Facility E award jumpstarts Qatar’s utility projects
13 January 2025

A developer team led by Japan’s Sumitomo Corporation won the contract in November to develop and operate the Facility E independent water and power project (IWPP) in Qatar.
The project’s $2.8bn engineering, procurement and construction (EPC) contract drove the overall value of awarded contracts in the state’s utility sector to $3.9bn in 2024.
This makes 2024 the second-best year ever for Qatar’s utility sector, after 2015, when it let contracts worth over $7bn, including its last IWPP, Facility D in Umm Al-Houl, and other key utility projects.
Qatar General Electricity & Water Corporation (Kahramaa) awarded the Facility E IWPP contract, which has a total cost of $3.7bn, five years after it was initially tendered.
It marks a milestone following a slower pace in contract awards in recent years due to the completed delivery of infrastructure projects catering to the 2022 Fifa World and Covid-19 uncertainties.
Peak demand growth
Qatar’s total contracted electricity capacity, which stood at 10,573MW in 2023, increases to over 11,300MW when the capacity from the 800MW Al-Kharsaah solar plant is included.
This equates to a reserve margin of around 14% given the 2023 peak electricity demand of 9,805MW, as reported by the state utility.
A steady growth in peak electricity demand, up 4.3% in 2023 and 5.9% the year before, even when water demand remained stable at 425 million imperial gallons a day (MIGD), implies the state utility requires substantial additional capacity, which helped trigger the award of the Facility E IWPP contract last year.
The Facility E IWPP developer consortium includes Japanese utility developer Shikoku Electric, Seoul-headquartered Korea Overseas Infrastructure & Urban Development Corporation (Kind) and Korea Southern Power Company (Kospo).
The consortium and the strategic national investors, Qatar Electricity & Water Company (QEWC) and QatarEnergy (QE), will co-own the project company that is implementing the project.
The equity distribution between the project company shareholders is:
- Sumitomo Corporation: 17%
- Shikoku Electric: 11%
- Kospo: 6%,
- Kind: 6%
- QEWC: 55%
- QE: 5%
South Korea’s Samsung C&T is the project’s overall EPC contractor. Japan’s Mitsubishi Power is supplying advanced combined-cycle gas turbines for the power plant, and Spain’s Acciona is contracted to build the integrated plant’s $500m seawater reverse osmosis (SWRO) unit.
Unlike previous IWPPs, the Facility E IWPP tender attracted a single bid on both the initial and final rounds. This demonstrates increasing reticence among international utility developers when bidding for thermal assets as they grapple with their carbon neutrality targets by or before 2050.
The state utility and developer consortium had to contend with issues including the final capacity, costs and decarbonisation aspects of the project.
In the end, they agreed to develop a gas-fired power plant with a final electricity generation capacity of 2,415MW and a SWRO-based desalination plant with a capacity of 110MIGD.
The power and water purchase agreement for the Facility E IWPP is valid for 21 years, until 2049, a year shy of the developers’ target date for reaching carbon neutrality.
They also agreed to a levelised electricity cost of about QR190.71 a megawatt-hour, equivalent to $cents 5.239 a kilowatt-hour, and a levelised water cost of QR2,914 per 1,000 cubic metres, or about $cents 8.0 a cubic metre.
The tariffs exclude potential carbon capture, utilisation and storage (CCUS) costs.
Expanding capacity
Following the award of the Facility E IWPP contract, QEWC said it is cooperating with Kahramaa to explore a build, own and operate peak power unit project with a production capacity of 500MW.
A peak power unit typically refers to an open-cycle gas turbine plant, which can help increase the electricity grid’s flexibility to meet peak demand. The planned 500MW power plant will be located in Qatar’s Ras Abu Fontas, the same area where the Facility E IWPP will be built.
Qatar has been expanding its renewable energy capacity following the completion of its first utility-scale solar photovoltaic (PV) project in Al-Kharsaah in 2023. This is in line with its long-term objective to have a renewable energy installed capacity of 5,000MW by 2035.
Samsung C&T is constructing two solar PV plants in the Gulf state, costing $632m and with a combined capacity of 875MW.
