Firms express interest in new Hail and Ghasha phase

22 May 2023

 

Register for MEED's guest programme 

Contractors have expressed interest in tendering for new engineering, procurement and construction (EPC) contracts for Abu Dhabi National Oil Company’s (Adnoc’s) multibillion-dollar Hail and Ghasha sour gas development.

Adnoc started a fresh EPC tendering round for the project on 29 April. Contractors were issued expression of interest (EoI) documents just days after the cancellation of the pre-construction services agreements (PCSAs) that had been awarded in January.

Firms were initially asked to express interest in the new EPC tendering round by 14 May. According to sources, the deadline was extended until 19 May and firms submitted EoIs by that date.

The new EoI document details Adnoc’s latest EPC execution strategy for the Hail and Ghasha development. Under these plans, the offshore and onshore scope of work has been divided into three packages:

  • Package one: Subsea pipelines, umbilicals, cables, risers and other offshore structures
  • Package two: Offshore drilling centre facilities, the Ghasha offshore processing plant and central living quarters
  • Package three: The Manayif onshore processing plant, including offsite export pipelines and tie-ins, utilities, the main control building and process buildings. Work on a Ruwais sulphur-handling terminal and other non-process buildings is an optional scope for this package.

An Adnoc spokesperson previously told MEED: “Adnoc and our international partners remain committed to delivering the gas mandated from the Ghasha concession. We do not comment on market speculation.”

PCSAs cancelled

The PCSAs signed in January with two consortiums, comprising three contractors each, marked the start of detailed engineering work and procurement of critical long-lead items for the offshore and onshore scope of work on the Hail and Ghasha development.

A consortium of France-headquartered Technip EnergiesSouth Korean contractor Samsung Engineering and Italy’s Tecnimont was awarded the PCSA for the onshore package. The contractors revealed the value of the contract to be approximately $80m.

Italian contractor Saipem, Abu Dhabi’s National Petroleum Construction Company (NPCC) and state-owned China Petroleum Engineering & Construction Company (CPECC) won the PCSA for the offshore package, worth $60m.

Previously, the onshore work on the Hail and Ghasha scheme involved the construction of a gas process plant, pipeline network and new gas gathering units.

The offshore PCSA covered installing offshore platforms, gas compression facilities and more than 400 kilometres of subsea pipelines.

The reason for these PCSAs being annulled is unclear, but sources previously said the cost estimates submitted for the project were higher than the client’s overall budget.

Protracted project timeline

The cancelled PCSAs were part of an early engagement process with contractors that Adnoc started following the termination of at least two earlier bidding rounds.

US engineering firm Bechtel completed the project’s original front-end engineering and design (feed) in 2019, with tenders for four EPC packages issued soon after.

Following the submission of commercial bids in early 2021, Adnoc made revisions to the feed as part of an optimisation process started by Technip Energies in November 2021. The revised feed aimed to reduce the scheme’s overall capital expenditure, which was previously estimated to be as high as $15bn.

The four original EPC packages were consolidated into two integrated offshore and onshore packages, thought to be worth as much as $5bn and $5.5bn, respectively, based on the previous version of the project.

MEED reported in September last year that early engagement contractors had submitted proposals for the detailed engineering work on the Hail and Ghasha development. The January PCSAs are understood to have been issued based on these proposals.

Hail and Ghasha fields

The Hail and Ghasha fields, along with the Hair Dalma, Satah, Bu Haseer, Nasr, Sarb, Shuwaihat and Mubarraz fields, are located in Abu Dhabi’s offshore Ghasha concession.

Adnoc holds the majority 55 per cent stake in the Ghasha concession. The other stakeholders are Italian energy major Eni with 25 per cent, Germany’s Wintershall Dea with 10 per cent and Austria’s OMV and Russia’s Lukoil, each with 5 per cent.

Adnoc plans to produce more than 1.5 billion cubic feet a day of sour gas from the Ghasha concession by the middle of this decade. This target is aligned with the company’s broader goal of achieving gas self-sufficiency for the UAE by 2030.

In November 2021, Adnoc and its partners in the Ghasha concession awarded two EPC contracts for the Dalma offshore sour gas development project. Abu Dhabi’s NPCC and Spain-headquartered Tecnicas Reunidas won contracts worth $1.46bn to execute offshore and onshore EPC works on the Dalma project, respectively.

Four artificial islands have already been completed in the Ghasha concession, and development drilling is under way.

In addition, Adnoc awarded two contracts totalling $2bn to its subsidiary Adnoc Drilling in July last year for the Hail and Ghasha offshore sour gas field development project.

The awards comprise a $1.3bn contract for integrated drilling services and fluids, and a $711m contract to provide four island drilling units. Their duration is 10 years.

