Familiar realities threaten Egypt’s energy ambitions

7 February 2024

This package on Egypt's power sector also includes:

Egypt to complete Gabal El Zeit wind farms sale
Egypt president and Putin mark El Dabaa construction
EBRD invests in 1.1GW Egypt wind farm
Scatec in talks for Nagaa Hammadi solar project
> Team signs land deal for 1.1GW Egypt wind project
Acwa Power moves forward with Egypt green hydrogen project


 

As of early 2024, Egypt appears to have come full circle in terms of providing electricity services to its citizens.

The country faced severe power shortages in 2013-14, which gave way to the fast-tracked construction of 14.4GW of gas-powered generation capacity in 2018. This, along with the increase in renewable energy capacity, resulted in a surplus of up to 25%, yet since late last year consumers have once again been experiencing power outages lasting up to two hours.

This time, however, the power outages – which began in the summer of 2023 and are expected to last until March this year – are not due to a capacity deficit.

The government-initiated load-shedding programme initially aimed to rein in rising electricity consumption and reduce pressure on the country's gas network.

According to the country’s Electricity & Renewable Energy Ministry, national electricity consumption reached 43,650MW in mid-July last year, up significantly from previous highs of about 31,000MW.

While the record-high consumption level is still way below the official generation installed capacity of close to 60,000MW, consumption levels of between 34,000MW and 36,000MW will require around 129-146 million cubic metres of gas and diesel a day.

Barring load-shedding, any increase in consumption beyond 36,000MW will require a commensurate increase in gas and diesel, which is understood to be beyond the government’s capacity to procure.

Crucially, the other side of the electricity rationing initiative has to do with the need to save gas for exports, to boost the government’s dollar reserves in the face of the ongoing currency crisis.

Frustration over the power cuts and their impact on job productivity and the overall economy has been growing over the past few months.

There are no magic pills, however, and any solution needs to start with broader economic and energy sector reforms, to improve the prospects of attracting investments, notes Jessica Obeid, a partner at Dubai-headquartered New Energy Consult.

“Reducing reliance on gas for domestic power generation and increasing renewable energy plus storage are critical, not only to reduce the shortage gap but also to improve energy security, since one gas field, Zohr, feeds almost half of the domestic needs,” she explains. “In the immediate term, doubling down on energy-efficient measures and demand-side management is needed.”

It is an awkward and unprecedented situation for the North African state, which has espoused a clear intention – and started executing relevant projects – to establish itself as a regional energy hub, exporting natural gas and electricity to neighbouring countries, as well as to Europe.

“The government has signaled its prioritisation of exports, although no economy can grow nor become a hub while dealing with energy shortages,” Obeid says.

“The Egyptian government has showcased that the focus is on economic revenues from gas exports, even if that is at the expense of the living conditions of the citizens. However, Egypt cannot realise its hefty regional ambitions without efficient measures and reforms to mend the high domestic reliance on gas, and the lower gas production prospects.”

Another expert on Egypt’s energy policies notes that the country is in a tough spot and “needs ideas to move ahead from this”.

In addition to its energy hub plans, Egypt could look into other opportunities such as setting up repair hubs for ships, as well as education centres to cater to the needs of those hubs, the expert suggests, while noting – as Obeid does – the need for wide-ranging reforms, including improving the rule of law and developing alternative sources of wealth and income.

Important milestones

Six months of electricity rationing makes it easy to overlook the cumulative – though, in hindsight, insufficient – steps that Egypt has taken to avoid falling once again into the power outage trap.

Egypt has one of the highest renewable energy penetration rates in relation to overall installed capacity in the Middle East and North Africa region. While this is commendable, it has only served to highlight the weakness of the country's electricity grid when it comes to handling intermittent renewable energy sources such as solar and wind.

Nonetheless, the country is continuing to build additional renewable energy capacity, including hydropower, and with the help of Russian financing, it has also embarked on the construction of its first nuclear power plant. These projects could replace the ageing oil and gas fleet, lowering the sector's emissions while also supporting the country's energy diversification and security agendas.

Egypt aims to be a global green hydrogen and ammonia hub, and signed preliminary agreements for over a dozen such schemes when it hosted the UN global climate summit, Cop27, in November 2022.

If these projects reach the execution stage, not only do they have the potential to advance the country’s ambition to be a global green energy hub, they will also help to attract much-needed dollars to fund its economic diversification plans.

However, the ability to implement reforms and develop bankable projects lies at the heart of the deployment of any technology in Egypt, points out Obeid.

