Firms express interest in Lower Zakum project
8 May 2023Contractors have expressed interest in bidding for the main contract for the first phase of the Lower Zakum Long-Term Development Plan (LTDP-1) project. The offshore arm of Abu Dhabi National Oil Company (Adnoc Offshore) owns the project.
The Lower Zakum LTDP-1 project is the larger of two projects that the offshore arm of Abu Dhabi National Oil Company has undertaken in line with its ambition to raise the oil and gas production potential of Abu Dhabi’s Lower Zakum offshore hydrocarbon concession over the long term.
Contractors submitted expression of interest (EoI) documents, as part of the prequalification process, for the LTDP-1 project by 27 April, according to sources.
Adnoc Offshore issued the EoI to contractors for the engineering, procurement and construction (EPC) tendering exercise for the Lower Zakum LTDP-1 “earlier in March”, sources previously told MEED, with contractors initially asked to respond by 10 April.
Lower Zakum oil production
The Lower Zakum hydrocarbons zone is 65 kilometres northwest of Abu Dhabi in the Gulf’s waters. Adnoc Offshore holds the majority 60 per cent stake in the Lower Zakum asset. Foreign partners include an Indian consortium of companies led by ONGC Videsh (10 per cent), Japan’s Inpex Corporation (10 per cent), China National Petroleum Corporation (10 per cent), Italy’s Eni (5 per cent) and France’s TotalEnergies (5 per cent).
Adnoc Offshore and its partners in the Lower Zakum concession intend to sustain oil production from the asset at its current level of 450,000 barrels a day (b/d) until 2025, and then increase output to 470,000 b/d. This target will be achieved through the Lower Zakum early production scheme 2 (EPS 2) and proved developed producing (PDP) project.
The larger, longer-term objective is to raise Lower Zakum’s oil production to 520,000 b/d by 2027 and maintain that level until 2034. This goal is to be accomplished through the LTDP-1 project.
Raising oil and gas production from the Lower Zakum asset is vital for Adnoc to achieve its accelerated target of increasing oil production capacity to 5 million b/d by 2027, and raising gas output potential by 3 billion cubic feet a day (cf/d) by the end of this decade.
Lower Zakum EPS 2/PDP project
Front-end engineering and design (feed) work is progressing on the Lower Zakum EPS 2/PDP project and is being performed by UK-headquartered Wood Group.
Adnoc Offshore, which, according to sources, awarded Wood the contract in November last year, expects feed work on the project to be completed by June.
The basic scope of work on the project involves the drilling of 17 additional producer and water injection wells on two new wellhead towers (WHTs) and the expansion of the gas compression capacity of the Zakum West Super Complex (ZWSC).
Integration of the Lower Zakum complexes with the onshore power grid at UZ AGI for electricity supply to the EPS 2/PDP project is also part of the scope.
Demolition of structures and as-built documentation and surveying are also included in the scope of work.
Adnoc Offshore solicited interest for the Lower Zakum EPS 2/PDP project EPC works in December last year. Contractors expressed interest in participating in the main contract tendering process in January, sources told MEED.
As per the schedule, Adnoc Offshore expects to issue the project’s main EPC tender in June, with the award of contracts to take place in September.
Lower Zakum LTDP-1 project
Feed work is progressing on the Lower Zakum LTDP-1 project and is being performed by France’s Technip Energies.
According to sources, Adnoc Offshore awarded Technip Energies the contract in November last year. The operator expects feed work on the project, which began in December, to be completed by January 2024.
Adnoc Offshore issued the expression of interest for the Lower Zakum LTDP-1 EPC tendering exercise “earlier in March”, with contractors asked to respond by 10 April.
The detailed scope of work on the Lower Zakum LTDP-1 project is as follows:
Topside facilities on G Island – Civil works on process facilities and associated buildings on the artificial greenfield G Island.
Process facilities include well pads, inlet and export reception, production separation, export pumps, gas compression, dehydration and lift, produced water treatment and disposal, vapour recovery units, water injection units, riser tower, flare towers, accommodation, drilling of high-pressure flare knock out drum, power distribution facility, substations and local equipment rooms.
Offshore WHTs and pipelines – Seven WHTs will be installed: six in the east area, and one in the AGI area. Five of the WHTs are to be 16-slot, while the two others are to be 9-slot.
Das Island Terminal, ZCSC and ZWSC – The five existing oil processing trains at the Lower Zakum offshore development are to be decommissioned in 2028, with the new configuration of the main processing plant at Das Island to be:
- Two existing trains with a processing/stabilisation capacity of 110,000 b/d each
- Three new trains with a processing/stabilisation capacity of 150,000 b/d
The scope of work also covers the installation of other structures such as:
- Three high-pressure separator trains
- High-pressure scrubber
- Three low-pressure separator trains
- Low-pressure scrubber
- Three atmospheric separator trains
- Four crude charge pumps
- Three crude charge heaters
- Three cold strippers integrated with a degassing vessel
- Six stripped crude product pumps
- Common ejector with a spare for three cold strippers
- Closed drain drum with transfer pump
- Blow case vessel
As per the schedule, Adnoc Offshore expects to issue the project’s main EPC tender in December, with the award of contracts to take place in March next year.
