Ewec to procure 1GW of solar capacity annually until 2036

8 March 2023

Abu Dhabi-based Emirates Water & Electricity Company (Ewec) aims to install a total of 16GW of solar photovoltaic (PV) capacity by 2036, according to its executive director for strategy and planning, Bruce Smith.

“This means we plan to procure 1GW of capacity every year until 2036,” the executive said.

Over the intervening period ending in 2030, Ewec envisages having an additional 5GW of solar capacity to reach a total solar installed capacity of 7.3GW by 2030.

The planned capacity aligns with the state utility’s carbon dioxide emissions reduction plan during this period, which includes potentially expanding its nuclear power capacity and deploying carbon capture technologies for its existing thermal power generation assets.

Smith said Ewec expects its first battery energy storage system to come online in the late 2020s to enable optimum use of renewable energy captured during daytime at times when the solar PV fleets do not produce energy.

Ewec aims to reduce its total carbon dioxide emissions from 43 million tonnes a year (t/y) in 2019 to 22 million t/y by 2035.

Ewec expects to achieve a substantial emissions reduction despite a projected 30 per cent increase in peak demand between 2022 and 2029 and 50 per cent between 2022 and 2050.

Ewec announced the company’s Statement of Future Capacity Requirements Summary Report covering 2023 to 2029  seven months after it published the summary of the previous report in August.

The annual document outlines the needed additional power and water production capacity in the emirate over a seven-year window based on expected macroeconomic developments and the retirement of existing fleets.

The previous capacity requirements report envisaged a 20 per cent gross peak power demand increase from 16.8GW in 2022 to 19.9GW in 2028.

Ewec said at the time: “The otherwise consistent increase in peak and total energy demand from 2022 is impacted by a reduction in exports to Sharjah Electricity & Water Authority (Sewa) over 2022-2023 due to the commissioning of their new power plant and the addition of new Adnoc Offshore demand from 2026.”

Ewec’s project’s activities in recent months have aligned with these projections.

The bidding process is under way for the 1.5GW Al-Ajban solar PV project, with Ewec expecting to receive proposals by June.

It has recently awarded the contract to develop the 120MIGD Mirfa 2 seawater reverse osmosis independent water plant (IWP) projects to France’s Engie and is expected to award the contract to develop the 70MIGD Shuweihat 4 IWP to South Korean/Spanish company GS Inima imminently.

MEED has reported that the procurement process may start before year-end for the next solar PV project in Al-Ain and a new gas-fired plant in Sweihan.

Ewec has recently sought transaction advisers for its first battery energy storage system (bess) project, which consists of two 150MW facilities.

MEED also understands that last year’s statement outlined the possibility of procuring up to 16GW of thermal power capacity and around 14GW of solar PV capacity by 2031 to accommodate expected demand until 2036.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10658756/main.jpg
Jennifer Aguinaldo
Related Articles
  • Etihad Rail to begin passenger rail operations from 30 June

    26 June 2026

    Abu Dhabi’s Etihad Rail is set to begin passenger rail operations on 30 June 2026, launching an introductory operational phase on the Abu Dhabi-Fujairah route. Tickets are already on sale through the operator’s digital platforms.

    The passenger roll-out marks a major milestone for Etihad Rail, the developer and operator of the UAE’s National Rail Network. Established in 2009, the company was tasked with delivering a roughly 900-kilometre railway linking key cities, ports and industrial hubs from Ghuwaifat to Fujairah on the eastern coast.

    The launch comes less than five years after the UAE announced its ambition to create a national passenger railway under the country’s “Projects of the 50” programme, which aims to support economic diversification and sustainable development.

    According to Etihad Rail, passenger services will be introduced in planned phases through 2026 and 2027:

    • 23 June 2026: Passenger tickets went on sale via the Etihad Rail app and a dedicated booking website (as well as the contact centre for certain fares)
    • 30 June 2026: Introductory operational phase begins with services between Abu Dhabi and Fujairah only
    • 30 September 2026: Passenger rail services formally commence and expand to include Abu Dhabi, Dubai, Al-Dhaid and Fujairah
    • 30 December 2026: Services extend to Al-Dhafra stations
    • 30 March 2027: Services expand further to include Sharjah

    Customers can book tickets up to four weeks before travel. Tickets for new destinations will be released in line with the phased roll-out.

    Once fully operational, Etihad Rail’s passenger service will connect 11 cities and regions across the UAE, supported by a station network that links key urban and economic centres. The station list includes:

    • Abu Dhabi – Mohamed Bin Zayed City Station
    • Dubai – Al-Yalayis Station
    • Sharjah – University City Station
    • Fujairah Station
    • Al-Dhaid Station
    • Al-Dhannah Station
    • Madinat Zayed Station
    • Liwa Station
    • Al-Mirfa Station
    • Al-Sila Station
    • Al-Faya Station

    For the initial Abu Dhabi–Fujairah service starting 30 June, Etihad Rail said fares will start from AED55 for Comfort class and AED120 for Premium class. The operator added that future fares and routes will be announced separately.

