Firms express interest in Lower Zakum project
8 May 2023

Contractors have expressed interest in bidding for the main contract for the first phase of the Lower Zakum Long-Term Development Plan (LTDP-1) project. The offshore arm of Abu Dhabi National Oil Company (Adnoc Offshore) owns the project.
The Lower Zakum LTDP-1 project is the larger of two projects that the offshore arm of Abu Dhabi National Oil Company has undertaken in line with its ambition to raise the oil and gas production potential of Abu Dhabi’s Lower Zakum offshore hydrocarbon concession over the long term.
Contractors submitted expression of interest (EoI) documents, as part of the prequalification process, for the LTDP-1 project by 27 April, according to sources.
Adnoc Offshore issued the EoI to contractors for the engineering, procurement and construction (EPC) tendering exercise for the Lower Zakum LTDP-1 “earlier in March”, sources previously told MEED, with contractors initially asked to respond by 10 April.
Lower Zakum oil production
The Lower Zakum hydrocarbons zone is 65 kilometres northwest of Abu Dhabi in the Gulf’s waters. Adnoc Offshore holds the majority 60 per cent stake in the Lower Zakum asset. Foreign partners include an Indian consortium of companies led by ONGC Videsh (10 per cent), Japan’s Inpex Corporation (10 per cent), China National Petroleum Corporation (10 per cent), Italy’s Eni (5 per cent) and France’s TotalEnergies (5 per cent).
Adnoc Offshore and its partners in the Lower Zakum concession intend to sustain oil production from the asset at its current level of 450,000 barrels a day (b/d) until 2025, and then increase output to 470,000 b/d. This target will be achieved through the Lower Zakum early production scheme 2 (EPS 2) and proved developed producing (PDP) project.
The larger, longer-term objective is to raise Lower Zakum’s oil production to 520,000 b/d by 2027 and maintain that level until 2034. This goal is to be accomplished through the LTDP-1 project.
Raising oil and gas production from the Lower Zakum asset is vital for Adnoc to achieve its accelerated target of increasing oil production capacity to 5 million b/d by 2027, and raising gas output potential by 3 billion cubic feet a day (cf/d) by the end of this decade.
Lower Zakum EPS 2/PDP project
Front-end engineering and design (feed) work is progressing on the Lower Zakum EPS 2/PDP project and is being performed by UK-headquartered Wood Group.
Adnoc Offshore, which, according to sources, awarded Wood the contract in November last year, expects feed work on the project to be completed by June.
The basic scope of work on the project involves the drilling of 17 additional producer and water injection wells on two new wellhead towers (WHTs) and the expansion of the gas compression capacity of the Zakum West Super Complex (ZWSC).
Integration of the Lower Zakum complexes with the onshore power grid at UZ AGI for electricity supply to the EPS 2/PDP project is also part of the scope.
Demolition of structures and as-built documentation and surveying are also included in the scope of work.
Adnoc Offshore solicited interest for the Lower Zakum EPS 2/PDP project EPC works in December last year. Contractors expressed interest in participating in the main contract tendering process in January, sources told MEED.
As per the schedule, Adnoc Offshore expects to issue the project’s main EPC tender in June, with the award of contracts to take place in September.
Lower Zakum LTDP-1 project
Feed work is progressing on the Lower Zakum LTDP-1 project and is being performed by France’s Technip Energies.
According to sources, Adnoc Offshore awarded Technip Energies the contract in November last year. The operator expects feed work on the project, which began in December, to be completed by January 2024.
Adnoc Offshore issued the expression of interest for the Lower Zakum LTDP-1 EPC tendering exercise “earlier in March”, with contractors asked to respond by 10 April.
The detailed scope of work on the Lower Zakum LTDP-1 project is as follows:
Topside facilities on G Island – Civil works on process facilities and associated buildings on the artificial greenfield G Island.
Process facilities include well pads, inlet and export reception, production separation, export pumps, gas compression, dehydration and lift, produced water treatment and disposal, vapour recovery units, water injection units, riser tower, flare towers, accommodation, drilling of high-pressure flare knock out drum, power distribution facility, substations and local equipment rooms.
Offshore WHTs and pipelines – Seven WHTs will be installed: six in the east area, and one in the AGI area. Five of the WHTs are to be 16-slot, while the two others are to be 9-slot.
