Firms express interest in Lower Zakum project
8 May 2023

Contractors have expressed interest in bidding for the main contract for the first phase of the Lower Zakum Long-Term Development Plan (LTDP-1) project. The offshore arm of Abu Dhabi National Oil Company (Adnoc Offshore) owns the project.
The Lower Zakum LTDP-1 project is the larger of two projects that the offshore arm of Abu Dhabi National Oil Company has undertaken in line with its ambition to raise the oil and gas production potential of Abu Dhabi’s Lower Zakum offshore hydrocarbon concession over the long term.
Contractors submitted expression of interest (EoI) documents, as part of the prequalification process, for the LTDP-1 project by 27 April, according to sources.
Adnoc Offshore issued the EoI to contractors for the engineering, procurement and construction (EPC) tendering exercise for the Lower Zakum LTDP-1 “earlier in March”, sources previously told MEED, with contractors initially asked to respond by 10 April.
Lower Zakum oil production
The Lower Zakum hydrocarbons zone is 65 kilometres northwest of Abu Dhabi in the Gulf’s waters. Adnoc Offshore holds the majority 60 per cent stake in the Lower Zakum asset. Foreign partners include an Indian consortium of companies led by ONGC Videsh (10 per cent), Japan’s Inpex Corporation (10 per cent), China National Petroleum Corporation (10 per cent), Italy’s Eni (5 per cent) and France’s TotalEnergies (5 per cent).
Adnoc Offshore and its partners in the Lower Zakum concession intend to sustain oil production from the asset at its current level of 450,000 barrels a day (b/d) until 2025, and then increase output to 470,000 b/d. This target will be achieved through the Lower Zakum early production scheme 2 (EPS 2) and proved developed producing (PDP) project.
The larger, longer-term objective is to raise Lower Zakum’s oil production to 520,000 b/d by 2027 and maintain that level until 2034. This goal is to be accomplished through the LTDP-1 project.
Raising oil and gas production from the Lower Zakum asset is vital for Adnoc to achieve its accelerated target of increasing oil production capacity to 5 million b/d by 2027, and raising gas output potential by 3 billion cubic feet a day (cf/d) by the end of this decade.
Lower Zakum EPS 2/PDP project
Front-end engineering and design (feed) work is progressing on the Lower Zakum EPS 2/PDP project and is being performed by UK-headquartered Wood Group.
Adnoc Offshore, which, according to sources, awarded Wood the contract in November last year, expects feed work on the project to be completed by June.
The basic scope of work on the project involves the drilling of 17 additional producer and water injection wells on two new wellhead towers (WHTs) and the expansion of the gas compression capacity of the Zakum West Super Complex (ZWSC).
Integration of the Lower Zakum complexes with the onshore power grid at UZ AGI for electricity supply to the EPS 2/PDP project is also part of the scope.
Demolition of structures and as-built documentation and surveying are also included in the scope of work.
Adnoc Offshore solicited interest for the Lower Zakum EPS 2/PDP project EPC works in December last year. Contractors expressed interest in participating in the main contract tendering process in January, sources told MEED.
As per the schedule, Adnoc Offshore expects to issue the project’s main EPC tender in June, with the award of contracts to take place in September.
Lower Zakum LTDP-1 project
Feed work is progressing on the Lower Zakum LTDP-1 project and is being performed by France’s Technip Energies.
According to sources, Adnoc Offshore awarded Technip Energies the contract in November last year. The operator expects feed work on the project, which began in December, to be completed by January 2024.
Adnoc Offshore issued the expression of interest for the Lower Zakum LTDP-1 EPC tendering exercise “earlier in March”, with contractors asked to respond by 10 April.
The detailed scope of work on the Lower Zakum LTDP-1 project is as follows:
Topside facilities on G Island – Civil works on process facilities and associated buildings on the artificial greenfield G Island.
Process facilities include well pads, inlet and export reception, production separation, export pumps, gas compression, dehydration and lift, produced water treatment and disposal, vapour recovery units, water injection units, riser tower, flare towers, accommodation, drilling of high-pressure flare knock out drum, power distribution facility, substations and local equipment rooms.
Offshore WHTs and pipelines – Seven WHTs will be installed: six in the east area, and one in the AGI area. Five of the WHTs are to be 16-slot, while the two others are to be 9-slot.
Das Island Terminal, ZCSC and ZWSC – The five existing oil processing trains at the Lower Zakum offshore development are to be decommissioned in 2028, with the new configuration of the main processing plant at Das Island to be:
- Two existing trains with a processing/stabilisation capacity of 110,000 b/d each
- Three new trains with a processing/stabilisation capacity of 150,000 b/d
The scope of work also covers the installation of other structures such as:
- Three high-pressure separator trains
- High-pressure scrubber
- Three low-pressure separator trains
- Low-pressure scrubber
- Three atmospheric separator trains
- Four crude charge pumps
- Three crude charge heaters
- Three cold strippers integrated with a degassing vessel
- Six stripped crude product pumps
- Common ejector with a spare for three cold strippers
- Closed drain drum with transfer pump
- Blow case vessel
As per the schedule, Adnoc Offshore expects to issue the project’s main EPC tender in December, with the award of contracts to take place in March next year.
