Frontrunner emerges for Master Gas System package

6 August 2024

Register for MEED's 14-day trial access 

Netherlands-headquartered A Hak has emerged as the frontrunner to win the contract for package 9 of Saudi Aramco’s third expansion phase of the Master Gas System network (MGS-3) in Saudi Arabia.

MEED recently reported that A Hak submitted the lowest bid for MGS-3 package 9, followed by Turkish firm Mapa Group. A consortium of Germany’s Max Streicher and locally-based National Basics Company was said to have offered the third-lowest bid.

“Aramco is close to awarding package 9 to A Hak,” one source said. “Negotiations between Aramco and the other bidders are understood to have completed now.”

Contractors submitted revised commercial bids for the package by the deadline of 26 May, MEED previously reported.

The original scope of work on package 9 mainly involves engineering, procurement and construction (EPC) of a 56-inch pipeline covering 458 kilometres from booster gas compression station 10 to sector 1 STS-2.

The estimated $10bn MGS-3 project consists of 17 EPC packages. The first two packages involve upgrading existing gas compression systems and installing new gas compressors. The 15 other packages relate to laying gas transport pipelines at various locations in the kingdom.

Aramco received technical bids for the 15 pipeline packages of the MGS-3 project, including package 9, during the third and fourth weeks of August last year. Contractors submitted commercial bids for the pipeline packages during the last two weeks of September, MEED reported.

While Aramco selected contractors for 14 EPC packages of the MGS-3 project in February this year, prices submitted by bidders for package 9 are understood to have “exceeded Aramco’s budget”, sources previously said.

This is understood to be the main reason Aramco sought revised commercial proposals for the package, adding that the scope of work on the package has also been modified.

MGS-3 EPC packages

On 30 June, Aramco officially awarded 15 lump-sum turnkey contracts for the MGS-3 project, worth $8.8bn.

The expansion, being conducted in collaboration with the Saudi energy ministry, will increase the size of the network and raise its total capacity by an additional 3.15 billion standard cubic feet a day (cf/d) by 2028, through the installation of about 4,000km of pipelines and 17 new gas compression trains, Aramco said in a statement.

Aramco selected the following contractors for 15 of the 17 EPC packages of the estimated $10bn MGS-3 project, MEED reported in February:

  • Package 1 – China Petroleum Engineering & Construction Company (China)
  • Package 2 – Sepco (China)
  • Packages 3 and 12 – Gas Arabian (Saudi Arabia)
  • Package 4 – Mapa (Turkiye)
  • Package 5 – Bin Quraya (Saudi Arabia)
  • Packages 6 and 7 – Sinopec Petroleum Services (China)
  • Package 8 – Larsen & Toubro Energy Hydrocarbon (India)
  • Packages 10 and 14 – Nesma & Partners (Saudi Arabia) / Sicim (Italy)
  • Package 11 – Max Streicher (Germany) / National Basics Company (Saudi Arabia)
  • Packages 13, 15 and 17 – Kalpataru Projects International (India)

Meanwhile, package 16, originally part of the tendering process for the MGS-3 project, has been carved out as a separate tender by Aramco. Contractors submitted proposals for this package by the deadline of 28 July.

The original Master Gas System (MGS) was built in the 1970s and commissioned in 1982. Since then, Aramco has been supplying natural gas to its customers across Saudi Arabia via the network, mainly channelling associated gas from Ghawar and other oil fields.

Over the past decade, amid rising gas demand from Saudi Arabia’s industrial and household sectors, Aramco has undertaken projects to increase its non-associated gas production. In 2015, it launched the second expansion phase of the MGS (MGS-2).

Local contractor Arkad Engineering & Construction won the three main pipeline packages of MGS-2, worth an estimated $1.3bn, in early 2016.

EPC works were completed in 2021, increasing the MGS network’s gas handling and transport capacity from 8.4 billion cf/d to 12.5 billion cf/d.

ALSO READ: Aramco tenders Jafurah fourth expansion phase

https://image.digitalinsightresearch.in/uploads/NewsArticle/12286082/main5505.jpg
Indrajit Sen
Related Articles
  • Consultants submit bids for Saudi Arabia’s GCC rail link

    20 July 2026

     

    Consultants submitted proposals on 14 July for a contract to provide design consultancy services for the Saudi Arabian section of the GCC railway network, which is intended to link all six member states.

    Saudi Arabia Railways (SAR) issued the tender on 7 May, MEED previously reported.

    The tender covers the concept, preliminary and issued for construction design stages. SAR requires the selected consultant to review, update and complete the existing preliminary design.