    The operator will offer two travel classes:

    • Comfort: guaranteed seating, Wi‑Fi, power at every seat and luggage space
    • Premium: wider reclining seats, extra legroom and complimentary refreshments

    Within each class, passengers can choose from three fare types based on flexibility:

    • Saver: lowest fare for fixed plans; available only via the app, booking website and contact centre
    • Value: includes complimentary seat selection and ticket changes
    • Flex: includes seat selection, ticket changes and refunds

    Etihad Rail said introductory fares are designed to encourage early uptake and will be available for a limited period, with pricing expected to transition “towards a more advanced fare structure and, ultimately, a broader fare framework” as the service matures.

    Etihad Rail’s passenger trains will have a maximum speed of 200km/h and, once fully operational, each train will carry up to 400 passengers, with an expected annual ridership of about 10 million.

    The journey times are as follows:

    • Abu Dhabi to Fujairah: 105 minutes
    • Abu Dhabi to Dubai: 57 minutes
    • Dubai to Fujairah: 69 minutes

    Train features include generous legroom, Wi‑Fi, power at every seat, foldable tray tables, overhead storage, space for larger baggage and accessibility provisions. Station features include clear signage, comfortable waiting areas, staff assistance, accessibility features and parking.

    Etihad Rail said the onboard experience is designed around “comfort and time well spent”, enabling passengers to work, relax or switch off in a “calm and spacious environment” with guaranteed seating, Wi‑Fi and charging points.

    Etihad Rail’s network currently supports freight operations across 11 terminals and four major ports, underpinning supply chain efficiency, emissions reduction and national connectivity.

    The company also pointed to the broader economic value of the UAE Railway Programme, stating that it creates opportunities worth AED200bn, while passenger rail is expected to generate around AED91bn in economic and social benefits over the next 50 years, driven by faster, safer and more efficient travel.

    Etihad Rail also differentiated the new passenger service from the UAE’s future high-speed rail plans, saying passenger rail is intended to connect more communities across the country with an affordable and comfortable service, while high-speed rail is being designed for “very fast journeys between central points of our major cities”, describing the two as “different products and services designed for different types of journeys”.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17448681/main.jpeg
    Yasir Iqbal
  • Firms prepare Hudayriat East PPP tunnels advisory bids

    25 June 2026

     

    Abu Dhabi’s Modon Infrastructure, formerly Gridora, has tendered a contract for technical advisory services for the construction of two underwater tunnels connecting the eastern side of Hudayriat Island with mainland Abu Dhabi.

    Consultants have until 26 June to submit their proposals.

    The project includes the construction of a 4.8-kilometre (km) highway, with four lanes in each direction, connecting Hudayriat Island to Mussafah 8th Street.

    The project will be delivered on a public-private partnership (PPP) basis in coordination with the Abu Dhabi Department of Municipalities and Transport and the Abu Dhabi Investment Office.

    The contract term is expected to be 25 years.

    The latest infrastructure development in Abu Dhabi follows Modon Infrastructure’s invitation in May for firms to register for the next phase of Abu Dhabi’s Mid Island Parkway Project (MIPP), which will also be developed on a PPP basis.

    Modon Infrastructure will act as the lead developer, holding the majority equity stake in the project company. It will award the engineering, procurement and construction contract, as well as the operations and maintenance services and advisory appointments.

    The second phase of the MIPP involves the construction of about 11km of highways, including a mix of three-, four- and five-lane sections. The highways will connect the Um-Yifeenah, Al-Jubail, Al-Sammaliyyah and Sas Al-Nakhl islands to Khalifa City and the E10 road.

    The scope also covers the construction of three interchanges: the E20, E10 and Dumbbell interchanges on Al-Sammaliyyah Island.

    The project includes several major structures, such as the E20 interchange, which will feature cast-in-place box-girder and void-slab bridges, and the E10 interchange with cast-in-place box-girder bridges. It also includes I-girder bridges between Raha Beach West and Sas Al-Nakhl Island, as well as a causeway at Sas Al-Nakhl Island.

    Further key elements include a cast-in-place balanced cantilever bridge between Sas Al-Nakhl Island and Al-Sammaliyyah Island; a tunnel between Al-Sammaliyyah Island and Bilrimaid Island; and a cut-and-cover (open) tunnel on Bilrimaid Island. The project will be completed with another tunnel connecting Bilrimaid Island to Um-Yifeenah Island.


    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17410214/main.jpg
    Yasir Iqbal
  • Algeria tenders upstream oil project contract

    25 June 2026

    Algeria’s state-owned national oil and gas company, Sonatrach, has tendered a contract for the development and rehabilitation of the central processing facility (CPF) at the Bir Berkine oil and gas field.

    The scope of the contract includes the study, supply, construction and commissioning of a project to rehabilitate the CPF facilities at the field, which is located in the Hassi Mesaoud region.

    Sonatrach says in the tender documents that the objective of the project is to ensure the continuity of production activities “under stable and secure operating conditions”.

