GCC battery storage pipeline hits over 55GWh

28 February 2025

Analysis
Jennifer Aguinaldo
Energy & technology editor

 

The battery energy storage system (bess) plant project pipeline in the GCC region – mainly in Saudi Arabia and the UAE – has reached 55.4 gigawatt-hours (GWh) of estimated rated capacity.

Data from MEED and regional projects tracker MEED Projects indicates that schemes with a total capacity of about 21.7GWh are under construction, primarily in Saudi Arabia, while bess plants in the pre-execution phase have an estimated cumulative rated capacity of 33.8GWh.

This substantial pipeline has been built over the past two to three years, when a total of 3.9GWh of capacity was built in Saudi Arabia through the 1.3GWh Red Sea multi-utility project and the recently completed 2.6GWh battery energy storage plant by Saudi Arabia's National Grid.

"The main energy storage driver across the GCC region is the rapid deployment of low-cost solar power to meet growing demand," notes Marek Kubik, a Saudi Arabia-based industry expert. 

"As photovoltaic (PV) produces power only in the day and is a non-synchronous form of power, this brings with it certain balancing, ramping and stability challenges. 

"Bess is needed for storing and shifting solar power from day to night, to reduce congestion and improve utilisation on the transmission system, as well as providing stability services to support stable grid operations," says Kubik.

Capacity ramp-up

With an estimated 775MW/3.9GWh of deployed capacity at the end of 2024, the GCC region accounts for a small proportion of the global deployment of about 160GW or 363GWh, according to the Volta Foundation.

The global not-for-profit group said global bess installations last year accounted for more than 45% of the total cumulative global capacity.

The region is poised to catch up with the rest of the world, however. Saudi Arabia's Bisha bess plant is one of 17 projects globally with a capacity of over 1GWh that entered operations in 2024.

A total of 21.7GWh of capacity is under construction in Saudi Arabia and is expected to be completed by the end of the year, with more under way.

Such growth will likely overtake the 55% year-on-year growth observed by the Volta Foundation.

The GCC region’s first major bess independent power producer (IPP) scheme was integrated into Red Sea Global’s multi-utility package in Saudi Arabia.

Developed by Saudi utility developer Acwa Power and built by China’s Huawei Digital, the 1,300 megawatt-hour (MWh) facility caters to the 28,000 square-kilometre “regenerative” tourism project on the west coast of the kingdom, which is being powered 100% by clean energy.

A bess facility with a capacity of 760MWh is also included in a similar multi-utility package for Red Sea Global’s sister development, Amaala.

The 2.6GWh Bisha represents an important milestone, ushering the kingdom onto the list of the world's top locations for lithium iron phosphate (LFP)-based bess.

So far, every utility or grid operator in the GCC, Morocco and Jordan plans to procure or has started to procure bess capacity independently, to balance their grid as electricity demand and renewable energy capacity increase, or as part of a solar power plant scheme.

In the absence of viable hydropower capacity, which is the main energy storage capacity in non-water-scarce regions, or thermal energy storage systems like molten salt, bess is emerging as the best alternative to enhance the flexibility of existing energy or electricity systems as sources increasingly diversify.

Abu Dhabi state utility Emirates Water & Electricity Company (Ewec) received 93 expressions of interest and prequalified more than two dozen companies to bid individually or as members of consortiums for its first pair of bess plants, which will have a capacity of up to 800MWh.

In January, Ewec and Abu Dhabi Future Energy Company (Masdar) announced a project that aims to convert solar power into base load capacity by coupling a 5GW solar PV plant with a 19GWh battery energy storage facility in Abu Dhabi.

Falling lithium prices and oversupply 

The need for grid flexibility and a steep fall in the price of lithium – the main raw material for the dominant battery technology – has helped utilities to move forward with their plans to procure bess, which was considered cost-prohibitive until a year ago.

According to a BloombergNEF (BNEF) report in December, lithium-ion battery pack prices dropped 20% from 2023, to a record-low of $115 a kilowatt-hour.

