Field report: Riyadh

5 May 2023

 

Register for the MEED.com guest programme 

Contracts worth over $2.7bn have been awarded in Riyadh Province so far this year. 

MEED field researchers visited Riyadh in mid-April to monitor the progress on construction projects including Diriyah Gate, King Salman International Park and Riyadh Sports Boulevard.

The team also called in on two of Saudi Entertainment Ventures' (Seven's) entertainment complexes and several National Housing Company housing schemes, among other projects.

DIRIYAH GATE

At the Diriyah Gate project, construction works are progressing on the digital arts centre Diriyah Art Futures and Heritage Five Star hotel in Samhan district.

MEED researchers were able to get visuals of Diriyah Gate's now-completed restaurant complex, Bujairi Terrace.


Opened in December 2022, Bujairi Terrace comprises 21 restaurants over a 15,000 square-metre area


Elsewhere, construction works have started on the Ministry of Culture's headquarters building at Diriyah, while the site preparatory works are under way at the Northern Cultural District P3 car park, where the ground-breaking ceremony took place recently.

Local/Chinese team begins underground main spine tunnel roundabout base slab works

Structural works are under way at Saudi Electricity Company's Diriyah 380/132/13.8kV substation and the super basement project, which WeBuild is delivering.


Diriyah Development Company's three-floor super basement car park will serve the mixed-use Diriyah Square district, which will include leisure and entertainment, hotels, retail, grade A offices, the King Salman Grand mosque and residential units designed in the traditional Najdi architectural style


KING SALMAN INTERNATIONAL PARK

Structural works are progressing well at the Royal Art Complex, the single biggest project in execution by value at King Salman International Park so far. Modern Building Leaders won the contract, worth $1.3bn, to build the project in 2022.


In addition to the Royal Art Complex, the 1,300-hectare masterplanned King Salman Park project includes a national theatre, museums, galleries, a golf course, and spaces for commercial, hospitality and residential components


Construction on the main tunnels and bridges project continues, with the bridge structure now in place. A joint venture (JV) of Consolidated Contractors Company and El-Seif Engineering Contracting Company is executing the project, which is scheduled for completion in the fourth quarter of 2024.


King Salman Park was launched by King Salman in March 2019, alongside the Green Riyadh, Riyadh Art and Riyadh Sports Boulevard projects


RIYADH SPORTS BOULEVARD

The construction works are ongoing at almost all of the packages for Riyadh Sports Boulevard.

The projects currently in execution at the Riyadh Sports Boulevard include King Abdul-Aziz underpass package 8 and Abu Bakr underpass package 9Zone 1AZone 1BZone 2AZone 5AZone 6: Package A, B, C, D, E and Cycling Bridge.


Riyadh Sports Boulevard – Package 5 Arts District. There are eight districts in total, with districts for entertainment, athletics and sports also planned


SEVEN ENTERTAINMENT COMPLEXES

The structural works are under way at Seven's Al-Hamra entertainment complex (Exit 10), for which Al-Futtaim Engineering has been appointed as the mechanical, electrical and plumbing (MEP) contractor.

Exit 10 is at the most advanced stage of construction out of the 21 planned entertainment complexes in 14 cities across the kingdom.

Meanwhile, early works proceed apace at Seven's Al-Nahdah entertainment complex (Exit 15) project. Consolidated Contractors Company is delivering the project.


Seven is owned by the Public Investment Fund and was formed in December 2017 as part of Riyadh’s push to localise Saudi spending on entertainment under the mandate of Vision 2030


Elsewhere in Riyadh, the client is delivering the housing units for Roshn's Sedra District community homes phase 1A, package 1. Indian contractor Shapoorji Pallonji is carrying out the construction works, which are in the finishing stages.


Located northeast of the Saudi capital, Sedra will consist of over 2,100 residential units, along with public parks, entertainment areas, retail, coffee shops and restaurants, community centres, schools, sports facilities and health care facilities


National Housing Company (NHC) is well on track with building its housing schemes in Riyadh. The infrastructure works are currently under way at the Dahiyat al-Fursan phase 1 project in the north of Riyadh. The work is being carried out by Al-Omaier Trading & Contracting.

