Facility E award jumpstarts Qatar’s utility projects
13 January 2025

A developer team led by Japan’s Sumitomo Corporation won the contract in November to develop and operate the Facility E independent water and power project (IWPP) in Qatar.
The project’s $2.8bn engineering, procurement and construction (EPC) contract drove the overall value of awarded contracts in the state’s utility sector to $3.9bn in 2024.
This makes 2024 the second-best year ever for Qatar’s utility sector, after 2015, when it let contracts worth over $7bn, including its last IWPP, Facility D in Umm Al-Houl, and other key utility projects.
Qatar General Electricity & Water Corporation (Kahramaa) awarded the Facility E IWPP contract, which has a total cost of $3.7bn, five years after it was initially tendered.
It marks a milestone following a slower pace in contract awards in recent years due to the completed delivery of infrastructure projects catering to the 2022 Fifa World and Covid-19 uncertainties.
Peak demand growth
Qatar’s total contracted electricity capacity, which stood at 10,573MW in 2023, increases to over 11,300MW when the capacity from the 800MW Al-Kharsaah solar plant is included.
This equates to a reserve margin of around 14% given the 2023 peak electricity demand of 9,805MW, as reported by the state utility.
A steady growth in peak electricity demand, up 4.3% in 2023 and 5.9% the year before, even when water demand remained stable at 425 million imperial gallons a day (MIGD), implies the state utility requires substantial additional capacity, which helped trigger the award of the Facility E IWPP contract last year.
The Facility E IWPP developer consortium includes Japanese utility developer Shikoku Electric, Seoul-headquartered Korea Overseas Infrastructure & Urban Development Corporation (Kind) and Korea Southern Power Company (Kospo).
The consortium and the strategic national investors, Qatar Electricity & Water Company (QEWC) and QatarEnergy (QE), will co-own the project company that is implementing the project.
The equity distribution between the project company shareholders is:
- Sumitomo Corporation: 17%
- Shikoku Electric: 11%
- Kospo: 6%,
- Kind: 6%
- QEWC: 55%
- QE: 5%
South Korea’s Samsung C&T is the project’s overall EPC contractor. Japan’s Mitsubishi Power is supplying advanced combined-cycle gas turbines for the power plant, and Spain’s Acciona is contracted to build the integrated plant’s $500m seawater reverse osmosis (SWRO) unit.
Unlike previous IWPPs, the Facility E IWPP tender attracted a single bid on both the initial and final rounds. This demonstrates increasing reticence among international utility developers when bidding for thermal assets as they grapple with their carbon neutrality targets by or before 2050.
The state utility and developer consortium had to contend with issues including the final capacity, costs and decarbonisation aspects of the project.
In the end, they agreed to develop a gas-fired power plant with a final electricity generation capacity of 2,415MW and a SWRO-based desalination plant with a capacity of 110MIGD.
The power and water purchase agreement for the Facility E IWPP is valid for 21 years, until 2049, a year shy of the developers’ target date for reaching carbon neutrality.
They also agreed to a levelised electricity cost of about QR190.71 a megawatt-hour, equivalent to $cents 5.239 a kilowatt-hour, and a levelised water cost of QR2,914 per 1,000 cubic metres, or about $cents 8.0 a cubic metre.
The tariffs exclude potential carbon capture, utilisation and storage (CCUS) costs.
Expanding capacity
Following the award of the Facility E IWPP contract, QEWC said it is cooperating with Kahramaa to explore a build, own and operate peak power unit project with a production capacity of 500MW.
A peak power unit typically refers to an open-cycle gas turbine plant, which can help increase the electricity grid’s flexibility to meet peak demand. The planned 500MW power plant will be located in Qatar’s Ras Abu Fontas, the same area where the Facility E IWPP will be built.
Qatar has been expanding its renewable energy capacity following the completion of its first utility-scale solar photovoltaic (PV) project in Al-Kharsaah in 2023. This is in line with its long-term objective to have a renewable energy installed capacity of 5,000MW by 2035.
Samsung C&T is constructing two solar PV plants in the Gulf state, costing $632m and with a combined capacity of 875MW.
One of the solar plants, located in Ras Laffan, has a capacity of 458MW. The other plant, located in Mesaieed, will have a capacity of 417MW.
The electricity generated by the two plants will be partly used for QatarEnergy’s liquefied natural gas production expansion.
In September 2024, Minister of State for Energy Affairs Saad Sherida Al-Kaabi also confirmed plans to build a 2,000MW solar power plant in Dukhan, 80 kilometres west of Doha.
