Egypt’s economy gets its mojo back
14 February 2025

Egypt’s economy is in stronger fettle than for at least a couple of years, and there is a sense of optimism about how things will transpire in 2025, even as recent pronouncements from the White House about Gaza weigh on policymakers in Cairo.
In a manifestation of that upbeat economic sentiment, Egypt in January staged a return to the international debt capital market for the first time in two years, with a $2bn issuance that was five-times oversubscribed. That was a straw in the wind that foreign investors’ concerns over the economy are finally abating.
After a battering inflicted on Egypt’s economy last year, when economic growth slipped to 2.4%, reflective of a weak currency, surging inflation and tougher public spending restrictions, analysts see a recovery in play that will drive stronger GDP growth in the coming year.
One key contributor to this improvement is the recovery in Suez Canal receipts, which dropped by about three-quarters last year after the Houthi attacks on shipping in the Red Sea. That loss of $7bn in revenues shaved off more than a percentage point from Egypt’s overall GDP growth rate, noted Moody’s Investors Service.
Growth dynamics are now improving, even if events in the region remain in flux. According to Capital Economics, there was a rise in real GDP growth to 3.5% in Q3 2024, up from 2.4% in Q2 2024. The manufacturing, transport and storage, and finance sectors were the key drivers of that improvement.
Egyptian banks are feeling the positive impact. Credit growth is reviving, with bank lending to the non-government sector growing by 2.9% in October 2024 – the fastest pace in two years.
Operating conditions for Egyptian lenders will continue improve in 2025, according to Fitch Ratings, underpinned by a sharp fall in inflation, along with an expected broadly stable currency, improved investor confidence and healthy foreign currency liquidity conditions. This should also support lower interest rates as inflation declines.
Foreign capital injection
Douglas Winslow, senior director at Fitch Ratings, says the improvement in market sentiment follows a combination of factors and is also seen in the return of non-resident inflows totalling more than $10bn into the domestic debt market since early last year.
Egypt's external finances have benefitted from Gulf state interventions, notably the UAE sovereign wealth fund ADQ’s major foreign investment in the Mediterranean resort of Ras El-Hekma, which was announced in 2024.
That deal injected $24bn of new foreign currency into Egypt, the remaining $11bn converting existing UAE foreign currency deposits held at the Central Bank of Egypt (CBE).
Saudi Arabia’s Public Investment Fund has also committed to invest $5bn in Egypt’s economy.
Such investments, eased by the weaker Egyptian pound – rendering assets more affordable – will also help to address Egypt’s dollar shortages, and assuage residual investor concerns about default risk.
“The huge Ras El-Hekma investment was a very important factor in the turnaround, and Fitch projects further foreign direct investment (FDI) of $7bn a year above the pre-ADQ position. The lion’s share of that is GCC investment,” says Winslow.
The $24bn of fresh foreign currency puts Egypt in a better place to move to a more flexible exchange rate.
The combination of these factors has enabled a rapid rebuilding of Egypt’s external coffers, which was the key risk facing near-term external financing. Fitch forecasts FDI to average $16.5bn across the fiscal year ending June 2025 and fiscal year 2026, with new investment from Saudi Arabia having an impact.
Alongside the Gulf support has come multilateral financing, including from Europe. Since March 2024, an $8bn IMF Extended Fund Facility and a €7.4bn ($7.64bn) three-year EU support package have been unlocked.
Together, these capital injections will also help cover Egypt’s current account deficit, which widened to 5.4% of GDP in 2024. Inflation is also headed in the right direction, after reaching a peak of 36% in February 2024. The expectation is that inflation will have more than halved by the end of financial year 2025-26.
Strong growth upside
Looking ahead, the more optimistic prognosis foresees GDP growth accelerating to 5% in the current fiscal year. Others are more circumspect, noting the recent recovery in Suez Canal receipts is very partial and that the government still needs to implement structural economic reform measures.
Fitch Rating’s forecast for GDP growth is 4% for fiscal year 2025. A pickup in growth is already detectable.
