Egypt approves construction permit for third nuclear unit

3 April 2023

The Egyptian Nuclear and Radiological Regulatory Authority (ENRRA) has agreed to grant the construction permit for the third unit of the nuclear power plant in El-Debaa.

The authority’s board of directors, headed by Sami Shaaban, made the decision on 29 March.



In January 2022, Egypt’s Nuclear Power Plants Authority (NPPA) applied for a construction permit for units three and four of the El-Dabaa nuclear power plant. 

The NPPA submitted the licensing documentation for the plant’s first two units to ENRRA in June 2021. It then granted the construction permit for the first unit in June 2022 and the construction permit for the second unit in October 2022.

MEED reported in November last year that South Korea’s Doosan Enerbility had begun mobilising teams to construct the turbine island for the El-Debaa nuclear power plant.

Earlier that month, the company signed a contract valued at $1.2bn with state-owned South Korea Hydro & Nuclear Power (KHNP), a subsidiary of Korea Electric Power Corporation (Kepco), for the project.

The main construction works for the first tower on the turbine island are expected to commence in the third quarter of 2023.  

The package is a sub-contract for the $2.2bn package that KHNP signed in August 2022 for the project after emerging as the sole bidder for the main and auxiliary buildings and structures of the turbine islands for the units, to be built between 2023-29.

The scope of the Doosan Enerbility contract entails the construction of 82 buildings and structures, covering the turbine building, water treatment and air conditioning systems. It includes installing the turbines and generators.

The first reactor at the plant is scheduled to be operational in 2026.

The facility, located in the Matrouh province on Egypt’s Mediterranean coast, will have four units, each with a capacity to generate 1,200MW.

Egypt and Russia signed the initial inter-governmental agreement for the North African state’s first nuclear facility in November 2015.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10727332/main.jpg
Colin Foreman
Related Articles
  • Dubai plans battery energy storage

    29 February 2024

    State utility Dubai Electricity & Water Authority (Dewa) has started planning for the next phase of the Mohammed Bin Rashid (MBR) Solar Park project in Dubai.

    According to a source familiar with the plans, the state utility is reviewing plans and considering a battery energy storage system as part of the solar park complex's seventh phase.

    Dewa and Abu Dhabi Future Energy Company (Masdar) recently reached financial close for the 1,800MW sixth phase of the MBR solar park.

    The independent power producer (IPP) project is expected to cost up to AED5.51bn ($1.5bn).

    According to Masdar, the lending group to the project includes:

    • Abu Dhabi Commercial Bank (local)
    • Commercial Bank of Dubai (local)
    • First Abu Dhabi Bank (local)
    • HSBC (UK)
    • Standard Chartered Bank (UK)
    • Abu Dhabi Islamic Bank (local)
    • Warba Bank (local)

    Once completed in 2026, the 1,800MW sixth phase of the solar park will increase its total production capacity to 4,660MW.

    The MBR Solar Park project’s phases and construction statuses are as follows:

    • 13MW solar PV phase one: Completed in 2013
    • 200MW solar PV phase two: Commissioned in 2017
    • 800MW solar PV phase three: Commissioned in 2020
    • 950MW hybrid CSP/solar PV phase four: Inaugurated in 2023
    • 900MW solar PV phase five: Commissioned in 2023
    • 1,800MW solar PV phase 6: Under construction

    The state utility aims to have around 27% of the generation mix sourced from clean energy sources by 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11557711/main.gif
    Jennifer Aguinaldo
  • UK firm lands lead role on world’s largest airport

    29 February 2024

     

    Register for MEED’s guest programme 

    UK-based Mace has won the delivery partner role on the world’s largest airport project, the King Salman International airport (KSIA) scheme in Riyadh.

    MEED reported in November last year that international firms were competing for the role. 

    Delivery partner roles typically involve assisting the project client with the development of the project. This includes project management, design management, cost consulting and procurement advice.

    Mace has extensive experience on airport projects and has worked on London’s Heathrow airport for over 30 years. In 2023, it was appointed as the delivery partner on three major infrastructure improvement projects at Heathrow.

    For KSIA, Foster + Partners, also based in the UK, won the competition to design the masterplan. The architectural firm is now working on the concept designs for the airport’s buildings, while US-based Jacobs is working on the infrastructure design for the airport.

    The project covers an area of about 57 square kilometres, allowing for six parallel runways, and will include the existing terminals at King Khalid International airport (KKIA). It will also include 12 sq km of airport support facilities, residential and recreational facilities, retail outlets and other logistics real estate. It is the largest airport project in the world, according to GlobalData.

    If the project is completed on time in 2030, it will become the world’s largest operating airport in terms of passenger capacity.

    The airport aims to accommodate up to 120 million passengers by 2030 and 185 million by 2050. For cargo, the goal is to process 3.5 million tonnes a year by 2050.

    There were contract awards for construction work at KKIA last year. In June, a joint venture of Turkiye’s IC Ictas and the local Al Rashid Trading & Contracting was awarded the contract to complete the renovation of Terminal 1 and Terminal 2. The joint venture finished renovating terminals 3 and 4 earlier this year.

    Aviation strategy

    Saudi Arabia plans to invest $100bn in its aviation sector. Riyadh’s Saudi Aviation Strategy, announced by the General Authority of Civil Aviation (Gaca), envisages tripling Saudi Arabia’s annual passenger traffic to 330 million travellers by 2030.

