Egypt’s construction sector faces delays
22 February 2023
This package on Egypt’s construction and transport sectors also includes:
> Egypt’s El-Attal launches $229m development
> Qatari Diar selects New Cairo project contractor
> Japan inks a new Cairo metro loan
> NMDC to execute $272m Egypt dredging works
> Bidders prepare Egypt dry port proposals
> Egypt qualifies firms for schools PPP

After seven years of continuous growth, Egypt’s construction sector is showing signs of wobbling amid the country’s economic troubles.
The value of construction and transport contract awards in Egypt has grown every year since 2015 and rose to record highs in the past two years, according to regional projects tracker MEED Projects. It grew by 44 per cent to $19.3bn in 2021 – from $13.4bn in 2020 – before rising again by 31 per cent to $25.4bn in 2022.
In January, however, the value of construction and transport contract awards fell to less than $200m. This was the lowest monthly total since July 2016, and well below the $2.6bn of contract awards in January 2022.
Although the general outlook for the construction sector is strong, economic volatility presents downside risks, at least in the short term.
“Things are at a standstill for the moment,” says Salwa Elbakry, business development director for Egis in Egypt.
“Several tenders were set to be issued in early January and February, but due to the current economic situation, including devaluation, there were some delays.”
This slowdown started in June, when the currency crises deepened. Companies remain optimistic, however, as “Egypt has proven to be a versatile economy”, says Elbakry. “There are a lot of positive outlooks for 2023. By the end of the first quarter or the beginning of the second quarter, things will get better.”
As Egypt’s major projects are backed by sovereign funds, international investors and institutions, it is “business as usual”, she adds.
Cairo’s positioning as a destination for international investment has grown in recent years. In 2021, Egypt’s International Cooperation Ministry secured $10.2bn in development financing, of which $8.7bn was dedicated to public sector projects and $1.5bn to private sector development.
GCC investors continue to believe in the Egyptian market as well. “The ties between the GCC and Egypt go way back,” says Elbakry.
Focus on key projects
While the IMF suggested in January that Egypt should curb its project spending, the government has said its major projects are vital for the country’s development and a vehicle for GDP growth.
Recently, Egyptian president Abdul Fattah al-Sisi pledged that national projects would continue. Ongoing infrastructure schemes include a high-speed railway network; roads and bridges; hospitals; and several new cities, including the $20bn new capital, to the east of Cairo.
“Egypt continues to be driving ahead with a lot of big projects,” says Raouf Ghali, CEO of Hill International. “It is the first time I have seen Egypt working on projects and programmes that rival the GCC, and this is very unusual.”
Other sectors that are expected to initiate new developments are tourism, healthcare and education, as well as logistics.
“This year will witness several public-private partnership schemes related to tourism, ports and industrial zones,” says Elbakry. “There is also a lot of buzz around the hospitality sector.”
Rail versus real estate
Railway projects make up $10.5bn, or 90 per cent, of the $11.7bn-worth of construction and transport projects in the bidding phase in Egypt.
The two largest upcoming projects are for work on the Cairo Metro: a $5bn Line 6 package and an $800m package for phase one of Line 4. Both schemes are in the bid evaluation phase.
Schemes on the Alexandria Metro are the next biggest pending awards. The National Authority for Tunnels is receiving bids for two $750m packages for the line between Abu Qir and Misr Station.
With the ongoing currency and inflation crisis, Egypt is trying to use more local resources and further reduce its imports of construction materials. The demand for foreign expertise remains strong in sectors such as rail, however.
“While the Egyptian market is rich in engineering and architectural skills, some projects like aviation, rail, ports, smart cities or water require international know-how,” says Elbakry.
The World Bank Group approved a further $400m in financing in 2022 to support railway network development in Alexandria and Cairo.
Real estate has been another booming sector in recent years, driven largely by domestic demand. Yet the outlook might be shifting now, with projects in the sector appearing to be scaling down and foreign funding showing signs of drying up.
“Egyptians rely on real estate as an investment,” says Elbakry, adding that the market is currently at a standstill because “the only people able to invest in real estate at the moment are high-income individuals”.
For the moment, “everybody is watching what the Central Bank is going to do with the currency and the exchange rate”, says Ghali.
“For construction companies, it is great to get these big contracts, but devaluations after signing contracts do not help profitability.
“It also creates a lot of insecurity because you have a lot of cash in the country that you cannot export, which makes it a very challenging environment,” he adds.
“Overall, we are bullish, but also very cautious because of the currency situation.”
