GCC leans towards battery energy storage

29 January 2024

 

The central tower of Noor Energy 1, the hybrid solar photovoltaic (PV) and concentrated solar power (CSP) fourth phase of the Mohammed bin Rashid Al Maktoum (MBR) Solar Park, is visible to motorists on the Saih Al Dahal Road on the outskirts of Dubai.

The 263-metre solar tower is part of the $4.3bn project that is touted as the largest CSP and thermal energy storage (TES) facility in the world.

It heats the salt stored in nearby tanks during the day to enable the production of energy at night.

Awarded in 2017 to a team led by Saudi utility developer Acwa Power, Noor Energy 1 will deliver electricity at a levelised tariff of $cents 7.30 a kilowatt-hour ($c/kWh), which Acwa Power says competes with fossil fuel-generated electricity without subsidy for reliable and dispatchable solar energy through the night.

Sheikh Mohammed bin Rashid Al Maktoum, UAE Vice President and Prime Minister and Ruler of Dubai, inaugurated the project in December.

The project’s higher levelised cost of energy (LCOE) compared to a plain solar PV plant accounts for the round-the-clock capability of the Noor Energy 1 plant to produce power.

The power-purchase agreement (PPA) for the project is for 35 years, which is 5-10 years longer than the average solar PPA in the Gulf region.

Competing technology

Six to seven years after the Noor Energy 1 contract was awarded, a competing technology addressing spinning reserve and intermittency when coupled with a renewable energy plant – battery energy storage –  is gaining acceptance.

Lithium-ion batteries store excess energy produced during the day, which can then be discharged at night, providing grid stability that until recently has been supplied by gas-powered or liquid fuel-powered generation plants.

The cost of batteries is forecast to decline significantly over the next six years and beyond, although the LCOEs for solar or wind farms with storage capacity are still broadly considered significantly higher than those without.

Source: Lazard

According to the US-headquartered financial advisory firm Lazard, the average LCOE in an unsubsidised, utility-scale solar PV averaged between $24 and $96 a megawatt-hour (MWh) in 2023. In comparison, the added cost of lithium-ion batteries with four-hour storage capacity to a similar solar PV farm takes the LCOE to between $46 and $102/MWh.

Critical choices

Several CSP with TES (CSP+TES) projects have been awarded and completed in the Middle East and North Africa region. Kuwait and Abu Dhabi have built 50MW and 100MW CSP facilities, respectively, while Acwa Power has developed three CSP plants with a total combined capacity of 500MW in Morocco.

However, not many CSP+TES projects are forthcoming.

Saudi Arabia previously planned to procure a hybrid solar and CSP+TES project, but such a scheme is not included in the fifth and sixth procurement rounds of its National Renewable Energy Programme.

In 2019, Morocco awarded the contract for Noor Midelt 1, an 800MW solar CSP scheme, but it is understood that the project has yet to reach financial close and construction work has yet to start.

In comparison, half of the GCC states are planning to procure battery energy storage system projects using an independent power producer (IPP) model.

Saudi Arabia plans to procure 10GW of battery energy storage capacity, equivalent to 40 gigawatt-hours (GWh), by 2030. The procurement process is expected to start this year for the first phase, which will comprise a dozen sites with a total capacity of 2GW.

Abu Dhabi's Emirates Water & Electricity Company (Ewec) received expressions of interest from developers last year for its first 400MW battery energy storage project.

Oman, which does not plan to procure further gas-powered plants, is also considering a similar project.

"Broadly, battery energy storage solutions make more sense now than CSP+TES technology," a Dubai-based renewable energy expert tells MEED.

Others, however, remain convinced that there will continue to be a place for CSP+TES, especially in jurisdictions with plenty of barren and unused land. This is mainly due to the technology's ability to produce up to eight hours of energy, compared to an average of four hours offered by lithium-ion batteries.

The first utility-scale battery storage installation in the GCC is in Saudi Arabia. The 1,300MWh facility is designed to support the off-grid utility infrastructure of the Red Sea Project development. The smaller Amaala project will also feature a 700MWh battery storage capacity.

Neom Green Hydrogen Company has incorporated a 400MW battery facility as part of the more than 4GW renewable energy contract it awarded India's Larsen & Toubro last year. The infrastructure will support a 2GW electrolysis plant that will produce green hydrogen to be converted into ammonia for export to Europe.

However, some Middle East-based renewable energy developers remain cautious about the timeline and the scale of the planned battery storage independent power projects across the region. 