Factors driving the decline include cell manufacturing overcapacity, economies of scale, low metal and component prices, the adoption of lower-cost LFP batteries and a slowdown in electric vehicle (EV) sales growth.

In the past two years, battery manufacturers have expanded production capacity in anticipation of surging demand for batteries in the EV and stationary storage sectors.

According to BNEF, overcapacity is rife, with 3.1 terawatt-hours of fully commissioned battery-cell manufacturing capacity globally, which is more than 2.5 times the annual demand for lithium-ion batteries in 2024.

It added that while demand in all sectors saw year-on-year growth, the EV market – the biggest demand driver for batteries – grew more slowly than in recent years.

In contrast, stationary storage markets have taken off, with strong competition in cell and system providers, especially in China.

Completed and under-construction bess plants in the GCC are all supplied by Chinese battery cell and system providers. BYD and Sungow account for 59% and 36% of completed and under-construction battery energy storage plants in Saudi Arabia, respectively, while Huawei accounts for the rest.

Contemporary Amperex Technology Company (CATL) will be supplying the battery cell and systems for Abu Dhabi's round-the-clock 1GW solar project.

Prices are expected to fall further, which will likely accelerate GCC deployments.

Some experts predict the prices could drop to as low as $50/kWh-$25/kWh and, at best, to as low as $10/kWh by the end of the decade, subject to extrapolating current battery learning rates of about 25% for every doubling of capacity. 

Longer-duration battery cells

Despite their expected widespread deployment, there are concerns that batteries providing up to six hours of storage may not be sufficient to address the peak electricity demand in most GCC states.

Demand in the GCC states peaks between 6pm and 6am, when air-conditioning systems, street lighting and other home appliances are turned on, and where there is little wind capacity to supply renewable power.  

Nevertheless, a staged approach to bess deployment is necessary to get to a fully net-renewable electricity system, says Kubik.

"Around the world, this is approached in a staged manner and bess of increasing duration is added over time, as the depth of renewable penetration increases," he says.

"The GCC has, to an extent, leapfrogged other markets by starting with four-hour to six-hour bess, but over time this need will grow to about eight- to 10-hours, which is enough to move to more or less a ‘baseload’ around-the-clock solar profile. As LFP costs continue to fall, longer-duration systems are rapidly becoming more economic." 


READ MEED’s YEARBOOK 2025

MEED’s 16th highly prized flagship Yearbook publication is available to read, offering subscribers analysis on the outlook for the Mena region’s major markets.

Published on 31 December 2024 and distributed to senior decision-makers in the region and around the world, the MEED Yearbook 2025 includes:

> GIGAPROJECTS INDEX: Gigaproject spending finds a level
https://image.digitalinsightresearch.in/uploads/NewsArticle/13438887/main5753.jpg
Jennifer Aguinaldo
Related Articles
  • Kuwait awards $381m oil project

    23 September 2026

    Register for MEED’s 14-day trial access 

    State-owned upstream operator Kuwait Oil Company (KOC) has awarded an oil project contract worth KD117m ($381m) to India’s Megha Engineering & Infrastructure (Meil).

    The Supreme Purchasing Committee for Kuwait Petroleum Corporation (KPC) approved the contract last month, paving the way for the official award.

    The project focuses on a water separation unit at the Al-Rawdatain facility in Kuwait.

    The water separation facility will be developed at Gathering Centre 25 (GC-25), along with a pumping facility at GC-30.

    The project will deliver a wide-ranging upgrade of processing and utility infrastructure, including new low-pressure separation and gas-handling equipment such as a three-phase wet separator package, a gas knock-out drum and associated low-pressure gas pipelines, as well as a high-integrity pressure protection system and a high-pressure flare.

    Meil will develop the new three-phase low-pressure wet separation facility at GC-25.

    The main process equipment will include two wet separator packages, each with a capacity of 150,000 barrels of liquid a day, and a low-pressure gas knock-out drum with a capacity of 53 million standard cubic feet a day, together with associated gas-handling facilities.

