Iraq electricity sector makes slow progress

9 May 2024

Latest news from Iraq's power and water sectors:

> Iraq plans new Baiji power plant
> Decision imminent on Iraq waste-to-energy project
> Iraq discusses nuclear projects with global watchdog
Siemens Energy and SLB sign Iraq flare gas-to-power deal
PowerChina in talks for Basra desalination plant
US seeks firms for Baghdad power plant package
Iraq plans green hydrogen project at refinery
Iraq approves long-term grid expansion


 

In late March, Iraq’s Electricity Ministry struck a five-year gas supply deal with National Iranian Gas Company for up to 50 million cubic metres a day (cm/d), contingent on the needs of Iraqi power stations, in exchange for oil and gasoline.

The deal offers a lifeline to Iraq’s deteriorating electricity sector and replaces an existing agreement whereby contractual volumes were theoretically set at 70 million cm/d for summer and 45 million cm/d for winter.

The two countries signed the deal following nearly three months of longer-than-usual power outages in Iraq, and after Baghdad settled part of the multibillion-dollar debt it owes Iran. The power cuts occurred due to a drastic reduction in Irani gas supply, which dipped to 10 million cm/d and wiped out 4GW from Iraq’s grid.

The deal is a compromise for both countries. It allows Iraq some breathing space to implement projects to reduce its dependence on Iran’s gas exports – a long-running and elusive objective among Iraq’s policymakers and its allies in the GCC states and the US.

The crisis should prompt Iraq to push ahead with projects to boost domestic gas production and build solar power plants, according to the Electricity Ministry.

Supply and demand mismatch

There has been a persistent mismatch between supply and demand in Iraq’s electricity sector, with peak demand during the summer months outstripping available capacity by a sizeable margin.

In recent years, the deficit has returned during the winter when heating requirements rise.

With a few exceptions, however, the procurement process or negotiations for additional generation capacity have been proceeding slowly, leaving a gap that is typically addressed by diesel generators.

Iraq aspires to build 12,000MW of solar capacity by the end of the decade, which is nearly half its known available capacity today.

The Electricity Ministry has signed deals with several companies to develop sizeable solar photovoltaic (PV) capacity over the past two to three years in line with this objective. Yet, despite regular pronouncements that the construction phase for these projects is about to start, none have reached final investment decisions (FIDs) or the construction phase so far.

The Electricity Ministry remains the dominant client for these projects, although the National Investment Commission (NIC) has been an active participant, particularly in bilateral or public-private partnership projects.

For example, the UAE’s Masdar signed a deal to develop 2GW of solar capacity in Iraq with the NIC. The commission is also procuring a contract to develop the country’s first waste-to-energy (WTE) project in coordination with the Municipality of Baghdad, the Electricity Ministry and the Environment Ministry.

Located in the Al Nahrawan area of Baghdad Governorate, the planned WTE project will have the capacity to treat 3,000 tonnes of waste a day and generate nearly 80 megawatt-hours (MWh) of electricity.

Other companies that have committed to develop solar PV projects in Iraq include Power China, which has pledged to develop solar PV projects with a combined total capacity of 2GW, and France’s Total Energies, which has committed to build a 1,000MW solar farm in Artawi.

The solar project in Artawi is a small part of a $27bn package that TotalEnergies is developing in partnership with QatarEnergy. The package involves the development of a common seawater supply project and oil and gas fields in Iraq.

Awarded projects

As earlier cited, there are some exceptions to the endemic start-stop mode for Iraq’s power generation and distribution projects.

For example, Germany’s Siemens Energy and the US-based GE have ongoing projects that include retrofitting or upgrading existing gas turbine power stations or building new substations as part of agreements to help rebuild Iraq and support its goal of reducing carbon emissions.

Earlier this month, the Electricity Ministry signed a preliminary agreement with Germany’s Siemens Energy and US firm SLB, formerly Schlumberger, to explore the development of a power generation plant using flare gas.

According to Siemens Energy Middle East managing director Dietmar Siersdorfer, the planned flare gas-to-power project in southern Iraq will help reduce carbon dioxide emissions and capture value from gas that would otherwise be wasted.

The planned flare gas-to-power plant could have a generation capacity of up to 2,000MW.

In January this year, China-based Oriental International is understood to have signed a contract to convert a single-cycle unit at the Baghdad South power plant complex into a combined-cycle power plant.

In April, the Electricity Ministry awarded another Chinese company, China Machinery Engineering Corporation (CMEC), a second year of operation and maintenance contracts for the Salah Al Din gas-fired power plant.