    The consultants who submitted bids include: 

    • Atkins with Khatib & Alami
    • DeutscheBahn with ARX
    • Egis with Sener
    • Idom with Dal al-Handasah
    • Systra

    Saudi Arabia’s section of the railway will start at Al-Khafji in the Eastern Province, near the border with Kuwait, and end at Al-Batha, on Saudi Arabia’s border with the UAE. The route length in Saudi Arabia will be about 672 kilometres (km).

    The railway will interface with the Kuwait National Rail Road (KNRR) project on the Kuwaiti side. Last year, MEED exclusively reported that the KNRR design contract was awarded to Turkiye’s Proyapi Muhendislik ve Musavirlik Anonim Sirketi.

    The KNRR forms part of the wider GCC rail network. GCC railway projects have gained renewed momentum since the six member states signed the Al-Ula Declaration in January 2021.

    In October last year, Qatar’s cabinet approved a draft agreement paving the way for a railway link between Qatar and Saudi Arabia as part of the GCC railway network.

    GCC railway line

    Under the overall plan, the railway will run from Kuwait, pass through Dammam in Saudi Arabia, reach Bahrain via a planned causeway, and continue from Dammam to Qatar, the UAE and, ultimately, Muscat via Sohar in Oman. The railway is reported to span about 2,186km in total.

    The route length within each member state is as follows: 684km in the UAE, 672km in Saudi Arabia, 306km in Oman, 283km in Qatar, 145km in Kuwait and 36km in Bahrain.

    The railway is designed for passenger trains travelling at 220km/h and freight trains operating at 80-120km/h.

    With high levels of project activity, governments in spending mode and renewed cooperation under the Al-Ula Declaration, the latest efforts to restart the GCC railway project may make more progress than previous attempts. If completed, the railway could prove transformational for a region that is globally connected but still divided by national borders.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17705320/main.gif
    Yasir Iqbal
  • Chinese firm wins Dubai drainage contract

    20 July 2026

    China State Construction Engineering Corporation (CSCEC) has announced it has won a contract to deliver a stormwater drainage pipeline package under Dubai Municipality’s Tasreef programme.

    The contract is for the TF-15-C2 stormwater drainage network project located along Umm Suqeim Road in the Al-Barsha and Al-Quoz areas of Dubai. 

    MEED exclusively revealed in May that the contractor had been selected for the engineering, procurement and construction (EPC) contract. The project is estimated to cost $162m.

    The scope of work includes the construction of about 20 kilometres of new stormwater pipelines, together with associated inspection and intake manholes. The project is located west of the Dubai Canal and will connect the Al-Quoz 3 and Al-Quoz 4 industrial areas with Al-Quoz 1.

    It is being delivered as part of Dubai’s Tasreef strategic plan, which supports the Dubai 2040 Urban Master Plan. Once completed, the new drainage infrastructure is expected to improve the emirate’s stormwater network, increase flood protection and enhance the resilience of Dubai’s infrastructure.

    In February, the municipality confirmed it had awarded contracts for five new projects under phase two of the programme to expand and strengthen Dubai’s stormwater drainage network.

    These include a separate contract awarded to CSCEC for the TF-11-C1 stormwater drainage project in the Dubailand area.

    Also in February, Dubai Municipality invited consultants to qualify for a contract to supervise construction on the TF-15-C2 stormwater drainage projects along with two other projects (TF-13-C1 and TF-16-C1) under the Tasreef programme.

    According to a source, a consultant has yet to be appointed.

    TF-16-C1 involves upgrading and rehabilitating the stormwater system east of the Dubai Canal, while TF-13-C1 involves building a water pipeline stormwater drainage system at Al-Marmoum, Al-Qudra and Al-Yalayis 2 & 3.

    Bids are currently under evaluation for the EPC contracts for both projects.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17705058/main.jpg
    Mark Dowdall
  • Dubai receives eight bids for Hassyan SWRO pipeline contract

    20 July 2026

    Register for MEED’s 14-day trial access 

    Eight contractors have made offers for a contract to supply, install, test and commission glass-reinforced epoxy (GRE) water transmission pipelines and associated works for the Hassyan seawater reverse osmosis (SWRO) phase two network in Dubai.

    The contract relates to project one of the Hassyan pipeline network expansion being undertaken by state utility Dubai Electricity & Water Authority (Dewa).

    Local firm Binladin Contracting Group submitted the lowest offer of AED335.92m ($91.5m), according to results published by the utility.

