GCC leans towards battery energy storage

29 January 2024

 

The central tower of Noor Energy 1, the hybrid solar photovoltaic (PV) and concentrated solar power (CSP) fourth phase of the Mohammed bin Rashid Al Maktoum (MBR) Solar Park, is visible to motorists on the Saih Al Dahal Road on the outskirts of Dubai.

The 263-metre solar tower is part of the $4.3bn project that is touted as the largest CSP and thermal energy storage (TES) facility in the world.

It heats the salt stored in nearby tanks during the day to enable the production of energy at night.

Awarded in 2017 to a team led by Saudi utility developer Acwa Power, Noor Energy 1 will deliver electricity at a levelised tariff of $cents 7.30 a kilowatt-hour ($c/kWh), which Acwa Power says competes with fossil fuel-generated electricity without subsidy for reliable and dispatchable solar energy through the night.

Sheikh Mohammed bin Rashid Al Maktoum, UAE Vice President and Prime Minister and Ruler of Dubai, inaugurated the project in December.

The project’s higher levelised cost of energy (LCOE) compared to a plain solar PV plant accounts for the round-the-clock capability of the Noor Energy 1 plant to produce power.

The power-purchase agreement (PPA) for the project is for 35 years, which is 5-10 years longer than the average solar PPA in the Gulf region.

Competing technology

Six to seven years after the Noor Energy 1 contract was awarded, a competing technology addressing spinning reserve and intermittency when coupled with a renewable energy plant – battery energy storage –  is gaining acceptance.

Lithium-ion batteries store excess energy produced during the day, which can then be discharged at night, providing grid stability that until recently has been supplied by gas-powered or liquid fuel-powered generation plants.

The cost of batteries is forecast to decline significantly over the next six years and beyond, although the LCOEs for solar or wind farms with storage capacity are still broadly considered significantly higher than those without.

Source: Lazard

According to the US-headquartered financial advisory firm Lazard, the average LCOE in an unsubsidised, utility-scale solar PV averaged between $24 and $96 a megawatt-hour (MWh) in 2023. In comparison, the added cost of lithium-ion batteries with four-hour storage capacity to a similar solar PV farm takes the LCOE to between $46 and $102/MWh.

Critical choices

Several CSP with TES (CSP+TES) projects have been awarded and completed in the Middle East and North Africa region. Kuwait and Abu Dhabi have built 50MW and 100MW CSP facilities, respectively, while Acwa Power has developed three CSP plants with a total combined capacity of 500MW in Morocco.

However, not many CSP+TES projects are forthcoming.

Saudi Arabia previously planned to procure a hybrid solar and CSP+TES project, but such a scheme is not included in the fifth and sixth procurement rounds of its National Renewable Energy Programme.

In 2019, Morocco awarded the contract for Noor Midelt 1, an 800MW solar CSP scheme, but it is understood that the project has yet to reach financial close and construction work has yet to start.

In comparison, half of the GCC states are planning to procure battery energy storage system projects using an independent power producer (IPP) model.

Saudi Arabia plans to procure 10GW of battery energy storage capacity, equivalent to 40 gigawatt-hours (GWh), by 2030. The procurement process is expected to start this year for the first phase, which will comprise a dozen sites with a total capacity of 2GW.

Abu Dhabi's Emirates Water & Electricity Company (Ewec) received expressions of interest from developers last year for its first 400MW battery energy storage project.

Oman, which does not plan to procure further gas-powered plants, is also considering a similar project.

"Broadly, battery energy storage solutions make more sense now than CSP+TES technology," a Dubai-based renewable energy expert tells MEED.

Others, however, remain convinced that there will continue to be a place for CSP+TES, especially in jurisdictions with plenty of barren and unused land. This is mainly due to the technology's ability to produce up to eight hours of energy, compared to an average of four hours offered by lithium-ion batteries.

