Frontrunner emerges for Master Gas System package

6 August 2024

Register for MEED's 14-day trial access 

Netherlands-headquartered A Hak has emerged as the frontrunner to win the contract for package 9 of Saudi Aramco’s third expansion phase of the Master Gas System network (MGS-3) in Saudi Arabia.

MEED recently reported that A Hak submitted the lowest bid for MGS-3 package 9, followed by Turkish firm Mapa Group. A consortium of Germany’s Max Streicher and locally-based National Basics Company was said to have offered the third-lowest bid.

“Aramco is close to awarding package 9 to A Hak,” one source said. “Negotiations between Aramco and the other bidders are understood to have completed now.”

Contractors submitted revised commercial bids for the package by the deadline of 26 May, MEED previously reported.

The original scope of work on package 9 mainly involves engineering, procurement and construction (EPC) of a 56-inch pipeline covering 458 kilometres from booster gas compression station 10 to sector 1 STS-2.

The estimated $10bn MGS-3 project consists of 17 EPC packages. The first two packages involve upgrading existing gas compression systems and installing new gas compressors. The 15 other packages relate to laying gas transport pipelines at various locations in the kingdom.

Aramco received technical bids for the 15 pipeline packages of the MGS-3 project, including package 9, during the third and fourth weeks of August last year. Contractors submitted commercial bids for the pipeline packages during the last two weeks of September, MEED reported.

While Aramco selected contractors for 14 EPC packages of the MGS-3 project in February this year, prices submitted by bidders for package 9 are understood to have “exceeded Aramco’s budget”, sources previously said.

This is understood to be the main reason Aramco sought revised commercial proposals for the package, adding that the scope of work on the package has also been modified.

MGS-3 EPC packages

On 30 June, Aramco officially awarded 15 lump-sum turnkey contracts for the MGS-3 project, worth $8.8bn.

The expansion, being conducted in collaboration with the Saudi energy ministry, will increase the size of the network and raise its total capacity by an additional 3.15 billion standard cubic feet a day (cf/d) by 2028, through the installation of about 4,000km of pipelines and 17 new gas compression trains, Aramco said in a statement.

Aramco selected the following contractors for 15 of the 17 EPC packages of the estimated $10bn MGS-3 project, MEED reported in February:

  • Package 1 – China Petroleum Engineering & Construction Company (China)
  • Package 2 – Sepco (China)
  • Packages 3 and 12 – Gas Arabian (Saudi Arabia)
  • Package 4 – Mapa (Turkiye)
  • Package 5 – Bin Quraya (Saudi Arabia)
  • Packages 6 and 7 – Sinopec Petroleum Services (China)
  • Package 8 – Larsen & Toubro Energy Hydrocarbon (India)
  • Packages 10 and 14 – Nesma & Partners (Saudi Arabia) / Sicim (Italy)
  • Package 11 – Max Streicher (Germany) / National Basics Company (Saudi Arabia)
  • Packages 13, 15 and 17 – Kalpataru Projects International (India)

Meanwhile, package 16, originally part of the tendering process for the MGS-3 project, has been carved out as a separate tender by Aramco. Contractors submitted proposals for this package by the deadline of 28 July.

The original Master Gas System (MGS) was built in the 1970s and commissioned in 1982. Since then, Aramco has been supplying natural gas to its customers across Saudi Arabia via the network, mainly channelling associated gas from Ghawar and other oil fields.

Over the past decade, amid rising gas demand from Saudi Arabia’s industrial and household sectors, Aramco has undertaken projects to increase its non-associated gas production. In 2015, it launched the second expansion phase of the MGS (MGS-2).

Local contractor Arkad Engineering & Construction won the three main pipeline packages of MGS-2, worth an estimated $1.3bn, in early 2016.

EPC works were completed in 2021, increasing the MGS network’s gas handling and transport capacity from 8.4 billion cf/d to 12.5 billion cf/d.

ALSO READ: Aramco tenders Jafurah fourth expansion phase

https://image.digitalinsightresearch.in/uploads/NewsArticle/12286082/main5505.jpg
Indrajit Sen
Related Articles
  • Adnoc secures Thailand LNG supply deal

    9 October 2026

    Abu Dhabi National Oil Company (Adnoc) has secured a deal with Thailand-based energy and infrastructure company Gulf Group to supply 2 million tonnes a year of liquefied natural gas (LNG), with deliveries starting in 2027.

