Emir Mishal faces familiar set of challenges

2 January 2024

 

The succession of a new emir in Kuwait hands formal power to another long-serving figure from the Al-Sabah dynasty. Sheikh Mishal al-Ahmad al-Jaber al-Sabah – only three years younger than his late elder brother, Sheikh Nawaf al-Ahmad al-Sabah – is a well-known figure who has held senior defence and security roles in the past, and since 2020, the crown prince position.

Effectively, Sheikh Mishal has been in charge of the government since at least November 2021, when Nawaf’s deteriorating health meant day-to-day power was transferred to his younger brother. This may be a positive, say analysts.

“Since then, there’s been an improvement in parliamentary relations with government, so that could be a positive sign for the future,” says Kristian Ulrichsen, a Middle East fellow at the Baker Institute.

Continuity candidate

Perhaps mindful of the view of many in Kuwait that the new emir hardly represents a break with the past, Sheikh Mishal’s first speech on taking power on 20 December was bold in tone and substance.

He told MPs that both they and the government had harmed the interests of the people. He even voiced disagreement with the late Emir Nawaf over some of the pardons he had issued to individuals accused of spying for Iran and Hezbollah.

That robust style was already evident in June 2022, when the then crown prince attacked the government for a “lack of clarity” in its vision, which he implied had done little to dampen broader opposition to the government.

Sheikh Mishal also appeared to hint that unless there was an improvement and the various logjams obstructing progress removed, the National Assembly could be suspended – regarded in Kuwaiti political circles as the “nuclear option”.

That seems an unlikely prospect. In fact, Sheikh Mishal has also taken conciliatory positions. According to Ulrichsen, many of the politicians who were convicted in the 2010s under former Emir Sheikh Sabah were granted amnesties out of a desire for reconciliation and to move on from the post-Arab Spring decade.

“Because of Nawaf’s ill health, Mishal was the driving force behind that. He’s been signalling to the political class that he’s willing to give them a chance,” says Ulrichsen.

Shifting power dynamics

If the new emir is to give substance to the more ambitious elements of his first speech on taking the oath, then he will need to make some senior appointments that can effect that change. 

“There’s certainly been an attempt to replace or reshuffle a lot of the old guard, and that’s associated with Mishal even if Nawaf was the emir in name,” says Ulrichsen.

Powerful incumbents such as Defence Minister Sheikh Ahmad Fahad al-Sabah are expected to remain in position. He has been viewed as a potential emir himself, enjoying the advantage of relative youth – he is in his late 60s.

The latter’s main rival within senior circles has been the former prime minister Sheikh Nasser Mohammed al-Sabah, who is 81 and less of a direct challenge to Sheikh Mishal. The intense competition between Nasser and Ahmad made it easier for Mishal to emerge as the consensus emir candidate.

Another brewing rivalry could see the sons of the late Emir Nawaf and Sheikh Mishal making plays for a shift in generational power.

Both men were influential in the reorganisation of senior decision-making processes, which saw a number of individuals associated with the late Sheikh Sabah removed from office. Emir Mishal’s son, Ahmad Mishal al-Ahmad, was the head of the Government Performance Monitoring Agency. Ahmad Nawaf al-Ahmad, who was prime minister between June 2022 and December 2023, remains a powerful figure in Kuwait City.  

Given Emir Mishal’s advanced age, these two men are viewed as potential succession candidates – representing a younger generation that some have viewed as presaging a shift seen over recent years in Saudi Arabia, the UAE and Qatar.

Such hopes may be dashed since the reality is that there is not a Kuwaiti version of Saudi Arabia’s Mohammed bin Salman waiting in the wings. And given the parliament’s important role in the approval process – uniquely in the Gulf – Kuwait’s ruler does not have the same freedom of action that his counterpart in Saudi Arabia has. 

Nevertheless, “the Al-Sabahs are running out of brothers. They’ve basically gone from one brother to another for the last 46 years, and their ability to continue that is in question”, says Ulrichsen.

