Ewec rules out solar in desalination projects
29 March 2023
Abu Dhabi-based Emirates Water & Electricity Company (Ewec) has ruled out integrating a captive solar photovoltaic (PV) plant in upcoming seawater reverse osmosis (SWRO) independent power projects (IPPs) in the emirate.
Its executive director for strategy and planning, Bruce Smith, recently confirmed this to MEED, citing better cost efficiencies when procuring solar PV IPPs separately.
The world’s largest RO-based desalination plant in Taweelah is nearing completion. The 200 million-imperial-gallon-a-day SWRO plant includes a 40MW captive solar PV plant. Half of the plant’s capacity began commercial operation in June last year.
Ewec’s next two independent water projects (IWPs), Mirfa 2 and Shuweihat 4, do not prescribe captive solar PV.
1GW a year
Abu Dhabi aims to install a total of 16GW of solar PV capacity by 2036, translating to an average of 1GW to 1.5GW of new capacity to be procured annually.
Over the intervening period ending in 2030, Ewec envisages having an additional 5GW of solar capacity to reach a total solar installed capacity of 7.3GW by 2030.
The planned capacity aligns with the state utility’s carbon dioxide emissions reduction plan during this period, which includes potentially expanding its nuclear power capacity and deploying carbon capture technologies for its existing thermal power generation assets.
Smith said Ewec expects its first battery energy storage system to come online in the late 2020s to enable optimum use of renewable energy captured during daytime at times when the solar PV fleets do not produce energy.
Ewec aims to reduce its total carbon dioxide emissions from 43 million tonnes a year (t/y) in 2019 to 22 million t/y by 2035.
Ewec expects to achieve a substantial emissions reduction despite a projected 30 per cent increase in peak demand between 2022 and 2029 and 50 per cent between 2022 and 2050.
Ewec recently announced the company’s latest Statement of Future Capacity Requirements Summary Report covering 2023 to 2029.
The annual document outlines the required additional power and water production capacity in the emirate over a seven-year window based on expected macroeconomic developments and the retirement of existing fleets.
New capacity
The bidding process is under way for the 1.5GW Al-Ajban solar PV project, with Ewec expecting to receive proposals by June.
It recently awarded the contract to develop the 120MIGD Mirfa 2 IWP to France’s Engie. The contract to develop the 70MIGD Shuweihat 4 IWP is expected to be awarded to South Korean/Spanish company GS Inima imminently.
Ewec has recently sought transaction advisers for its first battery energy storage system (bess) project, which consists of two 150MW facilities.
Exclusive from Meed
-
-
Kuwait tenders major infrastructure packages23 March 2026
-
Qiddiya tenders new infrastructure package23 March 2026
-
Kuwait’s Mina Al-Ahmadi refinery attacked23 March 2026
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Chinese firm announces $1.9bn Abu Dhabi renewables contract23 March 2026
China Power Construction Corporation (PowerChina) has announced details of a contract signed for the engineering, procurement and construction (EPC) works on part of Abu Dhabi’s $6bn round-the-clock solar and battery storage project.
The independent power project (IPP) will combine 5.2GW of solar photovoltaic (PV) capacity with 19GWh of battery storage. Last October, Emirates Water & Electricity Company (Ewec) and Abu Dhabi Future Energy Company (Masdar) broke ground on what will be the world’s largest combined solar and battery energy storage system (bess), designed to supply 1GW of round-the-clock power.
India’s Larsen & Toubro and Beijing-headquartered PowerChina were awarded the EPC contract for the project last year, with PwC Middle East advising Ewec on financial structuring.
According to the Chinese firm, the full project has been divided into two blocks, north and south, indicating at least two major packages.
PowerChina’s contract, valued at about $1.9bn, covers the northern block of the project, which includes 2.1GW of DC-side PV installations and a 7.75GWh bess. The scope includes the design, procurement and construction of substations, PV facilities and battery energy storage systems.
Located in the Mshayrif area of Abu Dhabi, the wider project is designed to supply steady delivery of power between April and October each year, the UAE’s peak electricity demand season due to cooling loads.
This includes serving large energy users that require 24/7 clean electricity, such as fast-growing data centre operators and technology firms driving artificial intelligence deployment in the region.
Ewec will act as the offtaker under a long-term power purchase agreement.
MEED previously reported that China’s CATL (Contemporary Amperex Technology Co), Jinko Solar and JA Solar will supply the bess and PV modules, with Jinko and JA each providing 2.6GW of modules.
The project will avoid 5.7 million tonnes of CO₂ emissions annually and provide enough clean energy to power nearly half a million homes.
Construction is expected to be completed in 2028.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16083288/main.jpg -
Kuwait tenders major infrastructure packages23 March 2026

Kuwait’s Ministry of Public Works (MPW) has tendered several contracts for infrastructure works across various parts of the country.
The first tender covers the construction of rainwater drainage systems in the Sabah Al-Ahmad South, Sabah Al-Ahmad, Al-Khairan and Al-Wafra residential areas.
The second tender includes the construction of a treated water system in Kuwait’s southern region.
The third tender covers the construction of a treated water system in Kuwait’s northern region.
The final tender covers the construction of roads, bridges, stormwater drainage, sewage and other services for a section of the Kabd-Sulaibiya Road, as well as a section of the Kabd-Sulaibiya industrial road link.
MPW issued all of these tenders on 22 March, with a bid submission deadline of 21 April.
