Iraq electricity sector makes slow progress
9 May 2024
Latest news from Iraq's power and water sectors:
> Iraq plans new Baiji power plant
> Decision imminent on Iraq waste-to-energy project
> Iraq discusses nuclear projects with global watchdog
> Siemens Energy and SLB sign Iraq flare gas-to-power deal
> PowerChina in talks for Basra desalination plant
> US seeks firms for Baghdad power plant package
> Iraq plans green hydrogen project at refinery
> Iraq approves long-term grid expansion

In late March, Iraq’s Electricity Ministry struck a five-year gas supply deal with National Iranian Gas Company for up to 50 million cubic metres a day (cm/d), contingent on the needs of Iraqi power stations, in exchange for oil and gasoline.
The deal offers a lifeline to Iraq’s deteriorating electricity sector and replaces an existing agreement whereby contractual volumes were theoretically set at 70 million cm/d for summer and 45 million cm/d for winter.
The two countries signed the deal following nearly three months of longer-than-usual power outages in Iraq, and after Baghdad settled part of the multibillion-dollar debt it owes Iran. The power cuts occurred due to a drastic reduction in Irani gas supply, which dipped to 10 million cm/d and wiped out 4GW from Iraq’s grid.
The deal is a compromise for both countries. It allows Iraq some breathing space to implement projects to reduce its dependence on Iran’s gas exports – a long-running and elusive objective among Iraq’s policymakers and its allies in the GCC states and the US.
The crisis should prompt Iraq to push ahead with projects to boost domestic gas production and build solar power plants, according to the Electricity Ministry.
Supply and demand mismatch
There has been a persistent mismatch between supply and demand in Iraq’s electricity sector, with peak demand during the summer months outstripping available capacity by a sizeable margin.
In recent years, the deficit has returned during the winter when heating requirements rise.
With a few exceptions, however, the procurement process or negotiations for additional generation capacity have been proceeding slowly, leaving a gap that is typically addressed by diesel generators.
Iraq aspires to build 12,000MW of solar capacity by the end of the decade, which is nearly half its known available capacity today.
The Electricity Ministry has signed deals with several companies to develop sizeable solar photovoltaic (PV) capacity over the past two to three years in line with this objective. Yet, despite regular pronouncements that the construction phase for these projects is about to start, none have reached final investment decisions (FIDs) or the construction phase so far.
The Electricity Ministry remains the dominant client for these projects, although the National Investment Commission (NIC) has been an active participant, particularly in bilateral or public-private partnership projects.
For example, the UAE’s Masdar signed a deal to develop 2GW of solar capacity in Iraq with the NIC. The commission is also procuring a contract to develop the country’s first waste-to-energy (WTE) project in coordination with the Municipality of Baghdad, the Electricity Ministry and the Environment Ministry.
Located in the Al Nahrawan area of Baghdad Governorate, the planned WTE project will have the capacity to treat 3,000 tonnes of waste a day and generate nearly 80 megawatt-hours (MWh) of electricity.
Other companies that have committed to develop solar PV projects in Iraq include Power China, which has pledged to develop solar PV projects with a combined total capacity of 2GW, and France’s Total Energies, which has committed to build a 1,000MW solar farm in Artawi.
The solar project in Artawi is a small part of a $27bn package that TotalEnergies is developing in partnership with QatarEnergy. The package involves the development of a common seawater supply project and oil and gas fields in Iraq.
Awarded projects
As earlier cited, there are some exceptions to the endemic start-stop mode for Iraq’s power generation and distribution projects.
For example, Germany’s Siemens Energy and the US-based GE have ongoing projects that include retrofitting or upgrading existing gas turbine power stations or building new substations as part of agreements to help rebuild Iraq and support its goal of reducing carbon emissions.
Earlier this month, the Electricity Ministry signed a preliminary agreement with Germany’s Siemens Energy and US firm SLB, formerly Schlumberger, to explore the development of a power generation plant using flare gas.
According to Siemens Energy Middle East managing director Dietmar Siersdorfer, the planned flare gas-to-power project in southern Iraq will help reduce carbon dioxide emissions and capture value from gas that would otherwise be wasted.
