Focus shifts to delivery of Iraq utilities expansion
12 May 2026

Iraq’s power and water sector recorded its largest year of investment on record in 2025, with more than $17bn in combined contract awards.
Several long-planned water infrastructure schemes finally reached contract award stage amid mounting supply pressures in the south of the country and a growing reliance on new desalination projects.
Iraq awarded $10bn-worth of water infrastructure contracts between January 2025 and May 2026, according to regional projects tracker MEED Projects.
This compares with just $1.8bn in total awards across 2022, 2023 and 2024, when only one seawater desalination plant reached the contract award stage.
Desalination projects
Attention is now turning to the delivery phase of new plants led by a series of major desalination and water treatment projects in Basra governorate.
In February, Iraqi officials said the flagship $2.42bn Basra seawater desalination plant could be financed through the Iraqi-Chinese Fund, weeks after the main engineering, procurement and construction (EPC) contract was awarded to PowerChina.
Located on the Arabian Gulf coast in Al-Faw, the plant is designed to produce 1 million cubic metres a day (cm/d) of potable water. The project also includes a water transmission network supplying 11 cities and a dedicated 300MW power plant.
Baghdad had earlier announced plans for four additional desalination plants across the province in July 2025. These include the Shatt Al-Arab plant, planned to produce 120,000 cm/d of desalinated water, and the Al-Faw and Al-Siba plants, each with a capacity of 72,000 cm/d.
The joint venture of Baghdad-headquartered Al-Rida Investment Group and PowerChina has been appointed as the main contractor for each project, with construction expected to begin in the third quarter of 2026.
Additional schemes include the $72m Safwan desalination plant and the $70m Abu Flous desalination project. Abu Flous is being undertaken by the Ministry of Water Resources and is designed to have a capacity of 72,000 cm/d.
The push to advance new projects follows warnings issued last year by Iraq’s High Commission for Human Rights about a worsening humanitarian situation linked to declining river flows and rising salinity levels in the Shatt Al-Arab waterway.
Alongside municipal water projects, Iraq is also advancing large industrial water infrastructure schemes tied to the energy sector. Last August, Iraq approved the award of the Common Seawater Supply Project package for the Artawi oil field to South Korea’s Hyundai Engineering & Construction.
The estimated $3.16bn contract covers the engineering, procurement, supply, construction, commissioning and operation of a major seawater treatment facility. Construction is expected to begin in 2026, further reflecting the scale of projects now in the execution stage.
Power expansion
In parallel, Iraq’s power sector is undergoing one of its largest expansion programmes in decades as the government attempts to address chronic electricity shortages, diversify fuel sources and strengthen regional grid connectivity. Over $40bn-worth of projects are under execution, following $4.2bn in new contracts last year.
In August 2025, the Iraqi cabinet approved five major power generation schemes with a combined capacity exceeding 10GW. The projects represent one of the country’s largest-ever single rounds of power project approvals.
The centrepiece of the programme is three independent power producer (IPP) combined-cycle plants at Al-Faw, Abu Ghraib and Kirkuk, with a total capacity of 7,500MW.
The largest schemes are the 3,000MW Al-Faw plant in southern Iraq, with US-based General Electric as the EPC contractor, and the 3,000MW Abu Ghraib facility near Baghdad. Both projects will be implemented under 25-year build-own-operate models.
A 1,500MW combined-cycle plant in Kirkuk will also be developed under long-term power purchase agreements backed by sovereign guarantees from the Finance Ministry. US-based GE Vernova is the technology provider for all three projects.
Furthermore, the government has approved two thermal power plants in Najaf and Youssifiyah, with planned capacities of 1,500MW and 1,800MW, respectively.
This is part of a wider 20-year electricity strategy unveiled last year in partnership with Siemens Energy and GE Vernova. The programme aims to add 57GW of new generation capacity through a mix of gas-fired, thermal and renewable energy projects.
Electricity shortfall
The scale of the challenge means timely project execution will be critical. Iraq currently produces about 28GW of electricity, according to the Electricity Ministry, but demand during peak summer periods is estimated at more than 50GW. The shortfall continues to result in widespread outages and pressure on the national grid.
The fragility of the system was exposed again in March, when Iraq suffered nationwide electricity blackouts after a sudden drop in gas supplies to the Rumaila power plant in Basra. The disruption led to the loss of about 1,900MW of generation capacity and triggered a nationwide grid collapse.
