Emir Mishal faces familiar set of challenges

2 January 2024

 

The succession of a new emir in Kuwait hands formal power to another long-serving figure from the Al-Sabah dynasty. Sheikh Mishal al-Ahmad al-Jaber al-Sabah – only three years younger than his late elder brother, Sheikh Nawaf al-Ahmad al-Sabah – is a well-known figure who has held senior defence and security roles in the past, and since 2020, the crown prince position.

Effectively, Sheikh Mishal has been in charge of the government since at least November 2021, when Nawaf’s deteriorating health meant day-to-day power was transferred to his younger brother. This may be a positive, say analysts.

“Since then, there’s been an improvement in parliamentary relations with government, so that could be a positive sign for the future,” says Kristian Ulrichsen, a Middle East fellow at the Baker Institute.

Continuity candidate

Perhaps mindful of the view of many in Kuwait that the new emir hardly represents a break with the past, Sheikh Mishal’s first speech on taking power on 20 December was bold in tone and substance.

He told MPs that both they and the government had harmed the interests of the people. He even voiced disagreement with the late Emir Nawaf over some of the pardons he had issued to individuals accused of spying for Iran and Hezbollah.

That robust style was already evident in June 2022, when the then crown prince attacked the government for a “lack of clarity” in its vision, which he implied had done little to dampen broader opposition to the government.

Sheikh Mishal also appeared to hint that unless there was an improvement and the various logjams obstructing progress removed, the National Assembly could be suspended – regarded in Kuwaiti political circles as the “nuclear option”.

That seems an unlikely prospect. In fact, Sheikh Mishal has also taken conciliatory positions. According to Ulrichsen, many of the politicians who were convicted in the 2010s under former Emir Sheikh Sabah were granted amnesties out of a desire for reconciliation and to move on from the post-Arab Spring decade.

“Because of Nawaf’s ill health, Mishal was the driving force behind that. He’s been signalling to the political class that he’s willing to give them a chance,” says Ulrichsen.

Shifting power dynamics

If the new emir is to give substance to the more ambitious elements of his first speech on taking the oath, then he will need to make some senior appointments that can effect that change. 

“There’s certainly been an attempt to replace or reshuffle a lot of the old guard, and that’s associated with Mishal even if Nawaf was the emir in name,” says Ulrichsen.

Powerful incumbents such as Defence Minister Sheikh Ahmad Fahad al-Sabah are expected to remain in position. He has been viewed as a potential emir himself, enjoying the advantage of relative youth – he is in his late 60s.

The latter’s main rival within senior circles has been the former prime minister Sheikh Nasser Mohammed al-Sabah, who is 81 and less of a direct challenge to Sheikh Mishal. The intense competition between Nasser and Ahmad made it easier for Mishal to emerge as the consensus emir candidate.

Another brewing rivalry could see the sons of the late Emir Nawaf and Sheikh Mishal making plays for a shift in generational power.

Both men were influential in the reorganisation of senior decision-making processes, which saw a number of individuals associated with the late Sheikh Sabah removed from office. Emir Mishal’s son, Ahmad Mishal al-Ahmad, was the head of the Government Performance Monitoring Agency. Ahmad Nawaf al-Ahmad, who was prime minister between June 2022 and December 2023, remains a powerful figure in Kuwait City.  

Given Emir Mishal’s advanced age, these two men are viewed as potential succession candidates – representing a younger generation that some have viewed as presaging a shift seen over recent years in Saudi Arabia, the UAE and Qatar.

Such hopes may be dashed since the reality is that there is not a Kuwaiti version of Saudi Arabia’s Mohammed bin Salman waiting in the wings. And given the parliament’s important role in the approval process – uniquely in the Gulf – Kuwait’s ruler does not have the same freedom of action that his counterpart in Saudi Arabia has. 

Nevertheless, “the Al-Sabahs are running out of brothers. They’ve basically gone from one brother to another for the last 46 years, and their ability to continue that is in question”, says Ulrichsen.

Regional implications

The change of guard in Kuwait also has implications for the rest of the Gulf, given the state’s historic role as a regional peace broker and bridge builder within the often-fractious Gulf Cooperation Council.

The aftermath of the Al-Ula agreement in 2021, which ushered in the reconciliation between Qatar and its GCC antagonists, Saudi Arabia, the UAE and Bahrain, means there is now less requirement for Kuwaiti intermediation.

In any case, Kuwait’s effectiveness in that role largely rested on the personal qualities of the late Emir Sabah, who had decades of diplomatic experience to draw on. His successors do not enjoy such elevated status.

