Fiscal deficit pushes Kuwait towards reforms

7 August 2024

 

The poor state of Kuwait’s public finances was laid bare in late July, when the Ministry of Finance announced it had run up a deficit of KD1.6bn ($5.2bn) for the fiscal year ending on 31 March.

A year earlier, the government had booked a rare budget surplus, following eight straight years in the red, but it seems unlikely that it will be able to return to a surplus any time soon. A combination of lower oil revenues, rising spending commitments and an underpowered non-oil sector means the strain on the public purse is rising rather than falling.

The main culprit for the recent budget shortfall was a 19% drop in oil revenue to KD21.5bn. Non-oil income rose by a little over 1% year-on-year, but at just KD2.1bn it remains a marginal element of the state’s finances.

Even as overall revenues were falling, state spending increased by around 13% to KD25.2bn. The vast majority of that – KD20.4bn – went on public sector wages and subsidies. Capital expenditure accounted for just 8% of the total, at KD1.9bn.

The outcome for the past year was, though, better than some had expected. The local NBK Capital, for example, had predicted a KD3bn deficit. Even so, it highlights how the economy remains almost entirely dependent on oil revenues and, by extension, how ill-prepared Kuwait is for a global transition away from hydrocarbons.

While other Gulf governments have been investing heavily in renewable energy projects and seeking to diversify their economies, Kuwait has made negligible progress in these areas.

Structural stagnation

The deficits of the past decade have dealt a significant blow to other elements of the country’s financial health. Speaking at the General Budget Forum in Kuwait in mid-July, Finance Minister Anwar Al-Mudhaf said the assets of the State Reserve Fund had fallen to just KD2bn, down from KD33.6bn a decade earlier.

The persistent failure of the government to push legislation through parliament allowing it to issue more debt has meant that savings have been steadily depleted to cover the budget deficits. The current trend is clearly unsustainable.

Ministry of Finance undersecretary Aseel Al-Munaifi told the same event on 14 July that the size of the budget deficit in the coming years would vary depending on oil prices, but predicted it could total KD26bn over the four years from 2025/26 to 2028/29 – far more than is left in the State Reserve Fund.

Falling oil revenues have also contributed to declines in the country’s GDP. The Washington-based IMF estimates it fell by 2.2% in 2023 and could drop by another 1.4% this year.

Amid all these problems, there have been a few positive signs. Annual inflation eased to 2.8% in June, its lowest level since November 2020, helped by softer prices for food, housing, utilities and transport. UK-based consultancy Oxford Economics predicts it should now stabilise, with a forecast of 2.9% in the coming year.

Kuwait Oil Company also announced a major discovery on 14 July, with an estimated 2.1 billion barrels of light oil and 5.1 trillion cubic feet of gas found at the offshore Al-Nokhatha field. More oil reserves will do little to change the economic climate of the country though, particularly when production levels are voluntarily capped under the Opec+ deal.

Controlling spending

The government of Prime Minister Sheikh Ahmed Abdullah Al-Salah appears to have recognised the need for a more fundamental change in direction, with Al-Mudhaf indicating that more will be done to keep spending under control.

The Ministry of Finance has pencilled in spending of KD24.5bn for the current fiscal year – against revenues of KD18.9bn, meaning a deficit of KD5.6bn. The finance minister has said the government is aiming to keep expenditure at the same level through to 2027/28.

That will be contentious though and may require more political resolve than the government is able to muster. On the other hand, it will find it easier to take unpopular action now than in the past, given the decision by Emir Sheikh Mishaal Al-Jaber Al-Ahmed Al-Sabah in May to suspend the National Assembly for up to four years, thereby removing a significant block to policy reforms.

The government may also now decide the time is right to follow most of its GCC neighbours and introduce VAT – more than six years after it was introduced in the UAE and Saudi Arabia – or other measures such as corporate income tax or ‘sin taxes’ on tobacco and sugary drinks. Such a move could provide a significant boost to non-oil revenues.

“I have been dubious about the prospects of substantial fiscal measures being implemented during the current period while parliament is suspended, given the risk that this would be unpopular and viewed as illegitimate, but the minister’s presentation seems to lay the groundwork for reforms,” said Justin Alexander, director of Khalij Economics.

If the government is to successfully limit its spending over the coming years, it will also need activity to pick up in the private sector, not least to provide more jobs for locals. At the moment, the vast majority of Kuwaitis who are in work are employed by a public sector entity.

The most recent employment market data showed job growth among Kuwaiti nationals of 3.2%, but as NBK Capital pointed out in a report on 23 July, “this was due to a gain in public sector jobs, while private sector employment fell”. Just 15% of working Kuwaitis have jobs in the private sector. Indeed, the public sector wage bill rose by 12% in the most recent financial year.

