Gas takes centre stage in Adnoc downstream expansion

13 April 2023

This package on the UAE’s downstream sector also includes:

Fertiglobe to pay $700m in second-half 2022 dividend

Borouge signs East Africa distribution agreement

Adnoc receives bids for key Estidama project packages

Adnoc to study ammonia value chain in German state

Adnoc Gas receives bids for ethane recovery project

Adnoc committed to supplying hydrogen says executive


Regional energy producers are racing to increase their gas production and supply potential as natural gas as a clean energy source becomes more important in the global energy mix.

By merging its gas processing and liquefied natural gas (LNG) businesses this year, Abu Dhabi National Oil Company (Adnoc) has made considerable strides in this race.

Adnoc Gas, the new, combined entity that began operating on 1 January, has a processing capacity of about 10 billion cubic feet a day (cf/d) of gas across eight onshore and offshore sites and a pipeline network of over 3,250 kilometres.

This makes the company, now listed on the Abu Dhabi Securities Exchange, one of the largest gas processing firms in the world.

The strategic move to consolidate its gas processing business underscores Adnoc’s ambition to propel the growth of its overall downstream portfolio, including petrochemicals, with the help of gas.

Adnoc Gas is already overseeing progress on vital downstream projects inherited from the erstwhile Adnoc Group subsidiaries Adnoc Gas Processing and Adnoc LNG.

Sales gas pipeline network

The Estidama project, crucial to enhancing Adnoc’s sales gas pipeline network across the UAE, is progressing under Adnoc Gas’ management.

The project is part of Adnoc Group’s 2030 mandate to ensure a sustainable natural gas supply to its key customers in the country. It aims to cater to increasing demand for gas from industrial consumers across the UAE, particularly in the Northern Emirates.

Contractors recently submitted bids for two key engineering, procurement and construction (EPC) packages of the Estidama project – commercial bids for package two and technical bids for combined package numbers four and seven.

The scope of work on Estidama package two broadly involves building a new facility at the KP-30 location of the Habshan gas compressor plant (HGCP) in Abu Dhabi and installing three variable frequency drive motor-driven compressors.

The combined package involves laying a new pipeline from the Al-Shuwaib pig launcher and pig receiver station to the Sajaa gas facility in Sharjah. The scope also covers building a new gas pipeline between BVS-2/KP28.7 in Abu Dhabi to Dubai’s Margham gas facility to meet increased gas demand from Adnoc Gas Processing’s customer Dubai Supply Authority (Dusup).

The EPC work on the estimated $2bn Estidama project has been divided into seven packages.

Abu Dhabi-based contractor Integrated Specialised General Contracting Company (Iscco) won package one, understood to have a contract value of $18m, in December 2021.

In January this year, MEED named frontrunners to win packages three and six.

Package five is expected to be tendered separately to contractors as part of a planned second phase of the sales gas pipeline upgrade project.

As per the original project schedule, EPC works on the Estidama project are due to be completed in 2025.

Ramping up ethane output

Adnoc Gas is in charge of one of the world’s largest gas processing complexes in Abu Dhabi, with the capacity to process about 8 billion cf/d from its Asab, Bab, Bu Hasa, Habshan and Ruwais plants.

Increased volumes of ethane production will allow the company to commercialise it to supply feedstock to Borouge for its under-construction Borouge 4 petrochemicals complex, as well as to derivatives plants in the upcoming Taziz complex. Adnoc Gas intends to achieve this through the Maximise Ethane Recovery & Monetisation (Meram) project.

Adnoc Gas is understood to have issued the main tender for Meram in February, with the scope of work comprising the detailed engineering aspect of the project. Contractors submitted technical bids for the tender in early March.

Taziz chemicals complex

Meanwhile, investors in the Taziz petrochemicals derivatives-producing industrial complex in Ruwais are pushing ahead with their projects.

Taziz – a 60:40 joint venture (JV) of Adnoc and Abu Dhabi’s industrial holding company ADQ – is overseeing the development of the sprawling industrial complex, which will mainly draw ethylene feedstock from the Borouge 4 facility to produce several in-demand chemicals.

A JV of UAE-based Fertiglobe, South Korea’s GS Energy and Japanese investment firm Mitsui has officially awarded Italian contractor Tecnimont the main EPC contract for its planned blue ammonia project in the Taziz Industrial Chemicals Zone.

The JV has appointed KBR to provide the technology licence, basic engineering design, proprietary equipment and catalyst for the low-carbon ammonia plant, which will have a capacity of 1 million tonnes a year (t/y).

India’s Reliance Industries is also an investor in the Taziz complex, having forged a partnership with Taziz and Abu Dhabi-based Shaheen Chem Holdings Investment (Shaheen) to invest $2bn in developing three chemical plants producing chlor-alkali (940,000 t/y), ethylene dichloride (1.1 million t/y) and polyvinyl chloride (360,000 t/y).

