Energy security facilitates upstream spending

1 March 2023

MEED's upstream oil & gas report also includes: Hydrocarbons exploration rebounds


 

Middle East and North Africa (Mena) oil and gas producers have stepped up to the challenge of meeting the world’s energy needs, especially since the outbreak of the Russia- Ukraine war in February 2022. Although state-owned and private energy producers alike are motivated by the profitability that high commodity prices bring, supply from the region is critical in addressing global energy security.

Regional hydrocarbons producers spent almost $19bn on upstream projects in 2022 as they sought to swiftly bring additional energy supplies online to offset the impact of the lack of Russian volumes on the global market, and particularly on Europe.

With the larger issue of an effective energy transition taking longer than projected, coupled with the prevailing supply shortage, Mena players have put in place major capital expenditure (capex) plans to boost their long-term oil and gas production potential.

The overall value of Mena oil and gas production projects in various pre-execution stages is more than $125bn, according to regional projects tracker MEED Projects.

Robust upstream spending

Qatar dominated spending on upstream projects for the second year in a row in 2022, accounting for more than a third of the $18.9bn of engineering, procurement and construction (EPC) contract awards in the Mena region.

With the goal of consolidating its position as the world’s largest supplier of gas, QatarEnergy is making progress with its North Field liquefied natural gas (LNG) expansion programme, estimated to be worth about $30bn. This will raise Qatar’s LNG production to 126 million tonnes a year (t/y) in two phases by 2027.

The two-stage North Field Production Sustainability (NFPS) programme will run in parallel, to help maintain gas production from the large offshore reserve in order to match the feedstock requirements of the LNG expansion scheme.

QatarEnergy’s biggest award in 2022 was a $4.5bn EPC contract won by Italian contractor Saipem. It covers the building and installation of two gas compression facilities as part of the second development phase of the NFPS project. 

The two gas compression complexes covered in the package will weigh 62,000 tonnes and 63,000 tonnes and will be the largest fixed steel jacket compression platforms ever built.

Saudi Aramco allocated a capex budget of $40bn-$50bn for 2022, an increase on the $31.9bn it spent in 2021. The firm came second to QatarEnergy, spending about $5.8bn on upstream EPC contracts in 2022. 

Aramco awarded contracts for 11 offshore engineering, procurement, construction and installation (EPCI) tenders during the year to contractors in its Long-Term Agreement (LTA) pool of offshore service providers.

Through these offshore structure refurbishment and modification works, Aramco intends to maintain and enhance the oil and gas production capacity of its Abu Safah, Manifa, Marjan, Qatif and Safaniya fields.

In the first quarter of 2022, Aramco also selected Japanese contractor JGC Corporation for the two main onshore packages of the Zuluf upstream project. Package one is estimated to be the bigger of the two onshore packages, with an approximate contract value of $2bn-$2.5bn. It covers EPC work to build hydrocarbons processing facilities. Package two, covering utilities and water injection facilities, is estimated to be worth about $1bn.

Healthy projects pipeline

With regional energy producers stepping up efforts to achieve their oil and gas output goals more quickly, the level of spending on upstream EPC project contracts this year is expected to increase to almost three times that of 2022.

Iran is still under the weight of economic sanctions and has failed to reach an agreement with Western governments regarding its nuclear programme. Despite this, the country appears to still be striving to increase its oil and gas production levels.

State-owned Pars Oil & Gas Company (POGC) is understood to be moving ahead with a programme to develop the offshore North Pars gas field, estimated to hold reserves of up to 55 trillion cubic feet. 

POGC has undertaken a $16bn EPC project, with offshore and onshore components, to start gas production from North Pars. With Tehran suffering from a lack of foreign investment in its energy sector, however, the actual size of the project could shrink significantly and there could be delays to its development timeline.

QatarEnergy, meanwhile, has progressed to the next phase of its North Field LNG expansion programme, known as North Field South (NFS). Contractors submitted commercial bids in February for the estimated $6bn package covering EPCI work on two main LNG trains.