Al-Mudhaf noted in his comments to the General Budget Forum that public sector salaries are now equivalent to around 30% of Kuwait’s GDP, compared to 7-13% in other GCC states. Among other things, he blamed undisciplined hiring and weak performance evaluations for the rising wage bill.

The situation could get worse before it gets better. Alexander noted that “the expectation is that the pending reforms to equalise employment grades across the public sector will boost salary costs even further”.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12289430/main.gif
Dominic Dudley
Related Articles
  • Kuwait awards $381m oil project

    23 September 2026

    Register for MEED’s 14-day trial access 

    State-owned upstream operator Kuwait Oil Company (KOC) has awarded an oil project contract worth KD117m ($381m) to India’s Megha Engineering & Infrastructure (Meil).

    The Supreme Purchasing Committee for Kuwait Petroleum Corporation (KPC) approved the contract last month, paving the way for the official award.

    The project focuses on a water separation unit at the Al-Rawdatain facility in Kuwait.

    The water separation facility will be developed at Gathering Centre 25 (GC-25), along with a pumping facility at GC-30.

    The project will deliver a wide-ranging upgrade of processing and utility infrastructure, including new low-pressure separation and gas-handling equipment such as a three-phase wet separator package, a gas knock-out drum and associated low-pressure gas pipelines, as well as a high-integrity pressure protection system and a high-pressure flare.

    Meil will develop the new three-phase low-pressure wet separation facility at GC-25.

    The main process equipment will include two wet separator packages, each with a capacity of 150,000 barrels of liquid a day, and a low-pressure gas knock-out drum with a capacity of 53 million standard cubic feet a day, together with associated gas-handling facilities.

    The facility will also incorporate an effluent water treatment and transfer system, including an effluent water balance tank equipped with microbubble flotation and induced gas flotation systems, as well as transfer pumps.

    Additional GC-25 facilities will include fuel gas treatment, chemical injection, oil recovery and flare connections, along with firewater and deluge systems.

    The scope also covers control and safety systems, substations, and associated civil, structural, mechanical, electrical and instrumentation works.

    At GC-30, the project will focus on treated-water filtration and high-pressure injection infrastructure.

    The scope includes nutshell filters and associated feed pumps with a combined capacity of approximately 500,000 barrels of water a day.

    Booster and injection pumps will transfer treated effluent water to designated injection wells.

    Additional facilities at GC-30 will include fuel gas treatment, sludge collection and disposal systems, oil recovery systems, control and safety systems, substations, laboratory and workshop facilities, and associated civil, structural, piping, mechanical, electrical and instrumentation works.

    The project also includes transfer pipelines connecting GC-25, GC-15 and GC-30.

    Meil will carry out modifications to existing tanks at GC-30, as well as process and utility tie-ins, electrical and instrumentation modifications and other infrastructure required to integrate the new facilities with KOC’s existing assets.

    Meil’s responsibilities cover the project lifecycle from design and engineering through procurement, construction, testing, pre-commissioning, commissioning, start-up and performance testing.

    The contract also includes operation, maintenance, repair and insurance responsibilities for the designated facilities during the applicable operations and maintenance period.

    Seven companies submitted bids for the project last November.

    The full list of bids was:

    • Meil (India) – KD117m ($381m)
    • Mechanical Engineering & Contracting Company (Kuwait) – KD130m
    • Spetco (Kuwait) – KD158m
    • Al-Kharafi (Kuwait) – KD164m
    • China Oil HBP Science & Technology (China) – KD169m
    • Alghanim International (Kuwait) – KD169m
    • Jereh Oil & Gas Engineering (China) – KD191m

    In October last year, KOC awarded Meil a separate contract for a project to develop a gas sweetening and recovery facility in west Kuwait.

    Meil submitted the lowest bid for that tender, at KD69.2m ($225.5m), in February 2025.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19911322/main.jpg
    Wil Crisp
  • Kuwait refinery project on track for year-end completion

    23 September 2026

     

    A $65m project to replace a substation at the Mina Al-Ahmadi (MAA) refinery is on schedule to be mechanically complete before the end of the year, according to industry sources.

    The project is being executed by India’s Larsen & Toubro (L&T), which was awarded the contract in October 2024.

    One source said: “This project is approaching completion and is currently on schedule to be completed before the end of the year, although it could still see delays related to the ongoing regional conflict.”

    The client is state-owned downstream operator Kuwait National Petroleum Company (KNPC).

    Kuwait’s Ministry of Electricity, Water & Renewable Energy (MEW) is also involved in the project and will provide final approvals and sign-off.