“Egypt’s existing experience in hydrogen, and being part of that trade market, along with abundant renewable energy resources, a vast land [area] and the country’s geographic location are enablers of a hydrogen market," she says.

“Yet, Egypt’s economic and financial challenges have led to higher interest rates, lower lending capacity and higher costs for system components, and these need to be addressed first.”

Never say die 

Despite a bleak short- to medium-term outlook, some projects are moving ahead in Egypt.

The European Bank for Reconstruction & Development will invest $75m in equity in the Netherlands-based subsidiary of Egypt's Hassan Allam Utilities, which along with Saudi utility developer Acwa Power is co-developing a wind independent power producer scheme in the country's Gulf of Suez and Gabal El Zeit area.

Acwa Power also reached financial close for a 200MW solar photovoltaic facility in Kom Ombo in August last year, two years after the project was put on hold due to rising solar panel and freight costs.

Even the 505MW Amunet wind farm project, located in Ras Ghareb in the Gulf of Suez on the Red Sea coast, is moving ahead. A consortium of the UAE-based Amea Power and Japan’s Sumitomo Corporation last year enlisted Shanghai-headquartered Envision Energy to supply wind turbines for the project.

According to the New & Renewable Energy Authority (NREA), solar and wind projects with a total capacity of close to 3.5GW were under development in Egypt as of the end of 2023, while schemes totalling 39GW are in the planning stage. 

Hydrogen and ammonia

In November, Abu Dhabi-based Fertiglobe delivered what might have been the world's first internationally certified renewable ammonia from its pilot electrolyser site in Egypt to India. The ammonia will be used to produce near-zero-emissions synthetic soda ash – a key ingredient in laundry powder – for Unilever.

Several planned integrated green hydrogen projects in Egypt are in the pre-front-end engineering and design (pre-feed) stage.

One of the green ammonia projects is being developed by Germany's DAI Infrastruktur. To be located in East Port Said, the Ra green ammonia project will have a total production capacity of 2 million tonnes a year (mtpa) of green ammonia, of which 1.65 mtpa is expected to be based purely on renewable energy resources when complete.

DAI has signed a preliminary agreement with Siemens Energy, which plans to supply electrolysers, auxiliary plant systems and critical equipment making up the hydrogen island of the project.

DAI and UK-headquartered Freepan Holding are also understood to have signed an offtake agreement for the ammonia produced at the Ra plant. The 10-year offtake agreement covers 800,000 tonnes a year of ammonia, with the first green ammonia delivery to Freepan expected in 2028.

A similarly sized project is being developed by Amea Power in the coastal town of Ain Sokhna in the Suez governorate. The company is in the process of appointing pre-feed consultants and contractors that will undertake geotechnical, topography and environmental studies for the project.

Detailed studies are also under way for interconnections transporting clean energy from Egypt to Europe, as the latter seeks alternatives to Russian energy exports.

Stakeholders in these projects will continue to monitor the Egyptian government's management of its energy policies at home and abroad over the next few months as they decide the next steps in their investment plans.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11489597/main.jpg
Jennifer Aguinaldo
Related Articles
  • Bahrain mall to install solar carport

    24 April 2024

    The Avenues-Bahrain has signed a solar power purchase agreement (PPA) with UAE-headquartered solar company Yellow Door Energy (YDE) for a 3.5MW solar carport system encompassing the mall’s entire outdoor parking facility.

    According to the shopping mall operator, YDE will build, operate and maintain the solar carport, which will comprise over 6,000 bi-facial solar panels providing shade for 1,025 parking spots while generating over 5.8 million kilowatt-hours (kWh) of clean energy in its first year.

    The Avenues-Bahrain expects construction of the solar carport to begin soon and be completed by the fourth quarter of 2024.

    The solar carport, covering an area of 23,500 square metres (sqm), will complement the mall’s four-year-old rooftop solar photovoltaic (PV) system, which has a capacity of 250KW and offsets 300 metric tonnes of carbon emissions annually.

    The Avenues-Bahrain win marks YDE’s sixth secured solar project in Bahrain, bringing its total portfolio in the country to over 30MW of awarded solar projects.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11709324/main.jpg
    Jennifer Aguinaldo
  • No extension for Dubai sewer tunnel prequalification

    24 April 2024

     

    Register for MEED's guest programme 

    Dubai Municipality expects interested engineering, procurement and construction (EPC) companies to submit their statements of qualifications (SOQs) by the end of April for the contracts to develop the Dubai Strategic Sewerage Tunnels (DSST) project.