    The multi-year sale and purchase agreement (SPA), whose exact duration Adnoc did not disclose, builds on an initial LNG supply deal agreed between the two companies last year. The transaction was arranged through Adnoc’s integrated LNG marketing and trading platform, which was established in July within Abu Dhabi Global Market.

    The hub integrates the marketing operations of Adnoc subsidiaries Adnoc Gas and XRG with the trading activities of Adnoc Trading. It targets a combined portfolio of 47 million t/y of marketable LNG by 2035. Adnoc Trading has developed an active third-party trading portfolio over the past four years, operating from commercial offices in Abu Dhabi, Singapore and Geneva.

    ALSO READ: Adnoc signs energy agreements with Japan and South Korea

    Separately, Adnoc has secured offtake commitments covering approximately 90% of the 9.6 million-t/y capacity planned for its low-carbon Ruwais LNG project.

    In July, Adnoc signed a 15-year SPA with Japan’s Inpex Corporation for the supply of up to 1 million t/y from Ruwais. That contract marked Adnoc’s third long-term Ruwais supply agreement with a Japanese buyer, following deals with Osaka Gas and Mitsui & Co in March and April 2025, respectively. Together, the agreements with the three Japanese firms account for 2.4 million t/y – one-quarter of the terminal’s total capacity, which will be delivered across two 4.8 million-t/y liquefaction trains.

    Adnoc has also secured long-term Ruwais LNG supply agreements with Malaysia’s Petronas, Germany’s EnBW Energie Baden-Wurttemberg and SEFE (Securing Energy for Europe), China’s ENN Natural Gas, UK-based Shell and Indian Oil Corporation.

    Currently under construction in Ruwais Industrial City, Abu Dhabi, the facility is scheduled to begin commercial operations in 2028. Its commissioning will more than double Adnoc’s LNG production capacity to approximately 15 million t/y.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20421415/main4048.jpg
    Indrajit Sen
  • Fibrex wins $217m Abu Dhabi Seamont residences contract

    9 October 2026

    Register for MEED’s 14-day trial access 

    Abu Dhabi-based contractor Fibrex Construction Group has won an AED800m ($217m) contract to build the Seamont Autograph Collection Residences project, located on Al-Reem Island in the UAE capital.

    Abu Dhabi-based real estate developer Royal Development Holding, a subsidiary of Emirates Stallion Group, and local firm Saas Properties awarded the contract.

    The development comprises two 22-storey towers offering 497 residences, ranging from one- to four-bedroom apartments.

    The construction programme is scheduled to run for 27 months, with completion due in December 2028.

    Fibrex will begin mobilisation immediately, following the completion of enabling works this month, which were undertaken by Sharjah-based Swiss Pro Foundations.

    Dubai-based architectural firm Dewan Architects & Engineers is the project consultant.

    The contract marks another major win for the contractor. Last year, Dubai-based developer Nakheel awarded Fibrex a AED2.6bn ($708m) contract to build the Bay Villas project at Dubai Islands.

    That contract includes the construction of 636 villas.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20420509/main.jpg
    Yasir Iqbal
  • Dubai picks contractor for Al-Maktoum airport terminal

    9 October 2026

     

    Dubai Aviation Engineering Projects (DAEP) has selected a contractor for an estimated AED10bn ($2.7bn) substructure package for the West Terminal, as part of the first phase of the $35bn expansion of Al-Maktoum International airport.

    A joint venture of Beijing-headquartered China Civil Engineering Construction Corporation (CCECC) and Abu Dhabi-based Tristar Engineering & Construction will execute the contract.

    According to a description on DAEP’s website, the expanded airport’s West Terminal will be a seven-level facility spanning 800,000 square metres, with annual capacity for 45 million passengers.

    The terminal will be the second of three planned terminals at Al-Maktoum International airport. It will connect to the airside via a 14-station automated people-mover (APM) system.

    In July, MEED exclusively reported that DAEP had awarded an estimated $1.5bn contract to a joint venture of Japan’s Mitsubishi Corporation and Indian contractor Larsen & Toubro for the APM system.

    The APM will run beneath the apron and terminal areas, using multiple tracks to transport passengers between terminals and concourses. Four underground stations are planned in the first phase, while the full airport development is expected to include 14 stations.

    The latest awards form part of a wider programme of contracts recently signed by DAEP, covering enabling works, the second runway, initial structural foundations for passenger terminals and concourse substructures.

