Firms express interest in Lower Zakum project
8 May 2023

Contractors have expressed interest in bidding for the main contract for the first phase of the Lower Zakum Long-Term Development Plan (LTDP-1) project. The offshore arm of Abu Dhabi National Oil Company (Adnoc Offshore) owns the project.
The Lower Zakum LTDP-1 project is the larger of two projects that the offshore arm of Abu Dhabi National Oil Company has undertaken in line with its ambition to raise the oil and gas production potential of Abu Dhabi’s Lower Zakum offshore hydrocarbon concession over the long term.
Contractors submitted expression of interest (EoI) documents, as part of the prequalification process, for the LTDP-1 project by 27 April, according to sources.
Adnoc Offshore issued the EoI to contractors for the engineering, procurement and construction (EPC) tendering exercise for the Lower Zakum LTDP-1 “earlier in March”, sources previously told MEED, with contractors initially asked to respond by 10 April.
Lower Zakum oil production
The Lower Zakum hydrocarbons zone is 65 kilometres northwest of Abu Dhabi in the Gulf’s waters. Adnoc Offshore holds the majority 60 per cent stake in the Lower Zakum asset. Foreign partners include an Indian consortium of companies led by ONGC Videsh (10 per cent), Japan’s Inpex Corporation (10 per cent), China National Petroleum Corporation (10 per cent), Italy’s Eni (5 per cent) and France’s TotalEnergies (5 per cent).
Adnoc Offshore and its partners in the Lower Zakum concession intend to sustain oil production from the asset at its current level of 450,000 barrels a day (b/d) until 2025, and then increase output to 470,000 b/d. This target will be achieved through the Lower Zakum early production scheme 2 (EPS 2) and proved developed producing (PDP) project.
The larger, longer-term objective is to raise Lower Zakum’s oil production to 520,000 b/d by 2027 and maintain that level until 2034. This goal is to be accomplished through the LTDP-1 project.
Raising oil and gas production from the Lower Zakum asset is vital for Adnoc to achieve its accelerated target of increasing oil production capacity to 5 million b/d by 2027, and raising gas output potential by 3 billion cubic feet a day (cf/d) by the end of this decade.
Lower Zakum EPS 2/PDP project
Front-end engineering and design (feed) work is progressing on the Lower Zakum EPS 2/PDP project and is being performed by UK-headquartered Wood Group.
Adnoc Offshore, which, according to sources, awarded Wood the contract in November last year, expects feed work on the project to be completed by June.
The basic scope of work on the project involves the drilling of 17 additional producer and water injection wells on two new wellhead towers (WHTs) and the expansion of the gas compression capacity of the Zakum West Super Complex (ZWSC).
Integration of the Lower Zakum complexes with the onshore power grid at UZ AGI for electricity supply to the EPS 2/PDP project is also part of the scope.
Demolition of structures and as-built documentation and surveying are also included in the scope of work.
Adnoc Offshore solicited interest for the Lower Zakum EPS 2/PDP project EPC works in December last year. Contractors expressed interest in participating in the main contract tendering process in January, sources told MEED.
As per the schedule, Adnoc Offshore expects to issue the project’s main EPC tender in June, with the award of contracts to take place in September.
Lower Zakum LTDP-1 project
Feed work is progressing on the Lower Zakum LTDP-1 project and is being performed by France’s Technip Energies.
According to sources, Adnoc Offshore awarded Technip Energies the contract in November last year. The operator expects feed work on the project, which began in December, to be completed by January 2024.
Adnoc Offshore issued the expression of interest for the Lower Zakum LTDP-1 EPC tendering exercise “earlier in March”, with contractors asked to respond by 10 April.
The detailed scope of work on the Lower Zakum LTDP-1 project is as follows:
Topside facilities on G Island – Civil works on process facilities and associated buildings on the artificial greenfield G Island.
Process facilities include well pads, inlet and export reception, production separation, export pumps, gas compression, dehydration and lift, produced water treatment and disposal, vapour recovery units, water injection units, riser tower, flare towers, accommodation, drilling of high-pressure flare knock out drum, power distribution facility, substations and local equipment rooms.
Offshore WHTs and pipelines – Seven WHTs will be installed: six in the east area, and one in the AGI area. Five of the WHTs are to be 16-slot, while the two others are to be 9-slot.
