Familiar realities threaten Egypt’s energy ambitions
7 February 2024
This package on Egypt's power sector also includes:
> Egypt to complete Gabal El Zeit wind farms sale
> Egypt president and Putin mark El Dabaa construction
> EBRD invests in 1.1GW Egypt wind farm
> Scatec in talks for Nagaa Hammadi solar project
> Team signs land deal for 1.1GW Egypt wind project
> Acwa Power moves forward with Egypt green hydrogen project

As of early 2024, Egypt appears to have come full circle in terms of providing electricity services to its citizens.
The country faced severe power shortages in 2013-14, which gave way to the fast-tracked construction of 14.4GW of gas-powered generation capacity in 2018. This, along with the increase in renewable energy capacity, resulted in a surplus of up to 25%, yet since late last year consumers have once again been experiencing power outages lasting up to two hours.
This time, however, the power outages – which began in the summer of 2023 and are expected to last until March this year – are not due to a capacity deficit.
The government-initiated load-shedding programme initially aimed to rein in rising electricity consumption and reduce pressure on the country's gas network.
According to the country’s Electricity & Renewable Energy Ministry, national electricity consumption reached 43,650MW in mid-July last year, up significantly from previous highs of about 31,000MW.
While the record-high consumption level is still way below the official generation installed capacity of close to 60,000MW, consumption levels of between 34,000MW and 36,000MW will require around 129-146 million cubic metres of gas and diesel a day.
Barring load-shedding, any increase in consumption beyond 36,000MW will require a commensurate increase in gas and diesel, which is understood to be beyond the government’s capacity to procure.
Crucially, the other side of the electricity rationing initiative has to do with the need to save gas for exports, to boost the government’s dollar reserves in the face of the ongoing currency crisis.
Frustration over the power cuts and their impact on job productivity and the overall economy has been growing over the past few months.
There are no magic pills, however, and any solution needs to start with broader economic and energy sector reforms, to improve the prospects of attracting investments, notes Jessica Obeid, a partner at Dubai-headquartered New Energy Consult.
“Reducing reliance on gas for domestic power generation and increasing renewable energy plus storage are critical, not only to reduce the shortage gap but also to improve energy security, since one gas field, Zohr, feeds almost half of the domestic needs,” she explains. “In the immediate term, doubling down on energy-efficient measures and demand-side management is needed.”
It is an awkward and unprecedented situation for the North African state, which has espoused a clear intention – and started executing relevant projects – to establish itself as a regional energy hub, exporting natural gas and electricity to neighbouring countries, as well as to Europe.
“The government has signaled its prioritisation of exports, although no economy can grow nor become a hub while dealing with energy shortages,” Obeid says.
“The Egyptian government has showcased that the focus is on economic revenues from gas exports, even if that is at the expense of the living conditions of the citizens. However, Egypt cannot realise its hefty regional ambitions without efficient measures and reforms to mend the high domestic reliance on gas, and the lower gas production prospects.”
Another expert on Egypt’s energy policies notes that the country is in a tough spot and “needs ideas to move ahead from this”.
In addition to its energy hub plans, Egypt could look into other opportunities such as setting up repair hubs for ships, as well as education centres to cater to the needs of those hubs, the expert suggests, while noting – as Obeid does – the need for wide-ranging reforms, including improving the rule of law and developing alternative sources of wealth and income.
Important milestones
Six months of electricity rationing makes it easy to overlook the cumulative – though, in hindsight, insufficient – steps that Egypt has taken to avoid falling once again into the power outage trap.
Egypt has one of the highest renewable energy penetration rates in relation to overall installed capacity in the Middle East and North Africa region. While this is commendable, it has only served to highlight the weakness of the country's electricity grid when it comes to handling intermittent renewable energy sources such as solar and wind.
Nonetheless, the country is continuing to build additional renewable energy capacity, including hydropower, and with the help of Russian financing, it has also embarked on the construction of its first nuclear power plant. These projects could replace the ageing oil and gas fleet, lowering the sector's emissions while also supporting the country's energy diversification and security agendas.
Egypt aims to be a global green hydrogen and ammonia hub, and signed preliminary agreements for over a dozen such schemes when it hosted the UN global climate summit, Cop27, in November 2022.
If these projects reach the execution stage, not only do they have the potential to advance the country’s ambition to be a global green energy hub, they will also help to attract much-needed dollars to fund its economic diversification plans.
