Egypt’s utility projects keep pace

11 February 2025

 

The overall value of awarded contracts in Egypt's power and water sector in 2024 doubled to $3.9bn compared to the previous year.

Water project contract awards significantly decelerated while power contract awards soared in 2024, according to the latest available data from regional projects tracker MEED Projects.

Egypt's water sector awarded just $113m-worth of contracts in 2024, compared to close to $1.3bn in 2023. Contract awards in the power sector, on the other hand, increased by more than five-fold to reach $3.8bn in 2024.

Power contract awards

Egypt awarded several solar, wind, nuclear and transmission and distribution contracts in 2024, including a 1,000MW solar photovoltaic (PV) and 100MW battery energy storage system plant to be developed by Norway's Scatec.

The Norwegian renewable energy developer also agreed to develop another 1,000MW solar PV farm with aluminium producer Egyptalum.

Red Sea Wind Energy, the project company developing a 500MW onshore wind farm in the Gulf of Suez, managed to obtain financing for a 150MW extension of the project.

Red Sea Wind Energy is a consortium of France’s Engie, which holds a 35% stake; the local Orascom Construction, which holds 25%; Japan’s Toyota Tsusho Corporation with 20%; and Eurus Energy Holdings Corporation with 20%.

According to the Japan Bank for International Cooperation, a total loan of $106m is co-financed with the London-based European Bank for Reconstruction & Development, Japan's Sumitomo Mitsui Banking Corporation and Norinchukin Bank, and France's Societe Generale.

Japan’s Nippon Export & Investment Insurance has also agreed to provide insurance for the loans.

On the nuclear power generation front, civil construction works are ongoing for the reactors of the El-Dabaa nuclear power plant in Matrouh.

Russia's Rosatom State Corporation Engineering Division appointed Northern Construction Department, a division of Titan-2 Holding, as the main contractor for the $563m civil works supporting the main and auxiliary buildings and structures of the nuclear islands for units three and four of the El-Dabaa plant.

Rosatom also appointed SC SEM, another Titan-2 Holding division, as the main contractor for the $421m package to undertake electrical installation works and foundation grounding systems for units three and four.

Other key projects awarded in 2024 include the 300MW Alexandria wind power plant and the 200MW Ras Ghareb wind farm.

Water sector

Egypt remains one of the most water-stressed states in the Middle East and North Africa region, with an annual water deficit of about 7 billion cubic metres, according to Unicef, and only 500 cubic metres of renewable water resources per capita a year, according to the Food & Agriculture Organisation.

Despite this, the procurement of water desalination public-private partnership (PPP) projects to augment the potable water supply continues to face delays.

In 2023, the Sovereign Fund of Egypt prequalified 17 teams and companies to bid for the contracts to develop up to 8.85 million cubic metres a day of renewable energy-powered desalination capacity in the North African state.

MEED reported in July 2024 that the technical consultant for these schemes was undertaking final assessments of the locations and land allocated for the first batch of projects.

However, as of February 2025, a request for proposals has yet to be issued to the prequalified developers. 

Only a handful of water sector-related contracts were awarded in 2024, including a lifting station project and a wastewater treatment scheme in Cairo and a contract to rehabilitate several canals in Dakahlia Governorate.

Outlook

In January, the developer team behind the 1,100MW Suez wind independent power project (IPP) in Egypt, which is led by Saudi utility developer Acwa Power, awarded the project's engineering, procurement and construction (EPC) contract to Beijing-headquartered PowerChina.

Located in the Gulf of Suez and the Gabal El-Zeit area, the Suez wind farm, Egypt's largest wind IPP to date, has an overall investment value of $1.2bn.

The project recently reached financial close, more than two years after the Acwa Power-led consortium signed the project agreements.

This indicates a promising change of pace, as well as gradually improving investor confidence, following years of uncertainty due to Egypt's currency crisis.

The project secured a $703.6m senior debt facility from a consortium of the following banks:

  • European Bank for Reconstruction & Development (EBRD)
  • African Development Bank 
  • British International Investment Corporation
  • German Investment Corporation
  • Opec Fund for International Development
  • Arab Petroleum Investments Corporation (Apicorp)

The senior debt funded by EBRD included a B loan structure provided by Standard Chartered Bank and Arab Bank. Acwa Power holds a 70% stake in the project, with HAU Energy owning the remaining 30%.