"It is not clear if they have received an official mandate to proceed with the projects, but we are definitely interested in bidding," says a Dubai International Financial Centre-based executive from an international utility developer.

Related reads:

 

https://image.digitalinsightresearch.in/uploads/NewsArticle/11469204/main1005.jpg
Jennifer Aguinaldo
Related Articles
  • EtihadWE tenders $150m Ajman substation project

    21 July 2026

    The UAE’s Etihad Water & Electricity (EtihadWE) has tendered a contract to build three new substations in Ajman.

    Estimated to cost $150m, the project involves the construction of three new 132/11kV substations in the Bahya, Rumaila and Liwara districts. It also includes associated 132kV underground cabling works to connect the substations to the existing transmission network.

    The bid submission deadline is 10 August.

    According to tender documents, the project will add distribution capacity to support load growth and improve the security of electricity supply in the emirate.

    The scope of work includes site preparation, construction of three substation buildings and foundations, installation of 132kV GIS/AIS switchgear, 132/11kV power transformers and 11kV switchgear, as well as protection, control, Scada and telecommunications systems.

    Etihad WE is responsible for electricity and water services in Ajman, Umm Al-Quwain, Ras Al-Khaimah, Fujairah and parts of Sharjah. The utility has been investing in new substations and transmission infrastructure as electricity demand continues to increase across the Northern Emirates.

    This includes a 132/33/11kV substation project on Al-Marjan Island in Ras Al-Khaimah. Construction work is ongoing on the project, with Maetal Dubai serving as the main contractor.

    EtihadWE is also finalising a new masterplan that will cover network capacity requirements and expansion priorities for the next 10 to 15 years.

    In June, Abdulla Al-Khemeiri, chief operations officer, told MEED: “We are currently reviewing it, and we need to obtain shareholder approval first. Once it is approved, it will be released, hopefully by the end of the year.” 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17710661/main.jpg
    Mark Dowdall
  • Seven seeks contractors for Dammam water park and hotel

    21 July 2026

     

    Saudi Entertainment Ventures (Seven), a wholly owned subsidiary of the Public Investment Fund, is preparing to shortlist general contractors for the main construction package of its Dammam Water Park & Hotel project in the Al-Hamra district.

    The waterfront development sits on a 324,300-square-metre (sq m) plot.

    A notice was issued to contractors in July, and the client is expected to finalise the shortlist by the end of this month.

    Seven is seeking firms capable of delivering a lump-sum, turnkey solution for both the water park and a 321-key lifestyle hotel. Construction is expected to take 24 months from contract award.

    The water park is designed around five themed zones and will feature what is billed as the world’s first double-tornado/triple-wave waterslide.

    The park will include 21 major rides and attractions, 21 food and beverage outlets, 66 cabanas, parking for 1,100 vehicles and a daily peak capacity of 4,500 guests.

    Slide procurement has already been completed directly by Seven. The selected contractor will be responsible for locally sourcing slide towers, integrating them with rockwork and secondary steel, and installing the units.

    Detailed design and issued-for-construction packages are complete.

    Marine works, piling, dewatering and site utilities are being progressed separately by the existing early works contractor.

    The hotel component covers roughly 31,700 sq m of gross floor area and will offer 321 guest rooms, four F&B outlets, spa and wellness facilities, a family pool, and meeting, incentive, conference and exhibition space.

    The new contractor’s scope includes superstructure concrete works, façade and roof works, mechanical, electrical and plumbing, interior fit-out and landscaping.

    Seven will consider only contractors with demonstrated experience delivering water parks with complex aquatics, theming and rockwork – either directly or through clearly defined subcontractor partnerships – along with a track record in high-end turnkey hotel fit-outs.

    Construction of Seven’s Dammam entertainment complex is currently under way. In October 2023, Saudi Binladin Group won contracts worth around SR5bn ($1.3bn) from Seven to build two entertainment destinations in the Dammam and Al-Khobar areas of the Kingdom’s Eastern Province.

    The Al-Khobar entertainment complex is being built on reclaimed waterfront land. The complex spans around 300,000 sq m and is also known as ‘The Waves’.

    The Dammam entertainment complex spans 360,000 sq m and is being built on reclaimed land on the Dammam waterfront.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17710096/main.jpg
    Yasir Iqbal
  • Al-Ula appoints equestrian village early works contractor

    21 July 2026

     

    Saudi Arabia’s Royal Commission for Al-Ula (RCU) has awarded a contract for early construction works at the Al-Muatadil Equestrian Village.