    The other bids were:

    • Green Oasis General Contracting (UAE) – AED345.00m ($93.9m)
    • Al-Nasr Contracting (UAE) – AED391.54m ($106.6m)
    • Wade Adams Contracting (UAE) – AED393.80m ($107.2m)
    • RMB Contracting (UAE) – AED437.96m ($119.3m) 
    • Tristar Engineering & Construction (UAE) – AED441.55m ($120.2m)
    • Shapoorji Pallonji Mideast (UAE/India) – AED451.47m ($122.9m)
    • Gulf Petrochemical Services Trading (UAE) – AED495.20m ($134.8m)

    RMB also submitted a conditional discounted offer of AED427.02m ($116.3m). Three companies submitted regret notices, while one offer was rejected after no valid commercial offer was received. 

    In January, Dewa announced that construction of the 180-million-imperial-gallon-a-day phase one of the Hassyan SWRO independent water project was 90% complete.

    Dewa has two other contracts out for tender for GRE water transmission pipeline work related to the Hassyan SWRO phase two network.

    Project two was tendered on 22 January and has a bid submission deadline of 21 July. Project three was tendered on 26 January and has a bid submission deadline of 29 July.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17704940/main.jpg
    Mark Dowdall
  • Abu Dhabi launches E20 highway expansion project

    20 July 2026

    Abu Dhabi’s Department of Municipalities and Transport (DMT) has announced the E20 highway expansion project.

    The scheme covers widening the main carriageway from three to five lanes, constructing more than 10 kilometres (km) of new ramps and loops, and building four bridges.

    Works also include 1.5km of internal roads and the addition of eight signalised junctions across Khalifa City and the Zayed International airport precinct.

    The project includes utility works, comprising 62km of stormwater drainage, 37km of irrigation networks and the installation of 485 streetlights.

    The E20 expansion is one of the major infrastructure schemes being overseen by DMT in Abu Dhabi.

    Separately, DMT is evaluating bids for a design-and-build contract to construct two bridges serving Hudayriyat Island in Abu Dhabi.

    The scope includes a two-lane bridge connecting 32nd Street to Shakhbout Bin Sultan Street, and a single-lane bridge on 8th Street. It also includes upgrades to signalised intersections.

    Shakhbout Bin Sultan Street is a two-way road with three lanes in each direction, providing access to and from Hudayriyat Island.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17704696/main.jpg
    Yasir Iqbal
  • Firms given more time for Mid Island Parkway prequalifications

    20 July 2026

     

    Abu Dhabi’s Modon Infrastructure has extended the deadline to 31 July for firms to submit expressions of interest and prequalification statements for the next phase of Abu Dhabi’s Mid Island Parkway Project (MIPP), which will be developed as a public-private partnership (PPP).

    The previous deadline was 15 July. MEED understands the prequalification notice was issued in June, following Modon Infrastructure’s invitation in May for firms to register their interest.

    Modon Infrastructure will act as the lead developer and will hold a majority equity stake in the project company. It will award contracts for engineering, procurement and construction; operations and maintenance; and project advisory services.

    Phase two of the MIPP involves the construction of about 11 kilometres (km) of highways, comprising a mix of three-, four- and five-lane sections. The highways will connect the Um-Yifeenah, Al-Jubail, Al-Sammaliyyah and Sas Al-Nakhl islands to Khalifa City and the E10 road.

    The scope also includes the construction of three interchanges – E20, E10 and Dumbbell – on Al-Sammaliyyah Island.

    The project includes several major structures, including the E20 interchange, which will feature cast-in-place box-girder and void-slab bridges, and the E10 interchange, which will feature cast-in-place box-girder bridges. It also includes I-girder bridges between Raha Beach West and Sas Al-Nakhl Island, as well as a causeway at Sas Al-Nakhl Island.

    Further elements include a cast-in-place balanced cantilever bridge between Sas Al-Nakhl Island and Al-Sammaliyyah Island; a tunnel between Al-Sammaliyyah Island and Bilrimaid Island; and a cut-and-cover (open) tunnel on Bilrimaid Island. Another tunnel will connect Bilrimaid Island to Um-Yifeenah Island.

    Abu Dhabi awarded three packages for phase one of the MIPP in 2024. The contract for Package 1A was awarded to a joint venture of Turkish contractor Dogus Construction and UAE firm Gulf Contractors. Package 1B was awarded to a joint venture of Yas Projects (Alpha Dhabi Holding) and China Railway International Group. Beijing-headquartered China Harbour Engineering Company and the UAE’s Agility Engineering & Contracting Company won the contract for Package 1C.

    Phase one starts at the existing Saadiyat Interchange, connecting the E12 to the MIPP, and ends at the recently constructed Um-Yifeenah Highway.

    It comprises a dual main road with a total length of 8km, including four traffic lanes in each direction, two interchanges, a tunnel and associated infrastructure works.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17704765/main.jpg
    Yasir Iqbal