National oil companies (NOCs) in the Middle East and North Africa (Mena) region are accelerating investment in gas processing and associated downstream infrastructure as demand rises and governments prioritise lower-carbon energy growth.
Rising regional gas consumption is being driven by rapid population growth, greater household electrification, expanding industrial bases and demand from gas-intensive downstream segments such as petrochemicals, fertilisers and metals.
Power generation and water desalination are also key sources of demand, while new industrial zones are adding further baseload requirements.
The push is not only about producing more gas, but also about treating it. As fields mature, a larger share of supply is sour, tight or associated gas that requires more complex processing, sulphur recovery and liquids handling.
At the same time, NOCs are targeting higher-value outputs such as ethane, liquefied petroleum gas and condensates, to feed chemicals and export markets.
This makes fractionation and the recovery of natural gas liquids (NGL) central to project economics. Emissions constraints further elevate the importance of efficient plants, flare reduction schemes and integrated gas-gathering networks.
Investment accelerates
The multibillion-dollar projects planned and under way in the region illustrate the scale of investment flowing into gas processing infrastructure.
Saudi Aramco is advancing gas and liquids infrastructure linked to its $100bn Jafurah unconventional gas development, in addition to expansions to strengthen the kingdom’s Master Gas System transmission network.
In the UAE, Abu Dhabi National Oil Company (Adnoc) continues to expand sour gas processing and downstream-
linked gas treatment capacity to support domestic power needs and industrial growth. Meanwhile, debottlenecking and compression and pipeline projects improve system resilience.
QatarEnergy, already a global leader in liquefied natural gas (LNG), is expanding upstream gas handling, condensate and NGL infrastructure as part of its North Field expansion programme. The programme will also increase feedstock supplies for local industry.
In Oman, majority state-owned Petroleum Development Oman (PDO) and its partners are similarly focused on gas processing, compression and network upgrades to sustain supplies to power generation, industrial users and LNG.

Saudi Aramco is expanding gas-processing and NGL infrastructure as domestic demand grows
Leading spender
The Mena region has seen significant spending on gas processing projects so far in 2026, with year-to-date capital expenditure (capex) exceeding levels recorded in any year since at least 2015.
Adnoc Gas, the natural gas processing business of Adnoc Group, has been the biggest spender this year, following final investment decisions (FIDs) on the second and third phases of its Rich Gas Development (RGD) programme, worth a total of $8.2bn. The FIDs are part of the company’s previously committed $28bn capex budget for 2026-30.
The second phase of the RGD programme relates to the construction of a new gas processing train at the Habshan gas processing complex, while the third phase covers an NGL fractionation train at the Ruwais gas processing facility.
In its Q2 2026 financial results, Adnoc Gas said China-based Wison Engineering had secured the $3.9bn EPC contract for phase two of the RGD, while Italian contractor Tecnimont was selected for the $4.3bn phase three contract.
Wison Engineering said the EPC contract for RGD phase two is the largest in its history. The Hong Kong-listed company said the $3.9bn EPC contract, together with an associated 220kV switch station, brings the total contract value to approximately $4.04bn. The scope includes gas pipelines, separation and condensate stabilisation units, acid gas removal units and core deep NGL recovery units, as well as the switch station.
Tecnimont’s parent company, Maire, said its scope of work on the RGD phase three project includes EPC activities for the fifth NGL fractionation unit, which will separate the various hydrocarbon components, in addition to treatment and sweetening systems to remove impurities and ensure product quality.
The contract scope also includes a regeneration gas treatment unit, a propane refrigeration system, ancillary systems and storage facilities. Once completed in 2030, the plant will have an output capacity of 23,000 tonnes a day, or about
8 million tonnes a year, Milan-headquartered Maire said.
Adnoc Gas also reiterated its $5bn capex for the first phase of the RGD scheme, which is under construction. The company awarded $5bn in engineering, procurement and construction management contracts in three tranches for phase one of the RGD in June 2025, marking its largest-ever capital investment in a single project.
Across all three phases, Adnoc Gas has made a total investment of $13.2bn in the RGD programme.
Capacity expansion
Saudi Aramco spent $7.7bn on EPC contract awards on the Fadhili gas processing plant expansion in 2024. The project is set to increase the Fadhili gas plant’s processing capacity from 2.5 billion cubic feet a day (cf/d) to up to 4 billion cf/d through the addition of three processing trains, each with a capacity of 500 million cf/d.
Following its significant capex on the Fadhili expansion, the Saudi energy giant is moving ahead with contract awards this year for various EPC packages under a wider project to boost gas compression capacity at the Shedgum and Uthmaniyah processing plants in the Eastern Province.