Likewise, construction works are at advanced stages at NHC’s Al-Mashraqiya housing complex as well as for several of the packages at the Murcia complex, most notably Narges View, Rabieh Housing, Saraya al-Gwan, Asalah al-Gwan, Rawa Housing and the Al-Muhannadiya complex.


National Housing Company's Al-Mashraqiya housing complex, where construction is at an advanced stage


The foundation works are in progress at Shomoul Holdings’ The Avenues Riyadh project. 

The project is one of the largest commercial malls in the Middle East and includes multiple districts such as Prestige, Grand Avenue, The Souk, The Mall, Electra, Oasis, Grand Plaza, The Forum and The Walk. Nesma & Partners won the project's main construction contract, worth $1.76bn, in 2021.

There is no construction activity at the Mall of Saudi project site. MEED exclusively reported this week that the Dubai-based developer Majid al-Futtaim (MAF) had put the plans for its estimated SR6bn ($1.6bn) project in Riyadh on hold.

By Yasir Iqbal, research manager MEED.com | MEED Projects | MEED Insight

https://image.digitalinsightresearch.in/uploads/NewsArticle/10817164/main.gif
MEED Editorial
Related Articles
  • Contractors prepare bids for Oxagon wastewater plant

    14 September 2026

     

    Contractors are preparing to submit bids to build a wastewater treatment plant for Oxagon, Neom’s industrial cluster.

    The industrial wastewater treatment package will have an initial capacity of 35,000 cubic metres a day (cm/d), supplied in modular trains of 5,000 cm/d each. A separate sanitary wastewater treatment package will have a capacity of 1,000 cm/d.

    The contract is structured as a design-build-operate project and covers the supply, installation and commissioning of industrial and sanitary wastewater treatment packages, as well as three years of operation and maintenance.

    Bids are due on 2 October, a source close to the project told MEED.

    It is understood that Neom’s water utility Enowa issued the request for proposals earlier this year. The plant is designed to provide “interim wastewater treatment” capacity for Neom’s Oxagon Industrial Quarter as industrial development in the area progresses.

    Enowa has described the treatment systems as interim and de-mountable, allowing them to be installed and subsequently removed or relocated as requirements at Oxagon develop. The plant can be expanded to a maximum of 45,000 cm/d.

    The tender documents also state that Neom may consider export credit agency (ECA) financing for the project, with the strength of bidders’ ECA financing proposals forming part of the commercial evaluation.

    The project follows an earlier tender for the Oxagon Village Water Recycling Plant, which was cancelled despite contractors submitting bids in 2024.

    MEED reported at the time that Beijing-based PowerChina, the local Alfanar Company and Cairo-headquartered Orascom had submitted bids for the project. It is understood that these firms are also likely to participate in the latest tender.

    The earlier scheme included truck receiving facilities, pretreatment, biological treatment using food chain reactor technology, tertiary treatment, sludge handling and recycled-water storage.

    The latest procurement appears to represent a reworked approach to wastewater treatment at Oxagon Industrial Quarter, with the previous engineering, procurement and construction scheme replaced by an interim, modular and de-mountable facility.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19640903/main.jpg
    Mark Dowdall
  • Saudi Arabia shuts East-West oil pipeline after drone strikes

    14 September 2026

    Saudi Arabia has temporarily closed its 1,200-kilometre East-West pipeline after it was targeted by multiple drones launched from Iraq, disrupting one of the kingdom’s most critical energy export routes and threatening global oil supplies already strained by conflict across the region.

    The Ministry of Energy said the pipeline, which connects the Abqaiq oil field in the east to the Red Sea port of Yanbu, was hit in the Riyadh and Medina regions on 12 September. Specialised teams have begun securing the facility and assessing damage. A Foreign Ministry statement said the attack resulted in injuries and “some damage that is currently being addressed”.