The planned Dukhan solar PV plant will help to “lower carbon emissions in the framework of a realistic energy transition”. Once completed, it will increase Qatar’s solar PV capacity to close to 4,000MW by 2030.
Grid stability
Qatar’s efforts to expand its thermal and solar power generation capacity have led to the expansion of its transmission and distribution network.
Last year, Kahramaa awarded Elsewedy Cables Qatar two EPC contracts with a total combined value of QR2.2bn ($604m).
The first contract involves supplying low- and medium-voltage cables catering to a planned new underground extra-high-voltage/high-voltage cable network.
The second contract involves providing EPC services, including supplying and installing 132-kilovolt (kV) power cables for strategic projects across the state.
In October, Kahramaa tendered two contracts to upgrade segments of its electricity grid. The first contract calls for upgrading Ras Laffan C’s existing 220kV and 400kV substations and adding 220kV gas-insulated switchgear bays and an 800-megavolt amps transformer.
Kahramaa also invited firms to submit their proposals for a contract to supply and install power transmission and distribution equipment, including providing and connecting substation main earth and equipment earthing, commissioning fitted substations and pre-commissioning protection testing for 11kV switchgear panels.
Future projects
As of January 2025, more than $4bn-worth of utility projects are under execution in Qatar, excluding the Facility IWPP, which has yet to reach financial close.
The largest scheme under execution is the $720m Wakra and Wukair independent sewage treatment plant project. It will have a capacity of 150,000 cubic metres a day (cm/d), which can be extended to 600,000 cm/d at a later stage. The project reached financial close last year.
An estimated $4bn of power and $5.8bn of water infrastructure contracts are planned and unawarded in Qatar at the beginning of 2025.
QatarEnergy’s 2,000MW Dukhan solar PV, the Public Works Authority’s (Ashghal) New District of Doha and South of Wakrah marine pump station and outfall facilities, and the 500MW Ras Abu Fontas open-cycle power plant are some of the key projects expected to come onto the market over the next 12 to 18 months.
Exclusive from Meed
-
Al-Maktoum airport is key to Dubai’s aviation hub status27 November 2026
-
Emaar tenders Dubai Creek Harbour mall27 November 2026
-
Contractor wins Arabian Beauty Horses Village in Qatar27 November 2026
-
King Salman airport sets new infrastructure bid deadline27 November 2026
-
PIF secures inaugural A+ rating from S&P26 November 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Al-Maktoum airport is key to Dubai’s aviation hub status27 November 2026
Commentary
Colin Foreman
EditorDubai’s position as a global aviation hub is central to its economy, and the expansion of Al-Maktoum International airport is critical to maintaining that role.
On 26 November, Dubai awarded AED56.5bn ($15bn) of contracts for the airport expansion, taking the total value of contracts awarded to more than AED80bn ($21.8bn). A workforce of 14,000 is working on the project, which will provide capacity for more than 260 million passengers a year when complete.
The economic stakes are high. A study published by Emirates Group and Dubai Airports in October 2024 found that aviation accounted for 27% of Dubai’s GDP in 2023. The sector contributed AED137bn ($37.3bn) in gross value added and supported 631,000 jobs – about one in five jobs in the emirate. The study forecast that aviation’s share of GDP would rise to 32% by 2030, contributing AED196bn in gross value added and supporting 816,000 jobs.
This year has demonstrated both the vulnerability and resilience of Dubai’s aviation model. Regional conflict has disrupted commercial air traffic across the Gulf since 28 February. Emirates Group’s profit before tax fell 66% year on year to AED4.1bn in the six months to 30 September, while Emirates carried 21.8 million passengers, down 22% on the prior-year period.
However, the network recovered quickly. By 30 September, Emirates was operating 91% of its pre-disruption network, serving 150 airports in 78 countries and territories. Emirates SkyCargo revenue rose 52%, the fleet increased to 289 aircraft, and the airline broke ground in May on a $5.1bn maintenance facility at Al-Maktoum International airport.
Maintaining that connectivity will require additional capacity. If aviation accounts for almost one-third of Dubai’s economy by 2030, as Emirates Group and Dubai Airports forecast, Al-Maktoum International airport will be central to the emirate’s ability to retain its position in global air travel.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21894329/main.jfif -
Emaar tenders Dubai Creek Harbour mall27 November 2026

Register for MEED’s 14-day trial access
Dubai developer Emaar Properties has invited contractors to submit bids by 9 December for the main construction package of the Dubai Creek Harbour mall, known as Dubai Square.
