Familiar realities threaten Egypt’s energy ambitions

7 February 2024

This package on Egypt's power sector also includes:

Egypt to complete Gabal El Zeit wind farms sale
Egypt president and Putin mark El Dabaa construction
EBRD invests in 1.1GW Egypt wind farm
Scatec in talks for Nagaa Hammadi solar project
> Team signs land deal for 1.1GW Egypt wind project
Acwa Power moves forward with Egypt green hydrogen project


 

As of early 2024, Egypt appears to have come full circle in terms of providing electricity services to its citizens.

The country faced severe power shortages in 2013-14, which gave way to the fast-tracked construction of 14.4GW of gas-powered generation capacity in 2018. This, along with the increase in renewable energy capacity, resulted in a surplus of up to 25%, yet since late last year consumers have once again been experiencing power outages lasting up to two hours.

This time, however, the power outages – which began in the summer of 2023 and are expected to last until March this year – are not due to a capacity deficit.

The government-initiated load-shedding programme initially aimed to rein in rising electricity consumption and reduce pressure on the country's gas network.

According to the country’s Electricity & Renewable Energy Ministry, national electricity consumption reached 43,650MW in mid-July last year, up significantly from previous highs of about 31,000MW.

While the record-high consumption level is still way below the official generation installed capacity of close to 60,000MW, consumption levels of between 34,000MW and 36,000MW will require around 129-146 million cubic metres of gas and diesel a day.

Barring load-shedding, any increase in consumption beyond 36,000MW will require a commensurate increase in gas and diesel, which is understood to be beyond the government’s capacity to procure.

Crucially, the other side of the electricity rationing initiative has to do with the need to save gas for exports, to boost the government’s dollar reserves in the face of the ongoing currency crisis.

Frustration over the power cuts and their impact on job productivity and the overall economy has been growing over the past few months.

There are no magic pills, however, and any solution needs to start with broader economic and energy sector reforms, to improve the prospects of attracting investments, notes Jessica Obeid, a partner at Dubai-headquartered New Energy Consult.

“Reducing reliance on gas for domestic power generation and increasing renewable energy plus storage are critical, not only to reduce the shortage gap but also to improve energy security, since one gas field, Zohr, feeds almost half of the domestic needs,” she explains. “In the immediate term, doubling down on energy-efficient measures and demand-side management is needed.”

It is an awkward and unprecedented situation for the North African state, which has espoused a clear intention – and started executing relevant projects – to establish itself as a regional energy hub, exporting natural gas and electricity to neighbouring countries, as well as to Europe.

“The government has signaled its prioritisation of exports, although no economy can grow nor become a hub while dealing with energy shortages,” Obeid says.

“The Egyptian government has showcased that the focus is on economic revenues from gas exports, even if that is at the expense of the living conditions of the citizens. However, Egypt cannot realise its hefty regional ambitions without efficient measures and reforms to mend the high domestic reliance on gas, and the lower gas production prospects.”

Another expert on Egypt’s energy policies notes that the country is in a tough spot and “needs ideas to move ahead from this”.

In addition to its energy hub plans, Egypt could look into other opportunities such as setting up repair hubs for ships, as well as education centres to cater to the needs of those hubs, the expert suggests, while noting – as Obeid does – the need for wide-ranging reforms, including improving the rule of law and developing alternative sources of wealth and income.

Important milestones

Six months of electricity rationing makes it easy to overlook the cumulative – though, in hindsight, insufficient – steps that Egypt has taken to avoid falling once again into the power outage trap.

Egypt has one of the highest renewable energy penetration rates in relation to overall installed capacity in the Middle East and North Africa region. While this is commendable, it has only served to highlight the weakness of the country's electricity grid when it comes to handling intermittent renewable energy sources such as solar and wind.

Nonetheless, the country is continuing to build additional renewable energy capacity, including hydropower, and with the help of Russian financing, it has also embarked on the construction of its first nuclear power plant. These projects could replace the ageing oil and gas fleet, lowering the sector's emissions while also supporting the country's energy diversification and security agendas.

Egypt aims to be a global green hydrogen and ammonia hub, and signed preliminary agreements for over a dozen such schemes when it hosted the UN global climate summit, Cop27, in November 2022.

If these projects reach the execution stage, not only do they have the potential to advance the country’s ambition to be a global green energy hub, they will also help to attract much-needed dollars to fund its economic diversification plans.

However, the ability to implement reforms and develop bankable projects lies at the heart of the deployment of any technology in Egypt, points out Obeid.

“Egypt’s existing experience in hydrogen, and being part of that trade market, along with abundant renewable energy resources, a vast land [area] and the country’s geographic location are enablers of a hydrogen market," she says.

