Firms express interest in Lower Zakum project

8 May 2023

Contractors have expressed interest in bidding for the main contract for the first phase of the Lower Zakum Long-Term Development Plan (LTDP-1) project. The offshore arm of Abu Dhabi National Oil Company (Adnoc Offshore) owns the project.

The Lower Zakum LTDP-1 project is the larger of two projects that the offshore arm of Abu Dhabi National Oil Company has undertaken in line with its ambition to raise the oil and gas production potential of Abu Dhabi’s Lower Zakum offshore hydrocarbon concession over the long term.

Contractors submitted expression of interest (EoI) documents, as part of the prequalification process, for the LTDP-1 project by 27 April, according to sources.

Adnoc Offshore issued the EoI to contractors for the engineering, procurement and construction (EPC) tendering exercise for the Lower Zakum LTDP-1 “earlier in March”, sources previously told MEED, with contractors initially asked to respond by 10 April.

Lower Zakum oil production

The Lower Zakum hydrocarbons zone is 65 kilometres northwest of Abu Dhabi in the Gulf’s waters. Adnoc Offshore holds the majority 60 per cent stake in the Lower Zakum asset. Foreign partners include an Indian consortium of companies led by ONGC Videsh (10 per cent), Japan’s Inpex Corporation (10 per cent), China National Petroleum Corporation (10 per cent), Italy’s Eni (5 per cent) and France’s TotalEnergies (5 per cent).

Adnoc Offshore and its partners in the Lower Zakum concession intend to sustain oil production from the asset at its current level of 450,000 barrels a day (b/d) until 2025, and then increase output to 470,000 b/d. This target will be achieved through the Lower Zakum early production scheme 2 (EPS 2) and proved developed producing (PDP) project.

The larger, longer-term objective is to raise Lower Zakum’s oil production to 520,000 b/d by 2027 and maintain that level until 2034. This goal is to be accomplished through the LTDP-1 project.

Raising oil and gas production from the Lower Zakum asset is vital for Adnoc to achieve its accelerated target of increasing oil production capacity to 5 million b/d by 2027, and raising gas output potential by 3 billion cubic feet a day (cf/d) by the end of this decade.

Lower Zakum EPS 2/PDP project

Front-end engineering and design (feed) work is progressing on the Lower Zakum EPS 2/PDP project and is being performed by UK-headquartered Wood Group.

Adnoc Offshore, which, according to sources, awarded Wood the contract in November last year, expects feed work on the project to be completed by June.

The basic scope of work on the project involves the drilling of 17 additional producer and water injection wells on two new wellhead towers (WHTs) and the expansion of the gas compression capacity of the Zakum West Super Complex (ZWSC).

Integration of the Lower Zakum complexes with the onshore power grid at UZ AGI for electricity supply to the EPS 2/PDP project is also part of the scope.

Demolition of structures and as-built documentation and surveying are also included in the scope of work.

Adnoc Offshore solicited interest for the Lower Zakum EPS 2/PDP project EPC works in December last year. Contractors expressed interest in participating in the main contract tendering process in January, sources told MEED.

As per the schedule, Adnoc Offshore expects to issue the project’s main EPC tender in June, with the award of contracts to take place in September.

Lower Zakum LTDP-1 project

Feed work is progressing on the Lower Zakum LTDP-1 project and is being performed by France’s Technip Energies.

According to sources, Adnoc Offshore awarded Technip Energies the contract in November last year. The operator expects feed work on the project, which began in December, to be completed by January 2024.

Adnoc Offshore issued the expression of interest for the Lower Zakum LTDP-1 EPC tendering exercise “earlier in March”, with contractors asked to respond by 10 April.

The detailed scope of work on the Lower Zakum LTDP-1 project is as follows:

Topside facilities on G Island – Civil works on process facilities and associated buildings on the artificial greenfield G Island.

Process facilities include well pads, inlet and export reception, production separation, export pumps, gas compression, dehydration and lift, produced water treatment and disposal, vapour recovery units, water injection units, riser tower, flare towers, accommodation, drilling of high-pressure flare knock out drum, power distribution facility, substations and local equipment rooms.

Offshore WHTs and pipelines – Seven WHTs will be installed: six in the east area, and one in the AGI area. Five of the WHTs are to be 16-slot, while the two others are to be 9-slot.