MEED's March 2023 special report on Egypt also includes:
> GOVERNMENT & ECONOMY: Egypt faces up to economic reality
> POWER: Crisis dampens Egypt’s energy diversification
> WATER: Egypt turns to private sector for water
> BANKING: Interesting times for Egypt’s lenders
Exclusive from Meed
-
Kuwait awards $381m oil project23 September 2026
-
Kuwait refinery project on track for year-end completion23 September 2026
-
Contractor wins $208m Almoosa hospital MEP contract23 September 2026
-
UAE to develop integrated waste-to-resource pilot23 September 2026
-
Contractors prepare Oxagon Highway 55 bids23 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Kuwait awards $381m oil project23 September 2026
Register for MEED’s 14-day trial access
State-owned upstream operator Kuwait Oil Company (KOC) has awarded an oil project contract worth KD117m ($381m) to India’s Megha Engineering & Infrastructure (Meil).
The Supreme Purchasing Committee for Kuwait Petroleum Corporation (KPC) approved the contract last month, paving the way for the official award.
The project focuses on a water separation unit at the Al-Rawdatain facility in Kuwait.
The water separation facility will be developed at Gathering Centre 25 (GC-25), along with a pumping facility at GC-30.
The project will deliver a wide-ranging upgrade of processing and utility infrastructure, including new low-pressure separation and gas-handling equipment such as a three-phase wet separator package, a gas knock-out drum and associated low-pressure gas pipelines, as well as a high-integrity pressure protection system and a high-pressure flare.
Meil will develop the new three-phase low-pressure wet separation facility at GC-25.
The main process equipment will include two wet separator packages, each with a capacity of 150,000 barrels of liquid a day, and a low-pressure gas knock-out drum with a capacity of 53 million standard cubic feet a day, together with associated gas-handling facilities.
The facility will also incorporate an effluent water treatment and transfer system, including an effluent water balance tank equipped with microbubble flotation and induced gas flotation systems, as well as transfer pumps.
Additional GC-25 facilities will include fuel gas treatment, chemical injection, oil recovery and flare connections, along with firewater and deluge systems.
The scope also covers control and safety systems, substations, and associated civil, structural, mechanical, electrical and instrumentation works.
At GC-30, the project will focus on treated-water filtration and high-pressure injection infrastructure.
The scope includes nutshell filters and associated feed pumps with a combined capacity of approximately 500,000 barrels of water a day.
Booster and injection pumps will transfer treated effluent water to designated injection wells.
Additional facilities at GC-30 will include fuel gas treatment, sludge collection and disposal systems, oil recovery systems, control and safety systems, substations, laboratory and workshop facilities, and associated civil, structural, piping, mechanical, electrical and instrumentation works.
The project also includes transfer pipelines connecting GC-25, GC-15 and GC-30.
Meil will carry out modifications to existing tanks at GC-30, as well as process and utility tie-ins, electrical and instrumentation modifications and other infrastructure required to integrate the new facilities with KOC’s existing assets.
Meil’s responsibilities cover the project lifecycle from design and engineering through procurement, construction, testing, pre-commissioning, commissioning, start-up and performance testing.
The contract also includes operation, maintenance, repair and insurance responsibilities for the designated facilities during the applicable operations and maintenance period.
Seven companies submitted bids for the project last November.
The full list of bids was:
- Meil (India) – KD117m ($381m)
- Mechanical Engineering & Contracting Company (Kuwait) – KD130m
- Spetco (Kuwait) – KD158m
- Al-Kharafi (Kuwait) – KD164m
- China Oil HBP Science & Technology (China) – KD169m
- Alghanim International (Kuwait) – KD169m
- Jereh Oil & Gas Engineering (China) – KD191m
In October last year, KOC awarded Meil a separate contract for a project to develop a gas sweetening and recovery facility in west Kuwait.
Meil submitted the lowest bid for that tender, at KD69.2m ($225.5m), in February 2025.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19911322/main.jpg -
Kuwait refinery project on track for year-end completion23 September 2026

A $65m project to replace a substation at the Mina Al-Ahmadi (MAA) refinery is on schedule to be mechanically complete before the end of the year, according to industry sources.
The project is being executed by India’s Larsen & Toubro (L&T), which was awarded the contract in October 2024.
One source said: “This project is approaching completion and is currently on schedule to be completed before the end of the year, although it could still see delays related to the ongoing regional conflict.”
The client is state-owned downstream operator Kuwait National Petroleum Company (KNPC).
Kuwait’s Ministry of Electricity, Water & Renewable Energy (MEW) is also involved in the project and will provide final approvals and sign-off.