CMEC was awarded the estimated $1bn contract to build the power plant in northern Iraq in 2011. After a series of delays and challenges, including the Isis uprising, the two 630MW capacity units began operating last year.

In December last year, Siemens Energy also signed a contract to deliver five high-voltage substations on a turnkey basis in Iraq. The 400-kilovolt substations, each with a capacity of 1,500MW, will be installed in Baghdad, Diyala, Najaf, Karbala and Basra.

Similarly, the US’s preoccupation with helping wean Iraq off Iran’s gas and electricity imports has spurred projects to interconnect Iraq’s grid with its neighbour Saudi Arabia through the GCC grid and Jordan.

In October last year, the governor of Saudi Arabia’s Eastern Province, Prince Saud Bin Naif Bin Abdulaziz, inaugurated the GCC grid's Iraq connection, which had been under development for several years. The 295-kilometre power transmission network will have a total transmission capacity of 1,800MW, with an initial phase expected to supply 500MW of electricity to Iraq.

Future projects

In February this year, Electricity Ministry spokesperson Ahmed Mousa said the government had approved funds for the long-term plans to expand the country’s power transmission and distribution network with Siemens Energy’s help.

Mousa said the ministry “received funds for long-term plans to develop the electricity sector in 2023 … the three-year budget approved in 2023 also includes funds this year and in 2025”. 

In early May, it was reported that the Electricity Ministry held discussions with Qatar’s UCC Holding to develop a 2,100MW gas-fired power plant in Baiji. The plant will replace a power station that was damaged during the war.

It is unclear if the project is part of a previous agreement between UCC Holding and NIC to develop two power plants with a capacity of 2,400MW in Iraq.

A new 2,000MW gas-fired power plant is also being proposed in Basra, which is expected to receive gas from the nearby West Qurna 1 and West Qurna 2 oil fields.

As it is, several projects are waiting for final approvals, such as the gas-fired 2,800MW Khairat independent power producer, which has yet to reach FID over two years after the contract was awarded.  

Going nuclear 

Project delays and indecision in Iraq do not appear to narrow down the options for future power generation expansion.  

In March, it was reported that senior Iraq and International Atomic Energy Agency (IAEA) officials had discussed Iraq’s plans for a possible nuclear energy programme, including small modular reactors.

According to the nuclear watchdog, discussions included maintaining strict adherence to non-proliferation norms.

IAEA director general Rafael Mariano Grossi said his agency has committed to supporting the foundations of what should be an entirely peaceful programme in Iraq.

Iraq, for its part, is considering nuclear energy to enable greater energy security and for water desalination projects as part of the country’s plans for a more sustainable future.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11745270/main.gif
Jennifer Aguinaldo
Related Articles
  • Amazon data centre hit highlights sector vulnerabilities

    2 March 2026

     

    Amid ongoing Iranian missile and drone attacks on GCC states, US cloud provider Amazon Web Services (AWS) has reported service outages following separate incidents at two of its UAE data centres.

    “At around 4.30AM PST [16.30 UAE time on 1 March], one of our Availability Zones (mec1-az2) was impacted by objects that struck the data centre, creating sparks and fire,” AWS said in an operational update on 1 March.

    At 10.46 UAE time on 2 March, the company announced a further update, saying that another of its three UAE Availability Zones had gone down.

    “We can confirm that a localised power issue has affected another Availability Zone in the ME-CENTRAL-1 Region (mec1-az3),” it said in the latest update. “Customers are also experiencing increased EC2 APIs and instance launch errors for the remaining zone (mec1-az1). At this point, it is not possible to launch new instances in the region, although existing instances should not be affected in mec1-az1.

    “Other AWS services, such as DynamoDB and S3, are also experiencing significant error rates and latencies. We are actively working to restore power and connectivity, at which time we will begin to work to recover affected resources. As of this time, we expect recovery is multiple hours away.”

    Regional footprint

    The company, part of the US’ giant Amazon group, is one of the world’s largest data centre and cloud operators. It operates three data centres in the UAE – one in Dubai and two in Abu Dhabi – and provides critical IT services to government and private sector operations and systems.

    Its Availability Zones consist of infrastructure in separate geographic locations, spaced far enough apart to significantly reduce the risk of a single event affecting customers’ business continuity, yet near enough to provide low latency for high-availability applications that use multiple zones.

    The targeting of the two data centres – and potentially others if the conflict continues – highlights the strategic importance of these types of facilities. The AWS attacks are believed to be the first time a data centre has been targeted in a conflict and are likely to drive a reconfiguration of future campus designs to account for similar risks.

    Such changes could include increased redundancies – particularly in power provision – enhanced structural resilience, and potentially a reconsideration of the location and clustering of data centre facilities.

