Firms express interest in new Hail and Ghasha phase
22 May 2023

Register for MEED's guest programme
Contractors have expressed interest in tendering for new engineering, procurement and construction (EPC) contracts for Abu Dhabi National Oil Company’s (Adnoc’s) multibillion-dollar Hail and Ghasha sour gas development.
Adnoc started a fresh EPC tendering round for the project on 29 April. Contractors were issued expression of interest (EoI) documents just days after the cancellation of the pre-construction services agreements (PCSAs) that had been awarded in January.
Firms were initially asked to express interest in the new EPC tendering round by 14 May. According to sources, the deadline was extended until 19 May and firms submitted EoIs by that date.
The new EoI document details Adnoc’s latest EPC execution strategy for the Hail and Ghasha development. Under these plans, the offshore and onshore scope of work has been divided into three packages:
- Package one: Subsea pipelines, umbilicals, cables, risers and other offshore structures
- Package two: Offshore drilling centre facilities, the Ghasha offshore processing plant and central living quarters
- Package three: The Manayif onshore processing plant, including offsite export pipelines and tie-ins, utilities, the main control building and process buildings. Work on a Ruwais sulphur-handling terminal and other non-process buildings is an optional scope for this package.
An Adnoc spokesperson previously told MEED: “Adnoc and our international partners remain committed to delivering the gas mandated from the Ghasha concession. We do not comment on market speculation.”
PCSAs cancelled
The PCSAs signed in January with two consortiums, comprising three contractors each, marked the start of detailed engineering work and procurement of critical long-lead items for the offshore and onshore scope of work on the Hail and Ghasha development.
A consortium of France-headquartered Technip Energies, South Korean contractor Samsung Engineering and Italy’s Tecnimont was awarded the PCSA for the onshore package. The contractors revealed the value of the contract to be approximately $80m.
Italian contractor Saipem, Abu Dhabi’s National Petroleum Construction Company (NPCC) and state-owned China Petroleum Engineering & Construction Company (CPECC) won the PCSA for the offshore package, worth $60m.
Previously, the onshore work on the Hail and Ghasha scheme involved the construction of a gas process plant, pipeline network and new gas gathering units.
The offshore PCSA covered installing offshore platforms, gas compression facilities and more than 400 kilometres of subsea pipelines.
The reason for these PCSAs being annulled is unclear, but sources previously said the cost estimates submitted for the project were higher than the client’s overall budget.
Protracted project timeline
The cancelled PCSAs were part of an early engagement process with contractors that Adnoc started following the termination of at least two earlier bidding rounds.
US engineering firm Bechtel completed the project’s original front-end engineering and design (feed) in 2019, with tenders for four EPC packages issued soon after.
Following the submission of commercial bids in early 2021, Adnoc made revisions to the feed as part of an optimisation process started by Technip Energies in November 2021. The revised feed aimed to reduce the scheme’s overall capital expenditure, which was previously estimated to be as high as $15bn.
The four original EPC packages were consolidated into two integrated offshore and onshore packages, thought to be worth as much as $5bn and $5.5bn, respectively, based on the previous version of the project.
MEED reported in September last year that early engagement contractors had submitted proposals for the detailed engineering work on the Hail and Ghasha development. The January PCSAs are understood to have been issued based on these proposals.
Hail and Ghasha fields
The Hail and Ghasha fields, along with the Hair Dalma, Satah, Bu Haseer, Nasr, Sarb, Shuwaihat and Mubarraz fields, are located in Abu Dhabi’s offshore Ghasha concession.
Adnoc holds the majority 55 per cent stake in the Ghasha concession. The other stakeholders are Italian energy major Eni with 25 per cent, Germany’s Wintershall Dea with 10 per cent and Austria’s OMV and Russia’s Lukoil, each with 5 per cent.
Adnoc plans to produce more than 1.5 billion cubic feet a day of sour gas from the Ghasha concession by the middle of this decade. This target is aligned with the company’s broader goal of achieving gas self-sufficiency for the UAE by 2030.
In November 2021, Adnoc and its partners in the Ghasha concession awarded two EPC contracts for the Dalma offshore sour gas development project. Abu Dhabi’s NPCC and Spain-headquartered Tecnicas Reunidas won contracts worth $1.46bn to execute offshore and onshore EPC works on the Dalma project, respectively.
Four artificial islands have already been completed in the Ghasha concession, and development drilling is under way.
In addition, Adnoc awarded two contracts totalling $2bn to its subsidiary Adnoc Drilling in July last year for the Hail and Ghasha offshore sour gas field development project.
The awards comprise a $1.3bn contract for integrated drilling services and fluids, and a $711m contract to provide four island drilling units. Their duration is 10 years.