Meanwhile, SCZone Istithmar has invited interested firms to prequalify to bid for a contract to develop a seawater desalination plant at Egypt’s Suez Canal Economic Zone. SCZone Istithmar is wholly owned by the General Authority for the Suez Canal Economic Zone.

The finance ministry's PPP Central Unit, along with EBRD, is supporting SCZone Istithmar in the project's tender proceedings.

Overall, an estimated $42bn-worth of power contracts are in the pre-execution phase in Egypt, which is significantly more than the $5.3bn of water sector contracts that are at the same stage.

These include major projects that are in the concept or memorandum of understanding stages, such as the 2,000MW onshore wind power project that Dubai-based renewable energy investor Alcazar Energy Partners plans to develop in Egypt.

The value of power contracts under execution, at about $10.4bn, is also three times the value of known water projects that are under construction in the North African state.

While the estimated value of overall utility contracts awarded in 2024 is far from being a record high, especially compared to the $9.3bn of awarded contracts in 2015, it shows a significant improvement compared to 2023.

The volume and value of pre-execution projects also remain robust, although a significant number – including the planned seawater desalination plants – have been in the planning and design stages for some time.

A good scenario would be for Egypt to be able to maintain, if not improve, the momentum of tender proceedings and awards in 2025. The project announcement activity during the first month of this year suggests that this could be a possibility.


READ THE FEBRUARY MEED BUSINESS REVIEW

Trump unleashes tech opportunities; Doha achieves diplomatic prowess and economic resilience; GCC water developers eye uptick in award activity in 2025.

Published on 1 February 2025 and distributed to senior decision-makers in the region and around the world, the February MEED Business Review includes:

> WATER & WASTEWATER: Water projects require innovation
https://image.digitalinsightresearch.in/uploads/NewsArticle/13372346/main1310.jpg
Jennifer Aguinaldo
Related Articles
  • Egypt’s crisis mode gives way to cautious revival

    26 February 2026

    Commentary
    John Bambridge
    Analysis editor

    In the past three years, Egypt has faced pressures that would test any market, with collapsed staple revenues, currency volatility and escalating debt pushing it to the fiscal brink. Yet if 2023 and 2024 were years of crisis management, 2025 was a year of economic policy and geopolitical realignment.

    Egypt’s foreign policy has always been rooted in pragmatism, but mounting economic fragility has sharpened that instinct. In 2022, Cairo faced just one geopolitical fracas on its borders: Libya. Since 2023 – amid the emergence of conflicts in Sudan and Israel-Palestine – the Egyptian government has become the unwilling inheritor of instability along all three of its land borders. This has eaten into regional trade and Egypt’s stake in it.

    In response, Cairo has retrenched around a few simple principles: insulating the domestic economy from geopolitical shocks, preserving internal stability, and leveraging Egypt’s strategic location and role in the region’s security architecture to pursue a more transactional foreign policy. This is inseparable from Egypt’s quest to restore macroeconomic credibility after successive devaluations and inflationary pressure. External actors, meanwhile, see Egypt as too vital a regional lynchpin to fail; US-based funds and Gulf governments have moved quickly to help stabilise Cairo’s finances.

    Looking ahead, Egypt’s stated ambition is to move back towards a more routine, predictable monetary policy framework by 2027, with an inflation target of 7% by Q4 2026. This is as much about signalling as substance, but so far investors appear to be buying it. The oil and gas sector is showing renewed momentum, supported by upstream incentives and improved payment discipline towards international operators. Utility infrastructure contracts, meanwhile, reached a decade-high $5bn in 2025, dominated by renewable energy schemes. The water sector is also full of potential, with projects worth about $4.5bn at the prequalification or bid stage.

    Beyond energy and utilities, coastal real estate is re-emerging as a hotspot, driven by huge new masterplans across the Mediterranean and Red Sea, supported by public and private entities in the UAE, Saudi Arabia and Qatar. These foreign-backed schemes offer a welcome counterweight to the slowdown in domestically financed projects and are a boon for a construction market that has otherwise cooled.