“Growth was 3.5% in Q1 of the current fiscal year and we expect it accelerates to just above 5% in fiscal year 2026, close to our assessment of the potential and rate of the Egyptian economy. That’s partly due to further falling inflation and a positive impact on real income,” says Winslow.
Despite these stronger macro metrics, the wider credit assessment is still constrained, due to relatively weak external finances. While the central bank can call upon larger foreign exchange reserves to support the currency, Capital Economics has warned that a return to a heavily managed exchange rate would worry investors and may also call into question IMF and Gulf willingness to provide further financing.
“The IMF programme does contain some wider structural reform measures to improve private sector competitiveness, but in our view, they're not particularly far-reaching, and we're not seeing really sizeable momentum in terms of delivering in this area,” Winslow says.
There is a need for measures to stimulate private sector growth and also to improve the competitiveness of the economy, support the trade balance and reduce the current deficit over the medium term.
“A better track record of ongoing political commitment to curbing off-budget spending pressures would also help Egypt’s rating,” says Winslow.
As to the potential for regional events to upset things, Egypt's credit fundamentals are at least better insulated from further geopolitical stress.
This, in turn, should give comfort to commercial banks in Egypt. Fitch upgraded the long-term issuer default ratings of all rated banks in November 2024, following the upgrade of Egypt’s sovereign rating.
There are other things that will need to be seen for the Egyptian economy’s recovery to sustain itself over the long-term.
“From a credit perspective, the composition of growth is equally important,” says Winslow.
“What we’ve seen in the past is that very large government off-budget megaprojects have not just led to weaker public finances, they've also contributed to external financing stress. So, what's particularly important is that the recent steps to try and better monitor and contain these off-budget infrastructure projects continues.”
MEED’s March special report on Egypt also includes:
> GOVERNMENT: Egypt is in the eye of Trump’s Gaza storm
> POWER & WATER: Egypt’s utility projects keep pace
> CONSTRUCTION: Coastal city scheme is a boon to Egypt construction
READ THE FEBRUARY MEED BUSINESS REVIEW
Trump unleashes tech opportunities; Doha achieves diplomatic prowess and economic resilience; GCC water developers eye uptick in award activity in 2025.
Published on 1 February 2025 and distributed to senior decision-makers in the region and around the world, the February MEED Business Review includes:
|
> AGENDA 1: Trump 2.0 targets technology
> AGENDA 2: Trump’s new trial in the Middle East
> AGENDA 3: Unlocking AI’s carbon conundrum
> GAZA: Gaza ceasefire goes into effect
> LEBANON: New Lebanese PM raises political hopes
> WATER DEVELOPERS: Acwa Power improves lead as IWP contract awards slow
> WATER & WASTEWATER: Water projects require innovation
> INTERVIEW: Omran’s tourism strategies help deliver Oman 2040
> PROJECTS RECORD: 2024 breaks all project records
> REAL ESTATE: Ras Al-Khaimah’s robust real estate boom continues
> QATAR: Doha works to reclaim spotlight
> GULF PROJECTS INDEX: Gulf projects market enters 2025 in state of growth
> CONTRACT AWARDS: Monthly haul cements record-breaking total for 2024
> ECONOMIC DATA: Data drives regional projects
> OPINION: Between the extremes as spring approaches
|
Exclusive from Meed
-
Algeria extends bid deadline for stalled power plant30 April 2026
-
Dewa announces new record for power reliability30 April 2026
-
Riyadh tenders PMC deal for major sports arena30 April 2026
-
-
Iraq sets up commission for $5bn pipeline project30 April 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Algeria extends bid deadline for stalled power plant30 April 2026
Algeria’s state-owned electricity and gas utility Sonelgaz has extended a deadline for contractors to submit expressions of interest for the construction of the 1.2GW Djelfa combined-cycle power plant.
The project is being procured through Sonelgaz’s power generation subsidiary, Societe Algerienne de l’Electricite et du Gaz – Production de l’Electricite (SPE).
In March, MEED reported that the utility was seeking contractors to complete works at the existing Djelfa plant, including the remaining construction, the supply of missing equipment and the assessment of installed equipment.