Das Island Terminal, ZCSC and ZWSC – The five existing oil processing trains at the Lower Zakum offshore development are to be decommissioned in 2028, with the new configuration of the main processing plant at Das Island to be:
- Two existing trains with a processing/stabilisation capacity of 110,000 b/d each
- Three new trains with a processing/stabilisation capacity of 150,000 b/d
The scope of work also covers the installation of other structures such as:
- Three high-pressure separator trains
- High-pressure scrubber
- Three low-pressure separator trains
- Low-pressure scrubber
- Three atmospheric separator trains
- Four crude charge pumps
- Three crude charge heaters
- Three cold strippers integrated with a degassing vessel
- Six stripped crude product pumps
- Common ejector with a spare for three cold strippers
- Closed drain drum with transfer pump
- Blow case vessel
As per the schedule, Adnoc Offshore expects to issue the project’s main EPC tender in December, with the award of contracts to take place in March next year.
The operator expects the Lower Zakum LTDP-1 project to be commissioned by the end of 2027.
Exclusive from Meed
-
UAE firm withdraws Yemen solar operations26 January 2026
-
Saudi Arabia postpones 2029 Trojena Asian Winter Games26 January 2026
-
McDermott wins $942m Adnoc Offshore field expansion contract23 January 2026
-
Oman signs PPAs for Misfah and Duqm power plants23 January 2026
-
Chiyoda wins feed contract for North Field West LNG project23 January 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
UAE firm withdraws Yemen solar operations26 January 2026

UAE-based Global South Utilities (GSU) has completed the handover of the Aden and Shabwa solar power plants to Yemen’s Public Electricity Corporation, following an official request by Yemeni authorities for the withdrawal of all UAE companies from the country.
The move comes amid Yemen’s ongoing political fragmentation and security challenges, which have complicated foreign commercial and infrastructure operations in the country.
In a letter dated 22 January 2026, GSU said it had evacuated all operations and maintenance teams from the 120MW Aden solar plant and the 53MW Shabwa solar plant.
Both facilities were handed over fully operational and placed under the authority of the state-owned utility.
GSU operates solar power plants in Yemen with a combined capacity of 173MW. The company said the withdrawal of its technical teams was carried out to ensure personnel safety and to enable a structured and responsible transfer of assets.
“Global South Utilities did not suspend operations unilaterally or abruptly,” the company said. “Both power plants were handed over while operating at full technical capacity, under a formal handover process.”
GSU added that continuing to operate large-scale power facilities without specialised technical teams on the ground would pose operational risks and would not meet internationally recognised standards for energy facility operations.
Several projects are at advanced stages of development and have been paused following the company’s exit from the Yemeni market, including:
- Al-Mokha – phase 2 (40MW): 85% complete
- Al-Khokha (10MW): 80% complete
- Hays (10MW): 75% complete
- Socotra (10MW): 35% complete (civil works and procurement)
- Aden expansion (120MW): 35% complete (civil works and procurement)
In November, GSU announced $1bn-worth of new energy projects in Yemen to support the rebuilding of the country’s electricity sector.
The programme was expected to be delivered through solar and wind energy projects, battery energy storage systems and the development of distribution networks.
According to GSU, its $1bn energy project portfolio in Yemen covers 13 projects across six governorates, with a combined capacity exceeding 1,000MW.
In August, GSU began work on a 120MW expansion of the Aden solar photovoltaic plant, doubling its capacity to 240MW. The plant began operations last year with a 120MW first phase.
At the time, the company said phase two would begin commercial operations in 2026.
READ THE JANUARY 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia courts real estate investment; EVs and battery production are key regional tech themes; Muscat holds a steady growth course despite headwinds
Distributed to senior decision-makers in the region and around the world, the January 2026 edition of MEED Business Review includes:
> AGENDA: Saudi real estate to surge in 2026> BATTERIES: Batteries shape the region's energy future> INTERVIEW: Tabreed finishes the year on a high> CONTRACTORS: Managing risk in the GCC construction market> ECONOMIC ACTIVITY INDEX: UAE and Qatar emerge as markets to watch> AIRSHOW: Top deals signed at Dubai Airshow 2025> MARKET FOCUS: Oman steadies growth with strategic restraintTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15511888/main.jpg -
Saudi Arabia postpones 2029 Trojena Asian Winter Games26 January 2026
Register for MEED’s 14-day trial access
Saudi Arabia has confirmed the postponement of the 2029 Asian Winter Games, which were scheduled to be held at the Trojena mountain destination in Neom, in the northwest of the kingdom.
