Glasspoint to start Maaden solar thermal showcase

27 November 2024

US-based GlassPoint, in partnership with the Ministry of Investment of Saudi Arabia (Misa), said it is moving towards building a technology showcase, which is the first step towards the construction of the planned $1.5bn industrial solar thermal project catering to mining and metals firm Saudi Arabian Mining Company (Maaden).

GlassPoint has also partnered with Cox as its technical and delivery partner to build the GlassPoint Maaden Technology Showcase (GMTS) and "several additional solar thermal projects globally".

GlassPoint said: "The GMTS is the first stage in building the world’s largest industrial solar thermal project, Maaden I, a $1.5B project which will combine direct solar to heat technology with advanced thermal storage to accelerate the decarbonising of Maaden's aluminum supply chain."

However, the company has yet to disclose the actual timeline for the construction of the main solar thermal plant.

To support these projects for Maaden and to export high-technology renewable energy components to the region, Glasspoint and Misa plan to construct a state-of-the-art solar manufacturing facility in the kingdom. 

GlassPoint specialises in decarbonising industrial process heat. MEED previously reported that the project's first stage will have the capacity to supply 9 tonnes of steam an hour to begin decarbonising Maaden's aluminum supply chain.

It will combine the direct generation of heat and storage to provide a continuous base load of steam to Maaden's alumina refinery in Ras Al-Khair.

The initial capacity will be about 1% of the larger project, which is expected to save Maaden's refinery more than 12 metric million British thermal units (MMBtus) of energy and reduce carbon emissions by 600,000 tonnes annually.

GlassPoint signed a memorandum of understanding with Maaden to develop Maaden Solar 1, potentially the world’s largest solar process heat plant, in June 2022.

When complete, Maaden Solar 1 will be a 1,500 megawatt-thermal (MWth) facility.

The technology showcase "is an important first step to kick off project development and begin building on location", said GlassPoint founder and CEO Rod MacGregor at the time.

It is understood that low-carbon aluminum increasingly commands a premium with industrial companies that are seeking to meet sustainability requirements from their customers.

"New policies such as the EU's carbon border adjustment mechanism will tax high-carbon imports and make low-carbon aluminum, enabled by solar thermal solutions, even more appealing," GlassPoint said.

The technology showcase will include several new advancements from GlassPoint that are expected to reduce the cost of its solutions by more than 30%.

Enhancements include GlassPoint's Unify storage system, which uses direct heat and ternary molten salts to provide around-the-clock steam, as well as lighter materials that will boost solar efficiency and reduce weight, materials, carbon intensity, shading and the levelised cost of energy.

Solar factory

In October last year, GlassPoint announced a partnership with the Ministry of Investment Saudi Arabia (Misa) to build a solar manufacturing facility in the Eastern Province of the kingdom.

At full capacity, the planned factory will produce enough renewable energy technology annually to generate 5,000 tonnes of solar steam a day, which will be sufficient to offset 4 MMBtus of gas and reduce carbon emissions by 200,000 tonnes each year.

Technology manufactured at the facility will be used for projects in the metals and mining, building materials and other industrial sectors. 

GlassPoint’s enclosed trough concentrated solar power technology uses large, curved mirrors to focus sunlight on a boiler tube containing water. The concentrated energy boils the water to produce high-quality steam, which is fed into existing industrial operations.

A self-cleaning structure encloses and protects the solar collectors from wind, sand and dust. The structure protects the operational environment, enabling lightweight mirrors and components.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13011091/main.jpg
Jennifer Aguinaldo
Related Articles
  • Kuwait awards $381m oil project

    23 September 2026

    Register for MEED’s 14-day trial access 

    State-owned upstream operator Kuwait Oil Company (KOC) has awarded an oil project contract worth KD117m ($381m) to India’s Megha Engineering & Infrastructure (Meil).

    The Supreme Purchasing Committee for Kuwait Petroleum Corporation (KPC) approved the contract last month, paving the way for the official award.

    The project focuses on a water separation unit at the Al-Rawdatain facility in Kuwait.

    The water separation facility will be developed at Gathering Centre 25 (GC-25), along with a pumping facility at GC-30.