The original bid submission deadline for prequalification was 7 April. The new deadline is 5 May.
The tender is open to both local and international companies, and will be conducted in three phases: prequalification, preliminary technical assessment, and final technical and financial submission.
The retender follows earlier plans to complete the project through a Chinese consortium comprising China Energy Engineering Group Company, Northwest Electric Power Design Institute and Anhui Electric Power Construction Company.
This proposal was made after Spanish contractor Duro Felguera halted work on the project in June 2024.
According to MEED Projects, construction works had progressed to 72% at the time of the suspension.
It is understood that an agreement in principle was then reached to transfer the remaining works to the Chinese group after the Spanish firm entered a pre-bankruptcy phase in December 2024.
A company statement at the time said: “The Chinese group is committed to completing the plant construction, with commissioning scheduled to start in the ninth month following the final agreement.”
However, in October 2025, it was revealed that the attempt to transfer the project to a consortium of Chinese companies had failed, leaving the Spanish firm with an official demand to pay €413m in compensation to Sonelgaz.
This was revealed via a lengthy report containing a restructuring plan sent by Duro Felguera to creditors in Spain and the Madrid Financial Markets Authority.
Gas-fired power plants
Located in Djelfa province, the project remains a key part of Algeria’s power generation expansion plans.
Sonelgaz has been seeking contractors to build a separate 1.2GW combined-cycle gas-fired power plant in Aldrar since last April.
The most recent deadline extension was 29 April.
According to recent reports, Algeria has also begun construction of a power generation plant in El-Aouinet, with a total installed capacity of 1,406MW.
The combined-cycle gas turbine plant is being developed in partnership with China National Electric Engineering Company.
Gas-fired combined-cycle plants continue to account for the majority of Algeria’s electricity generation capacity. Data from MEED Projects indicates that more than 5,000MW of oil- and gas-fired power capacity is currently in the execution phase.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16623787/main.jpg -
Dewa announces new record for power reliability30 April 2026
Dubai Electricity & Water Authority (Dewa) has announced that it set a new world record for the lowest electricity customer minutes lost (CML), at 0.82 minutes a year in 2025.
The figure is equivalent to about 49 seconds of annual outage per customer. It improves on the utility’s previous record of 0.94 minutes in 2024, a reduction of around 13%.
Dewa said it has reduced CML in Dubai from 6.88 minutes a year in 2012 to 0.82 minutes in 2025, significantly lower than the average of about 15 minutes recorded by leading electricity utilities in the European Union.
The smart grid is a central component of Dewa’s strategy to improve reliability and efficiency. The programme is being implemented with total investments of AED7bn up to 2035.
One of the key initiatives of the programme is the Automatic Smart Grid Restoration System, which enables remote, round-the-clock control and monitoring.
Dewa currently has tenders out for several power and water infrastructure projects in the emirate. These include at least four Glass Reinforced Epoxy (GRE) water transmission pipeline projects.
According to regional projects tracker MEED Projects, Dewa awarded $1.1bn-worth of new power and water contracts in 2025. Contract awards had previously reached $2.6bn in 2024, and $4bn in 2024.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16623721/main.jpg -
Riyadh tenders PMC deal for major sports arena30 April 2026

Saudi Arabia’s Sports Boulevard Foundation has tendered a contract inviting firms to bid for project management consultancy (PMC) services for the Global Sports Tower in the Athletics District of the Sports Boulevard development in Riyadh.
The tender was issued on 8 April, with a bid submission deadline of 10 May.
The 130-metre-tall Global Sports Tower will cover an area of 84,000 square metres and will include more than 30 sports facilities. The tower will feature the world’s tallest indoor climbing wall at 98 metres and a 250-metre running track.
Earlier this week, MEED reported that the Sports Boulevard Foundation is preparing to award the main construction contract for the Global Sports Tower. MEED understands that bid evaluation has reached an advanced stage and the contract is likely to be awarded by the end of May.