    The scope of the project includes:

    • Construction of a substation
    • Installation of transformers
    • Installation of medium-voltage switchgear
    • Installation of low-voltage auxiliary systems
    • Installation of network protection systems
    • Installation of disconnecting switches
    • Installation of surge arrestors
    • Installation of feeder breakers and cubicles
    • Installation of low-voltage A/C and D/C equipment
    • Installation of battery banks and battery chargers
    • Installation of related relay and control panel boards
    • Installation of fire alarm and fire protection equipment
    • Installation of a SCADA system
    • Installation of cables
    • Civil works
    • Associated facilities

    The current project to replace a substation at the MAA refinery closely resembles another project tendered by KNPC more than a decade ago, which L&T also won.

    On 18 May 2015, KNPC signed a contract with L&T to build a new 240MW substation at the MAA refinery, valued at KD21.866m.

    The new substation, known as M20, was designed to replace an existing substation that was considered old and obsolete.

    Mohammed Al-Mutairi, who was KNPC’s chief executive at the time, said the substation building would be explosion-proof and use state-of-the-art control systems.

    He said the station’s capacity would increase from 180MW to 240MW, supplying most of the refinery’s electricity needs.

    Given the similarities between the two projects, L&T has been able to reuse some designs, creating efficiencies, according to industry sources.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19911319/main.jpg
    Wil Crisp
  • Contractor wins $208m Almoosa hospital MEP contract

    23 September 2026

    Register for MEED’s 14-day trial access 

    Riyadh-based construction firm BEC Arabia has won a SR781m ($208m) contract for the mechanical, electrical and plumbing (MEP) works at Almoosa Hospital in Al-Khobar.

    Saudi Arabia’s Almoosa Health Company awarded the contract.

    The hospital complex consists of two towers: a 24-storey in-patient tower with 380 beds, and an 11-storey tower with 224 clinics and 113 additional treatment spaces.

    It will be built on a 45,000-square-metre site.

    A podium spanning the ninth and 10th floors will connect the two towers.

    The hospital will also include parking for 1,700 cars.

    BEC Arabia won the SR656m ($175m) main construction contract for the hospital in November last year.

    In August 2025, MEED reported that Almoosa Health Company had announced it had secured a sharia-compliant credit facility worth SR650m ($173m) from Banque Saudi Fransi.

    In a statement published on the Saudi stock exchange (Tadawul), the company said the seven-year facility would be used to support its expansion and growth strategy.

    Lebanon’s Dar, US-based Perkins&Will and French design firm Pierre-Yves Rochon designed the project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19910889/main.jpg
    Yasir Iqbal
  • UAE to develop integrated waste-to-resource pilot

    23 September 2026

    Emirates Biotech and United Arab Emirates University (UAEU) have launched a pilot project in Al-Ain that could provide a model for larger waste-to-resource facilities.

    The project involves developing the UAE’s first integrated organic-waste valorisation pilot plant, which will test whether food waste and compostable packaging can be processed together to recover resources and reduce waste sent to landfill.

    Located near the UAEU campus, the 40kg-a-day facility will process organic waste to produce renewable biogas and nutrient-rich compost. The project is intended to generate technical and operating data that could support the development of larger-scale facilities.

    Emirates Biotech and UAEU will design, build and operate the pilot plant as part of a two-year research project running from August 2026 to August 2028. Installation and commissioning are expected to be completed by August 2027.

    The plant will combine anaerobic digestion and composting. Anaerobic digestion will convert the organic waste into renewable biogas, while the resulting digestate will be composted to produce nutrient-rich compost.

    A laboratory-scale assessment will also examine the potential to convert the biogas into renewable hydrogen.

    Food waste accounts for nearly 40% of daily municipal solid waste in the UAE, according to Emirates Biotech, and much of it is currently disposed of in landfills.

    The pilot will therefore assess the technical and operational feasibility of recovering value from two waste streams through a single integrated process.

    If successfully scaled, Emirates Biotech says an integrated organic-waste valorisation plant could reduce CO₂ emissions by 89% compared with landfilling.

    The project is expected to provide a scalable and modular model for converting food waste and compostable packaging into renewable biogas and compost, with the findings intended to inform the development of larger waste-to-resource facilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19908972/main.jpg
    Mark Dowdall
  • Contractors prepare Oxagon Highway 55 bids

    23 September 2026

     

    Contractors are preparing to submit bids on 28 September for a design-and-build contract for permanent upgrade works on Highway 55 in the kingdom’s Oxagon region.

    The first phase of the project includes constructing 14 kilometres of road, with two lanes in each direction. It also includes one bridge and three interchanges.

    The project duration is 22 months.

    Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.

    MEED reported exclusively in August 2025 that contractors had submitted responses to an expression of interest notice that Neom had issued earlier that month.

    The project is expected to support cargo movement from Duba Port to other parts of the kingdom and the wider region.

    Last year, Neom tested a pilot initiative by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.

    In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”

    The Port of Neom is located on the Red Sea near the Arar border, a key entry point into Iraq.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19907876/main.jpg
    Yasir Iqbal