The coming months will give a clearer idea of how Emir Mishal intends to stamp his authority. Those anticipating root and branch change may be disappointed. A younger generation is still some way from taking the reins of power in Kuwait, and the country could still prove stubbornly resistant to the kinds of reforms that have swept through other GCC states.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11404550/main.gif
James Gavin
Related Articles
  • EtihadWE tenders $150m Ajman substation project

    21 July 2026

    The UAE’s Etihad Water & Electricity (EtihadWE) has tendered a contract to build three new substations in Ajman.

    Estimated to cost $150m, the project involves the construction of three new 132/11kV substations in the Bahya, Rumaila and Liwara districts. It also includes associated 132kV underground cabling works to connect the substations to the existing transmission network.

    The bid submission deadline is 10 August.

    According to tender documents, the project will add distribution capacity to support load growth and improve the security of electricity supply in the emirate.

    The scope of work includes site preparation, construction of three substation buildings and foundations, installation of 132kV GIS/AIS switchgear, 132/11kV power transformers and 11kV switchgear, as well as protection, control, Scada and telecommunications systems.

    Etihad WE is responsible for electricity and water services in Ajman, Umm Al-Quwain, Ras Al-Khaimah, Fujairah and parts of Sharjah. The utility has been investing in new substations and transmission infrastructure as electricity demand continues to increase across the Northern Emirates.

    This includes a 132/33/11kV substation project on Al-Marjan Island in Ras Al-Khaimah. Construction work is ongoing on the project, with Maetal Dubai serving as the main contractor.

    EtihadWE is also finalising a new masterplan that will cover network capacity requirements and expansion priorities for the next 10 to 15 years.

    In June, Abdulla Al-Khemeiri, chief operations officer, told MEED: “We are currently reviewing it, and we need to obtain shareholder approval first. Once it is approved, it will be released, hopefully by the end of the year.” 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17710661/main.jpg
    Mark Dowdall
  • Seven seeks contractors for Dammam water park and hotel

    21 July 2026

     

    Saudi Entertainment Ventures (Seven), a wholly owned subsidiary of the Public Investment Fund, is preparing to shortlist general contractors for the main construction package of its Dammam Water Park & Hotel project in the Al-Hamra district.

    The waterfront development sits on a 324,300-square-metre (sq m) plot.

    A notice was issued to contractors in July, and the client is expected to finalise the shortlist by the end of this month.

    Seven is seeking firms capable of delivering a lump-sum, turnkey solution for both the water park and a 321-key lifestyle hotel. Construction is expected to take 24 months from contract award.

    The water park is designed around five themed zones and will feature what is billed as the world’s first double-tornado/triple-wave waterslide.

    The park will include 21 major rides and attractions, 21 food and beverage outlets, 66 cabanas, parking for 1,100 vehicles and a daily peak capacity of 4,500 guests.

    Slide procurement has already been completed directly by Seven. The selected contractor will be responsible for locally sourcing slide towers, integrating them with rockwork and secondary steel, and installing the units.

    Detailed design and issued-for-construction packages are complete.

    Marine works, piling, dewatering and site utilities are being progressed separately by the existing early works contractor.

    The hotel component covers roughly 31,700 sq m of gross floor area and will offer 321 guest rooms, four F&B outlets, spa and wellness facilities, a family pool, and meeting, incentive, conference and exhibition space.

    The new contractor’s scope includes superstructure concrete works, façade and roof works, mechanical, electrical and plumbing, interior fit-out and landscaping.

    Seven will consider only contractors with demonstrated experience delivering water parks with complex aquatics, theming and rockwork – either directly or through clearly defined subcontractor partnerships – along with a track record in high-end turnkey hotel fit-outs.

    Construction of Seven’s Dammam entertainment complex is currently under way. In October 2023, Saudi Binladin Group won contracts worth around SR5bn ($1.3bn) from Seven to build two entertainment destinations in the Dammam and Al-Khobar areas of the Kingdom’s Eastern Province.

    The Al-Khobar entertainment complex is being built on reclaimed waterfront land. The complex spans around 300,000 sq m and is also known as ‘The Waves’.

    The Dammam entertainment complex spans 360,000 sq m and is being built on reclaimed land on the Dammam waterfront.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17710096/main.jpg
    Yasir Iqbal
  • Al-Ula appoints equestrian village early works contractor

    21 July 2026

     

    Saudi Arabia’s Royal Commission for Al-Ula (RCU) has awarded a contract for early construction works at the Al-Muatadil Equestrian Village.