Das Island Terminal, ZCSC and ZWSC – The five existing oil processing trains at the Lower Zakum offshore development are to be decommissioned in 2028, with the new configuration of the main processing plant at Das Island to be:

  • Two existing trains with a processing/stabilisation capacity of 110,000 b/d each
  • Three new trains with a processing/stabilisation capacity of 150,000 b/d

The scope of work also covers the installation of other structures such as:

  • Three high-pressure separator trains
  • High-pressure scrubber
  • Three low-pressure separator trains
  • Low-pressure scrubber
  • Three atmospheric separator trains
  • Four crude charge pumps
  • Three crude charge heaters
  • Three cold strippers integrated with a degassing vessel
  • Six stripped crude product pumps
  • Common ejector with a spare for three cold strippers
  • Closed drain drum with transfer pump
  • Blow case vessel

As per the schedule, Adnoc Offshore expects to issue the project’s main EPC tender in December, with the award of contracts to take place in March next year.

The operator expects the Lower Zakum LTDP-1 project to be commissioned by the end of 2027.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10825529/main4514.jpg
Indrajit Sen
Related Articles
  • Dubai tenders sewage and stormwater projects

    5 October 2026

    Dubai Municipality has issued tenders for a 3,000-cubic-metre-a-day (cm/d) sewage treatment plant (STP) and a strategic stormwater drainage system.

    The first tender is for the design and construction of the Al-Lissaily STP.

    The project, identified as DS311/1, covers the design, supply, installation, construction and commissioning of the plant in the Al-Lissaily area.

    Dubai Municipality’s Sewerage and Recycled Water Projects Department is issuing the tender. The bid submission deadline is 29 October.

    The facility is located near residential communities and farming areas. The project will therefore include measures for odour control, treated effluent quality, noise mitigation and environmental performance.

    The municipality said the plant will incorporate landscaping and architectural features designed to reflect Dubai’s heritage character and the surrounding farming environment.

    The second tender is for project TF-07-C1, a strategic stormwater drainage system covering more than 100 million square metres.

    The project area extends from Sheikh Mohammed Bin Zayed Road (E311) to the north to Emirates Road (E611) to the south, and from Expo Road in the west to Dubailand in the east.

    The project will provide stormwater infrastructure and service connections for more than 20 private developers, as well as the Al-Yalayis 5 community.

    It will also support major roads in the Jebel Ali area, including Sheikh Mohammed Bin Zayed Road, Emirates Road, Sheikh Zayed Road, Sheikh Zayed Bin Hamdan Al-Nahyan Road, Hessa Street, Al-Yalayis Road and Al-Fay Road.

    The scope includes a major stormwater gravity drainage system, with pipeline diameters of up to 3,000mm.

    Dubai Municipality said the project is intended to increase drainage capacity, improve relief for existing and new stormwater systems, and strengthen protection against extreme rainfall events.

    The bid submission deadline is 22 October.

    The municipality also recently invited contractors to bid for a contract to upgrade and rehabilitate the stormwater system in Abu Hail.

    The project comprises a stormwater pumping station with a total discharge capacity of 26 cubic metres a second. It is estimated to cost up to $163m.

    Bid submissions are due by 15 October.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20266881/main.jpg
    Mark Dowdall
  • QatarEnergy gives North Field West topside bidders more time

    2 October 2026

     

    QatarEnergy has granted contractors more time to prepare bids for a tender covering the engineering, procurement, construction and installation (EPCI) of large platforms for the North Field gas field in Qatari waters.

    Contractors now have until 12 October to submit technical bids for the project, according to sources. Commercial bids are currently due on 10 November.

    The following contractors, among others, are understood to be bidding for the North Field West (NFW) production deck modules (PDMs) tender:

    • China Offshore Oil Engineering Company (China)
    • Larsen & Toubro Energy Hydrocarbon (India)
    • McDermott (US)
    • Saipem (Italy)

    The core scope comprises the EPCI of four PDMs and associated structures. The PDMs will increase gas production from North Field reservoirs and provide additional gas feedstock for the NFW liquefied natural gas (LNG) development.

    The tender, issued earlier this year, forms part of the wider NFW project, the third and final phase of the state enterprise’s North Field LNG expansion programme.

