Egypt’s utility projects keep pace

11 February 2025

 

The overall value of awarded contracts in Egypt's power and water sector in 2024 doubled to $3.9bn compared to the previous year.

Water project contract awards significantly decelerated while power contract awards soared in 2024, according to the latest available data from regional projects tracker MEED Projects.

Egypt's water sector awarded just $113m-worth of contracts in 2024, compared to close to $1.3bn in 2023. Contract awards in the power sector, on the other hand, increased by more than five-fold to reach $3.8bn in 2024.

Power contract awards

Egypt awarded several solar, wind, nuclear and transmission and distribution contracts in 2024, including a 1,000MW solar photovoltaic (PV) and 100MW battery energy storage system plant to be developed by Norway's Scatec.

The Norwegian renewable energy developer also agreed to develop another 1,000MW solar PV farm with aluminium producer Egyptalum.

Red Sea Wind Energy, the project company developing a 500MW onshore wind farm in the Gulf of Suez, managed to obtain financing for a 150MW extension of the project.

Red Sea Wind Energy is a consortium of France’s Engie, which holds a 35% stake; the local Orascom Construction, which holds 25%; Japan’s Toyota Tsusho Corporation with 20%; and Eurus Energy Holdings Corporation with 20%.

According to the Japan Bank for International Cooperation, a total loan of $106m is co-financed with the London-based European Bank for Reconstruction & Development, Japan's Sumitomo Mitsui Banking Corporation and Norinchukin Bank, and France's Societe Generale.

Japan’s Nippon Export & Investment Insurance has also agreed to provide insurance for the loans.

On the nuclear power generation front, civil construction works are ongoing for the reactors of the El-Dabaa nuclear power plant in Matrouh.

Russia's Rosatom State Corporation Engineering Division appointed Northern Construction Department, a division of Titan-2 Holding, as the main contractor for the $563m civil works supporting the main and auxiliary buildings and structures of the nuclear islands for units three and four of the El-Dabaa plant.

Rosatom also appointed SC SEM, another Titan-2 Holding division, as the main contractor for the $421m package to undertake electrical installation works and foundation grounding systems for units three and four.

Other key projects awarded in 2024 include the 300MW Alexandria wind power plant and the 200MW Ras Ghareb wind farm.

Water sector

Egypt remains one of the most water-stressed states in the Middle East and North Africa region, with an annual water deficit of about 7 billion cubic metres, according to Unicef, and only 500 cubic metres of renewable water resources per capita a year, according to the Food & Agriculture Organisation.

Despite this, the procurement of water desalination public-private partnership (PPP) projects to augment the potable water supply continues to face delays.

In 2023, the Sovereign Fund of Egypt prequalified 17 teams and companies to bid for the contracts to develop up to 8.85 million cubic metres a day of renewable energy-powered desalination capacity in the North African state.

MEED reported in July 2024 that the technical consultant for these schemes was undertaking final assessments of the locations and land allocated for the first batch of projects.

However, as of February 2025, a request for proposals has yet to be issued to the prequalified developers. 

Only a handful of water sector-related contracts were awarded in 2024, including a lifting station project and a wastewater treatment scheme in Cairo and a contract to rehabilitate several canals in Dakahlia Governorate.

Outlook

In January, the developer team behind the 1,100MW Suez wind independent power project (IPP) in Egypt, which is led by Saudi utility developer Acwa Power, awarded the project's engineering, procurement and construction (EPC) contract to Beijing-headquartered PowerChina.

Located in the Gulf of Suez and the Gabal El-Zeit area, the Suez wind farm, Egypt's largest wind IPP to date, has an overall investment value of $1.2bn.

The project recently reached financial close, more than two years after the Acwa Power-led consortium signed the project agreements.

This indicates a promising change of pace, as well as gradually improving investor confidence, following years of uncertainty due to Egypt's currency crisis.

The project secured a $703.6m senior debt facility from a consortium of the following banks:

  • European Bank for Reconstruction & Development (EBRD)
  • African Development Bank 
  • British International Investment Corporation
  • German Investment Corporation
  • Opec Fund for International Development
  • Arab Petroleum Investments Corporation (Apicorp)

The senior debt funded by EBRD included a B loan structure provided by Standard Chartered Bank and Arab Bank. Acwa Power holds a 70% stake in the project, with HAU Energy owning the remaining 30%.