The incident highlighted Iraq’s continued dependence on associated gas production from the oil sector. With regional geopolitical tensions affecting oil exports and production, gas availability for power generation has become increasingly vulnerable.
Solar plants
As part of a strategy to diversify energy sources, the country inaugurated the first phase of the 300MW Karbala solar IPP plant in September 2025, marking Iraq’s first utility-scale solar scheme connected to the national grid.
Developed by a consortium of Norway’s Scatec, Egypt’s Orascom Construction and Iraq’s Al-Bilal Group, the project forms part of the government’s target to add 10GW of solar energy by 2030.
These plans also include the 1GW solar IPP in Najaf, now under construction and scheduled for commissioning in 2028.
Looking further ahead, the Iraqi government announced in February that it has allocated more than 140 sites for new solar power plants, following a six-month identification process. The locations are distributed across several regions, including the outskirts of Baghdad and areas such as Nahrawan, Al-Nasr, Al-Salam, Al-Hamamiyat, Taji and Al-Husseiniya.
Meanwhile, regional interconnection projects are also becoming increasingly important. Iraq is progressing with plans to integrate into the GCC electricity grid through a new 400kV transmission link between Kuwait’s Al-Wafra station and Iraq’s Al-Faw station.
The first phase of the project will allow 500MW of electricity imports into Iraq, rising to 1,800MW over time. Iraq is targeting full integration of the GCC-Iraq grid by the end of 2026.
MEED’s June 2026 report on Iraq also includes:
> OVERVIEW: Iraq enters era of resilience, reform and rising risks
> OIL & GAS: Iraqi oil and gas sector in crisis
Exclusive from Meed
-
Riyadh looks to reset its regional defence outlook11 September 2026
-
Consultant wins Dubai Al-Maktoum airport metro link11 September 2026
-
Saudi Arabia sets October deadline for Mecca metro design11 September 2026
-
Consortiums submit bids for Sadara cogeneration plant11 September 2026
-
UAE plans 150km Boring Company tunnel network11 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Riyadh looks to reset its regional defence outlook11 September 2026

Saudi Arabia may not have suffered as many Iranian missile and drone strikes as some of its neighbours – Bahrain, Jordan and Kuwait have all had to contend with many more during this year’s conflict – but it still feels exposed. Like other Gulf countries, Riyadh has learnt that its deep defence and economic ties to the US, which were meant to provide security and deter aggressors, have in some ways merely made it a target for Tehran.
The threats are not just from direct Iranian strikes, though. In late July, Saudi Arabia joined with the US to attack Iraqi militia groups alleged to have targeted Saudi energy sites in the preceding days.
Yemen’s Houthis are also re-emerging as a serious threat. After several years in which the conflict in Yemen was largely in abeyance, the Yemeni group has in recent months repeatedly launched attacks on Saudi airports and refineries, as well as on ships passing through the Bab El-Mandeb Strait.
From mid-July to mid-August, the Houthis carried out 16 attacks against Saudi assets, including seven oil facilities and six oil tankers, according to the conflict monitoring group Armed Conflict Location & Event Data (ACLED). Riyadh responded with hits on Houthi targets; most notably on weapons depots and other infrastructure in the port city of Hodeidah on 24 July.
The Houthis stepped up their attacks on 8 August, firing dozens of ballistic missiles and drones at Saudi Aramco facilities in Abha, Jaqzam, Khamis Mushait and Najran. The Saudi authorities said 73 civilians were injured. Major General Turki Al-Malki, a spokesman for the Saudi-dominated Coalition to Support Legitimacy in Yemen, described the Houthi attacks as “a dangerous escalation” and said Riyadh would take “all necessary operational measures” to deter further attacks.
So far, a return to a full-scale war in Yemen has been avoided, but ACLED’s Middle East analyst Sherwan Hindreen Ali warned in a report in August that, if both sides continue to escalate, the “chances for renewed full-scale war increase exponentially”.
New partnerships
The increasingly volatile nature of the region has prompted Riyadh to reevaluate its approach to security and to develop new defence partnerships with allies.