The operator expects the Lower Zakum LTDP-1 project to be commissioned by the end of 2027.
Exclusive from Meed
-
Arada completes Sokoon buildings construction26 March 2026
-
Local contractor wins Medina substation contract26 March 2026
-
Neom terminates $5bn Trojena dams contract with WeBuild26 March 2026
-
Iraq gas field project disrupted by regional conflict26 March 2026
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Arada completes Sokoon buildings construction26 March 2026
Sharjah-based private real estate developer Arada has announced the completion of five additional buildings in the Naseej District of its Aljada development.
Kuwaiti firm Mohammad Abdulmohsen Al-Kharafi & Sons secured the construction contract for the Sokoon buildings in 2023, replacing Airolink Building Contracting as the project’s main contractor.
The first four Sokoon buildings were completed in December 2023.
In April last year, Arada also announced the completion of all eight Tiraz buildings in the Naseej District. The Tiraz buildings comprise 920 homes, including studios, one-bedroom and two-bedroom apartments.
With the completion of the five Sokoon buildings, Aljada’s total number of completed residential units has risen to more than 8,200.
Spanning 2.2 square kilometres, Aljada features residential districts, retail spaces, educational institutions, healthcare services and other facilities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16141382/main.png -
Local contractor wins Medina substation contract26 March 2026
Danway Saudi Arabia has won a contract with National Grid SA to construct a new 110/13.8kV substation in Medina.
The contract is valued at more than SR100m ($26.7m) and covers the construction of the King Abdulaziz Road substation, including design, engineering, supply, installation, testing and commissioning.
The project is expected to take approximately 23 months to complete.
Key components include 110kV gas-insulated switchgear (GIS), 50/67MVA 110/13.8kV power transformers and 13.8kV switchgear.
National Grid SA is a wholly owned subsidiary of Saudi Energy, formerly Saudi Electricity Company. It owns and operates the kingdom’s high-voltage transmission network and is responsible for grid planning, interconnection and system reliability.
The operator recently appointed another local firm, Nesma Infrastructure & Technology, as the contractor for the construction of two 380kV double-circuit overhead transmission lines in Riyadh, connecting an existing substation to a wind power substation, referred to as Samha Wind BSP.
As MEED understands, National Grid SA is also due to begin construction on the replacement of 132kV oil-filled underground cable circuits between several substations in the Central Operation Area in Murabba in Riyadh.
Riyadh-based Keir International is the engineering, procurement and construction contractor for the project.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16139578/main.jpg -
Neom terminates $5bn Trojena dams contract with WeBuild26 March 2026
Register for MEED’s 14-day trial access
Neom has terminated its contract with Italian contractor Webuild for the construction of three dams feeding a freshwater lake, as well as ‘The Bow’ architectural structure at Trojena in northwest Saudi Arabia.
In a statement posted on its website, Webuild said: “The termination will become effective on 29 March. As of that date, the works are approximately 30% complete, with a remaining project backlog for Webuild of approximately €2.8bn ($3.2bn).”
Neom awarded Webuild a SR20bn ($5bn) contract to build the dams in late 2023, which MEED exclusively reported at the time.
The termination is the latest in a series of high-profile contract cancellations by Neom in recent weeks. Earlier this week, Neom terminated its contract with Malaysian contractor Eversendai Corporation for the steel structural works on the Ski Village project in Trojena.
In a statement published on its website, Eversendai said it had received an official notice that the termination would take effect from 26 March.
In January this year, Saudi Arabia confirmed the postponement of the 2029 Asian Winter Games, which were scheduled to be held at Trojena. Trojena was chosen to host the event in October 2022.
Neom has also cancelled contracts for the construction of the tunnel sections of The Line in northwest Saudi Arabia.
In a stock exchange filing dated 13 March, South Korean contractor Hyundai E&C said Neom cancelled its contract on 29 December last year.
Hyundai E&C was executing the drill-and-blast section of The Line’s tunnels in a joint venture with Greece’s Archirodon and South Korean counterpart Samsung C&T.
These developments follow a wider strategic review of Neom last year, as Saudi Arabia reassesses priorities under its Vision 2030 programme.
