Fertiglobe begins next growth chapter in Abu Dhabi

23 December 2024

 

The majority acquisition of ammonia-based fertilisers producer Fertiglobe by Abu Dhabi National Oil Company (Adnoc Group) could be an inflection point in its growth story, CEO Ahmed El-Hoshy says.

Fertiglobe is already the world’s largest seaborne exporter of urea and ammonia combined, exporting to 53 countries with a collective market share of about 10% of global trade.

Moreover, the company has invested about $500m, along with South Korea’s GS Energy Corporation and Japanese investment firm Mitsui & Company, to build a blue ammonia production facility in the Taziz Industrial Chemicals Zone in Abu Dhabi’s Ruwais, with a production capacity of 1 million tonnes a year (t/y).

“Adnoc is thinking about the future. Not just the immediate future, but medium to long term, in line with the move by Dr Sultan [Al-Jaber; group CEO and managing director of Adnoc] to future-proof the business,” El-Hoshy says. 

“So, when you are looking at a molecule like ammonia – where we’re a global leader, and are selling into some of the key markets – it’s a really good meeting of a big integrated energy company that reaches all over the world in traditional energy sales with an existing incumbent in the ammonia space that is operating in it today,” he says. 

“[The process is] not starting from scratch, but you’re starting from existing operations and expanding from there,” El-Hoshy tells MEED.

Adnoc, in a transaction completed in October, increased its shareholding in Fertiglobe to 86.2% through the acquisition of 50% + 1 share held by Netherlands-based OCI Global, which is backed by Egyptian billionaire Nassef Sawiris. The Abu Dhabi energy giant previously held a 36.2% stake in Fertiglobe.

The remaining 13.8% of Fertiglobe’s shares trade on the Abu Dhabi Securities Exchange, following the company’s stock listing in October 2022.

“I was previously at OCI for 15 years. Growing that business in the US and Europe is what I struggled with a little bit, because OCI was not a household name, like Adnoc is. To be able to go into Japan and South Korea, to the big power generators and utilities, to the governments in Europe, and having this long, far-reaching ability with Adnoc really can accelerate that,” the CEO says.

Fertiglobe is also studying the prospect of investing in another blue ammonia production facility in Abu Dhabi 

Ruwais project

In February 2023, the Fertiglobe-led joint venture awarded Italian firm Tecnimont the main contract for executing the engineering, procurement and construction works on the Taziz blue ammonia project.

El-Hoshy says construction work on the project is under way, with piling works ongoing and some of the civil foundation works to take place over the next six months. He expects the blue ammonia complex to enter operations in 2027. 

“We own 30% of the project currently. Mitsui and GS Energy own 10% stakes each. Adnoc, via Taziz, [Abu Dhabi’s industrial holding company] ADQ and some local shareholders own the remaining 50%. But Fertiglobe has now become the low-carbon ammonia vehicle for Adnoc. “So today we are at 30% in the project, and Adnoc is covering the costs till the project becomes operational. Once the project is commissioned, we will be able to acquire, at cost, almost double that of our stake today. Almost 55% that is,” the CEO says.

“To give you a sense, a project like this in the US would comfortably cost north of $1.2-$1.3bn. So that’s a big advantage on the capex side. Also, from the logistics perspective, being able to get to Asia is a huge advantage, versus in the US through the Panama Canal and all the way across the Pacific,” El-Hoshy says of the capex investment in the project. 

“So, there are a lot of key advantages here, obviously with the support of government and regulatory regime and the availability of renewable electricity here, whether it’s nuclear or solar or otherwise.

“Also, being able to share infrastructure in the broader Ruwais area in Abu Dhabi is another big advantage. We’re going to be using shared infrastructure for storage, for exports and for power utilities,” he says.

Second investment

Fertiglobe is also studying the prospect of investing in another blue ammonia production facility in Abu Dhabi, which could also be located within the Taziz industrial complex.

“Outside the one with GS and Mitsui, there’s another 1 million-t/y blue ammonia project that is pre-final investment decision that we’re doing [the] engineering [study] on. It’s called the Rabdan project,” he reveals.

“Adnoc/Fertiglobe is the sole developer of the Rabdan project. But we are going to bring in partners. The project will be handed over to Fertiglobe at cost and operations. But we are involved right from the start in commercialising and developing it,” the CEO says. 

El-Hoshy adds that Fertiglobe will not wait until the commissioning of the first blue ammonia project to make progress on the Rabdan project, and that work on both projects could proceed in parallel.

“We’ve done quite a bit of engineering work, some of it in-house. We we’re still in the [front-end engineering and design] feed stage now, but we’re yet to award any feed contract,” El-Hoshy says.

“Depending upon what the offtakes [agreements with potential customers] look like, we will be able to decide when to pull the trigger on the second [Rabdan] project,” he adds. 