The first major step came in late July, when Saudi Arabia launched the Multinational Maritime Defence Coalition with an initial band of 13 other countries; more are expected to sign up in the coming months. The group is designed to protect shipping in the Red Sea, the Gulf of Aden and nearby waters, with Saudi Arabia’s Rear Admiral Abdullah Bin Salem Al-Shehri as its commander.
That was followed by a trilateral mutual defence pact with Pakistan and Turkiye signed in Mecca on 7 August. Their joint defence agreement includes a provision that an attack on any one of them will be considered an attack on all three. At a meeting in Istanbul on 31 August, the partners agreed to set up a secretariat in Riyadh.
There have been other, smaller steps too. In late August, Saudi Arabia signed an agreement to expand defence co-operation with France, during a visit by Crown Prince Mohammed Bin Salman Al-Saud to Paris (pictured). And on 1 September, Saudi Arabia’s National Cybersecurity Authority signed a memorandum of understanding with Pakistan to strengthen cybersecurity cooperation.
Diplomatic tracks
For Riyadh, enhancing its security capabilities to deter Iran and the Islamic Republic’s allies in Yemen and Iraq is a critical issue. However, the Iran war looks unlikely to be resolved by military means alone. Indeed, Saudi officials have repeatedly emphasised their preference for a negotiated, diplomatic solution to the conflict.
The regional diplomatic efforts have been spearheaded by Pakistan, Oman and Qatar, but Saudi Foreign Minister Prince Faisal Bin Farhan Bin Abdullah Al-Saud has also spoken on several occasions to his Iranian counterpart Abbas Araghchi – most recently on 6 September.
One issue where Riyadh is less keen to publicly engage is in relation to Israel. When Saudi Arabia signed an agreement with the US in July covering the development of a civil nuclear power programme, the deal made no mention of Riyadh having to normalise links with Israel – a condition that previous US administrations had insisted on. That was a notable win for Saudi Arabia, although it was thrown into doubt when US President Donald Trump insisted in the following days that the deal would only proceed if Riyadh signed up to the Abraham Accords.
Trump sent the proposed nuclear deal to the US Congress for approval in late August, but administration officials reiterated at the time that the pact would only go into effect if Riyadh normalised relations with Israel – something that, in the current environment, looks extremely unlikely.
Alliance strains
Saudi Arabia’s close ties with the US have been a central element in the kingdom’s regional positioning for decades – but the combination of the Iran war and the volatile nature of the Trump administration means the strength and direction of those ties are now a matter of speculation.
The situation is made more complex by the rivalry between Riyadh and Abu Dhabi, with their differing approaches to regional conflicts and diplomatic initiatives creating a strain within the GCC bloc.
Both sides have tried to change the narrative. In July, Saudi Media Minister Salman Al-Dosary and the UAE’s National Media Authority (NMA) chairman Abdulla Bin Mohammed Al-Hamed issued similar statements on social media denying any rupture between the two governments, with Al-Dosary writing that the countries were “united by a shared history and heritage, and wise leadership”.
On the broader regional stage, Saudi Arabia remains unable to fully insulate itself against the Iran war. On 31 August, the Saudi oil tanker SIDR was hit by Iranian projectiles while transiting the Strait of Hormuz, resulting in the death of two crew members. On the same day, another Saudi oil tanker, the Amzan, was hit by Yemen’s Houthis off the coast of Yanbu, in the Red Sea.
Coupled with the wave of Houthi attacks on 8 September, it suggests that Saudi Arabia’s efforts to create new layers of deterrence have yet to make their mark.
Photo credit: SPA
MEED’s October special report on Saudi Arabia also includes:
> ECONOMY: Conflict bolsters case for Saudi economic diversification
> BANKING: Saudi lenders readjust to lower lending and deposit climate
> POWER: Saudi Arabia’s power award activity slows
> WATER: Saudi water sector hits sharp slowdown
> CONSTRUCTION: Saudi construction defies the headwinds
> TRANSPORT: Saudi infrastructure pushes forward amid conflicthttps://image.digitalinsightresearch.in/uploads/NewsArticle/19583845/main.gif -
Consultant wins Dubai Al-Maktoum airport metro link11 September 2026

Register for MEED’s 14-day trial access
US-based engineering firm Aecom has won a design contract for the Route 2020 extension, which will start from the Expo 2020 metro station and connect with Al-Maktoum International airport’s West Terminal.
Dubai’s Roads & Transport Authority (RTA) awarded the contract.