Meanwhile, SCZone Istithmar has invited interested firms to prequalify to bid for a contract to develop a seawater desalination plant at Egypt’s Suez Canal Economic Zone. SCZone Istithmar is wholly owned by the General Authority for the Suez Canal Economic Zone.

The finance ministry's PPP Central Unit, along with EBRD, is supporting SCZone Istithmar in the project's tender proceedings.

Overall, an estimated $42bn-worth of power contracts are in the pre-execution phase in Egypt, which is significantly more than the $5.3bn of water sector contracts that are at the same stage.

These include major projects that are in the concept or memorandum of understanding stages, such as the 2,000MW onshore wind power project that Dubai-based renewable energy investor Alcazar Energy Partners plans to develop in Egypt.

The value of power contracts under execution, at about $10.4bn, is also three times the value of known water projects that are under construction in the North African state.

While the estimated value of overall utility contracts awarded in 2024 is far from being a record high, especially compared to the $9.3bn of awarded contracts in 2015, it shows a significant improvement compared to 2023.

The volume and value of pre-execution projects also remain robust, although a significant number – including the planned seawater desalination plants – have been in the planning and design stages for some time.

A good scenario would be for Egypt to be able to maintain, if not improve, the momentum of tender proceedings and awards in 2025. The project announcement activity during the first month of this year suggests that this could be a possibility.


READ THE FEBRUARY MEED BUSINESS REVIEW

Trump unleashes tech opportunities; Doha achieves diplomatic prowess and economic resilience; GCC water developers eye uptick in award activity in 2025.

Published on 1 February 2025 and distributed to senior decision-makers in the region and around the world, the February MEED Business Review includes:

> WATER & WASTEWATER: Water projects require innovation
https://image.digitalinsightresearch.in/uploads/NewsArticle/13372346/main1310.jpg
Jennifer Aguinaldo
Related Articles
  • Firms submit Qiddiya high-speed rail EPC prequalifications

    22 April 2026

     

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s Royal Commission for Riyadh City, in collaboration with Qiddiya Investment Company (QIC) and the National Centre for Privatisation & PPP, received bids on 16 April from firms for the engineering, procurement, construction and financing (EPCF) package of the Qiddiya high-speed rail project in Riyadh.

    Firms interested in bidding for the project on a public-private partnership (PPP) basis have been given until 30 April to submit their prequalification statements, as MEED reported earlier this month.

    The prequalification notice was issued on 19 January, and a project briefing session was held on 23 February at Qiddiya Entertainment City.

    The Qiddiya high-speed rail project, also known as Q-Express, will connect King Salman International airport and the King Abdullah Financial District (KAFD) with Qiddiya City. The line will operate at speeds of up to 250 kilometres an hour, reaching Qiddiya in 30 minutes.

    The line is expected to be developed in two phases. The first phase will connect Qiddiya with KAFD and King Khalid International airport.

    The second phase will start from a development known as the North Pole and travel to the New Murabba development, King Salman Park, central Riyadh and Industrial City in the south of the city.

    In November last year, MEED reported that more than 145 local and international companies had expressed interest in developing the project, including 68 contracting companies, 23 design and project management consultants, 16 investment firms, 12 rail operators, 10 rolling stock providers and 16 other services firms.

    In November 2023, MEED reported that French consultant Egis had been appointed as the technical adviser for the project. UK-based consultancy Ernst & Young is acting as the transaction adviser, and Ashurst is the legal adviser.

    Qiddiya is one of Saudi Arabia’s five official gigaprojects and covers a total area of 376 square kilometres (sq km), with 223 sq km of developed land. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16514433/main.gif
    Yasir Iqbal
  • Qatar invites bids for major power grid expansion

    22 April 2026

    Qatar General Electricity & Water Corporation (Kahramaa) has invited bids for a major power transmission expansion project covering substations and extra-high-voltage cables.

    The bid submission deadline is 14 May.

    The engineering, procurement and construction (EPC) contract covers new substations at multiple voltage levels. It also includes the supply and installation of 400kV extra-high-voltage power cables.