    The closure removes about 4 million barrels a day from the global market, representing 4% of world oil supply. The pipeline’s role has become increasingly critical since the US-Iran conflict forced a near-complete shutdown of flows through the Strait of Hormuz in March.

    Saudi Arabia has been using the East-West route to bypass the chokepoint, but the assault has left the kingdom dependent on substantially reduced Hormuz exports and Red Sea shipping routes now threatened by Iran-backed Houthi forces in Yemen.

    Iraqi Prime Minister Ali Al-Zaidi’s office confirmed the drone strike on the East-West Pipeline originated in the Maysan province, which borders Iran. The government formally condemned the attack, announced an investigation into the Maysan operations command and dismissed its commander. No armed group has claimed responsibility, but security analysts attribute the strike to Iran-backed militias operating from Iraqi territory.

    Riyadh said it was not retaliating “at this stage”, choosing instead to support Iraqi efforts to prevent further strikes from its territory. 

    The attack comes amid wider regional upheaval. Houthi forces have rapidly advanced along Yemen’s coast, seizing the strategic Mokha port and the Zuqar Island in the southern Red Sea, moving closer to the Bab El-Mandab strait. Saudi authorities said the group simultaneously launched dozens of drones and missiles at the southern kingdom on 11 September, striking civilian and economic targets and injuring 73 people.

    Oil analysts and traders reported that Yanbu’s storage capacity, estimated at around 35 million barrels, now holds supplies sufficient for only five to seven days of exports without pipeline operations. Storage facilities at Egypt’s Ain Sokhna and Sidi Kerir ports have similar constraints. Repair timelines remain uncertain, with sources citing estimates ranging from days to five or six weeks.

    The dual disruption of both the pipeline and Red Sea shipping has compressed global energy supplies. Energy analysts warned that without pipeline repairs, oil prices could return to the $120-a-barrel peak reached earlier in the regional conflict.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19641513/main.gif
    Colin Foreman
  • WSP wins Dammam airport expansion design works

    14 September 2026

    WSP Middle East, the regional arm of Canadian engineering firm WSP, has won a design contract to expand King Fahd International airport in Dammam, Saudi Arabia.

    Dammam Airports Company (DACO) awarded the contract.

    The scope includes designing passenger terminal expansions, facility upgrades, and improvements to airport entrances and access roads.

    It also covers the development of baggage-handling systems, digital services and other associated infrastructure.

    The expansion works will be carried out in line with the airport’s approved masterplan, which targets serving more than 19 million passengers a year by 2030.

    The plan also aims to increase air cargo capacity to more than 600,000 tonnes a year and raise aircraft operational capacity to 77 movements per hour, supported by comprehensive expansions to infrastructure, runways and general aviation facilities.

    This contract forms part of DACO’s ongoing efforts to strengthen the airport ecosystem, enhance operational efficiency, and support the Aviation Programme and Saudi Vision 2030 objectives.

    King Fahd International airport is the kingdom’s third-largest airport by annual passenger traffic, behind Jeddah’s King Abdulaziz International and Riyadh’s King Khaled International.

    DACO was formed in July 2017 to manage, operate and develop King Fahd International airport in Saudi Arabia’s Eastern Province.

    It was established as part of the broader Saudi Vision 2030 privatisation and economic reform programme to corporatise the aviation sector, increase operational efficiency, upgrade infrastructure, and transition state-run airports into commercially viable, world-class regional aviation hubs.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19639910/main.jpg
    Yasir Iqbal
  • Dubai seeks contractors for multibillion-dollar road scheme

    14 September 2026

     

    Register for MEED’s 14-day trial access 

    Dubai’s Roads & Transport Authority (RTA) is seeking contractors to design and build a multibillion-dollar new road that will run parallel to Sheikh Zayed Road.

    MEED understands that the scope covers the construction of about 30 kilometres (km) of works.

    These include about 15km of viaduct along First Al-Khail Street and more than 14.5km of bridge ramps, along with other associated infrastructure works.

