Familiar realities threaten Egypt’s energy ambitions
7 February 2024
This package on Egypt's power sector also includes:
> Egypt to complete Gabal El Zeit wind farms sale
> Egypt president and Putin mark El Dabaa construction
> EBRD invests in 1.1GW Egypt wind farm
> Scatec in talks for Nagaa Hammadi solar project
> Team signs land deal for 1.1GW Egypt wind project
> Acwa Power moves forward with Egypt green hydrogen project

As of early 2024, Egypt appears to have come full circle in terms of providing electricity services to its citizens.
The country faced severe power shortages in 2013-14, which gave way to the fast-tracked construction of 14.4GW of gas-powered generation capacity in 2018. This, along with the increase in renewable energy capacity, resulted in a surplus of up to 25%, yet since late last year consumers have once again been experiencing power outages lasting up to two hours.
This time, however, the power outages – which began in the summer of 2023 and are expected to last until March this year – are not due to a capacity deficit.
The government-initiated load-shedding programme initially aimed to rein in rising electricity consumption and reduce pressure on the country's gas network.
According to the country’s Electricity & Renewable Energy Ministry, national electricity consumption reached 43,650MW in mid-July last year, up significantly from previous highs of about 31,000MW.
While the record-high consumption level is still way below the official generation installed capacity of close to 60,000MW, consumption levels of between 34,000MW and 36,000MW will require around 129-146 million cubic metres of gas and diesel a day.
Barring load-shedding, any increase in consumption beyond 36,000MW will require a commensurate increase in gas and diesel, which is understood to be beyond the government’s capacity to procure.
Crucially, the other side of the electricity rationing initiative has to do with the need to save gas for exports, to boost the government’s dollar reserves in the face of the ongoing currency crisis.
Frustration over the power cuts and their impact on job productivity and the overall economy has been growing over the past few months.
There are no magic pills, however, and any solution needs to start with broader economic and energy sector reforms, to improve the prospects of attracting investments, notes Jessica Obeid, a partner at Dubai-headquartered New Energy Consult.
“Reducing reliance on gas for domestic power generation and increasing renewable energy plus storage are critical, not only to reduce the shortage gap but also to improve energy security, since one gas field, Zohr, feeds almost half of the domestic needs,” she explains. “In the immediate term, doubling down on energy-efficient measures and demand-side management is needed.”
It is an awkward and unprecedented situation for the North African state, which has espoused a clear intention – and started executing relevant projects – to establish itself as a regional energy hub, exporting natural gas and electricity to neighbouring countries, as well as to Europe.
“The government has signaled its prioritisation of exports, although no economy can grow nor become a hub while dealing with energy shortages,” Obeid says.
“The Egyptian government has showcased that the focus is on economic revenues from gas exports, even if that is at the expense of the living conditions of the citizens. However, Egypt cannot realise its hefty regional ambitions without efficient measures and reforms to mend the high domestic reliance on gas, and the lower gas production prospects.”
Another expert on Egypt’s energy policies notes that the country is in a tough spot and “needs ideas to move ahead from this”.
In addition to its energy hub plans, Egypt could look into other opportunities such as setting up repair hubs for ships, as well as education centres to cater to the needs of those hubs, the expert suggests, while noting – as Obeid does – the need for wide-ranging reforms, including improving the rule of law and developing alternative sources of wealth and income.
Important milestones
Six months of electricity rationing makes it easy to overlook the cumulative – though, in hindsight, insufficient – steps that Egypt has taken to avoid falling once again into the power outage trap.
Egypt has one of the highest renewable energy penetration rates in relation to overall installed capacity in the Middle East and North Africa region. While this is commendable, it has only served to highlight the weakness of the country's electricity grid when it comes to handling intermittent renewable energy sources such as solar and wind.
Nonetheless, the country is continuing to build additional renewable energy capacity, including hydropower, and with the help of Russian financing, it has also embarked on the construction of its first nuclear power plant. These projects could replace the ageing oil and gas fleet, lowering the sector's emissions while also supporting the country's energy diversification and security agendas.