The extension will run about 3 kilometres (km) and include two stations.
MEED understands the invitation to bid was issued in January, with a submission deadline in mid-March.
The existing Route 2020 metro link is a 15km-long line that branches off the Red Line at Jebel Ali metro station. The line comprises 11.8km of elevated tracks and 3.2km of tunnels, and has five elevated stations and two underground stations.
The RTA awarded the AED10.6bn ($2.9bn) design-and-build contract for the project to a consortium of Spain’s Acciona, Turkiye’s Gulermak and France’s Alstom in 2016.
The RTA also selected Aecom to provide consultancy services for the upcoming Dubai Metro Gold Line project, also known as Metro Line 4, in October last year, as MEED reported.
The Gold Line will start at Al-Ghubaiba in Bur Dubai. It will run parallel to – and alleviate pressure on – the existing Red Line, before heading inland to Business Bay, Meydan, Global Village and residential developments in Dubailand.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19571676/main.jpg -
Saudi Arabia sets October deadline for Mecca metro design11 September 2026

The Royal Commission for Makkah City & Holy Sites (RCMC) has set a deadline of 14 October for a contract covering the initial design studies for its long-planned metro network in the holy city.
The scope includes reviewing existing studies, preparing a concept design, conducting land acquisition studies, developing an integration concept for future phases and other related studies.
The notice was issued in May, with an initial submission deadline of 5 August, as MEED reported.
In September last year, RCMC invited contractors to attend an early market engagement meeting for the project.
In an explanatory document inviting companies to attend the event, the RCMC’s General Transport Centre said it was seeking to gauge market interest in the multibillion-dollar project and obtain feedback on its proposed procurement approach.
MEED exclusively reported in June last year that the project was restarting. Current plans envisage a four-line network, named lines A-D, with 89 stations and three depots, to be implemented over three phases between 2032 and 2045.
Project scope
Stage 1 focuses on lines B and C, involving 2.4 kilometres of tunnelling under the Masar project and integration with the existing Mashaer line.
The network will run just over 62km and comprise 31 stations, 21 of which will be underground, including three iconic stations. A total of 19.5km will run through tunnels, while 41.2km will be elevated, with the remainder at grade.
The 66 required trainsets are projected to provide a daily passenger capacity of about 450,000, equating to annual ridership of 171 million.
The 84.7km-long second phase, due to be operational by 2038, will extend the two lines towards the outskirts of Mecca and includes construction of the initial inner and central segments of lines A and D.
Comprising 61.1km elevated and 18.6km underground, Phase 2 is planned to add 45 stations serving the two new lines, as well as two depots and a potential interconnection with the planned Saudi Landbridge. The 59 trainsets for Phase 2 will increase the network’s projected total annual passenger capacity to more than 500 million.
Phase 3 covers the elevated 36km extension of lines A and D and involves procurement of a further 72 trainsets, increasing the network’s ultimate passenger capacity to 1.2 million daily and 642 million annually by completion in 2045.
Associated development
The metro plan also envisages several transit-oriented developments (TODs) at different points on the route. These will typically comprise commercial, residential and retail elements to maximise the investment case.
The client’s proposed procurement approach involves three distinct packages: civil and systems works, TODs, and operations and maintenance.
The initial concept calls for some of the project to be delivered on a public-private partnership (PPP) basis, wherein the private sector, through special purpose vehicles, will part-finance, build, operate and then transfer commercially viable elements of the scheme.
The then-called Mecca Mass Rail Transit Company (MMRTC) first launched the metro project in 2013; however, the scheme has faltered for more than a decade due to funding issues, land acquisition challenges and scope changes.
The relaunch of the procurement process raises hopes that the project will now come to fruition, although it is likely to be at least 18 months before any definitive works start.
Mecca is home to Saudi Arabia’s first metro, the nine-station, 18km-long Mashaer line, which opened in 2010. It operates only seven days a year during Hajj, but carries more than 2 million pilgrims during that time.
Some 30 million pilgrims visit the city each year, with this number set to grow. A known, quantifiable and growing demand base will help facilitate the use of a PPP mechanism if the framework is adopted.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19569659/main.jpg -
Consortiums submit bids for Sadara cogeneration plant11 September 2026

Register for MEED’s 14-day trial access
At least three consortiums have submitted bids for the contract to develop and operate a cogeneration steam and power plant catering to the Sadara petrochemicals complex in Saudi Arabia.