The scope of the project includes:
- Construction of a substation
- Installation of transformers
- Installation of medium-voltage switchgear
- Installation of low-voltage auxiliary systems
- Installation of network protection systems
- Installation of disconnecting switches
- Installation of surge arrestors
- Installation of feeder breakers and cubicles
- Installation of low-voltage A/C and D/C equipment
- Installation of battery banks and battery chargers
- Installation of related relay and control panel boards
- Installation of fire alarm and fire protection equipment
- Installation of a SCADA system
- Installation of cables
- Civil works
- Associated facilities
The current project to replace a substation at the MAA refinery closely resembles another project tendered by KNPC more than a decade ago, which L&T also won.
On 18 May 2015, KNPC signed a contract with L&T to build a new 240MW substation at the MAA refinery, valued at KD21.866m.
The new substation, known as M20, was designed to replace an existing substation that was considered old and obsolete.
Mohammed Al-Mutairi, who was KNPC’s chief executive at the time, said the substation building would be explosion-proof and use state-of-the-art control systems.
He said the station’s capacity would increase from 180MW to 240MW, supplying most of the refinery’s electricity needs.
Given the similarities between the two projects, L&T has been able to reuse some designs, creating efficiencies, according to industry sources.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19911319/main.jpg -
Contractor wins $208m Almoosa hospital MEP contract23 September 2026
Register for MEED’s 14-day trial access
Riyadh-based construction firm BEC Arabia has won a SR781m ($208m) contract for the mechanical, electrical and plumbing (MEP) works at Almoosa Hospital in Al-Khobar.
Saudi Arabia’s Almoosa Health Company awarded the contract.
The hospital complex consists of two towers: a 24-storey in-patient tower with 380 beds, and an 11-storey tower with 224 clinics and 113 additional treatment spaces.
It will be built on a 45,000-square-metre site.
A podium spanning the ninth and 10th floors will connect the two towers.
The hospital will also include parking for 1,700 cars.
BEC Arabia won the SR656m ($175m) main construction contract for the hospital in November last year.
In August 2025, MEED reported that Almoosa Health Company had announced it had secured a sharia-compliant credit facility worth SR650m ($173m) from Banque Saudi Fransi.
In a statement published on the Saudi stock exchange (Tadawul), the company said the seven-year facility would be used to support its expansion and growth strategy.
Lebanon’s Dar, US-based Perkins&Will and French design firm Pierre-Yves Rochon designed the project.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19910889/main.jpg -
UAE to develop integrated waste-to-resource pilot23 September 2026
Emirates Biotech and United Arab Emirates University (UAEU) have launched a pilot project in Al-Ain that could provide a model for larger waste-to-resource facilities.
The project involves developing the UAE’s first integrated organic-waste valorisation pilot plant, which will test whether food waste and compostable packaging can be processed together to recover resources and reduce waste sent to landfill.
Located near the UAEU campus, the 40kg-a-day facility will process organic waste to produce renewable biogas and nutrient-rich compost. The project is intended to generate technical and operating data that could support the development of larger-scale facilities.
Emirates Biotech and UAEU will design, build and operate the pilot plant as part of a two-year research project running from August 2026 to August 2028. Installation and commissioning are expected to be completed by August 2027.
The plant will combine anaerobic digestion and composting. Anaerobic digestion will convert the organic waste into renewable biogas, while the resulting digestate will be composted to produce nutrient-rich compost.
A laboratory-scale assessment will also examine the potential to convert the biogas into renewable hydrogen.
Food waste accounts for nearly 40% of daily municipal solid waste in the UAE, according to Emirates Biotech, and much of it is currently disposed of in landfills.
The pilot will therefore assess the technical and operational feasibility of recovering value from two waste streams through a single integrated process.
If successfully scaled, Emirates Biotech says an integrated organic-waste valorisation plant could reduce CO₂ emissions by 89% compared with landfilling.
The project is expected to provide a scalable and modular model for converting food waste and compostable packaging into renewable biogas and compost, with the findings intended to inform the development of larger waste-to-resource facilities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19908972/main.jpg -
Contractors prepare Oxagon Highway 55 bids23 September 2026

Contractors are preparing to submit bids on 28 September for a design-and-build contract for permanent upgrade works on Highway 55 in the kingdom’s Oxagon region.
The first phase of the project includes constructing 14 kilometres of road, with two lanes in each direction. It also includes one bridge and three interchanges.
The project duration is 22 months.
Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.
MEED reported exclusively in August 2025 that contractors had submitted responses to an expression of interest notice that Neom had issued earlier that month.
The project is expected to support cargo movement from Duba Port to other parts of the kingdom and the wider region.
Last year, Neom tested a pilot initiative by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.
In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”
The Port of Neom is located on the Red Sea near the Arar border, a key entry point into Iraq.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19907876/main.jpg