The development covers a total retail, hospitality and commercial area of 2.6 million square metres, and is scheduled to open within three years.
Emaar unveiled Dubai Square in December 2025 as the anchor of its AED180bn ($49bn) Dubai Creek Harbour development.
The scheme has undergone several redesigns. MEED first reported on Emaar’s plans for a major retail centre at Dubai Creek Harbour in 2016. At the time, the project was envisioned to surpass Dubai Mall as the world’s largest retail destination, though its scale and layout have since evolved.
The mall will connect directly to the planned Dubai Creek Tower at the centre of the development.
UK-headquartered Brewer Smith Brewer Group is the project’s lead consultant, executive architect, architect of record and structural engineer. It is also the construction supervision consultant.
Dubai-based contractor Dutco Construction began mobilising last year for early site works.
In March last year, MEED reported that Emaar was preparing to relaunch development of both the tower and the mall. The developer had earmarked roughly AED14bn ($3.81bn) for the two assets as part of a wider AED65bn ($18bn), five-year capital expenditure programme.
Progress on the tower has been slower. First launched in 2015, it was promoted as the world’s tallest structure, designed to exceed the 828-metre Burj Khalifa. The original design was led by Spanish architect Santiago Calatrava and UK-based RMJM. The project stalled after concrete pile-cap works were completed in 2018.
In 2023, Emaar founder Mohamed Alabbar confirmed design works were continuing following an international design competition. In January 2026, Alabbar stated that a tender for the redesigned tower would be issued within three months. He later said the tender would be deferred until regional geopolitical tensions ease.
READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFGulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.
Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:
> AGENDA: GCC projects market holds its nerve> MARKET FOCUS: UAE economy shows resilience> INDUSTRY REPORT: Project financiers hold the line> STADIUMS: Stadium spending set to jump 39% in 2027> CONFLICT: Hormuz closure wipes out growth in 2026> INTERVIEW: WSP regional president Dean McGrail> INTERVIEW: UAE Ministry of Energy & InfrastructureTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/21892263/main.jpg -
Contractor wins Arabian Beauty Horses Village in Qatar27 November 2026

Qatar’s Culture Village Foundation (Katara) has awarded Qatar Trading & Contracting Group a QR574m ($158m) contract to build the Arabian Beauty Horses Village in Al-Uqdah Zone 74, in the Al-Khor area.
The project will include supporting infrastructure and public facilities designed for Arabian show horses and equestrian operations in the Al-Uqdah district.
Zone 74 is already an important centre for Qatar’s equestrian sector, anchored by the Al-Uqdah Equestrian Complex. The Qatar Racing & Equestrian Club began operating the complex in 2020 in coordination with Qatar’s Ministry of Culture and Sports.
The Arabian Beauty Horses Village is part of a broader, multistage state strategy to develop Al-Uqdah, on the outskirts of Al-Khor, as Qatar’s second major equestrian hub, alongside Al-Rayyan and Al-Shaqab in Doha.
According to UK analytics firm GlobalData, Qatar’s commercial construction sector is expected to grow at an average annual rate of 4.5% between 2025 and 2028, supported by investment in hotels, logistics facilities and data centres.
READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFGulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.
Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:
> AGENDA: GCC projects market holds its nerve> MARKET FOCUS: UAE economy shows resilience> INDUSTRY REPORT: Project financiers hold the line> STADIUMS: Stadium spending set to jump 39% in 2027> CONFLICT: Hormuz closure wipes out growth in 2026> INTERVIEW: WSP regional president Dean McGrail> INTERVIEW: Ministry of Energy & InfrastructureTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/21890026/main.jpg -
King Salman airport sets new infrastructure bid deadline27 November 2026

Saudi Arabia’s King Salman International Airport Development Company (KSIADC) has set a 10 January deadline for bids for the Zone C1+C2 roads, bridges and utility networks package for King Salman International airport (KSIA) in Riyadh.
The tender was issued on 26 October, with an initial bid-submission deadline of 6 December.
The request for proposals covers the procurement, construction, testing and commissioning of civil infrastructure supporting Terminal 6, alongside the existing Terminals 1-5.
The scope includes upgrades to Airport Road 539, which runs west of Terminals 1-5, and part of Mohamed bin Faraj Road 5333, west of Junction 6.
It also includes new roads, ramps, service roads and signalised at-grade junctions. An additional access road will connect the Terminal 6 site offices to Road 5333.
Structures will include the Junction 6 and Terminal 6 bridges, retaining walls and reinforced-soil structures.
