Firms express interest in new Hail and Ghasha phase

22 May 2023

 

Register for MEED's guest programme 

Contractors have expressed interest in tendering for new engineering, procurement and construction (EPC) contracts for Abu Dhabi National Oil Company’s (Adnoc’s) multibillion-dollar Hail and Ghasha sour gas development.

Adnoc started a fresh EPC tendering round for the project on 29 April. Contractors were issued expression of interest (EoI) documents just days after the cancellation of the pre-construction services agreements (PCSAs) that had been awarded in January.

Firms were initially asked to express interest in the new EPC tendering round by 14 May. According to sources, the deadline was extended until 19 May and firms submitted EoIs by that date.

The new EoI document details Adnoc’s latest EPC execution strategy for the Hail and Ghasha development. Under these plans, the offshore and onshore scope of work has been divided into three packages:

  • Package one: Subsea pipelines, umbilicals, cables, risers and other offshore structures
  • Package two: Offshore drilling centre facilities, the Ghasha offshore processing plant and central living quarters
  • Package three: The Manayif onshore processing plant, including offsite export pipelines and tie-ins, utilities, the main control building and process buildings. Work on a Ruwais sulphur-handling terminal and other non-process buildings is an optional scope for this package.

An Adnoc spokesperson previously told MEED: “Adnoc and our international partners remain committed to delivering the gas mandated from the Ghasha concession. We do not comment on market speculation.”

PCSAs cancelled

The PCSAs signed in January with two consortiums, comprising three contractors each, marked the start of detailed engineering work and procurement of critical long-lead items for the offshore and onshore scope of work on the Hail and Ghasha development.

A consortium of France-headquartered Technip EnergiesSouth Korean contractor Samsung Engineering and Italy’s Tecnimont was awarded the PCSA for the onshore package. The contractors revealed the value of the contract to be approximately $80m.

Italian contractor Saipem, Abu Dhabi’s National Petroleum Construction Company (NPCC) and state-owned China Petroleum Engineering & Construction Company (CPECC) won the PCSA for the offshore package, worth $60m.

Previously, the onshore work on the Hail and Ghasha scheme involved the construction of a gas process plant, pipeline network and new gas gathering units.

The offshore PCSA covered installing offshore platforms, gas compression facilities and more than 400 kilometres of subsea pipelines.

The reason for these PCSAs being annulled is unclear, but sources previously said the cost estimates submitted for the project were higher than the client’s overall budget.

Protracted project timeline

The cancelled PCSAs were part of an early engagement process with contractors that Adnoc started following the termination of at least two earlier bidding rounds.

US engineering firm Bechtel completed the project’s original front-end engineering and design (feed) in 2019, with tenders for four EPC packages issued soon after.

Following the submission of commercial bids in early 2021, Adnoc made revisions to the feed as part of an optimisation process started by Technip Energies in November 2021. The revised feed aimed to reduce the scheme’s overall capital expenditure, which was previously estimated to be as high as $15bn.

The four original EPC packages were consolidated into two integrated offshore and onshore packages, thought to be worth as much as $5bn and $5.5bn, respectively, based on the previous version of the project.

MEED reported in September last year that early engagement contractors had submitted proposals for the detailed engineering work on the Hail and Ghasha development. The January PCSAs are understood to have been issued based on these proposals.

Hail and Ghasha fields

The Hail and Ghasha fields, along with the Hair Dalma, Satah, Bu Haseer, Nasr, Sarb, Shuwaihat and Mubarraz fields, are located in Abu Dhabi’s offshore Ghasha concession.

Adnoc holds the majority 55 per cent stake in the Ghasha concession. The other stakeholders are Italian energy major Eni with 25 per cent, Germany’s Wintershall Dea with 10 per cent and Austria’s OMV and Russia’s Lukoil, each with 5 per cent.

Adnoc plans to produce more than 1.5 billion cubic feet a day of sour gas from the Ghasha concession by the middle of this decade. This target is aligned with the company’s broader goal of achieving gas self-sufficiency for the UAE by 2030.

In November 2021, Adnoc and its partners in the Ghasha concession awarded two EPC contracts for the Dalma offshore sour gas development project. Abu Dhabi’s NPCC and Spain-headquartered Tecnicas Reunidas won contracts worth $1.46bn to execute offshore and onshore EPC works on the Dalma project, respectively.

Four artificial islands have already been completed in the Ghasha concession, and development drilling is under way.

In addition, Adnoc awarded two contracts totalling $2bn to its subsidiary Adnoc Drilling in July last year for the Hail and Ghasha offshore sour gas field development project.

