Firms express interest in Lower Zakum project
8 May 2023

Contractors have expressed interest in bidding for the main contract for the first phase of the Lower Zakum Long-Term Development Plan (LTDP-1) project. The offshore arm of Abu Dhabi National Oil Company (Adnoc Offshore) owns the project.
The Lower Zakum LTDP-1 project is the larger of two projects that the offshore arm of Abu Dhabi National Oil Company has undertaken in line with its ambition to raise the oil and gas production potential of Abu Dhabi’s Lower Zakum offshore hydrocarbon concession over the long term.
Contractors submitted expression of interest (EoI) documents, as part of the prequalification process, for the LTDP-1 project by 27 April, according to sources.
Adnoc Offshore issued the EoI to contractors for the engineering, procurement and construction (EPC) tendering exercise for the Lower Zakum LTDP-1 “earlier in March”, sources previously told MEED, with contractors initially asked to respond by 10 April.
Lower Zakum oil production
The Lower Zakum hydrocarbons zone is 65 kilometres northwest of Abu Dhabi in the Gulf’s waters. Adnoc Offshore holds the majority 60 per cent stake in the Lower Zakum asset. Foreign partners include an Indian consortium of companies led by ONGC Videsh (10 per cent), Japan’s Inpex Corporation (10 per cent), China National Petroleum Corporation (10 per cent), Italy’s Eni (5 per cent) and France’s TotalEnergies (5 per cent).
Adnoc Offshore and its partners in the Lower Zakum concession intend to sustain oil production from the asset at its current level of 450,000 barrels a day (b/d) until 2025, and then increase output to 470,000 b/d. This target will be achieved through the Lower Zakum early production scheme 2 (EPS 2) and proved developed producing (PDP) project.
The larger, longer-term objective is to raise Lower Zakum’s oil production to 520,000 b/d by 2027 and maintain that level until 2034. This goal is to be accomplished through the LTDP-1 project.
Raising oil and gas production from the Lower Zakum asset is vital for Adnoc to achieve its accelerated target of increasing oil production capacity to 5 million b/d by 2027, and raising gas output potential by 3 billion cubic feet a day (cf/d) by the end of this decade.
Lower Zakum EPS 2/PDP project
Front-end engineering and design (feed) work is progressing on the Lower Zakum EPS 2/PDP project and is being performed by UK-headquartered Wood Group.
Adnoc Offshore, which, according to sources, awarded Wood the contract in November last year, expects feed work on the project to be completed by June.
The basic scope of work on the project involves the drilling of 17 additional producer and water injection wells on two new wellhead towers (WHTs) and the expansion of the gas compression capacity of the Zakum West Super Complex (ZWSC).
Integration of the Lower Zakum complexes with the onshore power grid at UZ AGI for electricity supply to the EPS 2/PDP project is also part of the scope.
Demolition of structures and as-built documentation and surveying are also included in the scope of work.
Adnoc Offshore solicited interest for the Lower Zakum EPS 2/PDP project EPC works in December last year. Contractors expressed interest in participating in the main contract tendering process in January, sources told MEED.
As per the schedule, Adnoc Offshore expects to issue the project’s main EPC tender in June, with the award of contracts to take place in September.
Lower Zakum LTDP-1 project
Feed work is progressing on the Lower Zakum LTDP-1 project and is being performed by France’s Technip Energies.
According to sources, Adnoc Offshore awarded Technip Energies the contract in November last year. The operator expects feed work on the project, which began in December, to be completed by January 2024.
Adnoc Offshore issued the expression of interest for the Lower Zakum LTDP-1 EPC tendering exercise “earlier in March”, with contractors asked to respond by 10 April.
The detailed scope of work on the Lower Zakum LTDP-1 project is as follows:
Topside facilities on G Island – Civil works on process facilities and associated buildings on the artificial greenfield G Island.
Process facilities include well pads, inlet and export reception, production separation, export pumps, gas compression, dehydration and lift, produced water treatment and disposal, vapour recovery units, water injection units, riser tower, flare towers, accommodation, drilling of high-pressure flare knock out drum, power distribution facility, substations and local equipment rooms.
Offshore WHTs and pipelines – Seven WHTs will be installed: six in the east area, and one in the AGI area. Five of the WHTs are to be 16-slot, while the two others are to be 9-slot.