Adnoc also awarded a third contract, valued at $681m, to another subsidiary, Adnoc Logistics & Services, to provide offshore logistics and marine support services for the planned Hail and Ghasha development.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10872981/main2245.jpg
Indrajit Sen
Related Articles
  • Libya and Tunisia reschedule joint oil and gas licensing round

    19 August 2026

    The Libyan-Tunisian Joint Oil Exploration, Exploitation and Petroleum Services Company (Joint Oil) has rescheduled its planned licensing round for offshore exploration and development projects in a zone spanning the waters of both countries.

    The bidding process is now due to open on 7 September 2026, with bid submissions due by 8 January 2027.

    Previously, in May, Joint Oil said it planned to open the bid round on 1 August 2026.

    The upcoming round will offer two oil and gas packages. The first is an exploration package across the 3,000-square-kilometre Joint Oil Block, in water depths of 80-120 metres.

    Significant data are available on the geology of this area, including 6,500km of 2D and 1,900 square kilometres of 3D seismic data. Data also exists from a run of legacy wells dating to 1976.

    The second package covers development of the Zarat discovery specifically. This is a gas-condensate reservoir straddling the boundary between Tunisia’s national acreage and the jointly-held Joint Oil Block.

    Joint Oil is equally owned by Tunisia’s national oil company, ETAP, and OLA Energy Holdings, a subsidiary of the Libya Africa Investment Portfolio (LAIP).

    LAIP is a subsidiary of Libya’s sovereign wealth institution, the Libya Investment Authority.

    Joint Oil was established under a bilateral agreement between Libya and Tunisia in 1988 to explore and develop hydrocarbons in offshore areas shared by the two countries.

    The key dates from the new schedule for the licensing round are:

    • 7 September 2026: Bid round opens; qualified offshore operators can apply for access to the Virtual Data Room
    • 9 September 2026: Joint Oil presents the opportunity at the MMEA Scout Group meeting in London
    • 29-30 September 2026: Joint Oil presents at the World Energy Summit in London
    • 31 December 2026: Bid round closes
    • 8 January 2027: Bid submissions due
    • 26 February 2027: Winning bidders notified
    • 30 April 2027: Formal awards expected

    Texas-based Moyes & Co is acting as a strategic adviser on the licensing round.

    Houston-headquartered Marathon discovered the Zarat field in 1992. It is estimated to hold around 0.4 trillion cubic feet of recoverable gas and 50 million barrels of liquids.

    A previous development project concept centred on a mobile production unit, worth around $1bn, tied back to the nearby Miskar platform.

    Despite this, the field has remained undeveloped for over three decades.

    One of the key challenges to developing the reserve is its high carbon dioxide content.

    Joint Oil has run bid rounds for the acreage before without success, including as recently as late 2023.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18861047/main.jpg
    Wil Crisp
  • UAE cuts trade and financial links with Iran

    19 August 2026

    Register for MEED’s 14-day trial access 

    The UAE has halted all trade, commercial exchanges and financial transactions with Iran until further notice, the Ministry of Foreign Affairs said on 19 August.

    The suspension has been imposed in light of escalations that undermine regional and international peace and security, the ministry said. It did not specify a timeframe for any resumption.

    The ministry rejected allegations regarding the status of the economic relationship between the UAE and Iran, and restated the UAE's commitment to dialogue, cooperation and regional integration as means of advancing peace, stability and prosperity in the region.

    It said the UAE remains committed to safeguarding the integrity of the financial system, in line with international law and global standards.

    The suspension covers the full range of commercial and financial links between the two countries. The UAE has historically been one of Iran's most significant trading partners, with much of the relationship built on re-export trade routed through Dubai to Iranian ports across the Gulf.

    The ministry statement did not detail the mechanism for enforcing the halt, the sectors affected, or arrangements for existing contracts and in-transit cargo.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18857953/main0856.jpg
    Colin Foreman
  • Abu Dhabi begins Dar Al-Funoon Saadiyat construction

    19 August 2026

     

    Register for MEED’s 14-day trial access 

    Abu Dhabi-based piling contractor APCC Piling & Marine Contracting has started the enabling works on Dar Al-Funoon, a cultural development near the Saadiyat Cultural District.

    The project, commissioned by the Department of Culture & Tourism – Abu Dhabi, was designed by the late Canadian-American architect Frank Gehry.

    The venue is scheduled to open in 2030.

    MEED understands that the main contract bids are under evaluation and the project is slated for award soon.

    The complex will feature a multipurpose hall with more than 2,000 seats, a 3,500-seat open-air amphitheatre, a 400-seat studio theatre and a 250-seat jazz venue, bringing total capacity to more than 6,000 across its performance spaces.

    The venue will host leading international productions, delivering high-quality cultural experiences for audiences locally, regionally and globally.

    Upon completion, it will become one of the region’s largest performing arts venues.

    The project was announced by Sheikh Khaled Bin Mohamed Bin Zayed Al-Nahyan, Crown Prince of Abu Dhabi and Chairman of the Abu Dhabi Executive Council in June, as MEED reported.

    During a review of the plans, he was briefed on the architectural concept and the development and construction phases, as well as the venue’s advanced technical capabilities, which are being designed to meet the highest international standards for staging major global productions.

