Firms express interest in new Hail and Ghasha phase

22 May 2023

 

Register for MEED's guest programme 

Contractors have expressed interest in tendering for new engineering, procurement and construction (EPC) contracts for Abu Dhabi National Oil Company’s (Adnoc’s) multibillion-dollar Hail and Ghasha sour gas development.

Adnoc started a fresh EPC tendering round for the project on 29 April. Contractors were issued expression of interest (EoI) documents just days after the cancellation of the pre-construction services agreements (PCSAs) that had been awarded in January.

Firms were initially asked to express interest in the new EPC tendering round by 14 May. According to sources, the deadline was extended until 19 May and firms submitted EoIs by that date.

The new EoI document details Adnoc’s latest EPC execution strategy for the Hail and Ghasha development. Under these plans, the offshore and onshore scope of work has been divided into three packages:

  • Package one: Subsea pipelines, umbilicals, cables, risers and other offshore structures
  • Package two: Offshore drilling centre facilities, the Ghasha offshore processing plant and central living quarters
  • Package three: The Manayif onshore processing plant, including offsite export pipelines and tie-ins, utilities, the main control building and process buildings. Work on a Ruwais sulphur-handling terminal and other non-process buildings is an optional scope for this package.

An Adnoc spokesperson previously told MEED: “Adnoc and our international partners remain committed to delivering the gas mandated from the Ghasha concession. We do not comment on market speculation.”

PCSAs cancelled

The PCSAs signed in January with two consortiums, comprising three contractors each, marked the start of detailed engineering work and procurement of critical long-lead items for the offshore and onshore scope of work on the Hail and Ghasha development.

A consortium of France-headquartered Technip Energies, South Korean contractor Samsung Engineering and Italy’s Tecnimont was awarded the PCSA for the onshore package. The contractors revealed the value of the contract to be approximately $80m.

Italian contractor Saipem, Abu Dhabi’s National Petroleum Construction Company (NPCC) and state-owned China Petroleum Engineering & Construction Company (CPECC) won the PCSA for the offshore package, worth $60m.

Previously, the onshore work on the Hail and Ghasha scheme involved the construction of a gas process plant, pipeline network and new gas gathering units.

The offshore PCSA covered installing offshore platforms, gas compression facilities and more than 400 kilometres of subsea pipelines.

The reason for these PCSAs being annulled is unclear, but sources previously said the cost estimates submitted for the project were higher than the client’s overall budget.

Protracted project timeline

The cancelled PCSAs were part of an early engagement process with contractors that Adnoc started following the termination of at least two earlier bidding rounds.

US engineering firm Bechtel completed the project’s original front-end engineering and design (feed) in 2019, with tenders for four EPC packages issued soon after.

Following the submission of commercial bids in early 2021, Adnoc made revisions to the feed as part of an optimisation process started by Technip Energies in November 2021. The revised feed aimed to reduce the scheme’s overall capital expenditure, which was previously estimated to be as high as $15bn.

The four original EPC packages were consolidated into two integrated offshore and onshore packages, thought to be worth as much as $5bn and $5.5bn, respectively, based on the previous version of the project.

MEED reported in September last year that early engagement contractors had submitted proposals for the detailed engineering work on the Hail and Ghasha development. The January PCSAs are understood to have been issued based on these proposals.

Hail and Ghasha fields

The Hail and Ghasha fields, along with the Hair Dalma, Satah, Bu Haseer, Nasr, Sarb, Shuwaihat and Mubarraz fields, are located in Abu Dhabi’s offshore Ghasha concession.

Adnoc holds the majority 55 per cent stake in the Ghasha concession. The other stakeholders are Italian energy major Eni with 25 per cent, Germany’s Wintershall Dea with 10 per cent and Austria’s OMV and Russia’s Lukoil, each with 5 per cent.

Adnoc plans to produce more than 1.5 billion cubic feet a day of sour gas from the Ghasha concession by the middle of this decade. This target is aligned with the company’s broader goal of achieving gas self-sufficiency for the UAE by 2030.

