Iraq electricity sector makes slow progress

9 May 2024

Latest news from Iraq's power and water sectors:

> Iraq plans new Baiji power plant
> Decision imminent on Iraq waste-to-energy project
> Iraq discusses nuclear projects with global watchdog
Siemens Energy and SLB sign Iraq flare gas-to-power deal
PowerChina in talks for Basra desalination plant
US seeks firms for Baghdad power plant package
Iraq plans green hydrogen project at refinery
Iraq approves long-term grid expansion


 

In late March, Iraq’s Electricity Ministry struck a five-year gas supply deal with National Iranian Gas Company for up to 50 million cubic metres a day (cm/d), contingent on the needs of Iraqi power stations, in exchange for oil and gasoline.

The deal offers a lifeline to Iraq’s deteriorating electricity sector and replaces an existing agreement whereby contractual volumes were theoretically set at 70 million cm/d for summer and 45 million cm/d for winter.

The two countries signed the deal following nearly three months of longer-than-usual power outages in Iraq, and after Baghdad settled part of the multibillion-dollar debt it owes Iran. The power cuts occurred due to a drastic reduction in Irani gas supply, which dipped to 10 million cm/d and wiped out 4GW from Iraq’s grid.

The deal is a compromise for both countries. It allows Iraq some breathing space to implement projects to reduce its dependence on Iran’s gas exports – a long-running and elusive objective among Iraq’s policymakers and its allies in the GCC states and the US.

The crisis should prompt Iraq to push ahead with projects to boost domestic gas production and build solar power plants, according to the Electricity Ministry.

Supply and demand mismatch

There has been a persistent mismatch between supply and demand in Iraq’s electricity sector, with peak demand during the summer months outstripping available capacity by a sizeable margin.

In recent years, the deficit has returned during the winter when heating requirements rise.

With a few exceptions, however, the procurement process or negotiations for additional generation capacity have been proceeding slowly, leaving a gap that is typically addressed by diesel generators.

Iraq aspires to build 12,000MW of solar capacity by the end of the decade, which is nearly half its known available capacity today.

The Electricity Ministry has signed deals with several companies to develop sizeable solar photovoltaic (PV) capacity over the past two to three years in line with this objective. Yet, despite regular pronouncements that the construction phase for these projects is about to start, none have reached final investment decisions (FIDs) or the construction phase so far.

The Electricity Ministry remains the dominant client for these projects, although the National Investment Commission (NIC) has been an active participant, particularly in bilateral or public-private partnership projects.

For example, the UAE’s Masdar signed a deal to develop 2GW of solar capacity in Iraq with the NIC. The commission is also procuring a contract to develop the country’s first waste-to-energy (WTE) project in coordination with the Municipality of Baghdad, the Electricity Ministry and the Environment Ministry.

Located in the Al Nahrawan area of Baghdad Governorate, the planned WTE project will have the capacity to treat 3,000 tonnes of waste a day and generate nearly 80 megawatt-hours (MWh) of electricity.

Other companies that have committed to develop solar PV projects in Iraq include Power China, which has pledged to develop solar PV projects with a combined total capacity of 2GW, and France’s Total Energies, which has committed to build a 1,000MW solar farm in Artawi.

The solar project in Artawi is a small part of a $27bn package that TotalEnergies is developing in partnership with QatarEnergy. The package involves the development of a common seawater supply project and oil and gas fields in Iraq.

Awarded projects

As earlier cited, there are some exceptions to the endemic start-stop mode for Iraq’s power generation and distribution projects.

For example, Germany’s Siemens Energy and the US-based GE have ongoing projects that include retrofitting or upgrading existing gas turbine power stations or building new substations as part of agreements to help rebuild Iraq and support its goal of reducing carbon emissions.

Earlier this month, the Electricity Ministry signed a preliminary agreement with Germany’s Siemens Energy and US firm SLB, formerly Schlumberger, to explore the development of a power generation plant using flare gas.

According to Siemens Energy Middle East managing director Dietmar Siersdorfer, the planned flare gas-to-power project in southern Iraq will help reduce carbon dioxide emissions and capture value from gas that would otherwise be wasted.

The planned flare gas-to-power plant could have a generation capacity of up to 2,000MW.

In January this year, China-based Oriental International is understood to have signed a contract to convert a single-cycle unit at the Baghdad South power plant complex into a combined-cycle power plant.

In April, the Electricity Ministry awarded another Chinese company, China Machinery Engineering Corporation (CMEC), a second year of operation and maintenance contracts for the Salah Al Din gas-fired power plant.

CMEC was awarded the estimated $1bn contract to build the power plant in northern Iraq in 2011. After a series of delays and challenges, including the Isis uprising, the two 630MW capacity units began operating last year.