However, the ability to implement reforms and develop bankable projects lies at the heart of the deployment of any technology in Egypt, points out Obeid.
“Egypt’s existing experience in hydrogen, and being part of that trade market, along with abundant renewable energy resources, a vast land [area] and the country’s geographic location are enablers of a hydrogen market," she says.
“Yet, Egypt’s economic and financial challenges have led to higher interest rates, lower lending capacity and higher costs for system components, and these need to be addressed first.”
Never say die
Despite a bleak short- to medium-term outlook, some projects are moving ahead in Egypt.
The European Bank for Reconstruction & Development will invest $75m in equity in the Netherlands-based subsidiary of Egypt's Hassan Allam Utilities, which along with Saudi utility developer Acwa Power is co-developing a wind independent power producer scheme in the country's Gulf of Suez and Gabal El Zeit area.
Acwa Power also reached financial close for a 200MW solar photovoltaic facility in Kom Ombo in August last year, two years after the project was put on hold due to rising solar panel and freight costs.
Even the 505MW Amunet wind farm project, located in Ras Ghareb in the Gulf of Suez on the Red Sea coast, is moving ahead. A consortium of the UAE-based Amea Power and Japan’s Sumitomo Corporation last year enlisted Shanghai-headquartered Envision Energy to supply wind turbines for the project.
According to the New & Renewable Energy Authority (NREA), solar and wind projects with a total capacity of close to 3.5GW were under development in Egypt as of the end of 2023, while schemes totalling 39GW are in the planning stage.
Hydrogen and ammonia
In November, Abu Dhabi-based Fertiglobe delivered what might have been the world's first internationally certified renewable ammonia from its pilot electrolyser site in Egypt to India. The ammonia will be used to produce near-zero-emissions synthetic soda ash – a key ingredient in laundry powder – for Unilever.
Several planned integrated green hydrogen projects in Egypt are in the pre-front-end engineering and design (pre-feed) stage.
One of the green ammonia projects is being developed by Germany's DAI Infrastruktur. To be located in East Port Said, the Ra green ammonia project will have a total production capacity of 2 million tonnes a year (mtpa) of green ammonia, of which 1.65 mtpa is expected to be based purely on renewable energy resources when complete.
DAI has signed a preliminary agreement with Siemens Energy, which plans to supply electrolysers, auxiliary plant systems and critical equipment making up the hydrogen island of the project.
DAI and UK-headquartered Freepan Holding are also understood to have signed an offtake agreement for the ammonia produced at the Ra plant. The 10-year offtake agreement covers 800,000 tonnes a year of ammonia, with the first green ammonia delivery to Freepan expected in 2028.
A similarly sized project is being developed by Amea Power in the coastal town of Ain Sokhna in the Suez governorate. The company is in the process of appointing pre-feed consultants and contractors that will undertake geotechnical, topography and environmental studies for the project.
Detailed studies are also under way for interconnections transporting clean energy from Egypt to Europe, as the latter seeks alternatives to Russian energy exports.
Stakeholders in these projects will continue to monitor the Egyptian government's management of its energy policies at home and abroad over the next few months as they decide the next steps in their investment plans.
Exclusive from Meed
-
Bidders get more time for Jebel Ali sewage EPC contract29 April 2026
-
Kuwait Oil Company prepares to sign flowline contract29 April 2026
-
-
UAE to withdraw from Opec and Opec+ alliance28 April 2026
-
NWC tenders package 14 of sewage treatment programme28 April 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Bidders get more time for Jebel Ali sewage EPC contract29 April 2026
Dubai Municipality has extended the deadline for contractors to submit bids for a contract covering the expansion of the Jebel Ali sewage treatment plant (STP) phases one and two.
Contractors now have until June to submit offers, a source told MEED. Bidding had been expected to close on 30 April.
The upgraded facility will be capable of treating an additional sewage flow of 100,000 cubic metres a day (cm/d), with the expansion estimated to cost $300m.
The scope includes the design, construction and commissioning of infrastructure and systems required to support the increased capacity.
Located on a 670-hectare site in Jebel Ali, the original wastewater facility has a treatment capacity of about 675,000 cm/d following the completion of phase two in 2019, combining approximately 300,000 cm/d from phase one and 375,000 cm/d from phase two.
The main element of the expansion involves modifications to the secondary treatment process at Jebel Ali STP phase two.
UK-headquartered KPMG and UAE-based Tribe Infrastructure are serving as financial advisers on the project.
