Familiar realities threaten Egypt’s energy ambitions
7 February 2024
This package on Egypt's power sector also includes:
> Egypt to complete Gabal El Zeit wind farms sale
> Egypt president and Putin mark El Dabaa construction
> EBRD invests in 1.1GW Egypt wind farm
> Scatec in talks for Nagaa Hammadi solar project
> Team signs land deal for 1.1GW Egypt wind project
> Acwa Power moves forward with Egypt green hydrogen project

As of early 2024, Egypt appears to have come full circle in terms of providing electricity services to its citizens.
The country faced severe power shortages in 2013-14, which gave way to the fast-tracked construction of 14.4GW of gas-powered generation capacity in 2018. This, along with the increase in renewable energy capacity, resulted in a surplus of up to 25%, yet since late last year consumers have once again been experiencing power outages lasting up to two hours.
This time, however, the power outages – which began in the summer of 2023 and are expected to last until March this year – are not due to a capacity deficit.
The government-initiated load-shedding programme initially aimed to rein in rising electricity consumption and reduce pressure on the country's gas network.
According to the country’s Electricity & Renewable Energy Ministry, national electricity consumption reached 43,650MW in mid-July last year, up significantly from previous highs of about 31,000MW.
While the record-high consumption level is still way below the official generation installed capacity of close to 60,000MW, consumption levels of between 34,000MW and 36,000MW will require around 129-146 million cubic metres of gas and diesel a day.
Barring load-shedding, any increase in consumption beyond 36,000MW will require a commensurate increase in gas and diesel, which is understood to be beyond the government’s capacity to procure.
Crucially, the other side of the electricity rationing initiative has to do with the need to save gas for exports, to boost the government’s dollar reserves in the face of the ongoing currency crisis.
Frustration over the power cuts and their impact on job productivity and the overall economy has been growing over the past few months.
There are no magic pills, however, and any solution needs to start with broader economic and energy sector reforms, to improve the prospects of attracting investments, notes Jessica Obeid, a partner at Dubai-headquartered New Energy Consult.
“Reducing reliance on gas for domestic power generation and increasing renewable energy plus storage are critical, not only to reduce the shortage gap but also to improve energy security, since one gas field, Zohr, feeds almost half of the domestic needs,” she explains. “In the immediate term, doubling down on energy-efficient measures and demand-side management is needed.”
It is an awkward and unprecedented situation for the North African state, which has espoused a clear intention – and started executing relevant projects – to establish itself as a regional energy hub, exporting natural gas and electricity to neighbouring countries, as well as to Europe.
“The government has signaled its prioritisation of exports, although no economy can grow nor become a hub while dealing with energy shortages,” Obeid says.
“The Egyptian government has showcased that the focus is on economic revenues from gas exports, even if that is at the expense of the living conditions of the citizens. However, Egypt cannot realise its hefty regional ambitions without efficient measures and reforms to mend the high domestic reliance on gas, and the lower gas production prospects.”
Another expert on Egypt’s energy policies notes that the country is in a tough spot and “needs ideas to move ahead from this”.
In addition to its energy hub plans, Egypt could look into other opportunities such as setting up repair hubs for ships, as well as education centres to cater to the needs of those hubs, the expert suggests, while noting – as Obeid does – the need for wide-ranging reforms, including improving the rule of law and developing alternative sources of wealth and income.
Important milestones
Six months of electricity rationing makes it easy to overlook the cumulative – though, in hindsight, insufficient – steps that Egypt has taken to avoid falling once again into the power outage trap.
Egypt has one of the highest renewable energy penetration rates in relation to overall installed capacity in the Middle East and North Africa region. While this is commendable, it has only served to highlight the weakness of the country's electricity grid when it comes to handling intermittent renewable energy sources such as solar and wind.
Nonetheless, the country is continuing to build additional renewable energy capacity, including hydropower, and with the help of Russian financing, it has also embarked on the construction of its first nuclear power plant. These projects could replace the ageing oil and gas fleet, lowering the sector's emissions while also supporting the country's energy diversification and security agendas.
Egypt aims to be a global green hydrogen and ammonia hub, and signed preliminary agreements for over a dozen such schemes when it hosted the UN global climate summit, Cop27, in November 2022.
If these projects reach the execution stage, not only do they have the potential to advance the country’s ambition to be a global green energy hub, they will also help to attract much-needed dollars to fund its economic diversification plans.
However, the ability to implement reforms and develop bankable projects lies at the heart of the deployment of any technology in Egypt, points out Obeid.
“Egypt’s existing experience in hydrogen, and being part of that trade market, along with abundant renewable energy resources, a vast land [area] and the country’s geographic location are enablers of a hydrogen market," she says.