The planned flare gas-to-power plant could have a generation capacity of up to 2,000MW.
In January this year, China-based Oriental International is understood to have signed a contract to convert a single-cycle unit at the Baghdad South power plant complex into a combined-cycle power plant.
In April, the Electricity Ministry awarded another Chinese company, China Machinery Engineering Corporation (CMEC), a second year of operation and maintenance contracts for the Salah Al Din gas-fired power plant.
CMEC was awarded the estimated $1bn contract to build the power plant in northern Iraq in 2011. After a series of delays and challenges, including the Isis uprising, the two 630MW capacity units began operating last year.
In December last year, Siemens Energy also signed a contract to deliver five high-voltage substations on a turnkey basis in Iraq. The 400-kilovolt substations, each with a capacity of 1,500MW, will be installed in Baghdad, Diyala, Najaf, Karbala and Basra.
Similarly, the US’s preoccupation with helping wean Iraq off Iran’s gas and electricity imports has spurred projects to interconnect Iraq’s grid with its neighbour Saudi Arabia through the GCC grid and Jordan.
In October last year, the governor of Saudi Arabia’s Eastern Province, Prince Saud Bin Naif Bin Abdulaziz, inaugurated the GCC grid's Iraq connection, which had been under development for several years. The 295-kilometre power transmission network will have a total transmission capacity of 1,800MW, with an initial phase expected to supply 500MW of electricity to Iraq.
Future projects
In February this year, Electricity Ministry spokesperson Ahmed Mousa said the government had approved funds for the long-term plans to expand the country’s power transmission and distribution network with Siemens Energy’s help.
Mousa said the ministry “received funds for long-term plans to develop the electricity sector in 2023 … the three-year budget approved in 2023 also includes funds this year and in 2025”.
In early May, it was reported that the Electricity Ministry held discussions with Qatar’s UCC Holding to develop a 2,100MW gas-fired power plant in Baiji. The plant will replace a power station that was damaged during the war.
It is unclear if the project is part of a previous agreement between UCC Holding and NIC to develop two power plants with a capacity of 2,400MW in Iraq.
A new 2,000MW gas-fired power plant is also being proposed in Basra, which is expected to receive gas from the nearby West Qurna 1 and West Qurna 2 oil fields.
As it is, several projects are waiting for final approvals, such as the gas-fired 2,800MW Khairat independent power producer, which has yet to reach FID over two years after the contract was awarded.
Going nuclear
Project delays and indecision in Iraq do not appear to narrow down the options for future power generation expansion.
In March, it was reported that senior Iraq and International Atomic Energy Agency (IAEA) officials had discussed Iraq’s plans for a possible nuclear energy programme, including small modular reactors.
According to the nuclear watchdog, discussions included maintaining strict adherence to non-proliferation norms.
IAEA director general Rafael Mariano Grossi said his agency has committed to supporting the foundations of what should be an entirely peaceful programme in Iraq.
Iraq, for its part, is considering nuclear energy to enable greater energy security and for water desalination projects as part of the country’s plans for a more sustainable future.
Exclusive from Meed
-
Executive briefing: US-Israel-Iran conflict6 March 2026
-
-
UAE utilities say services stable amid tensions6 March 2026
-
Drawn-out conflict may shift planning priorities6 March 2026
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Executive briefing: US-Israel-Iran conflict6 March 2026
In this executive briefing, Ed James and Colin Foreman from MEED outline the key developments in the US-Israel-Iran conflict and examine the potential economic, infrastructure and market impacts across the Middle East.
Drawing on regional data and analysis, the briefing explores the drivers behind the escalation, the scale of attacks across GCC states, and the possible short- and long-term implications for energy markets, shipping, aviation and regional investment.
For ongoing updates and verified reporting as events unfold, follow MEED’s mega thread here.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15890483/main.gif -
Kuwait extends bid deadline for Al-Khairan phase one IWPP6 March 2026

Kuwait has extended bidding for the first phase of the Al-Khairan independent water and power producer (IWPP) project.
