Focus shifts to delivery of Iraq utilities expansion

12 May 2026

 

Iraq’s power and water sector recorded its largest year of investment on record in 2025, with more than $17bn in combined contract awards.

Several long-planned water infrastructure schemes finally reached contract award stage amid mounting supply pressures in the south of the country and a growing reliance on new desalination projects.

Iraq awarded $10bn-worth of water infrastructure contracts between January 2025 and May 2026, according to regional projects tracker MEED Projects.

This compares with just $1.8bn in total awards across 2022, 2023 and 2024, when only one seawater desalination plant reached the contract award stage.

Desalination projects

Attention is now turning to the delivery phase of new plants led by a series of major desalination and water treatment projects in Basra governorate.

In February, Iraqi officials said the flagship $2.42bn Basra seawater desalination plant could be financed through the Iraqi-Chinese Fund, weeks after the main engineering, procurement and construction (EPC) contract was awarded to PowerChina.

Located on the Arabian Gulf coast in Al-Faw, the plant is designed to produce 1 million cubic metres a day (cm/d) of potable water. The project also includes a water transmission network supplying 11 cities and a dedicated 300MW power plant.

Baghdad had earlier announced plans for four additional desalination plants across the province in July 2025. These include the Shatt Al-Arab plant, planned to produce 120,000 cm/d of desalinated water, and the Al-Faw and Al-Siba plants, each with a capacity of 72,000 cm/d.

The joint venture of Baghdad-headquartered Al-Rida Investment Group and PowerChina has been appointed as the main contractor for each project, with construction expected to begin in the third quarter of 2026.

Additional schemes include the $72m Safwan desalination plant and the $70m Abu Flous desalination project. Abu Flous is being undertaken by the Ministry of Water Resources and is designed to have a capacity of 72,000 cm/d.

The push to advance new projects follows warnings issued last year by Iraq’s High Commission for Human Rights about a worsening humanitarian situation linked to declining river flows and rising salinity levels in the Shatt Al-Arab waterway.

Alongside municipal water projects, Iraq is also advancing large industrial water infrastructure schemes tied to the energy sector. Last August, Iraq approved the award of the Common Seawater Supply Project package for the Artawi oil field to South Korea’s Hyundai Engineering & Construction.

The estimated $3.16bn contract covers the engineering, procurement, supply, construction, commissioning and operation of a major seawater treatment facility. Construction is expected to begin in 2026, further reflecting the scale of projects now in the execution stage.

Power expansion

In parallel, Iraq’s power sector is undergoing one of its largest expansion programmes in decades as the government attempts to address chronic electricity shortages, diversify fuel sources and strengthen regional grid connectivity. Over $40bn-worth of projects are under execution, following $4.2bn in new contracts last year.

In August 2025, the Iraqi cabinet approved five major power generation schemes with a combined capacity exceeding 10GW. The projects represent one of the country’s largest-ever single rounds of power project approvals.

The centrepiece of the programme is three independent power producer (IPP) combined-cycle plants at Al-Faw, Abu Ghraib and Kirkuk, with a total capacity of 7,500MW.

The largest schemes are the 3,000MW Al-Faw plant in southern Iraq, with US-based General Electric as the EPC contractor, and the 3,000MW Abu Ghraib facility near Baghdad. Both projects will be implemented under 25-year build-own-operate models.

A 1,500MW combined-cycle plant in Kirkuk will also be developed under long-term power purchase agreements backed by sovereign guarantees from the Finance Ministry. US-based GE Vernova is the technology provider for all three projects.

Furthermore, the government has approved two thermal power plants in Najaf and Youssifiyah, with planned capacities of 1,500MW and 1,800MW, respectively.

This is part of a wider 20-year electricity strategy unveiled last year in partnership with Siemens Energy and GE Vernova. The programme aims to add 57GW of new generation capacity through a mix of gas-fired, thermal and renewable energy projects.

Electricity shortfall

The scale of the challenge means timely project execution will be critical. Iraq currently produces about 28GW of electricity, according to the Electricity Ministry, but demand during peak summer periods is estimated at more than 50GW. The shortfall continues to result in widespread outages and pressure on the national grid.

