Genel Energy cuts its workforce by more than half

27 March 2024

Register for MEED's guest programme 

The Jersey-listed upstream oil company Genel Energy has cut its workforce by more than 50% in the wake of the closure of the Kirkuk-Ceyhan oil pipeline, which transports Iraqi oil through Turkiye to be exported internationally.

In a statement accompanying the company’s full-year results, Genel chief executive Paul Weir said: “It is difficult to look at 2023 without it being dominated by the closure of the Iraq-Turkiye pipeline.

“The suspension of our route to export resulted in a material reduction in production and cash flow.”

He added: “We have more than halved our workforce, and we have shed non-profitable assets.”

Weir said that he believed that the pipeline would reopen this year, but he did not give reasons why he thought the reopening would occur.

“The reopening of the export route, with a stable and predictable payment environment, is one of the numerous catalysts that we can see ahead in 2024,” he said.

Weir said the company is currently looking for opportunities outside Iraqi Kurdistan and would consider opportunities beyond the Mena region.

A two-week arbitration hearing recently took place in London over the production sharing contracts (PSCs) for Iraqi Kurdistan’s Miran and Bina Bawi oil fields.

Genel Energy had licences for the two oil fields until the Kurdistan Regional Government (KRG) terminated them in December 2021.

Genel is seeking compensation in the wake of the contract termination.

It says that it spent over $1.4bn acquiring and attempting to develop these assets, both as operator and non-operator, until the termination of both PSCs in December 2021.

The two-week arbitration hearing in London ended on 1 March 2024.

According to Genel, the timing of the result is uncertain, but is expected by the end of this year.

Genel’s net production in 2023 averaged 12,410 barrels a day (b/d), significantly down from the previous year, when the company produced 30,150 b/d.

Genel said that the significant drop in production was due to the closure of the Kirkuk-Ceyhan oil pipeline.

It said: “This caused there to be minimal sales in the second quarter of the year, before the local sales market was established in Q3 and production was then ramped up in Q4.”

All of Genel’s production in the second half of 2023 came from its Tawke PSC.

Gross production from the Tawke licence increased to 65,780 b/d in Q4 2023, up from 25,980 b/d in Q3.

At the end of 2023, gross production from the Tawke licence averaged 80,000 b/d.

In its end-of-year results, Genel said: “With operational spend having been reduced by 65%, the Tawke PSC is currently generating over $3m a month in net cash flow for Genel from strong local sales, which, if retained at current levels, is able to cover total organisational spend away from the licence.”

The company has scrapped plans to drill at the Taq Taq licence due to issues related to the closure of the Kirkuk-Ceyhan oil pipeline.

Genel and its partner, the US-based oil company Chevron, have scrapped plans to develop the Sarta oil field in Iraqi Kurdistan.

In its statement, Genel said: “Genel and its joint venture partner, Chevron, informed the Ministry of Natural Resources of its intention to surrender the asset and thereby terminate the Sarta PSC on 1 December 2023.”

Genel said it swung to a pretax loss of $28.3m in 2023, following its $122.1m profit in 2022. Revenue dropped by 79% to $84.8m from $401.9m.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11633689/main.jpg
Wil Crisp
Related Articles
  • Hyundai E&C signs $725m Saudi high voltage deal

    13 November 2024

    Register for MEED's 14-day trial access 

    South Korea’s Hyundai Engineering & Construction (E&C) has won a KRW1tn ($725m) contract to build a high-voltage direct current (HVDC) network project in Saudi Arabia.

    The contract forms part of a 1,089-kilometre (km), 500-kilovolt (kV) HVDC transmission line connecting Riyadh Power Plant 14 (PP14) to the Kudmi substation in southwest Saudi Arabia.

    Related read: Interconnection vital to GCC energy future

    The company signed the contract to build the transmission line's first package, which extends over 369km, with National Grid, the power transmission unit of state utility Saudi Electricity Company (SEC).

    The lump sum turnkey project is expected to be completed by January 2027.

    Hyundai E&C said the project will utilise a double bipole HVDC system with a power transmission capacity of 4,000MW.

    Regarded as a next-generation electricity transmission technology, an HVDC transmission system is ideal for renewable energy such as solar or wind power. It uses direct current for electricity transmission, with voltages between 100kV and 800kV.

    An HVDC system is often referred to as a 'power superhighway', transporting significantly more power over greater distances than the common high-voltage alternating current line, and incurs lower power losses.

    The South Korean contractor said it has completed 35 transmission line projects in Saudi Arabia in the past 50 years.

    Related read: Hitachi Energy rides HVDC boom

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12909551/main.jpg
    Jennifer Aguinaldo
  • Chinese-led consortium wins $262m Algeria rail deal

    13 November 2024

    Register for MEED's 14-day trial access 

    Algeria’s Anesrif has awarded a $262m construction contract to a consortium led by the China Road & Bridge Corporation (CRBC).

    The CRBC-led consortium includes China Civil Engineering Construction Corporation and Algeria’s EPE SNTP.

    The contract covers construction work for the Bouchegouf-Souk Ahras-Drea railway section, with a total length of 121 kilometres (km). It is scheduled to be completed in 32 months.

    This contract is the latest example of Chinese companies undertaking major projects in Algeria.

    MEED reported in January this year that Algeria had selected a team of Beijing-headquartered China Railway Construction Corporation and local contractor Cosider Travaux Publics for a contract to build a 575km railway line.

