Firms express interest in Lower Zakum project
8 May 2023

Contractors have expressed interest in bidding for the main contract for the first phase of the Lower Zakum Long-Term Development Plan (LTDP-1) project. The offshore arm of Abu Dhabi National Oil Company (Adnoc Offshore) owns the project.
The Lower Zakum LTDP-1 project is the larger of two projects that the offshore arm of Abu Dhabi National Oil Company has undertaken in line with its ambition to raise the oil and gas production potential of Abu Dhabi’s Lower Zakum offshore hydrocarbon concession over the long term.
Contractors submitted expression of interest (EoI) documents, as part of the prequalification process, for the LTDP-1 project by 27 April, according to sources.
Adnoc Offshore issued the EoI to contractors for the engineering, procurement and construction (EPC) tendering exercise for the Lower Zakum LTDP-1 “earlier in March”, sources previously told MEED, with contractors initially asked to respond by 10 April.
Lower Zakum oil production
The Lower Zakum hydrocarbons zone is 65 kilometres northwest of Abu Dhabi in the Gulf’s waters. Adnoc Offshore holds the majority 60 per cent stake in the Lower Zakum asset. Foreign partners include an Indian consortium of companies led by ONGC Videsh (10 per cent), Japan’s Inpex Corporation (10 per cent), China National Petroleum Corporation (10 per cent), Italy’s Eni (5 per cent) and France’s TotalEnergies (5 per cent).
Adnoc Offshore and its partners in the Lower Zakum concession intend to sustain oil production from the asset at its current level of 450,000 barrels a day (b/d) until 2025, and then increase output to 470,000 b/d. This target will be achieved through the Lower Zakum early production scheme 2 (EPS 2) and proved developed producing (PDP) project.
The larger, longer-term objective is to raise Lower Zakum’s oil production to 520,000 b/d by 2027 and maintain that level until 2034. This goal is to be accomplished through the LTDP-1 project.
Raising oil and gas production from the Lower Zakum asset is vital for Adnoc to achieve its accelerated target of increasing oil production capacity to 5 million b/d by 2027, and raising gas output potential by 3 billion cubic feet a day (cf/d) by the end of this decade.
Lower Zakum EPS 2/PDP project
Front-end engineering and design (feed) work is progressing on the Lower Zakum EPS 2/PDP project and is being performed by UK-headquartered Wood Group.
Adnoc Offshore, which, according to sources, awarded Wood the contract in November last year, expects feed work on the project to be completed by June.
The basic scope of work on the project involves the drilling of 17 additional producer and water injection wells on two new wellhead towers (WHTs) and the expansion of the gas compression capacity of the Zakum West Super Complex (ZWSC).
Integration of the Lower Zakum complexes with the onshore power grid at UZ AGI for electricity supply to the EPS 2/PDP project is also part of the scope.
Demolition of structures and as-built documentation and surveying are also included in the scope of work.
Adnoc Offshore solicited interest for the Lower Zakum EPS 2/PDP project EPC works in December last year. Contractors expressed interest in participating in the main contract tendering process in January, sources told MEED.
As per the schedule, Adnoc Offshore expects to issue the project’s main EPC tender in June, with the award of contracts to take place in September.
Lower Zakum LTDP-1 project
Feed work is progressing on the Lower Zakum LTDP-1 project and is being performed by France’s Technip Energies.
According to sources, Adnoc Offshore awarded Technip Energies the contract in November last year. The operator expects feed work on the project, which began in December, to be completed by January 2024.
Adnoc Offshore issued the expression of interest for the Lower Zakum LTDP-1 EPC tendering exercise “earlier in March”, with contractors asked to respond by 10 April.
The detailed scope of work on the Lower Zakum LTDP-1 project is as follows:
Topside facilities on G Island – Civil works on process facilities and associated buildings on the artificial greenfield G Island.
Process facilities include well pads, inlet and export reception, production separation, export pumps, gas compression, dehydration and lift, produced water treatment and disposal, vapour recovery units, water injection units, riser tower, flare towers, accommodation, drilling of high-pressure flare knock out drum, power distribution facility, substations and local equipment rooms.