“Yet, Egypt’s economic and financial challenges have led to higher interest rates, lower lending capacity and higher costs for system components, and these need to be addressed first.”

Never say die 

Despite a bleak short- to medium-term outlook, some projects are moving ahead in Egypt.

The European Bank for Reconstruction & Development will invest $75m in equity in the Netherlands-based subsidiary of Egypt's Hassan Allam Utilities, which along with Saudi utility developer Acwa Power is co-developing a wind independent power producer scheme in the country's Gulf of Suez and Gabal El Zeit area.

Acwa Power also reached financial close for a 200MW solar photovoltaic facility in Kom Ombo in August last year, two years after the project was put on hold due to rising solar panel and freight costs.

Even the 505MW Amunet wind farm project, located in Ras Ghareb in the Gulf of Suez on the Red Sea coast, is moving ahead. A consortium of the UAE-based Amea Power and Japan’s Sumitomo Corporation last year enlisted Shanghai-headquartered Envision Energy to supply wind turbines for the project.

According to the New & Renewable Energy Authority (NREA), solar and wind projects with a total capacity of close to 3.5GW were under development in Egypt as of the end of 2023, while schemes totalling 39GW are in the planning stage. 

Hydrogen and ammonia

In November, Abu Dhabi-based Fertiglobe delivered what might have been the world's first internationally certified renewable ammonia from its pilot electrolyser site in Egypt to India. The ammonia will be used to produce near-zero-emissions synthetic soda ash – a key ingredient in laundry powder – for Unilever.

Several planned integrated green hydrogen projects in Egypt are in the pre-front-end engineering and design (pre-feed) stage.

One of the green ammonia projects is being developed by Germany's DAI Infrastruktur. To be located in East Port Said, the Ra green ammonia project will have a total production capacity of 2 million tonnes a year (mtpa) of green ammonia, of which 1.65 mtpa is expected to be based purely on renewable energy resources when complete.

DAI has signed a preliminary agreement with Siemens Energy, which plans to supply electrolysers, auxiliary plant systems and critical equipment making up the hydrogen island of the project.

DAI and UK-headquartered Freepan Holding are also understood to have signed an offtake agreement for the ammonia produced at the Ra plant. The 10-year offtake agreement covers 800,000 tonnes a year of ammonia, with the first green ammonia delivery to Freepan expected in 2028.

A similarly sized project is being developed by Amea Power in the coastal town of Ain Sokhna in the Suez governorate. The company is in the process of appointing pre-feed consultants and contractors that will undertake geotechnical, topography and environmental studies for the project.

Detailed studies are also under way for interconnections transporting clean energy from Egypt to Europe, as the latter seeks alternatives to Russian energy exports.

Stakeholders in these projects will continue to monitor the Egyptian government's management of its energy policies at home and abroad over the next few months as they decide the next steps in their investment plans.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11489597/main.jpg
Jennifer Aguinaldo
Related Articles
  • Abu Dhabi selects Yas Island site for $1.7bn Sphere venue

    14 May 2026

    Abu Dhabi’s Department of Culture & Tourism (DCT Abu Dhabi) and US-based Sphere Entertainment have selected Yas Island as the location for the $1.7bn Sphere Abu Dhabi project.

    The venue will be built on a plot between Yas Mall and SeaWorld Abu Dhabi, close to Yas Island’s theme parks and attractions. Construction is expected to be completed by the end of 2029. Dubai-listed Alec is understood to be the selected contractor and has been working on the project’s pre-construction phase.

    The project will be the first Sphere venue outside the US. It is expected to echo the scale of Sphere Las Vegas, with a capacity of up to 20,000 depending on configuration.

    DCT Abu Dhabi said it will coordinate enabling and infrastructure works with Abu Dhabi entities, including the Department of Municipalities & Transport and its Integrated Transport Centre, the Department of Energy, Taqa, Etihad Rail and Aldar. The scope includes road enhancements, site access and site-wide infrastructure integrated with surrounding Yas Island assets.

    Sphere Abu Dhabi is the latest addition to Abu Dhabi’s integrated tourism and destination-development pipeline on Yas Island, alongside major attractions and the Disney theme park resort that was announced in 2025.

    DCT and Sphere Entertainment finalised an agreement last year related to the construction, development and operation of the Sphere entertainment venue in Abu Dhabi. According to the agreement, Sphere Entertainment granted DCT the exclusive rights to build and operate the Sphere Abu Dhabi entertainment venue.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16837302/main.gif
    Colin Foreman
  • Consortiums prepare bids for Al-Khairan phase one IWPP

    14 May 2026

     

    Two developer consortiums are finalising bids for the first phase of Kuwait’s Al-Khairan independent water and power producer (IWPP) project, the deadline for which has been extended to 1 June.

