Facility E award jumpstarts Qatar’s utility projects

13 January 2025

 

A developer team led by Japan’s Sumitomo Corporation won the contract in November to develop and operate the Facility E independent water and power project (IWPP) in Qatar.

The project’s $2.8bn engineering, procurement and construction (EPC) contract drove the overall value of awarded contracts in the state’s utility sector to $3.9bn in 2024.

This makes 2024 the second-best year ever for Qatar’s utility sector, after 2015, when it let contracts worth over $7bn, including its last IWPP, Facility D in Umm Al-Houl, and other key utility projects.

Qatar General Electricity & Water Corporation (Kahramaa) awarded the Facility E IWPP contract, which has a total cost of $3.7bn, five years after it was initially tendered.

It marks a milestone following a slower pace in contract awards in recent years due to the completed delivery of infrastructure projects catering to the 2022 Fifa World and Covid-19 uncertainties.

Peak demand growth

Qatar’s total contracted electricity capacity, which stood at 10,573MW in 2023, increases to over 11,300MW when the capacity from the 800MW Al-Kharsaah solar plant is included.

This equates to a reserve margin of around 14% given the 2023 peak electricity demand of 9,805MW, as reported by the state utility.

A steady growth in peak electricity demand, up 4.3% in 2023 and 5.9% the year before, even when water demand remained stable at 425 million imperial gallons a day (MIGD), implies the state utility requires substantial additional capacity, which helped trigger the award of the Facility E IWPP contract last year.

The Facility E IWPP developer consortium includes Japanese utility developer Shikoku Electric, Seoul-headquartered Korea Overseas Infrastructure & Urban Development Corporation (Kind) and Korea Southern Power Company (Kospo).

The consortium and the strategic national investors, Qatar Electricity & Water Company (QEWC) and QatarEnergy (QE), will co-own the project company that is implementing the project.

The equity distribution between the project company shareholders is:

  • Sumitomo Corporation: 17%
  • Shikoku Electric: 11%
  • Kospo: 6%,
  • Kind: 6%
  • QEWC: 55%
  • QE: 5%

South Korea’s Samsung C&T is the project’s overall EPC contractor. Japan’s Mitsubishi Power is supplying advanced combined-cycle gas turbines for the power plant, and Spain’s Acciona is contracted to build the integrated plant’s $500m seawater reverse osmosis (SWRO) unit.

Unlike previous IWPPs, the Facility E IWPP tender attracted a single bid on both the initial and final rounds. This demonstrates increasing reticence among international utility developers when bidding for thermal assets as they grapple with their carbon neutrality targets by or before 2050.

The state utility and developer consortium had to contend with issues including the final capacity, costs and decarbonisation aspects of the project.

In the end, they agreed to develop a gas-fired power plant with a final electricity generation capacity of 2,415MW and a SWRO-based desalination plant with a capacity of 110MIGD.

The power and water purchase agreement for the Facility E IWPP is valid for 21 years, until 2049, a year shy of the developers’ target date for reaching carbon neutrality.

They also agreed to a levelised electricity cost of about QR190.71 a megawatt-hour, equivalent to $cents 5.239 a kilowatt-hour, and a levelised water cost of QR2,914 per 1,000 cubic metres, or about $cents 8.0 a cubic metre.

The tariffs exclude potential carbon capture, utilisation and storage (CCUS) costs.

Expanding capacity 

Following the award of the Facility E IWPP contract, QEWC said it is cooperating with Kahramaa to explore a build, own and operate peak power unit project with a production capacity of 500MW. 

A peak power unit typically refers to an open-cycle gas turbine plant, which can help increase the electricity grid’s flexibility to meet peak demand. The planned 500MW power plant will be located in Qatar’s Ras Abu Fontas, the same area where the Facility E IWPP will be built.

Qatar has been expanding its renewable energy capacity following the completion of its first utility-scale solar photovoltaic (PV) project in Al-Kharsaah in 2023. This is in line with its long-term objective to have a renewable energy installed capacity of 5,000MW by 2035.

Samsung C&T is constructing two solar PV plants in the Gulf state, costing $632m and with a combined capacity of 875MW.

One of the solar plants, located in Ras Laffan, has a capacity of 458MW. The other plant, located in Mesaieed, will have a capacity of 417MW.

The electricity generated by the two plants will be partly used for QatarEnergy’s liquefied natural gas production expansion.

In September 2024, Minister of State for Energy Affairs Saad Sherida Al-Kaabi also confirmed plans to build a 2,000MW solar power plant in Dukhan, 80 kilometres west of Doha.