Das Island Terminal, ZCSC and ZWSC – The five existing oil processing trains at the Lower Zakum offshore development are to be decommissioned in 2028, with the new configuration of the main processing plant at Das Island to be:
- Two existing trains with a processing/stabilisation capacity of 110,000 b/d each
- Three new trains with a processing/stabilisation capacity of 150,000 b/d
The scope of work also covers the installation of other structures such as:
- Three high-pressure separator trains
- High-pressure scrubber
- Three low-pressure separator trains
- Low-pressure scrubber
- Three atmospheric separator trains
- Four crude charge pumps
- Three crude charge heaters
- Three cold strippers integrated with a degassing vessel
- Six stripped crude product pumps
- Common ejector with a spare for three cold strippers
- Closed drain drum with transfer pump
- Blow case vessel
As per the schedule, Adnoc Offshore expects to issue the project’s main EPC tender in December, with the award of contracts to take place in March next year.
The operator expects the Lower Zakum LTDP-1 project to be commissioned by the end of 2027.
Exclusive from Meed
-
Firms announce 129MW Dubai data centre24 April 2026
-
Iraq signs upstream oil contract24 April 2026
-
Jordan tenders oil and gas terminal project24 April 2026
-
Decision imminent on Dubai sewerage tunnel contracts24 April 2026
-
Dubai scales up its metro ambitions23 April 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Firms announce 129MW Dubai data centre24 April 2026
Dubai’s Integrated Economic Zones Authority (DIEZ) has signed a joint-venture agreement with Netherlands-headquartered data centre developer Volt to build a new artificial intelligence (AI)-ready data centre in the emirate.
Planned for Dubai Silicon Oasis, the development will take the form of a campus covering up to 60,000 square metres.
The project will be delivered in two phases, starting with 29MW of immediately available capacity, followed by a second phase adding a further 100MW of committed power.
Under the arrangement, DIEZ will supply the land and essential infrastructure, while Volt will finance and develop the project, lead construction, and manage the design, leasing, implementation and day-to-day operations.
French firm Schneider Electric, which has its regional headquarters in Dubai Silicon Oasis, will support the development by supplying advanced electrical systems, power distribution capabilities and smart data centre infrastructure.
The GCC currently has more than 174 active data centre projects, representing over $93bn in investment, led by international players such as AWS, Google and Huawei, alongside regional developers including Khazna and Moro, supported by government-led localisation strategies.
More than a dozen large-scale facilities valued at over $100m each are currently under tender, with further packages expected to reach the market over the next six to 12 months.
The UAE is one of the leading data centre markets, with hyperscale campuses, sovereign cloud initiatives and edge data centre deployments underway.
Data centre development is closely aligned with the UAE’s digital economy and AI roadmap, as well as the wider smart city programme.
Priorities include hyperscale and colocation facilities to support cloud service providers; edge data centres to reduce latency and enable 5G and IoT use cases; energy-efficient designs using advanced cooling, modular construction and renewables; and strategic partnerships between global hyperscalers, local developers and utilities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16548972/main.JPG -
Iraq signs upstream oil contract24 April 2026
State-owned Iraqi Drilling Company (IDC) has signed a contract with China’s EBS Petroleum for a project to drill 17 horizontal wells in the southeastern portion of the East Baghdad field.
Mohamed Hantoush, the general manager of IDC, said the contract signing came after a “series of successful achievements” by the company at the field.
The achievements included the completion of a project to drill 27 horizontal wells and another project to drill 18 horizontal wells, according to a statement released by Iraq’s Ministry of Oil.
In January, Iraq’s Midland Oil Company (MOC), in collaboration with EBS Petroleum, completed the country’s longest horizontal oil well in the southern part of the East Baghdad field.
The well, which was called EBMK-8-1H, reached a total depth of 6,320 metres, and had a 3,535-metre horizontal section, making it the country’s largest horizontal well ever drilled.
Senior officials from the Iraqi Oil Ministry and representatives of EBS Petroleum attended the well’s completion ceremony.
EBS Petroleum is a subsidiary of China’s ZhenHua Oil, which is focused on Iraq.
ZhenHua Oil is the operator of the field and is working with Iraqi partners to oversee the field’s development.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16543675/main4942.jpg -
Jordan tenders oil and gas terminal project24 April 2026

Jordan’s Aqaba Development Corporation (ADC) has tendered a project for the development of the facilities at the Aqaba Oil and Gas Terminal.
The project has been divided into two packages, and a bid deadline has been set for 15 June 2026.
The oil and gas terminal is located south of the city of Aqaba in Jordan’s Southern Industrial Zone.