    The contract was awarded to Al-Khobar-based Al-Shalawi International Company.

    Canadian engineering firm AtkinsRealis is the project management consultant. UK-headquartered Baker Wilkins & Smith and local firm Al-Hoty Company are the cost consultants.

    Dubai-based SSH is the supervision consultant, and UK-based Hopkins Architects is the lead design consultant.

    RCU announced the project plans in March 2023, including the development of an equestrian hub with two arenas that can accommodate 5,000 and 1,400 spectators, respectively.

    The venue will also include grass polo, sand polo and endurance facilities, with capacities of 600, 400 and 600 seats, respectively.

    These facilities will be complemented by visitor amenities, two stable compounds with capacity for 740 horses, and accommodation and retail outlets for event participants and workers.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17710170/main.jpeg
    Yasir Iqbal
  • Contractors await decision on Riyadh airport sewage plant

    21 July 2026

     

    Seven contractors are awaiting a decision on a contract to build a sewage treatment plant at the King Salman International airport (KSIA) development in Riyadh, according to sources.

    It is understood that bids were submitted to King Salman International Airport Development Company (KSIADC) in March, following the tender’s release earlier this year.

    The plant will treat wastewater generated by the airport and surrounding developments, including passenger terminals, runways, residential districts, commercial facilities and logistics areas.

    The facility will have a treatment capacity of 92,000 cubic metres a day. The contract is estimated to be worth SR700m ($187m).

    The bidders (all local) are:

    • Al-Rawaf Trading & Contracting
    • Almajal Alarabi
    • Nesma Water & Energy
    • Safari Company
    • Saudi Services for Electro-Mechanic Works
    • Washnah Contracting
    • Water & Environment Technologies (Wetico)

    The project scope includes the construction of the treatment plant, the installation of preliminary, secondary and tertiary treatment systems, sewage collection and conveyance pipelines, pumping stations, and electrical and control systems.

    US-headquartered Jacobs is acting as the main project consultant. Commercial operations for the plant are scheduled for 2029.

    The sewage treatment plant is one of several water infrastructure packages planned for the airport. KSIADC is also evaluating bids for a separate $30m engineering, procurement and construction contract covering potable water and fire water tanks and an associated pumping station. The same seven companies have submitted bids for that package.

    Earlier in July, MEED exclusively reported that a joint venture of Beijing-headquartered China Civil Engineering Construction Corporation and Dammam-based Mofarreh AlHarbi & Partners had won a deal to undertake the enabling and substructure works for Terminal 6 at KSIA.

    The latest development followed KSIADC’s receipt of prequalification statements from contractors on 1 July for two new packages at KSIA.

    These include the construction of a permanent East-West corridor and landside access roads serving the North and South terminals.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17709281/main.jpg
    Mark Dowdall
  • Dubai Municipality awards Tasreef drainage contract

    21 July 2026

     

    Dubai Municipality has awarded local firm Detech Contracting the engineering, procurement and construction (EPC) contract for the TF-15-C1 package of its Tasreef Rainwater Drainage Network programme.

    It is understood the municipality issued the letter of award for the contract earlier this month, covering the construction of a stormwater drainage system along Al-Wasl Road and communities west of the Dubai Canal.

    The project includes the construction of a gravity-based stormwater pipeline network with diameters of up to 3.5 metres. It is estimated to cost $100m.

    It was tendered in February through the government’s Sewerage and Recycled Water Projects Department, with bids submitted in April.

    The package forms part of the wider Tasreef initiative, which is intended to improve Dubai’s flood resilience.

    The TF-15-C2 package was recently awarded to China State Construction Engineering Corporation for a stormwater drainage network project located along Umm Suqeim Road in the Al-Barsha and Al-Quoz areas of Dubai.

    The project is estimated to cost $162m and includes the construction of about 20 kilometres of new stormwater pipelines. Similar to the C1 package, it is located west of the Dubai Canal and will connect the Al-Quoz 3 and Al-Quoz 4 industrial areas with Al-Quoz 1.

    Separately, Al-Kharafi has won a drainage EPC contract (Ds207) to upgrade an existing pumping station for the municipality, a source said. The package focuses mainly on mechanical works and is valued at about $39m.

    In May, MEED reported that local firm Nael Construction & Contracting had signed a contract with Dubai Municipality to build a sewage and stormwater drainage system in Dubailand.

    The project (DS-204-C1) involves the construction of a drainage system with sewage gravity pipelines of up to 2,200mm in diameter.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17707980/main.jpg
    Mark Dowdall