The two plants currently receive about 870 million cf/d and 1.2 billion cf/d of Khuff raw gas, respectively. Through the multibillion-dollar project, Aramco aims to increase their compression and processing capacity and build new pipelines to improve gas transportation.
Aramco has divided the scope of work on the Shedgum and Uthmaniyah gas compression project into nine EPC packages. It awarded the Uthmaniyah gas compression plant package to locally based Saipem Nasser Saeed Al-Hajri Contracting Company (SNSH), a joint venture of Italian contractor Saipem and local contractor Nasser Saeed Al-Hajri & Partners Company for Contracting.
The SNSH contract is estimated at $1.24bn, with EPC works on the package scheduled to start in August. Separately, Milan-headquartered Saipem said its share of the contract is worth €900m ($1.04bn), with the EPC works scheduled to run for 42 months.
Earlier this year, Aramco also awarded the package related to early works and site preparation to local firm Al-Shalawi International Company Trading & Contracting.
The Shedgum and Uthmaniyah gas compression project will support Aramco’s target of increasing gas production and processing capacity by 80% by 2030, from a 2021 baseline.
In Oman, PDO also moved ahead this year with a project to expand the Birba gas station in Dhofar Governorate. Known as the Budour-Northeast Birba integrated project, it will add units to enable the station to process additional volumes of sour gas.
PDO awarded the EPC works on the project to Egypt’s Engineering for the Petroleum & Process Industries (Enppi), with the contract valued at $355m.
Future pipeline
Looking ahead, the Mena region has a gas processing pipeline worth at least $10.5bn, with planned projects in Oman, the UAE, Saudi Arabia, Kuwait, Iraq, Libya and Algeria at various stages of development.
Aramco is expected to award the EPC contract for the other main component of the Shedgum and Uthmaniyah gas compression project, the Shedgum gas compression package, later this year, after several weeks of discussions with bidders.
The project operator is also in advanced negotiations with frontrunners for the project’s two main pipeline packages and is expected to issue the EPC contracts in the third quarter of this year.
Meanwhile, state energy conglomerate OQ Group is planning to build an NGL facility at Saih Nihayda in central Oman that will extract condensates and transport them to Duqm on the sultanate’s Arabian Sea coast for fractionation and export.
OQ plans to deliver the project using a front-end engineering and design-to-EPC model and is in the process of evaluating the proposals it has received from shortlisted contractors. A main contract award is expected by the end of this year.
Adnoc Gas is expected to re-emerge as a top spender on gas processing when it takes a FID on its estimated $8bn Bab gas cap development project.
The project aims to build a gas processing plant and associated pipeline networks and ancillary units in the Bab area, about 170 kilometres from the city of Abu Dhabi. The planned facility will process up to 1.85 billion cf/d of additional raw gas once Adnoc Gas’ parent company, Adnoc Group, starts production from the onshore Bab gas cap reservoirs.
Adnoc Gas has divided the EPC scope on the Bab gas cap development project into four main packages, which are in different stages of tendering.
Regional gas processing capex is likely to remain robust through the remainder of the decade as NOCs seek to meet growing domestic demand, support industrial development and improve the efficiency of their gas networks.
Further awards are expected for gas treatment trains, sulphur units, NGL recovery, gas compression and pipeline infrastructure, particularly where projects support petrochemical integration, reduce flaring and increase domestic gas supplies.
Exclusive from Meed
-
Dubai evaluates Tasreef drainage bids24 November 2026
-
Muscat financial centre opens for business24 November 2026
-
Mecca university tenders water infrastructure projects24 November 2026
-
Oman’s OQT formalises Pakistan fuel supply agreement24 November 2026
-
Contractors bid for Aramco-backed logistics hub24 November 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Dubai evaluates Tasreef drainage bids24 November 2026

Up to eight stormwater and drainage projects under the next phase of Dubai Municipality’s AED30bn ($8.2bn) Tasreef programme have moved into the bid evaluation stage in recent weeks as procurement activity continues to drive the wider water infrastructure sector.
The projects cover major stormwater drainage networks, pumping stations, storage tanks and sewerage infrastructure. They include schemes serving Dubai South, Abu Hail, the area surrounding Dubai International airport, Dubailand and Al-Awir.
