Firms express interest in new Hail and Ghasha phase
22 May 2023

Register for MEED's guest programme
Contractors have expressed interest in tendering for new engineering, procurement and construction (EPC) contracts for Abu Dhabi National Oil Company’s (Adnoc’s) multibillion-dollar Hail and Ghasha sour gas development.
Adnoc started a fresh EPC tendering round for the project on 29 April. Contractors were issued expression of interest (EoI) documents just days after the cancellation of the pre-construction services agreements (PCSAs) that had been awarded in January.
Firms were initially asked to express interest in the new EPC tendering round by 14 May. According to sources, the deadline was extended until 19 May and firms submitted EoIs by that date.
The new EoI document details Adnoc’s latest EPC execution strategy for the Hail and Ghasha development. Under these plans, the offshore and onshore scope of work has been divided into three packages:
- Package one: Subsea pipelines, umbilicals, cables, risers and other offshore structures
- Package two: Offshore drilling centre facilities, the Ghasha offshore processing plant and central living quarters
- Package three: The Manayif onshore processing plant, including offsite export pipelines and tie-ins, utilities, the main control building and process buildings. Work on a Ruwais sulphur-handling terminal and other non-process buildings is an optional scope for this package.
An Adnoc spokesperson previously told MEED: “Adnoc and our international partners remain committed to delivering the gas mandated from the Ghasha concession. We do not comment on market speculation.”
PCSAs cancelled
The PCSAs signed in January with two consortiums, comprising three contractors each, marked the start of detailed engineering work and procurement of critical long-lead items for the offshore and onshore scope of work on the Hail and Ghasha development.
A consortium of France-headquartered Technip Energies, South Korean contractor Samsung Engineering and Italy’s Tecnimont was awarded the PCSA for the onshore package. The contractors revealed the value of the contract to be approximately $80m.
Italian contractor Saipem, Abu Dhabi’s National Petroleum Construction Company (NPCC) and state-owned China Petroleum Engineering & Construction Company (CPECC) won the PCSA for the offshore package, worth $60m.
Previously, the onshore work on the Hail and Ghasha scheme involved the construction of a gas process plant, pipeline network and new gas gathering units.
The offshore PCSA covered installing offshore platforms, gas compression facilities and more than 400 kilometres of subsea pipelines.
The reason for these PCSAs being annulled is unclear, but sources previously said the cost estimates submitted for the project were higher than the client’s overall budget.
Protracted project timeline
The cancelled PCSAs were part of an early engagement process with contractors that Adnoc started following the termination of at least two earlier bidding rounds.
US engineering firm Bechtel completed the project’s original front-end engineering and design (feed) in 2019, with tenders for four EPC packages issued soon after.
Following the submission of commercial bids in early 2021, Adnoc made revisions to the feed as part of an optimisation process started by Technip Energies in November 2021. The revised feed aimed to reduce the scheme’s overall capital expenditure, which was previously estimated to be as high as $15bn.
The four original EPC packages were consolidated into two integrated offshore and onshore packages, thought to be worth as much as $5bn and $5.5bn, respectively, based on the previous version of the project.
MEED reported in September last year that early engagement contractors had submitted proposals for the detailed engineering work on the Hail and Ghasha development. The January PCSAs are understood to have been issued based on these proposals.
Hail and Ghasha fields
The Hail and Ghasha fields, along with the Hair Dalma, Satah, Bu Haseer, Nasr, Sarb, Shuwaihat and Mubarraz fields, are located in Abu Dhabi’s offshore Ghasha concession.
Adnoc holds the majority 55 per cent stake in the Ghasha concession. The other stakeholders are Italian energy major Eni with 25 per cent, Germany’s Wintershall Dea with 10 per cent and Austria’s OMV and Russia’s Lukoil, each with 5 per cent.
Adnoc plans to produce more than 1.5 billion cubic feet a day of sour gas from the Ghasha concession by the middle of this decade. This target is aligned with the company’s broader goal of achieving gas self-sufficiency for the UAE by 2030.
In November 2021, Adnoc and its partners in the Ghasha concession awarded two EPC contracts for the Dalma offshore sour gas development project. Abu Dhabi’s NPCC and Spain-headquartered Tecnicas Reunidas won contracts worth $1.46bn to execute offshore and onshore EPC works on the Dalma project, respectively.
Four artificial islands have already been completed in the Ghasha concession, and development drilling is under way.
In addition, Adnoc awarded two contracts totalling $2bn to its subsidiary Adnoc Drilling in July last year for the Hail and Ghasha offshore sour gas field development project.
The awards comprise a $1.3bn contract for integrated drilling services and fluids, and a $711m contract to provide four island drilling units. Their duration is 10 years.
Adnoc also awarded a third contract, valued at $681m, to another subsidiary, Adnoc Logistics & Services, to provide offshore logistics and marine support services for the planned Hail and Ghasha development.