    Egypt remains highly fiscally vulnerable. However, if Cairo can maintain disciplined economic management and continue to use foreign policy pragmatism to secure investment and financial support from its neighbours and the international community, it may yet convert today’s fiscal strain into the foundation for a genuinely investable future.

     


    MEED’s March 2026 report on Egypt includes:

    > GOVERNMENT: Egypt adapts its foreign policy approach
    > ECONOMY & BANKING: Egypt nears return to economic stability
    > OIL & GAS: Egypt’s oil and gas sector shows bright spots
    > POWER & WATER: Egypt utility contracts hit $5bn decade peak
    > CONSTRUCTION: Coastal destinations are a boon to Egyptian construction

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15717634/main.gif
    John Bambridge
  • February 2026: Data drives regional projects

    26 February 2026

    Click here to download the PDF

    Includes: Commodity tracker | Construction risk | Brent Spot Price | Construction output


    MEED’s March 2026 report on Egypt includes:

    > COMMENT: Crisis gives way to cautious revival
    > GOVERNMENT: Egypt adapts its foreign policy approach

    > ECONOMY & BANKING: Egypt nears return to economic stability
    > OIL & GAS: Egypt’s oil and gas sector shows bright spots
    > POWER & WATER: Egypt utility contracts hit $5bn decade peak
    > CONSTRUCTION: Coastal destinations are a boon to Egyptian construction

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15781010/main.gif
    MEED Editorial
  • Lessons learnt from a power plant decommissioning

    26 February 2026

     

    Al-Kamil power plant, a 280MW, gas-fired power plant in the Sharqiya region of Oman, was recently decommissioned following nearly 20 years of operations as the country’s second independent power plant.

    The plant reached commercial operation in 2002, at which time it started to supply electricity to Nama Power & Water Procurement Company under a 15-year power purchase agreement that was later extended to the end of 2021. No further extension was granted so, in 2022, the decommissioning process was initiated.

    Al-Kamil power plant was one of the first privately owned power plants in Oman to be decommissioned. The entire process took significantly longer than planned – three years compared to an initial target of 12 months. This was not unexpected, however, as there were not yet any standard processes to follow. Everything was being done for the first time, and proper procedures had to be established.

    Starting decommissioning 

    The decommissioning of a power plant is a complex process and can take as much time to complete as it takes to build a plant. It involves environmental considerations, health and safety protocols, detailed surveys, de-energisation, dismantling, demolition, waste management and the segregation and storage of secondary valuables. 

    Careful planning and management are essential to ensure that decommissioning is accomplished safely, cost-effectively and in accordance with all government environmental standards.

    Consulting on the decommissioning of Al-Kamil were Dubai’s Golden Sands Marketing Consulting (GSMC), appointed in 2021, alongside Abu Dhabi’s Sustainable Water & Power Company (SWPC) and Dubai’s Tractebel Engineering Company (TEC).

    One of the first steps that GSMC undertook was to prepare a master plan covering the entire decommissioning process (see right).

    A site investigation was undertaken by GSMC and SWPC early in the process to determine the condition of the power assets and the overall site. 

    The Al-Kamil power plant was found to have been well maintained, with no major health, safety, security and environment (HSSE) issues.

    SWPC prepared the dismantling guidelines covering all plant equipment, and these were reviewed by TEC. The guidelines covered three main phases: the shut down and isolation of all assets; the de-
    energisation process; and the dismantling of the plant equipment, its removal from site and the demolition of all remaining civil works.

    GSMC designed a sales strategy for the plant equipment, taking into consideration the secondary market for power-related equipment, as well as the scrap market in Oman. A competitive procurement process was also followed in an effort to maximise sales revenues from plant equipment.

    A separate tender was issued to appoint a demolition contractor to remove the remaining civil works, and once this work was complete, a local environmental engineering company undertook a final environmental report to demonstrate that the site was properly cleared and ready for handover to the original owner, the Housing & Urban Planning Ministry.