In December last year, Siemens Energy also signed a contract to deliver five high-voltage substations on a turnkey basis in Iraq. The 400-kilovolt substations, each with a capacity of 1,500MW, will be installed in Baghdad, Diyala, Najaf, Karbala and Basra.

Similarly, the US’s preoccupation with helping wean Iraq off Iran’s gas and electricity imports has spurred projects to interconnect Iraq’s grid with its neighbour Saudi Arabia through the GCC grid and Jordan.

In October last year, the governor of Saudi Arabia’s Eastern Province, Prince Saud Bin Naif Bin Abdulaziz, inaugurated the GCC grid's Iraq connection, which had been under development for several years. The 295-kilometre power transmission network will have a total transmission capacity of 1,800MW, with an initial phase expected to supply 500MW of electricity to Iraq.

Future projects

In February this year, Electricity Ministry spokesperson Ahmed Mousa said the government had approved funds for the long-term plans to expand the country’s power transmission and distribution network with Siemens Energy’s help.

Mousa said the ministry “received funds for long-term plans to develop the electricity sector in 2023 … the three-year budget approved in 2023 also includes funds this year and in 2025”. 

In early May, it was reported that the Electricity Ministry held discussions with Qatar’s UCC Holding to develop a 2,100MW gas-fired power plant in Baiji. The plant will replace a power station that was damaged during the war.

It is unclear if the project is part of a previous agreement between UCC Holding and NIC to develop two power plants with a capacity of 2,400MW in Iraq.

A new 2,000MW gas-fired power plant is also being proposed in Basra, which is expected to receive gas from the nearby West Qurna 1 and West Qurna 2 oil fields.

As it is, several projects are waiting for final approvals, such as the gas-fired 2,800MW Khairat independent power producer, which has yet to reach FID over two years after the contract was awarded.  

Going nuclear 

Project delays and indecision in Iraq do not appear to narrow down the options for future power generation expansion.  

In March, it was reported that senior Iraq and International Atomic Energy Agency (IAEA) officials had discussed Iraq’s plans for a possible nuclear energy programme, including small modular reactors.

According to the nuclear watchdog, discussions included maintaining strict adherence to non-proliferation norms.

IAEA director general Rafael Mariano Grossi said his agency has committed to supporting the foundations of what should be an entirely peaceful programme in Iraq.

Iraq, for its part, is considering nuclear energy to enable greater energy security and for water desalination projects as part of the country’s plans for a more sustainable future.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11745270/main.gif
Jennifer Aguinaldo
Related Articles
  • SLB passes evaluation for Kuwait upstream project

    12 December 2025

    The US-based oilfield services company SLB, formerly Schlumberger, has passed the technical bid evaluation for a major project to develop Kuwait’s Mutriba oil field.

    The Houston-headquartered company was the only bidder to pass the technical evaluation for the Mutriba integrated project management (IPM) contract.

    The minimum passing technical evaluation score was 75%.

    The full list of bidders was:

    • SLB (US): 97%
    • Halliburton (US): 72%
    • Weatherford (US): 61.5%

    The decision was finalised at a meeting of the Higher Purchase Committee (HPC) of state-owned Kuwait Petroleum Corporation (KPC) on 20 November 2025.

    According to a document published earlier this year by KOC, the IPM tender for the Mutriba field aims to “accelerate production through a comprehensive study that includes economic feasibility evaluation, well planning and long-term sustainability strategies”.

    The field was originally discovered in 2009.

    Commercial production from the Mutriba field started earlier this year, on 15 June, after several wells were connected to production facilities.

    The field is located in a relatively undeveloped area in northwest Kuwait and spans more than 230 square kilometres.

    The oil at the Mutriba field has unusually high hydrogen sulfide content, which can be as much as 40%.

    This presents operational challenges requiring specialised technologies and safety measures.

    In order to start producing oil at the field, KOC deployed multiphase pumps to increase hydrocarbon pressure and enable transportation to the nearest Jurassic production facilities in north Kuwait.

    The company also built long-distance pipelines stretching 50 to 70 kilometres, using high-grade corrosion-resistant materials engineered to withstand the high hydrogen sulfide levels and ensure long-term reliability.

    KOC also commissioned the Mutriba long-term testing facility in northwest Kuwait, with a nameplate capacity of around 5,000 barrels of oil a day (b/d) and 5 million standard cubic feet of gas a day (mmscf/d).

    Once this facility was commissioned, production stabilised at 5,000 b/d and 7 mmscf/d.

    In documents published earlier this year, KOC said that starting production from the field had “laid a solid foundation” for the IPM contract by generating essential reservoir and surface data that will guide future development.