“Yet, Egypt’s economic and financial challenges have led to higher interest rates, lower lending capacity and higher costs for system components, and these need to be addressed first.”
Never say die
Despite a bleak short- to medium-term outlook, some projects are moving ahead in Egypt.
The European Bank for Reconstruction & Development will invest $75m in equity in the Netherlands-based subsidiary of Egypt's Hassan Allam Utilities, which along with Saudi utility developer Acwa Power is co-developing a wind independent power producer scheme in the country's Gulf of Suez and Gabal El Zeit area.
Acwa Power also reached financial close for a 200MW solar photovoltaic facility in Kom Ombo in August last year, two years after the project was put on hold due to rising solar panel and freight costs.
Even the 505MW Amunet wind farm project, located in Ras Ghareb in the Gulf of Suez on the Red Sea coast, is moving ahead. A consortium of the UAE-based Amea Power and Japan’s Sumitomo Corporation last year enlisted Shanghai-headquartered Envision Energy to supply wind turbines for the project.
According to the New & Renewable Energy Authority (NREA), solar and wind projects with a total capacity of close to 3.5GW were under development in Egypt as of the end of 2023, while schemes totalling 39GW are in the planning stage.
Hydrogen and ammonia
In November, Abu Dhabi-based Fertiglobe delivered what might have been the world's first internationally certified renewable ammonia from its pilot electrolyser site in Egypt to India. The ammonia will be used to produce near-zero-emissions synthetic soda ash – a key ingredient in laundry powder – for Unilever.
Several planned integrated green hydrogen projects in Egypt are in the pre-front-end engineering and design (pre-feed) stage.
One of the green ammonia projects is being developed by Germany's DAI Infrastruktur. To be located in East Port Said, the Ra green ammonia project will have a total production capacity of 2 million tonnes a year (mtpa) of green ammonia, of which 1.65 mtpa is expected to be based purely on renewable energy resources when complete.
DAI has signed a preliminary agreement with Siemens Energy, which plans to supply electrolysers, auxiliary plant systems and critical equipment making up the hydrogen island of the project.
DAI and UK-headquartered Freepan Holding are also understood to have signed an offtake agreement for the ammonia produced at the Ra plant. The 10-year offtake agreement covers 800,000 tonnes a year of ammonia, with the first green ammonia delivery to Freepan expected in 2028.
A similarly sized project is being developed by Amea Power in the coastal town of Ain Sokhna in the Suez governorate. The company is in the process of appointing pre-feed consultants and contractors that will undertake geotechnical, topography and environmental studies for the project.
Detailed studies are also under way for interconnections transporting clean energy from Egypt to Europe, as the latter seeks alternatives to Russian energy exports.
Stakeholders in these projects will continue to monitor the Egyptian government's management of its energy policies at home and abroad over the next few months as they decide the next steps in their investment plans.
Exclusive from Meed
-
Firms prepare bids for NWC sewage treatment package 144 September 2026
-
Egyptian contractor wins Abu Dhabi Ramhan Island deal4 September 2026
-
Dubai sets deadline for Jebel Ali waste-to-energy PPP4 September 2026
-
Egypt to invest $4.5bn in refinery upgrades4 September 2026
-
North Field West platform bidders get extra time4 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Firms prepare bids for NWC sewage treatment package 144 September 2026

At least three contractors are preparing to make offers for package 14 of Saudi Arabia’s long-term operations and maintenance (LTOM) sewage treatment programme, according to sources.
Known as Eastern A Cluster (LTOM14), the package was tendered by the state-owned National Water Company (NWC) in April, with a bid submission deadline of 30 September.
The contract covers the upgrade of six existing sewage treatment plants (STPs), with a capacity expansion of 30,000 cubic metres a day (cm/d) at the Al-Jarodia STP.
This will increase total treatment capacity from about 263,000 cm/d to approximately 293,000 cm/d, with an estimated cost of $180m.
According to sources, the firms preparing to submit bids include:
- Alkhorayef Water & Power Technologies (Saudi Arabia)
- Civil Works Company (Saudi Arabia)
- Miahona (Saudi Arabia)
The latest phase follows the formal signing of a $347m contract between NWC and a Saudi-Chinese consortium for Northern Cluster Sewage Treatment Plants Package 10 (LTOM10) on 2 September.
The same consortium led by United Water (China) is not planning to bid for LTOM14 and is expected to formally sign a contract for LTOM11 in the coming months, a source said.
In April, MEED exclusively reported that the group had won the contract for package 11, which will have a combined capacity of about 440,000 cm/d.
It is also understood that Beijing Enterprises, a bidder for North Western B Cluster (LTOM12), is not preparing to bid for package 14.
In the meantime, the contract for LTOM12 is moving towards award, with bids currently under evaluation.
