GCC battery storage pipeline hits over 55GWh

28 February 2025

Analysis
Jennifer Aguinaldo
Energy & technology editor

 

The battery energy storage system (bess) plant project pipeline in the GCC region – mainly in Saudi Arabia and the UAE – has reached 55.4 gigawatt-hours (GWh) of estimated rated capacity.

Data from MEED and regional projects tracker MEED Projects indicates that schemes with a total capacity of about 21.7GWh are under construction, primarily in Saudi Arabia, while bess plants in the pre-execution phase have an estimated cumulative rated capacity of 33.8GWh.

This substantial pipeline has been built over the past two to three years, when a total of 3.9GWh of capacity was built in Saudi Arabia through the 1.3GWh Red Sea multi-utility project and the recently completed 2.6GWh battery energy storage plant by Saudi Arabia's National Grid.

"The main energy storage driver across the GCC region is the rapid deployment of low-cost solar power to meet growing demand," notes Marek Kubik, a Saudi Arabia-based industry expert. 

"As photovoltaic (PV) produces power only in the day and is a non-synchronous form of power, this brings with it certain balancing, ramping and stability challenges. 

"Bess is needed for storing and shifting solar power from day to night, to reduce congestion and improve utilisation on the transmission system, as well as providing stability services to support stable grid operations," says Kubik.

Capacity ramp-up

With an estimated 775MW/3.9GWh of deployed capacity at the end of 2024, the GCC region accounts for a small proportion of the global deployment of about 160GW or 363GWh, according to the Volta Foundation.

The global not-for-profit group said global bess installations last year accounted for more than 45% of the total cumulative global capacity.

The region is poised to catch up with the rest of the world, however. Saudi Arabia's Bisha bess plant is one of 17 projects globally with a capacity of over 1GWh that entered operations in 2024.

A total of 21.7GWh of capacity is under construction in Saudi Arabia and is expected to be completed by the end of the year, with more under way.

Such growth will likely overtake the 55% year-on-year growth observed by the Volta Foundation.

The GCC region’s first major bess independent power producer (IPP) scheme was integrated into Red Sea Global’s multi-utility package in Saudi Arabia.

Developed by Saudi utility developer Acwa Power and built by China’s Huawei Digital, the 1,300 megawatt-hour (MWh) facility caters to the 28,000 square-kilometre “regenerative” tourism project on the west coast of the kingdom, which is being powered 100% by clean energy.

A bess facility with a capacity of 760MWh is also included in a similar multi-utility package for Red Sea Global’s sister development, Amaala.

The 2.6GWh Bisha represents an important milestone, ushering the kingdom onto the list of the world's top locations for lithium iron phosphate (LFP)-based bess.

So far, every utility or grid operator in the GCC, Morocco and Jordan plans to procure or has started to procure bess capacity independently, to balance their grid as electricity demand and renewable energy capacity increase, or as part of a solar power plant scheme.

In the absence of viable hydropower capacity, which is the main energy storage capacity in non-water-scarce regions, or thermal energy storage systems like molten salt, bess is emerging as the best alternative to enhance the flexibility of existing energy or electricity systems as sources increasingly diversify.

Abu Dhabi state utility Emirates Water & Electricity Company (Ewec) received 93 expressions of interest and prequalified more than two dozen companies to bid individually or as members of consortiums for its first pair of bess plants, which will have a capacity of up to 800MWh.

In January, Ewec and Abu Dhabi Future Energy Company (Masdar) announced a project that aims to convert solar power into base load capacity by coupling a 5GW solar PV plant with a 19GWh battery energy storage facility in Abu Dhabi.

Falling lithium prices and oversupply 

The need for grid flexibility and a steep fall in the price of lithium – the main raw material for the dominant battery technology – has helped utilities to move forward with their plans to procure bess, which was considered cost-prohibitive until a year ago.

According to a BloombergNEF (BNEF) report in December, lithium-ion battery pack prices dropped 20% from 2023, to a record-low of $115 a kilowatt-hour.

Factors driving the decline include cell manufacturing overcapacity, economies of scale, low metal and component prices, the adoption of lower-cost LFP batteries and a slowdown in electric vehicle (EV) sales growth.

In the past two years, battery manufacturers have expanded production capacity in anticipation of surging demand for batteries in the EV and stationary storage sectors.

According to BNEF, overcapacity is rife, with 3.1 terawatt-hours of fully commissioned battery-cell manufacturing capacity globally, which is more than 2.5 times the annual demand for lithium-ion batteries in 2024.

It added that while demand in all sectors saw year-on-year growth, the EV market – the biggest demand driver for batteries – grew more slowly than in recent years.

