Facility E award jumpstarts Qatar’s utility projects
13 January 2025

A developer team led by Japan’s Sumitomo Corporation won the contract in November to develop and operate the Facility E independent water and power project (IWPP) in Qatar.
The project’s $2.8bn engineering, procurement and construction (EPC) contract drove the overall value of awarded contracts in the state’s utility sector to $3.9bn in 2024.
This makes 2024 the second-best year ever for Qatar’s utility sector, after 2015, when it let contracts worth over $7bn, including its last IWPP, Facility D in Umm Al-Houl, and other key utility projects.
Qatar General Electricity & Water Corporation (Kahramaa) awarded the Facility E IWPP contract, which has a total cost of $3.7bn, five years after it was initially tendered.
It marks a milestone following a slower pace in contract awards in recent years due to the completed delivery of infrastructure projects catering to the 2022 Fifa World and Covid-19 uncertainties.
Peak demand growth
Qatar’s total contracted electricity capacity, which stood at 10,573MW in 2023, increases to over 11,300MW when the capacity from the 800MW Al-Kharsaah solar plant is included.
This equates to a reserve margin of around 14% given the 2023 peak electricity demand of 9,805MW, as reported by the state utility.
A steady growth in peak electricity demand, up 4.3% in 2023 and 5.9% the year before, even when water demand remained stable at 425 million imperial gallons a day (MIGD), implies the state utility requires substantial additional capacity, which helped trigger the award of the Facility E IWPP contract last year.
The Facility E IWPP developer consortium includes Japanese utility developer Shikoku Electric, Seoul-headquartered Korea Overseas Infrastructure & Urban Development Corporation (Kind) and Korea Southern Power Company (Kospo).
The consortium and the strategic national investors, Qatar Electricity & Water Company (QEWC) and QatarEnergy (QE), will co-own the project company that is implementing the project.
The equity distribution between the project company shareholders is:
- Sumitomo Corporation: 17%
- Shikoku Electric: 11%
- Kospo: 6%,
- Kind: 6%
- QEWC: 55%
- QE: 5%
South Korea’s Samsung C&T is the project’s overall EPC contractor. Japan’s Mitsubishi Power is supplying advanced combined-cycle gas turbines for the power plant, and Spain’s Acciona is contracted to build the integrated plant’s $500m seawater reverse osmosis (SWRO) unit.
Unlike previous IWPPs, the Facility E IWPP tender attracted a single bid on both the initial and final rounds. This demonstrates increasing reticence among international utility developers when bidding for thermal assets as they grapple with their carbon neutrality targets by or before 2050.
The state utility and developer consortium had to contend with issues including the final capacity, costs and decarbonisation aspects of the project.
In the end, they agreed to develop a gas-fired power plant with a final electricity generation capacity of 2,415MW and a SWRO-based desalination plant with a capacity of 110MIGD.
The power and water purchase agreement for the Facility E IWPP is valid for 21 years, until 2049, a year shy of the developers’ target date for reaching carbon neutrality.
They also agreed to a levelised electricity cost of about QR190.71 a megawatt-hour, equivalent to $cents 5.239 a kilowatt-hour, and a levelised water cost of QR2,914 per 1,000 cubic metres, or about $cents 8.0 a cubic metre.
The tariffs exclude potential carbon capture, utilisation and storage (CCUS) costs.
Expanding capacity
Following the award of the Facility E IWPP contract, QEWC said it is cooperating with Kahramaa to explore a build, own and operate peak power unit project with a production capacity of 500MW.
A peak power unit typically refers to an open-cycle gas turbine plant, which can help increase the electricity grid’s flexibility to meet peak demand. The planned 500MW power plant will be located in Qatar’s Ras Abu Fontas, the same area where the Facility E IWPP will be built.
Qatar has been expanding its renewable energy capacity following the completion of its first utility-scale solar photovoltaic (PV) project in Al-Kharsaah in 2023. This is in line with its long-term objective to have a renewable energy installed capacity of 5,000MW by 2035.
Samsung C&T is constructing two solar PV plants in the Gulf state, costing $632m and with a combined capacity of 875MW.
One of the solar plants, located in Ras Laffan, has a capacity of 458MW. The other plant, located in Mesaieed, will have a capacity of 417MW.