The contractor will also construct the central ground services equipment (GSE) bridge. Before construction begins, the contractor must validate the design, complete any outstanding elements – including mechanically stabilised earth walls, approach slabs, drainage and lighting – and secure the required authority approvals.
Dry utilities will comprise high- and extra-high-voltage containment, a 13.8kV medium-voltage network with package substations, low-voltage distribution and street lighting, and security-surveillance systems.
Wet utilities will include potable water, fire water, irrigation water, treated sewage effluent, district cooling and wastewater networks. Wastewater pipes will range from 200mm u-PVC gravity lines to 1,700mm glass-reinforced plastic mains.
The stormwater network will include channels, culverts, ponds and pipes ranging from 400mm to 1,400mm in diameter. Crossings will be constructed using open-cut excavation, horizontal directional drilling or microtunneling.
Utilities serving the operational terminals will be diverted on a design-and-build basis. Enabling works will include earthworks and the relocation of the security fence and trees. The contractor will also demolish a temporary car park, existing bridges and a sewage pumping station.
Optional works comprise two design-and-build elements that will proceed only at the client’s instruction.
The first is the south GSE bridge. The second is an approximately 1,400-metre, multi-lane access road to the Terminal 6 Transportation Hub, including bridges, underpasses, ramps and tunnels, as well as provisions for future Wadi Loop utilities and structures.
READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFGulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.
Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:
> AGENDA: GCC projects market holds its nerve> MARKET FOCUS: UAE economy shows resilience> INDUSTRY REPORT: Project financiers hold the line> STADIUMS: Stadium spending set to jump 39% in 2027> CONFLICT: Hormuz closure wipes out growth in 2026> INTERVIEW: WSP regional president Dean McGrail> INTERVIEW: Ministry of Energy & InfrastructureTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/21887157/main3955.png -
PIF secures inaugural A+ rating from S&P26 November 2026
Saudi Arabia’s Public Investment Fund (PIF) has received an inaugural A+ long-term foreign and local currency issuer credit rating from S&P Global Ratings, with a stable outlook.
The fund’s existing A-1 short-term rating from S&P is unchanged. PIF said its ratings are in line with those of Saudi Arabia.
PIF said S&P’s assessment cited its diversified funding profile, moderate leverage and its focus on value realisation under its 2026-30 strategy. The agency also pointed to the fund’s role in driving the kingdom’s economic transformation.
“The inaugural A+ long-term rating from S&P marks an important milestone in the continued development of PIF’s credit profile and our long-term funding plan,” said Ziyad Alfawzan, head of capital finance strategy at PIF.
The new rating makes PIF one of a small number of sovereign wealth funds with long-term credit ratings from all three leading agencies.
Moody’s Ratings confirmed PIF’s Aa3 long-term issuer rating and aa3 baseline credit assessment in September after a periodic review, with a stable outlook. In October, Fitch Ratings affirmed the fund’s long-term foreign and local currency issuer default ratings at A+, also with a stable outlook.
The Moody’s rating is one notch higher than the A+ grades from S&P and Fitch.
Debt is an increasingly important source of funding for PIF as it pays for domestic investment programmes and gigaprojects.
The fund raised $2bn in January from a 10-year sukuk, its first debt sale of 2026. In May, it raised $7bn from a three-tranche bond, its first hard-currency public issuance since the Iran conflict disrupted regional capital markets.
A full set of long-term ratings is likely to widen PIF’s investor base for future bond and sukuk issuance. The fund also borrows through loans and other debt instruments as part of its funding mix.
PIF is entering what it calls the value realisation phase of its strategy, covering 2026 to 2030. Over this period, it aims to deliver sustainable financial returns while continuing to drive the diversification of the Saudi economy.
MEED’s latest report on Saudi Arabia includes:
> COMMENT: Saudi projects hold steady
> GOVERNMENT: Riyadh looks to reset its regional defence outlook
> ECONOMY: Conflict bolsters case for Saudi economic diversification
> BANKING: Saudi lenders readjust to lower lending and deposit climate
> UPSTREAM: Aramco upstream spending gathers pace
> DOWNSTREAM: Sabic steps up Saudi petchems investment
> POWER: Saudi Arabia’s power award activity slows
> WATER: Saudi water sector hits sharp slowdown
> CONSTRUCTION: Saudi construction defies the headwinds
> TRANSPORT: Saudi infrastructure pushes forward amid conflict
> DATABANK: Saudi data indicates project spending shiftTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/21868102/main.gif