In contrast, stationary storage markets have taken off, with strong competition in cell and system providers, especially in China.

Completed and under-construction bess plants in the GCC are all supplied by Chinese battery cell and system providers. BYD and Sungow account for 59% and 36% of completed and under-construction battery energy storage plants in Saudi Arabia, respectively, while Huawei accounts for the rest.

Contemporary Amperex Technology Company (CATL) will be supplying the battery cell and systems for Abu Dhabi's round-the-clock 1GW solar project.

Prices are expected to fall further, which will likely accelerate GCC deployments.

Some experts predict the prices could drop to as low as $50/kWh-$25/kWh and, at best, to as low as $10/kWh by the end of the decade, subject to extrapolating current battery learning rates of about 25% for every doubling of capacity. 

Longer-duration battery cells

Despite their expected widespread deployment, there are concerns that batteries providing up to six hours of storage may not be sufficient to address the peak electricity demand in most GCC states.

Demand in the GCC states peaks between 6pm and 6am, when air-conditioning systems, street lighting and other home appliances are turned on, and where there is little wind capacity to supply renewable power.  

Nevertheless, a staged approach to bess deployment is necessary to get to a fully net-renewable electricity system, says Kubik.

"Around the world, this is approached in a staged manner and bess of increasing duration is added over time, as the depth of renewable penetration increases," he says.

"The GCC has, to an extent, leapfrogged other markets by starting with four-hour to six-hour bess, but over time this need will grow to about eight- to 10-hours, which is enough to move to more or less a ‘baseload’ around-the-clock solar profile. As LFP costs continue to fall, longer-duration systems are rapidly becoming more economic." 


READ MEED’s YEARBOOK 2025

MEED’s 16th highly prized flagship Yearbook publication is available to read, offering subscribers analysis on the outlook for the Mena region’s major markets.

Published on 31 December 2024 and distributed to senior decision-makers in the region and around the world, the MEED Yearbook 2025 includes:

> GIGAPROJECTS INDEX: Gigaproject spending finds a level
https://image.digitalinsightresearch.in/uploads/NewsArticle/13438887/main5753.jpg
Jennifer Aguinaldo
Related Articles
  • Adnoc plans new offshore-to-onshore oil transport pipeline

    20 August 2026

     

    Abu Dhabi National Oil Company is moving ahead with an ambitious plan to build an oil pipeline network that will transport oil from its main offshore oil processing islands in the Gulf to its onshore crude export terminal in Jebel Dhanna, Abu Dhabi.

    The planned pipeline network will source crude from Zirku Island and Das Island, where Adnoc gathers and treats oil produced at Abu Dhabi’s offshore fields, among other processing hubs, and transport those volumes across 300 kilometres inland to the Jebel Dhanna terminal.

    According to sources, the proposed pipelines will eventually connect to the West-East crude pipeline network currently being built from Abu Dhabi’s Jebel Dhanna to the emirate of Fujairah, and is expected to be commissioned in 2027.

    The Abu Dhabi energy giant has awarded a contract for concept studies and front-end engineering and design (feed) to Abu Dhabi-based NT Energies, a joint venture of Abu Dhabi-based contractor NMDC Energy and France’s Technip Energies, sources told MEED.

    NT Energies is expected to carry out the concept studies and feed on a “fast-track basis”, with the work anticipated to take seven months, sources said.

    A kick-off meeting between the client and the appointed consultant took place on 6 July, sources added.

    Additionally, Adnoc has appointed Australia-headquartered Worley to provide project management consultancy (PMC) services, sources further said.

    West-East oil pipeline

    In May, Adnoc said it was accelerating work on the West-East crude transport pipeline project from Jebel Dhanna to Fujairah, upon directions from its board.

    The West-East pipeline project involves constructing a cross-country pipeline to transport crude from Adnoc’s export terminal at Jebel Dhanna to the Fujairah terminal, covering a distance of about 520km.

    The pipeline will double Adnoc’s crude export capacity through Fujairah on the Indian Ocean coast and enable shipments to bypass the geopolitically volatile Strait of Hormuz.

    Crude will be sourced from Adnoc’s offshore processing centres at Das, Zakum and Umm Lulu islands before being stored at new storage facilities to be built at the Jebel Dhanna terminal.

    The pipeline will be segmented into three sections:

    • Jebel Dhanna to Habshan main pumping station (MPS) – 115km
    • Habshan MPS to Sweihan depot – 254km
    • Sweihan depot to Fujairah terminal – 153km

    Adnoc awarded Egyptian contractor Engineering for Petroleum & Process Industries (Enppi) an engineering, procurement and construction management (EPCm) contract for the project in February 2024.