The two projects in Abu Dhabi could add 2 million t/y of output potential, more than doubling Fertiglobe’s current commercial ammonia capacity of 1.6 million t/y and increasing its total sellable capacity to 8.6 million t/y of net ammonia and urea combined, in addition to other announced global projects.

Blue vs green ammonia

Fertiglobe is today, perhaps, one of the only companies in the world that has investments or stakes in both blue and green hydrogen/ammonia production. The company is also involved in a green ammonia project in Egypt, where it signed a 20-year ammonia offtake agreement with Egypt Green Hydrogen in July this year. Fertiglobe will supply the renewable ammonia to Germany’s Hydrogen Intermediary Network Company (Hint.co) following an offtake agreement between the two companies in August.

The signing of the offtake agreement with Hint.co came after Fertiglobe’s successful bid in the first tender by H2Global Foundation to supply green hydrogen-derived ammonia from Egypt to Europe.

“I'd say there is demand for both forms of ammonia right now. But I think when carbon has a price globally, like the carbon border adjusting mechanism in Europe that starts in 2026, you'll start seeing that blue will get the premium over time as that [EU tax] gets implemented. And blue definitely, in terms affordability, is much cheaper than green. So, I say, definitely blue kind of eats green's lunch,” El-Hoshy says.

“Green has technology risk. By technology risk I mean that, you might build all this and then the electrolysers don't work, or you have degradation, or they are up and down. They're very tough to operate, they're very temperamental and they haven't been proven over long periods of time,” he says. 

“And lastly, the EU carbon border tax just focuses on scope 1 and scope 2 emissions, and not scope 3. Scope 1 and 2 emissions for a blue plant, if done in the right way – where you use renewable electricity instead of regular electricity, and you capture over 99% of the CO2, which we intend to do with our blue projects – can be almost identical for a green molecule as a blue,” El-Hoshy says.

“So you think about me producing a much cheaper blue [molecule] without the technology risk and the headache, and I get the same carbon charge as green … that makes a lot more sense.”

https://image.digitalinsightresearch.in/uploads/NewsArticle/13140434/main.gif
Indrajit Sen
Related Articles
  • Oil prices rise above $100 a barrel as conflict escalates

    9 September 2026

    Register for MEED’s 14-day trial access 

    Oil prices rose above $100 a barrel on 9 September for the first time since July as the US-Iran conflict escalated and Iran-backed Houthi forces attacked Saudi energy infrastructure.

    Brent crude futures reached $100.95 a barrel, while US benchmark West Texas Intermediate (WTI) rose to $95.60. Brent had last traded above $100 on 24 July.

    The latest escalation has heightened concerns about oil supplies from the region, with shipping through both the Strait of Hormuz and the Red Sea facing disruption.

    Flows through the Strait of Hormuz, a key route for global oil shipments, had fallen below 2 million barrels a day from about 8-9 million b/d before the latest escalation, according to Rystad Energy.

    At the same time, Houthi attacks on Saudi Arabia threaten another important route for oil exports, with the group targeting energy infrastructure and shipping in and around the Red Sea.

    US strikes on Iranian tankers

    US forces destroyed five Iranian crude oil carriers on 8 September after Iran’s Islamic Revolutionary Guard Corps (IRGC) targeted a US Navy warship with ballistic missiles.

    The US Central Command (Centcom) said the warship successfully evaded two Iranian attacks and that no US personnel were harmed.

    Four of the Iranian vessels – Kaviz, Charminar, Horizon 1 and Riesco – were struck in the Gulf of Oman, while the Derya was attacked near Kharg Island, Iran’s main crude export hub.

    The M/T Riesco subsequently sank in the Gulf of Oman, according to Centcom.

    Iran responded by launching ballistic missiles towards Jordan. Jordan’s armed forces said 18 of 20 missiles were intercepted, with the remaining two falling in unpopulated areas.

    Iran’s IRGC also said it had attacked two US naval vessels, eight oil tankers and 10 other vessels in the Gulf, although it did not identify the vessels or provide evidence of the attacks.

    The latest exchanges mark a further escalation in the US-Iran conflict, which began on 28 February.

    Houthi attacks raise supply concerns

    The conflict has also widened into a renewed confrontation between Saudi Arabia and Yemen’s Iran-backed Houthi movement.

    On 8 September, Saudi authorities said Houthi attacks had targeted civilian and economic sites in Abha, Khamis Mushait, Jazan and Najran in the south of the kingdom, injuring 73 people.

    Saudi Arabia’s Ministry of Energy said several energy sector facilities and installations had been targeted, causing fires and forcing a temporary halt to some operations.

    The Houthis said their attacks were in response to Saudi military action in Yemen, including what they described as attacks on Houthi positions and a Saudi blockade of ports and airports.