    Final results

    The decommissioning project went well in terms of HSSE considerations, with no fatalities, no lost-time injuries and no first aid injuries over the more than 243,000 total workhours at the site. 

    There were no material environmental spills or incidents to report, and all above- and below-ground structures were demolished and safely removed from the site in accordance with local requirements. 

    The final environmental report, completed just before handover, showed that the site was effectively in the same condition as it was when originally taken over at the start of construction.

    The decommissioning was also successful from a financial perspective, as revenues from the sale of plant equipment and diesel fuel were beyond what was required to cover the costs associated with the decommissioning process. 

    Lessons learnt 

    Many lessons were learnt during the process that can benefit future power plant decommissioning efforts in the region.

    > Notify key stakeholders early: Key stakeholders are those that have a vested interest in the project, either through ownership of certain assets on site, such as grid connection assets, or via regulation, such as the environmental authority. Many of these stakeholders take time to respond, so notifying key stakeholders early in the process can ensure that unnecessary delays are avoided.

    > Prioritise HSSE: For any future decommissioning project, HSSE must be a top priority, and this should be the focus throughout the entire decommissioning process – at all levels of work and management. 

    The site manager at Al-Kamil installed a 24/7 closed-circuit television camera, which proved to be extremely effective in terms of monitoring progress and identifying potential HSSE issues before they became an incident. This simple and cost-effective practice should be replicated for all future decommissioning projects.

    > Appoint the environmental consultant early in the process: It is advisable to appoint an environmental consultant early in the process. The consultant is needed to coordinate activities with the local environmental authority and obtain a no-objection letter or certificate, complete an environmental management report and an update of the environmental impact assessment, which includes an environmental baseline.

    Ideally, these reports and environmental authority approvals should be completed well before any work is under way at the site. This information is also useful to potential bidders for the sale of equipment, or to contractors involved in the dismantling and demolition process.

    > Submit an environmental management plan for approval: It is unlikely that any environmental authority will provide a no-objection letter or certificate without reviewing the environmental plan. It is therefore necessary to complete the plan early, prior to informing the environmental authority. This can minimise potential delays in starting the decommissioning process. 

    As a general practice, an environmental consultant should be brought on board early in the process, ideally once the overall master plan is approved by the company.

    > Establish a proactive steering committee: This was done at Al-Kamil and proved to be effective when it came to overseeing project progress and dealing with issues as they arose. Certain members of the steering committee visited the site regularly and undertook spot HSSE inspections.

    At Al-Kamil, the overall decommissioning was relatively straightforward as the plant was in a remote area. However, decommissioning a power plant in a busier location, or when part of the power plant remains in operation, is more challenging. Under these circumstances, a steering committee is vital. 

    > Set realistic delivery and completion timelines: Decommissioning a power plant is a complex process. The initial timeline to complete the process for Al-Kamil was one year, which was the best estimate at the time as there were no benchmarks or references in Oman. However, the actual completion time turned out to be three years – longer than the approximately 2.5 years it took to build the plant, from the start of construction in early 2001 to full commercial operation in July 2003.

    Realistic delivery dates should be set for contractors, suppliers and others involved in the decommissioning process. This is likely to result in better pricing, as bidders tend to factor in higher contingencies with shorter or fast-track delivery dates. More realistic delivery dates also help management to allocate staff resources and manage the decommissioning budget. 

    Finally, realistic delivery dates help to manage owner and shareholder expectations regarding project completion.

    Given the experience with Al-Kamil, a reasonable decommissioning timeline for a power plant is probably close to the actual construction timeline for the plant involved.

    > Allow time to maximise revenues from the sale of assets: The market value for Al-Kamil’s power assets was estimated at a value significantly higher than the prevailing scrap value. This was based in part on the value of similar gas turbine units, after adjusting for age, usage and other factors that affect the net market value. However, the company realised a much lower value, even after retendering the equipment sales in an effort to get a better price.

    It appears that prices close to the market rate are only achievable if there is time to find a suitable buyer. This can take many months or even years – typically a longer time than the owners of power plants wish to take. 

