Ewec to procure 1GW of solar capacity annually until 2036
8 March 2023
Abu Dhabi-based Emirates Water & Electricity Company (Ewec) aims to install a total of 16GW of solar photovoltaic (PV) capacity by 2036, according to its executive director for strategy and planning, Bruce Smith.
“This means we plan to procure 1GW of capacity every year until 2036,” the executive said.
Over the intervening period ending in 2030, Ewec envisages having an additional 5GW of solar capacity to reach a total solar installed capacity of 7.3GW by 2030.
The planned capacity aligns with the state utility’s carbon dioxide emissions reduction plan during this period, which includes potentially expanding its nuclear power capacity and deploying carbon capture technologies for its existing thermal power generation assets.
Smith said Ewec expects its first battery energy storage system to come online in the late 2020s to enable optimum use of renewable energy captured during daytime at times when the solar PV fleets do not produce energy.
Ewec aims to reduce its total carbon dioxide emissions from 43 million tonnes a year (t/y) in 2019 to 22 million t/y by 2035.
Ewec expects to achieve a substantial emissions reduction despite a projected 30 per cent increase in peak demand between 2022 and 2029 and 50 per cent between 2022 and 2050.
Ewec announced the company’s Statement of Future Capacity Requirements Summary Report covering 2023 to 2029 seven months after it published the summary of the previous report in August.
The annual document outlines the needed additional power and water production capacity in the emirate over a seven-year window based on expected macroeconomic developments and the retirement of existing fleets.
The previous capacity requirements report envisaged a 20 per cent gross peak power demand increase from 16.8GW in 2022 to 19.9GW in 2028.
Ewec said at the time: “The otherwise consistent increase in peak and total energy demand from 2022 is impacted by a reduction in exports to Sharjah Electricity & Water Authority (Sewa) over 2022-2023 due to the commissioning of their new power plant and the addition of new Adnoc Offshore demand from 2026.”
Ewec’s project’s activities in recent months have aligned with these projections.
The bidding process is under way for the 1.5GW Al-Ajban solar PV project, with Ewec expecting to receive proposals by June.
It has recently awarded the contract to develop the 120MIGD Mirfa 2 seawater reverse osmosis independent water plant (IWP) projects to France’s Engie and is expected to award the contract to develop the 70MIGD Shuweihat 4 IWP to South Korean/Spanish company GS Inima imminently.
MEED has reported that the procurement process may start before year-end for the next solar PV project in Al-Ain and a new gas-fired plant in Sweihan.
Ewec has recently sought transaction advisers for its first battery energy storage system (bess) project, which consists of two 150MW facilities.
MEED also understands that last year’s statement outlined the possibility of procuring up to 16GW of thermal power capacity and around 14GW of solar PV capacity by 2031 to accommodate expected demand until 2036.
Exclusive from Meed
-
Aldar and Mubadala acquire Masdar City Square17 September 2026
-
Dubai announces new 80km highway corridor16 September 2026
-
Engineering progresses on Ras Laffan LNG terminal berths16 September 2026
-
Design completed for Libyan oil field development16 September 2026
-
Chinese contractor wins Qiddiya e-games arena16 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Aldar and Mubadala acquire Masdar City Square17 September 2026
Abu Dhabi-based sovereign wealth fund Mubadala Investment Company and local developer Aldar have completed the acquisition of Masdar City Square at Masdar City, in a transaction valued at AED918m ($250m).
The deal was executed through their joint venture established in 2024.
Masdar City Square comprises more than 47,000 square metres (sq m) of net leasable area across seven office buildings.
Completed in Q1 2026, the development is 99% occupied. Tenants include Taqa, the Department of Energy, Emirates College and the Mohamed Bin Zayed University of Artificial Intelligence.
The transaction expands the joint venture’s real estate portfolio in Masdar City, which is now valued at AED4.7bn ($1.3bn).
Masdar City is one of the region’s leading hubs for clean energy, artificial intelligence, advanced research and sustainable urban development.