Switzerland-based Proman, meanwhile, has committed to building the UAE’s first methanol plant at Taziz, with a planned production capacity of 1.8 million t/y.

As projects in the first phase of the chemicals complex move forward, Taziz is also understood to be gearing up for a second phase to more than double the number of chemicals produced at the derivatives hub.


This months special report on the UAE also includes: 

> UPSTREAM: Strategic Adnoc projects register notable progress

> POWER: UAE power sector shapes up ahead of Cop28

> WATER: UAE begins massive reverse osmosis buildup

> BANKING: UAE lenders chart a route to growth

https://image.digitalinsightresearch.in/uploads/NewsArticle/10748976/main1250.png
Indrajit Sen
Related Articles
  • Saudi Arabia battery storage awards provide fresh lift

    24 August 2026

    Commentary
    Mark Dowdall
    Power & water editor

    The latest battery storage awards provide a welcome injection of investment into Saudi Arabia’s power market, which has seen a sharp slowdown in contract awards this year.

    Saudi Power Procurement Company’s four Group 1 storage service agreements, announced last week, are worth more than $1.16bn and cover 2,000MW of capacity.

    That is significant against the wider market. According to regional project tracker MEED Projects, Saudi Arabia recorded $19.7bn in power sector contract awards in the first seven months of 2025, compared with just $2.5bn in new awards in the same period this year.

    The battery energy storage system (bess) awards therefore account for a sizeable share of the activity recorded so far this year and provide a much-needed source of new contracting activity.

    Importantly, this is not a one-off. SPPC issued the request for proposal (RFP) for its second group of bess projects in July, covering six projects with a combined capacity of 3,000MW and 12,000MWh.

    With the Group 1 tender taking around 18 months from RFP to contract award, it is reasonable to expect Group 2 contracts to be signed in 2027.

    At the same time, the awards for six independent renewable plants under Round 7 of Saudi Arabia’s National Renewable Energy Programme (NREP), with a combined capacity of 5,300MW, are also likely to move into next year, with the latest bid deadlines now extending into September.

    Although a substantial pipeline remains in procurement, it is only once these projects move from tender to award and into construction that this pipeline translates into market activity.

    It is important that these tenders continue to progress at the pace established by the early rounds of Saudi Arabia’s renewable energy programme and now also SPPC’s independent storage provider bess scheme.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962923/main.jpg
    Mark Dowdall
  • Qatar receives bids for major power grid expansion

    24 August 2026

     

    Qatar General Electricity & Water Corporation (Kahramaa) has received bids for several packages under a major power transmission expansion project tendered in April.

    The project covers new substations at multiple voltage levels, as well as the supply and installation of 400kV extra-high-voltage power cables. The overall scheme is estimated to cost $650m.

    It is being tendered as part of Kahramaa’s 2026 procurement plan, which includes 198 tenders with a total estimated value of QR21.4bn ($5.9bn).

    According to sources, bids were submitted for the following packages on 20 August:

    • Substation packages S1 and S2, covering new 132/11kV substations (estimated cost: $200m)
    • Package S3, covering new 66/11kV substations ($50m)
    • Package S4, including a new 400/220/132kV substation, as well as upgrades and modifications to existing 400kV and 220kV substations ($200m)
    • Package S5, covering new 132/11kV substations and upgrades to existing 132kV and 66kV substations ($100m)
    • Cable packages C1 and C2, covering 400kV cables ($100m)

    Kahramaa previously stated that foreign companies not registered in Qatar would be allowed to participate in the bidding, subject to meeting specified conditions, including registration and certification requirements.

    In June, the electricity and water utility awarded contracts worth more than QR2.2bn ($604m) to expand the electricity transmission network in the country’s western region.

    The engineering, procurement and construction (EPC) works will support the integration of the 2GW Dukhan solar power project into Qatar’s national electricity grid. The scope includes new and upgraded substations, as well as the installation of underground cables and overhead transmission lines.

    Kahramaa said contracts were awarded to local firm Voltage Engineering, Turkiye’s Best & Betas Consortium, India’s Larsen & Toubro and South Korea’s LS Cable.

    Of Kahramaa’s 2026 procurement plan, electricity transmission projects account for QR8.9bn ($2.4bn) and include the construction of new 400/132kV substations in Al-Wukair and Al-Mashaf, as well as the expansion of 400kV substations at Ras Laffan.

    These also cover the installation of 132kV underground cables between Al-Sailiya and Al-Rayyan over a 24-kilometre route, as well as upgrades to the 400kV and 220kV networks.

    Additionally, there are 64 planned electricity distribution projects managed by the Electricity Distribution Department that cover the medium-voltage and low-voltage networks throughout Doha and the regional municipalities. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962223/main.jpg
    Mark Dowdall
  • Maaden closes $1bn term loan and credit facility

    24 August 2026

    Saudi Arabian Mining Company (Maaden) has announced the closing of its inaugural international syndicated term loan and revolving credit facilities, worth a total of $1bn.