MEED reported in May last year that design work on the tower had been completed. Saudi Arabia’s Crown Prince Mohammed Bin Salman Bin Abdulaziz Al-Saud approved the designs in 2024.
The Sports Boulevard development runs across Riyadh from east to west and, once complete, is set to be the world’s longest park spanning more than 135 kilometres.
The development will be spread across several districts, including Wadi Hanifah, Arts, Urban Wadi, Entertainment, Athletics and Eco, as well as Sands Sports Park.
The large-scale project aims to transform central Riyadh – currently dominated by major highways – into a recreational corridor.
Sports Boulevard, which will feature 4.4 million sq m of public realm and landmark buildings, will also be home to the Centre for Cinematic Arts and a 2,000-seat amphitheatre.
The development will provide more than 2.3 million sq m of mixed-use commercial, residential, and retail assets, along with sports facilities around the park, known as Linear Park.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16622287/main.jpeg -
Contractors submit Saudi Arabia phosphate rail track bids30 April 2026

Saudi Arabian Railways (SAR) received bids from contractors on 27 April for a multibillion-riyal tender to double the tracks on the existing phosphate transport railway network connecting the Waad Al-Shamal mines to Ras Al-Khair in the kingdom’s Eastern Province.
The tender – covering the second section of the track-doubling works and spanning more than 150 kilometres (km) – was issued on 9 February.
This follows SAR receiving bids on 1 February for the project’s first phase, which spans about 100km from the AZ1/Nariyah Yard to Ras Al-Khair.
The scope includes track doubling, alignment modifications, new utility bridges, culvert widening and hydrological structures, as well as the conversion of the AZ1 siding into a mainline track. It also includes support for signalling and telecommunications systems.
The tender notice was issued in late November.
Switzerland-based engineering firm ARX is the project consultant.
MEED understands that these two packages are the first of four that SAR is expected to tender for the phosphate railway line. Other packages anticipated to be tendered shortly include the depot and systems packages.
In 2023, MEED reported that SAR was planning two projects to increase its freight capacity, including an estimated SR4.2bn ($1.1bn) project to install a second track along the North Train Freight Line and construct three new freight yards.
Formerly known as the North-South Railway, the North Train is a 1,550km-long freight line running from the phosphate and bauxite mines in the far north of the kingdom to the Al-Baithah junction. There, it diverges into a line southward to Riyadh and a second line running east to downstream fertiliser production and alumina refining facilities at Ras Al-Khair on the Gulf coast.
Adding a second track and the freight yards will significantly increase the network’s cargo-carrying capacity and facilitate increased industrial production. Project implementation is expected to take four years.
State-owned SAR is also considering increasing the localisation of railway materials and equipment, including the construction of a cement sleeper manufacturing facility.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16622526/main.jpg -
Iraq sets up commission for $5bn pipeline project30 April 2026
Iraq is setting up a high-level commission to oversee the development of the planned $5bn Basra-Haditha crude oil pipeline project.
The decision was made at a meeting held on 26 April, attended by Prime Minister Mohammed Shia Al-Sudani and the Minister of Petroleum Hayyan Abdul Ghani Al-Sawad, as well as other officials and consultants.
The commission will be chaired by the undersecretary of the Oil Ministry and include advisers to the prime minister, along with director-generals from the Oil Ministry and the Industry & Minerals Ministry.
Al-Sudani said the pipeline project will increase flexibility in transporting crude oil to the Turkish port of Ceyhan, as well as the Syrian port of Baniyas and Jordan’s port of Aqaba.
The pipeline is also expected to strengthen supply to refineries in central and northern Iraq and support higher domestic refining output.
The meeting also approved allocating $1.5bn to the project this year, with funding provided through the Iraq-China oil-for-infrastructure mechanism, according to a statement issued by the Petroleum Ministry.
Earlier this month, Iraq’s Council of Ministers approved amendments allowing the Oil Ministry to directly invite specialised companies to bid for the 685-kilometre pipeline.
The pipeline is expected to have a capacity of up to 2.25 million barrels a day.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16621546/main.jpg
.gif)