    Riyadh condemns attacks

    Saudi Arabia has strongly condemned the Houthi attacks and warned that it would take measures to defend its territory and national assets.

    In a statement on 8 September, the Ministry of Energy said authorities were working to address the impact of the attacks and ensure the safety of facilities and personnel while maintaining operations in accordance with approved plans.

    Saudi Arabia’s Ministry of Foreign Affairs also condemned the attacks and said the kingdom had the right to take measures to defend its sovereignty and protect its citizens, residents and national assets.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19505512/main0138.jpg
    Indrajit Sen
  • What actually slows a gigaproject down

    9 September 2026

     

    Ask anyone delivering a major programme in the GCC what causes delays and sequencing will come up early. Utilities go in too late. Approvals lag behind construction. Stations, depots and access roads are procured as if they belong to different projects rather than one system.

    “None of this is new. The industry has understood these risks for years,” says Alan Caldwell, managing director for transport and infrastructure at WSP Middle East.

    For Caldwell, that is what makes the pattern worth interrogating rather than simply restating.

    “The more important question is why the same issues around interfaces, approvals, stakeholder alignment and delivery sequencing continue to slow major programmes when the risks are already so well understood,” he says.

    The answer, he argues, is not that these programmes are too big or too technically complex. What breaks a schedule is a wider system delivered as a set of disconnected parts; an approval sitting with an authority team with no visibility of the construction sequence downstream; or a station package proceeding without the utilities diversion it depends on.

    “Infrastructure programmes do not struggle because a railway is too large or a highway network is too complex,” Caldwell says. “They encounter difficulties when interconnected elements are delivered in the wrong order.”

    Sequencing decisions are rarely purely technical either, he adds. They are commercial – shaped by which assets need to unlock value first, which phases are tied to funding, and where sales or investment assumptions depend on infrastructure landing in a particular order.

    Approvals sit at the centre of that logic. On many programmes, they become one of the biggest sources of lost time – not because the requirements are unreasonable, but because approvals are not planned, evidenced or owned as part of the delivery logic from day one.

    Caldwell has seen the same pattern across three decades of Gulf delivery, from early work on Palm Jumeirah to today’s region-wide transport programmes.

    “The decisive factor has often been the same: whether interfaces, approvals, responsibilities and delivery sequencing are aligned early enough to prevent complexity becoming delay.”

    Integration needs to be well understood

    “Most programme teams in the region would say they understand the need for integration,” Caldwell says. Fewer are structured to deliver it. “The harder task is turning that understanding into the way projects are actually set up and managed,” he argues.

    Riyadh Metro is the reference point he returns to, precisely because engineering complexity was not the deciding factor in its delivery.

    Coordinating a city-scale transport system meant aligning design, construction, systems, utilities and stakeholder interfaces across every delivery vertical.

    “The lesson for the region today is clear,” Caldwell says. “Ambitious programmes need a delivery model that gives every contributor a shared view of progress, risk, decision-making and the business case driving programme priorities.”

    That shared view, he argues, will be what the next phase of Gulf delivery is judged on.

    Whether clients, consultants, contractors, operators and approval authorities can work to a single delivery logic will be key.

    “This requires more than coordination meetings. It requires integrated ways of working, shared common data environments and governance structures that make risks, decisions and dependencies visible before they become delays,” he says.

    From reporting progress to managing risk before it lands

    Digital tools have a role here, Caldwell says, but not as a headline in themselves.

    Digital twins, programme visualisation and data-led modelling matter only if they help teams identify and address problems before they affect the wider programme.

    “The real value is not technology for its own sake,” he says. “It is the ability to see, in one place, where approvals are outstanding, where interfaces are unresolved, where programme dates are slipping, where clashes are emerging and where decisions need to be escalated."

    None of it works without governance behind it, he cautions. “A dashboard will not resolve a delayed approval if nobody knows who owns the decision, when it needs to be made, or how it should be escalated.”

    Data only has value if the processes and responsibilities around it are clear, which is why Caldwell frames the shift the region needs not as digitisation, but as a move “from programme management as a discipline focused mainly on reporting and coordination, and towards project and programme intelligence”.

    With many of the region’s programmes running for a decade or more, he adds, delivery models also need to flex as funding assumptions, user needs and policy priorities change along the way.

    “The ambition behind the Gulf’s transformation programmes is not in question,” Caldwell says.

    What will determine how much of it is realised on time is whether delivery models evolve at the same pace: earlier integration, clearer approval pathways, shared data environments, and every contributor working to a delivery logic that connects technical sequencing with the funding and operational case behind it.