Egypt aims to be a global green hydrogen and ammonia hub, and signed preliminary agreements for over a dozen such schemes when it hosted the UN global climate summit, Cop27, in November 2022.
If these projects reach the execution stage, not only do they have the potential to advance the country’s ambition to be a global green energy hub, they will also help to attract much-needed dollars to fund its economic diversification plans.
However, the ability to implement reforms and develop bankable projects lies at the heart of the deployment of any technology in Egypt, points out Obeid.
“Egypt’s existing experience in hydrogen, and being part of that trade market, along with abundant renewable energy resources, a vast land [area] and the country’s geographic location are enablers of a hydrogen market," she says.
“Yet, Egypt’s economic and financial challenges have led to higher interest rates, lower lending capacity and higher costs for system components, and these need to be addressed first.”
Never say die
Despite a bleak short- to medium-term outlook, some projects are moving ahead in Egypt.
The European Bank for Reconstruction & Development will invest $75m in equity in the Netherlands-based subsidiary of Egypt's Hassan Allam Utilities, which along with Saudi utility developer Acwa Power is co-developing a wind independent power producer scheme in the country's Gulf of Suez and Gabal El Zeit area.
Acwa Power also reached financial close for a 200MW solar photovoltaic facility in Kom Ombo in August last year, two years after the project was put on hold due to rising solar panel and freight costs.
Even the 505MW Amunet wind farm project, located in Ras Ghareb in the Gulf of Suez on the Red Sea coast, is moving ahead. A consortium of the UAE-based Amea Power and Japan’s Sumitomo Corporation last year enlisted Shanghai-headquartered Envision Energy to supply wind turbines for the project.
According to the New & Renewable Energy Authority (NREA), solar and wind projects with a total capacity of close to 3.5GW were under development in Egypt as of the end of 2023, while schemes totalling 39GW are in the planning stage.
Hydrogen and ammonia
In November, Abu Dhabi-based Fertiglobe delivered what might have been the world's first internationally certified renewable ammonia from its pilot electrolyser site in Egypt to India. The ammonia will be used to produce near-zero-emissions synthetic soda ash – a key ingredient in laundry powder – for Unilever.
Several planned integrated green hydrogen projects in Egypt are in the pre-front-end engineering and design (pre-feed) stage.
One of the green ammonia projects is being developed by Germany's DAI Infrastruktur. To be located in East Port Said, the Ra green ammonia project will have a total production capacity of 2 million tonnes a year (mtpa) of green ammonia, of which 1.65 mtpa is expected to be based purely on renewable energy resources when complete.
DAI has signed a preliminary agreement with Siemens Energy, which plans to supply electrolysers, auxiliary plant systems and critical equipment making up the hydrogen island of the project.
DAI and UK-headquartered Freepan Holding are also understood to have signed an offtake agreement for the ammonia produced at the Ra plant. The 10-year offtake agreement covers 800,000 tonnes a year of ammonia, with the first green ammonia delivery to Freepan expected in 2028.
A similarly sized project is being developed by Amea Power in the coastal town of Ain Sokhna in the Suez governorate. The company is in the process of appointing pre-feed consultants and contractors that will undertake geotechnical, topography and environmental studies for the project.
Detailed studies are also under way for interconnections transporting clean energy from Egypt to Europe, as the latter seeks alternatives to Russian energy exports.
Stakeholders in these projects will continue to monitor the Egyptian government's management of its energy policies at home and abroad over the next few months as they decide the next steps in their investment plans.
Exclusive from Meed
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Oman’s Barka 5 IWP solar plant begins full operations1 May 2026
Spain’s GS Inima has begun permanent operations at the solar photovoltaic (PV) plant serving the Barka 5 independent water project (IWP) in Oman.
The solar facility is the third of its kind in Oman to power a large-scale desalination facility through a self-supply model.