Investing in growth

Abu Dhabi National Oil Company (Adnoc) has adopted a five-year business plan with a capex budget of $150bn for 2023-27. The firm has also said it now aims to meet its oil production capacity target of 5 million barrels a day (b/d) by 2027 instead of 2030.

Having brought its oil and gas production capacity targets forward, Adnoc is accelerating work on key projects. The firm plans to raise gas output by 3 billion cubic feet a day (cf/d) in the next few years, and the Hail and Ghasha offshore sour gas production project will be central to achieving this goal.

In January, Adnoc signed pre-construction service agreements with two consortiums of contractors for the offshore and onshore EPC work on the gas production project, which is estimated to be worth more than $10bn.

France-headquartered Technip Energies, South Korean contractor Samsung Engineering and Italy’s Tecnimont have formed a consortium for the Hail and Ghasha onshore package. 

Italian contractor Saipem, Abu Dhabi’s National Petroleum Construction Company and state-owned China Petroleum Engineering & Construction Company will work together on the offshore package.

Under the agreements, which are valued at $80m and $60m for the onshore and offshore packages, respectively, the contractors will perform initial detailed engineering and procurement services for critical long-lead items. 

The consortiums will also prepare proposals for the main EPC work on the project, which Adnoc will evaluate on an open-book cost estimate basis.

Production from the Ghasha concession, where the Hail and Ghasha fields are located, is expected to start in 2025, ramping up to more than 1.5 billion cf/d before the end of the decade.

Meanwhile, Saudi Aramco is striving to increase its maximum oil output spare capacity to 13 million b/d by 2027 from about 12 million b/d currently, and raise gas production by 50 per cent by the end of this decade.

To realise these targets, Aramco is expected to significantly raise capex on upstream EPC contracts this year. The company is preparing to award more than $3bn-worth of offshore EPCI deals to its LTA contractors before the end of the first quarter of 2023.

Later this year, Aramco is anticipated to award several more multibillion-dollar offshore EPCI jobs. This will include 10 packages of a project to incrementally increase oil production from the Safaniya offshore oil and gas field in Saudi Arabia – the world’s largest offshore oil field.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10636457/main.gif
Indrajit Sen
Related Articles
  • Abu Dhabi and US firms form $25bn power joint venture

    20 March 2025

    Abu Dhabi-based critical infrastructure-focused sovereign investor, ADQ and US-headquartered Energy Capital Partners (ECP) have agreed to establish a 50:50 partnership in new build power generation and energy infrastructure.

    ECP is the largest private owner of power generation and renewable facilities in the US.

    The firms plan to make total capital investments of more than $25bn across 25GW worth of projects, with the US as the primary focus.

    The combined initial capital contribution from the partners is expected to amount to $5bn.

    “The partnership will focus on serving the needs of data centers and industrial centers in the US and selected other international markets over the long-term,” ADQ said in a statement on 19 March, a day after UAE National Security Adviser and Abu Dhabi Deputy Ruler, Sheikh Tahnoon bin Zayed Al- Nahyan met with US President Donald Trump at the White House.

    ADQ said the partnership aims to service the growing power needs of data centres, hyperscale cloud companies and other energy-intensive industries.

    “As the continuity and quality of power supply is crucial for these high-growth industries, the need for captive power plants that are in proximity is often a pre-requisite,” ADQ said.

    The partnership is focused on meeting these needs over the long term with its mandate including greenfield development, new build and expansion opportunity projects.

    A portion of the capital may also be allocated towards opportunities in selected other international markets.

    The statement cited a recent report by the International Energy Agency (IEA) stating the world’s electricity consumption is forecast to rise at its fastest pace in recent years.

    The growing need of data centers and industrial electrification partly account for the surging consumption.

    In the US, for instance, a substantial increase in electricity demand is expected to add the equivalent of California's current power consumption to the national total over the next three years.

    Recent research also forecasts that global power demand from data centres will increase by 50% by 2027 and by as much as 165% by the end of the decade, driven by the expansion of AI and high-density data centres.