In November 2021, Adnoc and its partners in the Ghasha concession awarded two EPC contracts for the Dalma offshore sour gas development project. Abu Dhabi’s NPCC and Spain-headquartered Tecnicas Reunidas won contracts worth $1.46bn to execute offshore and onshore EPC works on the Dalma project, respectively.

Four artificial islands have already been completed in the Ghasha concession, and development drilling is under way.

In addition, Adnoc awarded two contracts totalling $2bn to its subsidiary Adnoc Drilling in July last year for the Hail and Ghasha offshore sour gas field development project.

The awards comprise a $1.3bn contract for integrated drilling services and fluids, and a $711m contract to provide four island drilling units. Their duration is 10 years.

Adnoc also awarded a third contract, valued at $681m, to another subsidiary, Adnoc Logistics & Services, to provide offshore logistics and marine support services for the planned Hail and Ghasha development.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10872981/main2245.jpg
Indrajit Sen
Related Articles
  • Contractors win $317m Qatar road contracts

    15 October 2026

     

    Qatar’s Public Works Authority (Ashghal) has awarded three road development contracts worth more than QR1.1bn ($317m) to local contractors for works across Qatar.

    The contracts were formally awarded on 1 October, and each has a three-year construction period.

    Qatar Building Engineering Company secured a QR479m ($132m) contract for roads and infrastructure works in the Wadi Al-Banat North Zone 70 area.

    The contract covers constructing and upgrading local roads across several streets in the area. The scope also includes surface-water drainage, foul sewerage and treated sewage effluent networks, as well as connections to existing potable water, power and telecommunications infrastructure.

    The works include an attenuation tank near the Al-Khor Expressway and Link Road 7 to collect surface water and prevent infiltration into the Northern Aquifer.

    The contractor will also carry out groundwater mitigation works at the Al-Khor Expressway’s F1 interchange.

    Surface works include paved medians, including sections along Umm Al-Zubar Road near Lusail Palace, as well as landscaping.

    Qatar Trading & Contracting Group won the QR457m ($126m) contract to complete the remaining works on the C2021/44 roads and infrastructure scheme in Al-Sheehaniya (Package 1).

    The scheme covers site preparation, earthworks, and the construction of roads, pavements, road markings, signage, traffic-calming measures and street lighting.

    The scope also includes surface-water drainage and a complete pumping-station package encompassing civil, structural, mechanical, electrical, instrumentation, control and automation works.

    The contractor will also install a foul sewerage network with house connections across stages one and two, alongside a treated sewage effluent system, irrigation infrastructure, landscaping and landscape lighting.

    JAK Construction was awarded the QR217m ($60m) contract for the remaining works on the C/2021/038 roads and infrastructure project.

    The scope covers completing the remaining civil works, road network works, and key public-utility works across Umm Slal Ali, Umm Ebariya Village, South Umm Al-Amad and North Bu Fessela (Package 1).

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20617022/main.jpg
    Yasir Iqbal
  • Kuwait studies two oil export pipelines to bypass Hormuz

    15 October 2026

    State-owned Kuwait Petroleum Corporation is considering developing two oil export pipelines that would bypass the Strait of Hormuz, according to a senior Kuwaiti oil official.

    The pipelines would transport crude oil through Saudi Arabia and the UAE, aiming to diversify Kuwait’s export routes.

    Mohammed Al-Abduljalil, the deputy chief executive for planning and innovation at the KPC subsidiary Kuwait Oil Company, told Asharq Bloomberg that KPC had agreed with its partners in Saudi Arabia and the UAE to conduct feasibility studies for two separate projects.

    The first project extends from Kuwait’s Ahmadi region through Saudi Arabia to the Red Sea coast. The second extends from the Ahmadi region to Fujairah in the UAE.

    The pipelines would build on existing infrastructure and, if the plans are approved, are expected to take around four or five years to complete, Al-Abduljalil said.