    The line will connect the Gara Djebilet iron ore mine in Western Algeria’s Tindouf Province with the national rail network at Bechar.

    The project will facilitate transporting materials from the Gara Djebilet iron ore mine to industrial centres and ports along Algeria’s national rail network.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12908841/main5239.gif
    Colin Foreman
  • Hatta hydropower plant heads for trial operation

    13 November 2024

    Construction work on Dubai’s Hatta pumped-storage hydroelectric power plant is 94.15% complete, and generator installations are under way in preparation for a trial operation in the first quarter of 2025.

    According to the state utility, Dubai Electricity & Water Authority (Dewa), the plant’s upper dam, which includes a 72-metre-high main wall and a 37-metre-high side dam, has also been filled.

    The plant will have a production capacity of 250MW, a storage capacity of 1,500 megawatt-hours and a lifespan of up to 80 years.

    The state utility awarded the contract to build the plant to a consortium of Austrian firms Strabag and Andritz and Turkey’s Ozkar in August 2019.

    Dewa said on 12 November that the AED1.421bn ($387m) project is expected to be fully completed by the end of the second quarter of 2025.

    The hydroelectric power plant is designed as an energy storage facility with a turnaround efficiency of 78.9%.

    It uses the potential energy of water stored in the upper dam, converting it into kinetic energy as the water flows through a 1.2-kilometre subterranean tunnel.

    This kinetic energy rotates the turbines, converting mechanical energy into electrical energy, which can be delivered to Dewa’s grid within 90 seconds to meet demand.

    To store energy, clean power generated at the Mohammed Bin Rashid Al-Maktoum Solar Park will be used to pump water back to the upper dam, converting electrical power into kinetic energy during the process.

    Dewa said the project is part of a comprehensive vision to develop Hatta and enhance its sustainable development, including the creation of job opportunities for Emiratis.

    It added that the project “also supports the Dubai Clean Energy Strategy and the Dubai Net Zero Carbon Emissions Strategy 2050”.

    Through the project, Dewa aims to diversify energy production from renewable and clean sources in Dubai. These include different available technologies, such as solar photovoltaic panels and concentrated solar power, as well as the use of renewable energy to produce green hydrogen.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12908014/main.jpg
    Jennifer Aguinaldo
  • Bahrain invites independent water prequalifications

    13 November 2024

    Bahrain’s Electricity & Water Authority (EWA) has invited interested firms to prequalify for a tender to develop the state’s first independent water project (IWP).

    The Al-Hidd seawater reverse osmosis (SWRO) plant is expected to have a production capacity of about 60 million imperial gallons a day (MIGD) of potable water.

    The client expects firms to submit their statements of qualifications (SOQs) by 18 December.

    The facility will be developed on a brownfield site and is expected to be fully operational by the second quarter of 2028. It will help expand Bahrain’s water infrastructure to meet projected demand based on its 2030 master plan.

    The Al-Hidd IWP will be developed using a build, own and operate (BOO) model for 20 to 25 years.

    EWA has also issued the prequalification request for another BOO project, MEED reported on 11 November.

    The Sitra independent water and power project (IWPP) is a combined-cycle gas turbine (CCGT) plant expected to have a production capacity of about 1,200MW of electricity. The project’s SWRO desalination facility will have a production capacity of 30MIGD of potable water.

    The plant is Bahrain’s fourth IWPP, replacing the previously planned Al-Dur 3. The Sitra IWPP is expected to be fully operational by the second quarter of 2029.

    Sixty representatives from utility developers and contracting firms attended a market-sounding event for the two separate utility BOO projects in Manama on 21 October.

    The firms that sent representatives to the event included France’s Engie, Japan’s Mitsui, Saudi Arabia’s Acwa Power, AlJomaih Electricity & Water Company and Ajlan & Bros, and Kuwait’s Gulf Investment Corporation, among others, said sources.

    EWA’s transaction advisory team for the two BOO projects comprises KPMG Fakhro as the financial consultant, WSP Parsons Brinckerhoff as the technical consultant and Trowers & Hamlins as the legal consultant.

    MEED understands that EWA’s Sitra IWPP will likely be Bahrain’s last CCGT plant project. Solar power is expected to account for all future electricity generation capacity.

    Bahrain aims to reach net-zero carbon emissions by 2060.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12907891/main.gif
    Jennifer Aguinaldo
  • Neom replaces CEO

    12 November 2024

    Register for MEED's 14-day trial access 

    Nadhmi Al-Nasr has left his role as Neom CEO and will be replaced by Aiman Al-Mudaifer as acting CEO of the company developing the $500bn project in northwestern Saudi Arabia, which includes The Line, Trojena and Oxagon.

    In a statement published online, Neom said: “The Neom Board of Directors today announced the appointment of Eng. Aiman Al-Mudaifer as acting CEO of the company. Eng. Al-Mudaifer assumes leadership of Neom, following Nadhmi Al-Nasr’s departure.”

    The statement added: “As Neom enters a new phase of delivery, this new leadership will ensure operational continuity, agility and efficiency to match the overall vision and objectives of the project.”

    Al-Mudaifer has been head of the Public Investment Fund’s local real estate division since 2018, and the Neom statement says he has a deep and strategic understanding of Neom and its projects.

    Neom has attracted significant criticism over the past year as it grapples with major programmes of construction work such as The Line. In a statement announcing the appointment of consultants for work on The Line on 11 November, Neom said it “is currently focused on the initial phases of infrastructure and enabling works for the new city”.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12902059/main.jpg
    Colin Foreman