According to regional project tracker MEED Projects, the eight tenders have an estimated combined value of at least $800m. The tenders cover the following projects:
- DS-316-C1: Drainage networks serving Hind 4
- TF-24-C1: Connections to the stormwater network in Dubailand
- TF-25-C1: Stormwater trunk line serving Hind 3, Hind 4 and Umm Al-Daman
- TF-07-C1: Strategic stormwater drainage network between Sheikh Mohammed bin Zayed Road and Emirates Road
- TF-21-C1: Stormwater system upgrade and rehabilitation in Abu Hail
- TF-30-C1: Stormwater storage tanks serving the Dubai International airport area
- TF-06-C2: Stormwater drainage system connecting Al-Maktoum International airport and Dubai South
- DS317-C1: Sewerage and stormwater infrastructure in New Al-Awir 1st
According to sources, local firms Nael Construction & Contracting, Al-Nasr Contracting and Arifco Building Contracting are among those that submitted bids for the Dubailand stormwater network project (TF-24-C1) in October. The bidders for this tender do not include the local DeTech Contracting, which won the estimated $350m engineering, procurement and construction contract for a package on Al-Wasl Road (TF-15-C1), earlier this year.
On 29 October, DeTech, Mohammed Abdulmohsin Al-Kharafi & Sons and Green Oasis General Contracting Company were among those that submitted bids for TF-07-C1, sources told MEED.
It is undersood that both DeTech and Kharafi also submitted offers on 12 November for a contract to upgrade and rehabilitate the stormwater system in Abu Hail (TF-21-C1). The Abu Hail project comprises a stormwater pumping station with a total discharge capacity of 26 cubic metres a second. The wider project involves a major stormwater gravity drainage network, including large-diameter pipelines, and is estimated to cost up to $163m.
Meanwhile, the the municipality is preparing to receive bids for a further scheme (TF-06-C1) on 26 November, involving the construction of a stormwater pond connecting Al-Maktoum airport and Dubai South. Al-Nasr Contracting and Green Oasis are among those preparing to bid, sources said.
In October, the municipality confirmed it had awarded four contracts worth AED3bn ($817m) to expand the emirate’s stormwater drainage network by about 100 square kilometres under phase three of the Tasreef programme.
The projects will cover Jumeirah, Umm Suqeim, Al-Quoz, Al-Barsha, Al-Wasl and Al-Marmoom. The works include constructing and extending main stormwater drainage lines with diameters of up to 3 metres.
The Tasreef programme aims to increase the emirate’s stormwater drainage capacity by 700% and reduce costs associated with pumping stations, network operations and maintenance by 20%.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21756439/main.jpg -
Muscat financial centre opens for business24 November 2026
The International Financial Centre of Oman (IFC Oman) has opened its headquarters at Al-Mouj Business Park in Muscat and registered its first 13 companies.
Sayyid Theyazin bin Haitham Al-Said, Oman's Deputy Prime Minister for Economic Affairs and chairman of IFC Oman, opened the headquarters on 23 November. The ceremony also marked the official start of company registration, which allows local and international businesses to set up within the centre's jurisdiction.
The first 13 companies received their certificates of incorporation at the event. The centre was set up by Royal Decree No. 8/2026 in January, so the move from setting up a legal framework to taking in businesses has taken 10 months.
Registration follows royal decrees that put in place IFC Oman's operating law, regulatory law and courts law. Five core regulations sit alongside them and cover operations, companies, partnerships, foundations and interpretation. Together they set the rules for setting up and running a business in the centre, including corporate governance, regulatory obligations and dispute resolution.
Businesses can apply through a new digital registry platform. A separate regulatory framework for financial services is still being drafted, and licensing for those activities is expected to start in early 2027.
Finance Minister Sultan bin Salim Al-Habsi, who is vice-chairman of IFC Oman, said the decision by 13 companies to join from the start "reflects the strength of the business and investment environment the centre offers".
"We will maintain this momentum as we complete the regulatory framework ahead of the start of financial services licensing early next year," he said.
Sayyid Theyazin said the framework "lays the foundation for a stable and competitive business environment" and will strengthen Oman's appeal to international investors and financial institutions.
He also chaired a board meeting. It reviewed progress on finishing the centre's legal, regulatory and operational infrastructure and set priorities for attracting companies and investment.
IFC Oman aims to connect the national economy more closely to international capital and to support growth in financial and professional services, in line with the Oman Vision 2040 economic diversification programme.
The centre goes up against established regional financial hubs, including Dubai International Financial Centre, Abu Dhabi Global Market and Qatar Financial Centre.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21756636/main5305.gif -
Mecca university tenders water infrastructure projects24 November 2026
Mecca-based Umm Al-Qura University has issued two tenders for wastewater and water storage infrastructure at its student campus in the Al-Abidiyah district.
The first tender covers the second phase of the university’s main water storage scheme. The project involves building seven tanks with a combined capacity of 14,700 cubic metres.