The awards comprise a $1.3bn contract for integrated drilling services and fluids, and a $711m contract to provide four island drilling units. Their duration is 10 years.

Adnoc also awarded a third contract, valued at $681m, to another subsidiary, Adnoc Logistics & Services, to provide offshore logistics and marine support services for the planned Hail and Ghasha development.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10872981/main2245.jpg
Indrajit Sen
Related Articles
  • EtihadWE tenders $150m Ajman substation project

    21 July 2026

    The UAE’s Etihad Water & Electricity (EtihadWE) has tendered a contract to build three new substations in Ajman.

    Estimated to cost $150m, the project involves the construction of three new 132/11kV substations in the Bahya, Rumaila and Liwara districts. It also includes associated 132kV underground cabling works to connect the substations to the existing transmission network.

    The bid submission deadline is 10 August.

    According to tender documents, the project will add distribution capacity to support load growth and improve the security of electricity supply in the emirate.

    The scope of work includes site preparation, construction of three substation buildings and foundations, installation of 132kV GIS/AIS switchgear, 132/11kV power transformers and 11kV switchgear, as well as protection, control, Scada and telecommunications systems.

    Etihad WE is responsible for electricity and water services in Ajman, Umm Al-Quwain, Ras Al-Khaimah, Fujairah and parts of Sharjah. The utility has been investing in new substations and transmission infrastructure as electricity demand continues to increase across the Northern Emirates.

    This includes a 132/33/11kV substation project on Al-Marjan Island in Ras Al-Khaimah. Construction work is ongoing on the project, with Maetal Dubai serving as the main contractor.

    EtihadWE is also finalising a new masterplan that will cover network capacity requirements and expansion priorities for the next 10 to 15 years.

    In June, Abdulla Al-Khemeiri, chief operations officer, told MEED: “We are currently reviewing it, and we need to obtain shareholder approval first. Once it is approved, it will be released, hopefully by the end of the year.” 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17710661/main.jpg
    Mark Dowdall
  • Seven seeks contractors for Dammam water park and hotel

    21 July 2026

     

    Saudi Entertainment Ventures (Seven), a wholly owned subsidiary of the Public Investment Fund, is preparing to shortlist general contractors for the main construction package of its Dammam Water Park & Hotel project in the Al-Hamra district.

    The waterfront development sits on a 324,300-square-metre (sq m) plot.

    A notice was issued to contractors in July, and the client is expected to finalise the shortlist by the end of this month.

    Seven is seeking firms capable of delivering a lump-sum, turnkey solution for both the water park and a 321-key lifestyle hotel. Construction is expected to take 24 months from contract award.

    The water park is designed around five themed zones and will feature what is billed as the world’s first double-tornado/triple-wave waterslide.

    The park will include 21 major rides and attractions, 21 food and beverage outlets, 66 cabanas, parking for 1,100 vehicles and a daily peak capacity of 4,500 guests.

    Slide procurement has already been completed directly by Seven. The selected contractor will be responsible for locally sourcing slide towers, integrating them with rockwork and secondary steel, and installing the units.

    Detailed design and issued-for-construction packages are complete.

    Marine works, piling, dewatering and site utilities are being progressed separately by the existing early works contractor.

    The hotel component covers roughly 31,700 sq m of gross floor area and will offer 321 guest rooms, four F&B outlets, spa and wellness facilities, a family pool, and meeting, incentive, conference and exhibition space.

    The new contractor’s scope includes superstructure concrete works, façade and roof works, mechanical, electrical and plumbing, interior fit-out and landscaping.

    Seven will consider only contractors with demonstrated experience delivering water parks with complex aquatics, theming and rockwork – either directly or through clearly defined subcontractor partnerships – along with a track record in high-end turnkey hotel fit-outs.

    Construction of Seven’s Dammam entertainment complex is currently under way. In October 2023, Saudi Binladin Group won contracts worth around SR5bn ($1.3bn) from Seven to build two entertainment destinations in the Dammam and Al-Khobar areas of the Kingdom’s Eastern Province.

    The Al-Khobar entertainment complex is being built on reclaimed waterfront land. The complex spans around 300,000 sq m and is also known as ‘The Waves’.

    The Dammam entertainment complex spans 360,000 sq m and is being built on reclaimed land on the Dammam waterfront.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17710096/main.jpg
    Yasir Iqbal
  • Al-Ula appoints equestrian village early works contractor

    21 July 2026

     

    Saudi Arabia’s Royal Commission for Al-Ula (RCU) has awarded a contract for early construction works at the Al-Muatadil Equestrian Village.