    Moreover, as renewables continue to penetrate the market, there is less worldwide demand for used gas turbine units. Prevailing market supply and demand conditions also have a bearing on the sale price for secondary equipment, and this factor needs to be considered.

    If time is of the essence, then power plant owners need to accept the fact that the expected revenues will likely be on the low side, although still higher than the scrap value of the assets. 


    Main image: Picture 1: Al-Kamil power plant as constructed; Picture 2: Post decommissioning 


    https://image.digitalinsightresearch.in/uploads/NewsArticle/15780944/main.gif
  • Abu Dhabi’s Enersol charts acquisitions path

    26 February 2026

     

    With about half of its $1.5bn seed capital still available to deploy, Abu Dhabi- based oil and gas drilling services firm Enersol is firmly on a growth trajectory driven by acquisitions. Since its establishment in November 2023 as a 51:49 joint venture of Adnoc Drilling – a subsidiary of Abu Dhabi National Oil Company (Adnoc Group) – and holding company Alpha Dhabi, Enersol has pursued inorganic growth as its core expansion strategy.

    Having completed four key acquisitions to date, Enersol is now targeting opportunities that will not only expand its portfolio but also enhance the value of its offerings to customers, says the company’s CEO, Dean Watson.

    “The unifying theme that we want to focus on is around the production side of what we call the well lifecycle. Why is that important? For investors it is super important because that’s where we get to the opex [operating expenditure] side, moving away from capex [capital expenditure], achieving completions and recurring revenues. So, with the potential target acquisitions, that’s where we’re focused on,” Watson explains.

    “We think that they [future acquisitions] are going to unify and anchor our current portfolio,” he tells MEED in an interview.

    “We have a lot of dry powder to spend. We have identified targets that we want to go after. We are pursuing a few targets,” Watson says, without revealing details. “With the targets we are after, we want to make sure that they’ve got a presence here in the UAE and Mena. We’re also looking for a global footprint.”

    Completed acquisitions 

    Enersol became the majority shareholder in US oil and gas drilling firm Gordon Technologies in 2024, acquiring a 67.2% stake through two transactions with a combined value of $387m. 

    Louisiana-based Gordon Technologies provides measurement while drilling (MWD) technology. MWD technology captures critical data near the drill bit and transmits it to the surface in real time without interrupting normal drilling operations.

    “Gordon Technologies are number one in North America, by a long way, in terms of market share percentage. It’s quite amazing how big that difference is in terms of how much they dominate [in] North America,” Watson says about the rationale behind Enersol acquiring the majority stake.

    Enersol then initiated a $58m transaction in July 2024 to acquire a 51% majority stake in UAE-based oil and gas services provider NTS Amega from Alpha Dhabi.

    “NTS Amega is a manufacturing business with a rental component,” Watson explains. “It manufactures a product and rents out a portion of it.  What excites us about NTS Amega is its potential to serve as our manufacturing backbone, helping to strengthen and promote our in-country value, as it is based and originated in the UAE.”

    In August of the same year, Enersol started a transaction to fully acquire US-headquartered EV Holdings Limited, paying $45m to UK-based private equity firm Dunedin for 100% of the company’s shares.

    EV Holdings has a significant technology portfolio, with more than 100 pieces of intellectual property, primarily patents. It is a highly technical company that generates vast amounts of data, Watson explains.

    Aligned with Enersol’s focus on technology leadership, EV is the number one provider of downhole camera technology in oil field services. It therefore meets what Watson calls “the key investment criteria we are looking for”.

    In November 2024, Enersol entered into a $223m deal to acquire a 95% equity stake in US-based Deep Well Services (DWS). 

    The acquisition, which was completed in the first quarter of 2025, gives Enersol access to DWS’s hydraulic completion units, complemented by its data analytics software, BoreSite, as well as accredited training programmes designed to enhance operational safety and efficiency.

    We have a lot of dry powder to spend. We have identified targets that we want to go after. We are pursuing a few targets
    Dean Watson, Enersol

    Securing contracts

    Enersol is seeking to leverage the suite of capabilities and technologies it has acquired to secure oil field services contracts in the UAE and the wider regional market, Watson says.