In a statement, GS Inima said it will provide up to 50% of the desalination plant’s electricity needs during daytime operations, improving efficiency and reducing reliance on external power sources.
The PV plant has an installed capacity of 6.5MWp. It is designed to optimise energy consumption at the adjacent reverse osmosis desalination facility.
The project was developed by GS Inima in collaboration with local firm Nafath Renewable Energy as the engineering, procurement and construction (EPC) contractor. China-based OCA Global provided owner’s engineering services.
The Barka 5 IWP has a desalination capacity of approximately 100,000 cubic metres a day.
GS Inima won the contract to develop the Barka 5 IWP project in November 2020. As previously reported, financial close was reached in 2022, and construction of the facility was completed in 2024.
The self-supply solar PV plant is equipped with 10,504 bifacial modules supplied by China’s Jinko Solar. These are mounted on fixed structures provided by Mibet Energy.
Power is managed through 18 Sungrow inverters with a total capacity of 320kWac each, while electricity is fed into the desalination plant through an 11kV connection.
The integration of solar power supports the efficiency of the Barka 5 facility, which has an energy consumption rate of 2.7kWh per cubic metre.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16645971/main.jpg -
Qiddiya receives high-speed rail PPP prequalifications1 May 2026
Register for MEED’s 14-day trial access
Saudi Arabia’s Royal Commission for Riyadh City, in collaboration with Qiddiya Investment Company (QIC) and the National Centre for Privatisation & PPP, received prequalification statements from firms on 30 April for the public-private partnership (PPP) package of the Qiddiya high-speed rail project in Riyadh.
This follows the submission of prequalification statements for the engineering, procurement, construction and financing (EPCF) package on 16 April, as reported by MEED.
The prequalification notice was issued on 19 January, and a project briefing session was held on 23 February at Qiddiya Entertainment City.
The Qiddiya high-speed rail project, also known as Q-Express, will connect King Salman International airport and the King Abdullah Financial District (KAFD) with Qiddiya City. The line will operate at speeds of up to 250 kilometres an hour, reaching Qiddiya in 30 minutes.
The line is expected to be developed in two phases. The first phase will connect Qiddiya with KAFD and King Khalid International airport.
The second phase will start from a development known as the North Pole and travel to the New Murabba development, King Salman Park, central Riyadh and Industrial City in the south of the city.
In November last year, MEED reported that more than 145 local and international companies had expressed interest in developing the project, including 68 contracting companies, 23 design and project management consultants, 16 investment firms, 12 rail operators, 10 rolling stock providers and 16 other services firms.
In November 2023, MEED reported that French consultant Egis had been appointed as the technical adviser for the project. UK-based consultancy Ernst & Young is acting as the transaction adviser, and Ashurst is the legal adviser.
Qiddiya is one of Saudi Arabia’s five official gigaprojects and covers a total area of 376 square kilometres (sq km), with 223 sq km of developed land.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16641057/main.gif -
Bid deadline extensions hint at tighter project market1 May 2026
Commentary
Mark Dowdall
Power & water editorThere has been a steady run of bid deadline extensions across major power and water projects in recent weeks.
The latest is the Al-Dibdibah and Al-Shagaya solar independent power producer (IPP) plant in Kuwait, where the submission date has been moved again to 31 May, following an earlier shift from February to the end of April. Similarly, bidding for the first phase of the Al-Khairan IWPP has also been extended.
In Bahrain, bidding for the 1.2GW Sitra IWPP has been pushed back by another month to 17 May, having already been under main contract tender since last August.
Meanwhile, in Dubai, contractors have been given additional time to submit bids for both the Jebel Ali sewage treatment plant expansion and a dams rehabilitation project in Hatta.
Individually, these shifts are not unusual, and extensions are a routine part of the procurement cycle, especially with large, capital-intensive schemes.
However, amid regional tensions and increasingly complex risk profiles, stakeholders are having to weigh up how much they can absorb, whether that is performance guarantees, financing exposure or delivery risk.