Future expansion
It is understood that the project is part of long-term plans to treat about 1.05 million cm/d once all future phases are completed.
According to sources, this includes a Jebel Ali-based build-operate-transfer (BOT) project to be developed under a public-private partnership (PPP) model.
It is understood that the prequalification process for this will begin in the coming months.
In February, MEED exclusively revealed that the municipality is preparing to tender the main construction package for the Warsan STP by the end of the year.
As MEED understands, the Warsan STP had previously been planned as a PPP project.
The main package will now be procured as an engineering, procurement and construction contract, a source said.
The project involves the construction of a sewage treatment plant with a capacity of about 175,000 cm/d, including treatment units, sludge handling systems and associated infrastructure.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16608027/main.jpg -
Kuwait Oil Company prepares to sign flowline contract29 April 2026

State-owned upstream operator Kuwait Oil Company (KOC) is preparing to sign a contract worth KD174.2m ($565m) with Kuwait-based Heavy Engineering Industries & Shipbuilding Company (Heisco), according to industry sources.
The contract is focused on developing flowlines and associated works in North Kuwait.
One source said: “The contract is expected to be signed soon and everything associated with the contract award process is moving very smoothly.”
Heisco announced in a stock exchange statement earlier this month that it had received a formal contract award letter for the project.
While progress on the project is moving smoothly for now, the project may be impacted by fallout from the US and Israel’s war with Iran in the future.
The project requires a large volume of pipelines to be transported into Kuwait, which would normally be shipped through the Strait of Hormuz.
Heisco was the fourth-lowest bidder for the contract.
Also this month, Heisco submitted the lowest bid for a project to upgrade part of the Mina Abdullah refinery’s export infrastructure.
It submitted a bid of KD11,919,652 ($38.6m) for the project to implement renovation works on the artificial island that forms part of the port at the refinery.
The only other bidder was Kuwait’s International Marine Construction Company (IMCC), which submitted a bid of KD12,480,113 ($40.4m).
https://image.digitalinsightresearch.in/uploads/NewsArticle/16599814/main.png -
Algerian-Indian team makes oil and gas discovery in Libya29 April 2026
A consortium of state-owned companies from India and Algeria has made an oil and gas discovery in Libya’s Ghadames basin.
The consortium comprises Algeria’s Sonatrach International Petroleum Exploration & Production (Sipex), Oil India and Indian Oil Corporation.
The discovery was made in the Area 95/96 block, which is located near Libya’s border with Algeria.
In a statement, India’s Ministry of Petroleum & Natural Gas said that the well was completed to a final depth of 8,440 feet and achieved production of 13 million cubic feet of gas a day and 327 barrels of condensate a day during testing.
The hydrocarbons were extracted from the Awynat Wanin and Awyn Kaza formations.
The ministry added: “The discovery reflects the growing global footprints of Indian energy companies, importance of strategic international alliances, and our commitment to strengthening national energy security through overseas assets acquisition by national oil companies.”
The consortium won the exploration and production rights for the block, which covers an area of nearly 7,000 square kilometres, during Libya’s fourth oil and gas licensing round in December 2007.
Stakeholders are expecting a surge in oil and gas project activity in Libya after the country’s rival legislative bodies recently approved a unified state budget for the first time in more than 13 years.
The Central Bank of Libya confirmed on 11 April that both chambers had endorsed the budget, saying that it was a key step towards restoring financial stability after prolonged division.
The budget is valued at LD190bn ($29.95bn), and LD12bn ($1.9bn) has been allocated to the NOC.
An additional LD40bn ($6.3bn) has been allocated for “development projects”.
Libya has stated that a joint committee has been formed to help prioritise development projects, and the projects have been listed in the budget.
The development comes at a time when Libya’s oil and gas sector could be positioned to make windfall revenues as oil and gas prices remain high due to fallout from the US and Israel’s war with Iran.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16599813/main.png -
UAE to withdraw from Opec and Opec+ alliance28 April 2026
The UAE has announced its decision to withdraw from Opec and the Opec+ alliance from 1 May.
In a statement, the UAE Ministry of Energy said the move followed a “comprehensive review” of its production policy.
“While near-term volatility, including disruptions in the Arabian Gulf and the Strait of Hormuz, continues to affect supply dynamics, underlying trends point to sustained growth in global energy demand over the medium to long term,” the statement, issued on 28 April, said.