    “The region’s next challenge is not imagining bigger projects,” he says. “It is changing the way they are delivered, operated and adapted over time.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19502016/main.gif
    Yasir Iqbal
  • Qatari firm wins $221m Qiddiya stadium MEP deal

    9 September 2026

     

    Register for MEED’s 14-day trial access 

    Qatari contractor Elegancia MEP, part of Estithmar Holding, has won a SR829m ($221m) mechanical package contract for the Prince Mohammed Bin Salman Stadium in Qiddiya, Saudi Arabia.

    The contract covers full mechanical, electrical and plumbing (MEP) works for the stadium, and is Elegancia MEP’s largest award in Saudi Arabia to date.

    The 45,000-seat stadium will feature a fully combined retractable pitch, roof and LED wall.

    The stadium’s main construction works are being undertaken by a joint venture of Spanish firm FCC Construction and local firm Nesma & Partners.

    Saudi gigaproject developer Qiddiya Investment Company awarded an estimated SR15bn ($4bn) deal to build the stadium in October 2024, as MEED exclusively reported.

    The contract covered the construction of a multipurpose stadium on top of the 200-metre-high Tuwaiq cliff in the new sports and entertainment district of Qiddiya City.

    Once completed, the stadium will be the home ground for Saudi Pro League football clubs Al-Nassr and Al-Hilal.

    US-based architect Populous is the project consultant.

    The stadium is one of the venues for the kingdom’s 2034 Fifa World Cup bid and will host events such as the Saudi King Cup, the Asian Cup and the 2034 Asian Games.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19501493/main.jpg
    Yasir Iqbal
  • Jordan tenders advisory for wastewater treatment plant

    9 September 2026

    The Water Authority Jordan (WAJ) has issued an invitation to prequalify for advisory services for the rehabilitation and expansion of the Shallala wastewater treatment plant in Irbid, northern Jordan.

    The Shallala plant was commissioned in 2013 with a design capacity of about 14,000 cubic metres a day (cm/d).

    The rehabilitation and expansion project will increase its treatment capacity to about 30,500 cm/d to meet projected wastewater flows through 2050.

    The PIU Support and Construction Supervision Consultancy Services tender was released on 19 August.

    The submission deadline is 21 September.

    The consultancy will support the project implementation unit and provide construction supervision services for the project. The project has an estimated value of $69m and is being financed by the European Bank for Reconstruction and Development.

    The planned works include rehabilitating the existing activated sludge and treatment units and constructing a new treatment train.

    The scope also includes installing biogas combined heat and power units, improving sludge handling and dewatering systems, and installing odour control and chemical containment systems.

    WAJ is also undertaking the upgrade and expansion of the Ain Ghazal wastewater treatment plant in Amman.

    The existing facility had a capacity of 330,000 cm/d and is being upgraded to 726,712 cm/d to accept and treat expected incoming flows until 2045.

    The local Arab Towers Contracting Company was appointed as the main contractor for the project last year.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19498520/main.jpg
    Mark Dowdall
  • Consultants bid for Abu Dhabi light rail project management

    9 September 2026

     

    Register for MEED’s 14-day trial access 

    Abu Dhabi Transport Company (ADTC) has issued a request for prequalification (RFQ) notice to consultants for a contract for project management engineering consultancy services for the first phase of the light rail transit network, also known as ADT4.

    The notice was issued on 7 September, with a submission deadline of 9 November.

    The project’s first phase will span 19 kilometres (km) and include 23 stations, connecting Zayed International airport (AUH) with nearby areas, including Yas Island, Al‑Raha Beach and Khalifa City.

    The key sections of the tram are:

    AUH to Yas Island: The tram will start from Terminal A at AUH and run through the Yas tunnel to Yas Gateway Park. It will serve areas including Yas Bay, Media Zone, Yas Plaza, Yas Drive, Yas Mall, Sea World and Water Edge.

    This section covers 13km and includes 13 at-grade stations and one underground station.

    Al-Raha: This section will stretch for 4.3km and run along Al-Raha Street. It will serve areas including Al-Zeina, Al-Muneera and Al-Bandar, towards the Aldar head office. The section will include seven at-grade stations.

    Etihad Plaza: This section will pass the Etihad Aviation Training Centre and span about 1.7km. It will feature a main depot near the Etihad Airways headquarters, along with two at-grade stations.

    The tender also covers the procurement of 25 trams, each with a capacity of 270 people, along with associated systems.

    The project was officially launched at the GlobalRail exhibition in Abu Dhabi in October last year.

    Referred to as Abu Dhabi Tram Line 4, the project will be delivered in three phases.

    Construction of the first phase is expected to start next year. The tram is slated to begin operations by 2030.

    Future phases will extend towards Khalifa City and serve additional destinations across Yas Island.

    The project forms a key part of the recently announced AED170bn ($46bn) package of national transport and road projects to be implemented by 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19493532/main.jpg
    Yasir Iqbal