The fragility of the system was exposed again in March, when Iraq suffered nationwide electricity blackouts after a sudden drop in gas supplies to the Rumaila power plant in Basra. The disruption led to the loss of about 1,900MW of generation capacity and triggered a nationwide grid collapse.

The incident highlighted Iraq’s continued dependence on associated gas production from the oil sector. With regional geopolitical tensions affecting oil exports and production, gas availability for power generation has become increasingly vulnerable.

Solar plants

As part of a strategy to diversify energy sources, the country inaugurated the first phase of the 300MW Karbala solar IPP plant in September 2025, marking Iraq’s first utility-scale solar scheme connected to the national grid.

Developed by a consortium of Norway’s Scatec, Egypt’s Orascom Construction and Iraq’s Al-Bilal Group, the project forms part of the government’s target to add 10GW of solar energy by 2030.

These plans also include the 1GW solar IPP in Najaf, now under construction and scheduled for commissioning in 2028.

Looking further ahead, the Iraqi government announced in February that it has allocated more than 140 sites for new solar power plants, following a six-month identification process. The locations are distributed across several regions, including the outskirts of Baghdad and areas such as Nahrawan, Al-Nasr, Al-Salam, Al-Hamamiyat, Taji and Al-Husseiniya.

Meanwhile, regional interconnection projects are also becoming increasingly important. Iraq is progressing with plans to integrate into the GCC electricity grid through a new 400kV transmission link between Kuwait’s Al-Wafra station and Iraq’s Al-Faw station.

The first phase of the project will allow 500MW of electricity imports into Iraq, rising to 1,800MW over time. Iraq is targeting full integration of the GCC-Iraq grid by the end of 2026.


MEED’s June 2026 report on Iraq also includes:

> OVERVIEW: Iraq enters era of resilience, reform and rising risks
> OIL & GAS: Iraqi oil and gas sector in crisis

https://image.digitalinsightresearch.in/uploads/NewsArticle/16797622/main.gif
Mark Dowdall
Related Articles
  • Al-Maktoum airport is key to Dubai’s aviation hub status

    27 November 2026

    Commentary
    Colin Foreman
    Editor

    Dubai’s position as a global aviation hub is central to its economy, and the expansion of Al-Maktoum International airport is critical to maintaining that role.

    On 26 November, Dubai awarded AED56.5bn ($15bn) of contracts for the airport expansion, taking the total value of contracts awarded to more than AED80bn ($21.8bn). A workforce of 14,000 is working on the project, which will provide capacity for more than 260 million passengers a year when complete.

    The economic stakes are high. A study published by Emirates Group and Dubai Airports in October 2024 found that aviation accounted for 27% of Dubai’s GDP in 2023. The sector contributed AED137bn ($37.3bn) in gross value added and supported 631,000 jobs – about one in five jobs in the emirate. The study forecast that aviation’s share of GDP would rise to 32% by 2030, contributing AED196bn in gross value added and supporting 816,000 jobs.

    This year has demonstrated both the vulnerability and resilience of Dubai’s aviation model. Regional conflict has disrupted commercial air traffic across the Gulf since 28 February. Emirates Group’s profit before tax fell 66% year on year to AED4.1bn in the six months to 30 September, while Emirates carried 21.8 million passengers, down 22% on the prior-year period.

    However, the network recovered quickly. By 30 September, Emirates was operating 91% of its pre-disruption network, serving 150 airports in 78 countries and territories. Emirates SkyCargo revenue rose 52%, the fleet increased to 289 aircraft, and the airline broke ground in May on a $5.1bn maintenance facility at Al-Maktoum International airport.

    Maintaining that connectivity will require additional capacity. If aviation accounts for almost one-third of Dubai’s economy by 2030, as Emirates Group and Dubai Airports forecast, Al-Maktoum International airport will be central to the emirate’s ability to retain its position in global air travel.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21894329/main.jfif
    Colin Foreman
  • Emaar tenders Dubai Creek Harbour mall

    27 November 2026

     

    Register for MEED’s 14-day trial access 

    Dubai developer Emaar Properties has invited contractors to submit bids by 9 December for the main construction package of the Dubai Creek Harbour mall, known as Dubai Square.

