Emir Mishal faces familiar set of challenges

2 January 2024

 

The succession of a new emir in Kuwait hands formal power to another long-serving figure from the Al-Sabah dynasty. Sheikh Mishal al-Ahmad al-Jaber al-Sabah – only three years younger than his late elder brother, Sheikh Nawaf al-Ahmad al-Sabah – is a well-known figure who has held senior defence and security roles in the past, and since 2020, the crown prince position.

Effectively, Sheikh Mishal has been in charge of the government since at least November 2021, when Nawaf’s deteriorating health meant day-to-day power was transferred to his younger brother. This may be a positive, say analysts.

“Since then, there’s been an improvement in parliamentary relations with government, so that could be a positive sign for the future,” says Kristian Ulrichsen, a Middle East fellow at the Baker Institute.

Continuity candidate

Perhaps mindful of the view of many in Kuwait that the new emir hardly represents a break with the past, Sheikh Mishal’s first speech on taking power on 20 December was bold in tone and substance.

He told MPs that both they and the government had harmed the interests of the people. He even voiced disagreement with the late Emir Nawaf over some of the pardons he had issued to individuals accused of spying for Iran and Hezbollah.

That robust style was already evident in June 2022, when the then crown prince attacked the government for a “lack of clarity” in its vision, which he implied had done little to dampen broader opposition to the government.

Sheikh Mishal also appeared to hint that unless there was an improvement and the various logjams obstructing progress removed, the National Assembly could be suspended – regarded in Kuwaiti political circles as the “nuclear option”.

That seems an unlikely prospect. In fact, Sheikh Mishal has also taken conciliatory positions. According to Ulrichsen, many of the politicians who were convicted in the 2010s under former Emir Sheikh Sabah were granted amnesties out of a desire for reconciliation and to move on from the post-Arab Spring decade.

“Because of Nawaf’s ill health, Mishal was the driving force behind that. He’s been signalling to the political class that he’s willing to give them a chance,” says Ulrichsen.

Shifting power dynamics

If the new emir is to give substance to the more ambitious elements of his first speech on taking the oath, then he will need to make some senior appointments that can effect that change. 

“There’s certainly been an attempt to replace or reshuffle a lot of the old guard, and that’s associated with Mishal even if Nawaf was the emir in name,” says Ulrichsen.

Powerful incumbents such as Defence Minister Sheikh Ahmad Fahad al-Sabah are expected to remain in position. He has been viewed as a potential emir himself, enjoying the advantage of relative youth – he is in his late 60s.

The latter’s main rival within senior circles has been the former prime minister Sheikh Nasser Mohammed al-Sabah, who is 81 and less of a direct challenge to Sheikh Mishal. The intense competition between Nasser and Ahmad made it easier for Mishal to emerge as the consensus emir candidate.

Another brewing rivalry could see the sons of the late Emir Nawaf and Sheikh Mishal making plays for a shift in generational power.

Both men were influential in the reorganisation of senior decision-making processes, which saw a number of individuals associated with the late Sheikh Sabah removed from office. Emir Mishal’s son, Ahmad Mishal al-Ahmad, was the head of the Government Performance Monitoring Agency. Ahmad Nawaf al-Ahmad, who was prime minister between June 2022 and December 2023, remains a powerful figure in Kuwait City.  

Given Emir Mishal’s advanced age, these two men are viewed as potential succession candidates – representing a younger generation that some have viewed as presaging a shift seen over recent years in Saudi Arabia, the UAE and Qatar.

Such hopes may be dashed since the reality is that there is not a Kuwaiti version of Saudi Arabia’s Mohammed bin Salman waiting in the wings. And given the parliament’s important role in the approval process – uniquely in the Gulf – Kuwait’s ruler does not have the same freedom of action that his counterpart in Saudi Arabia has. 

Nevertheless, “the Al-Sabahs are running out of brothers. They’ve basically gone from one brother to another for the last 46 years, and their ability to continue that is in question”, says Ulrichsen.

Regional implications

The change of guard in Kuwait also has implications for the rest of the Gulf, given the state’s historic role as a regional peace broker and bridge builder within the often-fractious Gulf Cooperation Council.

The aftermath of the Al-Ula agreement in 2021, which ushered in the reconciliation between Qatar and its GCC antagonists, Saudi Arabia, the UAE and Bahrain, means there is now less requirement for Kuwaiti intermediation.

In any case, Kuwait’s effectiveness in that role largely rested on the personal qualities of the late Emir Sabah, who had decades of diplomatic experience to draw on. His successors do not enjoy such elevated status.