    “We’re very excited about being part of the Adnoc ecosystem. Gordon Technologies, through Turnwell, has just completed its first batch of wells and is currently working on the Turnwell project,” the Enersol CEO says, adding: “Gordon is the MWD provider on that project.”

    Adnoc Drilling signed a term sheet in 2024 to enter into a partnership with the Middle East arm of US oil field services provider SLB and US firm Patterson-UTI International Holdings to form a new company called Turnwell Industries.

    In May of that year, Adnoc Drilling was awarded a major contract, worth about $1.7bn, by its parent Adnoc Group, to provide drilling and associated services for the recovery of unconventional oil and gas resources. Work on this contract is being executed by Turnwell. The broad scope of work on the contract covers drilling and appraisal of 144 unconventional oil and gas wells.

    Separately, DWS won its first contract from Malaysia’s state energy company Petronas last November for deploying its hydraulic completion units and BoreSite systems to support a 12-well unconventional programme in Abu Dhabi.

    Watson is optimistic about Enersol securing additional work in Abu Dhabi from Adnoc Drilling. Beyond its home market, the company is “in active discussions and negotiations with our Saudi joint-venture partner on a major scope of work with Saudi Aramco,” he says.

    Enersol’s growing portfolio and its push to secure contracts across the region also place the company in competition with established oil field services majors. On that subject, Watson concludes: “I believe our offering is unique and does not necessarily compete directly with companies such as SLB or Weatherford. 

    “We will identify a niche that fits between the major players and deliver parallel value through our differentiated offering.” 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15780622/main.gif
    Indrajit Sen
  • Post tender clarifications begin for Riyadh Metro Line 7

    26 February 2026

     

    The Royal Commission for Riyadh City (RCRC) has started post-tender clarifications with bidders for a contract covering the design and build of Riyadh Metro’s Line 7.

    Contractors submitted their commercial proposals on 31 January, as MEED reported.

    The project involves constructing a metro line linking the Qiddiya entertainment city development, King Abdullah International Gardens, King Salman Park, Misk City and Diriyah Gate.

    The total length of the line will be about 65 kilometres (km), of which 47km will be underground and 19km will be elevated.

    The line will have 19 stations, 14 of which will be built underground and five above ground.

    According to sources close to the project, the consortium formation is as follows:

    • Alstom (France) / Webuild (Italy) / Nesma (local) / China Harbour Engineering Company
    • Siemens (Germany) / FCC (Spain) / Orascom Construction (Egypt) / Shibh Al-Jazira Contracting Company (local)
    • Hitachi Rail (Japan) / L&T (India) / Albawani (local) / Kalyon (Turkiye) / Cengiz (Turkiye) 
    • CRRC (China) / Mapa (Turkiye) / Limak (Turkiye)

    Earlier this week, MEED exclusively reported that firms are preparing bids for a contract covering the project management consultancy services for the construction of Riyadh Metro Line 7.

    MEED understands that RCRC has allowed firms until March to submit their proposals.

    Riyadh Metro’s first phase features six lines with 84 stations. The RCRC completed the phased roll-out of the Riyadh Metro network when it started operating the Orange Line in January this year.

    Construction has also begun on the next phase of Riyadh Metro, the extension of Line 2.

    In July last year, MEED exclusively reported that RCRC had awarded an estimated $800m-$900m contract for the project.

    The contract was awarded to the Arriyadh New Mobility Consortium, led by Italy’s Webuild. 

    The group also includes India’s Larsen & Toubro, Saudi Arabia’s Nesma & Partners and France’s Alstom.

    Line 3, also known as the Orange Line, stretches from east to west, from Jeddah Road to the Second Eastern Ring Road, covering a total distance of 41km. 

    The line spans 8.4km, of which 1.3km is elevated and 7.1km is underground. It includes five stations – two elevated and three underground.

    It will run from the current terminus of Line 2 at King Saud University (KSU) and continue to new stations at KSU Medical City, KSU West, Diriyah East and Diriyah Central – where it will interchange with the planned Line 7 – before terminating at Diriyah South.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15780624/main.jpg
    Yasir Iqbal