The scope of Package 1 includes:
- Rehabilitation of petroleum product pipelines of various sizes and their accessories (such as supports, structures and valves), including rectification of painting defects
- Inspection and repair of pipe welds
- Rectification and overall maintenance of the product booster pump
- Inspection, maintenance, testing and commissioning of liquefied petroleum gas (LPG) booster pumps
- Rectification of two overhead cranes
- Rectification and calibration of instrumentation, including pressure indicators and valves
The scope of Package 2 includes:
- Rehabilitation of control rooms and security rooms, replacing them with concrete control rooms, including infrastructure works and all required services
- Removal of unused tanks and equipment previously used for exporting crude oil
- Rehabilitation of the existing gate in order to improve safety and security with the installation of a tire killer
- Carrying out maintenance and repairs for the oil berth dolphins and trestle with inspection
- Maintenance, repair and reinstallation of oil berth concrete slabs
- Removal and extension of the jetty platform
- Installation of a lighting system at pipelines beside booster pumps
- Installation of stripping pumps at the LPG terminal
- Replacement of drain line path for slop tank of LPG booster pumps
- Rehabilitation of the existing closed drain drum
- Rectification of cone sealing issue of all truck loading arms
- Conversion of manual valves to motor-operated valves
- Remote operation of shut-off valves on the main pipeline alongside and near the entrance gate
- Upgrading of the firefighting system
The last date for questions and clarifications related to the project will be 13 May 2026.
The Aquaba Oil and Gas Terminal was built to meet demand for petroleum products and LPG imports into Jordan.
It is operated by state-owned Jordan Oil Terminals Company (JOTC), which was established in 2015 as a private shareholding company.
Earlier this year, Abu Dhabi’s AD Ports Group signed an agreement with ADC to manage and operate the Aqaba multipurpose port.
AD Ports is managing and operating the port under a 30-year concession agreement.
Under the agreement, AD Ports and ADC will establish a joint venture to oversee port operations.
AD Ports will hold a 70% stake in the joint venture, with the remaining 30% held by ADC.
AD Ports Group will also invest AED141m ($38.4m) in the joint venture.
The signing ceremony was held at the Aqaba Special Economic Zone Authority headquarters in Aqaba on 5 February.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16543632/main.jpg -
Decision imminent on Dubai sewerage tunnel contracts24 April 2026

A final decision on the first two packages of the flagship Dubai Strategic Sewerage Tunnels (DSST) project is imminent, with two remaining bidders having submitted best and final offers.
The AED80bn ($22bn) public-private partnership (PPP) scheme comprises three packages: J, W and Links.
According to a source, two consortiums led by Etihad Water & Electricity (UAE) and Vision Invest (Saudi Arabia) were recently invited to submit final bids for packages J and W, which were tendered last November.
The winning consortium is expected to be formally confirmed in the coming weeks once the required approval process is completed, the source said.
MEED had previously reported that three consortiums were bidding for the project, which is being procured by Dubai Municipality’s sewerage and recycled water projects department.
These included:
- Consortium 1: Led by Plenary Group (Australia) alongside Itochu (Japan) and Infrastructure Holding (UAE)
- Consortium 2: Led by Vision Invest (Saudi Arabia) alongside Suez Water Company (France)
- Consortium 3: Led by Etihad Water & Electricity (UAE) alongside Tamasuk Holding (Saudi Arabia) and Alkhorayef Water & Power (Saudi Arabia)
It is understood that the consortium led by Pleneray Group has since been dropped from consideration for the contract.
As MEED previously reported, the bid packages include equity partners, an appointed operator and a construction contractor.
Of the bidders still in contention, MEED understands that Vision Invest plans to act as operator for that consortium, while Suez will lead construction.
In the other consortium, EtihadWE plans to take the operator role, with construction led by France’s Veolia.
Large-scale sewerage network
The DSST masterplan project covers the construction of two sets of deep tunnels terminating at pump stations at Warsan and Jebel Ali Sewage Treatment Plants (STPs). It also includes over 200 kilometres of sewer links.
Construction work was previously categorised in multiple packages under the Warsan Strategic Tunnel Scheme (Package W) and the Jebel Ali Strategic Sewerage Scheme (J1 North, J2 South, J3 Jebel Ali Links).
These packages have now been restructured and renamed.
The bid submission deadline for the third 'Phase 2 Links' package, meanwhile, was recently extended.
The new deadline is June 30.
The three packages are being procured under 30-year design, build, finance, operate and maintain concession models.
The DSST project aims to convert Dubai’s sewerage system from a pumped network to a gravity-based system, enabling the emirate to replace existing sewage pumping stations and meet long-term capacity needs.