    The US Department of Energy estimates that data centre load growth has tripled over the past decade and is projected to double or triple by 2028.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13525493/main.jpg
    Jennifer Aguinaldo
  • QatarEnergy LNG receives bids for decarbonisation project

    20 March 2025

    Register for MEED’s 14-day trial access 

    QatarEnergy LNG has received bids from contractors for a carbon dioxide (CO2) sequestration complex project covering its liquefied natural gas (LNG) production operations in Qatar’s Ras Laffan Industrial City (RLIC).

    Once commissioned, the planned sequestration facility will be capable of capturing 4.3 million tonnes a year (t/y) of CO2 from QatarEnergy LNG’s production operations in RLIC.

    Contractors submitted bids for the project, estimated to be valued at $2bn-$2.5bn, by the deadline of 13 March, sources told MEED.

    The following contractors are among those that are understood to have submitted bids for engineering, procurement and construction (EPC) works on the QatarEnergy LNG CO2 sequestration project:

    • Chiyoda (Japan) / Consolidated Contractors Company (Greece/Lebanon)
    • Larsen and Toubro Energy Hydrocarbon (India)
    • Samsung C&T (South Korea)

    The planned sequestration facility will capture CO2 from seven LNG trains at the QG North complex and three LNG trains at the QG South complex. The CO2 captured from the trains is to be compressed and injected into new injection wells, for which new compression trains and pipelines need to be installed.

    The EPC scope of work on the project covers the following:

    • QG North complex:
      • Installation of four new electric-driven compressors
      • New power substation for power import from Kahramaa 65MW
      • New ITR for DCS/ESD/F&G
      • Tie-ins with utility units
      • Dehydration package
      • Pig launcher
         
    • QG South complex:
      • Installation of two new electric-driven compressors
      • Integration with South injection system unit 85
      • Solvent reformulation for South trains 1/23
      • New power substation for power import from Kahramaa 35MW
      • New SIH for DCS/ESD/F&G
      • Tie-ins with utility units
      • Dehydration package
      • Chillers package
      • Pig launcher
         
    • RLIC corridors
      • Common 22-inch export pipeline stretching 18 kilometres
      • Power tie-in RLF3 with Kahramaa
      • Electric cables
      • Fiber optic cable
         
    • Lot W15
      • Six injection wells by QatarEnergy LNG subsurface
      • Six injection flowlines and metring skid
      • Six wellhead control panels
      • Power tie-in from Barzan
      • Substation
      • Pig receiver
      • Access road and fencing

    QatarEnergy LNG awarded Australia-headquartered consultancy Worley a contract in September 2023 for the execution of the front-end engineering and design (feed) work on the project, as well as to prepare the EPC scope of work.

    North Field LNG expansion

    Meanwhile, QatarEnergy LNG, a subsidiary of state enterprise QatarEnergy, continues to press forward with its North Field LNG expansion programme.

    The estimated $40bn North Field LNG expansion programme aims to raise Qatar’s total LNG production capacity from 77.5 million t/y to 142 million t/y in three phases.

    QatarEnergy is understood to have spent almost $30bn on the two phases of the North Field LNG expansion programme, North Field East and North Field South, which will increase its LNG production capacity from 77.5 million t/y to 126 million t/y by 2028.

    EPC works on the two projects are making progress.

    QatarEnergy awarded the main EPC contracts in 2021 for the North Field East project, which is projected to increase LNG output to 110 million t/y by this year. The main $13bn EPC package, which covers the engineering, procurement, construction and installation of four LNG trains with capacities of 8 million t/y each, was awarded to a consortium of Japan’s Chiyoda Corporation and France’s Technip Energies in February 2021.

    QatarEnergy awarded the main EPC contract for the North Field South LNG project, worth $10bn, in May 2023. The contract covers two large LNG processing trains, each with a capacity of 7.8 million t/y, and was awarded to a consortium of Technip Energies and Lebanon-based Consolidated Contractors Company.

    When fully commissioned, the first two phases of the North Field LNG expansion programme will contribute a total supply capacity of 48 million t/y to the global LNG market.