    He said the first project, currently under study, would use the route of the existing East-West pipeline, which connects the kingdom’s eastern oil-producing regions to its western coast.

    The second project would follow the UAE’s Habshan-Fujairah pipeline route, enabling oil exports from the Sea of Oman coast, outside the Strait of Hormuz.

    Al-Abduljalil emphasised that both projects remain in a very early stage, noting that the agreement to conduct feasibility studies does not constitute a final investment decision to proceed with implementation.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20602978/main.jpg
    Wil Crisp
  • Gulf Spic submits lowest bid for Kuwait booster stations

    15 October 2026

     

    Kuwait-based Gulf Spic General Trading & Contracting Company has submitted the lowest bid for a contract to upgrade gas booster stations in the country.

    Gulf Spic’s bid was worth KD41.2m ($132m) and was one of four bids submitted for the contract.

    The project scope focuses on upgrading gas booster stations 140 and 150 (BS-140 and BS-150).

    The full list of bidders was:

    • Gulf Spic General Trading & Contracting Company, Kuwait – KD41.2m ($132m)
    • Combined Group Contracting Company (CGC), Kuwait  – KD45.5m ($146m)
    • Heavy Engineering Industries & Shipbuilding Company (Heisco), Kuwait – KD50.7m ($163m)
    • Alghanim International General Trading & Contracting Company, Kuwait – KD65.5m ($210m)

    The project was first announced in 2014. The invitation to bid was issued in May this year, and bids were submitted ahead of the 11 October deadline.

    The scope of work on the project covers:

    • Upgrade of BS-140 and BS-150
    • Replacement of dehydration facilities
    • Laying of pipelines
    • Installation of safety system
    • Construction of associated facilities

    Kuwait’s oil and gas sector is currently in the midst of a major crisis, as disruptions to shipping through the Strait of Hormuz have dramatically reduced exported crude oil volumes.

    The disruption is also creating significant challenges for oil and gas construction projects, which normally import equipment and materials through the Strait of Hormuz.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20602827/main.jpg
    Wil Crisp
  • Stability holds as project work continues

    14 October 2026

     

    When Dean McGrail describes the performance of the region’s construction market, he keeps returning to a single word: “stable”.

    After initial concerns that the market would experience a sharp downturn and project cancellations following the onset of conflict in the region, regional president McGrail says WSP has yet to see a single major contract cancelled across its regional portfolio.

    “We have seen some projects re-evaluated – questions around whether the mix between residential and commercial is right, and whether it should be luxury residential,” he says. “But as of today, we have not seen any projects cancelled, which is a real sign of resilience in the market.”

    Under the surface

    That resilience does not mean nothing has changed. McGrail is careful to separate re-evaluation from cancellation. Projects already on site and selling into the market are pressing ahead. It is schemes that have not yet been released for off-plan sales that are being paused and reconsidered.

    “None of the projects we are currently involved in have been put on hold or suspended,” he says. “It is more re-evaluation. Some of that is investor sentiment, but some of it is materials and logistics as well, which people do not necessarily consider.”

    Logistics, in particular, is a pressure that rarely makes the headlines. According to McGrail, shipping disruption has complicated the delivery of heavy equipment on certain schemes. “If we have big pieces of kit coming in – chillers or turbines for a power station – that becomes challenging,” he says.

    The bigger question is viability. And while rising material costs, set against softening sales prices, are forcing developers to reappraise the numbers, for now the balance sits firmly on the side of continuity. McGrail estimates that revalidation and feasibility work accounts for less than 3% of the firm’s current order book, with the remainder progressing as normal.

    “Requests for proposals have not slowed down across any of our disciplines or business units,” he says. “We are definitely seeing an uptick in infrastructure.”

    Infrastructure pivot

    That focus points to where McGrail expects the next few years of growth to come from. Rail sits at the centre of the UAE story, alongside road upgrades and other major developments in Abu Dhabi. In Dubai, the clearest signal of intent is the expansion of Al-Maktoum International airport.