    Adnoc’s total spend on EPCm works could be as high as $3bn, MEED previously reported.

    Sources have told MEED that Adnoc has, in turn, appointed state-owned China Petroleum Pipeline (CPP) and locally based Bin Asheer to carry out construction works on the three segments of the West-East pipeline network.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18887774/main0639.jpg
    Indrajit Sen
  • Contractors confirm Al-Maktoum airport people-mover award

    20 August 2026

    Register for MEED’s 14-day trial access 

    A team of Japan’s Mitsubishi Corporation and Indian contractor Larsen & Toubro (L&T) has confirmed that it has won a design-and-build contract for the automated people-mover (APM) system for phase one of Al-Maktoum International airport in Dubai.

    In a statement released earlier today, L&T classified the contract as large, a term the company uses to denote an order value of $261m-$523m.

    MEED exclusively reported in July that Dubai Aviation Engineering Projects (DAEP) had selected a contractor to deliver the APM system as part of the first phase of the $35bn expansion of the airport.

    The APM system will serve as a critical facility for operations at Al-Maktoum International. The system will run under the apron of the entire airfield and the airport’s terminals. It will consist of several tracks, taking passengers from the terminals to the concourses.

    Four underground stations will be built as part of the first phase. The overall plan includes 14 stations at the airport.

    The firms submitted the bids for the project in July last year, as MEED exclusively reported.

    The contract is the latest in a series of awards signed by DAEP recently. It has awarded contracts valued at about AED13bn ($3.5bn), with construction works currently under way on several airport packages.

    These include enabling works, the second runway and the initial structural foundations for passenger terminals and gates.

    Upcoming awards

    In June, DAEP said that it will award contracts worth over AED55bn ($15bn) by the end of this year for construction works at Al-Maktoum International airport.

    The projects slated for contract awards include the substructure works for the western passenger terminal, the fourth aircraft concourse building and the baggage handling system, in addition to the superstructure works for the western passenger terminal and the first, second and third aircraft concourses.

    The packages also encompass long-span structural frameworks for buildings covering about 1.5 million square metres (sq m), infrastructure works for the southern airfield area and power generation and district cooling plants supporting the construction programme.

    The award of the facade and roofing packages is also planned for this year.

    Construction progress

    In May last year, MEED exclusively reported that DAEP had awarded a AED1bn ($272m) deal to UAE firm Binladin Contracting Group to construct the second runway at the airport.

    The enabling works on the terminal were awarded to Abu Dhabi-based Tristar E&C.

    Construction on the project’s first phase is expected to be completed by 2032.

    Construction of substructure works began in November last year, when DAEP formally selected a contractor to deliver the package.

    The government approved the updated designs and timelines for its largest construction project in April 2024.

    In a statement, the authorities said the plan is for all operations from Dubai International airport to be transferred to Al-Maktoum International within 10 years.

    According to an official description on DAEP’s website, the expanded airport’s West Terminal will be a seven-level, 800,000 sq m facility with an annual capacity of 45 million passengers.

    It will be the second of three terminals at the airport.

    In September 2024, MEED exclusively reported that a team comprising Austria’s Coop Himmelb(l)au and Lebanon’s Dar Al-Handasah had been confirmed as the lead masterplanning and design consultant on the expansion of Al-Maktoum.

    The airport’s construction is planned to be undertaken in three phases. It will cover an area of 70 square kilometres south of Dubai and will have five parallel runways and 430 aircraft gates.

    It will be five times the size of the existing Dubai International airport and will have the world’s largest passenger-handling capacity of 260 million passengers a year. For cargo, it will have the capacity to handle 12 million tonnes a year.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18884056/main.png
    Yasir Iqbal
  • Saudi Arabia awards estimated $1bn phosphate rail deal

    20 August 2026

     

    Register for MEED’s 14-day trial access 

    Saudi Arabian Railways (SAR) has awarded an estimated SR4bn-plus ($1.1bn) contract to add another track to the first section of the existing phosphate transport railway network in the kingdom’s Eastern Province.

    The contract was awarded to local firm Alomaier Trading & Contracting Company.

    The scope includes track doubling, alignment modifications, utility bridges, culvert widening and hydrological structures, as well as the conversion of the AZ1 siding into a mainline track.

    The scope also covers support for signalling and telecommunications systems.

    The existing railway line runs from the Waad Al-Shamal mines to Ras Al-Khair. The new project will cover about 100 kilometres (km), connecting the AZ1/Nariyah Yard to Ras Al-Khair.

