GCC’s ambitious railway project gains momentum
17 July 2023

Register for MEED's guest programme
The GCC railway project has continued to make progress in 2023. After an official announcement by the GCC secretariat in January 2021 that effectively restarted the project, a string of recent moves and statements have meant all six members of the bloc have either declared or signalled their plans for their sections of the rail network.
In early July, officials from Bahrain's Ministry of Transportation and Telecommunications met with a delegation from the GCC Rail Authority led by Nasser Hamad al-Qahtani and Abdullah bin Abdulaziz al-Samaani.
The two sides discussed the railway connecting Saudi Arabia and Bahrain across the proposed King Hamad Causeway and reviewed the progress of the new crossing. The meeting also included the exchange of information regarding engineering designs and contact points between the two countries.
The railway crossing the King Hamad Causeway will extend inland by another 21 kilometres into Saudi Arabia and 24km into Bahrain. It is understood the railway route extending inland into Bahrain will eventually link up with the planned GCC railway network.
In November 2019, the Netherlands' KPMG, US-based Aecom and Germany-headquartered CMS were appointed as advisers for the project.
Kuwait advances
The meeting between the two countries follows developments elsewhere in the GCC. In May, Saudi Arabia’s King Salman bin Abdulaziz al-Saud authorised the minister of transport and logistics services as his representative to discuss a draft agreement with Kuwait regarding a rail link connecting the two countries.
MEED reported in early May that Saudi Arabia Railways (SAR) and the Saudi Public Transport Authority had appointed France’s Systra to complete the feasibility study for a high-speed rail link connecting the kingdom and Kuwait.
Bid submission is currently in progress for study and detailed design services for the rolling stock and civil works packages 1 and 2.
Kuwait is also pushing ahead with the Kuwait National Rail Road (KNRR) project. The scheme is seen as a significant component of the country's contribution to the GCC railway. The project owner, Kuwait’s Public Authority for Roads and Land Transportation (Part), through the Kuwait Authority for Partnership Projects (Kapp), issued a request for proposals (RFP) in January this year. The original closing date was 21 February and the deadline was then extended to 11 July.
Oman links
Progress is also being made on the railway linking the UAE and Oman. In September 2022, the two countries established Oman-Etihad Rail Company to implement the 303-kilometre network. The project received a further boost after Oman-Etihad Rail Company inked a strategic agreement with Abu Dhabi-based Mubadala Investment Company to support its development.
The prequalification process is underway for the UAE Civil Package A, Oman Civil Package B and Oman Civil Package C projects, and is expected to be completed in the third quarter of 2023. Contractors based in the UAE, Oman, Turkiye, Greece, India and China have started seeking to qualify for the packages on the $3bn rail connection.
“The prequalification process is currently under way, and we hope to award [the project] on schedule as planned,” said UAE Minister of Energy and Infrastructure, and Oman-Etihad Rail Company chairman of the board of directors, Suhail Mohamed Faraj al-Mazrouei, in an interview with MEED.
Oman-Etihad Rail Company also signed a memorandum of understanding (MoU) with Brazilian mining company Vale to explore using rail to transport iron ore and its derivatives between Oman and the UAE. Railways could connect Vale’s industrial complex in Oman’s Sohar Port and Freezone and its planned development, known as a Mega Hub, at Khalifa Economic Zones Abu Dhabi (Kezad).
Oman is also collaborating with Saudi Arabia for the establishment of a railway link connecting Duqm with Riyadh through the Ibri border. The railway line aims to serve the upcoming economic zone that the two countries are planning to build in the Al-Dhahirah area.
Qatar connection
Meanwhile, GCC railway projects have been progressing with renewed impetus following the Al-Ula declaration signed by the six member states in January 2021. Under the declaration, Saudi Arabia and Qatar agreed to restore their diplomatic ties and restart the rail link connecting the two countries.
In July 2021, Systra was selected to conduct a feasibility study on the proposed high-speed rail line connecting Riyadh and Doha, which could use maglev technology. The study works are still ongoing on the project. The railway line could be about 550 kilometres long. As well as maglev, the study will also evaluate using other high-speed rail technologies.
The restoration of diplomatic ties between Qatar and Bahrain in mid-April will improve the prospects of the $4bn Qatar-Bahrain Causeway. In March 2022, Manama called for work to restart on the causeway, which is a key link for the GCC rail network.
Rail authority
GCC leaders approved the establishment of the GCC Rail Authority in January 2022. The company was entrusted with the overall policymaking and coordination among member states to ensure smooth delivery and operations of the overall scheme.
