Firms bid for QatarEnergy LNG gas project package
21 July 2025
Register for MEED’s 14-day trial access
QatarEnergy LNG, a subsidiary of state enterprise QatarEnergy, has received technical bids from contractors for a new engineering, procurement, construction and installation (EPCI) package that is part of the second phase of its North Field Production Sustainability (NFPS) project.
Contractors submitted technical bids for the NFPS phase two COMP5 package “in late June”, sources told MEED. The value of the EPCI contract for the package could be in the “ballpark of $5bn”, the sources said.
Contractors that have submitted technical bids for the NFPS phase two COMP5 package are understood to include:
- China Offshore Oil Engineering Company
- Larsen & Toubro Energy Hydrocarbon (India)
- McDermott (US)
- Saipem (Italy)
The scope of work on the COMP5 package covers EPCI work on the following:
- Two gas compression platforms, each weighing 30,000-35,000 tonnes, plus jacket
- Two living quarter platforms, plus jacket
- Two gas flare platforms plus jacket
- Brownfield modification work at two complexes
According to sources, QatarEnergy LNG, formerly known as Qatargas, is evaluating technical bids for the COMP5 package and has yet to set a submission date for commercial bids from contractors.
NFPS scheme
QatarEnergy’s North Field liquefied natural gas (LNG) expansion programme requires the state enterprise to pump large volumes of gas from the North Field offshore reserve to feed the three phases of the estimated $40bn-plus programme.
QatarEnergy has already invested billions of dollars in engineering, procurement and construction works on the two phases of the NFPS project, which aims to maintain steady gas feedstock for the North Field LNG expansion phases.
The second NFPS phase will mainly involve building gas compression facilities to sustain and gradually increase gas production from Qatar’s offshore North Field gas reserve over the long term.
Saipem has been the most successful contractor on the second NFPS phase, securing work worth a total of $8.5bn.
QatarEnergy LNG awarded Saipem a $4.5bn order in October 2022 to build and install gas compression facilities. The main scope of work on the package, which is known as EPCI 2, covers two large gas compression complexes that will comprise decks, jackets, topsides, interconnecting bridges, flare platforms, living quarters and interface modules.
The gas compression complexes – CP65 and CP75 – will weigh 62,000 tonnes and 63,000 tonnes, respectively, and will be the largest fixed steel jacket compression platforms ever built.
Following that, Saipem won combined packages COMP3A and COMP3B of the NFPS project’s second phase in September last year.
The scope of work on the combined packages encompasses EPCI of a total of six platforms, approximately 100 kilometres (km) of corrosion resistance alloy rigid subsea pipelines of 28-inches and 24-inches diameter, 100km of subsea composite cables, 150km of fibre optic cables and several other subsea units.
Separately, QatarEnergy LNG awarded McDermott the contract for the NFPS second phase package known as EPCI 1, or COMP1, in July 2023. The scope of work on the estimated $1bn-plus contract is to install a subsea gas pipeline network at the North Field gas development.
In March this year, India’s Larsen & Toubro Energy Hydrocarbon (LTEH) won the main contract for the combined 4A and 4B package, which is the fourth package of the second phase of the NFPS project and is estimated to be valued at $4bn-$5bn.
The main scope of work on the package is the EPCI of two large gas compression systems that will be known as CP8S and CP4N, each weighing 25,000-35,000 tonnes. The contract scope also includes compression platforms, flare gas platforms and other associated structures.
LTHE sub-contracted detailed engineering and design works on the combined 4A and 4B package to French contractor Technip Energies.
NFPS first phase
Saipem is also executing the EPCI works on the entire first phase of the NFPS project, which consists of two main packages.
Through the first phase of the NFPS scheme, QatarEnergy LNG aims to increase the early gas field production capacity of the North Field offshore development to 110 million tonnes a year.
QatarEnergy LNG awarded Saipem the contract for the EPCI package in February 2021. The package is the larger of the two NFPS phase one packages and has a value of $1.7bn.
Saipem’s scope of work on the EPCI package encompasses building several offshore facilities for extracting and transporting natural gas, including platforms, supporting and connecting structures, subsea cables and anti-corrosion internally clad pipelines.