    The previous deadlines for technical bids were 30 August, 15 September and 28 September, while commercial bids were previously due on 25 October, as MEED reported.

    Before issuing the PDMs tender, QatarEnergy awarded US firm McDermott a contract for the EPCI of four offshore jackets that will also support gas feedstock supply for the NFW LNG project. The contract is estimated to be worth about $200m, MEED reported in January.

    North Field LNG expansion

    QatarEnergy is advancing the three phases of its estimated $40bn North Field LNG expansion project. EPC works on all three projects are progressing.

    QatarEnergy is understood to have committed nearly $30bn to the first two phases – North Field East (NFE) and North Field South (NFS) – which will lift Qatar’s LNG production capacity from 77.5 million tonnes a year (t/y) to 126 million t/y by 2028.

    QatarEnergy awarded the main EPC contracts for NFE in 2021. The project was intended to raise LNG output to 110 million t/y by 2025. The $13bn EPC package – covering the EPCI of four LNG trains, each with a capacity of 8 million t/y – was awarded in February 2021 to a consortium of Japan’s Chiyoda and France’s Technip Energies.

    In May 2023, QatarEnergy awarded the $10bn main EPC contract for NFS to a consortium of Technip Energies and Consolidated Contractors Company (CCC). The contract includes two LNG trains, each with a capacity of 7.8 million t/y.

    Once fully operational, the first two phases are expected to add 48 million t/y of LNG supply to the global market.

    QatarEnergy took the final investment decision on NFW earlier this year, awarding an EPC contract estimated at $8bn to a joint venture comprising Technip Energies, CCC and Gulf Asia Contracting in February.

    Chiyoda carried out the front-end engineering and design work for the NFW LNG project.

    The NFW scope covers the EPC of two LNG trains with a combined capacity of 16 million t/y, as well as associated facilities for gas treatment, natural gas liquids recovery and helium extraction.

    In addition to LNG, NFW is expected to produce about 175,000 barrels of oil equivalent a day of condensate, ethane and liquefied petroleum gas.

    With all three phases under EPC execution – and NFE scheduled for commissioning later this year – QatarEnergy is positioning itself to remain one of the world’s largest LNG suppliers in the long term.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20208200/main.jpg
    Indrajit Sen
  • Egypt implements oil and gas storage projects worth $1.1bn

    2 October 2026

    Egypt is implementing oil and gas storage projects worth a total of £E54bn ($1.1bn), according to a statement released by the country’s cabinet.

    Active developments include expanding El-Hamra Petroleum Port in El-Alamein on the Mediterranean coast, as well as building a jet-fuel storage and transport hub at the Badr depot in Cairo.

    Other projects include constructing new storage tanks at refinery complexes in Amreya, Alexandria; Assiut; and Cairo.

    Over the past 12 years, Egypt has built 84 petroleum storage facilities with a total capacity of 5.2 million tonnes, the cabinet statement said.

    Egypt has invested £E42.7bn ($880m) in developing these facilities, with the aim of bolstering domestic energy security.

    Completed infrastructure projects include facilities in Sohag (Upper Egypt) and Alexandria.

    They also include offshore terminal and storage facilities, a liquid bulk station in Ain Sokhna, and strategic crude oil storage tanks across the country.

    Storage facilities have become a strategic priority for Egypt since the US and Israel attacked Iran on 28 February, triggering a regional war that has disrupted shipping through the Strait of Hormuz.

    The disruption has made imports of hydrocarbon products into Egypt less predictable, increasing the importance of strategic stockpiles.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20208195/main.jpg
    Wil Crisp
  • Bankability key to Saudi PPP pipeline

    2 October 2026

     

    Saudi Arabia’s National Centre for Privatisation & PPP (NCP) holds structured talks with bidders and lenders before launching transactions to ensure projects in its pipeline are bankable, according to a senior official.

    Speaking on a panel at MEED’s Shaping Mega Projects conference in Riyadh on 28 September, Tariq Alghaziri, executive vice-president at the NCP, said the centre carries out market sounding with potential bidders and debt providers, including commercial and Islamic banks, before announcing deals.

    “Bankability is a key word for us,” he said. “You can structure the deal in the way you want. You can have whatever technicalities and technologies are required, but is it suitable for the private sector to deliver? That’s the big question.”