Adnoc also awarded a third contract, valued at $681m, to another subsidiary, Adnoc Logistics & Services, to provide offshore logistics and marine support services for the planned Hail and Ghasha development.
Exclusive from Meed
-
-
-
-
Frontrunner emerges for Bahrain’s Hidd IWP6 July 2026
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Contractor begins Burj Khalifa metro station expansion works6 July 2026

Dubai’s Roads & Transport Authority (RTA) has started construction on the expansion and upgrade of the Burj Khalifa/Dubai Mall metro station.
The main construction works are being carried out by Turkish contractor Mapa Group.
The RTA also announced that it is temporarily closing its bus and taxi service road at the metro station due to ongoing construction works, until the end of this year.
The contract was tendered in January 2025, as MEED exclusively reported.
The design-and-build contract covers the lift and station expansion works, including demolishing and replacing the existing pod entrance with a three-storey building. The new entrance will provide links to the Dubai Mall link bridge at the concourse level and a direct connection to the Rashidya platform.
The project will add three new hydraulic lifts and four escalators. The concourse level will be expanded to include a connection to the link bridge and 10 new retail units.
The project will also add two new hydraulic lifts and escalators within the Sheikh Zayed roadside extension serving the UAE Exchange platform.
The Burj Khalifa/Dubai Mall station expansion was first tendered as part of the RTA’s plan to upgrade four Dubai Metro stations in 2018.
Subsequently, the expansion works on the station were put on hold, whereas construction on the Damac, UAE Exchange and Dubai Internet City stations was completed in 2021.
Local firm Al-Shafar General Contracting undertook the expansion works.
Traffic at the Burj Khalifa/Dubai Mall station peaks on New Year’s Eve. In an official statement published by Emirates News Agency, the RTA said that last New Year’s Eve, Dubai Metro accommodated over 1 million passengers on its Red and Green lines, while the Dubai Tram transported 55,391 passengers.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17563784/main0706.png -
Morocco tenders 300MW El-Menzel pumped-storage plant6 July 2026
Morocco's Office National de l'Electricité et de l'Eau Potable (Onee) has tendered the main engineering, procurement and construction (EPC) contract for the 300MW El-Menzel pumped-storage hydropower project.
The bid submission deadline is 30 September.
The El-Menzel pumped energy transfer station will be developed in the Sefrou area of Morocco's Fes-Boulemane region. The project is intended to support Morocco's renewable energy programme and contribute to the country's target of sourcing 52% of its energy mix from renewables by 2030.
The project scope comprises upper and lower reservoirs, a 400kV substation and a 44-kilometre (km) transmission line. It also inlcudes the construction of 10km of access roads and associated facilities. The project is estimated to cost $244m.
According to regional project tracker MEED Projects, three consortiums prequalified to bid for the EPC contract last year.
They were:
- China International Water & Electric, Yellow River Engineering Consulting (China), Harbin Electric Machinery (China), Harbin Electric International (China) and Jet Contractors (Morocco)
- Sinohydro (China) and Andritz Hydro (Austria)
- Webuild (Italy) and Dongfang Electric International Corporation (China)
The project is being financed by the African Development Bank and Germany's KfW Development Bank.
Morocco's renewable energy plans received a boost recently, when the World Bank approved $265m in financing for a separate 300MW pumped hydropower storage project in Ifahsa in Chefchaouen Province.
The facility will act as a rechargeable battery for the national electricity grid, storing excess electricity generated from solar and wind projects before releasing it during periods of peak demand.
The Ifahsa and El-Menzel projects are both being developed by Onee as part of a broader energy storage strategy that targets 1GW of new pumped hydropower by 2030.
Onee commissioned the 350MW Abdelmoumen pumped-storage plant in 2024.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17562793/main.jpg -
Iraq readies tender for additional Al-Faw port piers6 July 2026
Iraq is preparing to issue a tender inviting international contractors to bid for a contract to build the remaining piers at Al-Faw Grand Port in Basra.
According to local media reports, construction work on the project's first phase is expected to be completed by the end of this year.
This will be followed by port operations, for which the client, state-owned General Company for Ports of Iraq, shortlisted three out of the initial 11 international companies that were invited to bid, as MEED reported last year.
At the time, the shortlisted companies included:
- China Merchants Port Group (China)
- Evergreen (Taiwan)
- CMA CGM (France)
- Mediterranean Shipping Company (Switzerland)
- Adani Group (India)
- International Container Terminal Services (Philippines)
- Cosco (China)
- ABM Global Shipping (UAE)
- AD Ports (UAE)
In April last year, Iraq’s Shafaq News Agency reported that the country was in talks with US-based KBR to assist in operating the Al-Faw port.
KBR was expected to provide training in port operations and management to Iraqi personnel, along with related services.
The first phase of the project is scheduled for completion by the end of this year, while the second phase is expected to be completed by 2029.