    “Al-Maktoum is a really good indicator of the future direction of travel,” he says. “That is not a project that is slowing down. There has been a commitment to Emirates that it will move there, and it is still progressing.”

    The scale of the airport – and the challenge of relocating an airline the size of Emirates in one move – raises the question of how it will be funded. Here, McGrail returns to the theme of stability and to the mechanism that underpins it.

    “One of the beauties of this region is the ability of government to step in,” he says. “They can fund it. If the private sector does start to suffer, that is the backstop. They push money into infrastructure – roads, rail, airports – which keeps our industry moving.”

    Saudi reset

    In Saudi Arabia, the recalibration story predates the conflict, and McGrail says the change should be read as a strength rather than a retreat.

    “I am positive,” he says. “When the reprioritisation started at the beginning of 2025, having lived through the global financial crisis here, I saw the decision to stop, re-evaluate and reprioritise expenditure as a positive. When Vision 2030 was set, Saudi Arabia had not won Expo or the World Cup, so the reprioritisation was the right thing to do. Saudi Arabia will come out of it stronger. Short-term pain, long-term gain.”

    The nature of the work is shifting with the budget. McGrail sees the kingdom moving towards a model long familiar in the UAE, in which core infrastructure and a handful of landmark buildings are delivered first, before surrounding plots are carved up and sold on.

    “You establish a few key iconic buildings, then the plots on the outside are carved up and they look for external investment to come in and develop them,” he says. “It is no different from Downtown Dubai, where Emaar built the Burj Khalifa and a few buildings, then started selling plots.”

    That approach is increasingly tied to public-private partnerships (PPPs), although McGrail is measured on how far the model will stretch.

    “PPP is definitely becoming more prevalent on some of the larger infrastructure projects, though still not as significant as it was made out to be when they first started talking about it,” he says. He sees industrials, mining, healthcare and schools as a natural fit, rather than PPP becoming a blanket procurement route.

    Aviation is another priority. WSP was recently appointed to the rehabilitation of the existing terminal at Jeddah’s King Abdulaziz International airport, alongside a new terminal. It also recently secured a role on the expansion and upgrade of King Fahd International airport in Dammam.

    “Aviation is definitely a key area of focus for us as we head into the next 12, 24, 36 months,” McGrail says.

    Beyond the two dominant markets, McGrail sees pockets of activity but no challenge to the balance of the portfolio. In Qatar, he points to a recovery taking shape towards the end of last year, with WSP active on the Qatar Children’s Museum and continuing its long-running work with the Public Works Authority (Ashghal). Oman is generating masterplanning work, including reviving the Blue City scheme.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20545689/main.gif
    Colin Foreman
  • Gas-fired projects drive resilience in UAE power sector

    14 October 2026

     

    The $3bn Taweelah C combined-cycle gas turbine (CCGT) project has been the UAE power sector’s standout contract award this year, accounting for the majority of the $4.17bn in awards as of early September.

    The total is well below the record $12.02bn awarded in 2025, when Abu Dhabi’s $6bn round-the-clock solar photovoltaic (PV) and battery energy storage system (bess) project lifted the market to record levels. However, 2026 remains broadly consistent with recent years, compared with $5.93bn in 2024 and $3.05bn in 2023.

    According to MEED Projects, generation accounted for $3.06bn across three awards, while transmission contracts totalled $1.11bn.

    Gas-fired focus

    Emirates Water & Electricity Company (Ewec) signed the power-purchase agreement (PPA) for Taweelah C in June with a consortium comprising Abu Dhabi National Energy Company (Taqa), Saudi Arabia’s Al-Jomaih Energy & Water Company and Singapore’s Sembcorp Industries.

    The scale of the 2.5GW independent power producer (IPP) provides a useful lens through which to view the wider market. Although the UAE continues to expand solar generation and battery storage, it is still investing heavily in flexible thermal capacity to support rising electricity demand and a grid with significant renewable generation.

    Major gas-fired opportunities are also moving into the Northern Emirates, with state utility Etihad Water & Electricity (EtihadWE) preparing to receive offers from five contractor groups for the 2.6GW Al-Zawra CCGT project in Ajman.