    The facility will also incorporate an effluent water treatment and transfer system, including an effluent water balance tank equipped with microbubble flotation and induced gas flotation systems, as well as transfer pumps.

    Additional GC-25 facilities will include fuel gas treatment, chemical injection, oil recovery and flare connections, along with firewater and deluge systems.

    The scope also covers control and safety systems, substations, and associated civil, structural, mechanical, electrical and instrumentation works.

    At GC-30, the project will focus on treated-water filtration and high-pressure injection infrastructure.

    The scope includes nutshell filters and associated feed pumps with a combined capacity of approximately 500,000 barrels of water a day.

    Booster and injection pumps will transfer treated effluent water to designated injection wells.

    Additional facilities at GC-30 will include fuel gas treatment, sludge collection and disposal systems, oil recovery systems, control and safety systems, substations, laboratory and workshop facilities, and associated civil, structural, piping, mechanical, electrical and instrumentation works.

    The project also includes transfer pipelines connecting GC-25, GC-15 and GC-30.

    Meil will carry out modifications to existing tanks at GC-30, as well as process and utility tie-ins, electrical and instrumentation modifications and other infrastructure required to integrate the new facilities with KOC’s existing assets.

    Meil’s responsibilities cover the project lifecycle from design and engineering through procurement, construction, testing, pre-commissioning, commissioning, start-up and performance testing.

    The contract also includes operation, maintenance, repair and insurance responsibilities for the designated facilities during the applicable operations and maintenance period.

    Seven companies submitted bids for the project last November.

    The full list of bids was:

    • Meil (India) – KD117m ($381m)
    • Mechanical Engineering & Contracting Company (Kuwait) – KD130m
    • Spetco (Kuwait) – KD158m
    • Al-Kharafi (Kuwait) – KD164m
    • China Oil HBP Science & Technology (China) – KD169m
    • Alghanim International (Kuwait) – KD169m
    • Jereh Oil & Gas Engineering (China) – KD191m

    In October last year, KOC awarded Meil a separate contract for a project to develop a gas sweetening and recovery facility in west Kuwait.

    Meil submitted the lowest bid for that tender, at KD69.2m ($225.5m), in February 2025.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19911322/main.jpg
    Wil Crisp
  • Kuwait refinery project on track for year-end completion

    23 September 2026

     

    A $65m project to replace a substation at the Mina Al-Ahmadi (MAA) refinery is on schedule to be mechanically complete before the end of the year, according to industry sources.

    The project is being executed by India’s Larsen & Toubro (L&T), which was awarded the contract in October 2024.

    One source said: “This project is approaching completion and is currently on schedule to be completed before the end of the year, although it could still see delays related to the ongoing regional conflict.”

    The client is state-owned downstream operator Kuwait National Petroleum Company (KNPC).

    Kuwait’s Ministry of Electricity, Water & Renewable Energy (MEW) is also involved in the project and will provide final approvals and sign-off.

    The scope of the project includes:

    • Construction of a substation
    • Installation of transformers
    • Installation of medium-voltage switchgear
    • Installation of low-voltage auxiliary systems
    • Installation of network protection systems
    • Installation of disconnecting switches
    • Installation of surge arrestors
    • Installation of feeder breakers and cubicles
    • Installation of low-voltage A/C and D/C equipment
    • Installation of battery banks and battery chargers
    • Installation of related relay and control panel boards
    • Installation of fire alarm and fire protection equipment
    • Installation of a SCADA system
    • Installation of cables
    • Civil works
    • Associated facilities

    The current project to replace a substation at the MAA refinery closely resembles another project tendered by KNPC more than a decade ago, which L&T also won.

    On 18 May 2015, KNPC signed a contract with L&T to build a new 240MW substation at the MAA refinery, valued at KD21.866m.

    The new substation, known as M20, was designed to replace an existing substation that was considered old and obsolete.

    Mohammed Al-Mutairi, who was KNPC’s chief executive at the time, said the substation building would be explosion-proof and use state-of-the-art control systems.