    The facility will have a capacity of 1,800MW and 150,000 cubic metres a day of desalinated water. It will be located in Al-Khairan, adjacent to the Al-Zour South thermal plant. 

    The project is expected to run on Low Sulphur Fuel Oil (LSFO) as the primary fuel and to accommodate crude oil, gas oil, and natural gas as backup fuels. Later phases will further expand capacity.

    The main contract was tendered last September. Three consortiums and two individual companies were previously prequalified to participate, with the following groups currently preparing offers:

    • Abu Dhabi National Energy Company (Taqa) / A H Al-Sagar & Brothers (Saudi Arabia) 
    • Acwa (Saudi Arabia) / Gulf Investment Corporation (Kuwait)

    The two individual companies, Sumitomo Corporation (Japan) and Nebras Power (Qatar), are now “unlikely” to submit a bid, according to a source close to the project.

    It is also understood that the third consortium of China Power, Malakoff International (Malaysia) and Abdul Aziz Al-Ajlan Sons (Saudi Arabia) is no longer bidding for the contract.

    The project is being procured by the Kuwait Authority for Partnership Projects (Kapp) and the Ministry of Electricity, Water & Renewable Energy (MEWRE).

    The Al-Khairan IWPP project is part of Kuwait’s long-term plan to expand power and water production capacity through public-private partnerships (PPPs).

    The winning bidder will sign a set of PPP agreements covering financing, design, construction, operation and transfer of the project.

    The energy conversion and water purchase agreement is expected to cover a 25-year supply period.

    Upcoming awards

    Kuwait is also preparing to offer a contract to develop zone one of the third phase of the Al-Dibdibah power and Al-Shagaya renewable energy project.

    In January, three consortiums submitted bids for a contract to develop Kuwait’s first utility-scale solar photovoltaic (PV) plant.

    The Al-Dibdibah power and Al-Shagaya renewable energy phase three, zone one independent power project (IPP) will have a total power-generating capacity of 1,100MW.

    MEED understands that the preferred bidder announcement will happen after the bid closes for zone two of the third phase of the Al-Dibdibah power and Al-Shagaya renewable energy project.

    The PPP authority is procuring the 500MW solar photovoltaic IPP in partnership with the ministry.

    The bid deadline for this project was recently extended to 31 May.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16835649/main.jpg
    Mark Dowdall
  • Bidders compete for new Dubai Metro line project

    14 May 2026

     

    Register for MEED’s 14-day trial access 

    Dubai’s Roads & Transport Authority (RTA) has held a pre-bid meeting for the Dubai Metro Airport Express Line with consultants understood to be competing for work on the project.

    It is understood that the RTA has requested firms to form joint ventures for the project. The firms that attended the meeting include:

    • Aecom (US)
    • Arup (UK)
    • ARX (Switzerland)
    • AtkinsRealis (Canada)
    • DB (Germany)
    • Egis (France)
    • Jacobs (US)
    • Mott Macdonald (UK)
    • Parsons (US)
    • Sener (Spain)
    • Surbana Jurong (Singapore)
    • Systra (France)
    • WSP (Canada)

    The consultancy contract covers the study and design of the Airport Express Line, which will extend from the Al-Garhoud area of the city to Al-Maktoum International airport (DWC) in the Jebel Ali area. The proposed line will stretch about 55 kilometres (km) and include five stations, providing passengers with facilities such as remote airline check-in, baggage drop-off and security screening.

    Consultants have been allowed until June to submit their proposals.

    The new line will run from the Red Line metro station at Dubai International airport through Al-Jaddaf, along Al-Khail Road to a new station at Jumeirah Village Circle (JVC) before continuing on to DWC.

    There will be two spur lines. The first will run from the new JVC station to the Al-Fardan Exchange metro station at Emirates Golf Club, while the second will branch out towards Business Bay, where another station will be built.

    The new line appears to follow a similar route to the Etihad Rail high-speed railway project, which is now under construction and due to be completed by 2030.

    Route 2020 extension

    The Airport Express Line scheme is the latest metro project to be tendered by the RTA this year. Tendering activity is already ongoing for the Route 2020 extension, which will start from the Expo 2020 metro station and connect to DWC’s West Terminal.

    In April, MEED exclusively reported that consultants had submitted bids for the project.

    The extension to the line will run for about 3km and will feature two stations.

    The existing Route 2020 metro link is a 15km-long line that branches off the Red Line at Jebel Ali metro station. The line comprises 11.8km of elevated tracks and 3.2km of tunnels, and has five elevated stations and two underground stations.