    “No further extension has been granted,” a source close to the project tells MEED.

    International, regional and local EPC contractors are keen to prequalify to bid for the contracts for the $22bn DSST scheme, which Dubai Municipality is implementing on a public-private partnership (PPP) basis.

    In addition to its size, the project is gaining significant interest due to its unique procurement approach, whereby EPC contractors’ prequalification precedes developers’ prequalification.

    Dubai Municipality is undertaking the prequalification process for EPC contractors ahead of prequalifying companies that can bid for the contracts to develop and operate various packages of the project.

    According to industry sources, the floods resulting from last week’s storm that hit Dubai and other emirates have also made implementing the project more urgent. 

    The bidders for each of the PPP requests for proposals (RFPs) will be prequalified consortiums comprised of sponsors, EPC contractors and operation and management (O&M) contractors.

    MEED previously reported that the overall project will require a capital expenditure of roughly AED30bn ($8bn), while the whole life cost over the full concession terms of the entire project is estimated to reach AED80bn.

    The project aims to convert Dubai’s existing sewerage system from a pumped system to a gravity system by decommissioning the existing pump stations and providing “a sustainable, innovative, reliable service for future generations”.

    Dubai currently has two major sewerage catchments. The first in Deira is Warsan, where the Warsan sewage treatment plant (STP) treats the flow.

    The second catchment, called Jebel Ali, is in Bur Dubai, where the wastewater is treated at the Jebel Ali STP.

    DSST-DLT packages

    Under the current plan, the $22bn DSST project is broken down into six packages, which will be tendered separately as PPP packages with concession periods lasting between 25 and 35 years.

    The first package, J1, comprises Jebel Ali tunnels (North) and terminal pump stations (TPS). The tunnels will extend approximately 42 kilometres, and the links will extend 10km. 

    The second package, J2, covers the southern section of the Jebel Ali tunnels, which will extend 16km and have a link stretching 46km.

    W for Warsan, the third package, comprises 16km of tunnels, TPS and 46km of links.

    J3, the fourth package, comprises 129km of links. Once completed, Dubai Municipality will operate them, unlike the first three packages, which are envisaged to be operated and maintained by the winning PPP contractors.  

    J1, J2 and W will be procured under a design-build-finance-operate-maintain model with a concession period of 25-35 years.

    J3 will be procured under a design-build-finance model with a concession period of 25-35 years.

    J1, J2, W and J3 will comprise the deep sewerage tunnels, links and TPS (DLT) components of the overall project.

    MEED understands the project’s remaining two packages, the expansion and upgrade of the Jebel Ali and Warsan STPs, will be procured in a process separate from the four DSST-DLT components.

    The RFPs for the four DSST-DLT packages will likely be issued sequentially, staggered around six to 12 months apart.

    Dubai Municipality has appointed Abu Dhabi-headquartered Tribe Infrastructure Group as lead and financial adviser, UK-based Ashurst as legal adviser and the US’ Parsons as technical adviser for the DSST project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11708845/main.jpg
    Jennifer Aguinaldo
  • UAE and Oman firms sign $32bn energy deal

    24 April 2024

    Register for MEED's guest programme 

    An industrial and energy project valued at an estimated AED117bn ($31.8bn) topped the recent investment agreements reached between the UAE and Oman following Sultan Haitham Bin Tariq’s visit to the UAE capital earlier this week.

    The package encompasses renewable energy initiatives, including wind and solar projects, alongside green metals production facilities.

    The agreement’s signatories included Abu Dhabi National Energy Company (Taqa), Abu Dhabi Future Energy Company (Masdar), Emirates Global Aluminium, Emirates Steel Arkan, OQ Alternative Energy and Oman Electricity Transmission Company.

    Details of the planned projects have not yet been disclosed, although the production of green steel and green aluminium in either jurisdiction is implied.

    The companies signed the agreements on 22 April in the presence of Sheikh Theyab Bin Mohamed Bin Zayed Al Nahyan, chairman of the Office of Development and Martyrs’ Families Affairs at the Presidential Court, and Sheikh Hamed Bin Zayed Al Nahyan, managing director of Abu Dhabi Investment Authority.

    Along with other technology and infrastructure-related partnerships and projects, an agreement for the UAE-Oman rail connectivity project, valued at AED11bn, was also signed.