    The announcement is part of the ongoing development of Saadiyat Island, which already includes Louvre Abu Dhabi, Zayed National Museum, Natural History Museum Abu Dhabi, teamLab Phenomena Abu Dhabi and the upcoming Guggenheim Abu Dhabi.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18852155/main4145.jpg
    Yasir Iqbal
  • Contractor wins Dubai Canal drainage deal

    19 August 2026

     

    Register for MEED’s 14-day trial access 

    Local firm Detech Contracting has won an engineering, procurement and construction (EPC) contract to upgrade and rehabilitate the East Dubai Canal stormwater system.

    The project, known as TF-16-C1, is part of Dubai’s Tasreef strategic plan to improve the emirate’s stormwater network, increase flood protection and enhance the resilience of Dubai’s infrastructure.
     
    According to a source, Lebanon's Khatib & Alami has also been appointed as a consultant on the project.

    The works will focus on upgrading existing stormwater infrastructure to increase capacity and improve reliability during heavy rainfall.

    The scope includes upgrading the stormwater drainage system, laying pipelines and constructing manholes and gullies. It also includes the construction of pumping stations and diversion works, site clearance and other associated facilities.

    In February, MEED reported that the municipality had invited consultants to qualify for a contract to supervise three stormwater drainage projects (TF-16-C1, TF-15-C2 and TF-13-C1)

    China State Construction Engineering Corporation announced in July that it had won the EPC contract for the TF-15-C2 stormwater drainage network project located on Umm Suqeim Road in the Al-Barsha and Al-Quoz areas of Dubai.

    MEED understands contractor bids are still being evaluated for the TF-13-C1 project, which focuses on developing a drainage system for the Al-Marmum area.

    Detech has been awarded several packages under the Tasreef programme in the past 18 months.

    These include:

    • TF-16-C1: upgrading and rehabilitation of East Dubai Canal stormwater system
    • TF-15-C1: stormwater drainage system at Al-Wasl Road for communities west of Dubai Canal
    • TF-05-C1: stormwater drainage system in Jebel Ali 
    • TF-04: stormwater drainage system on Sheikh Mohammed Bin Zayed Road and Al-Yalayis Road
    • DS-419: Tasreef rainwater drainage network: West Deira stormwater system upgrade and rehabilitation 

    As MEED exclusively reported, the municipality recently issued a letter of award for the TF-15-C1 project, covering the construction of a stormwater drainage system on Al-Wasl Road and communities west of Dubai Canal.

    The project includes the construction of a gravity-based stormwater pipeline network with diameters of up to 3.5 metres. It is estimated to cost $100m.

    This week, Dubai Municipality also issued three tenders for stormwater and sewerage infrastructure projects serving Hind City, Dubailand and surrounding areas.

    The projects cover drainage networks for Hind 4, connections to the stormwater network in Dubailand and a stormwater trunk line serving Hind 3, Hind 4 and Umm Al-Daman.

    All three have bid submission deadlines of 10 September.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18850438/main.jpg
    Mark Dowdall
  • Maaden and Aramco sign deal to create joint venture

    18 August 2026

    Register for MEED’s 14-day trial access 

    Saudi Arabian Mining Company (Maaden) and Saudi Aramco have signed a shareholders’ agreement to form a joint venture (JV). Maaden will hold a 51% stake in the JV, while Aramco will own the remaining 49%.

    Before signing the shareholders’ agreement, the two Saudi state-owned companies signed a non-binding heads of agreement in January 2025 aimed at establishing the JV.

    “Combining the strengths of two leaders in their respective fields, the JV will focus on copper and other minerals critical to the energy transition,” the two parties said in a joint statement.

    The JV will focus on exploration across Zone 4, also known as the Transition Zone, within the Arabian Platform in Saudi Arabia. Spanning approximately 182,000 square kilometres – nearly 10% of the kingdom’s total land area – the expected exploration area stretches along a 100-kilometre-wide corridor running parallel to the Arabian Shield.

    “It represents a major new opportunity for mineral discovery in the kingdom,” Maaden and Aramco said.

    Copper, which is increasingly significant for electric vehicles, power networks, energy storage and renewable energy systems, will be a main focus of the JV.

    Copper accounts for more than 20% of the $1.2tn mined-metals market. The copper market is currently valued at about $250bn and is projected to grow to more than $400bn by 2035.

    The JV will also explore for other energy transition minerals, including zinc, lead and rare earth elements, “that are expected to be crucial to industries of the future”.

    “Leveraging advanced computational algorithms, [artificial intelligence] AI, and high-performance computing, the JV intends to target areas most likely to contain copper and valuable minerals, accelerating the path from regional screening to target definition and discovery. This is expected to support long-term sector development, reinforce the kingdom’s role in the global minerals value chain, and help meet rising demand for transition minerals,” the partners said.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18833329/main.jpg
    Indrajit Sen