The operator expects the Lower Zakum LTDP-1 project to be commissioned by the end of 2027.
Exclusive from Meed
-
Oman makes strides forward in global LNG race
22 September 2025
-
Aseer-Jizan highway is a test case for Gulf infrastructure PPPs
19 September 2025
-
Kuwait aims to close bidding for $1.3bn oil projects
19 September 2025
-
Dubai heads towards record year for road construction
18 September 2025
-
Three bids submitted for Riyadh-Qassim IWTP
18 September 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends

Related Articles
-
Oman makes strides forward in global LNG race Indrajit Sen
22 September 2025
Commentary
Indrajit Sen
Oil & gas editorOman has recently made notable strides in the global race to lead the production and export of liquefied natural gas (LNG) — a critical enabler of the energy transition.
The Omani government made headlines in July last year, when it announced that majority state-owned Oman LNG would build a new train at its Qalhat LNG production complex in Sur. The new LNG train will have an output capacity of 3.8 million tonnes a year (t/y), increasing Oman LNG’s total production capacity to 15.2 million t/y when it is commissioned in 2029.
Oman LNG recently made key progress on its project to add a fourth processing train at the Sur LNG complex, shortlisting contractors to participate in the main tender for engineering, procurement and construction (EPC) works.
The start of the EPC tendering process and selection of bidders comes within ten months of Oman LNG awarding the contract for front-end engineering and design (feed) works on the project to US-based consultancy KBR.
Separately, MEED recently reported that France’s TotalEnergies is studying a potential expansion of its Marsa LNG bunkering and export terminal in Oman. The move is significant considering that the first phase of the project is currently under construction in the sultanate’s northern industrial city of Sohar, and will have an output capacity of 1 million t/y.
TotalEnergies purportedly began an initial study on a potential second phase of the Marsa LNG facility earlier this year. The French energy major might consider doubling the output capacity of the LNG complex, although the plan is yet to be laid out, according to sources.
Earlier this year, TotalEnergies appointed French contractor Technip Energies as a consultant to perform concept and feasibility studies on the proposed expansion phase of the Marsa LNG terminal, sources told MEED.
With Oman LNG going full throttle with its fourth LNG train project, and TotalEnergies mulling a potential doubling of LNG production in Oman, the sultanate is on course to establish itself as a prominent player in the global LNG domain by the end of this decade.
https://image.digitalinsightresearch.in/uploads/NewsArticle/14716054/main.jpg -
Aseer-Jizan highway is a test case for Gulf infrastructure PPPs Yasir Iqbal
19 September 2025
Commentary
Yasir Iqbal
Construction writerRegister for MEED’s 14-day trial access
The start of tendering for the Aseer-Jizan highway public-private patnership (PPP) is a watershed moment in the Gulf region's approach to infrastructure. For decades, the major highways in the GCC have been delivered in the same way: government-funded, government-managed, with little appetite for risk-sharing.
This project breaks that mould. Aiming to be the first full-concession transport PPP in the region, it hands the private partner responsibility for design, construction, financing, operations and maintenance. This is a major step forward.
According to industry experts, the move signals that Saudi Arabia, and by extension the GCC, is ready to treat private investors as partners rather than contractors. The PPP models in social infrastructure have been useful experiments, but this case, where the private sector is taking on long-term risks, demonstrates the market’s growing maturity.
This raises the bar for private involvement and brings the model closer to precedents seen in Europe, Asia and Latin America.
However, there are still unknowns: the offtaker is new to the PPP market, and that adds uncertainty. But for investors, the prestige of being associated with Saudi Arabia’s first highway concession has its own appeal. As long as the payment guarantees are firm, the risk may be worth the reward.
If the project is executed well, it will set the standard for a new pipeline of road, airport and rail schemes. It will also deliver confidence, both for investors, who want predictable frameworks, and for governments, which want to stretch budgets without compromising delivery.
The wider GCC will study the Aseer-Jizan highway PPP carefully. The concession is the first test case that could pave the way for the region's investment-driven infrastructure developments.
Webinar: Unlocking Opportunities: An Insight into the NCP’s Current PPP Project Pipeline in Saudi Arabia
Mon, 29 Sep 2025 | 13:00 GST / 12:00 KSA
Secure your spot now by clicking here
https://image.digitalinsightresearch.in/uploads/NewsArticle/14704209/main.jpg -
Kuwait aims to close bidding for $1.3bn oil projects Wil Crisp
19 September 2025
Register for MEED’s 14-day trial access
State-owned upstream operator Kuwait Oil Company (KOC) is aiming to close the bidding process for two major projects by the end of September, according to sources.
