Full construction starts for Neom hydrogen project
2 March 2023
Neom Green Hydrogen Company (NGHC) will now start full construction works on the integrated green hydrogen-based ammonia production facility, after having reached financial closure on the project.
The facility is expected to be commissioned in 2026, according to Andrea Lovato, executive vice-president and global head of hydrogen at Saudi utility developer Acwa Power, which is one of the three co-developers of the $8.5bn facility.
"Full construction works will now start, following the full financial closure of the project," says Lovato.
He adds they will now focus on their next plant in Oman, which is being co-developed with state energy enterprise OQ and Air Products.
"Hopefully it will take less time to reach financial close on the [Oman] project, but we will see. It could also be the first green hydrogen project of its scale to get under way in Oman. There will be a different set of regulations," Lovato tells MEED.
The three companies signed a joint development agreement for the multibillion-dollar facility to be located in Oman's Dhofar region in May last year.
Execution status
Neom, US-based Air Products and Acwa Power each have a 33.3 per cent stake in NGHC, the special project vehicle implementing the Neom green hydrogen project, which was first announced in July 2020.
The integrated facility will produce hydrogen to be synthesised into carbon-free ammonia for export exclusively by Air Products to global markets.
The green ammonia will be shipped through the under-construction port at Oxagon, formerly Neom Industrial City.
In addition to being the exclusive offtaker of the green ammonia produced at the plant for 30 years, Air Products is the main engineering, procurement and construction contractor and system integrator for the Neom green hydrogen project.
In February, Air Products said the Neom green hydrogen project’s engineering phase is 30 per cent complete, with all major subcontracts awarded. The land preparation is also complete.
It signed a sub-contract agreement with India’s Larsen & Toubro for the power grid and generation works for the Neom green hydrogen project, as MEED reported in January.
The contract covers the construction of a 2,930MW solar power generation plant, a 1,370MW wind power farm and a 400MW battery energy storage system, according to a source familiar with the plan.
The package also includes a power transmission network extending 190 kilometres.
The planned wind and solar power plants are located in northwest Saudi Arabia, close to the border with Jordan.
In addition to the renewable energy plants, battery storage and power transmission network, the Neom green hydrogen and ammonia project comprises 2,000MW of electrolysers to produce 650 tonnes of hydrogen a day, and air separation units to produce nitrogen for the conversion of hydrogen into 1.2 million tonnes of ammonia a year.
NGHC awarded Germany’s Thyssenkrupp Uhde Chlorine Engineers the contract to supply a more than 2GW electrolysis plant for the project. Thyssenkrupp will engineer, procure and fabricate the plant based on the firm’s 20MW alkaline water electrolysis module.
US-headquartered Baker Hughes will supply Air Products with advanced compression technology for the Neom facility’s electrolyser plant.
Financing structure
NGHC has signed financing agreements with banks and lenders for the project, according to a bourse filing by Acwa Power on 1 March.
The total financing consists of $5.85bn of senior debt and $475m of mezzanine debt facilities.
Both are arranged on a non-recourse project finance basis, as follows:
- $1.5bn from the National Development Fund on behalf of the National Infrastructure Fund
- $1.25bn in the form of SR-denominated financing from the Saudi Industrial Development Fund
The balance is from a consortium of financiers, structured as a combination of long-term uncovered tranches and an Euler Hermes covered tranche, comprising:
- First Abu Dhabi Bank
- HSBC
- Standard Chartered Bank
- Mitsubishi UFJ Financial Group
- BNP Paribas
- Abu Dhabi Commercial Bank
- Natixis
- Saudi British Bank
- Sumitomo Mitsui Banking Corporation
- Saudi National Bank
- KFW
- Riyad Bank
- Norinchukin Bank
- Mizuho Bank
- Banque Saudi Fransi
- Alinma Bank
- Apicorp
- JP Morgan
- DZ Bank
- Korea Development Bank
- Credit Agricole
MEED previously reported that the project capital needs for the integrated Neom green hydrogen project have increased to $8.5bn, up 70 per cent from the original cost estimated at $5bn when the project was first announced in July 2020.
The project’s capital requirement had increased to $6.7bn during the intervening period, before reaching the current estimate.
The increases accounted for inflation since 2020, land costs and the additional scope to make the project more self-sufficient and with lower operating costs.
The latest upward capital revision accounts for project financing costs, up-front fees, interest during construction, additional joint venture costs and land, among other expenses.
Exclusive from Meed
-
Eni completes $1bn Libya gas project20 October 2026
-
Diriyah Company tenders East Wadi bridge20 October 2026
-
Kuwait selects firms for power works at housing projects20 October 2026
-
Taqa moves forward with Mirfa-Liwa scheme20 October 2026
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Eni completes $1bn Libya gas project20 October 2026
Register for MEED’s 14-day trial access
Libya’s Mellitah Oil & Gas Company, a joint venture of Libya’s National Oil Corporation (NOC) and Italian oil and gas company Eni, has achieved mechanical completion on its Bouri gas utilisation project (GUP).