The joint venture acquired The Link project at Masdar City for AED654m ($178m) in April.
Comprising about 32,000 sq m of net leasable area across five buildings, The Link is fully leased to a portfolio of major tenants, including Abu Dhabi Future Energy Company (Masdar) and the Mohamed Bin Zayed University of Artificial Intelligence.
The asset includes Grade A, Leed Platinum office space, a net-zero-energy headquarters building, a multi-use hall and residential accommodation, supporting its position as a high-performing, integrated component of Masdar City.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19748241/main5814.png -
Dubai announces new 80km highway corridor16 September 2026
Dubai has approved the construction of the new fourth corridor, a major highway programme aimed at boosting inter-emirate connectivity, increasing road capacity and easing congestion.
The corridor will extend 80 kilometres, from Al-Faya Road in Abu Dhabi to Al-Shanouf Road in Sharjah.
It will include 12 lanes, 72 bridges and 17 tunnels.
The project is expected to reduce travel times by up to 60% and serve more than 3.1 million people, while providing links to Al-Maktoum International airport and Etihad Rail.
It will have the capacity to accommodate 24,000 vehicles per hour in each direction.
The project will be delivered in two phases. The first phase, running from Al-Shanouf Road to Dubai-Al Ain Road, will be delivered at a cost of AED3.5bn ($953m).
The second phase will stretch from Dubai-Al Ain Road to Al-Faya Road in Abu Dhabi.
Hamdan bin Mohammed: In line with the directives of His Highness Sheikh Mohammed bin Rashid Al Maktoum to boost investment in infrastructure, I approved the New Fourth Corridor to strengthen Dubai’s road network and enhance connectivity with the UAE’s federal road network.… pic.twitter.com/zlIyY2yKBN
— Dubai Media Office (@DXBMediaOffice) September 16, 2026
The scheme adds a fourth spine to a network that has long relied on three main corridors: the E11 (Sheikh Zayed Road/Al-Ittihad Road); the E311 (Sheikh Mohamed Bin Zayed Road) and the E611 (Emirates Road), which together carry more than 850,000 vehicles commuting between Dubai and the northern emirates daily.
That concentration has made the route one of the country’s most congested, with peak-hour bottlenecks a persistent problem for residents. The new corridor is designed to divert a significant share of that traffic onto a higher-capacity route, rather than add pressure to the existing network.
The project also aligns with the Dubai 2040 Urban Master Plan, which anticipates population growth to 5.8 million by 2040 and calls for the expansion of roads, railways, airports and ports to support that growth and reinforce Dubai’s position as a global trading hub. This is reflected in the corridor’s direct links to Al-Maktoum International airport and Etihad Rail.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19725878/main.jpeg -
Engineering progresses on Ras Laffan LNG terminal berths16 September 2026

Register for MEED’s 14-day trial access
Front-end engineering and design (feed) works are progressing on a QatarEnergy LNG project to build 13 liquefied natural gas (LNG) loading berths at the south export terminal in Qatar’s Ras Laffan Industrial City.
Ras Laffan Industrial City, which lies about 90 kilometres north of Doha, is the world's largest integrated LNG production and export complex, comprising 15 processing trains with a total capacity of 77.5 million tonnes a year (t/y). QatarEnergy began LNG operations at the facility, which houses all its processing trains and export infrastructure, in 1984.
According to sources, QatarEnergy LNG, a subsidiary of state enterprise QatarEnergy, awarded the feed contract for the project to build 13 LNG berths at the south export terminal at Ras Laffan to Australia-headquartered Worley.
The contract was awarded to Worley in the second quarter of this year. Its duration is estimated to be 200,000-250,000 man hours, sources told MEED.
Ras Laffan’s LNG processing and export capabilities will increase by up to about 63% when the three phases of QatarEnergy’s estimated $40bn North Field LNG expansion project come into operation by the end of this decade. Engineering, procurement and construction (EPC) works on all three projects are progressing.