The project is being procured by the Kuwait Authority for Partnership Projects (Kapp) and the Ministry of Electricity, Water & Renewable Energy (MEWRE).
The facility will have a capacity of 1,800MW and 33 million imperial gallons a day (MIGD) of desalinated water.
It will be located at Al-Khairan, adjacent to the Al-Zour South thermal plant.
The new deadline is 30 April.
The main contract was tendered last September, and the deadline had already been extended once, most recently until 4 March.
Three consortiums and two individual companies were previously prequalified to participate.
These include:
- Abu Dhabi National Energy Company (Taqa) / A H Al-Sagar & Brothers (Saudi Arabia) / Jera (Japan)
- Acwa (Saudi Arabia) / Gulf Investment Corporation (Kuwait)
- China Power / Malakoff International (Malaysia) / Abdul Aziz Al-Ajlan Sons (Saudi Arabia)
- Nebras Power (Qatar)
- Sumitomo Corporation (Japan)
The Al-Khairan IWPP project is part of Kuwait’s long-term plan to expand power and water production capacity through public-private partnerships (PPPs).
The winning bidder will sign a set of PPP agreements covering financing, design, construction, operation and transfer of the project.
The energy conversion and water purchase agreement is expected to cover a 25-year supply period.
Kapp extended another deadline recently for a contract to develop zone two of the third phase of the Al-Dibdibah power and Al-Shagaya renewable energy project.
The PPP authority is procuring the 500MW solar photovoltaic independent power project (IPP) in partnership with the ministry.
The bid submission deadline was moved to the end of April, a source close to the project told MEED.
According to the MEWRE, the total generation capacity currently offered under partnership projects has reached 6,100MW, equivalent to about 30% of Kuwait’s existing power capacity.
The ministry and Kapp are also preparing to tender the main contract for the 3,600MW Nuwaiseeb power and water desalination plant after plans were approved by Kuwait’s Council of Ministers last November.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15889101/main.jpg -
UAE utilities say services stable amid tensions6 March 2026
Register for MEED’s 14-day trial access
Abu Dhabi National Energy Company (Taqa) and Etihad Water & Electricity (EtihadWE) have confirmed that water and electricity services in the UAE are operating normally amid ongoing regional tensions.
In a statement, Taqa said it had activated its risk management frameworks and “power generation, water desalination, transmission, distribution and wastewater services are operating safely and without interruption”.
According to Etihad WE, services are being delivered with “approved response plans” and “precautionary operational procedures” amid the current regional circumstances.
Taqa is one of the UAE’s largest integrated utilities, with assets including the Taweelah B independent power and water (IWPP) plant and the 2,400MW Fujairah F3 combined-cycle power plant.
EtihadWE operates electricity and water distribution networks across the Northern Emirates, supplying more than two million residents.
Iran’s recent missile attacks on energy infrastructure across the GCC in retaliation for US-Israel attacks have drawn renewed attention to the importance of the region’s utilities sector.
While power and water assets have largely avoided damage, there have been some incidents affecting broader energy infrastructure.
Saudi Aramco had shut down its Ras Tanura refinery following a drone strike, while US cloud provider Amazon Web Services reported service outages after incidents at two data centres in the UAE.
In January, Taqa and Etihad won a contract alongside France’s Saur to develop and operate a major wastewater treatment plant in the UAE’s northern emirate of Ras Al-Khaimah.
The Rakwa wastewater infrastructure project is RAK’s first public-private partnership for a sewage treatment plant.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15888121/main.jpg -
Drawn-out conflict may shift planning priorities6 March 2026
Commentary
Mark Dowdall
Power & water editorAcross the GCC, power and water networks have largely been planned around steadily rising consumption, driven by population growth and cooling demand.
A drawn-out conflict in the region may begin to change how planners think about these systems – particularly how they can keep operating if parts of the network are disrupted.
On Thursday, Iran’s Energy Minister Abbas Aliabadi said that US-Israeli attacks had damaged water and electricity supply facilities in several parts of the country, while urging the public to be careful with water and electricity consumption.