With high project activity levels, governments in spending mode, and the agreements under the Al-Ula declaration, the latest efforts to restart the GCC railway project may make more progress than previous attempts. If the railway is finally completed, it could prove transformative for a region that feels connected to the world but divided between its constituent parts.
Exclusive from Meed
-
Kuwait awards $381m oil project23 September 2026
-
Kuwait refinery project on track for year-end completion23 September 2026
-
Contractor wins $208m Almoosa hospital MEP contract23 September 2026
-
UAE to develop integrated waste-to-resource pilot23 September 2026
-
Contractors prepare Oxagon Highway 55 bids23 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Kuwait awards $381m oil project23 September 2026
Register for MEED’s 14-day trial access
State-owned upstream operator Kuwait Oil Company (KOC) has awarded an oil project contract worth KD117m ($381m) to India’s Megha Engineering & Infrastructure (Meil).
The Supreme Purchasing Committee for Kuwait Petroleum Corporation (KPC) approved the contract last month, paving the way for the official award.
The project focuses on a water separation unit at the Al-Rawdatain facility in Kuwait.
The water separation facility will be developed at Gathering Centre 25 (GC-25), along with a pumping facility at GC-30.
The project will deliver a wide-ranging upgrade of processing and utility infrastructure, including new low-pressure separation and gas-handling equipment such as a three-phase wet separator package, a gas knock-out drum and associated low-pressure gas pipelines, as well as a high-integrity pressure protection system and a high-pressure flare.
Meil will develop the new three-phase low-pressure wet separation facility at GC-25.
The main process equipment will include two wet separator packages, each with a capacity of 150,000 barrels of liquid a day, and a low-pressure gas knock-out drum with a capacity of 53 million standard cubic feet a day, together with associated gas-handling facilities.
The facility will also incorporate an effluent water treatment and transfer system, including an effluent water balance tank equipped with microbubble flotation and induced gas flotation systems, as well as transfer pumps.
Additional GC-25 facilities will include fuel gas treatment, chemical injection, oil recovery and flare connections, along with firewater and deluge systems.
The scope also covers control and safety systems, substations, and associated civil, structural, mechanical, electrical and instrumentation works.
At GC-30, the project will focus on treated-water filtration and high-pressure injection infrastructure.
The scope includes nutshell filters and associated feed pumps with a combined capacity of approximately 500,000 barrels of water a day.
Booster and injection pumps will transfer treated effluent water to designated injection wells.
Additional facilities at GC-30 will include fuel gas treatment, sludge collection and disposal systems, oil recovery systems, control and safety systems, substations, laboratory and workshop facilities, and associated civil, structural, piping, mechanical, electrical and instrumentation works.
The project also includes transfer pipelines connecting GC-25, GC-15 and GC-30.
Meil will carry out modifications to existing tanks at GC-30, as well as process and utility tie-ins, electrical and instrumentation modifications and other infrastructure required to integrate the new facilities with KOC’s existing assets.
Meil’s responsibilities cover the project lifecycle from design and engineering through procurement, construction, testing, pre-commissioning, commissioning, start-up and performance testing.
The contract also includes operation, maintenance, repair and insurance responsibilities for the designated facilities during the applicable operations and maintenance period.
Seven companies submitted bids for the project last November.
The full list of bids was:
- Meil (India) – KD117m ($381m)
- Mechanical Engineering & Contracting Company (Kuwait) – KD130m
- Spetco (Kuwait) – KD158m
- Al-Kharafi (Kuwait) – KD164m
- China Oil HBP Science & Technology (China) – KD169m
- Alghanim International (Kuwait) – KD169m
- Jereh Oil & Gas Engineering (China) – KD191m
In October last year, KOC awarded Meil a separate contract for a project to develop a gas sweetening and recovery facility in west Kuwait.
Meil submitted the lowest bid for that tender, at KD69.2m ($225.5m), in February 2025.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19911322/main.jpg -
Kuwait refinery project on track for year-end completion23 September 2026

A $65m project to replace a substation at the Mina Al-Ahmadi (MAA) refinery is on schedule to be mechanically complete before the end of the year, according to industry sources.
The project is being executed by India’s Larsen & Toubro (L&T), which was awarded the contract in October 2024.
One source said: “This project is approaching completion and is currently on schedule to be completed before the end of the year, although it could still see delays related to the ongoing regional conflict.”
The client is state-owned downstream operator Kuwait National Petroleum Company (KNPC).
Kuwait’s Ministry of Electricity, Water & Renewable Energy (MEW) is also involved in the project and will provide final approvals and sign-off.
