EPC teams start forming for $22bn Dubai tunnels

24 September 2024

Register for MEED's 14-day trial access 

Some prequalified engineering, procurement and construction (EPC) companies for the contracts to develop and operate various packages of the $22bn Dubai Strategic Sewerage Tunnels (DSST) project have started forming teams in anticipation of the next stage of the tendering process.    

In August, Dubai Municipality prequalified 21 companies and consortiums that can bid for three packages known as J1, J2 and W, and 19 for a fourth package known as J3, of the six-package project.

Some companies are in the process of finalising their partners, while at least one has said it does not intend to tap a partner.

While the country of origin is expected to play a role in the formation of teams, it is expected that the complementarity of the companies' expertise and resources will be crucial in the selection process.  

The client and its advisers have opted to prequalify EPC contractors ahead of investors in a departure from the classic public-private partnership (PPP) procurement process.

"The idea is to issue the technical information pack to the prequalified EPC contractors before the prequalification process for investors starts, allowing EPC contractors time to undertake the design process," a source familiar with the project recently told MEED.

He added: "These designs should be ready once Dubai Municipality completes the prequalification process for investors, saving roughly three months compared to the usual route, where the prequalification processes for developers and EPC contractors are done simultaneously."

The staggered prequalification process is expected to help ensure the request for proposals process takes about six months rather than the typical nine months.

Six packages

Under the current plan, the $22bn DSST project is broken down into six packages, which will be tendered as PPP packages with concession periods lasting between 25 and 35 years.

The first package, J1, comprises Jebel Ali tunnels (North) and terminal pump stations (TPS). The tunnels will extend approximately 42 kilometres, and the links will extend 10 kilometres (km). 

The second package, J2, covers the southern section of the Jebel Ali tunnels, which will extend 16km and have a link stretching 46km.

W for Warsan, the third package, comprises 16km of tunnels, TPS and 46km of links.

J3, the fourth package, comprises 129km of links.

J1, J2 and W will be procured under a design-build-finance-operate-maintain model with a concession period of 25-35 years.

J3 will be procured under a design-build-finance model with a concession period of 25-35 years. Once completed, Dubai Municipality will operate them, unlike the first three packages, which are planned to be operated and maintained by the winning PPP contractors.

J1, J2, W and J3 will comprise the deep sewerage tunnels, links and TPS (DLT) components of the overall project.

The project’s remaining two packages entail the expansion and upgrade of the Jebel Ali and Warsan sewage treatment plants (STPs), and will be procured in a process separate from the four DSST-DLT components.

Prequalified EPC contractors  

The prequalified EPC companies for packages J1, J2 and W are:

  • Acciona Construccion (Spain) – Dubai branch
  • Besix Construct (Belgium)
  • China Harbour Engineering (China)
  • China Railway Group (China)
  • China State Construction Engineering Corporation (China)
  • Daewoo Engineering & Construction (South Korea) 
  • Dogus Insaat VE Ticaret Anonim Sirketi (Turkiye) – Abu Dhabi
  • FCC Construcccion (Spain)
  • Archirodon Construction (Overseas) Company (Greece) / BESSAC (France)
  • China Civil Engineering Construction Corporation – Dubai Branch / Shanghai Tunnel Engineering Company (STEC) / China Railway 14th Bureau Group Corporation 
  • Gulermak Agir Sanayi Insaat (Turkiye) / DETech Contracting (local)
  • National Marine Dredging Company (local) / Afcons Infrastructure (India) / ITD Cementation India 
  • The Arab Contractors (Osman Ahmed Osman & Company, Egypt) / Darwish Engineering Emirates (local) / AqualiaMACE Contracting Operation & General Maintenance (local)
  • Larsen & Toubro (India)
  • Porr (Austria)
  • Power Construction Corporation of China (China) – Dubai branch
  • Samsung C&T Corporation (South Korea) – Dubai Branch
  • SK Ecoplant (South Korea) 
  • Strabag Dubai (Austria)
  • The Petroleum Projects & Technical Consultation Company (Petrojet) – Egypt
  • Webuild  (Italy)

EPC companies that have been prequalified for package J3 are:

  • Acciona Construccion (Spain) – Dubai branch
  • Alghanim International General Trading & Contracting (Kuwait) 
  • China Railway Group (China)
  • China State Construction Engineering Corporation (China)
  • Daewoo Engineering & Construction (South Korea)
  • DETech Contracting
  • Archirodon Construction (Overseas) Company (Greece) / BESSAC (France)
  • China Civil Engineering Construction Corporation (China) – Dubai branch / Shanghai Tunnel Engineering Company (STEC) / China Railway 14th Bureau Group Corporation 
  • Gulermak Agir Sanayi Insaat (Turkiye) / DETech Contracting (local) 
  • International Foundation Group (IFG, local) / General Construction Company (local)
  • Nael Construction & Contracting (UAE) / Concord for Engineering & Contracting (Egypt) – Dubai branch
  • National Marine Dredging Company (local) / Afcons Infrastructure (India) / ITD Cementation India 
  • Mapa Insaat Ve Ticaret (Turkiye)
  • Mohammed Abdulmohsin Al-Kharafi & Sons (Kuwait)
  • Porr (Austria)
  • Power Construction Corporation of China – Dubai branch
  • Strabag (Austria)
  • Tecton Engineering & Construction (local)
  • The Petroleum Projects & Technical Consultation Company – Petrojet (Egypt)
Market-sounding

Dubai Municipality is expected to hold a market-sounding event for investors, MEED reported in early September .

The event is set to take place during the first week of October, a few weeks before interested investors submit their statements of qualifications (SOQ) for the projects' various packages.

MEED previously reported that the client had extended the SOQ submission deadline from 5 September to 21 October.

 Gravity system project

The DSST project aims to convert Dubai’s existing sewerage system from a pumped system to a gravity system by decommissioning the existing pump stations and providing “a sustainable, innovative, reliable service for future generations”.

Dubai currently has two major sewerage catchments. The first in Deira is Warsan, where the Warsan STP treats the flow.

The second catchment is in Bur Dubai, where the wastewater is treated at the Jebel Ali STP.

According to a source close to the project, the DSST will replace 120 pump stations, saving approximately 100 gigawatt-hours of electricity annually. 

https://image.digitalinsightresearch.in/uploads/NewsArticle/12590337/main0016.jpg
Jennifer Aguinaldo
Related Articles
  • Local firm wins contract for Kuwait power project

    19 November 2025

    Local firm Alghanim International has won a contract to provide engineering services at the Subiya power and water distillation plant.

    Kuwait’s Central Agency for Public Tenders approved the award following a request from the Ministry of Electricity, Water & Renewable Energy.

    The contract, valued at $286m, covers engineering, supply, installation, operation and maintenance services to convert the 250MW second phase of the plant’s open-cycle gas turbines to combined-cycle gas turbines.

    The upgrade is intended to increase efficiency and provide additional generation capacity during periods of high demand.

    In July, MEED reported that Alghanim had submitted the lowest bid for the tender ahead of local firms Al-Daw Engineering General Trading & Contracting and Al-Zain United General Trading & Contracting.

    In 2024, US-based GE Vernova completed separate upgrades of four GE Vernova 9F.03 class gas turbines at the 2GW Sabiya combined-cycle power plant. Alghanim International acted as GE’s local engineering partner for that work.

    The Subiya power and water distillation plant is the largest power and water plant in Kuwait, with a power generation capacity of 7,046.7MW, accounting for 35% of the country’s installed capacity.

    It has a water desalination capacity of 100 million imperial gallons a day.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15116135/main.jpg
    Mark Dowdall
  • UKEF issues $3.5bn interest letter for Al-Maktoum airport

    19 November 2025

    Register for MEED’s 14-day trial access 

    The UK’s export credit agency UK Export Finance (UKEF) has issued a $3.5bn expression of interest letter to support the participation of UK businesses in the $35bn expansion of Al-Maktoum International airport, which is also known as Dubai World Central (DWC).

    Chris Bryant, UK minister for trade, handed the letter to Khalifa Al-Zaffin, executive chairman of Dubai Aviation City Corporation and Dubai Aviation Engineering Projects (DAEP), and Paul Griffiths, CEO of Dubai Airports.

