Egypt’s utility projects keep pace
11 February 2025

The overall value of awarded contracts in Egypt's power and water sector in 2024 doubled to $3.9bn compared to the previous year.
Water project contract awards significantly decelerated while power contract awards soared in 2024, according to the latest available data from regional projects tracker MEED Projects.
Egypt's water sector awarded just $113m-worth of contracts in 2024, compared to close to $1.3bn in 2023. Contract awards in the power sector, on the other hand, increased by more than five-fold to reach $3.8bn in 2024.
Power contract awards
Egypt awarded several solar, wind, nuclear and transmission and distribution contracts in 2024, including a 1,000MW solar photovoltaic (PV) and 100MW battery energy storage system plant to be developed by Norway's Scatec.
The Norwegian renewable energy developer also agreed to develop another 1,000MW solar PV farm with aluminium producer Egyptalum.
Red Sea Wind Energy, the project company developing a 500MW onshore wind farm in the Gulf of Suez, managed to obtain financing for a 150MW extension of the project.
Red Sea Wind Energy is a consortium of France’s Engie, which holds a 35% stake; the local Orascom Construction, which holds 25%; Japan’s Toyota Tsusho Corporation with 20%; and Eurus Energy Holdings Corporation with 20%.
According to the Japan Bank for International Cooperation, a total loan of $106m is co-financed with the London-based European Bank for Reconstruction & Development, Japan's Sumitomo Mitsui Banking Corporation and Norinchukin Bank, and France's Societe Generale.
Japan’s Nippon Export & Investment Insurance has also agreed to provide insurance for the loans.
On the nuclear power generation front, civil construction works are ongoing for the reactors of the El-Dabaa nuclear power plant in Matrouh.
Russia's Rosatom State Corporation Engineering Division appointed Northern Construction Department, a division of Titan-2 Holding, as the main contractor for the $563m civil works supporting the main and auxiliary buildings and structures of the nuclear islands for units three and four of the El-Dabaa plant.
Rosatom also appointed SC SEM, another Titan-2 Holding division, as the main contractor for the $421m package to undertake electrical installation works and foundation grounding systems for units three and four.
Other key projects awarded in 2024 include the 300MW Alexandria wind power plant and the 200MW Ras Ghareb wind farm.
Water sector
Egypt remains one of the most water-stressed states in the Middle East and North Africa region, with an annual water deficit of about 7 billion cubic metres, according to Unicef, and only 500 cubic metres of renewable water resources per capita a year, according to the Food & Agriculture Organisation.
Despite this, the procurement of water desalination public-private partnership (PPP) projects to augment the potable water supply continues to face delays.
In 2023, the Sovereign Fund of Egypt prequalified 17 teams and companies to bid for the contracts to develop up to 8.85 million cubic metres a day of renewable energy-powered desalination capacity in the North African state.
MEED reported in July 2024 that the technical consultant for these schemes was undertaking final assessments of the locations and land allocated for the first batch of projects.
However, as of February 2025, a request for proposals has yet to be issued to the prequalified developers.
Only a handful of water sector-related contracts were awarded in 2024, including a lifting station project and a wastewater treatment scheme in Cairo and a contract to rehabilitate several canals in Dakahlia Governorate.
Outlook
In January, the developer team behind the 1,100MW Suez wind independent power project (IPP) in Egypt, which is led by Saudi utility developer Acwa Power, awarded the project's engineering, procurement and construction (EPC) contract to Beijing-headquartered PowerChina.
Located in the Gulf of Suez and the Gabal El-Zeit area, the Suez wind farm, Egypt's largest wind IPP to date, has an overall investment value of $1.2bn.
The project recently reached financial close, more than two years after the Acwa Power-led consortium signed the project agreements.
This indicates a promising change of pace, as well as gradually improving investor confidence, following years of uncertainty due to Egypt's currency crisis.
The project secured a $703.6m senior debt facility from a consortium of the following banks:
- European Bank for Reconstruction & Development (EBRD)
- African Development Bank
- British International Investment Corporation
- German Investment Corporation
- Opec Fund for International Development
- Arab Petroleum Investments Corporation (Apicorp)
The senior debt funded by EBRD included a B loan structure provided by Standard Chartered Bank and Arab Bank. Acwa Power holds a 70% stake in the project, with HAU Energy owning the remaining 30%.