Both projects are focused on the development of an oil separation facility, with their combined value expected to be about KD396m ($1.3bn).
Both tenders have seen several extensions to their bid deadlines since they were originally tendered.
One source said: “KOC has signalled to bidders that the bid deadline extensions are coming to an end.
“They are aiming to see bids submitted before the end of September. There maybe will be a small delay of a week, or something like that, but KOC is really looking to get bids in before the end of September.”
Both contracts were tendered in December 2024 and the original deadline for bid submission for both contracts was set for 16 March.
The first tender, estimated to be worth KD292m ($951m), is focused on developing a separation facility in the NK SA/BA area, close to Gathering Centre 23 (GC-23) and GC-24. The scope of the contract also includes a new injection facility at GC-31 and effluent water injection networks in north Kuwait.
The second contract, estimated to be worth KD104m ($338m), is focused on developing separation facilities at GC-25 and a water injection facility at GC-30.
Kuwait is in the middle of an upstream projects push, in line with producing 4 million barrels a day of oil by 2035.
On 10 May 2024, Kuwait’s Emir, Sheikh Mishal Al-Ahmad Al-Sabah, announced the indefinite suspension of parliament in a televised speech.
Under Kuwaiti law, parliament can be suspended for a maximum of four years.
Prior to the suspension of Kuwait’s parliament, the country suffered from very low levels of project awards for several years due to political gridlock and infighting between the country’s cabinet and parliament.
https://image.digitalinsightresearch.in/uploads/NewsArticle/14702553/main0703.png -
Dubai heads towards record year for road construction MEED EDITORIAL
18 September 2025
Commentary
Colin Foreman
EditorDubai is investing heavily in infrastructure as it strives to keep up with the pace of real estate development across the city.
The most recent award was in early September, when the Roads & Transport Authority (RTA) selected Beijing-headquartered China Civil Engineering Construction Corporation as the contractor for the Al-Safa Street improvement project.
According to regional projects tracker MEED Projects, Dubai is on course for a record year in 2025, with awards already reaching $1.216bn year-to-date. That exceeds the 2024 total of $774m and is almost equal to the total for the whole of 2023, positioning 2025 to surpass the previous peaks of $1.621bn in 2017 and $1.644bn in 2008.
Road construction awards had slumped to just $101m in 2020 and $139m in 2021, reflecting both the impact of the pandemic and a slowdown in project spending. Since then, a strong recovery has taken hold as the government prioritises transport links to support growth areas such as Dubai South, Al-Maktoum International airport and new housing corridors.
By allocating record spending to road construction, Dubai is signalling that it recognises the urgency of the problem.
Building roads alone is not enough. To remain an efficient global city, Dubai needs a modern transportation network that does not just rely on roads. More metro lines are under construction and are being planned, and there are also plans for cable car systems and tunnel networks.
These projects will take time to be delivered. In the meantime, the record awards of 2025 are a welcome sign that road capacity will increase, even if congestion remains an ongoing problem in the short term.
https://image.digitalinsightresearch.in/uploads/NewsArticle/14696781/main.jpg -
Three bids submitted for Riyadh-Qassim IWTP Mark Dowdall
18 September 2025
Register for MEED’s 14-day trial access
State water offtaker Saudi Water Partnership Company (SWPC) has received three bids from the private sector for the development of the Riyadh-Qassim independent water transmission pipeline (IWTP) project.
The bids were submitted by two consortiums and one individual company.
The first consortium comprises Saudi firms Al-Jomaih Energy & Water, Al-Khorayef Water & Power Technologies, AlBawani Capital and Buhur for Investment Company.
The second consortium comprises Bahrain/Saudi Arabia-based Lamar Holding, the UAE's Etihad Water & Electricity and China’s Shaanxi Construction Installation Group.
The third bid was submitted by Saudi Arabia's Vision Invest.
In August, MEED exclusively reported that SWPC had extended the bid submission deadline again for a contract to develop and operate the project.
The deadline for bids was 17 September.
The project will have a transmission capacity of 685,000 cubic metres a day. It will include a pipeline length of 859 kilometres (km) and a total storage capacity of 1.59 million cubic metres.
The scheme is the third IWTP contract to be tendered by SWPC since 2022.
The first two are the 150km Rayis-Rabigh IWTP, which is under construction, and the 603km Jubail-Buraydah IWTP, the contract for which was awarded to a team of Riyadh-based companies comprising Al-Jomaih Energy & Water, Nesma Group and Buhur for Investment Company.
Like the first two IWTPs, the Riyadh-Qassim IWTP project will be developed using a 35-year build-own-operate-transfer contracting model.
Commercial operations are expected to commence in the first quarter of 2030.
https://image.digitalinsightresearch.in/uploads/NewsArticle/14691078/main.jpg