The scope of work also includes decommissioning a pipeline and other significant modifications to existing offshore facilities.
In addition, in April 2021, QatarEnergy LNG awarded Saipem two options for additional work within the EPCI package, worth about $350m.
QatarEnergy LNG awarded Saipem the second package of the NFPS phase one project, estimated to be worth $1bn, in March 2021.
Saipem’s scope of work on the package, which is known as EPCL, mainly covers installing three offshore export trunklines running almost 300km from their respective offshore platforms to the QatarEnergy LNG north and south plants located in Ras Laffan Industrial City.
Saipem performed the front-end engineering and design work on the main production package of the first phase of the NFPS as part of a $20m contract that it was awarded in January 2019. This provided a competitive advantage to the Italian contractor in its bid to win the package.
READ THE JULY 2025 MEED BUSINESS REVIEW – click here to view PDF
UAE and Turkiye expand business links; Renewed hope lies on the horizon for trouble-beset Levant region; Gulf real estate momentum continues even as concerns emerge
Distributed to senior decision-makers in the region and around the world, the July 2025 edition of MEED Business Review includes:
> AGENDA: UAE-Turkiye trade gains momentum
> INTERVIEW 1: Building on UAE-Turkiye trade
> INTERVIEW 2: Turkiye's Kalyon goes global
> INTERVIEW 3: Strengthening UAE-Turkiye financial links
> INTERVIEW 4: Turkish Airlines plans further growth
> CURRENT AFFAIRS: Middle East tensions could reduce gas investments
> GCC REAL ESTATE: Gulf real estate faces a more nuanced reality
> PROJECTS MARKET: GCC projects market collapses
> INTERVIEW 5: Hassan Allam eyes role in Saudi Arabia’s transformation
> INTERVIEW 6: Aseer region seeks new investments for Saudi Arabia
> LEADERSHIP: Nuclear power makes a global comeback
> LEVANT MARKET FOCUS: Levant states wrestle regional pressures
> GULF PROJECTS INDEX: Gulf projects index continues climb
> CONTRACT AWARDS: Mena contract award activity remains subdued
> ECONOMIC DATA: Data drives regional projects
> OPINION: A farcical tragedy that no one can end
|
Exclusive from Meed
-
Egis to supervise Riyadh Kafd monorail construction
26 August 2025
-
Dubai’s RTA awards airport road bridge deal
26 August 2025
-
Kafd monorail in Riyadh to commence operations in 2027
25 August 2025
-
-
Acwa Power, SEC and Kepco close $4bn Saudi IPP deals
25 August 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends

Related Articles
-
Egis to supervise Riyadh Kafd monorail construction
26 August 2025
French engineering firm Egis Group has confirmed that it has been selected by King Abdullah Financial District Development & Management Company (Kafd DMC) for a contract to supervise the construction of the Kafd monorail project.
In an official statement published on its website, Egis said that, in its role as site supervision consultant, “its scope includes supervision of rolling stock, rail systems, civil and structural works, mechanical, electrical and plumbing, architecture, utilities and landscaping.”
“Egis is also tasked with reviewing and approving shop drawings, method statements and material submittals, while overseeing critical compliance and quality control processes throughout the project’s construction phase,” the statement added.
Earlier this week, MEED reported that Kafd DMC expects to begin monorail operations in 2027.
According to local media reports, Faddy Alaql, chief asset delivery officer at Kafd, said construction is anticipated to begin by the end of this year, with the project ready for commissioning by 2027.
The scope of work includes the construction of a 3.6-kilometre elevated monorail in a loop configuration, with six elevated stations and six trains – each consisting of two carriages.
The monorail will connect public buildings within Kafd and integrate with the Riyadh Metro system.
It is expected to carry up to 3,500 passengers an hour during peak times.
In October last year, MEED exclusively reported that Kafd DMC had awarded an estimated SR1.2bn ($320m) deal to complete its monorail project at Riyadh’s King Abdullah Financial District.
The contract was awarded to the joint venture of Egyptian contractor Hassan Allam and Chinese rolling stock provider CRRC.