Meanwhile, SCZone Istithmar has invited interested firms to prequalify to bid for a contract to develop a seawater desalination plant at Egypt’s Suez Canal Economic Zone. SCZone Istithmar is wholly owned by the General Authority for the Suez Canal Economic Zone.
The finance ministry's PPP Central Unit, along with EBRD, is supporting SCZone Istithmar in the project's tender proceedings.
Overall, an estimated $42bn-worth of power contracts are in the pre-execution phase in Egypt, which is significantly more than the $5.3bn of water sector contracts that are at the same stage.
These include major projects that are in the concept or memorandum of understanding stages, such as the 2,000MW onshore wind power project that Dubai-based renewable energy investor Alcazar Energy Partners plans to develop in Egypt.
The value of power contracts under execution, at about $10.4bn, is also three times the value of known water projects that are under construction in the North African state.
While the estimated value of overall utility contracts awarded in 2024 is far from being a record high, especially compared to the $9.3bn of awarded contracts in 2015, it shows a significant improvement compared to 2023.
The volume and value of pre-execution projects also remain robust, although a significant number – including the planned seawater desalination plants – have been in the planning and design stages for some time.
A good scenario would be for Egypt to be able to maintain, if not improve, the momentum of tender proceedings and awards in 2025. The project announcement activity during the first month of this year suggests that this could be a possibility.
READ THE FEBRUARY MEED BUSINESS REVIEW
Trump unleashes tech opportunities; Doha achieves diplomatic prowess and economic resilience; GCC water developers eye uptick in award activity in 2025.
Published on 1 February 2025 and distributed to senior decision-makers in the region and around the world, the February MEED Business Review includes:
|
> AGENDA 1: Trump 2.0 targets technology
> AGENDA 2: Trump’s new trial in the Middle East
> AGENDA 3: Unlocking AI’s carbon conundrum
> GAZA: Gaza ceasefire goes into effect
> LEBANON: New Lebanese PM raises political hopes
> WATER DEVELOPERS: Acwa Power improves lead as IWP contract awards slow
> WATER & WASTEWATER: Water projects require innovation
> INTERVIEW: Omran’s tourism strategies help deliver Oman 2040
> PROJECTS RECORD: 2024 breaks all project records
> REAL ESTATE: Ras Al-Khaimah’s robust real estate boom continues
> QATAR: Doha works to reclaim spotlight
> GULF PROJECTS INDEX: Gulf projects market enters 2025 in state of growth
> CONTRACT AWARDS: Monthly haul cements record-breaking total for 2024
> ECONOMIC DATA: Data drives regional projects
> OPINION: Between the extremes as spring approaches
|
Exclusive from Meed
-
Chinese contractor wins Saudi power and gas contracts4 August 2026
-
Contractors submit bids for key Aramco offshore tenders4 August 2026
-
Credit ratings key to infrastructure finance4 August 2026
-
AtkinsRealis confirms Sphere Abu Dhabi role4 August 2026
-
Oman opens door to direct power sales4 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Chinese contractor wins Saudi power and gas contracts4 August 2026
Chinese contractor Ningxia Power Construction has announced it has won two contracts in Saudi Arabia covering power and gas infrastructure projects with a combined value of about RMB280m ($39m).
The awards cover the third phase of cable laying and connection works for Saudi Aramco’s Master Gas System (MGS-III) project and the first phase of a 380kV transmission line for the Red Sea Aluminium project, the company said in a statement.
The MGS gas booster station contract covers electrical, instrumentation and control, communications, pre-commissioning, commissioning and defect rectification works.
The project is located northwest of Al-Mendassah in Medina Province. Construction is scheduled to last 670 days and continue through to partial mechanical completion and mechanical completion.
The Red Sea Aluminium contract involves the first phase of a 380kV overhead transmission line project.