    The project is divided into the following packages:

    • Substation packages S1 and S2 cover new 132/11kV substations  
    • Package S3 covers new 66/11kV substations
    • Package S4 includes a new 400/220/132kV substation, along with upgrades and modifications to existing 400kV and 220kV substations
    • Package S5 covers new 132/11kV substations and upgrades to existing 132kV and 66kV substations
    • Cable packages C1 and C2 cover 400kV cables

    The bid bond is set at QR7m ($1.9m) for the full tender, while bids for individual packages require a QR1m ($0.27m) bond per package. 

    Kahramaa stated that foreign companies not registered in Qatar may participate, subject to meeting specified conditions, including registration and certification requirements.

    It added that it may increase or decrease the scope during the contract period in line with Qatar’s Tenders & Auctions Law.

    Kahramaa procurement plan

    Kahramaa’s 2026 procurement plan includes 198 tenders with a total estimated value of QR21.4bn ($5.9bn).

    Electricity transmission projects account for QR8.9bn ($2.4bn) and include the construction of new 400/132kV substations in Al-Wukair and Al-Mashaf, as well as the expansion of 400kV substations at Ras Laffan.

    These also cover the installation of 132kV underground cables between Al-Sailiya and Al-Rayyan over a 24-kilometre route, as well as upgrades to the 400kV and 220kV networks.

    Additionally, there are 64 planned electricity distribution projects managed by the Electricity Distribution Department that cover the medium-voltage and low-voltage networks throughout Doha and the regional municipalities. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16513966/main.jpg
    Mark Dowdall
  • Riyadh awards Expo 2030 infrastructure work

    22 April 2026

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s Expo 2030 Riyadh Company (ERC), tasked with delivering the Expo 2030 Riyadh venue, has awarded two contracts for the next phase of infrastructure works at the site.

    The contracts were awarded to local firm Al-Yamama Company. Their scope covers the construction of road networks and infrastructure for water, sewage, electricity, telecommunications and electric vehicle charging.

    ERC did not disclose the contract values or project timelines.

    The awards follow ERC’s January award of an estimated SR1bn ($267m) contract for initial infrastructure works at the site to local firm Nesma & Partners. That scope covers about 50 kilometres of integrated infrastructure networks, including internal roads and essential utilities such as water, sewage, electrical and communication systems, and electric vehicle charging stations.

    The overall infrastructure works – covering the construction of main utilities and civil works at Expo 2030 Riyadh – is split into three packages:

    • Lot 1 covers the main utilities corridor
    • Lot 2 includes the northern cluster of the nature corridor
    • Lot 3 comprises the southern cluster of the nature corridor 

    The masterplan encompasses an area of 6 square kilometres, making it one of the largest sites designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport, providing direct access to various landmarks within Riyadh.

    The Public Investment Fund (PIF), Saudi Arabia’s sovereign wealth vehicle, launched ERC, a wholly owned subsidiary, in June last year to build and operate facilities for Expo 2030.


    MEED’s April 2026 report on Saudi Arabia includes:

    > COMMENT: Risk accelerates Saudi spending shift
    > GVT &: ECONOMY: Riyadh navigates a changed landscape
    > BANKING: Testing times for Saudi banks
    > UPSTREAM: Offshore oil and gas projects to dominate Aramco capex in 2026
    > DOWNSTREAM: Saudi downstream projects market enters lean period
    > POWER: Wind power gathers pace in Saudi Arabia

    > WATER: Sharakat plan signals next phase of Saudi water expansion
    > CONSTRUCTION: Saudi construction enters a period of strategic readjustment
    > TRANSPORT: Rail expansion powers Saudi Arabia’s infrastructure push

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16512261/main.jpg
    Yasir Iqbal
  • Trump confirms UAE currency swap talks

    22 April 2026

    Register for MEED’s 14-day trial access 

    US President Donald Trump has confirmed that Washington is considering a currency swap agreement with the UAE.

    During an interview with US broadcaster CNBC, Trump acknowledged that the arrangement is being considered. “It is [under consideration], but it’s been a good country. It’s been a good ally of ours,” Trump stated, noting that the request stems from a liquidity challenge rather than a solvency issue.