    The development covers a total retail, hospitality and commercial area of 2.6 million square metres, and is scheduled to open within three years.

    Emaar unveiled Dubai Square in December 2025 as the anchor of its AED180bn ($49bn) Dubai Creek Harbour development.

    The scheme has undergone several redesigns. MEED first reported on Emaar’s plans for a major retail centre at Dubai Creek Harbour in 2016. At the time, the project was envisioned to surpass Dubai Mall as the world’s largest retail destination, though its scale and layout have since evolved.

    The mall will connect directly to the planned Dubai Creek Tower at the centre of the development.

    UK-headquartered Brewer Smith Brewer Group is the project’s lead consultant, executive architect, architect of record and structural engineer. It is also the construction supervision consultant.

    Dubai-based contractor Dutco Construction began mobilising last year for early site works.

    In March last year, MEED reported that Emaar was preparing to relaunch development of both the tower and the mall. The developer had earmarked roughly AED14bn ($3.81bn) for the two assets as part of a wider AED65bn ($18bn), five-year capital expenditure programme.

    Progress on the tower has been slower. First launched in 2015, it was promoted as the world’s tallest structure, designed to exceed the 828-metre Burj Khalifa. The original design was led by Spanish architect Santiago Calatrava and UK-based RMJM. The project stalled after concrete pile-cap works were completed in 2018.

    In 2023, Emaar founder Mohamed Alabbar confirmed design works were continuing following an international design competition. In January 2026, Alabbar stated that a tender for the redesigned tower would be issued within three months. He later said the tender would be deferred until regional geopolitical tensions ease.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21892263/main.jpg
    Yasir Iqbal
  • Contractor wins Arabian Beauty Horses Village in Qatar

    27 November 2026

     

    Qatar’s Culture Village Foundation (Katara) has awarded Qatar Trading & Contracting Group a QR574m ($158m) contract to build the Arabian Beauty Horses Village in Al-Uqdah Zone 74, in the Al-Khor area.

    The project will include supporting infrastructure and public facilities designed for Arabian show horses and equestrian operations in the Al-Uqdah district.

    Zone 74 is already an important centre for Qatar’s equestrian sector, anchored by the Al-Uqdah Equestrian Complex. The Qatar Racing & Equestrian Club began operating the complex in 2020 in coordination with Qatar’s Ministry of Culture and Sports.

    The Arabian Beauty Horses Village is part of a broader, multistage state strategy to develop Al-Uqdah, on the outskirts of Al-Khor, as Qatar’s second major equestrian hub, alongside Al-Rayyan and Al-Shaqab in Doha.

    According to UK analytics firm GlobalData, Qatar’s commercial construction sector is expected to grow at an average annual rate of 4.5% between 2025 and 2028, supported by investment in hotels, logistics facilities and data centres.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21890026/main.jpg
    Yasir Iqbal
  • King Salman airport sets new infrastructure bid deadline

    27 November 2026

     

    Saudi Arabia’s King Salman International Airport Development Company (KSIADC) has set a 10 January deadline for bids for the Zone C1+C2 roads, bridges and utility networks package for King Salman International airport (KSIA) in Riyadh.

    The tender was issued on 26 October, with an initial bid-submission deadline of 6 December.

    The request for proposals covers the procurement, construction, testing and commissioning of civil infrastructure supporting Terminal 6, alongside the existing Terminals 1-5.

    The scope includes upgrades to Airport Road 539, which runs west of Terminals 1-5, and part of Mohamed bin Faraj Road 5333, west of Junction 6.

    It also includes new roads, ramps, service roads and signalised at-grade junctions. An additional access road will connect the Terminal 6 site offices to Road 5333.

    Structures will include the Junction 6 and Terminal 6 bridges, retaining walls and reinforced-soil structures.