The scope includes eight new transmission circuits. Four incoming double-circuit lines will extend about 15.2 kilometres from the connection point to the switchyard. Four outgoing double-circuit lines will run about 0.2 kilometres from the switchyard to the aluminium plant power station. Provision has also been made for two additional outgoing circuits in the future.
The Red Sea Aluminium complex is a planned integrated aluminium production facility in Yanbu Industrial City being developed by Red Sea Aluminium Holdings (RSAH), a joint venture of Innovation Global Industries, Innovation New Materials and Shandong Innovation Group
In June, RSAH awarded China’s Shandong Electric Power Construction Corporation (Sepco) an estimated $100m engineering, procurement and construction contract for a 380kV overhead transmission line project at the Red Sea Aluminium complex.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18081852/main.jpg -
Contractors submit bids for key Aramco offshore tenders4 August 2026

Register for MEED’s 14-day trial access
Contractors in Saudi Aramco’s Long-Term Agreement (LTA) pool of offshore service providers have submitted bids for five offshore tenders covering the engineering, procurement, construction and installation (EPCI) of structures at the Abu Safah, Berri, Manifa, Marjan, Safaniya and Zuluf offshore oil and gas fields in Saudi Arabia.
The tenders are numbers 167, 168, 169, 170 and 171 on Aramco’s Contract Release and Purchase Order (CRPO) system, according to sources.
Aramco issued the five CRPOs to its offshore LTA contractors in December, setting an initial bid submission deadline of 3 February.
The Saudi energy giant has since extended the bid submission deadline several times – to 31 March, 1 June, 1 July and then 30 July – to allow LTA contractors sufficient time to prepare proposals.
At the request of certain bidders, Aramco granted a final two-day extension, with LTA contractors submitting their proposals for the five CRPOs on 1 August, sources told MEED.
The basic scope of EPCI work on the tenders is as follows:
- CRPO 167 – eight jackets at the Marjan field development
- CRPO 168 – four production deck modules (PDMs) at the Abu Safah, Berri, Manifa and Safaniya fields
- CRPO 169 – three PDMs at the Marjan field development
- CRPO 170 – three PDMs at the Marjan field development
- CRPO 171 – three PDMs at the Zuluf field development
Offshore contract awards
Aramco spent almost $11bn on offshore EPCI contracts last year, more than double its capital expenditure on offshore projects in 2024, marking another year of robust upstream project spending in Saudi Arabia.
In July, Aramco selected contractors for five CRPOs – numbers 150, 157, 158, 159 and 160 – worth over $3bn. These involve EPCI work and infrastructure upgrades at the Abu Safah, Berri, Manifa, Marjan and Zuluf offshore fields.
The Saudi energy giant then picked contractors for four more CRPOs that are part of the large-scale project to expand infrastructure at the Zuluf offshore field development. The tenders are CRPOs 145, 146, 147 and 148, and their combined value is estimated to be almost $6bn.
In late December last year, Italian contractor Saipem announced securing contracts for CRPOs 162 and 165. The scope of work on CRPO 162 covers the EPCI of two rigid pipelines – a 30-inch pipeline stretching 23.98 kilometres (km) and a 20-inch pipeline, 10.23km-long; replacement of a flexible 10-inch pipeline that spans 5.1km; and modification work on topsides at the Berri and Abu Safah field developments. The duration of this contract is 32 months, Saipem said.
The scope of work on CRPO 165, lasting 12 months, includes subsea interventions at the Marjan field development and the EPCI of 300 metres of onshore pipeline and associated tie-ins.
In early January 2026, MEED reported that Aramco had selected US-based McDermott International for CRPO 166. The scope of work is understood to have been carved out of the $15bn Marjan offshore field development project, under which Aramco issued contracts for 20 EPCI packages in 2019. McDermott won the largest share of work on the project, securing an estimated $4.5bn of contracts across two packages.
The contract for CRPO 166 was single-sourced to McDermott without a competitive tendering process and issued as a change order, sources told MEED.
Aramco then awarded its second offshore contract of the year, CRPO 156, to Saipem. The scope of work covers the EPCI of a 48-inch trunkline, spanning roughly 65km offshore and 12km onshore, from the Safaniya offshore oil field to the onshore processing facility, plus associated works such as subsea hook-ups.