    The project will deliver a wide-ranging upgrade of processing and utility infrastructure, including new low-pressure separation and gas-handling equipment such as a three-phase wet separator package, a gas knock-out drum and associated low-pressure gas pipelines, as well as a high-integrity pressure protection system and a high-pressure flare.

    Meil will develop the new three-phase low-pressure wet separation facility at GC-25.

    The main process equipment will include two wet separator packages, each with a capacity of 150,000 barrels of liquid a day, and a low-pressure gas knock-out drum with a capacity of 53 million standard cubic feet a day, together with associated gas-handling facilities.

    The facility will also incorporate an effluent water treatment and transfer system, including an effluent water balance tank equipped with microbubble flotation and induced gas flotation systems, as well as transfer pumps.

    Additional GC-25 facilities will include fuel gas treatment, chemical injection, oil recovery and flare connections, along with firewater and deluge systems.

    The scope also covers control and safety systems, substations, and associated civil, structural, mechanical, electrical and instrumentation works.

    At GC-30, the project will focus on treated-water filtration and high-pressure injection infrastructure.

    The scope includes nutshell filters and associated feed pumps with a combined capacity of approximately 500,000 barrels of water a day.

    Booster and injection pumps will transfer treated effluent water to designated injection wells.

    Additional facilities at GC-30 will include fuel gas treatment, sludge collection and disposal systems, oil recovery systems, control and safety systems, substations, laboratory and workshop facilities, and associated civil, structural, piping, mechanical, electrical and instrumentation works.

    The project also includes transfer pipelines connecting GC-25, GC-15 and GC-30.

    Meil will carry out modifications to existing tanks at GC-30, as well as process and utility tie-ins, electrical and instrumentation modifications and other infrastructure required to integrate the new facilities with KOC’s existing assets.

    Meil’s responsibilities cover the project lifecycle from design and engineering through procurement, construction, testing, pre-commissioning, commissioning, start-up and performance testing.

    The contract also includes operation, maintenance, repair and insurance responsibilities for the designated facilities during the applicable operations and maintenance period.

    Seven companies submitted bids for the project last November.

    The full list of bids was:

    • Meil (India) – KD117m ($381m)
    • Mechanical Engineering & Contracting Company (Kuwait) – KD130m
    • Spetco (Kuwait) – KD158m
    • Al-Kharafi (Kuwait) – KD164m
    • China Oil HBP Science & Technology (China) – KD169m
    • Alghanim International (Kuwait) – KD169m
    • Jereh Oil & Gas Engineering (China) – KD191m

    In October last year, KOC awarded Meil a separate contract for a project to develop a gas sweetening and recovery facility in west Kuwait.

    Meil submitted the lowest bid for that tender, at KD69.2m ($225.5m), in February 2025.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19911322/main.jpg
    Wil Crisp
  • Kuwait refinery project on track for year-end completion

    23 September 2026

     

    A $65m project to replace a substation at the Mina Al-Ahmadi (MAA) refinery is on schedule to be mechanically complete before the end of the year, according to industry sources.

    The project is being executed by India’s Larsen & Toubro (L&T), which was awarded the contract in October 2024.

    One source said: “This project is approaching completion and is currently on schedule to be completed before the end of the year, although it could still see delays related to the ongoing regional conflict.”

    The client is state-owned downstream operator Kuwait National Petroleum Company (KNPC).

    Kuwait’s Ministry of Electricity, Water & Renewable Energy (MEW) is also involved in the project and will provide final approvals and sign-off.

    The scope of the project includes:

    • Construction of a substation
    • Installation of transformers
    • Installation of medium-voltage switchgear
    • Installation of low-voltage auxiliary systems
    • Installation of network protection systems
    • Installation of disconnecting switches
    • Installation of surge arrestors
    • Installation of feeder breakers and cubicles
    • Installation of low-voltage A/C and D/C equipment
    • Installation of battery banks and battery chargers
    • Installation of related relay and control panel boards
    • Installation of fire alarm and fire protection equipment
    • Installation of a SCADA system
    • Installation of cables
    • Civil works
    • Associated facilities

    The current project to replace a substation at the MAA refinery closely resembles another project tendered by KNPC more than a decade ago, which L&T also won.

    On 18 May 2015, KNPC signed a contract with L&T to build a new 240MW substation at the MAA refinery, valued at KD21.866m.