    Future output from the field is expected to range between 80,000 and 120,000 b/d, in addition to approximately 150 mmscf/d of gas.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15235579/main.png
    Wil Crisp
  • SAR to tender new phosphate rail track section in January

    12 December 2025

     

    Saudi Arabian Railways (SAR) is expected to float another multibillion-riyal tender to double the tracks on the existing phosphate railway network, connecting the Waad Al-Shamal mines to Ras Al-Khair in the Eastern Province.

    MEED understands that the new tender – covering the second section of the track-doubling works, spanning more than 150 kilometres (km) – will be issued in January.

    The new tender follows SAR’s issuance of the tender for the project's first phase in November, which spans about 100km from the AZ1/Nariyah Yard to Ras Al-Khair.

    The scope includes track doubling, alignment modifications, new utility bridges, culvert widening and hydrological structures, as well as the conversion of the AZ1 siding into a mainline track.

    The scope also covers support for signalling and telecommunication systems.

    The tender notice was issued in late November, with a bid submission deadline of 20 January.

    Switzerland-based engineering firm ARX is the project consultant.

    MEED understands that these two packages are the first of four that SAR is expected to tender for the phosphate railway line.

    The other packages expected to be tendered shortly include the depot and the systems package.

    In 2023, MEED reported that SAR was planning two projects to increase its freight capacity, including an estimated SR4.2bn ($1.1bn) project to install a second track along the North Train Freight Line and construct three new freight yards.

    Formerly known as the North-South Railway, the North Train is a 1,550km-long freight line running from the phosphate and bauxite mines in the far north of the kingdom to the Al-Baithah junction. There, it diverges into a line southward to Riyadh and a second line running east to downstream fertiliser production and alumina refining facilities at Ras Al-Khair on the Gulf coast.

    Adding a second track and the freight yards will significantly increase the network’s cargo-carrying capacity and facilitate increased industrial production. Project implementation is expected to take four years.

    State-owned SAR is also considering increasing the localisation of railway materials and equipment, including the construction of a cement sleeper manufacturing facility.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15229624/main.jpg
    Yasir Iqbal
  • Contract award nears for Saudi Defence Ministry headquarters

    10 December 2025

     

    Saudi Arabia’s Defence Ministry (MoD) is preparing to award the contract to build a new headquarters building, as part of its P-563 programme in Riyadh.

    MEED understands that bid evaluation has reached advanced stages and the contract award is imminent.

    The MoD issued the tender in April. The commercial bids were submitted in September, as MEED reported.

    Located to the northwest of Riyadh, the P-563 programme includes the development of facilities and infrastructure to support the MoD’s broader initiatives under the kingdom’s Vision 2030 strategy.

    It covers the construction of:

    • A new military city featuring the MoD headquarters, support and logistics facilities, a residential and commercial community and space for future command centres
    • A National Defence University with a library, conference centre and academic buildings
    • A self-sustaining Joint Forces Command compound located approximately 50 kilometres from the military city

    The budget for the entire programme is expected to be $10bn-$12bn.

    In September 2023, MEED reported that Spain-headquartered Typsa had won two contracts for the project.

    The first contract, worth $11.4m, included data management, geographic information systems management, geotechnical reporting and the preparation of the phase one final traffic report. The contract duration was 270 days from the notice to proceed.

    The second contract, valued at $10.8m, involved preparing four conceptual masterplans for the P-563 site. It was set to last 255 days from the notice to proceed.

    These followed a $290m consultancy contract awarded to Typsa in March of the same year. The single-award task order covered a three-year base period, with an optional two-year extension.

    Typsa’s scope of work included programme management planning, communications, change and quality management and cost and schedule tracking.

    It also included design requirements, codes, standards and submission requirements, programme guidance, study integration, risk analysis and management, design reviews and a programme-of-work breakdown plan.


    READ THE DECEMBER 2025 MEED BUSINESS REVIEW – click here to view PDF

    Prospects widen as Middle East rail projects are delivered; India’s L&T storms up MEED’s EPC contractor ranking; Manama balances growth with fiscal challenges

    Distributed to senior decision-makers in the region and around the world, the December 2025 edition of MEED Business Review includes:

    > BAHRAIN MARKET FOCUS: Manama pursues reform amid strain
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15222401/main.gif
    Yasir Iqbal
  • Firms prepare Riyadh government office PPP bids

    10 December 2025

     

    Firms are preparing to submit bids for a contract covering the construction of the Riyadh administrative office for Defence Ministry (MoD) personnel.

    The clients have asked firms to submit their bids by 26 March 2026.