    The contract was awarded to Al-Khobar-based Al-Shalawi International Company.

    Canadian engineering firm AtkinsRealis is the project management consultant. UK-headquartered Baker Wilkins & Smith and local firm Al-Hoty Company are the cost consultants.

    Dubai-based SSH is the supervision consultant, and UK-based Hopkins Architects is the lead design consultant.

    RCU announced the project plans in March 2023, including the development of an equestrian hub with two arenas that can accommodate 5,000 and 1,400 spectators, respectively.

    The venue will also include grass polo, sand polo and endurance facilities, with capacities of 600, 400 and 600 seats, respectively.

    These facilities will be complemented by visitor amenities, two stable compounds with capacity for 740 horses, and accommodation and retail outlets for event participants and workers.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17710170/main.jpeg
    Yasir Iqbal
  • Contractors await decision on Riyadh airport sewage plant

    21 July 2026

     

    Seven contractors are awaiting a decision on a contract to build a sewage treatment plant at the King Salman International airport (KSIA) development in Riyadh, according to sources.

    It is understood that bids were submitted to King Salman International Airport Development Company (KSIADC) in March, following the tender’s release earlier this year.

    The plant will treat wastewater generated by the airport and surrounding developments, including passenger terminals, runways, residential districts, commercial facilities and logistics areas.

    The facility will have a treatment capacity of 92,000 cubic metres a day. The contract is estimated to be worth SR700m ($187m).

    The bidders (all local) are:

    • Al-Rawaf Trading & Contracting
    • Almajal Alarabi
    • Nesma Water & Energy
    • Safari Company
    • Saudi Services for Electro-Mechanic Works
    • Washnah Contracting
    • Water & Environment Technologies (Wetico)

    The project scope includes the construction of the treatment plant, the installation of preliminary, secondary and tertiary treatment systems, sewage collection and conveyance pipelines, pumping stations, and electrical and control systems.

    US-headquartered Jacobs is acting as the main project consultant. Commercial operations for the plant are scheduled for 2029.

    The sewage treatment plant is one of several water infrastructure packages planned for the airport. KSIADC is also evaluating bids for a separate $30m engineering, procurement and construction contract covering potable water and fire water tanks and an associated pumping station. The same seven companies have submitted bids for that package.

    Earlier in July, MEED exclusively reported that a joint venture of Beijing-headquartered China Civil Engineering Construction Corporation and Dammam-based Mofarreh AlHarbi & Partners had won a deal to undertake the enabling and substructure works for Terminal 6 at KSIA.

    The latest development followed KSIADC’s receipt of prequalification statements from contractors on 1 July for two new packages at KSIA.

    These include the construction of a permanent East-West corridor and landside access roads serving the North and South terminals.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17709281/main.jpg
    Mark Dowdall
  • Dubai Municipality awards Tasreef drainage contract

    21 July 2026

     

    Dubai Municipality has awarded local firm Detech Contracting the engineering, procurement and construction (EPC) contract for the TF-15-C1 package of its Tasreef Rainwater Drainage Network programme.

    It is understood the municipality issued the letter of award for the contract earlier this month, covering the construction of a stormwater drainage system along Al-Wasl Road and communities west of the Dubai Canal.

    The project includes the construction of a gravity-based stormwater pipeline network with diameters of up to 3.5 metres. It is estimated to cost $100m.

    It was tendered in February through the government’s Sewerage and Recycled Water Projects Department, with bids submitted in April.

    The package forms part of the wider Tasreef initiative, which is intended to improve Dubai’s flood resilience.

    The TF-15-C2 package was recently awarded to China State Construction Engineering Corporation for a stormwater drainage network project located along Umm Suqeim Road in the Al-Barsha and Al-Quoz areas of Dubai.

    The project is estimated to cost $162m and includes the construction of about 20 kilometres of new stormwater pipelines. Similar to the C1 package, it is located west of the Dubai Canal and will connect the Al-Quoz 3 and Al-Quoz 4 industrial areas with Al-Quoz 1.

    Separately, Al-Kharafi has won a drainage EPC contract (Ds207) to upgrade an existing pumping station for the municipality, a source said. The package focuses mainly on mechanical works and is valued at about $39m.

    In May, MEED reported that local firm Nael Construction & Contracting had signed a contract with Dubai Municipality to build a sewage and stormwater drainage system in Dubailand.

    The project (DS-204-C1) involves the construction of a drainage system with sewage gravity pipelines of up to 2,200mm in diameter.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17707980/main.jpg
    Mark Dowdall