The electricity generated by the two plants will be partly used for QatarEnergy’s liquefied natural gas production expansion.
In September 2024, Minister of State for Energy Affairs Saad Sherida Al-Kaabi also confirmed plans to build a 2,000MW solar power plant in Dukhan, 80 kilometres west of Doha.
The planned Dukhan solar PV plant will help to “lower carbon emissions in the framework of a realistic energy transition”. Once completed, it will increase Qatar’s solar PV capacity to close to 4,000MW by 2030.
Grid stability
Qatar’s efforts to expand its thermal and solar power generation capacity have led to the expansion of its transmission and distribution network.
Last year, Kahramaa awarded Elsewedy Cables Qatar two EPC contracts with a total combined value of QR2.2bn ($604m).
The first contract involves supplying low- and medium-voltage cables catering to a planned new underground extra-high-voltage/high-voltage cable network.
The second contract involves providing EPC services, including supplying and installing 132-kilovolt (kV) power cables for strategic projects across the state.
In October, Kahramaa tendered two contracts to upgrade segments of its electricity grid. The first contract calls for upgrading Ras Laffan C’s existing 220kV and 400kV substations and adding 220kV gas-insulated switchgear bays and an 800-megavolt amps transformer.
Kahramaa also invited firms to submit their proposals for a contract to supply and install power transmission and distribution equipment, including providing and connecting substation main earth and equipment earthing, commissioning fitted substations and pre-commissioning protection testing for 11kV switchgear panels.
Future projects
As of January 2025, more than $4bn-worth of utility projects are under execution in Qatar, excluding the Facility IWPP, which has yet to reach financial close.
The largest scheme under execution is the $720m Wakra and Wukair independent sewage treatment plant project. It will have a capacity of 150,000 cubic metres a day (cm/d), which can be extended to 600,000 cm/d at a later stage. The project reached financial close last year.
An estimated $4bn of power and $5.8bn of water infrastructure contracts are planned and unawarded in Qatar at the beginning of 2025.
QatarEnergy’s 2,000MW Dukhan solar PV, the Public Works Authority’s (Ashghal) New District of Doha and South of Wakrah marine pump station and outfall facilities, and the 500MW Ras Abu Fontas open-cycle power plant are some of the key projects expected to come onto the market over the next 12 to 18 months.
Exclusive from Meed
-
Dewa raises Empower stake in $1.41bn deal12 February 2026
-
Saudi cabinet approves Qatar high-speed rail link12 February 2026
-
Bidders line up for Saudi sewage treatment contract12 February 2026
-
Indian firm wins Dubai Latifa Bint Hamdan road project12 February 2026
-
SAR tenders Riyadh section of Saudi Landbridge12 February 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Dewa raises Empower stake in $1.41bn deal12 February 2026
Dubai Electricity & Water Authority (Dewa) has announced it has increased its stake in Emirates Central Cooling Systems Corporation (Empower) from 56% to 80%.
The transaction was completed through the purchase of 2.4 billion shares and the transfer of the entire ownership of Emirates Power Investment (EPI), which is wholly owned by Dubai Holding.
The total value of the deal is AED5.184bn ($1.41bn).
Empower currently holds over 80% of Dubai’s district cooling market and operates 88 district cooling plants across the emirate.
According to MEED Projects, the UAE’s district cooling sector currently has nine projects worth $1.29bn in the pre-execution phase.
Empower has ownership in four of these projects, which have a combined value of $472m.
This includes a $200 million district cooling plant at Dubai Science Park, with a total capacity of 47,000 refrigeration tonnes serving 80 buildings.
Empower signed a contract to design the plant last August, with construction scheduled to begin by the end of the first quarter of 2026.
The utility is also building a district cooling plant at Dubai Internet City.
UAE-based TMF Euro Foundations was recently appointed as the enabling and piling subcontractor for the project.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15635949/main.jpg -
Saudi cabinet approves Qatar high-speed rail link12 February 2026
Saudi Arabia has approved the establishment of a proposed high-speed rail line connecting Riyadh and Doha.
The approval was granted during a cabinet session chaired by King Salman Bin Abdulaziz Al-Saud in Riyadh on 10 February.