QatarEnergy is understood to have committed nearly $30bn to the first two phases – North Field East (NFE) and North Field South (NFS) – which will lift Qatar’s LNG production capacity from 77.5 million t/y to 126 million t/y by 2028.
QatarEnergy awarded the main EPC contracts for NFE in 2021. The project was intended to raise LNG output to 110 million t/y by 2025. The $13bn EPC package – covering the engineering, procurement, construction and installation of four LNG trains, each with a capacity of 8 million t/y – was awarded in February 2021 to a consortium of Japan’s Chiyoda and France’s Technip Energies.
In May 2023, QatarEnergy awarded the $10bn main EPC contract for NFS to a consortium of Technip Energies and Consolidated Contractors Company (CCC). The contract includes two LNG trains, each with a capacity of 7.8 million t/y.
Once fully operational, the first two phases are expected to add 48 million t/y of LNG supply to the global market.
QatarEnergy took the final investment decision on the third phase, North Field West (NFW), this year, awarding an EPC contract estimated at $8bn to a joint venture comprising Technip Energies, CCC and Gulf Asia Contracting in February.
Chiyoda carried out the feed work for the NFW LNG project.
The NFW scope covers the EPC of two LNG trains with a combined capacity of 16 million t/y, as well as associated facilities for gas treatment, natural gas liquids recovery and helium extraction.
In addition to LNG, NFW is expected to produce about 175,000 barrels of oil equivalent a day of condensate, ethane and liquefied petroleum gas.
With all three phases under EPC execution – and NFE scheduled for commissioning later this year – QatarEnergy is positioning itself to remain one of the world’s largest LNG suppliers in the long term.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19715235/main5946.jpg -
Design completed for Libyan oil field development16 September 2026

Register for MEED’s 14-day trial access
Design work has been completed for a project to develop Libya’s I/R oil field, according to industry sources.
The front-end engineering and design work was completed by a team in the London offices of Italy’s EniProgetti and paves the way for the main engineering, procurement and construction contract to be tendered.
One source said: “At the moment, there is no fixed date for when the invitation to bid for the main contract will be issued, but the project has a lot of momentum and is progressing towards tendering.”
The I/R oil field is located in Murzuq Basin in southwestern Libya.
In June this year, Libya's National Oil Corporation (NOC) signed a unified operating agreement for the field.
The I/R field is operated by Akakus Oil Operations, which is a joint venture of NOC in partnership with Spain’s Repsol, France’s TotalEnergies Repsol, Austria’s OMV and Norway’s Equinor.
The agreement in June was signed by NOC as well as its concession partners.
NOC said the agreement would unify operational and administrative procedures related to field management, optimise resource utilisation and support production sustainability.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19711588/main.jpg -
Chinese contractor wins Qiddiya e-games arena16 September 2026

Saudi gigaproject developer Qiddiya Investment Company (QIC) has awarded an estimated $600m-$700m contract to build an e-games arena, also known as the Fortress Arena, at its Qiddiya Entertainment City development outside Riyadh.
The contract was awarded to Beijing-headquartered Metallurgical Corporation of China.
The scope of work covers the construction of an auditorium with a capacity of about 5,100 seats, as well as commercial areas, hospitality facilities and other associated infrastructure.
The e-games arena will provide space for local, national and international competitions.
MEED understands that QIC tendered the contract in January, with bids submitted in March.
Completion is expected by April 2029.
US-based architectural firm Populous designed the project, supported by New York-based Thornton Tomasetti.
The project is located in District 18, Upper Plateau, in Qiddiya City.
The Fortress Arena is one of several major projects within the wider Qiddiya development.
Other projects include the Dragon Ball theme park, Prince Mohammed Bin Salman Stadium, a horse racing venue, a performing arts centre, the Speed Park, the National Tennis Centre and the Six Flags theme parks and Aquarabia waterpark.
The project is a key part of Riyadh’s strategy to boost leisure tourism in the kingdom. According to UK analytics firm GlobalData, leisure tourism in Saudi Arabia has grown significantly in recent years.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19661939/main.jpg