CRPO 156 comprises the third package in Aramco’s latest expansion phase at Safaniya – the world’s largest offshore oil field, with a production capacity of nearly 1.2 million barrels a day (b/d). Discovered in 1951, the field is located in Gulf waters approximately 265km north of Aramco’s headquarters in Dhahran.
MEED also reported that Saipem was selected by Aramco for two more tenders as part of the Safaniya field development expansion phase – CRPOs 154 and 155. The combined contract value for CRPOs 154 and 155 is estimated at $600m, sources said.
In April, state-owned China Offshore Oil Engineering Company won CRPO 161, which covers the EPCI of four gas jackets at the Arabiyah, Hasbah and Karan offshore fields.
Healthy contract award pipeline
Looking ahead, in addition to CRPOs 167-171, which are currently under bidding, Aramco is evaluating bids submitted by its offshore LTA contractors in July and August last year for at least two additional tenders.
These are CRPOs 163 and 164, relating to the EPCI of infrastructure at the Abu Safah, Berri, Karan, Marjan and Safaniya fields.
Separately, the offshore LTA contractors are also bidding for a new tender – CRPO 176 – that was issued by Aramco in May, according to sources.
The scope of work on CRPO 176 covers the EPCI of seven flexible subsea pipelines with a combined length of 17km at the Berri and Marjan offshore field developments.
Aramco’s LTA pool of offshore service providers comprises the following entities:
- Saipem (Italy)
- McDermott International (US)
- Larsen & Toubro Energy Hydrocarbon (LTEH, India) / Subsea7 (UK)
- NMDC Energy (UAE)
- Lamprell (UAE/Saudi Arabia)
- China Offshore Oil Engineering Company (China)
- Dynamic Industries (US)
- Sapura Energy (Malaysia)
- TechnipFMC (France) / MMHE (Malaysia)
- Hyundai Heavy Industries (South Korea)
In April 2025, Aramco renewed its LTAs with the following contractors, whose contracts had either lapsed or were close to expiry:
- Saipem
- McDermott International
- Larsen & Toubro Energy Hydrocarbon / Subsea7
- NMDC Energy
- Lamprell
- China Offshore Oil Engineering Company
ALSO READ: Aramco moves apace with Jafurah unconventional gas campaign
https://image.digitalinsightresearch.in/uploads/NewsArticle/18080836/main0627.jpg -
Credit ratings key to infrastructure finance4 August 2026
A global convergence in how infrastructure is financed is creating new pools of capital for Gulf projects, but the region’s non-OECD status means credit ratings will be central to unlocking the largest of these, according to Fitch Ratings.
The ratings agency said the boundaries between project finance, corporate credit and structured finance are blurring as investors seek to optimise financing for the infrastructure required to support the digital buildout and energy transition. Rising interest from institutional investors in private credit, particularly asset-backed lending, is accelerating the adoption of tailored financing structures.
For the GCC, the shift is important because of a specific regulatory constraint. Under EU Solvency II rules, unrated infrastructure debt sourced from outside the OECD cannot be treated as qualifying infrastructure. Fitch said this means that for investors seeking to access infrastructure opportunities in Saudi Arabia, India and other non-OECD markets, a credit rating is necessary for regulatory capital treatment.
The distinction is significant for a region running one of the world’s largest project pipelines. Saudi Arabia, the UAE and their neighbours are financing large-scale projects across the power, water, transport and digital infrastructure sectors, and much of the incremental capital Fitch identifies is held by regulated institutions for which ratings determine capital charges.
Insurers pivot
Insurers and pension funds are among the most significant structural sources of infrastructure capital, with global aggregated assets of about $45tn and $40tn respectively. Fitch says their increasing involvement is directly intertwined with the role of credit ratings, as cost-of-duration mismatches within solvency regimes push insurers towards liability-driven investment strategies that better match assets with liabilities.