Offshore WHTs and pipelines – Seven WHTs will be installed: six in the east area, and one in the AGI area. Five of the WHTs are to be 16-slot, while the two others are to be 9-slot.
Das Island Terminal, ZCSC and ZWSC – The five existing oil processing trains at the Lower Zakum offshore development are to be decommissioned in 2028, with the new configuration of the main processing plant at Das Island to be:
- Two existing trains with a processing/stabilisation capacity of 110,000 b/d each
- Three new trains with a processing/stabilisation capacity of 150,000 b/d
The scope of work also covers the installation of other structures such as:
- Three high-pressure separator trains
- High-pressure scrubber
- Three low-pressure separator trains
- Low-pressure scrubber
- Three atmospheric separator trains
- Four crude charge pumps
- Three crude charge heaters
- Three cold strippers integrated with a degassing vessel
- Six stripped crude product pumps
- Common ejector with a spare for three cold strippers
- Closed drain drum with transfer pump
- Blow case vessel
As per the schedule, Adnoc Offshore expects to issue the project’s main EPC tender in December, with the award of contracts to take place in March next year.
The operator expects the Lower Zakum LTDP-1 project to be commissioned by the end of 2027.
Exclusive from Meed
-
Lebanon sets October deadline for power generation projects23 September 2026
-
Jedco maps next phase of Jeddah airport expansion22 September 2026
-
Contractor wins $105m Medina university hospital deal22 September 2026
-
Fourteen contractors bid for Oman dam drainage project22 September 2026
-
Oman tenders Thumrait Industrial City infrastructure22 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Lebanon sets October deadline for power generation projects23 September 2026

Lebanon’s Electricity Regulatory Authority (ERA) has extended the deadline for private sector companies to submit expressions of interest (EoIs) for several upcoming power generation projects.
The new deadline is 15 October. The original deadline was 30 September.
The regulator said the extension follows “requests received from interested applicants for additional time to finalise and submit the required documentation”.
The EoI covers up to five grid-connected solar photovoltaic projects with a combined installed capacity of 350 megawatts-peak. The projects are also expected to include battery energy storage systems with a combined capacity of 1,000 megawatt-hours.
The regulator is also seeking proposals for distributed dual-fired thermal power plants with net capacities ranging from 20MW to 100MW. The plants are expected to run on natural gas as the primary fuel and heavy fuel oil as a backup.
The ERA invited companies to submit EoIs at the beginning of August.
On 11 August, the ERA issued its first set of clarifications following queries regarding the EoI. The clarifications confirmed that “proposed dual-fired plants should be gas-ready”, with natural-gas infrastructure planned but no implementation timeline yet available.
The ERA also said key power purchase agreement (PPA) terms, including duration, tariff structure and indexation mechanisms, will be determined “during a future procurement process”.
Electricity reforms
The EoI comes as the government advances wider reforms to Lebanon’s electricity sector. On 4 September, the Higher Council for Privatisation and Partnership discussed steps to transform the state utility Electricite du Liban (EDL) into a company, including creating a new entity, transferring its assets, and taking measures to protect employees’ rights during the transition.
The government said the restructuring aims to improve the financial sustainability of the electricity sector, recover costs and improve electricity supply.
On 18 September, the council discussed a draft decree to establish the new EDL company, evaluate its assets and separate its activities. However, it deferred a decision for further study.
The ERA was established earlier this year, more than two decades after it was envisaged under Law No. 462/2002 but not implemented due to political delays. The Energy & Water Ministry and EDL previously oversaw the electricity sector.
Lebanon’s electricity sector continues to face insufficient generation capacity, fuel supply constraints, ageing generation assets and limited grid flexibility. These challenges have led to prolonged electricity shortages and increased reliance on private diesel generation and distributed solar systems, prompting the government to seek additional private investment in new generation capacity.
According to the EoI document, the projects are expected to be structured as independent power producer (IPP) schemes. The competent public authority will determine any future contractual arrangements, including PPAs, under the applicable legal framework.
The ERA said the EoI is open to private investors, IPP operators, engineering, procurement and construction contractors, equipment suppliers and consortiums. It aims to assess market interest, identify potential generation projects, and evaluate the technical and financial capabilities of prospective developers.