The high-speed railway line will cover 785 kilometres (km) and will pass through Hofuf and Dammam, while also linking King Salman International airport and Hamad International airport.
Saudi Arabia and Qatar signed an agreement in December last year to build a high-speed rail line.
The agreement was inked by Saudi Arabia’s Transport & Logistics Services Minister, Saleh Al-Jasser, and Qatar’s Transport Minister, Sheikh Mohammed Bin Abdulla Bin Mohammed Al-Thani.
Trains will reach speeds exceeding 300 kilometres an hour, reducing the travel time between the two capitals to about two hours.
The project is slated for completion in six years. It is expected to serve over 10 million passengers annually and create more than 30,000 direct and indirect jobs.
Riyadh and Doha relaunched the proposed rail link between the two countries in 2022, after agreeing to set a date to begin studying the connection.
In July of that year, France’s Systra was selected to conduct a feasibility study on the proposed scheme, as MEED reported.
A rail link connecting Saudi Arabia and Qatar was planned before the diplomatic dispute that froze relations between Riyadh and Doha from 2017 until the Al-Ula Declaration was signed in January 2021.
In 2016, Qatar Railways Company (Qatar Rail) planned to tender a design-and-build contract for the construction of regional railways in Qatar, including a link to the Saudi border.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15635582/main.jpg -
Bidders line up for Saudi sewage treatment contract12 February 2026

Six bidders are competing in the next phase of Saudi Arabia’s long-term operations and maintenance (LTOM) sewage treatment programme, as National Water Company (NWC) moves closer to awarding a contract.
The contract covers the North Western A Cluster Sewage Treatment Plants Package 11 (LTOM11) and has an estimated value of about $211m.
The project involves the construction and upgrade of two sewage treatment plants with a combined capacity of about 440,000 cubic metres a day (cm/d).
As MEED understands, the companies that have submitted proposals include:
- Alkhorayef Water & Power Technologies (Saudi Arabia)
- Civil Works Company (Saudi Arabia)
- United Water (China)
- Kuzu Group (Turkey)
- VA Tech Wabag (India)
- Aguas de Valencia (Spain)
LTOM11, also known as the North Western A Cluster, forms part of the second phase of NWC’s rehabilitation of sewage treatment plants programme.
The scheme is being procured on an engineering, procurement and construction (EPC) basis with a long-term operations component.
The scope also includes a pumping station, surplus discharge lines, SCADA installation and associated infrastructure.
The main contract was tendered last year, with an award initially expected by the end of 2025.
It is now understood that NWC is preparing to offer the main contract in this quarter.
LTOM programme
LTOM11 follows a series of earlier awards under the programme.
In January, a consortium of United Water (China), Prosus Energy (UAE) and Armada Holding (Saudi Arabia) won the main contract for the Northern Cluster Sewage Treatment Plants Package 10 (LTOM10).
This has an estimated value of about SR203m ($54.1m).
NWC previously awarded $2.7bn-worth of contracts for the first phase of its LTOM programme. This comprises nine packages covering the treatment of 4.6 million cm/d of sewage water for the next 15 years.
As MEED reported, local contracting firm Alkhorayef Water & Power Technologies won three contracts with a combined capacity of 2.04 million cm/d, nearly half of the awarded total. These three contracts are worth more than SR5.53bn ($1.47bn).
A consortium of France’s Suez and the local Al-Awael Modern Contracting Group, with its affiliate Civil Works Company (CWC), won two packages worth a combined SR1.84bn.
A consortium comprising France’s Veolia and Awael-CWC won a single package worth SR1.26bn, and local utility developer Miahona won one package worth SR392m.
In 2024, a joint venture of CWC and Al-Awael Modern Contracting was awarded a $211m contract for LTOM9.
As part of the second phase, the main contract bids for LTOM12 (North Western B Cluster) have also been submitted.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15635292/main.jpg -
Indian firm wins Dubai Latifa Bint Hamdan road project12 February 2026
Indian contractor Larsen & Toubro (L&T) has won a contract to construct the first phase of the Latifa Bint Hamdan Street development project in Dubai.
The contract value is between $110m and $275m, according to L&T’s contract classification.