With tighter liquidity at the sovereign wealth fund level, resources are being redirected towards projects linked to the Fifa World Cup 2034, Expo 2030, and essential housing, healthcare and education initiatives.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16140200/main.jpg -
Iraq gas field project disrupted by regional conflict26 March 2026

Register for MEED’s 14-day trial access
Progress on Iraq’s project to develop the strategically important Akkas gas field has been disrupted by security issues related to the US and Israel’s ongoing war with Iran, according to industry sources.
Work activity at the project site has been significantly reduced due to security concerns, and the project is now expected to take longer to complete.
Iraq held a ceremony in January this year to mark the restart of drilling operations at the site as part of the field development project.
In July last year, Iraq’s Oil Ministry announced signing a contract with the US-based oil field services provider SLB to develop production at Iraq’s Akkas gas field.
Under the terms of the deal, SLB will drill wells at the Akkas field, aiming to initially raise production to 100 million cubic feet a day (cf/d).
Many of SLB’s non-Iraqi employees have now been evacuated from the country.
Over the long term, Iraq is targeting gas production of 400 million cf/d from the field.
The contract with SLB replaces a previous deal with Ukraine-based Ukrzemresurs, which has been terminated.
It also covers the construction of surface infrastructure and pipelines to connect Akkas to central processing units.
The gas produced at Akkas will be used to fuel the Anbar combined-cycle power plant, which is under construction by the Electricity Ministry.
Akkas gas field development
The Akkas gas field, located in Anbar province in western Iraq, has 5.6 trillion cubic feet of proven reserves. The field was discovered in 1992 and began production in 1993.
Since then, Iraq’s plans to develop the Akkas gas field to its full potential have experienced several setbacks.
In April last year, the Iraqi Oil Ministry signed an agreement with Ukrzemresurs to develop the field.
At the time, the Oil Ministry said that the partners were aiming to produce 100 million cf/d in the first two years, as per the agreement, with output targeted to increase to 400 million cf/d within four years.
Prior to Ukrzemresurs, South Korean company Kogas was responsible for developing the field.
Rights to the field were originally awarded to a consortium of Kogas and Kazakhstan’s state-owned oil company KazMunaiGas (KMG) in the third licensing round, which was launched in October 2011.
KMG pulled out, leaving Kogas as the sole investor and operator on new contract terms.
When the deal with Ukrzemresurs was originally announced last year, it was negatively received by some Iraqi politicians, with the Oil and Gas Committee in Iraq’s parliament rejecting the contract signing.
At the time, Ali Al-Mashkour, a member of the Oil and Gas Committee, told Iraq’s Shafaq News Agency: “This contract involves a great waste of Iraq’s wealth, and there will be a waste of Iraq’s oil, and this confirms that Iraq is once again failing to choose reputable companies to work with in the most important economic field in the country.”
He added: “We will work to uncover and expose the suspicions in this contract during the next stage, especially since this contract was made by some representatives for specific interests, which we will reveal soon with evidence.”
Plans to sign the contract to develop the Akkas gas field with a Ukrainian company were first announced by the Oil Ministry in September 2023, but Ukrzemresurs was not named at the time.
Iraq’s government is trying to transform the country into a gas-exporting nation. Currently, Iraq is reliant on Iran for gas imports.
Both Saudi Arabia and the US, which are looking to contain Iranian influence in the region, have been supporting Iraq in developing its non-associated gas fields as this will reduce Iraq’s economic reliance on Iran.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16138892/main.png -
Dubai seeks contractors for Nadd Hessa stormwater project26 March 2026
Dubai Municipality has invited contractors to prequalify for a contract to build a sewerage and stormwater system in the Nadd Hessa area.
The project is being procured through the Sewerage and Recycled Water Projects Department.
The submission deadline is 2 April.
Nadd Hessa is an emerging development area, located between Dubai Silicon Oasis and Academic City along the E311 corridor.
It has been earmarked for future residential expansion, with enabling infrastructure now being tendered to support planned housing and community developments in the area.
The scheme, known as DS 328/1–C1, covers the construction of sewerage and stormwater infrastructure, including approximately 12.4 kilometres of sewerage lines with diameters of up to 400 millimetres.
The scope also includes about 14km of stormwater lines with diameters of up to 1,000 millimetres.
In addition, the project involves around 500 metres of microtunnelling works for both sewerage and stormwater networks.
The municipality is currently prequalifying contractors for several upcoming water projects, including the expansion of the Jebel Ali sewage treatment plant (STP) phases one and two.
The upgraded facility will be capable of treating an additional sewage flow of 100,000 cubic metres a day (cm/d).
Bid submissions for this project are also due by 2 April.
In addition, the authority is planning a broader review of Dubai’s water and wastewater infrastructure to support future population growth, including identifying locations for future infrastructure.
Two separate consultancy tenders were issued in March.
One involves a study to develop a sustainable urban drainage systems strategy across the emirate. The other covers a review of the emirate’s sewage treatment and recycled water distribution strategy.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16138660/main.jpg