So far, major power and water infrastructure in the GCC has largely avoided damage. In the case of desalination, plants of this scale supply drinking water to millions of people, so striking them would immediately affect civilian populations and represent a significant escalation.
There is also an element of mutual vulnerability. Iran relies on its own electricity and water infrastructure, and Aliabadi’s comments this week suggest those systems are already under pressure. Targeting desalination plants in the GCC could invite similar disruptions at home.
However, if infrastructure disruption becomes a recurring risk in the region, the question may gradually shift from how to produce more water and electricity to how to reduce immediate reliance on continuous supply.
Some elements of that thinking are already visible in the project pipeline. In Saudi Arabia, for example, total reservoir storage capacity has reached about 25.1 million cubic metres, with roughly 44% located in the Mecca region and 31% in Riyadh. This provides a buffer that can sustain supply temporarily if desalination production is disrupted.
Additionally, the kingdom has about $8bn-worth of water storage projects in early study or feed stages. As regional tensions persist, schemes like this may move higher up the priority list.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15887101/main.jpg -
US oil companies to profit while Middle East exports are curtailed6 March 2026
While the oil and gas operations of the Middle East’s biggest producers are being dramatically curtailed by the conflict sparked by the US and Israel’s attack on Iran, US producers are likely to see windfall profits.
So far, the list of oil and gas assets in the Mena region disrupted by the conflict is long and includes facilities in all GCC nations, as well as Iraq and Iran itself.
In addition to oil fields and refineries that have been shut – either due to direct Iranian attacks or concerns over further strikes – about 20 million barrels a day (b/d) of production has been removed from the global market by the effective closure of the Strait of Hormuz.
Oil price
The disruption to global oil and gas supplies caused by the Iran conflict has pushed oil prices up by around 15%, with Brent briefly rising above $85 a barrel on 3 March – its highest level since July 2024.
This has boosted investor optimism about the outlook for US oil companies.
Texas-headquartered ExxonMobil made $56bn in profit in 2022 after Russia’s invasion of Ukraine created a sustained period of higher oil prices. It was a record year for the company, and it could see a similar bump this year if oil prices remain high.
Shale response
US shale producers are ramping up production to capitalise on higher oil prices, according to the Paris-based International Energy Agency (IEA).
Recently drilled shale wells could add around 240,000 b/d of supply in May, and an additional 400,000 b/d could be added in the second half of the year, according to an IEA document cited by the Financial Times.
Gas impact
The impact of the Iran conflict on liquefied natural gas (LNG) prices has been even more pronounced than on oil, with several gas benchmarks hitting multi-year highs.
The Dutch Title Transfer Facility rose by 55%, reaching its highest level since fuel markets spiked after Russia’s 2022 invasion of Ukraine.
One of the key factors driving prices higher was Qatar – the world’s second-biggest LNG producer – halting exports on 2 March after Iranian attacks on several facilities.
Qatar is expected to take at least several weeks to restart exports from its liquefaction terminals.
Not only will time be required to ensure the export route through the Strait of Hormuz is secure, but restarting LNG export terminals is also a gradual process. They require a slow restart to avoid damaging cryogenic equipment, which cools natural gas to around -160°C.
In addition, LNG trains must be brought back online sequentially; Qatar’s Ras Laffan hub has 14 trains.
US advantage
While the world’s second-biggest LNG producer is likely to be offline for some time, the US – the world’s biggest LNG producer – is already operating near full capacity and is benefiting from the higher-price environment.
Cheniere and Venture Global, the two biggest US LNG producers, have both seen their share prices rise amid the conflict.
Cheniere shares are up 18% since the start of February, while Venture Global’s share price has risen 12% over the same period.
The scale of additional revenues earned by US companies – and the revenue losses suffered in the Middle East’s oil and gas sector – will largely depend on how long the disruption linked to the Iran conflict continues.
If the disruption persists and significant long-term damage is done to Middle East oil and gas infrastructure, US-based oil and gas companies could record another year of record profits.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15886759/main.png