    Letters of interest from UKEF, although not binding commitments, help ensure that UK exporters are given every opportunity to bid for contracts on a project. This is typically achieved by providing financial solutions in exchange for an agreed level of UK content used on the project.  

    Previous letter

    It is not the first time UKEF has issued a letter of interest for the expansion of Al-Maktoum International airport. In 2014, it issued a $2bn letter of interest. In a statement at the time, UKEF said five prime UK-based contractors were being supported, along with UK suppliers across the supply chain.

    The five prime contractors were Carillion, Kier, Balfour Beatty, Laing O’Rourke and Interserve. Of those five companies, Carillion entered liquidation in 2018 and Interserve entered administration in 2019. Balfour Beatty sold its shareholding in Dubai-based Dutco Balfour Beatty in 2017.

    Although some progress was made on the project after the UKEF offer in 2014, the scheme stalled and was revived again in April 2024, when Dubai approved new designs for the airport.

    Project progress

    Since then, the project client, DAEP, has been awarding and tendering contracts for the first construction packages. It has awarded a AED1bn ($272m) deal to UAE firm Binladin Contracting Group to construct the second runway at the airport.

    The enabling works for the terminal building are being undertaken by Abu Dhabi-based Tristar E&C.

    DAEP is also close to formally awarding a contract for the substructure works for the West Terminal and Concourse One, Concourse Two and Concourse Three.

    Tendering is also ongoing for an automated people-mover (APM) system. The system will run under the apron of the entire airfield and the airport’s terminals. It will consist of several tracks, taking passengers from the terminals to the concourses.

    Four underground stations will be built as part of the first phase. The overall plan includes 14 stations across the airport.

    The airport’s construction is planned to be undertaken in three phases. Construction works on the project’s first phase are expected to be completed by 2032.

    The airport will cover an area of 70 square kilometres (sq km) south of Dubai and will have five parallel runways, five terminal buildings and 400 aircraft gates.

    It will be five times the size of the existing Dubai International airport and will have the world’s largest passenger-handling capacity of 260 million passengers a year. For cargo, it will have the capacity to handle 12 million tonnes a year.

    Dubai has said the plan is for all operations from Dubai International airport to be transferred to Al-Maktoum International within 10 years.


    This aviation package also includes:

    > Middle East invests in giant airports
    > Broader region upgrades its airports
    > Global air travel shifts east

     

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15115788/main.jpg
    Colin Foreman
  • Riyadh gives Expo infrastructure bidders more time

    19 November 2025

     

    Saudi Arabia’s Expo 2030 Riyadh Company (ERC), which is tasked with delivering the Expo 2030 Riyadh venue, has extended the deadline for firms to submit commercial offers for the contract to undertake the initial infrastructure works at the site to 23 November.

    ERC had initially set deadlines of 26 October and 9 November for the submission of technical and commercial bids, respectively.

    The tender for the project’s initial infrastructure works was issued in September, as MEED reported.

    In October, MEED revealed that 16 firms had been invited to bid for the contract to undertake the initial infrastructure works at the Expo 2030 Riyadh site.

    The firms invited to bid include:

    • Shibh Al-Jazira Contracting (local)
    • Hassan Allam Construction (Egypt)
    • El-Seif Engineering Contracting (local)
    • Al-Ayuni Investment & Contracting (local)
    • Kolin Construction (Turkiye)
    • Al-Yamama Trading & Contracting Company (local)
    • Saudi Pan Kingdom (local)
    • Unimac (local)
    • Mapa Insaat (Turkiye)
    • Yuksel Insaat (Turkiye)
    • IC Ictas / Al-Rashid Trading & Contracting (Turkiye/local)
    • Mota-Engil / Albawani (Portugal/local)
    • Almabani / FCC Construction (local/Spain)

    The overall infrastructure works – covering the construction of the main utilities and civil works at Expo 2030 Riyadh – will be split into three packages:

    • Lot 1 covers the main utilities corridor
    • Lot 2 includes the northern cluster of the nature corridor
    • Lot 3 comprises the southern cluster of the nature corridor

    MEED previously reported that ERC was expected to issue the tender for some of the infrastructure packages in September.