The contract covers the construction and upgrade of seven STPs with a combined capacity of about 162,000 cm/d. As previously reported, NWC opened financial bids for the project in April.
Future phases
In total, the LTOM programme comprises 19 packages split into two phases. In May 2024, NWC announced it had awarded $2.5bn-worth of contracts in the first phase. Phase two of the programme includes 10 packages covering 117 treatment plants.
In April, MEED exclusively reported that NWC had held several discussions regarding changes in scope details and potential expansions to upcoming projects. This involved “grouping some upcoming projects”.
The request for proposals for LTOM13 was subsequently put on hold and it is now understood that this tender has likely been merged with other packages in the programme.
According to a source, Eastern B Cluster (LTOM15) has also been cancelled and has likely been merged. LTOM15 had comprised two STPs with a total capacity of 152,000 cm/d.
The next contract to be tendered will be Central Cluster (LTOM16), potentially in November, a source added.
Under the original scope, LTOM16 covers the construction of 14 STPs with a total capacity of 153,000 cm/d.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19358188/main.jpg -
Egyptian contractor wins Abu Dhabi Ramhan Island deal4 September 2026
Egypt-headquartered contractor Rowad Modern Engineering has been awarded the main works contract for the Marina Apartments project on Ramhan Island, Abu Dhabi.
The contract was awarded by the local firm Eagle Hills, which is led by Mohamed Alabbar, the founder and chairman of Emaar Properties.
Rowad’s scope includes structural and architectural works, finishing, and mechanical, electrical and plumbing systems.
The company will also deliver infrastructure works, including utility connections to external networks, testing and commissioning.
The development comprises two residential towers offering 187 residential units.
The works will be carried out under the consultancy supervision of local engineering firm Mirage Leisure & Development.
The latest contract award follows Eagle Hills awarding the local firm Arabian Construction Company (ACC) an estimated AED2.5bn ($680m) construction contract to build about 500 villas at the Ramhan Island development, as reported by MEED previously.
Located off the coast of Abu Dhabi, the Ramhan Island development spans an area of over 4 million square metres.
The overall development includes the construction of 1,800 villas, 900 residences, a hotel and retail facilities.
Mohamed Alabbar launched the Ramhan Island development in May 2024.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19355437/main.jpg -
Dubai sets deadline for Jebel Ali waste-to-energy PPP4 September 2026

Register for MEED’s 14-day trial access
Dubai Municipality has set a 27 September deadline for developers to submit expressions of interest (EOIs) for its planned Jebel Ali waste-to-energy (WTE) public-private partnership (PPP), according to a source.
The greenfield facility is planned to treat up to 6,000 tonnes of municipal solid waste a day.
The municipality is seeking international and local developers to develop, finance and operate the facility. It is planning to prequalify developers later this year before issuing a request for proposals (RFP) in the first quarter of next year, a source said.
The Jebel Ali facility is intended to support Dubai’s waste-management strategy and its target of reducing reliance on landfill.
Dubai Municipality is being advised by a team led by Abu Dhabi’s Tribe Infrastructure Group, with UK-headquartered Ashurst and Germany’s Fichtner also involved.
It was confirmed to MEED that the project is separate from the planned second phase of the Warsan WTE facility, for which Dubai Municipality issued a consultancy tender in February.
That facility will be located in Warsan 2, next to the Al-Aweer sewage treatment plant. The expansion is expected to increase waste-conversion capacity at the existing Warsan site with an estimated budget of $500m. The consultancy contract has a duration of six years.
The original Warsan WTE plant, Dubai’s first major WTE public-private partnership (PPP) project, reached full commercial operations in 2024.
Located in the Warsan area, the AED4bn ($1.1bn) facility treats 1.9 million tonnes of municipal solid waste annually, generating up to 220MW of thermal energy that is fed into the local grid.
In February 2023, state utility Dubai Electricity & Water Authority (Dewa) and Dubai Waste Management Company signed the power-purchase agreement (PPA) for the project.
Dubai Waste Management Company, the special-purpose vehicle implementing the scheme, reached financial close in June 2021 for the project.
The Warsan project was developed under a 35-year PPP concession by a consortium comprising Dubai Holding, Dubai Aluminium, Tech Group and Itochu Corporation.
The main contractor was a joint venture of Belgium’s Besix Group and Hitachi Zosen Inova of Switzerland.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19354502/main.jpg -
Egypt to invest $4.5bn in refinery upgrades4 September 2026
Egypt is planning to invest $4.5bn in refinery upgrades, according to the country’s Minister of Petroleum and Mineral Resources, Karim Badawi.
Egyptian refineries are operating at 80% of capacity compared with 66% two years ago, according to Badawi, who wants further increases in utilisation of existing facilities.
“We aim to invest around $4.5bn to develop existing refineries and build new units to reduce imports and achieve self-sufficiency in refined products,” he said in a statement.