    The new substation, known as M20, was designed to replace an existing substation that was considered old and obsolete.

    Mohammed Al-Mutairi, who was KNPC’s chief executive at the time, said the substation building would be explosion-proof and use state-of-the-art control systems.

    He said the station’s capacity would increase from 180MW to 240MW, supplying most of the refinery’s electricity needs.

    Given the similarities between the two projects, L&T has been able to reuse some designs, creating efficiencies, according to industry sources.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19911319/main.jpg
    Wil Crisp
  • Contractor wins $208m Almoosa hospital MEP contract

    23 September 2026

    Register for MEED’s 14-day trial access 

    Riyadh-based construction firm BEC Arabia has won a SR781m ($208m) contract for the mechanical, electrical and plumbing (MEP) works at Almoosa Hospital in Al-Khobar.

    Saudi Arabia’s Almoosa Health Company awarded the contract.

    The hospital complex consists of two towers: a 24-storey in-patient tower with 380 beds, and an 11-storey tower with 224 clinics and 113 additional treatment spaces.

    It will be built on a 45,000-square-metre site.

    A podium spanning the ninth and 10th floors will connect the two towers.

    The hospital will also include parking for 1,700 cars.

    BEC Arabia won the SR656m ($175m) main construction contract for the hospital in November last year.

    In August 2025, MEED reported that Almoosa Health Company had announced it had secured a sharia-compliant credit facility worth SR650m ($173m) from Banque Saudi Fransi.

    In a statement published on the Saudi stock exchange (Tadawul), the company said the seven-year facility would be used to support its expansion and growth strategy.

    Lebanon’s Dar, US-based Perkins&Will and French design firm Pierre-Yves Rochon designed the project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19910889/main.jpg
    Yasir Iqbal
  • UAE to develop integrated waste-to-resource pilot

    23 September 2026

    Emirates Biotech and United Arab Emirates University (UAEU) have launched a pilot project in Al-Ain that could provide a model for larger waste-to-resource facilities.

    The project involves developing the UAE’s first integrated organic-waste valorisation pilot plant, which will test whether food waste and compostable packaging can be processed together to recover resources and reduce waste sent to landfill.

    Located near the UAEU campus, the 40kg-a-day facility will process organic waste to produce renewable biogas and nutrient-rich compost. The project is intended to generate technical and operating data that could support the development of larger-scale facilities.

    Emirates Biotech and UAEU will design, build and operate the pilot plant as part of a two-year research project running from August 2026 to August 2028. Installation and commissioning are expected to be completed by August 2027.

    The plant will combine anaerobic digestion and composting. Anaerobic digestion will convert the organic waste into renewable biogas, while the resulting digestate will be composted to produce nutrient-rich compost.

    A laboratory-scale assessment will also examine the potential to convert the biogas into renewable hydrogen.

    Food waste accounts for nearly 40% of daily municipal solid waste in the UAE, according to Emirates Biotech, and much of it is currently disposed of in landfills.

    The pilot will therefore assess the technical and operational feasibility of recovering value from two waste streams through a single integrated process.

    If successfully scaled, Emirates Biotech says an integrated organic-waste valorisation plant could reduce CO₂ emissions by 89% compared with landfilling.

    The project is expected to provide a scalable and modular model for converting food waste and compostable packaging into renewable biogas and compost, with the findings intended to inform the development of larger waste-to-resource facilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19908972/main.jpg
    Mark Dowdall
  • Contractors prepare Oxagon Highway 55 bids

    23 September 2026

     

    Contractors are preparing to submit bids on 28 September for a design-and-build contract for permanent upgrade works on Highway 55 in the kingdom’s Oxagon region.

    The first phase of the project includes constructing 14 kilometres of road, with two lanes in each direction. It also includes one bridge and three interchanges.

    The project duration is 22 months.

    Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.

    MEED reported exclusively in August 2025 that contractors had submitted responses to an expression of interest notice that Neom had issued earlier that month.

    The project is expected to support cargo movement from Duba Port to other parts of the kingdom and the wider region.

    Last year, Neom tested a pilot initiative by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.

    In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”

    The Port of Neom is located on the Red Sea near the Arar border, a key entry point into Iraq.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19907876/main.jpg
    Yasir Iqbal