Regional implications

The change of guard in Kuwait also has implications for the rest of the Gulf, given the state’s historic role as a regional peace broker and bridge builder within the often-fractious Gulf Cooperation Council.

The aftermath of the Al-Ula agreement in 2021, which ushered in the reconciliation between Qatar and its GCC antagonists, Saudi Arabia, the UAE and Bahrain, means there is now less requirement for Kuwaiti intermediation.

In any case, Kuwait’s effectiveness in that role largely rested on the personal qualities of the late Emir Sabah, who had decades of diplomatic experience to draw on. His successors do not enjoy such elevated status.

The coming months will give a clearer idea of how Emir Mishal intends to stamp his authority. Those anticipating root and branch change may be disappointed. A younger generation is still some way from taking the reins of power in Kuwait, and the country could still prove stubbornly resistant to the kinds of reforms that have swept through other GCC states.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11404550/main.gif
James Gavin
Related Articles
  • Dubai scales up its metro ambitions

    23 April 2026

     

    Dubai’s rail sector has rarely seen such a concentrated burst of procurement activity as it has in the past year.

    Within the space of a few months, Dubai’s Roads & Transport Authority (RTA) has moved simultaneously on three distinct fronts: tendering design consultancy for the Route 2020 extension that will connect the Expo 2020 metro station to Al-Maktoum International airport; inviting study-and-design bids for a 55-kilometre Airport Express Line linking Dubai International airport to Al-Maktoum International airport; and culminating in Dubai Ruler Sheikh Mohammed Bin Rashid Al-Maktoum’s approval of the AED34bn ($9.2bn) Gold Line, a 42km fully underground route that the emirate is calling the largest transportation project in its history.

    These projects form a key part of the Dubai Rail Network Plan 2032, which outlines the development of six public transportation schemes comprising a mix of metro, passenger and high-speed rail lines.

    The most prominent feature of the plan is the addition of new lines to Dubai Metro’s existing network, representing a systematic effort to support the shift of Dubai’s economic centre of gravity towards Dubai South and the vast development corridors in between.

    The city is also seeking to stay ahead of the curve by investing heavily in infrastructure. Data from regional projects tracker MEED Projects shows that the emirate has awarded over $14bn-worth of transport projects in the past two years alone, with several other multibillion-dollar schemes still moving through the planning stages.

    All of this work is being carried out in line with the Dubai 2040 Urban Master Plan, which forecasts the emirate’s population will reach 5.8 million by 2040 – a clear indication of the scale of daily movement the city must accommodate.

    Project progress

    Dubai Metro Gold Line

    On 21 April, Sheikh Mohammed officially announced the launch of the new AED34bn ($9.2bn) Gold Line project.

    The line will be a fully underground network spanning over 42 kilometres, with 18 stations.

    It will run from Al-Ghubaiba in Bur Dubai to Jumeirah Golf Estates.

    The Gold Line will connect with Dubai Metro’s existing Red and Green lines and integrate with the Etihad Rail passenger network.

    In October last year, MEED exclusively reported that the RTA had selected US-based engineering firm Aecom to provide consultancy services for the project.

    Stage one covers concept design; stage two, preliminary design; stage three, preparation of tender documents; stage four, construction supervision; and stage five, the defects liability period.

    Airport Express Line

    Procurement has started for another metro line extending from Dubai International airport (DXB) in Al-Garhoud to Al-Maktoum International airport (DWC) in Jebel Ali.

    Earlier this month, the RTA invited consultants to bid for a contract to study and design what is referred to as the Airport Express Line.

    The proposed line will stretch about 55km and include five stations that will provide passengers with facilities such as remote airline check-in, baggage drop-off and security screening.

    The new line will run from the Red Line metro station at DXB through Al-Jaddaf, along Al-Khail Road to a new station at Jumeirah Village Circle (JVC), before continuing on to DWC.

    There will be two spur lines. The first will run from the new JVC station to Al-Fardan Exchange metro station at Emirates Golf Club, while the second will branch toward Business Bay, where another station will be built.