The coming months will give a clearer idea of how Emir Mishal intends to stamp his authority. Those anticipating root and branch change may be disappointed. A younger generation is still some way from taking the reins of power in Kuwait, and the country could still prove stubbornly resistant to the kinds of reforms that have swept through other GCC states.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11404550/main.gif
James Gavin
Related Articles
  • Kuwait awards $381m oil project

    23 September 2026

    Register for MEED’s 14-day trial access 

    State-owned upstream operator Kuwait Oil Company (KOC) has awarded an oil project contract worth KD117m ($381m) to India’s Megha Engineering & Infrastructure (Meil).

    The Supreme Purchasing Committee for Kuwait Petroleum Corporation (KPC) approved the contract last month, paving the way for the official award.

    The project focuses on a water separation unit at the Al-Rawdatain facility in Kuwait.

    The water separation facility will be developed at Gathering Centre 25 (GC-25), along with a pumping facility at GC-30.

    The project will deliver a wide-ranging upgrade of processing and utility infrastructure, including new low-pressure separation and gas-handling equipment such as a three-phase wet separator package, a gas knock-out drum and associated low-pressure gas pipelines, as well as a high-integrity pressure protection system and a high-pressure flare.

    Meil will develop the new three-phase low-pressure wet separation facility at GC-25.

    The main process equipment will include two wet separator packages, each with a capacity of 150,000 barrels of liquid a day, and a low-pressure gas knock-out drum with a capacity of 53 million standard cubic feet a day, together with associated gas-handling facilities.

    The facility will also incorporate an effluent water treatment and transfer system, including an effluent water balance tank equipped with microbubble flotation and induced gas flotation systems, as well as transfer pumps.

    Additional GC-25 facilities will include fuel gas treatment, chemical injection, oil recovery and flare connections, along with firewater and deluge systems.

    The scope also covers control and safety systems, substations, and associated civil, structural, mechanical, electrical and instrumentation works.

    At GC-30, the project will focus on treated-water filtration and high-pressure injection infrastructure.

    The scope includes nutshell filters and associated feed pumps with a combined capacity of approximately 500,000 barrels of water a day.

    Booster and injection pumps will transfer treated effluent water to designated injection wells.

    Additional facilities at GC-30 will include fuel gas treatment, sludge collection and disposal systems, oil recovery systems, control and safety systems, substations, laboratory and workshop facilities, and associated civil, structural, piping, mechanical, electrical and instrumentation works.

    The project also includes transfer pipelines connecting GC-25, GC-15 and GC-30.

    Meil will carry out modifications to existing tanks at GC-30, as well as process and utility tie-ins, electrical and instrumentation modifications and other infrastructure required to integrate the new facilities with KOC’s existing assets.

    Meil’s responsibilities cover the project lifecycle from design and engineering through procurement, construction, testing, pre-commissioning, commissioning, start-up and performance testing.

    The contract also includes operation, maintenance, repair and insurance responsibilities for the designated facilities during the applicable operations and maintenance period.

    Seven companies submitted bids for the project last November.

    The full list of bids was:

    • Meil (India) – KD117m ($381m)
    • Mechanical Engineering & Contracting Company (Kuwait) – KD130m
    • Spetco (Kuwait) – KD158m
    • Al-Kharafi (Kuwait) – KD164m
    • China Oil HBP Science & Technology (China) – KD169m
    • Alghanim International (Kuwait) – KD169m
    • Jereh Oil & Gas Engineering (China) – KD191m

    In October last year, KOC awarded Meil a separate contract for a project to develop a gas sweetening and recovery facility in west Kuwait.

    Meil submitted the lowest bid for that tender, at KD69.2m ($225.5m), in February 2025.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19911322/main.jpg
    Wil Crisp
  • Kuwait refinery project on track for year-end completion

    23 September 2026

     

    A $65m project to replace a substation at the Mina Al-Ahmadi (MAA) refinery is on schedule to be mechanically complete before the end of the year, according to industry sources.

    The project is being executed by India’s Larsen & Toubro (L&T), which was awarded the contract in October 2024.

    One source said: “This project is approaching completion and is currently on schedule to be completed before the end of the year, although it could still see delays related to the ongoing regional conflict.”

    The client is state-owned downstream operator Kuwait National Petroleum Company (KNPC).

    Kuwait’s Ministry of Electricity, Water & Renewable Energy (MEW) is also involved in the project and will provide final approvals and sign-off.

    The scope of the project includes:

    • Construction of a substation
    • Installation of transformers
    • Installation of medium-voltage switchgear
    • Installation of low-voltage auxiliary systems
    • Installation of network protection systems
    • Installation of disconnecting switches
    • Installation of surge arrestors
    • Installation of feeder breakers and cubicles
    • Installation of low-voltage A/C and D/C equipment
    • Installation of battery banks and battery chargers
    • Installation of related relay and control panel boards
    • Installation of fire alarm and fire protection equipment
    • Installation of a SCADA system
    • Installation of cables
    • Civil works
    • Associated facilities

    The current project to replace a substation at the MAA refinery closely resembles another project tendered by KNPC more than a decade ago, which L&T also won.