In a statement, Eni said that start-up procedures are currently under way, enabling the recovery of associated gas produced from the Bouri field, which is located in Libya’s western offshore area.
The main contract for the project, worth $1bn, was awarded to Italy’s Saipem in August 2023.
The project involved the construction and installation of the new Bouri gas recovery module and related tie-in infrastructure that enables the recovery and treatment of gas that was previously flared.
In its statement, Eni said that the project “represents one of the most significant emissions reduction initiatives in Libya’s energy sector”.
It also said that it would contribute to improving the environmental performance of the country’s production system by reducing greenhouse gas emissions by approximately 1.5 million tonnes of carbon dioxide a year.
The recovered gas will be supplied to the domestic market, adding about 700 million cubic metres a year and helping meet demand from the power generation sector.
The project will also support additional gas volumes available for export to Europe through the GreenStream pipeline.
Eni said: “The start-up of the Bouri GUP confirms the joint commitment of Eni and NOC to the development of Libya’s energy sector through initiatives that combine production growth, operational efficiency and environmental stewardship.
“The project is part of a broader strategy aimed at enhancing the value of the country’s gas resources while reducing the emissions intensity of upstream activities.”
Other key projects currently under way in Libya include the A&E Structures Project, which is focused on bringing new offshore gas resources onstream for both the domestic market and exports, as well as initiatives aimed at upgrading and optimising gas production and transportation infrastructures.
Eni has been present in Libya since 1959, and the company’s equity production in the country in 2025 amounted to approximately 162,000 barrels of oil equivalent a day.
The Bouri offshore field is part of Libya’s Block NC-41, located 120 kilometres north of the Libyan coast in the Mediterranean Sea.
It was first discovered in 1976 at a depth of 8,700 feet. It is estimated to contain 4.5 billion barrels in proven recoverable crude oil reserves and 3.5 trillion cubic feet of associated natural gas, with an annual production potential of 6 billion cubic metres.
The first development phase, costing nearly $2bn, was completed in 1990.
This was immediately followed by a second development phase, which entailed drilling 55 new wells and constructing three additional platforms. Production began from the oil platforms DP4 and DP3 in August 1998.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20770288/main3529.jpg -
Diriyah Company tenders East Wadi bridge20 October 2026

Saudi Arabia’s Diriyah Company has invited contractors to bid on the construction of the DG II East Wadi Bridge, a key crossing within Riyadh’s Diriyah master development.
The bridge will provide an arterial road connection linking the Diriyah Gate Phase 2 (DG II) Infrastructure Package 1 and Package 2 zones.
The project scope involves the construction of a 100-metre clear-span, 44-metre-wide, single-span post-tensioned concrete bridge structure with integrated abutments and four architectural towers.
The contract also encompasses approach slabs, access roads, pavements, associated earthworks, architectural finishes and cladding, mechanical, electrical and plumbing installations, utility interfaces, bridge parapets, vehicle restraint systems, waterproofing, testing and commissioning, and associated temporary works.
The client will supply the detailed engineering design, and the selected contractor will develop the construction methodology.
Diriyah Company issued the prequalification tender on 14 September, with submissions due by 10 December.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20769223/main.png -
Kuwait selects firms for power works at housing projects20 October 2026

Kuwait’s Public Authority for Housing Welfare (PAHW) has appointed contractors for works covering the supply and installation of 132kV underground cables at South Sabah Al-Ahmad Residential City.
The contracts relate to engineering, procurement and construction (EPC) packages for works for 28 main 132/11kV substations across four phases.
According to sources, Egypt’s Elsewedy Cables has won contracts for phases 1 and 3, while China’s TBEA Shandong Luneng Taishan Cable Company has won contracts for phases 2 and 4 of the development.
In April, MEED reported that PAHW had received at least five bids for each of the first two packages, with Elsewedy and TBEA offering $44m and $40.5m, respectively.
The first contract (phase 1) covers seven substations in zones N9, N7 and N5. The second contract (phase 2) covers seven substations in zones N10 and N5.
PAHW issued two further 132kV underground cable tenders for the South Sabah Al-Ahmad residential development at the end of May, as reported by MEED.
This included a contract (phase 3) covering the supply, extension and maintenance of 132kV underground cables linked to seven substations serving the N5, N6, N8 and N10 districts. Egytech Cables, a subsidiary of Elsewedy, submitted an offer of $39.95m, the lowest of four bids.
The other contract (phase 4) covers the supply, extension and maintenance of 132kV underground cables feeding eight main transformer substations serving the N1, N6 and N11 districts.
