Gigaproject spending finds a level

29 November 2024

 

By the end of October 2024, there had been $17bn of contract awards across Saudi Arabia’s five gigaprojects, according to regional projects tracker MEED Projects, up from the $16bn recorded during the same period in 2023. 

The five official gigaprojects named by Saudi Crown Prince Mohammed Bin Salman Bin Abdulaziz Al-Saud are: Diriyah, Neom, Qiddiya, Roshn and the projects being developed by Red Sea Global.

While the growth in awards on these schemes in 2024 is positive, the pace of activity falls short of the strong growth that was expected as the gigaprojects move into the delivery phase. 

The highlights for 2024 have been a $4.7bn contract to build dams at the Trojena mountain resort that was won by Italy’s WeBuild, a $2bn contract won by a joint venture (JV) of local firm Albawani and Qatar’s Urbacon Trading & Contracting for the construction of assets in the Wadi Safar development of the Diriyah project in Riyadh, and a $1bn contract secured by a JV of Spanish firm FCC Construction and local firm Nesma & Partners to build the Prince Mohammed Bin Salman Stadium at the Qiddiya City project on the outskirts of Riyadh.

These awards appear to confirm the consensus in Saudi Arabia that the focus for development is on projects underpinned by events. These are Trojena, which will host the Asian Winter Games in 2029; stadiums for the Asian Cup in 2027 and the Fifa World Cup in 2034; along with Expo 2030 Riyadh and the Asian Games in 2034. 

There is also a view that projects in and around Riyadh are being prioritised ahead of schemes in remote areas. 

The stabilisation of activity in 2024, rather than the expected growth, combined with the intermittent nature of contract awards, has led to concerns about the prospects for the future of the market. 

The concerns peaked when no contract awards were recorded in August on any of the five official gigaprojects, but were abated when there were several high-profile awards in September and October, most notably the Qiddiya stadium deal.

The Line

The most scruntinised project in 2024 has been The Line at Neom. 

Since January, there have been reports about how the delivery of The Line will be phased, as well as rephasing exercises for other projects as budgets came under strain. Neom effectively confirmed these reports in November, when it said it is focused on the initial phases of infrastructure and enabling works for the new city. 

Neom commented on the next phase of the project when it replaced CEO Nadhmi Al-Nasr with Aiman Al-Mudaifer as acting CEO, saying: “As Neom enters a new phase of delivery, this new leadership will ensure operational continuity, agility and efficiency to match the overall vision and objectives of the project.” 

https://image.digitalinsightresearch.in/uploads/NewsArticle/13025339/main.gif
Colin Foreman
Related Articles
  • Chinese firm wins Qiddiya Janadriyah cultural district hotels

    30 June 2026

     

    Beijing-headquartered China State Construction Engineering Corporation (CSCEC) has won a contract to deliver the Janadriyah cultural district at Qiddiya entertainment city on the outskirts of Riyadh.

    The contract was awarded by gigaproject developer Qiddiya Investment Company (QIC).

    The scope covers the construction of six structures, including a heritage building, a gateway hotel, a wadi hotel, a creative hub, a community centre and an open-air market.

    QIC tendered the contract in December last year, as MEED exclusively reported.

    The award is CSCEC’s second major win at Qiddiya in recent weeks.

    Earlier this week, MEED exclusively reported that QIC had awarded CSCEC a contract to build a new transport hub at Qiddiya entertainment city.

    The project is located within the resort core zone of the development.

    MEED understands the scope includes construction of a parking structure for up to 2,000 vehicles; a transport hub comprising a passenger flow system and ticketing and transit-related facilities; retail, food and beverage and hospitality facilities; mechanical, electrical and plumbing (MEP) systems; and soft and hard landscaping works.

    QIC is accelerating plans to develop additional assets at Qiddiya City.

    Last week, MEED reported that QIC had invited contractors to prequalify for a contract to build an indoor sports arena within its Qiddiya entertainment city project.

    The multipurpose arena is designed to International Olympic Committee standards.

    It will be located in District 18, in the Uptown South area of Qiddiya.

    Once completed, the indoor arena will be capable of hosting a wide range of sports, cultural and entertainment events.

    The arena will feature numerous sports courts for basketball, handball, futsal, volleyball, tennis, boxing and gymnastics.

    It will have a seating capacity of 18,000 spectators.

    QIC’s other major projects include an e-sports arena, the National Tennis Centre, Prince Mohammed Bin Salman Stadium, a motorsports track, a racecourse, the Dragon Ball and Six Flags theme parks, and Aquarabia.

    QIC opened the Six Flags theme park to the public in December last year.

    The park covers 320,000 square metres and features 28 rides and attractions, including 10 thrill rides and 18 aimed at families and young children.

    The Qiddiya project is a key part of Riyadh’s strategy to boost leisure tourism in the kingdom.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17489285/main.jpg
    Yasir Iqbal
  • Aldar launches Yas Island community park project

    30 June 2026

    Abu Dhabi-based real estate developer Aldar, in partnership with the Abu Dhabi Department of Community Development (DCD), has announced the launch of Yas Community Park on Yas Island.