One of the solar plants, located in Ras Laffan, has a capacity of 458MW. The other plant, located in Mesaieed, will have a capacity of 417MW.
The electricity generated by the two plants will be partly used for QatarEnergy’s liquefied natural gas production expansion.
In September 2024, Minister of State for Energy Affairs Saad Sherida Al-Kaabi also confirmed plans to build a 2,000MW solar power plant in Dukhan, 80 kilometres west of Doha.
The planned Dukhan solar PV plant will help to “lower carbon emissions in the framework of a realistic energy transition”. Once completed, it will increase Qatar’s solar PV capacity to close to 4,000MW by 2030.
Grid stability
Qatar’s efforts to expand its thermal and solar power generation capacity have led to the expansion of its transmission and distribution network.
Last year, Kahramaa awarded Elsewedy Cables Qatar two EPC contracts with a total combined value of QR2.2bn ($604m).
The first contract involves supplying low- and medium-voltage cables catering to a planned new underground extra-high-voltage/high-voltage cable network.
The second contract involves providing EPC services, including supplying and installing 132-kilovolt (kV) power cables for strategic projects across the state.
In October, Kahramaa tendered two contracts to upgrade segments of its electricity grid. The first contract calls for upgrading Ras Laffan C’s existing 220kV and 400kV substations and adding 220kV gas-insulated switchgear bays and an 800-megavolt amps transformer.
Kahramaa also invited firms to submit their proposals for a contract to supply and install power transmission and distribution equipment, including providing and connecting substation main earth and equipment earthing, commissioning fitted substations and pre-commissioning protection testing for 11kV switchgear panels.
Future projects
As of January 2025, more than $4bn-worth of utility projects are under execution in Qatar, excluding the Facility IWPP, which has yet to reach financial close.
The largest scheme under execution is the $720m Wakra and Wukair independent sewage treatment plant project. It will have a capacity of 150,000 cubic metres a day (cm/d), which can be extended to 600,000 cm/d at a later stage. The project reached financial close last year.
An estimated $4bn of power and $5.8bn of water infrastructure contracts are planned and unawarded in Qatar at the beginning of 2025.
QatarEnergy’s 2,000MW Dukhan solar PV, the Public Works Authority’s (Ashghal) New District of Doha and South of Wakrah marine pump station and outfall facilities, and the 500MW Ras Abu Fontas open-cycle power plant are some of the key projects expected to come onto the market over the next 12 to 18 months.
Exclusive from Meed
-
-
Algeria tenders upstream oil project contract25 June 2026
-
-
-
Chinese firm wins $265m Saudi hospital contract24 June 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Firms prepare Hudayriat East PPP tunnels advisory bids25 June 2026

Abu Dhabi’s Modon Infrastructure, formerly Gridora, has tendered a contract for technical advisory services for the construction of two underwater tunnels connecting the eastern side of Hudayriat Island with mainland Abu Dhabi.
Consultants have until 26 June to submit their proposals.
The project includes the construction of a 4.8-kilometre (km) highway, with four lanes in each direction, connecting Hudayriat Island to Mussafah 8th Street.
The project will be delivered on a public-private partnership (PPP) basis in coordination with the Abu Dhabi Department of Municipalities and Transport and the Abu Dhabi Investment Office.
The contract term is expected to be 25 years.
The latest infrastructure development in Abu Dhabi follows Modon Infrastructure’s invitation in May for firms to register for the next phase of Abu Dhabi’s Mid Island Parkway Project (MIPP), which will also be developed on a PPP basis.
Modon Infrastructure will act as the lead developer, holding the majority equity stake in the project company. It will award the engineering, procurement and construction contract, as well as the operations and maintenance services and advisory appointments.
The second phase of the MIPP involves the construction of about 11km of highways, including a mix of three-, four- and five-lane sections. The highways will connect the Um-Yifeenah, Al-Jubail, Al-Sammaliyyah and Sas Al-Nakhl islands to Khalifa City and the E10 road.
The scope also covers the construction of three interchanges: the E20, E10 and Dumbbell interchanges on Al-Sammaliyyah Island.