Das Island Terminal, ZCSC and ZWSC – The five existing oil processing trains at the Lower Zakum offshore development are to be decommissioned in 2028, with the new configuration of the main processing plant at Das Island to be:
- Two existing trains with a processing/stabilisation capacity of 110,000 b/d each
- Three new trains with a processing/stabilisation capacity of 150,000 b/d
The scope of work also covers the installation of other structures such as:
- Three high-pressure separator trains
- High-pressure scrubber
- Three low-pressure separator trains
- Low-pressure scrubber
- Three atmospheric separator trains
- Four crude charge pumps
- Three crude charge heaters
- Three cold strippers integrated with a degassing vessel
- Six stripped crude product pumps
- Common ejector with a spare for three cold strippers
- Closed drain drum with transfer pump
- Blow case vessel
As per the schedule, Adnoc Offshore expects to issue the project’s main EPC tender in December, with the award of contracts to take place in March next year.
The operator expects the Lower Zakum LTDP-1 project to be commissioned by the end of 2027.
Exclusive from Meed
-
Egypt tenders 500MW solar IPP19 February 2026
-
Local contractor wins $143m Jeddah sewage contracts19 February 2026
-
Saudi Arabia prequalifies firms for gas transmission grids19 February 2026
-
Consultants bid for Abu Dhabi airport delivery partner role19 February 2026
-
Qatari firm wins Damascus airport MEP works19 February 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Egypt tenders 500MW solar IPP19 February 2026
Register for MEED’s 14-day trial access
Egyptian Electricity Transmission Company (EETC) has issued a request for qualifications for a 500MW solar photovoltaic (PV) independent power producer project in Egypt’s West of Nile area.
The bid submission deadline is 11 May.
The project is being supported by the European Bank for Reconstruction & Development and will be developed under a build-own-operate model.
Developers will be responsible for designing, financing, constructing, owning and operating the plant, with EETC acting as the offtaker for generated electricity.
US/India-based Synergy Consulting is acting as lead, financial and commercial advisor for this transaction.
The project forms part of Egypt’s strategy to strengthen long-term electricity supply and increase renewable generation capacity.
Egypt is targeting 42% renewable energy in its power mix by 2030. The country aims to raise this share to 65% by 2040.
EETC previously had plans to build a 200MW solar plant in a west Nile area but cancelled the tender for the project in 2020.
Egypt's power sector had its strongest year in over a decade last year, accounting for $4.2bn of total contract awards.
Despite dipping from the previous year, solar accounted for about $1bn of total awards.
In November, a consortium of local firms Hassan Allam Utilities and Infinity Power won contracts to develop two solar PV projects with a combined capacity of 1,200MW, supported by 720 megawatt-hours (MWh) of battery storage.
The UAE’s Amea Power and Japan’s Kyuden International Corporation also recently reached financial close on a $700m project comprising a 1,000MW solar plant and 600MWh battery system in Aswan.
The scheme is backed by a $570m debt package led by the International Finance Corporation and is expected to become Africa’s largest single-asset solar and storage facility when it enters operation later this year.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15701778/main.jpg -
Local contractor wins $143m Jeddah sewage contracts19 February 2026
Register for MEED’s 14-day trial access
Saudi Arabia’s National Water Company (NWC) has awarded two sewage network contracts worth a combined SR536.3m ($143m) to local contractor Civil Works Company.
The projects will be implemented over 32 months from site handover and will serve northern Jeddah districts.
The first contract, valued at SR278.5m ($74.3m), covers incomplete main lines and secondary sewage networks serving parts of the Al-Bashair, Al-Asala and Al-Falah neighbourhoods.
The scope includes pipelines ranging from 200mm to 800mm in diameter with a total length of about 54.8 kilometres (km).
The package also includes sewage tunnels with diameters ranging from 600mm to 1,800mm and a total length of approximately 6.5km. Works will also serve the Taybah, Abhar Al-Shamaliyah and Al-Hamdaniyah districts.
The second contract is valued at SR257.8m ($68.8m). It covers the implementation of main lines and sub-networks to serve part of the Al-Hamdaniya neighbourhood.
The works include pipelines ranging from 200mm to 1,500mm in diameter with a total length of about 78.5km. The scope also includes horizontal drilling works for sewage tunnels with diameters from 1,200mm to 1,400mm and a total length of approximately 205 metres.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15699620/main.jpg -
Saudi Arabia prequalifies firms for gas transmission grids19 February 2026
Register for MEED’s 14-day trial access
Saudi Arabia's Energy Ministry has prequalified companies to develop natural gas distribution networks in five industrial cities in the kingdom on a build-own-operate (BOO) basis.
The industrial zones earmarked are Al-Kharj Industrial City; Sudair City for Industry and Business; and the First, Second and Third Industrial Cities in Jeddah, the Energy Ministry said in a statement.