This project covers 12.2 kilometres of road network from its intersection with Al-Khail Road to Emirates Road.
The project also includes 8.1km of bridges and will add capacity for about 16,000 vehicles an hour in both directions.
The scope also involves widening the two-lane dual carriageway to four lanes in each direction.
The project is scheduled for completion within 36 months.
The contract was awarded by Dubai’s Roads & Transport Authority (RTA).
The project is part of the RTA’s estimated AED16bn ($4.3bn) 2024-27 Main Roads Development Plan, which includes 22 projects across Dubai’s road network, as announced in November 2024.
The development plan includes the construction of new roads and bridges to alleviate traffic congestion at several key locations across Dubai.
Planning for growth
The Dubai 2040 Urban Master Plan was launched in March 2021. Its launch referenced studies indicating that the emirate’s population will reach 5.8 million by 2040, up from 3.3 million in 2020. The daytime population is set to increase from 4.5 million in 2020 to 7.8 million in 2040.
In December 2022, Sheikh Mohammed Bin Rashid Al-Maktoum, Vice President and Prime Minister of the UAE and Ruler of Dubai, approved the 20-Minute City Policy as part of the second phase of the Dubai 2040 Urban Master Plan.
In addition to the road projects, the RTA’s Dubai Metro Blue Line extension also forms part of Dubai’s plans to improve residents’ quality of life by cutting journey times, as outlined in the policy.
The policy aims to ensure that residents can meet 80% of their daily needs within a 20-minute walk or bike ride. This goal will be achieved by developing integrated service centres with the necessary facilities and by increasing population density around mass transit stations.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15635237/main.gif -
SAR tenders Riyadh section of Saudi Landbridge12 February 2026

Saudi Arabia Railways (SAR) has tendered a design-and-build contract for the construction of a new railway line, the Riyadh Rail Link, which will run from north to south Riyadh.
The tender was issued on 29 January, with a bid submission deadline of 29 March.
The scope of work includes constructing a 35-kilometre-long double-track railway line connecting SAR’s North-South Railway to the Eastern Railway network.
The contract also covers the procurement, construction and installation of associated infrastructure such as viaducts, civil works, utility installations, signalling systems and other related works.
The project is expected to form a key component of the Saudi Landbridge railway.
Last month, SAR said it would deliver the Saudi Landbridge project through a “new mechanism” by 2034, after failing to reach an agreement with a Chinese consortium for the construction of the project, as MEED reported.
In an interview with local media, SAR CEO Bashar Bin Khalid Al-Malik said the consortium failed to meet local content requirements and that the project will now be delivered in several phases under a different procurement model.
The project has been under negotiation between Saudi Arabia and China-backed investors keen to develop it through a public-private partnership.
Al-Malik said that the project cost is about SR100bn ($26.6bn).
It comprises more than 1,500 kilometres (km) of new track. The core component is a 900km new railway between Riyadh and Jeddah, which will provide direct freight access to the capital from King Abdullah Port on the Red Sea.
Other key sections include upgrading the existing Riyadh-Dammam line, a bypass around the capital called the Riyadh Link, and a link between King Abdullah Port and Yanbu.
The Saudi Landbridge is one of the kingdom’s most anticipated project programmes. Plans to develop it were first announced in 2004, but put on hold in 2010 before being revived a year later. Key stumbling blocks were rights-of-way issues, route alignment and its high cost.
In April last year, MEED exclusively reported that SAR had issued a tender for the lead design consultancy services contract on the Saudi Landbridge railway network.
MEED understands that the scope covered the concept design and options for the preliminary and issued-for-construction design stages on the network.
MEED reported that the launch of a design tender directly by SAR suggested that Riyadh was looking at other options to develop it alongside the Chinese proposal.
In December 2023, MEED reported that a team of US-based Hill International, Italy’s Italferr and Spain’s Sener had been awarded the contract to provide project management services for the programme.
If it proceeds, the Saudi Landbridge will be one of the largest railway projects ever undertaken in the Middle East and one of the biggest globally. Based on typical design timeframes, tenders for construction are likely to be ready by mid-2026, although the question of how it will be financed will need to be answered before it can proceed to the next step.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15635220/main.jpg

.gif)