Insurer allocations to infrastructure have historically been low, at a global median of about 1% of investment portfolios. Fitch said this is changing rapidly. It cited a Nuveen survey conducted at the end of 2025 indicating that private market infrastructure debt is set to be the most favoured destination for fixed-income allocation for the third consecutive year, with 46% of respondents planning to grow allocations over the next two years.
Sovereign wealth funds also play a major role, with over 30% of their private market fund allocations going to infrastructure, with AI-linked infrastructure the dominant sub-theme, displacing transport and logistics for new commitments. Energy transition ranked a close second, often aligned with national strategic objectives.
Larger funds with more than $100bn in assets are deploying directly and through co-investments, bypassing fund structures to reduce fees and increase control. Fitch said such funds are increasingly price-setters in large infrastructure deals, and that their strategic national mandates mean they will absorb assets at returns that pure financial investors would reject.
Regional outlook
For the GCC specifically, Fitch said additional investment is likely to support security enhancements for core infrastructure assets in response to conflict in the region, alongside upgrades to transport and social infrastructure. It expects increased renewable power capacity and enhanced oil and gas-related infrastructure.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18079923/main.gif -
AtkinsRealis confirms Sphere Abu Dhabi role4 August 2026
AtkinsRealis has confirmed it has been appointed lead design and supervision consultant on the $1.7bn Sphere Abu Dhabi project on Yas Island.
The Canadian engineering and project management firm said it will partner with local firm Alec Engineering & Contracting on the venue, which is scheduled to open in 2029.
AtkinsRealis will be responsible for overall design coordination across architecture, structural engineering and specialist immersive technologies. Alec – appointed by Abu Dhabi’s Department of Culture & Tourism (DCT Abu Dhabi) – will oversee procurement, construction delivery and project completion.
The project is being delivered under a design-and-build framework.
Alec Holdings confirmed in May that its subsidiary, Alec Engineering & Contracting, had received a letter of award for the construction contract. MEED previously reported that Alec was the selected contractor and had been working on the project during the pre-construction phase.
Sphere Abu Dhabi will be built on Yas Island on a plot between Yas Mall and SeaWorld Abu Dhabi. It will be the first Sphere venue outside the US and is expected to echo the scale of Sphere Las Vegas, with a capacity of up to 20,000, depending on configuration.
The venue will feature a fully programmable LED exosphere and a wraparound interior display capable of delivering 16K-resolution visuals, alongside beamforming audio technology that can direct sound to individual seats.
DCT Abu Dhabi is developing Sphere Abu Dhabi with US-based Sphere Entertainment.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18079715/main.jpg -
Oman opens door to direct power sales4 August 2026
Commentary
Mark Dowdall
Power & water editorOman’s Direct Sales Framework has been in place since April, but its success will ultimately depend on whether developers and large electricity users choose to adopt it.
The framework establishes a regulated process that allows qualifying private renewable energy developers to sell electricity directly to eligible consumers, instead of through Oman’s traditional single-buyer model.
For the first time, large electricity consumers have a formal mechanism to procure renewable power directly from developers, rather than relying solely on electricity supplied through the wider grid.
The recently tendered 280MW Marsa solar independent power project could provide an early indication of how the framework will be used in practice.
The project has been identified as a potential early application of the new regime, with electricity generated near Haima expected to be supplied to the Marsa LNG facility at Sohar through Oman’s transmission network.
The framework also requires grid-connection studies, network approvals and annual capacity limits, underscoring that direct sales will continue to operate within a regulated market rather than an open one.
Developers will also need customers willing to sign long-term agreements, while large electricity users will need to see clear value in procuring renewable power directly.
The scale of electricity demand expected over the coming decade will be a key factor in driving these decisions. Large industrial consumers are expected to account for a growing share of Oman’s future electricity demand as mining, green hydrogen, metals and other energy-intensive industries expand.
Oman’s procurement of utility-scale generation through competitive tenders is not slowing down either, as evidenced by recent advisory tenders for up to 4GW of solar projects targeted for commercial operation by Q2 2030.
In the meantime, for some users, securing renewable electricity directly from developers may become an attractive alternative to relying solely on the traditional supply model.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18038648/main.jpg