    In February 2024, QatarEnergy announced the third phase of its North Field LNG expansion programme. To be called North Field West, the project will further increase QatarEnergy’s LNG production capacity to 142 million t/y when it is commissioned by 2030.

    The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. The new project will draw feedstock for LNG production from the western zone of Qatar’s North Field offshore gas reserve.


    February's special report on Qatar includes

    > COMMENT: Doha works to reclaim spotlight
    > ECONOMY: Qatar economy rebounds alongside diplomatic activity
    > BANKING: Qatar banks look to calmer waters in 2025
    > UPSTREAM: QatarEnergy strives to raise gas and oil production capacity
    > DOWNSTREAM: Qatar chemical projects take a step forward
    > POWER & WATER: Facility E award jumpstarts Qatar’s utility projects
    > CONSTRUCTION: Qatar construction shows signs of recovery
    > DATABANK: Qatar maintains stable growth heading

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13525489/main2030.jpg
    Indrajit Sen
  • Teams form for Al-Sila wind IPP

    20 March 2025

     

    Register for MEED’s 14-day trial access 

    Prequalified developers have started to form consortiums to bid for a contract to develop a wind farm in Abu Dhabi.

    In February, Abu Dhabi state offtaker Emirates Water & Electricity Company (Ewec) invited prequalified developers to submit their proposals for the contract.

    According to an industry source, Ewec expects to receive bids for the Al-SIla wind independent power project (IPP) by 31 July.

    The 140MW Al-Sila wind IPP will have a generation capacity of up to 140MW. When fully operational, it will more than double the existing wind generation capacity in the UAE.

    Ewec has prequalified 10 firms as managing partners, which "are free to bid either individually or as part of a consortium with other prequalified bidders". These are:

    • Acciona (Spain)
    • Alfanar (Saudi Arabia)
    • AlJomaih Energy & Water (Saudi Arabia)
    • EDF Renewables (France)
    • Envision (China)
    • International Power (Engie, France)
    • Jera (Japan)
    • Marubeni (Japan)
    • SPIC Huanghe Hydropower Development Company (HHDC, China)
    • Sumitomo (Japan)

    Ewec prequalified six firms as consortium members, which can bid as part of a consortium with a managing partner listed above.

    These are:

    • Alghanim International (Kuwait)
    • China Energy Overseas Investment Company (China)
    • Etihad Water & Electricity (local)
    • Ming Yang Smart Energy Group (China)
    • Orascom Construction (Egypt)
    • PowerChina International Group (China)

    The Al-Sila wind project will involve the development, financing, construction, operation, maintenance and ownership of the wind farm and associated infrastructure. 

    The project will follow Abu Dhabi’s IPP model, where developers enter into a long-term power-purchase agreement with Ewec as the sole procurer of electricity. 

    Ewec expects the project to generate enough clean electricity to power 36,000 homes, displacing 190,000 tonnes of carbon dioxide annually.

    It will also directly contribute to Abu Dhabi’s Clean Energy Strategic Target 2035, which calls for 60% of electricity production to be generated from renewable and clean sources. 

    Together with the existing UAE wind assets, the new project will increase the UAE’s wind generation capacity to approximately 240MW, laying the foundation for further wind energy expansion, according to Ewec’s latest Statement of Future Capacity Requirements report.

    In October last year, Ewec and Abu Dhabi Future Energy Company (Masdar) signed a power-purchase agreement for several wind power plants in Abu Dhabi and the emirate of Fujairah, with a combined capacity of over 100MW.

    Their locations and capacities are:

    • Sir Baniyas Island (Abu Dhabi): 45MW
    • Delma Island (Abu Dhabi): 27MW
    • Al-Sila Abu Dhabi: 27MW
    • Al-Halah (Fujairah): 4.5MW

    Masdar developed the 103.5MW wind power projects, which use “the latest technology and innovation to capture low wind speeds at utility scale, adopting advances in material science and aerodynamics to make wind power possible in the country”.