    Expo 2020 route extension

    Dubai is also undertaking the Route 2020 extension of its metro system, which will start from the Expo 2020 metro station and connect with Al-Maktoum International airport’s West Terminal.

    Consultants submitted their bids earlier this month for the design contract.

    The extension will run for about 3km and feature two stations.

    The existing Route 2020 metro link is a 15km line that branches off the Red Line at Jebel Ali metro station. The line comprises 11.8km of elevated tracks and 3.2km of tunnels, and has five elevated stations and two underground stations.

    Dubai Metro Blue Line extension

    Construction progress on the Dubai Metro Blue Line extension is expected to reach 30% by the end of 2026, according to official accounts.

    In December 2024, the RTA awarded a AED20.5bn ($5.5bn) main contract for the construction of the project.

    The contract was awarded to a consortium of Turkiye’s Limak Holding, Mapa Group, also of Turkiye, and the Hong Kong office of China Railway Rolling Stock Corporation (CRRC).

    The Blue Line will connect the existing Red and Green lines. It will be 30km long, with 15.5km underground and 14.5km above ground.

    The line will have 14 stations, seven of which will be elevated. There will be five underground stations, including one interchange station, and two elevated transfer stations connected to the existing Centrepoint and Creek stations.

    The project is scheduled for completion in September 2029.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16534887/main.png
    Yasir Iqbal
  • Sports Boulevard tenders Wadi Hanifa road works

    23 April 2026

     

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s Sports Boulevard Foundation has issued a tender inviting firms to bid for a contract to build a road and associated infrastructure in the Wadi Hanifa area of Riyadh.

    The bid submission deadline is 27 April.

    The scope includes construction of an 11.4-kilometre road and associated infrastructure, including public realm works, utilities and security systems.

    The scheme is the latest package to progress on Riyadh’s Sports Boulevard project.

    The Sports Boulevard Foundation is also evaluating bids for its Global Sports Tower in the development’s Athletics District.

    The 130-metre-tall Global Sports Tower will have a gross floor area of 84,000 square metres (sq m) and will include more than 30 sports facilities. The tower will feature what is billed as the world’s tallest indoor climbing wall, at 98 metres, and a 250-metre running track.

    Sports Boulevard will run across Riyadh from east to west. Once complete, it is intended to be the world’s longest park, stretching more than 135 kilometres.

    The project is divided into multiple districts, including the Wadi Hanifah, Arts, Urban Wadi, Entertainment, Athletics and Eco districts, as well as Sands Sports Park.

    The large-scale development aims to transform central Riyadh – currently dominated by major highways – into a recreational corridor.

    Sports Boulevard will include 4.4 million sq m of public realm and landmark buildings. Along with the Global Sports Tower, there will be a Centre for Cinematic Arts and a 2,000-seat amphitheatre.

    It will also deliver more than 2.3 million sq m of mixed-use commercial, residential and retail space, alongside sports facilities, around the park, known as the Linear Park.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16534345/main.jpg
    Yasir Iqbal
  • Masdar to develop renewables projects in Montenegro

    23 April 2026

    Abu Dhabi Future Energy Company (Masdar) and Elektroprivreda Crne Gore (EPCG) have agreed to establish a 50:50 joint venture to develop and operate renewable energy projects in Montenegro.

    The planned projects include solar photovoltaic (PV), wind, hydropower, pumped-hydro storage and battery energy storage systems.

    The joint venture will be headquartered in Niksic in western Montenegro and is intended to support Montenegro’s domestic energy needs while also enabling the export of renewable electricity to the Western Balkans and Southern Europe, Masdar said in a statement.

    The companies plan to leverage an existing sub-sea interconnection with Italy. Montenegro is connected to Italy via a 600MW HVDC submarine cable, enabling electricity exports to the Italian market.

    Masdar has an existing presence in Montenegro through its investment in the 72MW Krnovo wind farm.

    The developer has recently accelerated foreign investment plans as part of its broader expansion. In April, it signed a binding agreement with France’s TotalEnergies to establish a $2.2bn joint venture to develop, build and operate renewable energy projects across Asia.