    Alghaziri said the national privatisation strategy, approved at the end of 2025 and published at the start of 2026, sets the NCP’s targets up to 2030 and outlines its project pipeline. The strategy coincides with the third phase of Vision 2030, which he said is focused on measuring impact after earlier phases established the legal framework and enabled the private sector.

    Public-private partnership (PPP) contracts typically run for 25 years and, in some cases, more than 40 years, he said, which makes early engagement essential. “When we launch it, all the bidders, suppliers, EPC contractors, banks and ECAs are on the same page, and then they just have to align on commercial points and not negotiate legal aspects.”

    Risk transfer

    Jonathan Looker, managing director for Saudi Arabia at UK consultancy Mott MacDonald, said the public and private sectors often perceive risk very differently.

    "Can you put yourself in the shoes of the person you’re trying to transfer risk to?” he said. “There isn’t one single allocation model that is fit for every project.”

    Looker said failure to agree on risk can prevent projects from reaching financial close. "I’ve unfortunately been involved in a number of projects where we just can’t get the deal done because there is not a meeting of minds around a specific aspect of risk.”

    Alghaziri said Saudi regulations now state that the party with the capacity to manage a risk should take it, but that risk carries a cost. “You cannot just give the risk without pricing it,” he said. The NCP has trained more than 300 people over the past five or six years, including through a PPP professional certification it introduced in the kingdom.

    Early planning

    Hesham Ouf, senior director of finance at Roshn Group, the Public Investment Fund (PIF) subsidiary, said risk management begins at the feasibility stage. “You need to have the stage gates right from the beginning until the project is delivered,” he said.

    Ali Al-Kuwari, senior manager of export development at Qatar Development Bank (QDB), said early disclosure of procurement needs allows lenders to assess project risk. “For me, the answer is very easy. I’ll ask for a sovereign guarantee,” he said.

    Wesley Thomson, partner and head of environmental, social and governance (ESG) at UK property consultancy Knight Frank, said climate exposure is becoming a central risk for long-life assets. “Mitigation is not the right word any more. I prefer to say adaptation, because the truth is you need to adapt to what we’re seeing.”


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20207592/main.png
    Colin Foreman
  • Financing hinders progress at major Iraqi refinery project

    2 October 2026

     

    Financial problems are hindering progress at Iraq’s Al-Faw Investment Refinery project, according to industry sources.

    Despite the main contract being signed more than two years ago, construction of the main refinery units has yet to begin because of ongoing financial issues, sources said.

    In May 2024, a statement released by the Iraqi Prime Minister’s Office said that Iraq’s state-owned Southern Refineries Company and China National Chemical Engineering Company (CNCEC) had signed a contract to develop the project.

    Iraq’s Oil Ministry previously said the project would be worth $7bn-$8bn.

    The project has struggled to make progress even after direct intervention by Iraq’s previous prime minister.

    On 6 August 2025, 15 months after the May 2024 contract signing with CNCEC, Mohammed Shia Al-Sudani, then prime minister, chaired a special meeting to resolve administrative and technical obstacles preventing the project from starting.

    At the time, Al-Sudani said the refinery project would have significant financial returns and would be “a breakthrough in the oil industry”.

    While the meeting in 2025 is believed to have solved some of the administrative issues blocking progress, financial problems with the project remain, sources said.

    The Al-Faw project is part of the Iraqi government’s plan to increase Iraq’s refining capacity, attract foreign investment and increase domestic production of petroleum products.

    Under existing plans, the refinery will have a capacity of 300,000 barrels a day and will produce oil derivatives for both domestic and international markets.

    The project will be carried out in two stages.

    The first phase will involve refining operations, while the second will involve constructing a petrochemicals complex with a capacity of 3 million tonnes a year.

    The project also includes building a 2,000MW power plant and establishing the Al-Faw Academy for Refinery Technology to train 5,000 Iraqi workers who will eventually work at the facility.

    Hualu, a subsidiary of CNCEC, signed a preliminary principles agreement for the project in December 2021.

    Due to material price inflation since December 2021, some insiders believe the project value may now be significantly higher than the previously estimated $7bn-$8bn.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20207119/main.jpg
    Wil Crisp