Enowa expects Duba energy park bids

23 July 2024

 

Saudi Arabia’s Enowa, a fully owned subsidiary of Neom, expects to receive bids within two weeks for the engineering, procurement, construction (EPC) and operations and maintenance (O&M) services contract to build the first phase of Duba Energy Park in Tabuk.

The tender was floated in early March with an initial bid deadline of 26 May, as MEED reported.

According to a source close to the project, the tender closing date has since been extended to 5 August.

The site is located northwest of the existing 380/132/13.8kV Duba Energy Park, along the highway between Duba and Neom airport.

Two power stations are set to be developed at Duba Energy Park. The first phase comprises a 300MW transportable gas turbine generator (GTG) designed to deliver emergency power to Neom.

The second phase is a permanently installed 500MW facility comprising heavy-duty GTGs.

Both are considered fast-track projects, with the first phase due for completion in 2024 and the second phase in 2025.

Power generated by both plants will be used for baseload operations until 2030. The plan entails converting the plants' fuel to 100% renewable fuel or hydrogen by 2027 or 2028, aligning with Neom's goal to be powered 100% by renewable energy by the end of the decade.

US-based engineering firm Jacobs is the project consultant.

MEED reported in February that Enowa had received bids for a contract to undertake early works at Duba Energy Park.

The contract scope covers the site preparatory works for constructing new power plants at the energy park in Tabuk. 

Neom utility projects

Tenders are being issued rapidly for utility project-related packages catering to Saudi Arabia's SR1.9tn ($500bn) Neom development.

In addition to the Gayal wind and Shiqri solar photovoltaic projects, which have a total combined capacity of 2GW, Enowa has started the procurement process for a 2GW pumped hydropower system at the development.

It has also sought interest from companies for a small battery energy storage facility with a capacity of 21 megawatt-hours. The long-duration energy storage pilot project will be located at Oxagon, Neom's industrial cluster.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12202177/main5529.jpg
Jennifer Aguinaldo
Related Articles
  • Jordan tenders IPP8 power project

    14 July 2026

    Jordan’s National Electric Power Company (Nepco) has issued a tender for a contract to develop the 700MW combined-cycle gas turbine (CCGT) power project known as independent power project 8 (IPP8).

    Companies understood to have prequalified include France’s EDF, Saudi Arabia’s Acwa and Egypt’s Orascom Construction. Bids are due in July, although the market expects the closing date may be extended.

    MEED reported in November last year that Nepco had invited developers to submit prequalification documents for IPP8. The project will be developed on a build, own and operate (BOO) basis and will supply power to the national grid under a 25-year agreement.

    Natural gas will serve as the primary fuel, with light distillate as backup. The facility will be connected to Nepco’s 132kV/400kV transmission infrastructure, which will be built separately.

    In April, MEED reported that Nepco had signed an agreement to establish a natural gas supply point for the 700MW IPP7. The agreement was signed with Fajr Jordanian-Egyptian for Natural Gas Transmission and Supply to support fuel provision for the CCGT plant.

    The plant will be developed in partnership with Etihad Development Company, a subsidiary of the UAE’s Etihad Water & Electricity (EtihadWE), following recent approval by the Ministry of Energy & Mineral Resources.

    The IPP7 plant is expected to meet about 10% of Jordan’s electricity demand once operational. It is also intended to enhance the reliability and efficiency of the national power system.

    The project is scheduled to become operational between 2027 and 2028.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17662814/main.jpg
    Colin Foreman
  • AtkinsRealis wins key Riyadh infrastructure roles

    14 July 2026

    Canadian engineering firm AtkinsRealis has been awarded a contract by the Royal Commission for Riyadh City (RCRC) to support the operation and expansion of the Riyadh Metro and oversee the delivery of major road infrastructure projects across the capital.

    AtkinsRealis will provide engineering consultancy, project management, construction supervision and technical oversight for ongoing works on the Riyadh Metro.

    The agreement was signed during the Saudi Arabia-Canada Investment Forum in Jeddah, held on the sidelines of Canadian Prime Minister Mark Carney’s visit to the kingdom.

    The company will also supervise a portfolio of strategic road development schemes designed to strengthen Riyadh’s wider transport network.

    AtkinsRealis also recently secured a contract to deliver lead design services for the Place & Planet Pavilion at the Expo 2030 Riyadh site.

    The contract was awarded by Expo 2030 Riyadh Company, which is tasked with delivering the Expo 2030 Riyadh venue.

    AtkinsRealis will deliver the full architectural and engineering design for the pavilion, coordinate all relevant design disciplines and embed sustainable design principles throughout.

    The Place & Planet Pavilion is anticipated to be a key attraction at Expo 2030 Riyadh.


    READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Stress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.

    Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17660065/main.jpg
    Yasir Iqbal
  • Clarifications begin for Saudi Landbridge Riyadh section

    14 July 2026

     

    Register for MEED’s 14-day trial access 

    Saudi Arabia Railways (SAR) has begun post-tender clarifications with bidders for a contract to design and build the Riyadh Rail Link, a new north-to-south railway line across the capital.