The planned Dukhan solar PV plant will help to “lower carbon emissions in the framework of a realistic energy transition”. Once completed, it will increase Qatar’s solar PV capacity to close to 4,000MW by 2030.

Grid stability

Qatar’s efforts to expand its thermal and solar power generation capacity have led to the expansion of its transmission and distribution network.

Last year, Kahramaa awarded Elsewedy Cables Qatar two EPC contracts with a total combined value of QR2.2bn ($604m).

The first contract involves supplying low- and medium-voltage cables catering to a planned new underground extra-high-voltage/high-voltage cable network.

The second contract involves providing EPC services, including supplying and installing 132-kilovolt (kV) power cables for strategic projects across the state.

In October, Kahramaa tendered two contracts to upgrade segments of its electricity grid. The first contract calls for upgrading Ras Laffan C’s existing 220kV and 400kV substations and adding 220kV gas-insulated switchgear bays and an 800-megavolt amps transformer.

Kahramaa also invited firms to submit their proposals for a contract to supply and install power transmission and distribution equipment, including providing and connecting substation main earth and equipment earthing, commissioning fitted substations and pre-commissioning protection testing for 11kV switchgear panels.

Future projects

As of January 2025, more than $4bn-worth of utility projects are under execution in Qatar, excluding the Facility IWPP, which has yet to reach financial close.

The largest scheme under execution is the $720m Wakra and Wukair independent sewage treatment plant project. It will have a capacity of 150,000 cubic metres a day (cm/d), which can be extended to 600,000 cm/d at a later stage. The project reached financial close last year.

An estimated $4bn of power and $5.8bn of water infrastructure contracts are planned and unawarded in Qatar at the beginning of 2025.

QatarEnergy’s 2,000MW Dukhan solar PV, the Public Works Authority’s (Ashghal) New District of Doha and South of Wakrah marine pump station and outfall facilities, and the 500MW Ras Abu Fontas open-cycle power plant are some of the key projects expected to come onto the market over the next 12 to 18 months.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13240142/main4659.gif
Jennifer Aguinaldo
Related Articles
  • Dubai prequalifies developers for $22bn tunnels PPP

    6 February 2025

    Dubai Municipality has prequalified developers for the first four packages of the $22bn Dubai Strategic Sewerage Tunnels (DSST) project.

    According to industry sources, at least three companies have been prequalified as lead members of potential consortiums that can bid for the contracts.

    These include:

    • Etihad Water & Electricity subsidiary (local)
    • Itochu (Japan)
    • Vision Invest (Saudi Arabia)

    Other companies have been prequalified as technical members. 

    MEED reported in October that over a dozen companies were keen to prequalify as investors or sponsors of the planned public-private partnership (PPP) project.

    They included:

    • Abrdn Investcorp Infrastructure Investments Manager (UK)
    • Besix (Belgium)
    • China Railway Construction Corporation (CRCC)
    • China Railway Engineering Group (CREG)
    • China State Construction Engineering Corporation (China)
    • Itochu (Japan)
    • Nesma Company (Saudi Arabia)
    • Plenary (Australia)
    • Samsung C&T (South Korea)
    • Vision Invest (Saudi Arabia)
    • Webuild (Italy)

    The request for proposals for the project's first two packages is expected to be issued imminently.

    MEED previously reported that the bidders for the PPP packages will be prequalified consortiums comprised of sponsors or investors, EPC contractors, and operations and maintenance contractors.

    The overall project will require a capital expenditure of about AED30bn ($8bn), while the whole-life cost over the full concession terms of the entire project is estimated to reach AED80bn.

    The investor prequalification process for the scheme comes after the client prequalified EPC contractors that can partner with the developers or investors to bid for the contracts.

    MEED understands that packages J1 and W will be tendered together as separate contracts first, followed by J2 and J3, with the requests for proposals to be issued sequentially, staggered about six to 12 months apart.

    DSST packages

    Under the current plan, the $22bn DSST project is broken down into six packages, which will be tendered as PPP packages with concession periods lasting between 25 and 35 years.

    The first package, J1, comprises Jebel Ali tunnels (North) and terminal pump stations (TPS). The tunnels will extend approximately 42 kilometres (km), and the links will extend 10km. 

    The second package, J2, covers the southern section of the Jebel Ali tunnels, which will extend 16km and have a link stretching 46km.

    The third package, W for Warsan, comprises 16km of tunnels, TPS and 46km of links.

    J3, the fourth package, comprises 129km of links.

    J1, J2, W and J3 will comprise the deep sewerage tunnels, links and TPS (TLT) components of the overall project.

    J1, J2 and W will be procured under a design-build-finance-operate-maintain model with a concession period of 25-35 years.