The first phase of the project cost approximately $5bn, including $2.5bn for its five main piers, which were constructed by South Korea’s Daewoo Engineering & Construction.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17562198/main.jpg -
Frontrunner emerges for Bahrain’s Hidd IWP6 July 2026

Saudi Arabia's Acwa has emerged as the frontrunner for a contract to develop and operate Bahrain’s Al-Hidd independent water project (IWP) following the disqualification of the only other bidder for the plant, a source has told MEED.
The seawater reverse osmosis (SWRO) plant is the state's first IWP project. It is expected to have a production capacity of about 60 million imperial gallons a day (MIGD), equivalent to roughly 272,000 cubic metres a day of potable water.
Acwa offered to develop the project at a levelised cost of water of BD0.276 ($0.73) a cubic metre, according to details published on Bahrain’s Tender Board on 2 July.
GS Inima (South Korea/Spain) was the only other bidder for the project.
Bids for the project had been submitted earlier this year.
The source added that Acwa's financial bid is now under evaluation and has yet to be selected as the preferred bidder. This will only be determined "subject to compliance with the [request for proposal] requirements".
Nine companies and consortiums had previously been shortlisted following the completion of the prequalification process last August.
The facility will be developed on a brownfield site and is expected to be fully operational by 2029. It will be developed using a build, own and operate (BOO) model for 20-25 years and aims to help expand Bahrain’s water infrastructure to meet projected demand based on its 2030 masterplan.
This includes doubling the state's installed power generation capacity to over 10GW by 2030, according to UK data analytics firm GlobalData.
Sitra IWPP
Bahrain's 1.2GW Sitra independent water and power plant (IWPP) project is also advancing, with two bids having been submitted for the plant in June.
The offers were made by Acwa and Abu Dhabi National Energy Company (Taqa). The technical element of the bid was opened on 18 June.
The Sitra IWPP is a combined-cycle gas turbine plant and is expected to have a production capacity of about 1,200MW of electricity. The project’s SWRO desalination facility will have a production capacity of 30 MIGD of potable water.
The plant is Bahrain’s fourth IWPP, replacing the previously planned Al-Dur 3. The Sitra IWPP is expected to be fully operational by the second quarter of 2029.
The Bahraini Electricity & Water Authority’s transaction advisory team for the two BOO projects comprises KPMG Fakhro as the financial consultant and Trowers & Hamlins as the legal consultant.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17562089/main.jpg -
Chinese contractor completes 70% of Iraq oil project6 July 2026

The project to develop new crude oil processing facilities at Iraq’s Rumaila field is 70% complete, according to industry sources.
The project scope for the planned plant in Mishrif Qurainat includes developing two new oil trains, each with a capacity of 120,000 barrels a day (b/d).
When it was originally announced, the planned plant in Mishrif Qurainat was the first new crude oil processing facility project at the oil field in 10 years.
In the fourth quarter of 2022, China Petroleum Engineering & Construction Corporation signed a contract for the design, procurement, construction and testing of the crude oil processing facilities.
The contract was valued at about $386m, and construction was expected to take three years to complete.
Since 2022, the project has seen significant delays and the date for completion is currently uncertain, according to industry sources, as bringing the new crude processing facility online is no longer a priority for the client.
One source said: “Work is continuing on this project at a slow pace because the client is not prioritising commissioning the oil trains.
“The companies that form the joint venture, which operates the Rumaila field, are dealing with a range of other issues right now as a result of the regional war and disruption to shipping through the Strait of Hormuz.”
Rumaila is operated by Rumaila Operating Organisation (ROO).
ROO is a joint venture formed by state-owned Basra Oil Company; Iraq’s State Oil Marketing Organisation (Somo); and Basra Energy Company, a joint venture owned by UK-based oil company BP and PetroChina.
PetroChina is the listed arm of state-owned China National Petroleum Corporation.
Oil exports from Iraq have dropped steeply since the US and Israel attacked Iran on 28 February, leading to a regional conflict.
The conflict has caused significant disruption to Iraq’s oil exports via the Strait of Hormuz.
This has had a knock-on impact for production in the country, where output from many major oil fields has had to stop or has been significantly lowered.
One source said: “At the moment, Basra Oil Company is prioritising restoring production, where it is possible, from assets that have seen reductions in output.
“They are using a lot of resources just to keep existing facilities online and restarting facilities that have stopped due to the crisis.
“Commissioning a brand new project, like the Mishrif Qurainat facilities, is unlikely to be a priority until Iraq’s oil sector returns to a situation that is more like business as usual prior to the conflict with Iran.”
Rumaila is the second-largest producing field in the world, and it is estimated to have about 17 billion barrels of recoverable oil remaining.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17561830/main.jpg