    The combined business will have 3GW of operational capacity and 6GW of projects in advanced development, targeted for commissioning by 2030.

    Masdar is targeting a global renewable energy portfolio of 100GW by 2030. It recently reached 65GW, two-thirds of the way to that target.

    The company plans to deploy an additional $30bn-$35bn in equity and project finance by 2030, adding an average of 10GW of new capacity each year.

    This expansion will be funded through a mix of equity, green bonds and long-term project financing.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16534112/main.jpg
    Mark Dowdall
  • Qiddiya sets new deadline for infrastructure package

    23 April 2026

     

    Saudi gigaproject developer Qiddiya Investment Company (QIC) has set a 13 May deadline for bids for a contract covering new infrastructure works at Qiddiya Entertainment City.

    The scope comprises two infrastructure development packages for District 0 of Qiddiya Entertainment City, including the construction of four event park-and-ride facilities.

    The tender was issued on 11 March, with an initial bid submission deadline of 22 April.

    Lebanese firm Dar Al-Handasah and Saudi-based Sets International are serving as project consultants.

    QIC is accelerating plans to develop additional assets at Qiddiya City. Earlier this month, the company received prequalification statements from firms for the engineering, procurement, construction and finance package for the Qiddiya high-speed rail project.

    MEED has also reported that QIC received bids from contractors on 23 February for a SR980m ($261m) contract covering the construction of staff accommodation at Qiddiya Entertainment City.

    The project will cover an area of more than 105,000 square metres (sq m).

    Also in February, QIC started the main construction works on its performing arts centre at the entertainment hub.

    The Qiddiya City performing arts centre is one of several major projects within the greater Qiddiya development. Other projects include an e-games arena, Prince Mohammed Bin Salman Stadium, a motorsports track, the Dragon Ball and Six Flags theme parks, and Aquarabia.

    QIC officially opened the Six Flags theme park to the public in December last year.

    The park covers 320,000 sq m and features 28 rides and attractions, including 10 thrill rides and 18 aimed at families and young children.

    The Qiddiya project is a key part of Riyadh’s strategy to boost leisure tourism in the kingdom. According to UK analytics firm GlobalData, leisure tourism in Saudi Arabia has experienced significant growth in recent years.

    Saudi Arabia’s tourism sector posted record figures last year, with more than 130 million domestic and international visitors – a 6% increase on 2024.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16533776/main.jpg
    Yasir Iqbal
  • Detailed design progressing for major Iraqi oil project

    23 April 2026

     

    Detailed design work is progressing on Iraq’s 950-kilometre seawater pipeline network under the Common Seawater Supply Project (CSSP), according to industry sources.

    They added that on-site construction would begin only after the detailed design is complete.

    Iraq’s state-owned Basra Oil Company (BOC) and China Petroleum Pipeline Engineering (CPP) signed a $2.5bn contract for the pipeline package in September last year.

    The project is being supervised by Austria’s ILF Consulting Engineers.

    The pipeline package is one of two main CSSP packages.

    The second focuses on a seawater treatment facility, expected to have a capacity of 5 million barrels a day (b/d), potentially rising to 7-8 million b/d in later phases.

    Processed water will be injected into some of Iraq’s largest oil fields – Rumaila, Zubair, West Qurna 1, West Qurna 2 and Majnoon – and also used in the Maysan and Dhi Qar fields.

    Iraq’s Oil Ministry said the injected water will help maintain reservoir pressure and sustain crude production.

    CPP is a subsidiary of state-owned China National Petroleum Corporation.

    TotalEnergies is responsible for the CSSP as part of the larger $27bn Gas Growth Integrated Project.

    Iraq approved a $2.45bn contract with South Korea’s Hyundai Engineering & Construction (Hyundai E&C) in August last year for the engineering, procurement and construction of the seawater treatment plant.

    Over recent weeks, Iraq’s oil exports have collapsed by about 80% due to fallout from the US and Israel’s war with Iran.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16527404/main.jpg
    Wil Crisp