The confirmation came on 25 January, when the Olympic Council of Asia (OCA) and the Saudi Olympic & Paralympic Committee (SOPC) released a joint statement saying that they have agreed to indefinitely postpone the event.
The OCA and SOPC have yet to announce a revised timeline or confirm whether another country will now host the event.
In October 2022, Trojena was chosen to host the Asian Winter Games in 2029, as MEED previously reported.
Construction is progressing on the Trojena Ski Village project; however, the overall infrastructure required for the venue to be ready remains behind schedule.
The most recent edition of the Asian Winter Games was held in February last year in the city of Harbin, China.
Japan held the first edition in 1986 and went on to host four of the previous editions of the event.
China has hosted three editions, while South Korea and Kazakhstan have each hosted the games once.
South Korea staged the Winter Youth Olympics in 2024, using mostly the same venues built for the 2018 Winter Olympics in the eastern province of Gangwon.
In August last year, MEED reported that high-level discussions had started regarding changing the 2029 Asian Winter Games venue, possibly from Saudi Arabia to South Korea.
According to reports in South Korean media, citing a senior Korean Sport & Olympic Committee official, the OCA had contacted the Korean Sport & Olympic Committee about the possibility of hosting the event.
The report added that the meeting was followed by an official letter sent by the OCA to South Korea.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15511718/main.jpg -
McDermott wins $942m Adnoc Offshore field expansion contract23 January 2026
Adnoc Offshore, a subsidiary of Abu Dhabi National Oil Company (Adnoc Group), has awarded US-based contractor McDermott International a contract valued at $942m to perform engineering, procurement and construction (EPC) works on a project to increase the oil production capacity of the Nasr offshore field to 115,000 barrels a day (b/d).
The Nasr offshore oil field is located approximately 130 kilometres (km) northwest of Abu Dhabi. The Nasr-115 expansion project is a critical component of the overall Nasr phase two full field development project that is expected to increase oil production capacity to 115,000 b/d by 2027.
In a statement, McDermott said the scope of work on its contract covers comprehensive engineering, procurement, construction and installation services for two topside structures, one new manifold tower, one jacket, one bridge and all associated pipelines, high-speed subsea cables and brownfield modifications.
“This is the latest milestone in Adnoc’s strategy to deliver an oil production capacity of 5 million barrels a day by 2027, as we help responsibly meet the world’s long-term energy demand,” .
More than 55% of the investment value will flow back into the UAE economy through Adnoc’s In-Country Value programme, the Abu Dhabi energy giant added.
Sarb deep gas development project
Prior to winning the main EPC contract for the Nasr-115 project from Adnoc Offshore, McDermott also won a key contract for a project covering deep gas development at the Satah Al-Razboot (Sarb) oil and gas field, located 120km offshore Abu Dhabi.
Adnoc achieved the financial investment decision on the Sarb project earlier in January. The company said it intends to produce 200 million standard cubic feet a day of gas from the Sarb field through this project before the end of the decade, “enough energy to power more than 300,000 homes daily”.
The value of the EPC contract won by McDermott is estimated to be worth about $500m, sources told MEED.
The basic scope of work on the Sarb deep gas development project covers EPC of a large offshore wellhead tower with four gas production wells, which will be connected to Das Island, where the gas produced will be tied into Adnoc Gas facilities for upstream treatment, “maximising the integration with other Adnoc projects”.
The work scope also includes installation of pipelines and intra-field lines connecting the Sarb field development to gas processing facilities at Das Island.
READ THE JANUARY 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia courts real estate investment; EVs and battery production are key regional tech themes; Muscat holds a steady growth course despite headwinds
Distributed to senior decision-makers in the region and around the world, the January 2026 edition of MEED Business Review includes:
> AGENDA: Saudi real estate to surge in 2026> BATTERIES: Batteries shape the region's energy future> INTERVIEW: Tabreed finishes the year on a high> CONTRACTORS: Managing risk in the GCC construction market> ECONOMIC ACTIVITY INDEX: UAE and Qatar emerge as markets to watch> AIRSHOW: Top deals signed at Dubai Airshow 2025> MARKET FOCUS: Oman steadies growth with strategic restraintTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15501962/main1449.jpg -
Oman signs PPAs for Misfah and Duqm power plants23 January 2026
Register for MEED’s 14-day trial access
Oman's Nama Power & Water Procurement (Nama PWP) has signed power purchase agreements (PPAs) for the development and operation of the Misfah and Duqm gas-fired independent power projects (IPPs).