Respondents must provide information on their technical and financial capabilities, proposed project locations, grid connection plans and relevant project experience.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19906210/main.jpg -
Jedco maps next phase of Jeddah airport expansion22 September 2026

Jeddah Airports Company (Jedco) has outlined plans for the next phase of expansion at King Abdulaziz International airport (KAIA) in Jeddah.
The programme comprises six upcoming contractor packages spanning airside works, terminal upgrades and utilities as Jedco advances its long-term expansion plans.
The opportunities include airfield rehabilitation; a five-year construction framework covering multiple workstreams and facility types; a Terminal 3A (T3A) package; Terminal 1 (T1) optimisation; a fuel farm; and Concourse C works.
The packages cover terminal buildings and ancillary facilities, runways, taxiways and aprons, hangars, fuel systems, airside facilities, supporting infrastructure and utility networks.
Tendering and award activity will be staggered over the next two years. Airfield rehabilitation is targeted for Q3 2026. The construction framework is scheduled for Q4 2026 and will run for five years.
The T3A package is planned for Q1 2027 and will be delivered under an early contractor involvement contract. Local contractors are encouraged to bid as part of a joint venture with an experienced international partner.
T1 optimisation is planned for Q4 2027, the fuel farm for Q2 2027, and Concourse C – currently the latest of the six milestones – for Q2 2028.
The new packages add detail to Jedco’s wider expansion plans disclosed in 2023, when it was reported that the company would invest SR115bn ($31bn) to increase KAIA’s capacity to 114 million passengers a year, with an overall completion target of 2031.
Jedco has recently awarded several significant contracts linked to the airport’s upgrade programme.
In November 2024, a joint venture of local Algihaz Contracting and Turkey’s TAV was awarded a contract to rehabilitate the South Terminal to serve Umrah and Hajj pilgrims, with Singapore’s Surbana Jurong acting as consultant.
Earlier that year, Jedco also awarded France’s Alstom a contract to increase the capacity of the Innovia automated people mover at Terminal 1, including new cars and upgrades to signalling, communications and controls.
Surbana Jurong is expected to play a leading role in future KAIA expansion plans and is currently providing technical advisory and project management consultancy for more than 100 capital projects for Jedco, valued at over SR6bn ($1.6bn).
These upgrades are expected to boost KAIA’s annual capacity in line with Saudi Arabia’s Vision 2030 and National Aviation Strategy, enhancing the experience for domestic travellers and millions of Hajj and Umrah pilgrims.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19877992/main.jpg -
Contractor wins $105m Medina university hospital deal22 September 2026

Riyadh-based construction firm Al-Mansouria General Contracting Company has been awarded a SR396m ($105.6m) contract to complete the remaining construction works on the Taiba University Hospital project in Medina.
The contract scope includes structural completion, remaining civil works, mechanical, electrical and plumbing installations, specialised clinical fit-outs and medical gas infrastructure to bring the long-stalled facility into operation.
Located on King Khalid Road along Medina’s Third Ring Road, the teaching hospital will have a capacity of 563 beds.
The contract duration is three years, with delivery targeted for late 2029.
The latest award follows a prolonged procurement cycle that began more than a decade ago as part of a public budget drive to expand Saudi Arabia’s higher education infrastructure.
The project’s first phase was initially signed in December 2011 with local firm Al-Muhaidib Contracting under a SR500m ($133.3m) contract.
Groundbreaking for the eight-storey complex took place in July 2013. The project covers a gross floor area of more than 200,000 square metres.
Progress stalled shortly thereafter due to reported structural delays and the reallocation of public capital budgets across the kingdom’s social infrastructure pipeline.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19870032/main.jpg -
Fourteen contractors bid for Oman dam drainage project22 September 2026
Fourteen contractors have submitted bids for a major drainage project designed to manage flows downstream of Oman’s Al-Khawd Recharge Dam and strengthen flood protection in Al-Seeb, Muscat Governorate.
The proposed works will manage flows downstream of the Al-Khawd Recharge Dam and reduce flood and erosion risks around Al-Khawd village and surrounding assets. The project site includes remote wadi reaches, with access constraints expected to affect construction logistics and temporary access arrangements.
Oman’s Ministry of Agriculture, Fisheries & Water Resources (MAFWR) is the project client.