For contractors and developers, this could mean looking more closely at supply chains, insurance costs and the potential for disruption. Lenders, too, are likely taking a more measured view on long-term exposure.
This caution can show up in the bid process. More internal approvals, more conservative pricing, and in some cases, perhaps a hesitation to commit altogether.
At the same time, strong pipelines across the GCC mean contractors are not short of work. Firms can afford to be selective, focusing on projects where risk and return are better aligned.
Clients, in turn, face a choice. Push ahead with more limited competition or extend and try to draw in stronger participation. Most appear to be opting for the latter.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16640998/main.jpg -
Saudi Arabia launches $2bn Jawharat Al-Arous project1 May 2026
Saudi Arabia has launched Jawharat Al-Arous, an SR8bn ($2bn) private-sector-led residential development in north Jeddah.
The scheme covers 107 million square metres and comprises 18 residential neighbourhoods planned to accommodate more than 700,000 residents. It will provide more than 80,000 residential and commercial plots.
The masterplan also includes 41 government-backed infrastructure and service zones to support large-scale urban expansion.
The project was unveiled by Mecca Region Governor Khalid Al-Faisal and will be overseen by Saud Bin Mishaal Bin Abdulaziz.
According to a recent report by real estate firm Cavendish Maxwell, Jeddah’s residential stock stood at about 1.09 million units at the end of 2025, following the completion of around 4,000 units that year.
An expanding pipeline of about 18,000 units in 2026 and 22,000 units in 2027 is expected to bring total stock to around 1.14 million units by 2027, gradually adding supply without destabilising market equilibrium.
GlobalData expects the Saudi construction industry to grow by 3.6% in real terms in 2026, supported by increased foreign direct investment (FDI) and investment in the housing and manufacturing sectors.
The residential construction sector is forecast to grow by 3.8% in real terms in 2026 and to record an average annual growth rate of 4.7% between 2027 and 2030, supported by Saudi Vision 2030’s goal of increasing homeownership from 65.4% in 2024 to 70% by 2030, including through the delivery of 600,000 homes by 2030.
MEED’s April 2026 report on Saudi Arabia includes:
> COMMENT: Risk accelerates Saudi spending shift
> GVT &: ECONOMY: Riyadh navigates a changed landscape
> BANKING: Testing times for Saudi banks
> UPSTREAM: Offshore oil and gas projects to dominate Aramco capex in 2026
> DOWNSTREAM: Saudi downstream projects market enters lean period
> POWER: Wind power gathers pace in Saudi Arabia
> WATER: Sharakat plan signals next phase of Saudi water expansion
> CONSTRUCTION: Saudi construction enters a period of strategic readjustment
> TRANSPORT: Rail expansion powers Saudi Arabia’s infrastructure pushTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16640863/main.png -
Damage to US bases in region expected to cost more than $15bn1 May 2026
The $25bn estimate a Pentagon official gave US lawmakers on 29 April did not include the cost of repairing damage to US bases in the Middle East, and the real cost of the war is likely to be between $40bn and $50bn, according to CNN.
That would put the cost of repairing bases and replacing destroyed assets at between $15bn and $25bn.
Jules Hurst III, the Pentagon official serving as the agency’s comptroller, told the House Armed Services Committee that “most” of the $25bn he cited had been spent on munitions. Defence Secretary Pete Hegseth declined to say whether the figure included repairs to damaged US bases.
Iranian strikes across the Gulf in the early days of the war significantly damaged at least nine US military sites in 48 hours, hitting facilities in Bahrain, Kuwait, Iraq, the UAE and Qatar.
Six US servicemembers were killed in an attack on a command post in Kuwait, and 20 more were injured.
Three sources told CNN that the figure provided to the House Armed Services Committee did not include the cost of rebuilding US military installations and replacing destroyed assets.
One source said the true cost would likely be between $40bn and $50bn.
US contractors such as KBR and Fluor, as well as local firms, are likely to be among the leading contenders for contracts to repair and rebuild US bases in the region.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16638663/main.gif