    Switzerland-based engineering firm ARX is the project consultant.

    The project is the first of four packages for the phosphate railway line that SAR is expected to award imminently.

    In 2023, MEED reported that SAR was planning two projects to increase its freight capacity, including an estimated SR4.2bn ($1.1bn) project to install a second track on the North Train freight line and construct three new freight yards.

    Formerly known as the North-South Railway, the North Train is a 1,550km-long freight line running from the phosphate and bauxite mines in the far north of the kingdom to the Al-Baithah junction. There, it diverges into a line southward to Riyadh and a second line running east to downstream fertiliser production and alumina refining facilities at Ras Al-Khair on the Gulf coast.

    Adding a second track and the freight yards will significantly increase cargo-carrying capacity on the network and facilitate growth in industrial production. Project implementation is expected to take four years.

    State-owned SAR is also considering increasing the localisation of railway-focused materials and equipment, including the construction of a cement sleeper manufacturing facility.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18876428/main.jpg
    Yasir Iqbal
  • Libya and Tunisia reschedule joint oil and gas licensing round

    19 August 2026

    The Libyan-Tunisian Joint Oil Exploration, Exploitation & Petroleum Services Company (Joint Oil) has rescheduled its planned licensing round for offshore exploration and development projects in a zone spanning the waters of both countries.

    The bidding process is now due to open on 7 September 2026, with bid submissions due by 8 January 2027.

    Previously, in May, Joint Oil said it planned to open the bid round on 1 August 2026.

    The upcoming round will offer two oil and gas packages. The first is an exploration package across the 3,000-square-kilometre Joint Oil Block, in water depths of 80-120 metres.

    Significant data is available on the geology of this area, including 6,500km of 2D and 1,900 square kilometres of 3D seismic data. Data also exists from a run of legacy wells dating to 1976.

    The second package covers development of the Zarat discovery specifically. This is a gas-condensate reservoir straddling the boundary between Tunisia’s national acreage and the jointly-held Joint Oil Block.

    Joint Oil is equally owned by Tunisia’s national oil company, ETAP, and OLA Energy Holdings, a subsidiary of the Libya Africa Investment Portfolio (LAIP).

    LAIP is a subsidiary of Libya’s sovereign wealth institution, the Libya Investment Authority.

    Joint Oil was established under a bilateral agreement between Libya and Tunisia in 1988 to explore and develop hydrocarbons in offshore areas shared by the two countries.

    The key dates from the new schedule for the licensing round are:

    • 7 September 2026: Bid round opens; qualified offshore operators can apply for access to the Virtual Data Room
    • 9 September 2026: Joint Oil presents the opportunity at the MMEA Scout Group meeting in London
    • 29-30 September 2026: Joint Oil presents at the World Energy Summit in London
    • 31 December 2026: Bid round closes
    • 8 January 2027: Bid submissions due
    • 26 February 2027: Winning bidders notified
    • 30 April 2027: Formal awards expected

    Texas-based Moyes & Co is acting as a strategic adviser on the licensing round.

    Houston-headquartered Marathon discovered the Zarat field in 1992. It is estimated to hold around 0.4 trillion cubic feet of recoverable gas and 50 million barrels of liquids.

    A previous development project concept centred on a mobile production unit, worth around $1bn, tied back to the nearby Miskar platform.

    Despite this, the field has remained undeveloped for over three decades.

    One of the key challenges to developing the reserve is its high carbon dioxide content.

    Joint Oil has run bid rounds for the acreage before without success, including as recently as late 2023.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18861047/main0914.jpg
    Wil Crisp
  • UAE cuts trade and financial links with Iran

    19 August 2026

    Register for MEED’s 14-day trial access 

    The UAE has halted all trade, commercial exchanges and financial transactions with Iran until further notice, the Ministry of Foreign Affairs said on 19 August.

    The suspension has been imposed in light of escalations that undermine regional and international peace and security, the ministry said. It did not specify a timeframe for any resumption.

    The ministry rejected allegations regarding the status of the economic relationship between the UAE and Iran, and restated the UAE's commitment to dialogue, cooperation and regional integration as means of advancing peace, stability and prosperity in the region.

    It said the UAE remains committed to safeguarding the integrity of the financial system, in line with international law and global standards.

    The suspension covers the full range of commercial and financial links between the two countries. The UAE has historically been one of Iran's most significant trading partners, with much of the relationship built on re-export trade routed through Dubai to Iranian ports across the Gulf.

    The ministry statement did not detail the mechanism for enforcing the halt, the sectors affected, or arrangements for existing contracts and in-transit cargo.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18857953/main0856.jpg
    Colin Foreman