    Upcoming awards

    In June 2026, DAEP said it will award construction contracts worth over AED55bn ($15bn) for Al-Maktoum International airport by the end of the year.

    At the time, DAEP said the planned awards included substructure works for the West Terminal, the fourth aircraft concourse and the baggage-handling system. The programme also included superstructure works for the West Terminal and the first, second and third aircraft concourses.

    The packages are expected to include long-span structural frameworks for buildings covering about 1.5 million square metres, infrastructure works for the southern airfield area, and power-generation and district-cooling plants supporting the construction programme.

    DAEP also plans to award façade and roofing packages in 2026.

    The Dubai Government approved updated designs and timelines for its largest construction project in April 2024. In September 2024, MEED exclusively reported that a team comprising Austria’s Coop Himmelb(l)au and Lebanon’s Dar Al-Handasah had been confirmed as lead masterplanning and design consultants for the Al-Maktoum International airport expansion.

    Construction of the airport is planned in three phases. Once complete, the airport will cover 70 square kilometres south of Dubai and include five parallel runways and 430 aircraft gates.

    It will be five times the size of Dubai International airport and is planned to have a passenger-handling capacity of 260 million passengers a year – the largest in the world. For cargo, it is planned to have the capacity to handle 12 million tonnes a year.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20417755/main.jpg
    Yasir Iqbal
  • Nakheel awards Dubai Islands marine works contract

    9 October 2026

    Dubai-based developer Nakheel, part of Dubai Holding Real Estate, has awarded local firm Mar Marine & Building Contracting a contract for marine and beach works on Island B at Dubai Islands.

    The scope includes constructing breakwaters, removing existing rock revetments and forming a new 320-metre beach near the Bay Villas development.

    The contractor will also refurbish existing beach areas and undertake remedial works along approximately 3 kilometres of the island’s western shoreline.

    The works are scheduled for completion in the fourth quarter of 2027.

    The package supports the Bay Villas project, which comprises 636 villas and townhouses on Island B. Nakheel awarded Fibrex Contracting an AED2.6bn ($708m) construction contract for the residential development in August 2025.

    The marine works award follows Nakheel’s AED527m primary infrastructure and utilities contract for Island B, which was awarded to Al-Nasr Contracting Company in April 2026.

    In September, Nakheel awarded a main construction contract worth more than AED800m ($218m) for phases one and three of Bay Grove Residences at Dubai Islands. The contract was awarded to local firm Metac General Contracting Company.

    The contract covers the construction of 537 apartments, comprising one- to four-bedroom units, across seven residential buildings. Phase one includes 296 units in four buildings, while phase three comprises 241 units across three buildings.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20418469/main.jpg
    Yasir Iqbal
  • Iraq refinery project given regional approval

    9 October 2026

    Plans to establish a 70,000-barrel-a-day (b/d) refinery in the Iraqi town of Qayyarah have been approved by the Nineveh Provincial Council, which has called for the project to be referred to Iraq’s Council of Ministers. The council also recommended that Duhok-based Karband Company, an industrial manufacturer of asphalt products and lubricating oils, be involved in the project.

    The council’s vote follows a meeting held in September between Iraq’s Oil Ministry and Angola’s Sonangol on potentially jointly developing the Qayyarah refinery.

    The planned refinery would allow more of the crude produced in Qayyarah to be processed locally, increasing supplies of petroleum products and reducing the need to transport locally produced crude south for export via the Strait of Hormuz.

    Iraq awarded the Qayyarah oil field to Sonangol in its second licensing round in 2009, with an initial target of around 120,000 b/d.

    A new upstream expansion phase began in January 2025, when Sonangol contracted the Iraqi Drilling Company to drill 10 wells, with an option for three additional appraisal wells.

    An existing refinery in Qayyarah, built in 1955, has a capacity of 20,000 b/d.

    Progress on the new facility has stalled in recent years, with little movement since 2021, when Iraq signed a memorandum of understanding with Sweden’s SEAB and Turkiye’s Limak on developing the refinery.

    Previously, Iraq’s Oil Ministry said the project would include modern units and complex refining technology to produce products meeting Euro 5 standards

    The scope of the project is expected to include:

    • Processing units
    • Storage tanks
    • Distillation units
    • Associated facilities

    The project was first announced in 2018 and has encountered several delays due to funding problems.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20413126/main.png
    Wil Crisp