French engineering firm Systra is understood to have updated the technical and supervision studies for both systems and civil engineering works.
Project background
According to data from regional projects tracker MEED Projects, the scheme was put on hold in 2016 after a decade of planning.
In 2010, Bombardier, now part of French firm Alstom, won a $241m contract to build the monorail.
Bombardier, in partnership with local contractor Saudi Oger, was selected to provide its Innovia operation and maintenance services for the system over a 10-year period.
Located in Riyadh, Kafd is a mixed-use development managed by Kafd DMC, a wholly owned subsidiary of the kingdom’s Public Investment Fund (PIF).
Rayadah Investment Corporation previously managed the district.
Construction contracts for several towers in the district were awarded in 2009.
The project stalled when work was approximately 70% complete and later resumed in 2018, after the PIF took over from the Public Pension Agency in 2016-17.
https://image.digitalinsightresearch.in/uploads/NewsArticle/14542797/main.jpg -
Dubai’s RTA awards airport road bridge deal
26 August 2025
Dubai’s Roads & Transport Authority (RTA), in partnership with Dubai Aviation City Corporation (DACC), has awarded a contract for the expansion and enhancement of the bridge leading to Terminal One of Dubai International airport (DXB).
The project will expand the existing bridge from three lanes to four, using a steel box girder system combined with a composite concrete slab.
The bridge will measure 171 metres in length, including its ramps, with the central span measuring 70 metres.
The upgrade is expected to boost the bridge’s capacity from 4,200 to 5,600 vehicles an hour, representing a 33% increase.
This project aims to improve traffic flow, minimise journey times and accommodate rising passenger numbers, which surpassed 92 million in 2024.
Previously, the RTA completed works on Airport Street from Sheikh Mohammed Bin Zayed Road to Casablanca Street.
This project involved building bridges and tunnels, and modifying intersections to facilitate access to DXB.
The RTA also constructed a single-lane bridge for direct access to DXB’s Terminal Three, a bridge to the Dubai Aviation Engineering Projects complex, and another single-lane bridge for traffic from Airport Street to Casablanca Street.
Additionally, Casablanca Street was widened from three to four lanes in the direction of Al-Garhoud bridge.
https://image.digitalinsightresearch.in/uploads/NewsArticle/14542143/main.jpg -
Kafd monorail in Riyadh to commence operations in 2027
25 August 2025
Saudi Arabia’s King Abdullah Financial District Development & Management Company (Kafd DMC) is expected to begin monorail operations in 2027.
According to local media reports, Faddy Alaql, chief asset delivery officer at Kafd, said construction is anticipated to begin by the end of this year, with the project ready for commissioning by 2027.
The scope of work includes the construction of a 3.6-kilometre elevated monorail in a loop configuration, with six elevated stations and six trains – each consisting of two carriages.
The monorail will connect public buildings within Kafd and integrate with the Riyadh Metro system.
It is expected to carry up to 3,500 passengers an hour during peak times.
In October last year, MEED exclusively reported that Kafd DMC had awarded an estimated SR1.2bn ($320m) deal to complete its monorail project at Riyadh’s King Abdullah Financial District.
The contract was awarded to the joint venture of Egyptian contractor Hassan Allam and Chinese rolling stock provider CRRC.
French engineering firm Systra is understood to have updated the technical and supervision studies for both systems and civil engineering works.
Project background
According to data from regional projects tracker MEED Projects, the scheme was put on hold in 2016 after a decade of planning.
In 2010, Bombardier, now part of French firm Alstom, won a $241m contract to build the monorail.
Bombardier, in partnership with local contractor Saudi Oger, was selected to provide its Innovia operation and maintenance services for the system over a 10-year period.
Located in Riyadh, Kafd is a mixed-use development managed by Kafd DMC, a wholly owned subsidiary of the kingdom’s Public Investment Fund (PIF).
The district was previously managed by Rayadah Investment Corporation.
Construction contracts for several towers in the district were awarded in 2009.