    The RTA floated the expression of interest notice to contractors in early September, with a submission deadline of 10 October.

    The project is another significant initiative aimed at alleviating pressure on the existing Sheikh Zayed Road section from Hadiqa Street to Hessa Street.

    Dubai has previously explored bold concepts to expand capacity on Sheikh Zayed Road, including proposals to introduce double-decker sections to add extra lanes without widening the existing corridor.

    The idea was discussed in the context of rising congestion and limited right-of-way along one of the city’s busiest arterial roads, with elevated decks potentially carrying through-traffic while the existing at-grade lanes served local access.

    The plans ultimately progressed as standalone schemes, with subsequent efforts focusing instead on corridor-wide upgrades, interchange improvements and complementary public transport expansions to manage demand more sustainably.

    The latest project aligns with Dubai’s continued investment in upgrading and expanding its road network to keep pace with rapid population growth and rising commuting demand.

    Planning for growth

    Dubai launched the 2040 Urban Master Plan in March 2021, referencing studies indicating that the emirate’s population will reach 5.8 million by 2040, up from 3.3 million in 2020. The daytime population is set to increase from 4.5 million in 2020 to 7.8 million in 2040.

    In December 2022, Sheikh Mohammed Bin Rashid Al-Maktoum, Vice President and Prime Minister of the UAE and Ruler of Dubai, approved the 20-Minute City Policy as part of the second phase of the Dubai 2040 Urban Master Plan. 

    In addition to the road projects, the RTA’s Dubai Metro Blue Line extension and Dubai Metro Gold Line form part of Dubai’s plans to improve residents’ quality of life by cutting journey times, as outlined in the policy.

    The policy aims for residents to have 80% of their daily requirements within a 20-minute journey, on foot or by bicycle. This goal will be achieved by developing integrated service centres with all necessary facilities and increasing population density around mass transit stations.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19639621/main.gif
    Yasir Iqbal
  • Kuwait postpones contractor meeting for $3.3bn gas project

    14 September 2026

     

    State-owned Kuwait Gulf Oil Company (KGOC) has rescheduled a key meeting about the development of the planned onshore gas plant next to the Al-Zour refinery, according to industry sources.

    The project was tendered last month with an estimated budget of $3.3bn and a bid deadline of 29 December 2026.

    If it goes ahead as planned, the project is expected to be the country’s biggest oil and gas sector contract award in more than a decade.

    The meeting with contractors is now scheduled for 14 October 2026. Previously, it was scheduled to take place on 14 September.

    Sources said contractors have not been told why the meeting date was pushed back.

    While the date for the initial meeting with contractors has been postponed, the bid deadline of 29 December 2026 remains the same, according to industry sources.

    The proposed plant will have the capacity to process up to 632 million cubic feet a day of gas and 60,000 b/d a day of condensates from the Dorra offshore field, located in Gulf waters in the Saudi-Kuwait Neutral Zone.

    In February, MEED reported that at least seven companies had shown interest in participating in the tender.

    Contractors that sent representatives to previous meetings to discuss the project include:

    • Samsung E&A (South Korea)
    • Larsen & Toubro (India)
    • Tecnicas Reunidas (Spain)
    • Saipem (Italy)
    • Hyundai Engineering & Construction (South Korea)
    • Hyundai Engineering Company (South Korea)
    • JGC (Japan)

    The tender process is using a fast-track model, which means that Kuwait’s Central Agency for Public Tenders (Capt) will not be involved in the tender process.

    Capt typically reviews the technical and commercial evaluations of bids and verifies that the bidding process is competitive.

    It is understood that not requiring Capt to approve this tender is expected to speed up the tender process.

    Iran disputes ownership of the field, referring to it as Arash.

    Iran claims the field partially extends into Iranian territory and asserts that Tehran should be a stakeholder in its development.

    The Dorra field’s close proximity to Iran could make development difficult due to current security concerns.

    The offshore elements of the wider Dorra field development project are expected to be especially difficult to protect from attacks from Iran.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19639451/main.jpg
    Wil Crisp