The first utility-scale battery storage installation in the GCC is in Saudi Arabia. The 1,300MWh facility is designed to support the off-grid utility infrastructure of the Red Sea Project development. The smaller Amaala project will also feature a 700MWh battery storage capacity.

Neom Green Hydrogen Company has incorporated a 400MW battery facility as part of the more than 4GW renewable energy contract it awarded India's Larsen & Toubro last year. The infrastructure will support a 2GW electrolysis plant that will produce green hydrogen to be converted into ammonia for export to Europe.

However, some Middle East-based renewable energy developers remain cautious about the timeline and the scale of the planned battery storage independent power projects across the region. 

"It is not clear if they have received an official mandate to proceed with the projects, but we are definitely interested in bidding," says a Dubai International Financial Centre-based executive from an international utility developer.

Related reads:

 

https://image.digitalinsightresearch.in/uploads/NewsArticle/11469204/main1005.jpg
Jennifer Aguinaldo
Related Articles
  • Abu Dhabi seeks firms for Mid Island Parkway PPP

    15 May 2026

     

    Register for MEED’s 14-day trial access 

    Modon Infrastructure, formerly known as Gridora, has invited firms to submit their registrations for the next phase of Abu Dhabi’s Mid Island Parkway Project (MIPP), which will be developed on a public-private partnership (PPP) basis.

    The request for qualifications (RFQ) is expected to be issued to interested parties soon.

    Modon Infrastructure will act as the lead developer with the majority of the equity in the project company. It will award the engineering, procurement, and construction contractor, the operations and maintenance providers, and the advisers.

    The second phase of the MIPP involves the construction of about 11 kilometres (km) of highways, including a mix of three-, four- and five-lane highways. The highways will connect the Um-Yifeenah, Al-Jubail, Al-Sammaliyyah and Sas Al-Nakhl islands to Khalifa City and the E10 road.

    The scope also covers the construction of three interchanges: the E20, E10 and Dumbbell interchanges on Al-Sammaliyyah Island.

    The project includes several major structures, such as the E20 interchange featuring cast-in-place box girder and void slab bridges, and the E10 interchange with cast-in-place box girder bridges. It also includes I-girder bridges between Raha Beach West and Sas Al-Nakhl Island, as well as a causeway at Sas Al-Nakhl Island.

    Further key elements include a cast-in-place balanced cantilever bridge between Sas Al-Nakhl Island and Al-Sammaliyyah Island, a tunnel between Al-Sammaliyyah Island and Bilrimaid Island, and a cut-and-cover (open) tunnel on Bilrimaid Island. The project is completed with another tunnel connecting Bilrimaid Island to Um-Yifeenah Island.

    Abu Dhabi awarded three packages for phase one of the MIPP in 2024. The contract for package 1A was awarded to a joint venture of Turkish contractor Dogus Construction and UAE firm Gulf Contractors. Package 1B was awarded to a joint venture of Yas Projects (Alpha Dhabi Holding) and China Railway International Group. Beijing-headquartered China Harbour Engineering Company and the UAE’s Agility Engineering & Contracting Company won the contract for package 1C.

    Phase one starts at the existing Saadiyat interchange, connecting the E12 to the MIPP, and ends at the recently constructed Um-Yifeenah highway. 

    It comprises a dual main road with a total length of 8km, including four traffic lanes in each direction, two interchanges, a tunnel and associated infrastructure works.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16858325/main.jpg
    Colin Foreman
  • Oman seeks adviser for gas-fired IPPs

    15 May 2026

    Oman’s Nama Power & Water Procurement Company (PWP) has issued a request for proposals for technical consultancy services for the development of new gas-fired independent power projects (IPPs) in the sultanate.

    The state offtaker said the projects will have a total capacity of up to 2,800MW.

    The bid submission deadline is 17 June.

    While Oman is accelerating investment in renewable energy and battery storage, gas-fired thermal generation is expected to remain a core part of the country’s power mix over the coming decade.