The scope includes three ground-level tanks with a total capacity of 7,500 cubic metres and four elevated tanks with a combined capacity of 7,200 cubic metres.
It also includes a 2.1-kilometre backup water supply pipeline with a diameter of 400 millimetres, as well as pumping stations, inlet and outlet pipework, valves and water control systems.
The second tender covers the construction of a wastewater treatment plant with a capacity of 4,000 cubic metres a day at the university’s student campus. The contract duration is listed as two years.
The projects will expand the campus’s water infrastructure, adding storage capacity and wastewater treatment facilities to support its operational requirements.
Both tenders were issued in November. Bids for the water storage tanks and wastewater plant are due by 14 December and 13 December, respectively.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21752745/main.jpg -
Oman’s OQT formalises Pakistan fuel supply agreement24 November 2026
Oman's state-owned commodity trader OQT has signed a petroleum products supply agreement with Pakistan State Oil (PSO), the South Asian country's national oil marketing company.
The deal was signed on 8 October and formally marked at a ceremony in Muscat on 22 November. It was made under the Oman-Pakistan intergovernmental framework and gives OQT a structured arrangement for supplying petroleum products to PSO.
The two companies have yet to disclose the agreement's value, volumes or duration.
The agreement builds on an existing trading relationship. OQT says it has supplied more than 1 million tonnes of gasoline to PSO in 2026.
OQT also supplies Pakistan's liquefied petroleum gas (LPG) market, selling to both state-owned and private buyers. The company expects its LPG deliveries to Pakistan to pass 120,000 tonnes by the end of the year.
"This agreement gives us a stronger framework to build on that relationship, combining OQT's international trading capabilities with PSO's position in the Pakistani market," said OQT chief executive Wail Al-Jamali.
PSO chief executive Jawwad Ahmed Cheema said the partnership is now "formal, government-backed and built for the long term under the Oman-Pakistan Intergovernmental Agreement".
"For PSO, this is about more than supply. It is about ensuring that Pakistan has the fuel it needs, when it needs it, on terms that protect our national interest," he said.
Oman's Energy & Minerals Minister Salim Al-Aufi and Pakistan's Petroleum Minister Ali Pervaiz Malik attended the ceremony, along with Mulham Al-Jarf, deputy president of investment at the Oman Investment Authority, which owns OQT.
The companies said the agreement will support reliable supply at a time of continued volatility in regional energy markets. They will now focus on implementation and deliveries, and will continue talks on wider petroleum and energy cooperation.
OQT trades crude oil, refined products, petrochemicals, LPG, liquefied natural gas, fertilisers and carbon-related products, and is expanding into metals. It has offices in Muscat, Dubai, London, Rotterdam, Singapore, Houston and Shanghai.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21750539/main1214.jpeg -
Contractors bid for Aramco-backed logistics hub24 November 2026

Asmo, the logistics joint venture of Saudi Aramco and DHL Supply Chain, received proposals from contractors on 15 November for a contract to expand the logistics complex at King Salman Energy Park (Spark) in Saudi Arabia’s Eastern Province.
The logistics hub will add over 124,000 square metres (sq m) at Spark.
Al-Khobar-based engineering firm House of Consulting Office is the project consultant.
The tender for the expansion works comes after Asmo awarded an estimated SR820m ($218m) contract to build the logistics complex’s first phase in May this year.
The overall project will feature a 43,000 sq m, temperature-controlled Grade A warehouse; more than 3,000 sq m of offices and staff amenities; 5,300 sq m dedicated to chemicals storage; and an open yard covering about 1.2 million sq m.
Asmo signed an agreement with Bahrain‑headquartered Arcapita Group Holdings in February to deliver the project at Spark.
Planned for large-scale industrial use, the site is expected to incorporate advanced warehouse and building management systems, end-to-end digital connectivity, automation and robotics.
It will also be developed in line with internationally recognised sustainability standards, featuring solar photovoltaic readiness, electric-vehicle charging infrastructure and a target of Leed Gold certification.
The development aims to support the next stage of Saudi Arabia’s logistics and supply chain expansion.
Under the deal structure, Arcapita will provide funding and retain ownership of the asset, while Asmo will develop the facility and then lease and operate it under a 22-year occupational lease.
According to a statement, “the scheme will be executed via a forward-funding model, underscoring a long-term commitment to national infrastructure”.
Asmo added that this will be its first purpose-built logistics centre and one of four strategic locations planned to anchor its nationwide logistics network, aligned with the National Transport and Logistics Strategy under Saudi Vision 2030.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21747071/main.gif