    The project follows the retirement of EtihadWE’s older 200MW Al-Zawra gas plant in 2023. With Ewec acting as offtaker, the scheme also points to a wider role for EtihadWE in developing large-scale generation.

    It is understood that the Ajman project will be the first of at least three planned power plant projects procured by the utility under a new long-term roadmap for future projects across both power and water.

    Abu Dhabi’s 3.3GW Al-Nouf IPP is another major gas-fired plant moving towards execution. Japan’s Sumitomo Corporation is expected to formally sign the PPA by the end of the year, while the joint venture of Spain’s Tecnicas Reunidas and Egypt’s Orascom Construction is also set to be confirmed as the engineering, procurement and construction (EPC) contractor.

    To put this into context, the deal would make 2026 the second most valuable year for power sector investment on record, eclipsing both 2017 and 2018, when contract awards in the UAE reached $7.39bn and $7.27bn, respectively.

    Solar and storage

    The UAE’s renewable procurement is increasingly combining solar generation with storage to provide electricity beyond daylight hours.

    Dubai Electricity & Water Authority (Dewa) is preparing to award the seventh phase of the Mohammed Bin Rashid Al-Maktoum Solar Park, with Abu Dhabi Future Energy Company (Masdar) submitting the lowest tariff for the project in July.

    China’s BYD will act as a bess supplier for the project, which combines 2,000MW of PV capacity with a 1,400MW bess designed to discharge for six hours, equivalent to 8,400MWh of stored energy.

    The storage component will allow Dewa to use more solar power after sunset, reducing the gap between daytime generation and the evening demand peak.

    The 1,800MW sixth phase is also nearing completion, with Larsen & Toubro delivering the estimated $1.5bn project for Shuaa Energy 4, the project company formed by Dewa and Masdar.

    Dewa has increased the planned capacity of the solar park to 7,260MW by 2030, from its earlier target of 5,000MW.

    Furthermore, Ewec is advancing its 1.5GW Al-Zarraf solar PV plant, with EDF and Korea Western Power Company selected as the consortium to develop the project.

    Grid expansion

    Multibillion-dollar IPP schemes have driven annual award values in recent years, while transmission work continues to provide a steadier flow of opportunities for contractors and equipment suppliers.

    Transmission awards fell to $1.11bn across 22 packages in 2026, from $2.98bn in 2025, reflecting the absence of a comparable large-scale package rather than a halt in network investment.

    Ewec and Taqa are expanding 400kV and 132kV networks across Abu Dhabi and the Northern Emirates, while Dewa continues to reinforce its cable and substation systems in Dubai.

    In September, EtihadWE received bids for a contract to carry out a techno-economic feasibility study for a proposed 2GW subsea electricity interconnector with India.

    The proposed 1,400-kilometre link would be the UAE’s first direct subsea cross-border electricity interconnector, illustrating a potential longer-term ambition to connect the UAE to wider regional and international power markets.

    Earlier this year, the GCC Interconnection Authority awarded Omexom, part of France’s Vinci Group, a contract to build a 400kV overhead transmission line between the UAE and Saudi Arabia.

    In October, the UAE and Saudi Arabia signed a memorandum of understanding to advance cross-border electricity interconnection, paving the way for feasibility studies on power exchange, commercial electricity trading and the expansion of the wider GCC interconnection grid.

    Waste-to-energy

    Waste-to-energy continues to become an increasingly important part of the UAE’s infrastructure pipeline as the country seeks to reduce landfill dependence and diversify its power mix through alternative generation sources.

    Dubai Municipality recently invited developers to submit expressions of interest for its planned Jebel Ali waste-to-energy public-private partnership, a greenfield facility designed to treat up to 6,000 tonnes of municipal solid waste a day.

    According to a source, the municipality plans to prequalify developers later this year, then issue a request for proposals in the first quarter of 2027.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20582379/main.gif
    Mark Dowdall