    The contractor will also construct the central ground services equipment (GSE) bridge. Before construction begins, the contractor must validate the design, complete any outstanding elements – including mechanically stabilised earth walls, approach slabs, drainage and lighting – and secure the required authority approvals.

    Dry utilities will comprise high- and extra-high-voltage containment, a 13.8kV medium-voltage network with package substations, low-voltage distribution and street lighting, and security-surveillance systems.

    Wet utilities will include potable water, fire water, irrigation water, treated sewage effluent, district cooling and wastewater networks. Wastewater pipes will range from 200mm u-PVC gravity lines to 1,700mm glass-reinforced plastic mains.

    The stormwater network will include channels, culverts, ponds and pipes ranging from 400mm to 1,400mm in diameter. Crossings will be constructed using open-cut excavation, horizontal directional drilling or microtunneling.

    Utilities serving the operational terminals will be diverted on a design-and-build basis. Enabling works will include earthworks and the relocation of the security fence and trees. The contractor will also demolish a temporary car park, existing bridges and a sewage pumping station.

    Optional works comprise two design-and-build elements that will proceed only at the client’s instruction.

    The first is the south GSE bridge. The second is an approximately 1,400-metre, multi-lane access road to the Terminal 6 Transportation Hub, including bridges, underpasses, ramps and tunnels, as well as provisions for future Wadi Loop utilities and structures.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21887157/main3955.png
    Yasir Iqbal
  • PIF secures inaugural A+ rating from S&P

    26 November 2026

    Saudi Arabia’s Public Investment Fund (PIF) has received an inaugural A+ long-term foreign and local currency issuer credit rating from S&P Global Ratings, with a stable outlook.

    The fund’s existing A-1 short-term rating from S&P is unchanged. PIF said its ratings are in line with those of Saudi Arabia.

    PIF said S&P’s assessment cited its diversified funding profile, moderate leverage and its focus on value realisation under its 2026-30 strategy. The agency also pointed to the fund’s role in driving the kingdom’s economic transformation.

    “The inaugural A+ long-term rating from S&P marks an important milestone in the continued development of PIF’s credit profile and our long-term funding plan,” said Ziyad Alfawzan, head of capital finance strategy at PIF.

    The new rating makes PIF one of a small number of sovereign wealth funds with long-term credit ratings from all three leading agencies.

    Moody’s Ratings confirmed PIF’s Aa3 long-term issuer rating and aa3 baseline credit assessment in September after a periodic review, with a stable outlook. In October, Fitch Ratings affirmed the fund’s long-term foreign and local currency issuer default ratings at A+, also with a stable outlook.

    The Moody’s rating is one notch higher than the A+ grades from S&P and Fitch.

    Debt is an increasingly important source of funding for PIF as it pays for domestic investment programmes and gigaprojects.

    The fund raised $2bn in January from a 10-year sukuk, its first debt sale of 2026. In May, it raised $7bn from a three-tranche bond, its first hard-currency public issuance since the Iran conflict disrupted regional capital markets.

    A full set of long-term ratings is likely to widen PIF’s investor base for future bond and sukuk issuance. The fund also borrows through loans and other debt instruments as part of its funding mix.

    PIF is entering what it calls the value realisation phase of its strategy, covering 2026 to 2030. Over this period, it aims to deliver sustainable financial returns while continuing to drive the diversification of the Saudi economy.


    MEED’s latest report on Saudi Arabia includes:

    > COMMENT: Saudi projects hold steady
    > GOVERNMENT: Riyadh looks to reset its regional defence outlook
    > ECONOMY: Conflict bolsters case for Saudi economic diversification

    > BANKING: Saudi lenders readjust to lower lending and deposit climate
    > UPSTREAM: Aramco upstream spending gathers pace
    > DOWNSTREAM: Sabic steps up Saudi petchems investment

    > POWER: Saudi Arabia’s power award activity slows
    > WATER: Saudi water sector hits sharp slowdown
    > CONSTRUCTION: Saudi construction defies the headwinds
    > TRANSPORT: Saudi infrastructure pushes forward amid conflict
    > DATABANK: Saudi data indicates project spending shift

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21868102/main.gif
    Colin Foreman