Bidders submitted their main contract bids on 14 September, with prices ranging from about $126m to $390m.
The bidders and their prices are:
- China International Water & Electric Corporation: $125.94m
- Eksen Project Construction Tourism & Trade (Turkiye): $149.09m
- Ozkar Construction (Turkiye): $149.71m
- United Thumtait Lines (Oman): $149.80m
- Portex Construction Industry & Trade (Turkiye): $154.67m
- Galfar Engineering & Contracting (Oman): $154.80m
- The Arab Contractors (Egypt): $159.70m
- Yildizlar Grup (Turkiye): $172.03m
- Hindustan Construction Company (India): $182.15m
- Strabag Oman (Oman): $205.80m
- AZ Engineers (Oman): $231.19m
- Sarooj Construction Company (Oman): $232.33m
- The Egyptian Contracting Company (Egypt): $239.25m
- Al-Adrak Trading & Contracting (Oman): $389.93m
The project scope includes a drainage network, channel lining and bed protection works, pipelines and concrete box culverts.
MAFWR appointed Muscat-based ARQ and Partners Consulting Engineers to carry out the design works in July 2025. The main contract tender was subsequently issued in May 2026.
Dam pipeline
In parallel, Oman continues to advance a pipeline of major flood protection schemes across the sultanate.
In August, MAFWR received bids from nine contractors to construct the Wadi Rijma flood protection dam (R2A) in Liwa, North Batinah Governorate.
The Wadi Rijma dam project is one of four flood protection dams being planned in the sultanate to intercept floodwaters flowing from the northern Omani mountain range into the coastal plain.
In June 2025, MEED reported that the Islamic Development Bank (ISDB) had extended a $632m loan to the ministry to fund the construction of four major flood protection dams in the sultanate.
The four projects are:
- Wadi Al-Khoud Flood Protection Dam (AK01) in Seeb
- Wadi Rijma Flood Protection Dam (R2A) in Liwa
- Wadi Majlas Flood Protection Dam in Qurayat
- Wadi Ahin Flood Protection Dam in Saham North
In June, the ministry invited contractors to bid to construct the Wadi Al-Khoudh flood protection dam in Wilayat Al-Seeb, Muscat Governorate, reviving a project that had been on hold since 2019.
The design review and supervision services contracts have been awarded for both the Wadi Majlas Flood Protection Dam and Wadi Ahin Flood Protection Dam projects.
The contracts were awarded to local firms Al-Abraj Consulting Engineering and Atlas International Engineering Consultants, respectively. The main contract tenders for these projects are expected to be released by the end of the year.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19868201/main.jpg -
Oman tenders Thumrait Industrial City infrastructure22 September 2026

Oman’s Public Establishment for Industrial Estates (Madayn) has tendered an estimated RO15m ($39m) contract to develop infrastructure for Thumrait Industrial City.
The tender was issued on 14 September, with bids due by 12 November.
The scope covers site-wide utilities and services, including an internal road network, stormwater channels and culverts. It also includes installing sewerage and water networks, along with landscaping works.
In addition, Madayn intends to build plug-and-play industrial units and a facilities building.
The first phase of the development will cover about 120,000 square metres (sq m).
Thumrait Industrial City is located in Oman’s Dhofar Governorate and spans an area of more than four million sq m.
The project location is close to concession blocks, quarry sites and the Najd agricultural areas. It is positioned to attract industrial investments in sectors such as mining and minerals processing (including gypsum and cement), food production, and a range of light and general manufacturing activities.
In March, Madayn said it is preparing to invest more than RO245m ($637m) to upgrade and expand infrastructure across its industrial cities between 2026 and 2030, as part of efforts to attract new investment and advance economic diversification.
According to media reports, Madayn chief executive Dawood Bin Salim Al-Hadabi said the programme is part of an expanded, phased plan aligned with Oman Vision 2040 and the authority’s long-term Madayn 2040 strategy.
The objective is to deepen Oman’s industrial base and spread growth across the sultanate’s governorates.
Madayn said the pipeline comprises about 90 strategic projects to improve industrial-city infrastructure, extend serviced land and increase the overall ease of doing business for investors.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19866218/main.jpg
