 2024, the RTA awarded a AED20.5bn main contract for the Dubai Metro Blue Line project to a consortium of Turkish firms Limak Holding and Mapa Group and the Hong Kong office of China Railway Rolling Stock Corporation.
The Blue Line consists of 14 stations, including three interchange stations at Jaddaf, Rashidiya and International City 1, as well as a station in Dubai Creek Harbour.
By 2040, the number of daily passengers on the Blue Line is projected to reach 320,000. It will be the first Dubai Metro line to cross Dubai Creek, doing so on a 1,300-metre viaduct.
> Be recognised among the best in the industry at the MEED Projects Awards 2026 …
https://image.digitalinsightresearch.in/uploads/NewsArticle/16833450/main.jpg -
Local firm wins $100m Kuwait substation contract14 May 2026

The local Al-Ahleia Switchgear Company has won an engineering, procurement and construction contract for a $100m substation project in Wafra in Kuwait’s Al-Ahmadi Governorate.
According to a source, the firm has been appointed as the contractor for the Wafra 2Z substation 400/132/33kV project, with construction scheduled for completion in January 2029.
The contract was awarded by US-headquartered Chevron, which is undertaking its first major power project in Kuwait, according to data from MEED Projects.
It is understood that contractor bids for the project were first submitted in 2023 by National Contracting Company (Kuwait), Al-Ahleia Switchgear (Kuwait), Imco Engineering & Construction Company (Kuwait) and Larsen & Toubro (India).
The tender was cancelled in 2024, and a new tender was issued last year.
In April, Al-Ahleia Switchgear won a contract to build a 400/132/11kV substation at the South Surra township for Kuwait’s Public Authority for Housing Welfare.
The firm also recently won a separate contract in Oman for the supply, installation, execution and maintenance of a main power substation.
The contract was awarded by Oman’s Public Authority for Social Insurance as part of its affordable housing project, known locally as Al-Masaken Al-Muyassara.
According to MEED Projects, Chevron owns about $11.2bn-worth of operational oil and gas projects across the Middle East and Africa. It also owns four major power generation projects in Saudi Arabia, valued at $810m.
> Be recognised among the best in the industry at the MEED Projects Awards 2026 …
https://image.digitalinsightresearch.in/uploads/NewsArticle/16832909/main.jpg -
Al-Ain breaks ground on Four Seasons Saadiyat14 May 2026
Al-Ain Asset Management has held a groundbreaking ceremony for its Four Seasons Private Residences Abu Dhabi project at Saadiyat Beach.
Due for completion in 2029, the gated beachfront scheme will comprise 116 ultra-luxury homes with direct beach access. The unit mix includes villas, beachfront mansions, suites and penthouses, alongside a range of bespoke amenities and Four Seasons-branded services, Wam reported.
Al-Ain Asset Management said the majority of the residences have been sold, and that AED250m ($68m) of new villa sales were recorded within one week, underlining demand for ultra-prime homes in Abu Dhabi.
The developer added that the development set new pricing benchmarks for the emirate’s luxury coastal real estate, achieving prices above AED14,000 a square foot. Total sales have exceeded AED4bn since the project launched less than a year ago.
The groundbreaking ceremony was attended by senior leadership and key partners, including Four Seasons, Killa Design and Mirage Leisure & Development. LW Design Group is also involved in the development.
Al-Ain Asset Management is also developing another residential scheme on Saadiyat Island. The Vida Residences development will comprise apartment units geared towards long-stay living, supported by hotel-style facilities and operational spaces. Mimar Architecture & Engineering is working as the consultant.
> Be recognised among the best in the industry at the MEED Projects Awards 2026 …
https://image.digitalinsightresearch.in/uploads/NewsArticle/16833035/main.jpeg -
Aldar acquires Dubai Studio City development14 May 2026
Abu Dhabi-based developer Aldar has acquired a residential and community retail development in Dubai Studio City from Dubai-based developer SRG for AED1.1bn ($300m).
The deal is part of Aldar’s long-term strategy to build a high-quality, recurring-income portfolio and to scale its presence in the city.
Scheduled for delivery in 2028, the project comprises six mid-rise buildings with 312 homes, including one-, two- and three-bedroom apartments and duplexes. It also includes a community mall with retail, leisure and food-and-beverage offerings, as well as a 16,000-square-metre park.
“Dubai is a priority growth market for Aldar, and this acquisition reflects our belief in the city’s residential market and the central role that institutionally owned, professionally managed rental housing plays in meeting the needs of a growing population,” said Jassem Saleh Busaibe, CEO of Aldar Investment.
“Dubai Studio City’s established infrastructure, vibrant community and strong connectivity make it an excellent location for a high-quality, professionally managed living environment. This transaction is the latest step in a deliberate and broadening strategy to build a diversified portfolio of income-generating assets in Dubai, one that we expect to continue growing as the city attracts increasing global interest and talent,” he added.
The transaction expands Aldar’s activities in Dubai across a range of property types. Aldar Investment’s recurring-income portfolio in the emirate now includes residential, commercial, logistics and mixed-use assets. Key holdings include a mixed-use joint venture with Expo City Dubai, a signature office tower in Dubai International Financial Centre, a Grade A office building on Sheikh Zayed Road, and logistics facilities in National Industries Park and Dubai South.
On the development front, Aldar’s partnership with Dubai Holding continues to gain traction, with three master-planned residential communities already launched and a pipeline exceeding 2.3 million sq m of new gross floor area.
> Be recognised among the best in the industry at the MEED Projects Awards 2026 …
https://image.digitalinsightresearch.in/uploads/NewsArticle/16832033/main.jpg