    WATCH: Ed James explores the rapidly evolving GCC data centres market

    Historically, data centres in the region were largely smaller enterprise facilities dedicated to storage services for organisations such as banks. Their locations were often confidential and in areas that were difficult to target, making them harder to disrupt.

    However, the emergence of large in-region hyperscale data centres – with IT loads of 200MW or more and larger physical footprints – may necessitate a rethink of how such infrastructure is delivered, not just in the GCC but worldwide.

    According to MEED Projects data, there are believed to be about 185 data centres in the region, each with an estimated capex investment value of more than $10m, of which about 99 are either planned or under construction.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15823937/main.gif
    Edward James
  • Contractor wins Oman water network contract

    2 March 2026

    Egypt’s Hassan Allam Construction has won an engineering, procurement and construction (EPC) contract for a water transmission network project from Al-Jardaa to Mihlaih (Sawt) in Oman’s North Al-Sharqiyah Governorate.

    The contract was awarded by Oman Water & Wastewater Services Company (OWWSC).

    The scope includes 76 kilometres of transmission lines and nearly 600km of distribution networks.

    The project also covers seven high-capacity reservoirs, two pumping stations and seven solar-powered systems.

    Hassan Allam Construction won a separate contract with OWWSC in August 2025 to build and supervise the construction of a large-scale water supply and wastewater system in Al-Amerat, Muscat.

    The Al-Amerat Catchment 10 water supply, sewer system and treated effluent networks project covers the construction of a 64km gravity sewer network.

    Last month, MEED exclusively revealed that China’s Hunan Installation Overseas Engineering had won an EPC contract to build water supply and sewage networks in Muscat. 

    The contract was awarded by state utility Nama Water Services (NWS).

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15823693/main.jpg
    Mark Dowdall
  • RTA opens bridge as part of Trade Centre road project

    2 March 2026

    Dubai’s Roads & Transport Authority (RTA) has opened a key bridge as part of the World Trade Centre roundabout project.

    Extending 1 kilometre (km) from Sheikh Zayed Road to Sheikh Khalifa Bin Zayed Street towards Deira, the bridge has a capacity of 3,000 vehicles an hour.

    It comprises two lanes, reducing journey time from six minutes to one minute.

    In a statement, the RTA said overall project construction progress has reached 60%.

    The project’s main construction works are being undertaken by the local firm Wade Adams, which was awarded a AED696m ($189m) contract to upgrade the Trade Centre roundabout in October 2024.

    The project will enhance connections between Sheikh Zayed Road and five main streets: Sheikh Khalifa Bin Zayed Street, Sheikh Rashid Street, 2nd December Street, Zabeel Palace Street and Al-Mustaqbal Street.

    The project’s scope covers the construction of five bridges spanning a total length of 5km. 

    In addition to the recently opened bridge, two other two-lane bridges will extend 2km and will connect Sheikh Rashid Street with 2nd December Street, with a capacity of 6,000 vehicles an hour.

    The fourth and fifth two-lane bridges will span 2km from Al-Majles Street to 2nd December Street and will connect Al-Mustaqbal Street with 2nd December Street, with a capacity of 6,000 vehicles an hour.

    The scope also covers converting the existing roundabout into a surface intersection to improve the flow of traffic inbound from Sheikh Zayed Road to 2nd December Street and of southbound traffic from Al-Mustaqbal Street to Sheikh Zayed Road.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15823684/main.png
    Yasir Iqbal
  • Riyadh selects three teams for King Salman airport ECI

    2 March 2026

     

    Saudi Arabia’s King Salman International Airport Development Company (KSIADC) has selected three groups for the construction of Terminal 6 at King Salman International airport (KSIA) in Riyadh.

    KSIADC, which is backed by Saudi sovereign wealth vehicle, the Public Investment Fund, will deliver the project on an early contractor involvement (ECI) basis.

    The selected groups include:

    • UCC / CCC (Qatar/Greece)
    • Al-Gihaz Holding / TAV / WeBuild (local/Turkiye/Italy)
    • PowerChina / MBL (China/local)

    MEED understands that the ECI timeframe will be around six months.

    The ECI process requires selected contractors to submit methodologies for the project and a design proposal. One team will then be selected for the construction.

    In November last year, MEED exclusively reported that KSIADC was targeting mid-2026 to award the contract for the construction of Terminal 6 at KSIA in Riyadh.

    In July last year, MEED exclusively reported that several contractor consortiums had submitted proposals for a contract to develop the first phase of Terminal 6 and the Iconic Terminal at KSIA.