    It also aims to increase air cargo traffic to 4.5 million tonnes and raise the country’s total air connections to more than 250 destinations. 

    Global industry

    The global airport projects pipeline, as tracked by GlobalData, is worth $580.4bn, slightly less than the $588.4bn pipeline recorded in Q4 2023.

    The global pipeline is dominated by projects in the advanced stages of development, with 78.2% of projects in the pre-execution and execution phases. This amounts to $453.7bn in total value.

    Of this amount, $329bn is in the execution stage and $124.7bn is in the pre-execution stages of design, tender, and engineering, procurement and construction (EPC) award. Projects in the early stages account for a relatively small share, with 21.8% of the pipeline by value, reflecting projects in the pre-planning stage (announcement and study) and planning stages.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11559421/main.jpg
    Colin Foreman
  • Amea Power starts Egypt hydrogen engineering

    29 February 2024

    A global engineering services company has started pre-front-end engineering (feed) works for an integrated green hydrogen-based ammonia production facility in Egypt.

    Dubai-based clean energy developer and investor Amea Power is the developer of the project, located in the coastal town of Ain Sokhna in the Suez Governorate.

    An engineering, procurement and construction (EPC) company has also started detailed engineering works for the scheme, according to the company's project development manager, Ignacio Carreras.

    Carreras said Amea Power is working with a hydrogen electrolyser and ammonia licensor, which are both "tier-1 companies".

    "Other contractors for the wind and solar measurement campaign are also being mandated as we speak," Carreras told MEED on the sidelines of the ongoing World Hydrogen Mena summit in Dubai.

    Amea Power aims to reach a financial investment decision (FID) by the first quarter of 2026. "We are progressing as planned and will have a very well-defined project ready to go for financing in the first quarter of 2025," the executive said.

    The project's feasibility study was completed last year, as MEED reported.

    In November, the company doubled the intended green ammonia production capacity of the project to 800,000 tonnes a year (t/y).

    The proposed integrated project will involve the development of 2,000MW of renewable energy plants and 1,000MW of electrolysers to produce green hydrogen.    

    The project was first announced in April 2022 with an initial plan to produce 390,000 t/y of green ammonia.

    The company subsequently decided to double the planned capacity and output of the project to meet market demand, with a current target to produce 800,000 t/y of green ammonia.

    Amea Power signed a memorandum of understanding for the project with the General Authority for the Economic Zone of the Suez Canal, the Sovereign Fund of Egypt, the Egyptian Electricity Transmission Company and the New & Renewable Energy Authority in 2022.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11559285/main.gif
    Jennifer Aguinaldo
  • Kepco to divest stakes in Jordan energy assets

    29 February 2024

    South Korea’s Korea Electric Power Corporation (Kepco) has started the process of partially divesting its stakes in two power plants in Jordan.

    Kepco plans to divest 40% stake and shareholder loans in the 89MW Fujeij wind power plant, in which it has a 100% direct investment.

    It also intends to divest 36.25% of the 80% stake and shareholder loans it maintains in Jordan's 373MW Qatrana gas-fired combined cycle power.

    Kepco has appointed KPMG Korea as its sell-side adviser for the transaction, which offers options for individual sales or a package deal for the two power plants.

    The utility developer expects to receive letters of intent from interested bidders by 3 April.  It aims to conclude the sale within the first half of 2024.

    “This move aligns with Kepco’s  commitment to restructure its overseas assets to optimise its global business portfolio and move forward with energy transition, developing low-carbon and eco-friendly new businesses, such as hydrogen and ammonia, renewable energy and grid,” the firm said.

    The Fujeij wind and Qatrana CCPP plants became in 2019 and 2011, and have delivered Ebitda margins of 85% and 70%, respectively.

    Fujeij wind and Qatrana CCPP are backed by 20- and 25-year power-purchase agreements (PPA) with Jordan’s National Electric Power Company (Nepco), “ensuring a steady revenue stream until 2039 and 2035, respectively”.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11557646/main.jpg
    Jennifer Aguinaldo
  • Roshn has 50,000 homes under construction

    28 February 2024

    Register for MEED's guest programme 

    Saudi gigaproject developer Roshn is busy building residential units while diversifying its business at the same time.

    “We’ve got 50,000 homes in construction,” said David Grover, CEO of Roshn, speaking on stage at McKinsey’s Global Infrastructure Initiative in Dubai on 28 February.

    Roshn, which was founded in 2019, builds homes that are sold to local Saudi nationals.

    “We sold $2.5bn-worth of homes last year and collected the cash,” said Grover. “That shows how quickly Roshn has come from setting up a company with only 35 to 40 people and now having 1,500.”

    The houses are part of the community housing gigaproject that Roshn is developing across the kingdom. “Our communities might have between 25,000 and 50,000 homes. That’s a city of 250,000 people,” he said.

    As Roshn builds homes, it is also diversifying its business by establishing units that will develop other real estate assets and social infrastructure and provide related services for the property businesses.

    “The business has morphed and changed a lot,” said Grover. “We’ve become a multi-faceted real estate developer. So now we’re developing 2 million square metres of commercial space. We have 1,000 schools and 1,000 mosques. We are delivering substations, sewage treatment plants, and six to eight-lane highways. We also have a dotcom business.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11556607/main.gif
    Colin Foreman