    A key feature of the park is Nabdh Yas, a community hub developed in collaboration with DCD.

    Once open, Nabdh Yas will serve as a central gathering space and host a range of community-led programmes.

    In a statement, Aldar said: “Nabdh Yas will be delivered on a public-private partnership (PPP) basis, marking the first time private sector investment has been directed towards this type of community infrastructure.

    “With DCD overseeing the hub’s development and long-term management, the initiative reflects Abu Dhabi’s focus on innovative approaches that generate lasting social value and enhance community wellbeing,” the statement added.

    A memorandum of understanding was signed between Aldar and DCD.

    The agreement establishes a framework to expand the Nabdh Community Hub model across Aldar developments in Abu Dhabi, Al-Ain and Al-Dhafra.

    Last month, Aldar announced its Q1 financial results, reporting a 20% year-on-year increase in net profit after tax to AED2.3bn ($626m).

    Aldar Development recorded a 14% year-on-year rise in revenue to $1.7bn, while earnings before interest, taxes, depreciation and amortisation (Ebitda) increased 23% to $599m.

    UAE revenue backlog rose to $17bn at the end of March from $16.6bn at the end of December, with an average duration of 29 months.

    The group attributed its performance to revenue from its development backlog and steady income from its investment properties.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17489270/main.jpeg
    Yasir Iqbal
  • Dubai sets August deadline for Airport Express metro bids

    30 June 2026

     

    Dubai’s Roads & Transport Authority (RTA) has given consultants until 10 August to submit proposals for a contract to study and design the Airport Express Line, which will extend from Dubai International airport (DXB) in the Al-Garhoud area to Al-Maktoum International Airport (DWC) in the Jebel Ali area.

    The previous deadline was 8 July.

    The proposed line will stretch about 55 kilometres and include five stations, providing passengers with facilities such as remote airline check-in, baggage drop-off and security screening.

    The RTA issued the tender in April, with an initial deadline of June, as MEED reported.

    The new line will run from the Red Line metro station at DXB through Al Jaddaf, along Al-Khail Road to a new station at Jumeirah Village Circle (JVC), before continuing to DWC.

    There will be two spur lines. The first will run from the new JVC station to Al-Fardan Exchange metro station at Emirates Golf Club, while the second will branch towards Business Bay, where another station will be built.

    The new line appears to follow a similar route to the Etihad Rail high-speed railway project, which is under construction and due to be completed by 2030.

    The Airport Express Line scheme is the latest metro project to be tendered by the RTA this year. Earlier this month, MEED exclusively reported that the RTA had issued the request for qualification notice for a contract to build the new Gold Line, as part of its expansion of the Dubai Metro network.

    Tendering activity is also ongoing for the Route 2020 extension, which will start from the Expo 2020 metro station and connect to DWC’s West Terminal.

    MEED exclusively reported in April that consultants had submitted bids for the project.

    The extension to the line will run for about 3km and will feature two stations.

    The existing Route 2020 metro link is a 15km-long line that branches off the Red Line at Jebel Ali metro station. The line comprises 11.8km of elevated tracks and 3.2km of tunnels, and has five elevated stations and two underground stations.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17489266/main.jpg
    Yasir Iqbal
  • Eni increases gas production in Libya

    30 June 2026

    The Italian oil and gas company Eni has announced the startup of offshore gas production enabled by the Sabratha compression project in Libya.

    The client on the project was Mellitah Oil & Gas (MOG), a joint venture of Eni and Libya’s state-owned National Oil Corporation (NOC).

    The Sabratha compression project was designed to increase gas output from the Bahr Essalam gas field, located approximately 100 kilometres off Libya’s coast.

    The scope of the project included the installation of a new 1,600-tonne compression module on the Sabratha platform, equipped with new compression trains, providing an overall compression capacity of about 440 million cubic feet a day.

    In a statement, Eni said: “The new module enables production under low-pressure conditions, offsetting the natural decline of the Bahr Essalam field and maximising gas recovery, ensuring increased volumes of gas of about 800 million cubic metres per year and associated condensate.

    “This additional production will play a critical role in sustaining national power generation, reinforcing Libya’s energy security, and supporting export to Italy via the Greenstream pipeline.”

    The company also said that the project strengthened the resilience of Libya’s gas infrastructure and represented “a tangible contribution to the stability and growth of the country’s energy sector”.

    MOG also has two other projects in Libya that are currently under execution.

    The first is the Bouri gas utilisation project, whose tie-in and commissioning activities are under way following the recent installation of the Bouri gas recovery module.

    The other project, known as ‘Structures A&E’, will develop two offshore gas fields.

    Eni has been present in Libya since 1959 and last year had average equity production in the country of approximately 162,000 barrels of oil equivalent a day.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17489032/main3444.jpg
    Wil Crisp
  • Jordan faces fresh round of challenges

    29 June 2026

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17479483/main.gif
    MEED Editorial