The contractors prequalified to bid for the natural gas transmission grids BOO scheme include eight standalone firms and seven consortiums:
- East Gas (Egypt)
- Natural Gas Distribution Company (Saudi Arabia)
- Egyptian Kuwaiti Advanced Operation and Maintenance (Saudi Arabia)
- Modern Gas (Egypt)
- Saab Energy Solutions (Saudi Arabia)
- Sergas Contracting (Saudi Arabia)
- Bharat Petroleum Corporation (India)
- UniGas Arabia (Saudi Arabia)
- Best Gas Carrier / Khazeen / Mubadra (Saudi Arabia)
- Al Sharif Contracting (Saudi Arabia) / Anton Oilfield Services Group (China) China Oil and Gas Group
- Hulul (owned by Saudi Arabia’s National Gas and Industrialization Company) /Al-Fanar Gas Group (UAE)
- Indraprastha Gas (India) / Masah Contracting (Saudi Arabia)
- Expertise Contracting / PGL Pipelines (UK)
- National Gas Company (Egypt) / Egypt Gas (Egypt)
- Taqa Arabia (Egypt) / Taqa Group (UAE)
The Energy Ministry has set a deadline of 23 April for these prequalified contractors to submit technical bids.
The ministry added in its statement that it has identified a total of 36 industrial cities in Saudi Arabia for gas infrastructure development.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15699582/main0334.png -
Consultants bid for Abu Dhabi airport delivery partner role19 February 2026

Abu Dhabi Airports Company (Adac) received bids from major international firms on 19 January for a contract covering the delivery partner role for the upcoming packages at Zayed International airport (AUH).
The project is part of the AUH satellite terminal programme, estimated at AED10bn ($2.7bn).
MEED understands that the following firms have submitted bids:
- Aecom (US)
- AtkinsRealis/Egis/Mace (Canada/France/UK)
- Bechtel (US)
- Hill International (US)
- Jacobs / Surbana Jurong (US/Singapore)
- Parsons Corporation / Arup (US/UK)
The plan includes a new satellite concourse east of Terminal A, linked by an underground tunnel housing both an automated people mover and a baggage handling system.
It also includes apron stands, taxi lanes and taxiways, East Midfield landside access and utilities, additional bus gates and the reconfiguration of the North and South aprons and Apron 6.
The latest tendering activity follows the start of construction works on the East Midfield cargo terminal located at AUH, as MEED reported in December 2024.
Local firm Raq Contracting is undertaking the construction works on this project.
The terminal will cover an area of 90,000 square metres and will have the capacity to handle about 1.5 million tonnes of cargo annually.
The project is part of a broader plan to enhance the new airport's profile.
Abu Dhabi opened a new passenger terminal in November 2023 as part of the airport’s plan to increase its passenger traffic in line with the UAE’s wider growth plans, along with projects such as the rail network being built by Etihad Rail.
In May 2024, MEED reported that AUH's new Terminal A could connect to the Etihad Rail network in the future, as part of its growth and interconnectivity plans.
Plans are in progress to link the new terminal at AUH to the UAE’s growing rail network, according to the CEO of Adac.
Speaking to UK analytic firm GlobalData's Airport Technology during a tour of the new Terminal A at AUH, CEO Elena Sorlini said that Abu Dhabi Aviation is planning to improve the transport links to the site.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15698728/main.png -
Qatari firm wins Damascus airport MEP works19 February 2026
Qatari firm Elegancia MEP, which is owned by local investment firm Estithmar Holding, has won a contract to undertake the mechanical, electrical and plumbing (MEP) and extra-low-voltage (ELV) systems works for the Damascus International airport Terminal 2 project.
In a statement, Elegancia MEP said that its scope covers the execution of MEP and ELV systems works to support terminal operations, passenger facilities, safety systems and overall operational efficiency.
The MEP works for the airport project include electrical installations; heating, ventilation and air conditioning (HVAC) systems; safety and security systems; firefighting systems; surveillance and monitoring systems; control systems; and plumbing works.
The contract award follows the signing of the final concession contracts in November last year by Qatar’s UCC-led consortium to redevelop Damascus airport, formalising the prior memorandum of understanding (MoU) inked in August 2025 with Syria’s General Authority of Civil Aviation.
The contract will see the consortium redevelop and expand the airport in several phases under a build-operate-transfer framework, with a view to raising total capacity to 31 million passengers annually upon the completion of all phases.
The agreement is valued at an estimated $4bn and includes plans for the overhaul of all existing terminals, the construction of other passenger facilities and 500 kilometres of access roads, as well as the development of a commercial complex centred around a five-star hotel.
The signing of the final concession contracts followed UCC Holding’s provisional signing in October last year of five consultancy and design agreements for planned work on the project.
The earlier MoU designated UCC Holding as the primary developer through its investment arm UCC Concessions Investment, alongside three Turkish partners – Cengiz, Kalyon and TAV – and the US-based Assets Investments USA.
US-based firm Synergy Consulting is the financial adviser for the consortium.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15698666/main.png