    On 18 May 2015, KNPC signed a contract with L&T to build a new 240MW substation at the MAA refinery, valued at KD21.866m.

    The new substation, known as M20, was designed to replace an existing substation that was considered old and obsolete.

    Mohammed Al-Mutairi, who was KNPC’s chief executive at the time, said the substation building would be explosion-proof and use state-of-the-art control systems.

    He said the station’s capacity would increase from 180MW to 240MW, supplying most of the refinery’s electricity needs.

    Given the similarities between the two projects, L&T has been able to reuse some designs, creating efficiencies, according to industry sources.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19911319/main.jpg
    Wil Crisp
  • Contractor wins $208m Almoosa hospital MEP contract

    23 September 2026

    Register for MEED’s 14-day trial access 

    Riyadh-based construction firm BEC Arabia has won a SR781m ($208m) contract for the mechanical, electrical and plumbing (MEP) works at Almoosa Hospital in Al-Khobar.

    Saudi Arabia’s Almoosa Health Company awarded the contract.

    The hospital complex consists of two towers: a 24-storey in-patient tower with 380 beds, and an 11-storey tower with 224 clinics and 113 additional treatment spaces.

    It will be built on a 45,000-square-metre site.

    A podium spanning the ninth and 10th floors will connect the two towers.

    The hospital will also include parking for 1,700 cars.

    BEC Arabia won the SR656m ($175m) main construction contract for the hospital in November last year.

    In August 2025, MEED reported that Almoosa Health Company had announced it had secured a sharia-compliant credit facility worth SR650m ($173m) from Banque Saudi Fransi.

    In a statement published on the Saudi stock exchange (Tadawul), the company said the seven-year facility would be used to support its expansion and growth strategy.

    Lebanon’s Dar, US-based Perkins&Will and French design firm Pierre-Yves Rochon designed the project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19910889/main.jpg
    Yasir Iqbal
  • UAE to develop integrated waste-to-resource pilot

    23 September 2026

    Emirates Biotech and United Arab Emirates University (UAEU) have launched a pilot project in Al-Ain that could provide a model for larger waste-to-resource facilities.

    The project involves developing the UAE’s first integrated organic-waste valorisation pilot plant, which will test whether food waste and compostable packaging can be processed together to recover resources and reduce waste sent to landfill.

    Located near the UAEU campus, the 40kg-a-day facility will process organic waste to produce renewable biogas and nutrient-rich compost. The project is intended to generate technical and operating data that could support the development of larger-scale facilities.

    Emirates Biotech and UAEU will design, build and operate the pilot plant as part of a two-year research project running from August 2026 to August 2028. Installation and commissioning are expected to be completed by August 2027.

    The plant will combine anaerobic digestion and composting. Anaerobic digestion will convert the organic waste into renewable biogas, while the resulting digestate will be composted to produce nutrient-rich compost.

    A laboratory-scale assessment will also examine the potential to convert the biogas into renewable hydrogen.

    Food waste accounts for nearly 40% of daily municipal solid waste in the UAE, according to Emirates Biotech, and much of it is currently disposed of in landfills.

    The pilot will therefore assess the technical and operational feasibility of recovering value from two waste streams through a single integrated process.

    If successfully scaled, Emirates Biotech says an integrated organic-waste valorisation plant could reduce CO₂ emissions by 89% compared with landfilling.

    The project is expected to provide a scalable and modular model for converting food waste and compostable packaging into renewable biogas and compost, with the findings intended to inform the development of larger waste-to-resource facilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19908972/main.jpg
    Mark Dowdall
  • Contractors prepare Oxagon Highway 55 bids

    23 September 2026

     

    Contractors are preparing to submit bids on 28 September for a design-and-build contract for permanent upgrade works on Highway 55 in the kingdom’s Oxagon region.

    The first phase of the project includes constructing 14 kilometres of road, with two lanes in each direction. It also includes one bridge and three interchanges.

    The project duration is 22 months.

    Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.

    MEED reported exclusively in August 2025 that contractors had submitted responses to an expression of interest notice that Neom had issued earlier that month.

    The project is expected to support cargo movement from Duba Port to other parts of the kingdom and the wider region.

    Last year, Neom tested a pilot initiative by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.

    In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”

    The Port of Neom is located on the Red Sea near the Arar border, a key entry point into Iraq.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19907876/main.jpg
    Yasir Iqbal