“This decision follows decades of constructive cooperation. The UAE joined Opec in 1967 through the Emirate of Abu Dhabi and continued its membership following the formation of the United Arab Emirates in 1971. Throughout this period, the UAE has played an active role in supporting global oil market stability and strengthening dialogue among producing nations.”
The announcement was timed to coincide with an Opec ministerial meeting in Vienna and was communicated through state news agency Wam.
Abu Dhabi National Oil Company (Adnoc) has set a target of raising production capacity to 5 million barrels a day (b/d) by 2027 – up from a current capacity of around 4.85 million b/d, though the country has been constrained to producing approximately 3.4 million b/d under Opec+ quota agreements.
Membership of a quota-constrained group sits uneasily with that ambition. The non-oil economy now accounts for roughly 75% of the UAE’s GDP, reducing the political cost of rupture with the organisation.
The Iran war wiped out 7.88 million b/d of Opec production in March, cutting group output 27% to 20.79 million b/d – the steepest supply collapse in the organisation’s recorded history, exceeding the Covid-19 demand shock of May 2020 and the disruptions of both the 1970s oil crisis and the 1991 Gulf War. Gulf producers have been struggling to route exports through the Strait of Hormuz amid Iranian threats and attacks on vessels, further straining the group’s cohesion.
Against that backdrop, the UAE’s departure deals a significant blow to Opec and its de facto leader, Saudi Arabia, which has sought to project unity despite persistent internal disagreements over quotas and geopolitics.
The US-Israeli war on Iran since late February has had a detrimental effect on a number of Gulf states, including the UAE.
The UAE was targeted by thousands of Iranian ballistic missiles and drones, damaging strategic oil and gas facilities, denting Dubai’s appeal as a luxury tourism hotspot and slowing oil exports to a trickle.
Whereas some Gulf states have urged dialogue with Iran, the UAE has maintained a more hawkish position. Analysts say that position is partially due to its reliance on the Strait of Hormuz for oil exports and the UAE’s unwillingness to see Iran cement itself as a regional power in the Gulf.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16596229/main.gif -
NWC tenders package 14 of sewage treatment programme28 April 2026

Register for MEED’s 14-day trial access
Saudi Arabia’s National Water Company (NWC) has tendered a contract for the construction of 10 sewage treatment plants as part of the next phase of its long-term operations and maintenance (LTOM) sewage treatment programme.
According to the original scope, the Eastern A Cluster (LTOM14) package will have a total treatment capacity of 184,440 cubic metres a day (cm/d) at an estimated cost of $180m.
The bid submission deadline is 30 September.
The tender follows recent contract awards for North Western A Cluster Sewage Treatment Plants Package 11 (LTOM11) and the Northern Cluster Sewage Treatment Plants Package 10 (LTOM10).
MEED exclusively reported that a consortium comprising China’s Jiangsu United Water Technology, the UAE’s Prosus Energy and Saudi Arabia’s Armada Holding had been appointed as a contractor for each of these projects.
Package 11 will have a combined capacity of about 440,000 cm/d at an estimated cost of about SR211m ($56.3m).
Package 12 will have a combined treatment capacity of 337,800 cm/d at an estimated cost of about SR203m ($54.1m).
In April, NWC also opened finanical bids for North Western B Cluster (LTOM12) of its sewage treatment programme.
The contract covers the construction and upgrade of seven sewage treatment plants with a combined capacity of about 162,000 cm/d.
MEED previously reported that the following companies had submitted proposals:
- Alkhorayef Water & Power Technologies (Saudi Arabia)
- Civil Works Company (Saudi Arabia)
- Miahona (Saudi Arabia)
- Beijing Enterprises Water Group – BEWG (Hong Kong)
- Al-Yamama (Saudi Arabia)
These bids are currently under evaluaton, with an award expected in the coming weeks, a source said.
The tender for the North Western C Cluster (LTOM13) project had been put on hold, although it is understood that this is now likely to be the next package to be tendered.
Under the original scope, this package covers the construction of 10 sewage treatment plants.
In total, the LTOM programme comprises 19 packages split into two phases. This contract for LTOM10 was the first to be awarded under the second phase of NWC’s rehabilitation of sewage treatment plants programme.
As MEED understands, there have been several discussions in recent months regarding changes in scope details and potential expansions. This involves potentially grouping some upcoming projects.
NWC previously awarded $2.5bn-worth of contracts in the first phase. This comprises nine packages covering the treatment of 4.6 million cm/d of sewage water for the next 15 years. Phase two of the programme includes 10 packages covering 117 treatment plants.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16591851/main.jpg