The programme also marks the first time the municipality will implement In-Country Value (ICV), a local content programme that promotes economic benefits.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16536060/main.jpg -
Dubai scales up its metro ambitions23 April 2026

Dubai’s rail sector has rarely seen such a concentrated burst of procurement activity as it has in the past year.
Within the space of a few months, Dubai’s Roads & Transport Authority (RTA) has moved simultaneously on three distinct fronts: tendering design consultancy for the Route 2020 extension that will connect the Expo 2020 metro station to Al-Maktoum International airport; inviting study-and-design bids for a 55-kilometre Airport Express Line linking Dubai International airport to Al-Maktoum International airport; and culminating in Dubai Ruler Sheikh Mohammed Bin Rashid Al-Maktoum’s approval of the AED34bn ($9.2bn) Gold Line, a 42km fully underground route that the emirate is calling the largest transportation project in its history.
These projects form a key part of the Dubai Rail Network Plan 2032, which outlines the development of six public transportation schemes comprising a mix of metro, passenger and high-speed rail lines.
The most prominent feature of the plan is the addition of new lines to Dubai Metro’s existing network, representing a systematic effort to support the shift of Dubai’s economic centre of gravity towards Dubai South and the vast development corridors in between.
The city is also seeking to stay ahead of the curve by investing heavily in infrastructure. Data from regional projects tracker MEED Projects shows that the emirate has awarded over $14bn-worth of transport projects in the past two years alone, with several other multibillion-dollar schemes still moving through the planning stages.
All of this work is being carried out in line with the Dubai 2040 Urban Master Plan, which forecasts the emirate’s population will reach 5.8 million by 2040 – a clear indication of the scale of daily movement the city must accommodate.
Project progress
Dubai Metro Gold Line
On 21 April, Sheikh Mohammed officially announced the launch of the new AED34bn ($9.2bn) Gold Line project.
The line will be a fully underground network spanning over 42 kilometres, with 18 stations.
It will run from Al-Ghubaiba in Bur Dubai to Jumeirah Golf Estates.
The Gold Line will connect with Dubai Metro’s existing Red and Green lines and integrate with the Etihad Rail passenger network.
In October last year, MEED exclusively reported that the RTA had selected US-based engineering firm Aecom to provide consultancy services for the project.
Stage one covers concept design; stage two, preliminary design; stage three, preparation of tender documents; stage four, construction supervision; and stage five, the defects liability period.
Airport Express Line
Procurement has started for another metro line extending from Dubai International airport (DXB) in Al-Garhoud to Al-Maktoum International airport (DWC) in Jebel Ali.
Earlier this month, the RTA invited consultants to bid for a contract to study and design what is referred to as the Airport Express Line.
The proposed line will stretch about 55km and include five stations that will provide passengers with facilities such as remote airline check-in, baggage drop-off and security screening.
The new line will run from the Red Line metro station at DXB through Al-Jaddaf, along Al-Khail Road to a new station at Jumeirah Village Circle (JVC), before continuing on to DWC.
There will be two spur lines. The first will run from the new JVC station to Al-Fardan Exchange metro station at Emirates Golf Club, while the second will branch toward Business Bay, where another station will be built.
Expo 2020 route extension
Dubai is also undertaking the Route 2020 extension of its metro system, which will start from the Expo 2020 metro station and connect with Al-Maktoum International airport’s West Terminal.
Consultants submitted their bids earlier this month for the design contract.
The extension will run for about 3km and feature two stations.
The existing Route 2020 metro link is a 15km line that branches off the Red Line at Jebel Ali metro station. The line comprises 11.8km of elevated tracks and 3.2km of tunnels, and has five elevated stations and two underground stations.
Dubai Metro Blue Line extension
Construction progress on the Dubai Metro Blue Line extension is expected to reach 30% by the end of 2026, according to official accounts.
In December 2024, the RTA awarded a AED20.5bn ($5.5bn) main contract for the construction of the project.
The contract was awarded to a consortium of Turkiye’s Limak Holding, Mapa Group, also of Turkiye, and the Hong Kong office of China Railway Rolling Stock Corporation (CRRC).
The Blue Line will connect the existing Red and Green lines. It will be 30km long, with 15.5km underground and 14.5km above ground.
The line will have 14 stations, seven of which will be elevated. There will be five underground stations, including one interchange station, and two elevated transfer stations connected to the existing Centrepoint and Creek stations.
The project is scheduled for completion in September 2029.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16534887/main.png