    He said the station’s capacity would increase from 180MW to 240MW, supplying most of the refinery’s electricity needs.

    Given the similarities between the two projects, L&T has been able to reuse some designs, creating efficiencies, according to industry sources.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19911319/main.jpg
    Wil Crisp
  • Contractor wins $208m Almoosa hospital MEP contract

    23 September 2026

    Register for MEED’s 14-day trial access 

    Riyadh-based construction firm BEC Arabia has won a SR781m ($208m) contract for the mechanical, electrical and plumbing (MEP) works at Almoosa Hospital in Al-Khobar.

    Saudi Arabia’s Almoosa Health Company awarded the contract.

    The hospital complex consists of two towers: a 24-storey in-patient tower with 380 beds, and an 11-storey tower with 224 clinics and 113 additional treatment spaces.

    It will be built on a 45,000-square-metre site.

    A podium spanning the ninth and 10th floors will connect the two towers.

    The hospital will also include parking for 1,700 cars.

    BEC Arabia won the SR656m ($175m) main construction contract for the hospital in November last year.

    In August 2025, MEED reported that Almoosa Health Company had announced it had secured a sharia-compliant credit facility worth SR650m ($173m) from Banque Saudi Fransi.

    In a statement published on the Saudi stock exchange (Tadawul), the company said the seven-year facility would be used to support its expansion and growth strategy.

    Lebanon’s Dar, US-based Perkins&Will and French design firm Pierre-Yves Rochon designed the project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19910889/main.jpg
    Yasir Iqbal
  • UAE to develop integrated waste-to-resource pilot

    23 September 2026

    Emirates Biotech and United Arab Emirates University (UAEU) have launched a pilot project in Al-Ain that could provide a model for larger waste-to-resource facilities.

    The project involves developing the UAE’s first integrated organic-waste valorisation pilot plant, which will test whether food waste and compostable packaging can be processed together to recover resources and reduce waste sent to landfill.

    Located near the UAEU campus, the 40kg-a-day facility will process organic waste to produce renewable biogas and nutrient-rich compost. The project is intended to generate technical and operating data that could support the development of larger-scale facilities.

    Emirates Biotech and UAEU will design, build and operate the pilot plant as part of a two-year research project running from August 2026 to August 2028. Installation and commissioning are expected to be completed by August 2027.

    The plant will combine anaerobic digestion and composting. Anaerobic digestion will convert the organic waste into renewable biogas, while the resulting digestate will be composted to produce nutrient-rich compost.

    A laboratory-scale assessment will also examine the potential to convert the biogas into renewable hydrogen.

    Food waste accounts for nearly 40% of daily municipal solid waste in the UAE, according to Emirates Biotech, and much of it is currently disposed of in landfills.

    The pilot will therefore assess the technical and operational feasibility of recovering value from two waste streams through a single integrated process.

    If successfully scaled, Emirates Biotech says an integrated organic-waste valorisation plant could reduce CO₂ emissions by 89% compared with landfilling.

    The project is expected to provide a scalable and modular model for converting food waste and compostable packaging into renewable biogas and compost, with the findings intended to inform the development of larger waste-to-resource facilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19908972/main.jpg
    Mark Dowdall
  • Contractors prepare Oxagon Highway 55 bids

    23 September 2026

     

    Contractors are preparing to submit bids on 28 September for a design-and-build contract for permanent upgrade works on Highway 55 in the kingdom’s Oxagon region.

    The first phase of the project includes constructing 14 kilometres of road, with two lanes in each direction. It also includes one bridge and three interchanges.

    The project duration is 22 months.

    Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.

    MEED reported exclusively in August 2025 that contractors had submitted responses to an expression of interest notice that Neom had issued earlier that month.

    The project is expected to support cargo movement from Duba Port to other parts of the kingdom and the wider region.

    Last year, Neom tested a pilot initiative by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.

    In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”

    The Port of Neom is located on the Red Sea near the Arar border, a key entry point into Iraq.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19907876/main.jpg
    Yasir Iqbal