The scope of the project includes:
- Construction of a substation
- Installation of transformers
- Installation of medium-voltage switchgear
- Installation of low-voltage auxiliary systems
- Installation of network protection systems
- Installation of disconnecting switches
- Installation of surge arrestors
- Installation of feeder breakers and cubicles
- Installation of low-voltage A/C and D/C equipment
- Installation of battery banks and battery chargers
- Installation of related relay and control panel boards
- Installation of fire alarm and fire protection equipment
- Installation of a SCADA system
- Installation of cables
- Civil works
- Associated facilities
The current project to replace a substation at the MAA refinery closely resembles another project tendered by KNPC more than a decade ago, which L&T also won.
On 18 May 2015, KNPC signed a contract with L&T to build a new 240MW substation at the MAA refinery, valued at KD21.866m.
The new substation, known as M20, was designed to replace an existing substation that was considered old and obsolete.
Mohammed Al-Mutairi, who was KNPC’s chief executive at the time, said the substation building would be explosion-proof and use state-of-the-art control systems.
He said the station’s capacity would increase from 180MW to 240MW, supplying most of the refinery’s electricity needs.
Given the similarities between the two projects, L&T has been able to reuse some designs, creating efficiencies, according to industry sources.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19911319/main.jpg -
Contractor wins $208m Almoosa hospital MEP contract23 September 2026
Register for MEED’s 14-day trial access
Riyadh-based construction firm BEC Arabia has won a SR781m ($208m) contract for the mechanical, electrical and plumbing (MEP) works at Almoosa Hospital in Al-Khobar.
Saudi Arabia’s Almoosa Health Company awarded the contract.
The hospital complex consists of two towers: a 24-storey in-patient tower with 380 beds, and an 11-storey tower with 224 clinics and 113 additional treatment spaces.
It will be built on a 45,000-square-metre site.
A podium spanning the ninth and 10th floors will connect the two towers.
The hospital will also include parking for 1,700 cars.
BEC Arabia won the SR656m ($175m) main construction contract for the hospital in November last year.
In August 2025, MEED reported that Almoosa Health Company had announced it had secured a sharia-compliant credit facility worth SR650m ($173m) from Banque Saudi Fransi.
In a statement published on the Saudi stock exchange (Tadawul), the company said the seven-year facility would be used to support its expansion and growth strategy.
Lebanon’s Dar, US-based Perkins&Will and French design firm Pierre-Yves Rochon designed the project.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19910889/main.jpg -
UAE to develop integrated waste-to-resource pilot23 September 2026
Emirates Biotech and United Arab Emirates University (UAEU) have launched a pilot project in Al-Ain that could provide a model for larger waste-to-resource facilities.
The project involves developing the UAE’s first integrated organic-waste valorisation pilot plant, which will test whether food waste and compostable packaging can be processed together to recover resources and reduce waste sent to landfill.
Located near the UAEU campus, the 40kg-a-day facility will process organic waste to produce renewable biogas and nutrient-rich compost. The project is intended to generate technical and operating data that could support the development of larger-scale facilities.
Emirates Biotech and UAEU will design, build and operate the pilot plant as part of a two-year research project running from August 2026 to August 2028. Installation and commissioning are expected to be completed by August 2027.
The plant will combine anaerobic digestion and composting. Anaerobic digestion will convert the organic waste into renewable biogas, while the resulting digestate will be composted to produce nutrient-rich compost.
A laboratory-scale assessment will also examine the potential to convert the biogas into renewable hydrogen.
Food waste accounts for nearly 40% of daily municipal solid waste in the UAE, according to Emirates Biotech, and much of it is currently disposed of in landfills.
The pilot will therefore assess the technical and operational feasibility of recovering value from two waste streams through a single integrated process.
If successfully scaled, Emirates Biotech says an integrated organic-waste valorisation plant could reduce CO₂ emissions by 89% compared with landfilling.
The project is expected to provide a scalable and modular model for converting food waste and compostable packaging into renewable biogas and compost, with the findings intended to inform the development of larger waste-to-resource facilities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19908972/main.jpg -
Contractors prepare Oxagon Highway 55 bids23 September 2026

Contractors are preparing to submit bids on 28 September for a design-and-build contract for permanent upgrade works on Highway 55 in the kingdom’s Oxagon region.
The first phase of the project includes constructing 14 kilometres of road, with two lanes in each direction. It also includes one bridge and three interchanges.
The project duration is 22 months.
Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.
MEED reported exclusively in August 2025 that contractors had submitted responses to an expression of interest notice that Neom had issued earlier that month.
The project is expected to support cargo movement from Duba Port to other parts of the kingdom and the wider region.
Last year, Neom tested a pilot initiative by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.
In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”
The Port of Neom is located on the Red Sea near the Arar border, a key entry point into Iraq.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19907876/main.jpg