The planned independent steam and power plant (ISPP) project will have a capacity for 400MW-450MW of combined-cycle electricity generation and 550-700 tonnes an hour of steam.
According to sources, bids were submitted for the contract at the end of August.
The consortium bidders include:
- Abu Dhabi National Energy Company (Taqa) / Samsung C&T (South Korea)
- Al-Jomaih Energy & Water (Saudi Arabia) / Albawani (Saudi Arabia) / Sepco 3 (China)
- Acwa (Saudi Arabia), Korea Electric Power Corporation (Kepco) / Doosan Enerbility (South Korea)
Sadara Chemical Company (Sadara) is the project client. It is the downstream joint venture of Saudi Aramco and US-headquartered Dow Chemical.
The estimated $500m project includes construction of a power plant, substations, a seawater intake system and associated switchyards and switchgear.
The project will also include gas turbines and a back-pressure steam turbine, as well as facilities for steam production.
In 2024, MEED exclusively reported that Sadara had prequalified potential bidders for the project. It is understood that the request for proposals was issued towards the end of last year.
The first units at the $20bn Sadara petrochemicals complex in Jubail began production in 2016, and the complex became operational in 2017.
The Sadara complex is designed to produce more than 3 million tonnes a year (t/y) of chemicals and performance plastics, including polyurethanes, propylene oxide, propylene glycol, elastomers, polyethylene, glycol ethers and amines.
Construction is also continuing on the Najim cogeneration facility, which will supply the Amiral petrochemicals complex with up to 475MW of power and approximately 452 tonnes an hour of steam.
Previously known as the Amiral cogeneration independent steam and power plant, the project is being developed by a team comprising Abu Dhabi National Energy Company (Taqa) and Japanese power generation company Jera.
South Korean contractor Samsung C&T is the engineering, procurement and construction contractor for the project.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19567716/main.jpg -
UAE plans 150km Boring Company tunnel network11 September 2026
The UAE plans to build more than 150 kilometres of underground tunnel with US tunnelling firm The Boring Company, in a programme backed by a $3bn funding round the UAE led.
The Series D round values the Boring Company at $23bn, about four times the $5.7bn it was worth after a 2022 funding round. The UAE and affiliated investment entities led the round, which will accelerate a partnership to deploy underground infrastructure across the UAE, the firm said.
The 150km target marks a substantial expansion of the company’s footprint in the country, extending work already committed through the Dubai Loop project. It contrasts sharply with what has been contracted so far. The Boring Company has signed a construction contract with Dubai’s Roads & Transport Authority (RTA) for the pilot phase of Dubai Loop, covering a 6.4km route and four stations linking Dubai International Financial Centre (DIFC) and Dubai Mall. The pilot is expected to cost about AED565m ($154m), with tunnelling due to begin in the second half of this year.
The 150km figure therefore represents an ambition for the wider partnership rather than a contracted volume, with the bulk of the network yet to be tendered, designed or awarded. No timeframe has been attached to the target.
A second Dubai Loop phase will connect Dubai World Trade Centre and DIFC with Business Bay, extending the tunnels to 22km across 19 stations. The total cost across both phases is expected to be about AED2bn ($545m), with completion scheduled within three years. The pilot route is projected to carry about 13,000 passengers a day, rising to about 30,000 a day across the full route.
Other investors in the round include Human Capital, Vy Capital, Valor Equity Partners, Sequoia Capital, Andreessen Horowitz, Temasek, Shamal Holding and Baron Capital. The proceeds will also fund hiring, the scaling of the company’s Loop transit systems in the US cities of Las Vegas and Nashville, and further development of its Prufrock tunnel-boring machines, which it says can operate in both soft ground and hard rock.
The RTA and the Boring Company signed a memorandum of understanding in February last year to explore developing the Dubai Loop, and the construction contract followed in February this year. In May, US engineering firm Parsons was appointed as programme manager for the pilot phase, with a scope covering independent design verification, permitting and multidisciplinary design reviews.
The appointment comes amid a broader shift towards underground construction across the Gulf, as metro, sewerage and highway works in the UAE, Saudi Arabia and Qatar increasingly default to tunnelling.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19567623/main.jpg