The project stalled when work was approximately 70% complete and later resumed in 2018, after the PIF took over from the Public Pension Agency in 2016-17.
https://image.digitalinsightresearch.in/uploads/NewsArticle/14535623/main.jpg -
Iraq deploys Turkish power ships to ease electricity shortfall
25 August 2025
Iraq’s Ministry of Electricity has begun deploying electricity-generating ships to bolster the national power system. The first Turkish vessel, capable of producing 125MW, arrived at Umm Qasr Port on Thursday.
Minister of Electricity Ziyad Ali Fadhil told the Iraqi News Agency that the ships are part of a government plan to add 600MW to the national grid while reducing reliance on imported fuel.
“The Council of Ministers has taken decisions related to purchasing energy through barges to enhance the electricity system’s production and reduce dependence on imported fuel,” he said.
The second vessel, Orka Sultan, arrived at Khor Al-Zubair Port in Basra province on Saturday. It docked at berth 13 and has the same capacity of 125MW, bringing the combined output of the two vessels to 250MW.
Fadhil said the first barge will be fully docked at the quay within seven days of fuel delivery and will begin generating electricity within the same period.
Preparations are under way to supply gas oil fuel for the operation of both stations once the operating company takes over.
The vessels are part of a project led by BKPS, a Karpowership affiliate, to deploy its signature powerships to support Iraq’s energy security.
The deployment comes as Iraq faces near-nationwide blackouts, with recent temperatures as high as 50 degrees Celsius (122 degrees Fahrenheit) driving electricity demand for air conditioning.
The country periodically suffers from power outages, especially during the summer months, when increased cooling requirements overwhelm its power plants and electricity grid.
The country’s power shortfall has been exacerbated by underinvestment in infrastructure, repeated heatwaves and disruptions to gas imports from neighbouring Iran.
The Turkish vessels are part of a broader model of floating power stations, often deployed by companies such as Karpowership to countries needing electricity but lacking the time or resources to build permanent onshore capacity.
Karpowership said in a statement that it will “provide electricity for an initial contract period of 71 days”, helping to stabilise the national grid and meet demand.
https://image.digitalinsightresearch.in/uploads/NewsArticle/14534752/main.jpg -
Acwa Power, SEC and Kepco close $4bn Saudi IPP deals
25 August 2025
Register for MEED’s 14-day trial access
Acwa Power, Saudi Electricity Company (SEC) and Korea Electric Power Corporation (Kepco) have achieved financial close for the 3,600MW Rumah 1 and Nairyah 1 independent power producer (IPP) projects in Saudi Arabia. The two projects represent a total investment of about SR15bn ($4bn).
Saudi Power Procurement Company is the principal buyer for the projects, responsible for tendering and power offtake. Ownership of the project companies, Remal Energy Company for Rumah 1 and Naseem Energy Company for Nairyah 1, is split between Acwa Power (35%), SEC (35%) and Kepco (30%).
The projects form part of the Saudi Energy Ministry’s plan to maximise local power supply in line with Vision 2030.
They also support the kingdom’s net-zero 2060 target and allow for future integration of carbon capture facilities.
Financing was secured from a syndicate of local, regional and international lenders, including Export Import Bank of Korea, Saudi National Bank, Saudi Investment Bank, Banque Saudi Fransi, Standard Chartered Bank, Bank of China, Agricultural Bank of China, Industrial & Commercial Bank of China and Arab Petroleum Investments Corporation.
MEED reported in Novemeber that the Acwa, SEC and Kepco consortium had won the contracts to develop the two combined-cycle gas turbine IPPs. Tokyo-headquartered Mitsubishi Power was to supply the gas turbines to power the plants.
The team offered a levelised electricity cost of 4.5859 $cents a kilowatt-hour ($c/kWh) for Rumah 1 and 4.6114 $c/kWh for Nairiyah 1.
Rumah 1 involves the construction of a combined-cycle gas turbine plant with a capacity of 1,800MW in Riyadh Province. The project will be developed by Remal Energy Company with an investment of SR7.5bn ($2bn).
Nairyah 1, also with a capacity of 1,800MW, will be built in the Eastern Province and developed by Naseem Energy Company. The investment value is about SR7.5bn ($2bn)
https://image.digitalinsightresearch.in/uploads/NewsArticle/14534558/main3558.jpg