    The Misfah and Duqm combined-cycle gas turbine power plants are advancing towards construction following the appointment of China-headquartered Shandong Electric Power Construction No. 3 Company (Sepco 3) and South Korea’s Doosan Enerbility as contractors.

    According to Nama PWP’s 2025 annual report, the Duqm IPP will have a total capacity of 877MW, including 555MW of early power capacity, which is scheduled to commence in Q2 2028.

    The Misfah IPP will have a total capacity of 1,700MW, including 1,203MW of early power capacity, which is scheduled to commence in the same quarter.

    Nama PWP has also recently awarded new power-purchase agreements (PPAs) to three IPPs to extend the operating life of existing gas-fired power plants beyond the expiry of their current contracts.

    The new agreements for the 750MW Sohar 2 IPP and 750MW Barka 3 IPP will take effect on 1 April 2028 and run until 31 March 2043. The agreement for the 200MW Sur IPP will commence on 1 April 2029 and run until 31 March 2044.

    The awards form part of Nama PWP’s 2028-29 procurement programme. The programme aims to secure firm generation capacity from existing assets whose current PPAs are due to expire during that period.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16857037/main4750.jpg
    Mark Dowdall
  • Alghanim submits lowest offer for Kuwait oil refinery project

    15 May 2026

    Kuwait’s Alghanim International General Trading & Contracting has submitted the lowest bid for a contract to upgrade the country’s Mina Al-Ahmadi (MAA) refinery.

    The client is state-owned downstream operator Kuwait National Petroleum Company (KNPC). The project scope covers upgrades to water transmission and storage infrastructure at the refinery.

    The contract will be delivered under an engineering, procurement and construction (EPC) model. The tender was issued in October 2025 with an initial bid deadline of 4 January 2026, which was later extended several times. The most recent rescheduling moved the deadline from 19 April to 10 May.

    Alghanim submitted a bid of KD37.0m ($120m), significantly lower than the other two bidders, both Kuwait-based: Heavy Engineering Industries & Shipbuilding Company (Heisco) at KD60.6m ($197m) and Gulf Spic General Trading & Contracting at KD63.9m ($207m).

    The project is expected to take two years to complete and will expand water storage capacity at the facility by extending existing tanks or constructing new ones. The contractor will also develop associated infrastructure and upgrade systems that transport desalinated water to the refinery, including pipelines and related equipment.

    In its 2024-25 annual report, KNPC said the project will help meet water demand for the facility’s refining and gas production units.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16852744/main.jpg
    Wil Crisp
  • Civil and piping work starts on Iraq field development

    15 May 2026

     

    Civil works and piping work have started for the project to develop a second central processing facility (CPF) at Iraq’s Ratawi oil and gas field, according to industry sources.

    The project is part of the $27bn Gas Growth Integrated Project (GGIP), which is being developed by TotalEnergies along with its partners Basra Oil Company (BOC) and Qatar Energy.

    Phase one of the GGIP is expected to be worth about $10bn.

    Work is progressing on the project despite logistical problems related to the regional conflict that broke out after the US and Israel attacked Iran on 28 February.

    While early works are ongoing, equipment needed for later stages of the project is being delayed as it was due to be transported to the project site using ships that would have travelled through the Strait of Hormuz.

    Shipping through the Strait is still severely disrupted due to the regional conflict.

    In September, Turkiye’s Enka signed a contract to develop the second CPF at Iraq’s Ratawi field as part of the second phase of the field’s development.

    Enka did not give a value for the contract, but it is believed to be worth more than $1bn.

    In November, US-based KBR was selected by Enka to provide detailed design services for the project.

    Enka’s contract covers the engineering, procurement, supply, construction and commissioning of the CPF for the project known as the Associated Gas Upstream Project Phase 2 (AGUP2).

    The aim of the AGUP2 project is to process oil and associated gas from the Ratawi oil field to increase production capacity to 210,000 barrels a day of oil and 154 million standard cubic feet a day of gas.