Exclusive from Meed
-
-
Algeria tenders upstream oil project contract25 June 2026
-
-
-
Chinese firm wins $265m Saudi hospital contract24 June 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Firms prepare Hudayriat East PPP tunnels advisory bids25 June 2026

Abu Dhabi’s Modon Infrastructure, formerly Gridora, has tendered a contract for technical advisory services for the construction of two underwater tunnels connecting the eastern side of Hudayriat Island with mainland Abu Dhabi.
Consultants have until 26 June to submit their proposals.
The project includes the construction of a 4.8-kilometre (km) highway, with four lanes in each direction, connecting Hudayriat Island to Mussafah 8th Street.
The project will be delivered on a public-private partnership (PPP) basis in coordination with the Abu Dhabi Department of Municipalities and Transport and the Abu Dhabi Investment Office.
The contract term is expected to be 25 years.
The latest infrastructure development in Abu Dhabi follows Modon Infrastructure’s invitation in May for firms to register for the next phase of Abu Dhabi’s Mid Island Parkway Project (MIPP), which will also be developed on a PPP basis.
Modon Infrastructure will act as the lead developer, holding the majority equity stake in the project company. It will award the engineering, procurement and construction contract, as well as the operations and maintenance services and advisory appointments.
The second phase of the MIPP involves the construction of about 11km of highways, including a mix of three-, four- and five-lane sections. The highways will connect the Um-Yifeenah, Al-Jubail, Al-Sammaliyyah and Sas Al-Nakhl islands to Khalifa City and the E10 road.
The scope also covers the construction of three interchanges: the E20, E10 and Dumbbell interchanges on Al-Sammaliyyah Island.
The project includes several major structures, such as the E20 interchange, which will feature cast-in-place box-girder and void-slab bridges, and the E10 interchange with cast-in-place box-girder bridges. It also includes I-girder bridges between Raha Beach West and Sas Al-Nakhl Island, as well as a causeway at Sas Al-Nakhl Island.
Further key elements include a cast-in-place balanced cantilever bridge between Sas Al-Nakhl Island and Al-Sammaliyyah Island; a tunnel between Al-Sammaliyyah Island and Bilrimaid Island; and a cut-and-cover (open) tunnel on Bilrimaid Island. The project will be completed with another tunnel connecting Bilrimaid Island to Um-Yifeenah Island.
> Be recognised among the best in the industry at the MEED Projects Awards 2026 …
https://image.digitalinsightresearch.in/uploads/NewsArticle/17410214/main.jpg -
Algeria tenders upstream oil project contract25 June 2026
Algeria’s state-owned national oil and gas company, Sonatrach, has tendered a contract for the development and rehabilitation of the central processing facility (CPF) at the Bir Berkine oil and gas field.
The scope of the contract includes the study, supply, construction and commissioning of a project to rehabilitate the CPF facilities at the field, which is located in the Hassi Mesaoud region.
Sonatrach says in the tender documents that the objective of the project is to ensure the continuity of production activities “under stable and secure operating conditions”.
It also says the project aims to improve production yields and quality.
The contract includes both initial and detailed studies as well as the supply of all equipment and materials.
It also includes the execution of works, the assembly of all equipment and materials, and the commissioning of all relevant facilities.
The tender has a two-stage submission process, with the first stage requiring technical bids to be submitted by 23 August.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17423013/main3916.jpg -
Red Sea Global tenders King Salman Bay construction work25 June 2026

Saudi gigaproject developer Red Sea Global (RSG) has tendered a contract inviting firms to undertake marine infrastructure works at King Salman Bay on the Red Sea coast, north of Jeddah.
The scope includes dredging and earthworks, as well as quay wall and edge protection works spanning about 11 kilometres.
The bid submission deadline is 31 July.
King Salman Bay is expected to be a waterfront development aimed at reshaping the city’s northern Red Sea frontage into a mixed-use destination, anchored by public-realm improvements and leisure-led development.
The update follows RSG’s award of an estimated SR100m ($27m) contract to construct a solid waste management centre at its Red Sea Project. The scope includes four buildings: a material recycling facility, a transfer station, an administration building and a vehicle maintenance building.
In October last year, MEED reported that RSG had secured a SR6.5bn ($1.7bn) credit facility to further develop Amaala, its luxury tourism destination on Saudi Arabia’s northwestern Red Sea coast.
According to an official statement, “The funding is led by Riyad Bank as the sole underwriter, along with Saudi Investment Bank and Bank Al-Bilad as mandated lead arrangers.
“The loan arrangement comprises a mix of conventional and Islamic financing and adheres to RSG’s Green Loan Framework, which was first established when it secured private funding from a consortium of four banks for the Red Sea destination in 2021,” the statement added.
The announcement followed RSG’s opening of its first properties for sale at Amaala, including branded residential communities and a five-bedroom villa on a private island.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17430045/main.jpg -
MECC submits lowest bid on three Kuwaiti oil and gas contracts25 June 2026

Kuwait-based Mechanical Engineering & Contracting Company (MECC) has submitted the lowest bid across three separate contracts tendered by the state-owned upstream operator Kuwait Oil Company (KOC).