The project includes several major structures, such as the E20 interchange, which will feature cast-in-place box-girder and void-slab bridges, and the E10 interchange with cast-in-place box-girder bridges. It also includes I-girder bridges between Raha Beach West and Sas Al-Nakhl Island, as well as a causeway at Sas Al-Nakhl Island.
Further key elements include a cast-in-place balanced cantilever bridge between Sas Al-Nakhl Island and Al-Sammaliyyah Island; a tunnel between Al-Sammaliyyah Island and Bilrimaid Island; and a cut-and-cover (open) tunnel on Bilrimaid Island. The project will be completed with another tunnel connecting Bilrimaid Island to Um-Yifeenah Island.
> Be recognised among the best in the industry at the MEED Projects Awards 2026 …
https://image.digitalinsightresearch.in/uploads/NewsArticle/17410214/main.jpg -
Algeria tenders upstream oil project contract25 June 2026
Algeria’s state-owned national oil and gas company, Sonatrach, has tendered a contract for the development and rehabilitation of the central processing facility (CPF) at the Bir Berkine oil and gas field.
The scope of the contract includes the study, supply, construction and commissioning of a project to rehabilitate the CPF facilities at the field, which is located in the Hassi Mesaoud region.
Sonatrach says in the tender documents that the objective of the project is to ensure the continuity of production activities “under stable and secure operating conditions”.
It also says the project aims to improve production yields and quality.
The contract includes both initial and detailed studies as well as the supply of all equipment and materials.
It also includes the execution of works, the assembly of all equipment and materials, and the commissioning of all relevant facilities.
The tender has a two-stage submission process, with the first stage requiring technical bids to be submitted by 23 August.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17423013/main3916.jpg -
Red Sea Global tenders King Salman Bay construction work25 June 2026

Saudi gigaproject developer Red Sea Global (RSG) has tendered a contract inviting firms to undertake marine infrastructure works at King Salman Bay on the Red Sea coast, north of Jeddah.
The scope includes dredging and earthworks, as well as quay wall and edge protection works spanning about 11 kilometres.
The bid submission deadline is 31 July.
King Salman Bay is expected to be a waterfront development aimed at reshaping the city’s northern Red Sea frontage into a mixed-use destination, anchored by public-realm improvements and leisure-led development.
The update follows RSG’s award of an estimated SR100m ($27m) contract to construct a solid waste management centre at its Red Sea Project. The scope includes four buildings: a material recycling facility, a transfer station, an administration building and a vehicle maintenance building.
In October last year, MEED reported that RSG had secured a SR6.5bn ($1.7bn) credit facility to further develop Amaala, its luxury tourism destination on Saudi Arabia’s northwestern Red Sea coast.
According to an official statement, “The funding is led by Riyad Bank as the sole underwriter, along with Saudi Investment Bank and Bank Al-Bilad as mandated lead arrangers.
“The loan arrangement comprises a mix of conventional and Islamic financing and adheres to RSG’s Green Loan Framework, which was first established when it secured private funding from a consortium of four banks for the Red Sea destination in 2021,” the statement added.
The announcement followed RSG’s opening of its first properties for sale at Amaala, including branded residential communities and a five-bedroom villa on a private island.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17430045/main.jpg -
MECC submits lowest bid on three Kuwaiti oil and gas contracts25 June 2026

Kuwait-based Mechanical Engineering & Contracting Company (MECC) has submitted the lowest bid across three separate contracts tendered by the state-owned upstream operator Kuwait Oil Company (KOC).
The total value of the low bids is $427m, and all of the contracts are focused on developing substations to power industrial lift pumps and remote header manifolds
Five companies submitted bids for a contract to develop several substations to power industrial lift pumps and remote header manifolds in areas 6, 10 and 12 in southern and eastern Kuwait.
The bidders were:
- MECC: KD65,760,000 ($212m)
- Heavy Engineering Industries & Shipbuilding Company: KD70,630,000 ($228m)
- Amco Engineering & Construction: KD73,446,100 ($237m)
- Combined Group Contracting Company: KD76,186,000 ($246m)
- Nasser Mohammed Al-Badah & Partner General Trading & Contracting: KD79,332,417 ($256m)
Six companies submitted bids for a contract to develop several substations to power industrial lift pumps and remote header manifolds in areas 8 and 13 in southern and eastern Kuwait.