UK analytics firm GlobalData expects Kuwait’s construction industry to grow by 5.1% in 2026-29, supported by government investment in the oil and gas sector aimed at raising production, as well as investment in the infrastructure sector.
In the short term, growth will be boosted by planned expenditure under the 2025-26 budget, which was approved in March 2025.
The construction industry in Kuwait is expected to record an annual average growth rate of 4.9% in 2026-29, supported by investments in renewable energy, transport, and oil and gas projects.
The commercial construction sector is expected to grow by 4.8% in 2026-29, supported by public and private sector investment in the construction of hotels, retail outlets and office buildings.
READ THE MARCH 2026 MEED BUSINESS REVIEW – click here to view PDFRiyadh urges private sector to take greater role; Chemical players look to spend rationally; Economic uptick lends confidence to Cairo’s reforms.
Distributed to senior decision-makers in the region and around the world, the March 2026 edition of MEED Business Review includes:
> RAMADAN: Data disproves the Ramadan slowdown story> INDUSTRY REPORT: Chemicals producers look to cut spending> INDUSTRY REPORT: Global petrochemical project capex set to rise until 2030> MARKET FOCUS: Egypt’s crisis mode gives way to cautious revival> LEADERSHIP: Delivering Saudi Arabia’s next phase of rail growth> INTERVIEW: Abu Dhabi’s Enersol charts acquisitions pathTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16083252/main.jpg -
Qiddiya tenders new infrastructure package23 March 2026

Saudi Arabian gigaproject developer Qiddiya Investment Company (QIC) has tendered a contract inviting firms to bid for new infrastructure works in Qiddiya Entertainment City.
The scope covers two infrastructure development packages in District 0 of Qiddiya Entertainment City, including the construction of four event park-and-ride facilities.
The tender was issued on 11 March, with a bid submission deadline of 22 April.
Lebanese firm Dar Al-Handasah and Saudi-based Sets International are serving as project consultants.
QIC is accelerating plans to develop additional assets at Qiddiya City. Earlier this month, the company set a 16 April deadline for firms to submit prequalification statements for the Qiddiya high-speed rail project in Riyadh.
Previously, MEED reported that QIC had received bids from contractors on 23 February for a SR980m ($261m) contract covering the construction of staff accommodation at Qiddiya Entertainment City.
The project will cover an area of more than 105,000 square metres (sq m).
Last month, QIC started the main construction works on its performing arts centre at Qiddiya Entertainment City.
The Qiddiya City performing arts centre is one of several major projects within the greater Qiddiya development. Other projects include an e-games arena, Prince Mohammed Bin Salman Stadium, a motorsports track, the Dragon Ball and Six Flags theme parks, and Aquarabia.
In December last year, QIC officially opened the Six Flags theme park to the public.
The theme park covers an area of 320,000 sq m and features 28 rides and attractions, 10 of which are thrill rides and 18 designed for families and young children.
The Qiddiya project is a key part of Riyadh’s strategy to boost leisure tourism in the kingdom. According to UK analytics firm GlobalData, leisure tourism in Saudi Arabia has experienced significant growth in recent years.
The kingdom’s tourism sector posted record-breaking numbers last year, with over 130 million domestic and international visitors entering the kingdom, representing a 6% increase over 2024.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16083013/main.jpg -
Kuwait’s Mina Al-Ahmadi refinery attacked23 March 2026
Register for MEED’s 14-day trial access
Several units were shut down at Kuwait’s largest oil refinery after it was hit by drones as Iran targeted energy infrastructure across the Gulf, according to a statement from state-owned Kuwait Petroleum Corporation (KPC).
Fires broke out across multiple units at the Mina Al-Ahmadi refinery in the morning of 20 March 2026 following the attack.
The refinery normally processes about 730,000 barrels of oil a day.
There were no casualties as a result of the attack, according to KPC.
Kuwait’s oil and gas sector has been severely disrupted by the ongoing regional conflict.
On 10 March, MEED revealed that the state-owned upstream operator Kuwait Oil Company (KOC) was operating with just 30% of its total workforce in their normal workplaces.
Earlier in the month, KPC also declared force majeure due to difficulties transporting oil and gas through the Strait of Hormuz caused by the conflict.
Force majeure, a French term meaning “superior force”, is a clause included in many international commercial contracts. It allows companies to suspend contractual obligations when extraordinary events occur beyond their control.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16067425/main.gif -
Iraq declares force majeure on foreign-operated oil fields23 March 2026
Register for MEED’s 14-day trial access
Iraq has declared force majeure on all oil fields developed by foreign oil companies as the US and Israel’s war with Iran disrupts navigation through the Strait of Hormuz.
The initial attack and Iran’s response have slashed Iraq’s exports.
Prior to the war starting on 28 February, Iraq was exporting between 3.3 and 3.5 million barrels a day of crude oil.
Oil sales account for nearly 90% of Iraq’s government revenues.
Earlier this month, two drone strikes hit infrastructure at Iraq’s Majnoon oil field, increasing security concerns in the country’s energy sector.
One of the drones hit a communications tower, and the other hit the office of the US engineering company KBR.
There were no casualties as a result of the attacks.
Foreign workers were evacuated from the site days after the US and Israel’s war with Iran started, and only Iraqi staff are currently working at the site.
Shortly before the war started, KBR announced that it had been awarded a “major contract” by Iraq’s state-owned Basra Oil Company to provide integrated field management services for the Majnoon oil field.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16067302/main.png