    The Al-Sila wind farm takes the total number of IPPs that are at various procurement stages in Abu Dhabi to seven. The other schemes are:

    • Al-Nouf combined-cycle gas turbine (CCGT) plant: 3,300MW
    • Taweelah C CCGT plant: 2,500MW
    • Madinat Zayed open-cycle gas turbine plant: 1,500MW
    • Al-Khazna solar IPP: 1,500MW
    • Al-Zarraf solar IPP: 1,500MW
    • Battery energy storage system 1: 400MW

    These IPPs have a total combined capacity of over 10.7GW.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13525006/main4931.jpg
    Jennifer Aguinaldo
  • Barakah 2 talks may start in two years

    19 March 2025

     

    Discussions for the next phase of the UAE's nuclear power plant in Barakah may be delayed by around two years, a source familiar with the plans tells MEED.

    The 5.6GW Barakah nuclear power plant's four reactors entered full operations in September last year, which has intensified speculation about when the procurement process for the plant's next phase could start.

    "I think they might be considering comparing the tariffs between the next nuclear power plant and the round-the-clock renewable energy project," the source said, referring to the 5.2GW solar photovoltaic plus 19 gigawatt-hour battery energy storage system project in Abu Dhabi, which Abu Dhabi Future Energy Company (Masdar) is developing.

    The round-the-clock project is expected to deliver 1GW of 'baseload' renewable power.

    In addition, the state utility, Emirates Water & Electricity Company (Ewec) does not foresee an additional 2.8GW of nuclear energy installed capacity until 2039, which implies that – given the average 10-year construction period for nuclear power plants – procurement talks "will only likely start sometime between 2027 and 2028".  

    Prior to the Barakah nuclear power plant's completion, Hamad Alkaabi, the UAE's permanent representative to the Austria-based International Atomic Energy Agency, was quoted as saying that the tendering process for the UAE's next nuclear power plant could start before the end of 2024.

    The government has yet to budget for a second power plant or decide on the size or location of such a project, but Alkaabi said it is possible that a tender could be issued this year, the Reuters report, published in July 2024, said.

    However, indications started to emerge in December that the planned second phase of the nuclear power plant could be delayed.

    MEED has requested a comment from Emirates Nuclear Energy Company.

    Expansion plans

    The next phase of the Barakah power plant, comprising reactors five to eight, has been in the planning stage since 2019, according to regional projects tracker MEED Projects.

    The UAE became the first Arab state to operate a nuclear power plant when the plant's first reactor became operational in 2021.

    Each of the four reactors at the Barakah nuclear power plant can produce 1,400MW of electricity.

    The entire plant reached full commercial operations approximately 16 years after Abu Dhabi first announced the project in 2008, and 12 years after construction works commenced on Unit 1.


    READ THE MARCH MEED BUSINESS REVIEW – click here to view PDF

    Chinese contractors win record market share; Cairo grapples with political and fiscal challenges; Stronger upstream project spending beckons in 2025

    Distributed to senior decision-makers in the region and around the world, the March 2025 edition of MEED Business Review includes:

    > GULF PROJECTS INDEX: Gulf hits six-month growth streak
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/13513708/main5944.jpg
    Jennifer Aguinaldo
  • Chinese firm wins Damac Riverside villas construction

    19 March 2025

    Register for MEED’s 14-day trial access 

    Dubai-based real estate developer Damac Properties has appointed Chinese contractor China Nuclear Industry No. 22 Construction Company (CNNCC) as the main contractor to build its Damac Riverside villas project.

    The 594-unit residential project is located in the Dubai Investment Park area.

    The project award follows Damac's appointment of CNNCC as the main contractor for its Damac Casa tower.

    Damac Casa is a 43-storey residential building being built in the Al-Sufouh 2 area of Dubai.

    Dubai’s heightened real estate activity is in line with GlobalData’s forecast that the construction industry will register annual growth of 3.9% in 2025-27, supported by investments in infrastructure, renewable energy, oil and gas, housing, industrial and tourism projects. 

    The residential construction sector is expected to record an annual average growth rate of 2.7% in 2025-28, supported by private investments in the residential housing sector, along with government initiatives to meet rising housing demand.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13510084/main.jpg
    Yasir Iqbal