    GGIP masterplan

    The GGIP programme is being led by TotalEnergies, the operator, which holds a 45% stake.

    Basra Oil Company and QatarEnergy hold 30% and 25% stakes, respectively. The consortium formalised the investment agreement with the Iraqi government in September 2021.

    The four projects that comprise the GGIP are:

    • The Common Seawater Supply Project (CSSP)
    • The Ratawi gas processing complex
    • A 1GW solar power project for Iraq’s electricity ministry
    • A field development project at Ratawi, known as the Associated Gas Upstream Project (AGUP)

    The CSSP is designed to support oil production in Iraq’s southern oil and gas fields – mainly Zubair, Rumaila, Majnoon, West Qurna and Ratawi – by delivering treated seawater for injection, a method used to boost crude recovery rates and improve long-term reservoir performance.

    China Petroleum Engineering & Construction Corporation (CPECC) won a $1.61bn contract in May to execute EPC work for the gas processing complex at the Ratawi field development.

    CPECC’s project team based in its Dubai office is performing detailed engineering work on the project.

    In August last year, TotalEnergies awarded China Energy Engineering International Group the engineering, procurement and construction (EPC) contract for the 1GW solar project at the Ratawi field. A month later, QatarEnergy signed an agreement with TotalEnergies to acquire a 50% interest in the project.

    The 1GW Ratawi solar scheme will be developed in phases, with each phase coming online between 2025 and 2027. It will have the capacity to provide electricity to about 350,000 homes in Iraq’s Basra region.

    The project, consisting of 2 million bifacial solar panels mounted on single-axis trackers, will include the design, procurement, construction and commissioning of the photovoltaic power station site and 132kV booster station.

    Separately, in June, TotalEnergies awarded China Petroleum Pipeline Engineering an EPC contract worth $294m to build a pipeline as part of a package known as the Ratawi Gas Midstream Pipeline.

    Also, TotalEnergies awarded UK-based consultant Wood Group a pair of engineering framework agreements in April, worth a combined $11m, under the GGIP scheme.

    The agreements have a three-year term under which Wood will support TotalEnergies in advancing the AGUP.

    One of the aims of the AGUP is to debottleneck and upgrade existing facilities to increase production capacity to 120,000 b/d of oil on completion of the first phase, according to a statement by Wood.


    READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Global energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.

    Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16852654/main.png
    Wil Crisp
  • Abu Dhabi selects Yas Island site for $1.7bn Sphere venue

    14 May 2026

    Abu Dhabi’s Department of Culture & Tourism (DCT Abu Dhabi) and US-based Sphere Entertainment have selected Yas Island as the location for the $1.7bn Sphere Abu Dhabi project.

    The venue will be built on a plot between Yas Mall and SeaWorld Abu Dhabi, close to Yas Island’s theme parks and attractions. Construction is expected to be completed by the end of 2029. Dubai-listed Alec is understood to be the selected contractor and has been working on the project’s pre-construction phase.

    The project will be the first Sphere venue outside the US. It is expected to echo the scale of Sphere Las Vegas, with a capacity of up to 20,000 depending on configuration.

    DCT Abu Dhabi said it will coordinate enabling and infrastructure works with Abu Dhabi entities, including the Department of Municipalities & Transport and its Integrated Transport Centre, the Department of Energy, Taqa, Etihad Rail and Aldar. The scope includes road enhancements, site access and site-wide infrastructure integrated with surrounding Yas Island assets.

    Sphere Abu Dhabi is the latest addition to Abu Dhabi’s integrated tourism and destination-development pipeline on Yas Island, alongside major attractions and the Disney theme park resort that was announced in 2025.

    DCT and Sphere Entertainment finalised an agreement last year related to the construction, development and operation of the Sphere entertainment venue in Abu Dhabi. According to the agreement, Sphere Entertainment granted DCT the exclusive rights to build and operate the Sphere Abu Dhabi entertainment venue.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16837302/main.gif
    Colin Foreman