    In July, US-based engineering firm Bechtel Corporation announced it had won the project management consultancy deal for the delivery of the Expo 2030 Riyadh masterplan construction works.

    The masterplan encompasses an area of 6 square kilometres, making it one of the largest sites designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport, providing direct access to various landmarks within Riyadh.

    Countries participating in Expo 2030 Riyadh will have the option to construct permanent pavilions. This initiative is expected to create opportunities for business and investment growth in the region.

    The expo is forecast to attract more than 40 million visitors.

    The Public Investment Fund (PIF), Saudi Arabia’s sovereign wealth vehicle, launched ERC in June as a wholly owned subsidiary to build and operate facilities for Expo 2030.

    In a statement, the PIF said: “During its construction phases, Expo 2030 Riyadh and its legacy are projected to contribute around $64bn to Saudi GDP and generate approximately 171,000 direct and indirect jobs. Once operational, it is expected to contribute approximately $5.6bn to GDP.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15115697/main.jpg
    Yasir Iqbal
  • NHC and Turkish firm sign $266m investment deal

    19 November 2025

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s National Housing Company (NHC) has signed an investment agreement worth over SR1bn ($266m) with Turkiye’s Emlak Konut to develop new residential communities within the Mecca Gate project in Mecca.

    The agreement was signed on the sidelines of the Cityscape Global 2025 event in Riyadh.

    Emlak Konut will develop 1,000 residential villas spanning over 255,000 square metres (sq m).

    The latest agreement follows the NHC’s signing of deals worth over SR8.5bn ($2.2bn) for the development of two mixed-use and residential communities in Riyadh.

    The first agreement, worth over SR5.2bn ($1.4bn), was signed with local developer Retal Urban Development Company.

    The deal encompasses the development of 4,839 residential units in the Al-Fursan suburb of Riyadh.

    The other contract, worth over SR3.3bn ($880m), was signed with a joint venture of Egypt’s Hassan Allam Holding and local developer Tilal Real Estate for a mixed-use project in the Khozam district.

    The development will cover an area of over 228,000 sq m.

    It will be delivered through Grova Developments, the development arm of Hassan Allam Holding.

    In 2023, NHC and Saudi Arabia’s Housing Ministry signed investment agreements totalling more than SR24bn ($6.4bn) to launch the Al-Fursan residential project.

    Al‑Fursan is described as the largest scheme in terms of area and number of housing units that NHC is implementing in partnership with other real estate developers. 

    MEED reported in 2020 that Riyadh planned to oversee the development of more than 1 million homes by 2025 to meet growing demand in the kingdom.

    By 2030, the Saudi capital aims to more than double its population, from 7-8 million to 15-20 million, and become one of the 10 wealthiest cities in the world.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15115626/main.png
    Yasir Iqbal
  • Egypt announces oil discovery in Western Desert

    19 November 2025

    Register for MEED’s 14-day trial access 

    A new gas discovery has been made in Egypt’s Western Desert region, according to a statement released by the Ministry of Petroleum & Mineral Resources.

    The discovery was made by Khalda Petroleum Company, a joint venture of state-owned Egyptian General Petroleum Corporation (EGPC) and US-headquartered Apache Corporation.

    The field is expected to be brought online this week, according to the ministry.

    The reserves were discovered after drilling the exploratory well ‘Gomana-1’, the ministry said.

    It added that sensors confirmed the presence of gas reserves, and tests indicated that the well is expected to have a production rate of around 36 million standard cubic feet of gas a day.

    Further tests are ongoing, and the initial evaluation of the well’s reserves is currently being finalised.

    The ministry said that the discovery followed the introduction of new incentives designed to encourage additional gas investment within Khalda’s areas of operation.

    Earlier this month, Egypt started gas production from the West Burullus field in the Mediterranean Sea, after connecting the first wells to the national gas grid.

    The country is currently pushing to increase domestic gas production in order to meet domestic demand and reduce its import bill.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15112551/main.png
    Wil Crisp