The bidders were:
- MECC: KD30,760,000 ($99m)
- Badr Al-Mulla & Brothers: KD32,662,040 ($106m)
- Heavy Engineering Industries & Shipbuilding Company: KD34,139,000 ($110m)
- Industrial Company for Electrical Projects: KD36,375,520 ($118m)
- Nasser Mohammed Al-Badah & Partner General Trading & Contracting: KD37,278,526 ($120m)
- Combined Group Contracting Company: KD37,790,000 ($122m)
Eight companies submitted bids for a contract focused on developing several substations to power industrial lift pumps and remote header manifolds in areas 7, 9, and 11 in southern and eastern Kuwait.
The bidders were:
- MECC: KD35,760,000 ($116m)
- Badr Al-Mulla & Brothers: KD39,447,165 ($127m)
- Amco Engineering & Construction: KD39,736,800 ($128m)
- Heavy Engineering Industries & Shipbuilding Company: KD40,105,000 ($130m)
- Industrial Company for Electrical Projects: KD43,238,265 ($140m)
- Engineering Company for Petroleum & Chemical Industries (Enppi): KD43,514,805 ($141m)
- Combined Group Contracting Company: KD43,650,000 ($141m)
- Nasser Mohammed Al-Badah & Partner General Trading & Contracting: KD43,706,826 ($141m)
Kuwait’s oil and gas sector has been in crisis in recent months due to disruption from the regional conflict that started after the US and Israel attacked Iran on 28 February 2026.
A preliminary peace agreement between the US and Iran, which was announced on 14 June, has increased optimism that disruption to the sector will decrease in the coming weeks.
Under the terms of the agreement, both sides have stated that the free flow of vessels will be permitted through the Strait of Hormuz, through which nearly all of Kuwait’s crude oil is normally exported.
READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDFGCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.
Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:
> AGENDA: Gulf races to reroute trade> EXPORT ROUTES: Regional war boosts oil and gas pipeline project activity> CURRENT AFFAIRS: UAE’s Opec departure fulfils multiple ends> MEED TOP 100: Middle East stocks recover unevenly> LEADERSHIP: Building the infrastructure that makes net zero possible> TRADE DEAL: UK-GCC trade deal talks concludeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17423009/main.jpg -
Chinese firm wins $265m Saudi hospital contract24 June 2026
Zhejiang Construction International, the local subsidiary of Chinese contractor Zhejiang Construction Investment Group, has won a $265m contract to build the Prince Mohammed Bin Fahd University Speciality Hospital in Al-Khobar.
Construction is expected to take three years from the start date.
Prince Mohammed Bin Fahd University awarded the contract.
Located in Al-Raja district, Al-Khobar, in Saudi Arabia’s Eastern Province, the hospital project will cover about 60,000 square metres.
The contract covers the construction of a 10-storey hospital building, two five-storey auxiliary buildings connected by corridors and a basement.
Work will include civil works, mechanical and electrical installation, curtain walling, landscaping, detailed design and the procurement of medical equipment.
The award is the latest in a series of contracts secured by Chinese contractors from Saudi entities in recent months.
Last week, MEED reported that Saudi Arabia’s Ministry of Municipalities & Housing awarded contracts worth more than SR1.9bn ($506m) to Chinese contractors for two residential developments in the kingdom.
China Architectural Construction Corporation won the first contract, valued at SR875m ($233m), to build 2,010 housing units at the Al-Ruba residential project in Riyadh.
China State Construction Engineering Corporation secured the other contract, valued at more than SR1bn ($266m), for the Al-Rasha Al-Faisaliah residential project in Dammam, comprising 2,426 housing units.
GlobalData expects Saudi Arabia’s construction industry to record average annual growth of 5.2% in 2025-28, supported by investments in transport, electricity, housing and tourism infrastructure, as well as the $850bn-plus gigaprojects programme.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17412846/main.jpg