    MEED reported in May last year that US firm Bechtel Corporation had been appointed as the delivery partner for the terminals at KSIA.

    According to local media reports, KSIADC’s acting CEO, Marco Mejia, said the project developer had completed the project’s masterplan.

    The reports added that Terminal 6 will boost the airport’s capacity by 40 million passengers.

    The project is expected to be delivered before the start of the Expo 2030 Riyadh event.

    Project scale

    The project covers an area of about 57 square kilometres (sq km), allowing for six parallel runways, and will include the existing terminals at King Khalid International airport. It will also include 12 sq km of airport support facilities, residential and recreational facilities, retail outlets and other logistics real estate.

    If the project is completed on time in 2030, it will become the world’s largest operating airport in terms of passenger capacity, according to UK analytics firm GlobalData.

    The airport aims to accommodate up to 120 million passengers by 2030 and 185 million by 2050. The goal for cargo is to process 3.5 million tonnes a year by 2050.

    Saudi Arabia plans to invest $100bn in its aviation sector. Riyadh’s Saudi Aviation Strategy, announced by the General Authority of Civil Aviation, aims to triple Saudi Arabia’s annual passenger traffic to 330 million travellers by 2030.

    It also aims to increase air cargo traffic to 4.5 million tonnes and raise the country’s total air connections to more than 250 destinations.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15823432/main.jpg
    Yasir Iqbal
  • Petrofac cuts staff in Libya and puts oil project on hold

    2 March 2026

     

    The financially troubled engineering company Petrofac has cut its staff in Libya and stopped work on a key oil project in the country, according to industry sources.

    Between 15 and 20 Libyan members of staff have been released by the company, and work on a project to develop the Erawin oil field has been paused, sources said.

    Petrofac secured a contract with Zallaf Libya Oil & Gas Exploration & Production Company to deliver its Erawin field development project phase 1 early production facilities (EPF) in September 2021.

    The project’s scope of work encompassed surface equipment, including well pads and flowlines, at the Erawin oil field.

    It also included a pipeline to transport crude oil approximately 100 kilometres (km) to the El-Sharara oil field, along with a control room, substation and telecom system located there.

    In a statement to MEED, Petrofac said:

    “Petrofac has not exited Libya. Our Tripoli office remains operational and we continue to maintain an active presence in the country.

    “Regarding the Erawin project, the pipeline infrastructure was completed and has been in operation for more than a year.

    “A small number of remaining activities were paused while we continue discussions with the client on the project’s final scope and close‑out arrangements.

    “Petrofac has not abandoned the project, nor have we shut down our operations in Libya.”

    Commenting on the cut to employee numbers in Libya, the company said:

    “Recent workforce adjustments reflect the normal lifecycle of a project.”

    The company added: “Libya remains an important market for Petrofac, and we remain committed to supporting the development of the country’s energy sector.

    “As discussions with the client are ongoing, we are not in a position to comment further at this time.”

    Zallaf Libya Oil & Gas Exploration & Production Company was established in Libya in 2013 and is wholly owned by Libya’s National Oil Corporation.

    It awarded the Erawin EPF contract to Petrofac using the engineering, procurement, construction and commissioning (EPCC) contract model.

    In a statement in 2021, Petrofac said the contract was valued at over $100m, but did not give a precise figure.

    The regional project-tracking service MEED Projects has estimated that the contract was worth $440m.

    Petrofac problems

    On 27 October last year, Petrofac announced that it had applied to appoint administrators, a move that potentially put thousands of jobs at risk and increased uncertainty for projects worth billions of dollars in the Middle East and North Africa (Mena) region.

    At the time, the total value of projects awarded to Petrofac and under construction in the region was $5.83bn, according to information recorded by MEED Projects.

    Petrofac also had bids under evaluation for 15 projects in the region worth a total of $19.28bn.

    Since then, key parts of the business have been sold off, and many of the company’s staff have been made redundant.

    The redundancies included around 180 employees who were issued termination notices in October last year.

    In December, the US-based company CB&I announced it had entered into a deal to buy Petrofac’s asset solutions business in the first quarter of 2026.

    In January this year, the proposed company voluntary arrangement (CVA) related to the sale of its Asset Solutions business was approved.

    Erawin exports

    Libya shipped its first cargo of crude from the Erawin oil field in November 2023.

    The shipment departed from Libya’s Zawiyah port and consisted of 600,000 barrels of crude.

    Australia-based Worley Parsons was appointed as the front-end engineering and design (feed) contractor for the EPF project in 2019.

    The Erawin field development project is located about 800km south of Tripoli and 100km southwest of the El-Sharara field.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15821861/main.jpg
    Wil Crisp