    Addressing the scale of the conflict’s impact on the federation, he added, “UAE got hit with 1,400 missiles. Now, fortunately, they had the Patriots, and they had a great defence … but they did get hit hard. They were hit the hardest of the group, actually.”

    The president also emphasised the strength of the bilateral economic relationship and his personal regard for the country’s leadership. “They’re really led by incredible people,” Trump told CNBC. “A year ago, I went there and I got them to invest $1tn in the United States. So, yeah, if I could help them, I would.”

    An early report by the Wall Street Journal said that high-level talks were initiated by UAE Central Bank governor Khaled Mohamed Balama, who recently met with Treasury secretary Scott Bessent and Federal Reserve officials in Washington.

    The UAE’s move is viewed as a precautionary effort to protect the dirham’s peg to the dollar and maintain its position as a global financial hub. The conflict has already inflicted significant damage on Emirati oil-and-gas infrastructure and disrupted tanker traffic through the Strait of Hormuz, which has historically been the primary source of the nation’s dollar revenues.

    While swap lines are traditionally managed by the Federal Reserve and reserved for major economies with deep ties to US markets, the Trump administration may look to the Treasury Department for a solution. Trump referenced a recent $20bn swap for Argentina facilitated by Secretary Bessent through the Exchange Stabilisation Fund as a potential model for the UAE.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16512000/main.jpg
    Colin Foreman
  • Egyptian and Chinese firms sign green hydrogen deal

    22 April 2026

    A group of Egyptian companies and China’s UEG have signed a preliminary agreement to explore developing a Mediterranean green hydrogen hub in the port city of Alexandria.

    The memorandum of understanding was signed by:

    • Abu Qir Fertilisers & Chemicals Company (Egypt)
    • AlexFert (Egypt)
    • Orascom Construction (Egypt)
    • UEG Green Hydrogen Development Holding (China)

    In a joint statement, the companies said: “The collaboration marks a significant step toward advancing Egypt’s position as a regional leader in green hydrogen and sustainable energy solutions.

    “The proposed project aims to develop a large-scale green hydrogen production facility powered by renewable energy, with integration into existing ammonia production infrastructure.”

    Under the terms of the deal, UEG and Orascom Construction will lead feasibility studies for 500MW of renewable energy generation and 480 tonnes a day (t/d) of green hydrogen production.

    Abu Qir and AlexFert will evaluate the integration of green hydrogen into ammonia production processes and support access to local resources and infrastructure.

    The renewable energy will be a mix of wind and solar, according to the statement.

    Hany Dahy, the chairman of Abu Qir Fertilisers & Chemicals Company, said: “This partnership reflects Abu Qir’s commitment to leading the transition toward low-carbon ammonia production, leveraging our existing assets while integrating green hydrogen solutions.”

    Joe Williams, the chief executive of the Green Hydrogen Organisation, said: “The announcement of this project comes at a crucial time, as geopolitical tensions in the Middle East highlight the importance of diversifying energy and fuel supply chains.

    “Developing integrated green ammonia and fertiliser production in Alexandria supports local industrial value, and strengthens long-term energy and food security.

    “As green ammonia production scales in Egypt, it can also be used as a clean shipping fuel given Egypt’s strategic maritime location.”

    The preliminary agreement establishes a framework for cooperation while the parties conduct technical, commercial and regulatory assessments.

    Subject to the outcomes, the partners intend to negotiate definitive agreements for the project’s development, according to their statement.

    Abu Qir Fertilisers established North Abu Qir for Agricultural Nutrients in May 2023 to develop a major Egyptian fertiliser project designed to produce 2,400 t/d of ammonium nitrate.

    Located next to Abu Qir Fertilisers in Alexandria, on a site formerly occupied by the Rakta paper manufacturing facility, the project is a joint venture with a capital investment of £E10bn ($190m), of which Abu Qir Fertilisers holds a 45% stake.

    The state-owned companies Egyptian General Petroleum Corporation and Egyptian Petrochemicals Holding Company hold stakes of 45% and 10%, respectively.

    The project focuses on the production of ammonia and nitric acid.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16498782/main.jpg
    Wil Crisp