MEED reported in July that TBEA had submitted an offer of $44.06m for the contract.
South Saad Al-Abdullah
Separately, PAHW has appointed contractors for power transmission works at the South Saad Al-Abdullah residential development.
The local firm Sayed Hamid Behbehani & Sons has won a contract to supply, install and maintain 10 main 132/11kV transformer substations for the development’s third phase.
Another local firm, Al-Ahleia Switchgear, has won a contract to supply, install and maintain 10 main 132/11kV transformer substations for the project’s fourth phase.
As reported in August, the contractors submitted bids of $104.2m and $103.3m, respectively.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20761431/main.jpg -
Taqa moves forward with Mirfa-Liwa scheme20 October 2026

Taqa Transmission and Taqa Distribution are advancing a major water transmission and distribution scheme serving Mirfa, Madinat Zayed and Liwa in Abu Dhabi, sources told MEED.
The project, originally estimated to cost $775m, has been in procurement for several years. According to sources, a request for proposals has been issued, with bids due on 5 January 2027.
The initial submission deadline was 11 November, before it was extended.
The project was previously tendered in December 2024, with contractors submitting bids for transmission and distribution packages in January 2025. As of August, the bids were still under evaluation. It is unclear whether the latest tender represents a revised procurement process for the same scheme.
The project comprises a water transmission system from Mirfa, alongside distribution networks serving farms and settlements in the western region.
According to details seen by MEED, the latest scope includes a pumping station at Mirfa with a capacity of 128 million imperial gallons a day, about 125 kilometres of transmission pipelines to Muzairah, with branches to Madinat Zayed and Liwa Summit, and storage tanks at the three locations.
The distribution network is divided into four geographic clusters covering Liwa East, Liwa West, Madinat Zayed and Seih Al-Kheir. The works include associated pipelines, pumping stations and storage facilities.
The earlier procurement was structured as an engineering, procurement and construction scheme, divided between transmission and distribution works.
As MEED understands, the latest tender is being pursued under a design, build and operate model, which extends the contractor’s responsibilities to operating the infrastructure after construction.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20758109/main2934.jpg -
Contractors prepare prices for Adnoc Onshore field facilities project20 October 2026

Contractors are preparing commercial bids for Adnoc Onshore’s project to build on-plot and off-plot facilities at the Rumaitha and Shanayel fields in Abu Dhabi’s North East Bab oil field cluster.
The project will enhance and sustain crude output at Rumaitha and Shanayel at 45,000 barrels a day (b/d), supporting Adnoc’s Accelerated Integrated Programme 5 (AiP5) drive to lift capacity to 5 million b/d by 2027.
Adnoc Onshore issued the main tender for engineering, procurement and construction (EPC) works on 19 June. Contractors submitted technical bids by 5 August, sources told MEED.
The on-plot works include adding a crude processing train, produced water treatment and reinjection systems, surface water pumps, and multi-stage gas compression and dehydration units. Works also include utilities, safety and control systems, modifications to existing Phase 1 units and 220kV power infrastructure.
The off-plot scope includes installing and tying in new gas-lifted producer and water-injection wells, as well as building and expanding wellhead clusters. Contractors will also lay crude-gathering, water-injection and gas-export pipelines connecting to the Adnoc Gas network and extend 33kV overhead power lines across the fields.
The tender follows Adnoc Onshore’s shift in strategy for the wider North East Bab development – comprising the Al-Nouf, Rumaitha and Shanayel fields – after scrapping an earlier engineering, procurement and construction management (EPCm) approach. MEED reported in December that the operator had cancelled an off-plot EPCm contract awarded to China Petroleum Engineering & Construction Corporation (CPECC) in October 2024. Adnoc later cancelled a separate on-plot EPCm tender that it received bids for in the second quarter of 2025.
In addition to the North East cluster, Adnoc Onshore continues to make progress on EPC works for another similar project to build off-plot facilities at the South East cluster of oil fields in Abu Dhabi, which is also integral to Adnoc Group’s AiP5 campaign.
The South East cluster comprises the Asab, Mender, Qusahwira, Sahil and Shah fields and accounts for approximately a third of Adnoc Onshore’s oil production capacity.
MEED previously reported that Adnoc Onshore awarded CPECC the EPC works for the South East off-plot facilities project, with the contract value estimated at around $1.2bn.
CPECC is also performing EPC works on the South East on-plot facilities project in a consortium with Greece-headquartered Archirodon. Adnoc Onshore awarded an estimated $1.5bn contract for that project to the consortium in December 2024, with EPC works scheduled for completion in 2027.
ALSO READ: Adnoc Onshore seeks bids for Bu Hasa field EOR project
https://image.digitalinsightresearch.in/uploads/NewsArticle/20757699/main.jpeg