    MEED understands that the latest round of clarifications with bidders was held last week.

    Contractors submitted their commercial proposals on 30 June, as MEED reported.

    The bidders include:

    • China Civil Engineering Construction Corporation / Al-Ayuni Investment & Contracting (China/local)
    • Nesma & Partners / China Harbour Engineering Company (local/China)
    • Al-Rashid Trading & Contracting / IC Ictas Construction / Saipem (local/Turkiye/Spain)
    • Saudi Binladin Group (local)

    The scope includes a 35-kilometre double-track line connecting SAR’s North-South Railway to the Eastern Railway network.

    Issued on 29 January, the tender also covers the procurement, construction and installation of associated infrastructure, including viaducts, civil works, utility diversions/installations, signalling systems and other related works.

    Once delivered, the Riyadh Rail Link is expected to become a key component of the Saudi Landbridge railway.

    In January, SAR said it would deliver the Saudi Landbridge project through a “new mechanism” by 2034, after failing to reach an agreement with a Chinese consortium to construct it, as MEED reported.

    In an interview with local media, SAR CEO Bashar Bin Khalid Al-Malik said the consortium failed to meet local content requirements, and that the project would instead be delivered in several phases under a different procurement model.

    Negotiations have been under way between Saudi Arabia and China-backed investors interested in developing the scheme through a public-private partnership (PPP). Al-Malik put the project cost at about SR100bn ($26.6bn).

    Overall, it comprises more than 1,500km of new track. A core element is a 900km railway between Riyadh and Jeddah, providing the capital with direct freight access to King Abdullah Port on the Red Sea.

    Other key elements include upgrading the existing Riyadh-Dammam line, a bypass around the capital known as the Riyadh Link, and a connection between King Abdullah Port and Yanbu.

    The Saudi Landbridge is one of the kingdom’s most anticipated project programmes. First announced in 2004, it was put on hold in 2010 before being revived a year later. Rights-of-way issues, route alignment and the high cost have been among the main stumbling blocks.


    READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Stress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.

    Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17659657/main.jpg
    Yasir Iqbal
  • Contractors win $213m King Salman airport deal

    14 July 2026

     

    Register for MEED’s 14-day trial access 

    A joint venture of Beijing-headquartered China Civil Engineering Construction Corporation and Dammam-based Mofarreh AlHarbi & Partners has won an estimated SR800m ($213m) deal to undertake the enabling and substructure works for Terminal 6 at King Salman International airport (KSIA) in Riyadh.

    The contract was awarded by King Salman International Airport Development Company (KSIADC).

    In March, MEED exclusively reported that KSIADC had selected three groups for the main construction of Terminal 6.

    KSIADC, which is backed by Saudi sovereign wealth vehicle the Public Investment Fund, will initially deliver the Terminal 6 main works on an early contractor involvement basis.

    The latest development follows KSIADC’s receipt of prequalification statements from contractors on 1 July for two new packages at KSIA.

    These include the construction of a permanent East-West corridor and landside access roads serving the North and South terminals.

    In May, KSIADC selected three groups to deliver the Terminal 6 apron, taxiways and other airfield infrastructure at KSIA.

    MEED reported in May 2025 that US firm Bechtel Corporation had been appointed as the delivery partner for the terminals at KSIA.

    Terminal 6 will boost the airport’s capacity by 40 million passengers.

    The project is expected to be delivered before the start of Expo 2030 Riyadh.


    READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Stress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.

    Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17659431/main.jpg
    Yasir Iqbal
  • I Squared eyes $2bn deployment across PIF portfolio

    13 July 2026

    Register for MEED’s 14-day trial access 

    Saudi Arabia's Public Investment Fund (PIF) has signed a memorandum of understanding (MoU) with US infrastructure investor I Squared Capital, under which the firm will pursue the deployment of up to $2bn in real estate and infrastructure assets owned by the sovereign fund and its portfolio companies.

    The non-binding agreement, announced on 13 July, will see the two work with PIF portfolio companies to identify opportunities in digital infrastructure and district cooling, which the parties describe as critical enablers of the real estate sector. I Squared will target allocating up to $1bn in each of the two areas, with the option to scale across additional related business themes.

    The MoU aligns with PIF's 2026-30 strategic objectives to partner with global investors on opportunities within its portfolio and to maximise the value of its portfolio companies. The collaboration is expected to accelerate project delivery and increase the contribution of third-party capital into opportunities across the portfolio.

    Founded in 2012 and headquartered in Miami, I Squared Capital manages $60bn in assets across power and utilities, transport and logistics, digital infrastructure, and environmental and social infrastructure. Its portfolio includes more than 100 companies operating in over 70 countries.


    READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Stress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.

    Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17655682/main2812.png
    Colin Foreman