The total value of the low bids is $427m, and all of the contracts are focused on developing substations to power industrial lift pumps and remote header manifolds
Five companies submitted bids for a contract to develop several substations to power industrial lift pumps and remote header manifolds in areas 6, 10 and 12 in southern and eastern Kuwait.
The bidders were:
- MECC: KD65,760,000 ($212m)
- Heavy Engineering Industries & Shipbuilding Company: KD70,630,000 ($228m)
- Amco Engineering & Construction: KD73,446,100 ($237m)
- Combined Group Contracting Company: KD76,186,000 ($246m)
- Nasser Mohammed Al-Badah & Partner General Trading & Contracting: KD79,332,417 ($256m)
Six companies submitted bids for a contract to develop several substations to power industrial lift pumps and remote header manifolds in areas 8 and 13 in southern and eastern Kuwait.
The bidders were:
- MECC: KD30,760,000 ($99m)
- Badr Al-Mulla & Brothers: KD32,662,040 ($106m)
- Heavy Engineering Industries & Shipbuilding Company: KD34,139,000 ($110m)
- Industrial Company for Electrical Projects: KD36,375,520 ($118m)
- Nasser Mohammed Al-Badah & Partner General Trading & Contracting: KD37,278,526 ($120m)
- Combined Group Contracting Company: KD37,790,000 ($122m)
Eight companies submitted bids for a contract focused on developing several substations to power industrial lift pumps and remote header manifolds in areas 7, 9, and 11 in southern and eastern Kuwait.
The bidders were:
- MECC: KD35,760,000 ($116m)
- Badr Al-Mulla & Brothers: KD39,447,165 ($127m)
- Amco Engineering & Construction: KD39,736,800 ($128m)
- Heavy Engineering Industries & Shipbuilding Company: KD40,105,000 ($130m)
- Industrial Company for Electrical Projects: KD43,238,265 ($140m)
- Engineering Company for Petroleum & Chemical Industries (Enppi): KD43,514,805 ($141m)
- Combined Group Contracting Company: KD43,650,000 ($141m)
- Nasser Mohammed Al-Badah & Partner General Trading & Contracting: KD43,706,826 ($141m)
Kuwait’s oil and gas sector has been in crisis in recent months due to disruption from the regional conflict that started after the US and Israel attacked Iran on 28 February 2026.
A preliminary peace agreement between the US and Iran, which was announced on 14 June, has increased optimism that disruption to the sector will decrease in the coming weeks.
Under the terms of the agreement, both sides have stated that the free flow of vessels will be permitted through the Strait of Hormuz, through which nearly all of Kuwait’s crude oil is normally exported.
READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDFGCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.
Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:
> AGENDA: Gulf races to reroute trade> EXPORT ROUTES: Regional war boosts oil and gas pipeline project activity> CURRENT AFFAIRS: UAE’s Opec departure fulfils multiple ends> MEED TOP 100: Middle East stocks recover unevenly> LEADERSHIP: Building the infrastructure that makes net zero possible> TRADE DEAL: UK-GCC trade deal talks concludeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17423009/main.jpg -
Chinese firm wins $265m Saudi hospital contract24 June 2026
Zhejiang Construction International, the local subsidiary of Chinese contractor Zhejiang Construction Investment Group, has won a $265m contract to build the Prince Mohammed Bin Fahd University Speciality Hospital in Al-Khobar.
Construction is expected to take three years from the start date.
Prince Mohammed Bin Fahd University awarded the contract.
Located in Al-Raja district, Al-Khobar, in Saudi Arabia’s Eastern Province, the hospital project will cover about 60,000 square metres.
The contract covers the construction of a 10-storey hospital building, two five-storey auxiliary buildings connected by corridors and a basement.
Work will include civil works, mechanical and electrical installation, curtain walling, landscaping, detailed design and the procurement of medical equipment.
The award is the latest in a series of contracts secured by Chinese contractors from Saudi entities in recent months.
Last week, MEED reported that Saudi Arabia’s Ministry of Municipalities & Housing awarded contracts worth more than SR1.9bn ($506m) to Chinese contractors for two residential developments in the kingdom.
China Architectural Construction Corporation won the first contract, valued at SR875m ($233m), to build 2,010 housing units at the Al-Ruba residential project in Riyadh.
China State Construction Engineering Corporation secured the other contract, valued at more than SR1bn ($266m), for the Al-Rasha Al-Faisaliah residential project in Dammam, comprising 2,426 housing units.
GlobalData expects Saudi Arabia’s construction industry to record average annual growth of 5.2% in 2025-28, supported by investments in transport, electricity, housing and tourism infrastructure, as well as the $850bn-plus gigaprojects programme.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17412846/main.jpg