    The $500m international term loan facility will support Maaden’s growth agenda and general corporate purposes, including funding growth projects across its portfolio.

    The $500m international revolving credit facility, which is expected to remain undrawn, provides additional committed funding capacity “as Maaden continues to scale its business and execute its long-term growth strategy”.

    The transaction “was met with strong support from the international banking market, attracting participation from a diverse group of leading international banks across key global financial markets”, including the US, Canada, Europe, China and Japan. The facilities were oversubscribed, Maaden said.

    ALSO READ: Maaden and Aramco sign deal to create joint venture

    “The level of demand reflects the global banking community’s confidence in Maaden’s financial strength, strategic direction and ambitious growth plans,” the Saudi state miner said in its statement.

    “The facilities mark another significant milestone in Maaden’s funding journey – further diversifying its sources of funding and broadening its access to global capital providers as the company continues to advance its long-term growth ambitions.

    “Maaden continues to make significant progress across its growth pipeline, expanding production, advancing major projects and accelerating exploration as it builds a world-class mining company at the heart of Saudi Arabia’s economic transformation.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962086/main4516.jpg
    Indrajit Sen
  • Dubai inflation slows to 5.3% in July

    24 August 2026

    Dubai’s annual inflation rate slowed to 5.3% in July, down from 5.7% in June, as a decline in transport costs eased pressure on consumer prices, according to Emirates NBD.

    The bank said the slowdown supported its view that price growth peaked at mid-year, and it expects inflation to continue easing through the rest of 2026. Monthly price growth slowed to 0.1% in July, from 0.4% in June, the weakest pace since February.

    Transport was the clearest sign of the moderation. Annual price growth in the category slowed to 11.9% in July, from 18.1% in June, as transport costs fell 3.7% over the month. Fuel and lubricant inflation eased to 24.1% year on year, from 48.3%, tracking a decline in local petrol prices.

    Petrol remains the main swing factor in the emirate’s inflation. Transport contributed 1.1 percentage points to headline inflation in July, down from 1.7 percentage points in June. Emirates NBD said the relief may prove temporary, with Super 98 petrol prices climbing 5.9% in August to leave them 33.8% higher than a year earlier. The bank expects headline inflation to edge higher in the August figures before easing again later in the year.

    The UAE deregulated petrol and diesel prices in 2015 and reviews them monthly against global prices, meaning changes in global fuel costs pass through to consumers quickly. Transport, which includes fuel, accounts for 9% of Dubai’s consumer price index basket.

    Housing remained the largest contributor to inflation even as its impulse faded. Housing and utilities, which account for about two-fifths of the basket, added 2.8 percentage points to headline inflation. Annual price growth in the category slowed to 7.0%, from 7.4% in January.

    Food inflation edged up to 7.8% year on year, from 7.6% in June, which the bank attributed to lingering supply-chain disruption from the regional conflict. Inflation in restaurants and hotels accelerated to 4.5% year on year, from 1.7% in June.

    Emirates NBD forecasts inflation of 2.9% by year-end but said risks to that projection were tilted to the upside, given lingering pressures in food and housing.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18961735/main1839.jpg
    Colin Foreman
  • Libya oil project on track for 2027 completion

    24 August 2026

     

    The project to develop a workers’ camp at Libya’s Erawin oil field is on track for completion next year, according to industry sources.

    The project, estimated to be worth about $50m, is being executed by the Libyan oil services company Al-Saraya Al-Hamara, headquartered in the city of Sebha.

    The Libyan company was awarded the contract in February 2025.

    The scope of the project includes:

    • Construction of an accommodation camp
    • Construction of the camp maintenance warehouse
    • Construction of the camp office
    • Construction of a fire brigade shelter
    • Construction of a kitchen and mess hall
    • Construction of a mosque
    • Construction of a laundry room
    • Construction of a clinic
    • Construction of parking facilities
    • Installation of a fire and gas system
    • Installation of a power generator
    • Construction of associated facilities

    The client on the project is Zallaf Libya Oil & Gas Exploration & Production Company.

    Zallaf Libya Oil & Gas Exploration & Production Company was established in Libya in 2013 and is wholly owned by Libya’s state-owned National Oil Corporation.

    The Erawin field development project is located about 800 kilometres south of Tripoli and 100km southwest of the El-Sharara field.

    Libya shipped its first cargo of crude from the Erawin oil field in November 2023.

    The shipment departed from Libya’s Zawiyah port and consisted of 600,000 barrels of crude.

    Australia-based Worley Parsons was appointed as the front-end engineering and design (feed) contractor for the early production facility project in 2019.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18953632/main.jpg
    Wil Crisp