    J3 will be procured under a design-build-finance model with a concession period of 25-35 years. Once completed, Dubai Municipality will operate J3, unlike the first three packages, which are planned to be operated and maintained by the winning PPP contractors.  

    The project’s remaining two packages entail expanding and upgrading the Jebel Ali and Warsan sewage treatment plants. MEED understands that these packages will be procured at a later stage.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13370610/main.jpg
    Jennifer Aguinaldo
  • Iraq and GE Vernova complete plants upgrade

    6 February 2025

    US-headquartered energy technology provider GE Vernova has completed the upgrades of “several key” power plants in Iraq.

    The firm and the Iraqi Ministry of Electricity (MoE) announced the upgrade’s completion on 5 February.

    The overall upgrade project, which GE Vernova previously announced, covers 46 gas turbines across 12 power plants, adding up to 500MW to Iraq’s national grid before the summer of 2025.

    They did not specify which power plants have completed upgrade works.  

    According to GE, some of the power plants included in this project already transitioned from heavy fuel oil (HFO) to natural gas, with a capacity increase of approximately 260MW. These plants include Ninawa, Al-Diwaniyah, Hilla, Karbala, Shat Al-Basra, Najibiya, Samawa, Dhiqar, Al-Khairat and Al-Haidariya.

    GE Vernova added: “The other plants are expected to be modernised within the summer of 2025, with an expected additional increase in capacity of approximately 250MW.

    “This modernisation is expected to improve operational flexibility and boost output, efficiency and availability of the power generation assets.”

    In addition, the firm announced the successful installation of its Advanced Gas Path (AGP) upgrades on several 9. E gas turbines powering the Al-Quds and Dhiqar power plants, and MXLII upgrades on 13E2 gas turbines powering the Al-Mansouriya power plant.

    According to GE Vernova, the expected output increases of up to 6% for each power plant will enable the MoE to generate more electricity using the same amount of fuel.

    In addition, as part of the services and upgrade agreement announced in 2024 with the MoE to enhance the availability of power plants across the country, GE Vernova completed comprehensive maintenance projects across several of these power plants, corresponding to a total capacity of 3.7GW.

    These power plants include Qayyarah, Diwaniyah, Al-Haydariyah and Baghdad South. 

    Iraq periodically suffers from power outages, especially during the summer months, when increased cooling requirements overwhelm its power plants and electricity grid.  


    READ THE FEBRUARY MEED BUSINESS REVIEW

    Trump unleashes tech opportunities; Doha achieves diplomatic prowess and economic resilience; GCC water developers eye uptick in award activity in 2025.

    Published on 1 February 2025 and distributed to senior decision-makers in the region and around the world, the February MEED Business Review includes:

    > WATER & WASTEWATER: Water projects require innovation
    https://image.digitalinsightresearch.in/uploads/NewsArticle/13370380/main.jpg
    Jennifer Aguinaldo
  • Bankability remains hydrogen’s unbreakable challenge

    6 February 2025

    Commentary
    Jennifer Aguinaldo
    Energy & technology editor

    There is some indication that green hydrogen as an industry has arrived at the valley of disillusionment if the Gartner hype cycle is anything to go by.

    This is evident with the dwindling number of attendees and absence of offtakers – global commodity trading companies that are expected to buy premium green hydrogen and derivative products – at previously well-attended green hydrogen summits in major cities in the Gulf.

    Following frenzied announcements of multibillion-dollar integrated green hydrogen and ammonia plants in the Middle East and North Africa region, particularly Egypt, Morocco, Oman and the UAE, between 2021 and 2023, it appears that key stakeholders have started coming to grips with reality.

    Of the close to 80 green hydrogen projects that MEED and MEED Projects track, only three have so far signed an offtake agreement, and only one has managed to reach financial close.

    The $8.4bn Neom green hydrogen project in Saudi Arabia reached financial close in March 2023, nearly two years after it was announced.

    The project, the largest of its kind requiring over 4GW of renewable energy and 2GW of electrolyser capacity, managed to reach financial close based on one of the three co-developers, the US’ Air Products, assuming the full offtake and construction risks for the project, note some experts.

    A project’s bankability ultimately relies on suitable stakeholders taking on the risks for every aspect of the project, from construction to operations.

    Currently, the risks or threats include evolving global regulations related to consumption and carbon emissions pricing; lack of technology maturity; supply and demand uncertainty; and the lack of mainstream demand, according to Wael Almazeedi, chief executive at Abu Dhabi-based International Renewable Energy Certification (I-rec) certified firm Avance Energy.