    The RTA awarded the AED10.6bn ($2.9bn) design-and-build contract for the project to a consortium of Spain’s Acciona, Turkiye’s Gulermak and France’s Alstom in 2016.

    Gold Line

    Dubai’s plans for its metro network do not stop with connecting the extension of the Route 2020 metro line to DWC. There are long-term plans for further extensions.

    In October last year, MEED exclusively reported that the RTA had selected US-based engineering firm Aecom to provide consultancy services for the upcoming Dubai Metro Gold Line project, also known as Metro Line 4.

    The Gold Line will start at Al-Ghubaiba in Bur Dubai. It will run parallel to – and alleviate pressure on – the existing Red Line, before heading inland to Business Bay, Meydan, Global Village and residential developments in Dubailand.

    The existing network includes the Red and Green lines of the Dubai Metro and the Dubai Tram, which connects Al-Sufouh and Dubai Marina to the metro network. The last rail project to start operations in Dubai was the Red Line extension that opened for Expo 2020.

    There are also existing and planned rail lines connecting Dubai to other emirates that are being developed and operated by Abu Dhabi-based Etihad Rail. These include passenger and freight services, as well as a high-speed rail connection.

    Blue Line

    In December 2024, the RTA awarded a AED20.5bn main contract for the Dubai Metro Blue Line project to a consortium of Turkish firms Limak Holding and Mapa Group and the Hong Kong office of China Railway Rolling Stock Corporation.

    The Blue Line consists of 14 stations, including three interchange stations at Jaddaf, Rashidiya and International City 1, as well as a station in Dubai Creek Harbour.

    By 2040, the number of daily passengers on the Blue Line is projected to reach 320,000. It will be the first Dubai Metro line to cross Dubai Creek, doing so on a 1,300-metre viaduct.

    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16833450/main.jpg
    Colin Foreman
  • Local firm wins $100m Kuwait substation contract

    14 May 2026

     

    The local Al-Ahleia Switchgear Company has won an engineering, procurement and construction contract for a $100m substation project in Wafra in Kuwait’s Al-Ahmadi Governorate.

    According to a source, the firm has been appointed as the contractor for the Wafra 2Z substation 400/132/33kV project, with construction scheduled for completion in January 2029.

    The contract was awarded by US-headquartered Chevron, which is undertaking its first major power project in Kuwait, according to data from MEED Projects.

    It is understood that contractor bids for the project were first submitted in 2023 by National Contracting Company (Kuwait), Al-Ahleia Switchgear (Kuwait), Imco Engineering & Construction Company (Kuwait) and Larsen & Toubro (India).

    The tender was cancelled in 2024, and a new tender was issued last year.

    In April, Al-Ahleia Switchgear won a contract to build a 400/132/11kV substation at the South Surra township for Kuwait’s Public Authority for Housing Welfare.

    The firm also recently won a separate contract in Oman for the supply, installation, execution and maintenance of a main power substation.

    The contract was awarded by Oman’s Public Authority for Social Insurance as part of its affordable housing project, known locally as Al-Masaken Al-Muyassara.

    According to MEED Projects, Chevron owns about $11.2bn-worth of operational oil and gas projects across the Middle East and Africa. It also owns four major power generation projects in Saudi Arabia, valued at $810m.

    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16832909/main.jpg
    Mark Dowdall
  • Al-Ain breaks ground on Four Seasons Saadiyat

    14 May 2026

    Al-Ain Asset Management has held a groundbreaking ceremony for its Four Seasons Private Residences Abu Dhabi project at Saadiyat Beach.

    Due for completion in 2029, the gated beachfront scheme will comprise 116 ultra-luxury homes with direct beach access. The unit mix includes villas, beachfront mansions, suites and penthouses, alongside a range of bespoke amenities and Four Seasons-branded services, Wam reported.

    Al-Ain Asset Management said the majority of the residences have been sold, and that AED250m ($68m) of new villa sales were recorded within one week, underlining demand for ultra-prime homes in Abu Dhabi.

    The developer added that the development set new pricing benchmarks for the emirate’s luxury coastal real estate, achieving prices above AED14,000 a square foot. Total sales have exceeded AED4bn since the project launched less than a year ago.

    The groundbreaking ceremony was attended by senior leadership and key partners, including Four Seasons, Killa Design and Mirage Leisure & Development. LW Design Group is also involved in the development.

    Al-Ain Asset Management is also developing another residential scheme on Saadiyat Island. The Vida Residences development will comprise apartment units geared towards long-stay living, supported by hotel-style facilities and operational spaces. Mimar Architecture & Engineering is working as the consultant.

    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16833035/main.jpeg
    Colin Foreman