    It also says the project aims to improve production yields and quality.

    The contract includes both initial and detailed studies as well as the supply of all equipment and materials.

    It also includes the execution of works, the assembly of all equipment and materials, and the commissioning of all relevant facilities.

    The tender has a two-stage submission process, with the first stage requiring technical bids to be submitted by 23 August.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17423013/main3916.jpg
    Wil Crisp
  • Red Sea Global tenders King Salman Bay construction work

    25 June 2026

     

    Saudi gigaproject developer Red Sea Global (RSG) has tendered a contract inviting firms to undertake marine infrastructure works at King Salman Bay on the Red Sea coast, north of Jeddah.

    The scope includes dredging and earthworks, as well as quay wall and edge protection works spanning about 11 kilometres.

    The bid submission deadline is 31 July.

    King Salman Bay is expected to be a waterfront development aimed at reshaping the city’s northern Red Sea frontage into a mixed-use destination, anchored by public-realm improvements and leisure-led development.

    The update follows RSG’s award of an estimated SR100m ($27m) contract to construct a solid waste management centre at its Red Sea Project. The scope includes four buildings: a material recycling facility, a transfer station, an administration building and a vehicle maintenance building.

    In October last year, MEED reported that RSG had secured a SR6.5bn ($1.7bn) credit facility to further develop Amaala, its luxury tourism destination on Saudi Arabia’s northwestern Red Sea coast.

    According to an official statement, “The funding is led by Riyad Bank as the sole underwriter, along with Saudi Investment Bank and Bank Al-Bilad as mandated lead arrangers.

    “The loan arrangement comprises a mix of conventional and Islamic financing and adheres to RSG’s Green Loan Framework, which was first established when it secured private funding from a consortium of four banks for the Red Sea destination in 2021,” the statement added.

    The announcement followed RSG’s opening of its first properties for sale at Amaala, including branded residential communities and a five-bedroom villa on a private island.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17430045/main.jpg
    Yasir Iqbal
  • MECC submits lowest bid on three Kuwaiti oil and gas contracts

    25 June 2026

     

    Kuwait-based Mechanical Engineering & Contracting Company (MECC) has submitted the lowest bid across three separate contracts tendered by the state-owned upstream operator Kuwait Oil Company (KOC).

    The total value of the low bids is $427m, and all of the contracts are focused on developing substations to power industrial lift pumps and remote header manifolds

    Five companies submitted bids for a contract to develop several substations to power industrial lift pumps and remote header manifolds in areas 6, 10 and 12 in southern and eastern Kuwait.

    The bidders were:

    • MECC: KD65,760,000 ($212m)
    • Heavy Engineering Industries & Shipbuilding Company: KD70,630,000 ($228m)
    • Amco Engineering & Construction: KD73,446,100 ($237m)
    • Combined Group Contracting Company: KD76,186,000 ($246m)
    • Nasser Mohammed Al-Badah & Partner General Trading & Contracting: KD79,332,417 ($256m)

    Six companies submitted bids for a contract to develop several substations to power industrial lift pumps and remote header manifolds in areas 8 and 13 in southern and eastern Kuwait.

    The bidders were:

    • MECC: KD30,760,000 ($99m)
    • Badr Al-Mulla & Brothers: KD32,662,040 ($106m)
    • Heavy Engineering Industries & Shipbuilding Company: KD34,139,000 ($110m)
    • Industrial Company for Electrical Projects: KD36,375,520 ($118m)
    • Nasser Mohammed Al-Badah & Partner General Trading & Contracting: KD37,278,526 ($120m)
    • Combined Group Contracting Company: KD37,790,000 ($122m)

    Eight companies submitted bids for a contract focused on developing several substations to power industrial lift pumps and remote header manifolds in areas 7, 9, and 11 in southern and eastern Kuwait.

    The bidders were:

    • MECC: KD35,760,000 ($116m)
    • Badr Al-Mulla & Brothers: KD39,447,165 ($127m)
    • Amco Engineering & Construction: KD39,736,800 ($128m)
    • Heavy Engineering Industries & Shipbuilding Company: KD40,105,000 ($130m)
    • Industrial Company for Electrical Projects: KD43,238,265 ($140m)
    • Engineering Company for Petroleum & Chemical Industries (Enppi): KD43,514,805 ($141m)
    • Combined Group Contracting Company: KD43,650,000 ($141m)
    • Nasser Mohammed Al-Badah & Partner General Trading & Contracting: KD43,706,826 ($141m)

    Kuwait’s oil and gas sector has been in crisis in recent months due to disruption from the regional conflict that started after the US and Israel attacked Iran on 28 February 2026.

    A preliminary peace agreement between the US and Iran, which was announced on 14 June, has increased optimism that disruption to the sector will decrease in the coming weeks.

    Under the terms of the agreement, both sides have stated that the free flow of vessels will be permitted through the Strait of Hormuz, through which nearly all of Kuwait’s crude oil is normally exported.


    READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDF

    GCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.

    Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17423009/main.jpg
    Wil Crisp