    Almazeedi said these risks “need to be mitigated to the satisfaction of project lenders” if the planned green hydrogen projects in the region are to secure financing and reach the construction phase.

    The challenges do not necessarily mean all projects will fail, however.

    Similar to predecessors such as solar and electrification technologies, the hope is for the planned green hydrogen projects to eventually emerge out of the realm of disillusionment and reach the so-called enlightenment slope and, ultimately, plateaus of productivity, using Gartner’s hype cycle model.

    Government support in terms of regulatory frameworks, inevitably including some form of subsidies to bridge the so-called green premium, as well as global certification standards, are at the top of suppliers’ agendas. 

    Across the key aspiring Mena clean hydrogen hubs, like the UAE in particular, clearer regulatory frameworks have started to emerge, which could encourage more cohesive cooperation and enable projects to get off the ground.

    Key EU countries also appear to remain committed to clean and green hydrogen imports as part of the green deal, while at least one power plant in Japan has completed a three-month trial of co-firing green ammonia with coal “with positive results”.  

    But until all these come together to ensure an unencumbered global supply chain, offtakers and project financing deals will likely remain elusive. 

    Related reads:


    READ THE FEBRUARY MEED BUSINESS REVIEW

    Trump unleashes tech opportunities; Doha achieves diplomatic prowess and economic resilience; GCC water developers eye uptick in award activity in 2025.

    Published on 1 February 2025 and distributed to senior decision-makers in the region and around the world, the February MEED Business Review includes:

    > WATER & WASTEWATER: Water projects require innovation
    https://image.digitalinsightresearch.in/uploads/NewsArticle/13370135/main.gif
    Jennifer Aguinaldo
  • Morocco explores salt caverns for hydrogen storage

    6 February 2025

     

    A feasibility study is under way for a project to explore underground salt cavern sites for green hydrogen storage in Morocco.

    According to Samir Rachidi, director-general at Iresen, the underground salt caverns are located near the capital Casablanca.

    “There is already an existing cavity used to store natural gas,” Rachidi told MEED.

    It is understood the same process or principle will be used to store green hydrogen in salt caverns.

    The potential storage capacity of the salt caverns for green hydrogen can only be determined once the feasibility study is completed.  

    Photo credit: Shutterstock

    Underground salt caverns offer an option for the bulk storage of very large amounts of gaseous hydrogen.

    According to Ireland-headquartered chemicals firm Linde, which operates the world’s first commercial hydrogen high-purity cavern in Texas, the gas has to be purified and compressed before it can be injected into a cavern.

    It added that hydrogen-filled cavities can act as a backup for a pipeline network.

    First green ammonia project

    Rachidi also said that Moroccan phosphate specialist OCP is in the advanced stages of studying a project to produce 1 million tonnes of green ammonia annually by 2027.

    The planned facility, which will cater to export markets, will include a 200,000 tonne-a-year (t/y) green hydrogen production plant and 4,000MW of renewable energy plants.

    It will also include an electrolyser plant with a capacity of 2,000MW.

    At least seven other green hydrogen or ammonia projects are under study or in the pre-front-end engineering and design stage in the North African state.

    In April 2023, a team led by China Energy International Construction Group signed a memorandum of cooperation to develop a green hydrogen project in a coastal area in southern Morocco.

    A year earlier, Serbia-headquartered renewables developer and investor CWP Global appointed US firm Bechtel to support the development of large-scale green hydrogen and ammonia facilities in Morocco and Mauritania.

    The Amun green hydrogen project, which CWP Global plans to develop in Morocco, is understood to require 15GW of renewable energy and has an estimated budget of between $18bn and $20bn.

    Morocco established a National Hydrogen Commission in 2019 and published a green hydrogen roadmap in 2021. 

    The roadmap entails the production of green hydrogen for local ammonia production and export between 2020 and 2030; the production and export of green hydrogen, green ammonia and synthetic fuels between 2030 and 2040; and the global trade of these products between 2040 and 2050.   

    Main photo: For illustrative purposes only (Adnoc)


    READ THE FEBRUARY MEED BUSINESS REVIEW

    Trump unleashes tech opportunities; Doha achieves diplomatic prowess and economic resilience; GCC water developers eye uptick in award activity in 2025.

    Published on 1 February 2025 and distributed to senior decision-makers in the region and around the world, the February MEED Business Review includes:

    > WATER & WASTEWATER: Water projects require innovation
    https://image.digitalinsightresearch.in/uploads/NewsArticle/13369568/main.jpg
    Jennifer Aguinaldo
  • Qatar maintains stable growth heading

    6 February 2025

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13369431/main.gif
    MEED Editorial