    The MoD is developing the project in collaboration with Saudi Arabia's National Centre for Privatisation & PPP (NCP). 

    The project will be implemented under a design, build, finance and maintain contract with a term of 27.5 years.

    The administrative complex, located in the north of Riyadh, will cover about 52,793 square metres. It will accommodate 4,500 employees and provide 3,200 parking spaces.

    In September, the NCP announced the prequalified bidders for the project. These include:

    • Tamasuk / Alghanim International (local/Kuwait)
    • Mota-Engil / Tatweer Buildings Company / Alternative Resources Investments (Portugal/local/UAE)
    • Albawani / Areic (local/local)
    • Bonyan Real Estate Investment / Artar (local/local)
    • FCC / IHCC (Spain/local)
    • Vision Invest (local)
    • Own Real Estate (local)
    • Alfanar (local)
    • Lamar Holding (local)
    • Alyamama (local)
    • El-Seif Engineering Contracting (local)
    • Al-Kifah Holding Company (local)
    • Alargan (Kuwait) 
    • Asyad (Oman)

    The NCP and MoD started the expression of interest and request for qualification process for the project in May, as MEED reported.

    According to an official statement, "the selected private-sector partner will be responsible for the design, construction and long-term maintenance of the facilities and supporting infrastructure, as well as coordination with stakeholders and obtaining all necessary permits".

    The value of public-private partnership (PPP) contracts in Saudi Arabia has risen sharply over the past few years as the government seeks to develop projects through the private sector and diversify funding sources.

    PPPs have been used in Saudi Arabia and the wider GCC region for over two decades, but have been mainly limited to power generation and water desalination plants, where the developer benefits from guaranteed take-or-pay power-purchase agreements that eliminate demand risk.

    However, in the past three years, the government has successfully implemented PPPs in several new sectors, including education and healthcare, to finance, build and operate schools and hospitals. Forthcoming PPP projects include the estimated $2.5bn Asir-Jizan highway, which would be the first road concession in the GCC; the multibillion-dollar contract to develop the expansion of Abha International airport; and the Qiddiya high-speed rail scheme.

    Outside the utilities sector, the NCP has more than 170 PPPs in the pipeline, covering long-term concession agreements in projects as diverse as municipal laboratories, television and radio tower infrastructure, court complexes and logistics zones.

    As capital expenditure continues to increase, the NCP is expected to add dozens more PPPs to its future pipeline to relieve the state’s financial burden and to stimulate the private sector’s involvement in the local projects market.


    READ THE DECEMBER 2025 MEED BUSINESS REVIEW – click here to view PDF

    Prospects widen as Middle East rail projects are delivered; India’s L&T storms up MEED’s EPC contractor ranking; Manama balances growth with fiscal challenges

    Distributed to senior decision-makers in the region and around the world, the December 2025 edition of MEED Business Review includes:

    > BAHRAIN MARKET FOCUS: Manama pursues reform amid strain
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15222216/main.jpg
    Yasir Iqbal
  • Municipality seeks consultants for Dubailand drainage project

    10 December 2025

    Register for MEED’s 14-day trial access 

    Dubai Municipality has invited consultants to prequalify for a contract to provide supervision services on a major drainage infrastructure project serving developed communities in Dubailand.

    The sewerage and stormwater drainage project, listed under the code DS-204-S1, is being procured through the government’s Sewerage and Recycled Water Projects Department (SRPD).

    The bid submission deadline is 8 January.

    The consultancy contract follows the issuance in November of the related construction package, DS-204-C1, for which the municipality invited contractors to prequalify.

    The scope includes sewage gravity pipelines with diameters of up to 2,200mm, a sewage lift station with a capacity of three cubic metres a second, and a 1,400mm-diameter sewage rising main that will take pumped sewage from the lift station to the main sewer network.

    The bid submission deadline for the construction package is also 8 January 2026.

    The tenders form part of Dubai’s wider investment in sewerage expansion, including the $8bn Tasreef programme, for which several projects have moved into the execution phase in recent months.

    Once completed, the Tasreef system is expected to increase Dubai’s overall drainage capacity by about 700% and provide daily stormwater treatment capacity exceeding 20 million cubic metres.


    READ THE DECEMBER 2025 MEED BUSINESS REVIEW – click here to view PDF

    Prospects widen as Middle East rail projects are delivered; India’s L&T storms up MEED’s EPC contractor ranking; Manama balances growth with fiscal challenges

    Distributed to senior decision-makers in the region and around the world, the December 2025 edition of MEED Business Review includes:

    > BAHRAIN MARKET FOCUS: Manama pursues reform amid strain
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15218750/main.jpg
    Mark Dowdall