In May, Egypt said that it had increased its fuel import budget by almost 40% for the 2026-27 fiscal year amid higher global prices driven by the Iran war, which started when the US and Israel launched an attack on Iran on 28 February.
Brent crude prices are up about a third since the conflict started, trading at more than $90 a barrel for most of this month so far.
Badawi said a decline in Egypt’s oil and gas production between 2021 and 2024 occurred because foreign companies were reluctant to invest in the country’s energy sector due to unpaid government debts.
He said: “We have settled all the debt, which reached $6.1bn in June 2024. As a result, hydrocarbon exploration and production activity grew by nearly 20% this year.
“We are now moving in the right direction to increase oil and gas output gradually.”
Despite the ongoing push to develop projects in the country’s oil and gas sector, several key projects have seen significant delays in recent years.
These include a $2bn hydrocracking complex package that forms part of the wider Assiut oil refinery upgrade project.
Earlier this month, MEED revealed that mechanical completion of the hydrocracking package is now unlikely to be reached until early next year due to complications in the final stages of construction.
The hydrocracking complex package has experienced extensive delays over several years.
In April this year, Badawi called for work to accelerate on the Assiut oil refinery upgrade project, saying it is important for reducing the country’s spending on imported refined products.
At the time, the oil ministry said the project was 88% complete, with trial operations planned by the end of the year.
Assiut Oil Refining Company (ASORC), a subsidiary of state-owned Egyptian General Petroleum Corporation, is the project operator.
France’s Technip Energies is the main contractor, performing engineering, procurement and construction work on the Assiut hydrocracking complex under a $2bn contract awarded by ASORC in February 2020.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19353521/main.jpg -
North Field West platform bidders get extra time4 September 2026

QatarEnergy has granted contractors additional time to prepare bids for a key tender for the engineering, procurement, construction and installation (EPCI) of large platforms for the giant North Field gas field in Qatari waters.
The tender, issued earlier this year, forms part of the wider North Field West (NFW) project, the third and last phase of the state enterprise’s North Field liquefied natural gas (LNG) expansion programme.
The core scope comprises the EPCI of four production deck modules (PDMs) and associated structures. The new PDMs will increase gas production from North Field reservoirs and provide additional gas feedstock for the NFW LNG development.
QatarEnergy has set 15 September as the deadline for technical bid submissions, while commercial bids are due on 10 November, according to sources.
The previous deadlines for submission of technical and commercial bids were 30 August and 25 October, respectively, MEED previously reported.
The following contractors, among others, are understood to be bidding:
- China Offshore Oil Engineering Company (China)
- Larsen & Toubro Energy Hydrocarbon (India)
- McDermott (US)
- Saipem (Italy)
Before issuing the PDM tender, QatarEnergy awarded McDermott a contract for the EPCI of four offshore jackets that will also support gas feedstock supply for the NFW LNG project. The contract is estimated to be worth about $200m, MEED reported in January.
North Field LNG expansion
QatarEnergy is advancing the three phases of its estimated $40bn North Field LNG expansion project. EPC works on all three giant projects are progressing.
QatarEnergy is understood to have committed nearly $30bn to the first two phases – North Field East (NFE) and North Field South (NFS) – which will lift Qatar’s LNG production capacity from 77.5 million tonnes a year (t/y) to 126 million t/y by 2028.
QatarEnergy awarded the main EPC contracts for NFE in 2021. The project was intended to raise LNG output to 110 million t/y by 2025. The $13bn EPC package – covering the EPCI of four LNG trains, each with a capacity of 8 million t/y – was awarded in February 2021 to a consortium of Japan’s Chiyoda and France’s Technip Energies.
In May 2023, QatarEnergy awarded the $10bn main EPC contract for NFS to a consortium of Technip Energies and Consolidated Contractors Company (CCC). The contract includes two LNG trains, each with a capacity of 7.8 million t/y.
Once fully operational, the first two phases are expected to add 48 million t/y of LNG supply to the global market.
QatarEnergy took the final investment decision on NFW this year, awarding an EPC contract estimated at $8bn to a joint venture comprising Technip Energies, CCC and Gulf Asia Contracting (GAC) in February.
Chiyoda carried out the front-end engineering and design (feed) work for the NFW LNG project.
The NFW scope covers the EPC of two LNG trains with a combined capacity of 16 million t/y, as well as associated facilities for gas treatment, natural gas liquids recovery and helium extraction.
In addition to LNG, NFW is expected to produce about 175,000 barrels of oil equivalent a day of condensate, ethane and LPG.
With all three phases now under EPC execution – and NFE scheduled for commissioning later this year – QatarEnergy is positioning itself to remain one of the world’s largest LNG suppliers over the long term.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19352006/main.jpg