The two combined cycle gas turbine plants have been awarded to a consortium comprising Korea Western Power (Kowepo), Qatar’s Nebras Power, the UAE’s Etihad Water & Electricity (EtihadWE) and Oman’s Bhawan Infrastructure Services.
The Misfah IPP will be led by Nebras Power and located in Wilayat Bousher in Muscat Governorate, with a planned capacity of 1,600MW.
The Duqm IPP will be led by Kowepo and located in Wilayat Duqm in Al-Wusta Governorate, with a capacity of 800MW.
According to Nama PWP, the total investment for the two projects is estimated at approximately RO1bn ($2.6bn)
MEED reported in October that Nama PWP had received three bids for the development and operation of the gas-fired IPPs.
The other bids included a consortium comprising China’s Shenzhen Energy Group and Oman National Engineering & Investment Company, and a lone bid from Saudi Arabia’s Acwa Power.
Synergy Consulting is the financial advisor and lead advisor to Nama PWP for these projects.
In November, Oman’s OQ Gas Networks received final investment approval to proceed with gas supply connections for the facilities.
The Misfah IPP will receive 8.5 million cubic metres a day (cm/d) of natural gas. The Duqm IPP will be supplied with 4.5 million cm/d of natural gas.
Both plants are scheduled to deliver early power by April 2028 and to reach full commercial operations in 2029.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15499940/main.jpg -
Chiyoda wins feed contract for North Field West LNG project23 January 2026
Register for MEED’s 14-day trial access
QatarEnergy has awarded Japan-based Chiyoda Corporation a contract for front-end engineering and design (feed) work on its North Field West liquefied natural gas (LNG) project.
The North Field West project is the next phase of QatarEnergy’s North Field LNG expansion programme. The scheme will further increase Qatar’s overall LNG production capacity to 142 million tonnes a year (t/y) upon commissioning, which is scheduled for 2030.
Chiyoda said in a statement that the feed contract for the project was awarded by QatarEnergy’s subsidiary QatarEnergy LNG, which is overseeing the North Field LNG expansion programme on behalf of its parent company. The Japanese firm has yet to provide further details about its contract.
QatarEnergy announced the North Field West project, which is the third phase of its estimated $40bn North Field LNG expansion programme, in February 2024.
The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. The new project will draw feedstock for LNG production from the western zone of the North Field offshore gas reserve.
MEED recently reported that QatarEnergy had awarded a contract for the engineering, procurement, construction and installation (EPCI) of four offshore jackets and associated units at the North Field gas reserve in Qatari waters, as part of the wider North Field West project.
US-headquartered McDermott International won the contract for the offshore jackets package, which is estimated to be valued at around $200m, according to sources. The new jackets to be installed will boost gas production from the North Field reservoirs, providing additional gas feedstock for the North Field West LNG project.
Major projects under execution
QatarEnergy is understood to have spent nearly $30bn on the first two phases of its North Field expansion programme – North Field East and North Field South – which will raise its LNG production capacity from 77.5 million t/y to 126 million t/y by 2028. Engineering, procurement and construction (EPC) works on both projects are progressing.
QatarEnergy awarded the main EPC contracts for the North Field East project in 2021. The project aimed to boost LNG output to 110 million t/y by 2025. The $13bn EPC package – covering the EPCI of four LNG trains, each with a capacity of 8 million t/y – was awarded in February 2021 to a consortium of Chiyoda and France’s Technip Energies.
In May 2023, QatarEnergy awarded the $10bn main EPC contract for the North Field South project to a consortium of Technip Energies and Lebanon-based Consolidated Contractors Company.
The contract includes two large LNG trains, each with a capacity of 7.8 million t/y.
Once fully operational, the first two phases of the North Field expansion will add 48 million t/y of supply to the global LNG market.
ALSO READ: QatarEnergy achieves strategic oil and gas goals in 2025
https://image.digitalinsightresearch.in/uploads/NewsArticle/15493998/main.jpg