    Photo: WAM


    MEED’s latest special report on Oman includes: 

    > COMMENT: Muscat needs to stimulate growth
    > GOVERNMENT & ECONOMY: Muscat performs tricky budget balancing act

    > BANKING: Oman banks look to projects for growth
    > OIL & GAS: Oman diversifies hydrocarbons value chain
    > POWER & WATER: Oman expands grid connectivity
    > HYDROGEN: Oman seeks early hydrogen success

    > CONSTRUCTION: Oman construction is back on track

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11706425/main5922.jpg
    Jennifer Aguinaldo
  • Abu Dhabi and Oman launch $180m tech fund

    24 April 2024

    Abu Dhabi-based investment and holding company, ADQ, and Oman Investment Authority (OIA) have launched a $180m technology focused vehicle called Jasoor Fund.

    Jasoor Fund aims to bolster Oman’s digital economy as well as the wider Middle East and North Africa (Mena) region by supporting high-growth technology companies in sectors such as finance, education, health care, clean energy, food, agriculture and logistics.

    OIA is represented by Ithca Group, formerly known as Oman Information and Communication Technologies Group, in the fund.

    According to ADQ, the fund’s core focus will be on innovative technology companies established in the sultanate, in addition to technology startups in other countries in the region.

    It will undertake investments in high-growth technology companies at various stages of development that have established business models.

    Mohamed Hassan Alsuwaidi, ADQ managing director and chief executive, said the launch of Jasoor Fund “reinforces our commitment to make investments that unlock the potential of key sectors of the economy, while creating lasting value for stakeholders”.

    Jasoor Fund is part of broader framework agreement signed between both parties in 2022, when they identified investment opportunities worth over $8bn across key sectors of Oman’s economy.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11707308/main.jpg
    Jennifer Aguinaldo
  • Contractors win Oman-Etihad Rail packages

    23 April 2024

    Register for MEED's guest programme 

    Oman-Etihad Rail Company (OERC) has announced that it has awarded contracts for three civil works packages for the railway project linking Oman and the UAE, which is now officially called Hafeet Rail.

    The estimated AED5.5bn ($1.5bn) design-and-build contract was awarded to a consortium of Abu Dhabi-based National Projects Construction (NPC), National Infrastructure Construction Company (NICC), Tristar Engineering & Construction and Oman’s Galfar Engineering & Contracting.

    NPC is the infrastructure development arm of the Abu Dhabi-based Trojan Construction Group, which is a subsidiary of local investment firm Alpha Dhabi.

    According to sources close to the project, the clients are expected to appoint an engineering design firm for the project imminently.

    NICC is the project management consultant for the Hafeet Rail scheme.

    OERC also awarded a separate contract for the rolling stock systems and integration contracts to German firm Siemens and Egyptian contractor Hassan Allam Construction.

    Several high-ranking officials from both sides attended the agreement signing ceremony.

    They included Sheikh Hamed Bin Zayed Al Nahyan, managing director of Abu Dhabi Investment Authority; Suhail Bin Mohammed Al Mazrouei, minister of energy and infrastructure; Abdul Salam Bin Mohammed Al Murshidi, chairman of the Omani Investment Authority; Qais Bin Mohammed Al Yousef, minister of commerce, industry and investment promotion; and Ahmed Bin Hilal Al Busaidi, Oman’s ambassador to the UAE.

    In January, MEED reported that OERC had received bids for three civil works packages for the railway project linking the two countries.

    According to regional projects tracker MEED Projects, the firms submitted their bids on 4 December for packages A and B. The bid for package C was submitted on 11 December.

    OERC qualified companies that could bid for the three civil works packages for the railway project in August last year.

    Network development

    Oman-Etihad Rail Company was established in September 2022 to implement the railway network between the two countries.

    The project subsequently received a push after Oman-Etihad Rail Company inked a strategic agreement with Abu Dhabi-based Mubadala Investment Company to support its development.

    The UAE-Oman Rail Network is set to improve the two countries’ competitiveness in global trade and help establish their positions as logistics hubs that serve as gateways to regional markets.

    The scheme supports both countries’ sustainable development goals by improving their transport and infrastructure sectors.

    The line’s increased efficiency compared to other modes of transport is expected to reduce the overall cost of supply chains. The network will also provide trade and investment opportunities for the private sector and new job opportunities.

    Passenger trains will run up to 200 kilometres (km) an hour on the line, reducing the journey time between Sohar and Abu Dhabi to 100 minutes and between Sohar and Al Ain to 47 minutes.

    Freight trains will reach a top speed of 120km/hour.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11706161/main.gif
    Yasir Iqbal