    The contract was awarded to Al-Khobar-based Al-Shalawi International Company.

    Canadian engineering firm AtkinsRealis is the project management consultant. UK-headquartered Baker Wilkins & Smith and local firm Al-Hoty Company are the cost consultants.

    Dubai-based SSH is the supervision consultant, and UK-based Hopkins Architects is the lead design consultant.

    RCU announced the project plans in March 2023, including the development of an equestrian hub with two arenas that can accommodate 5,000 and 1,400 spectators, respectively.

    The venue will also include grass polo, sand polo and endurance facilities, with capacities of 600, 400 and 600 seats, respectively.

    These facilities will be complemented by visitor amenities, two stable compounds with capacity for 740 horses, and accommodation and retail outlets for event participants and workers.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17710170/main.jpeg
    Yasir Iqbal
  • Contractors await decision on Riyadh airport sewage plant

    21 July 2026

     

    Seven contractors are awaiting a decision on a contract to build a sewage treatment plant at the King Salman International airport (KSIA) development in Riyadh, according to sources.

    It is understood that bids were submitted to King Salman International Airport Development Company (KSIADC) in March, following the tender’s release earlier this year.

    The plant will treat wastewater generated by the airport and surrounding developments, including passenger terminals, runways, residential districts, commercial facilities and logistics areas.

    The facility will have a treatment capacity of 92,000 cubic metres a day. The contract is estimated to be worth SR700m ($187m).

    The bidders (all local) are:

    • Al-Rawaf Trading & Contracting
    • Almajal Alarabi
    • Nesma Water & Energy
    • Safari Company
    • Saudi Services for Electro-Mechanic Works
    • Washnah Contracting
    • Water & Environment Technologies (Wetico)

    The project scope includes the construction of the treatment plant, the installation of preliminary, secondary and tertiary treatment systems, sewage collection and conveyance pipelines, pumping stations, and electrical and control systems.

    US-headquartered Jacobs is acting as the main project consultant. Commercial operations for the plant are scheduled for 2029.

    The sewage treatment plant is one of several water infrastructure packages planned for the airport. KSIADC is also evaluating bids for a separate $30m engineering, procurement and construction contract covering potable water and fire water tanks and an associated pumping station. The same seven companies have submitted bids for that package.

    Earlier in July, MEED exclusively reported that a joint venture of Beijing-headquartered China Civil Engineering Construction Corporation and Dammam-based Mofarreh AlHarbi & Partners had won a deal to undertake the enabling and substructure works for Terminal 6 at KSIA.

    The latest development followed KSIADC’s receipt of prequalification statements from contractors on 1 July for two new packages at KSIA.

    These include the construction of a permanent East-West corridor and landside access roads serving the North and South terminals.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17709281/main.jpg
    Mark Dowdall
  • Dubai Municipality awards Tasreef drainage contract

    21 July 2026

     

    Dubai Municipality has awarded local firm Detech Contracting the engineering, procurement and construction (EPC) contract for the TF-15-C1 package of its Tasreef Rainwater Drainage Network programme.

    It is understood the municipality issued the letter of award for the contract earlier this month, covering the construction of a stormwater drainage system along Al-Wasl Road and communities west of the Dubai Canal.

    The project includes the construction of a gravity-based stormwater pipeline network with diameters of up to 3.5 metres. It is estimated to cost $100m.

    It was tendered in February through the government’s Sewerage and Recycled Water Projects Department, with bids submitted in April.

    The package forms part of the wider Tasreef initiative, which is intended to improve Dubai’s flood resilience.

    The TF-15-C2 package was recently awarded to China State Construction Engineering Corporation for a stormwater drainage network project located along Umm Suqeim Road in the Al-Barsha and Al-Quoz areas of Dubai.

    The project is estimated to cost $162m and includes the construction of about 20 kilometres of new stormwater pipelines. Similar to the C1 package, it is located west of the Dubai Canal and will connect the Al-Quoz 3 and Al-Quoz 4 industrial areas with Al-Quoz 1.

    Separately, Al-Kharafi has won a drainage EPC contract (Ds207) to upgrade an existing pumping station for the municipality, a source said. The package focuses mainly on mechanical works and is valued at about $39m.

    In May, MEED reported that local firm Nael Construction & Contracting had signed a contract with Dubai Municipality to build a sewage and stormwater drainage system in Dubailand.

    The project (DS-204-C1) involves the construction of a drainage system with sewage gravity pipelines of up to 2,200mm in diameter.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17707980/main.jpg
    Mark Dowdall