Dukhan solar award drives Qatar’s utility sector

13 January 2026

 

South Korea’s Samsung C&T won a contract with state-owned petroleum firm QatarEnergy in September to build a 2,000MW solar photovoltaic (PV) power plant in Dukhan, accelerating the country’s renewable generation strategy.

Once completed, the project will double Qatar’s solar generation capacity and is expected to supply up to 30% of the country’s total peak electricity demand.

The Dukhan solar PV project will be delivered in two phases and is scheduled to be fully operational by mid-2029. The first 1,000MW phase is due to be connected to the Qatar General Electricity & Water Corporation (Kahramaa) grid by the end of 2028, with the second phase following a year later.

The award reflects a broader acceleration in Qatar’s renewable energy programme, which began with the 800MW Al-Kharsaah solar independent power producer (IPP) project.

Al-Kharsaah, Qatar’s first utility-scale solar PV facility, entered commercial operation in 2022 and marked a structural shift in the country’s approach to power generation planning. The project established solar PV as a core component of the national energy mix, rather than a supplementary source of capacity.

Expanding solar capacity

Since then, progress has focused on scaling capacity at pace. In 2025, construction was completed on two additional solar PV plants, located in Ras Laffan and Mesaieed, adding a combined 875MW of capacity.

The Ras Laffan plant has a capacity of 458MW, while the Mesaieed facility contributes a further 417MW. Samsung C&T was also the contractor for these projects, reinforcing its role as the dominant solar engineering, procurement and construction (EPC) contractor in the country.

With Al-Kharsaah, Ras Laffan and Mesaieed now operational, Qatar’s installed solar generation capacity stands at about 1,675MW. This is in line with its long-term objective to install 5,000MW in renewable energy capacity by 2035.

Peak electricity demand remains driven by summer cooling loads. On the supply side, Qatar’s total contracted electricity capacity now exceeds 13,000MW following the award of the Dukhan project.

As in the previous year, the utilities market in 2025 was dominated by a single large power generation scheme.

In 2024, Japan’s Sumitomo Corporation won the contract to develop and operate the $2.3bn Facility E independent water and power project (IWPP), accounting for more than half of total contract awards. The project, which entered construction in September, will have a power generation capacity of 2,300MW and a water desalination capacity of 100 million imperial gallons a day.

In 2025, the Dukhan solar project played a comparable role, driving the overall value of awarded contracts in Qatar’s utilities sector to about $2.7bn and accounting for approximately 39% of total awards.

Although this fell short of the previous year’s peak, it still made 2025 the second-strongest year for Qatar’s utilities sector since 2017, with a lower degree of concentration.

The level of activity points to a more sustained flow of awards following a slowdown linked to the completion of World Cup-related infrastructure and disruption during the Covid-19 period.

Grid investment

In parallel, Qatar also continued to advance its thermal power generation programme to support system flexibility and peak demand management.

Qatar Electricity & Water Company (QEWC), in collaboration with Kahramaa, is undertaking the construction of a 511MW single-cycle gas turbine plant at Ras Abu Fontas Industrial Zone on the south side of Doha.

The main EPC contract was awarded to a consortium led by South Korea’s Doosan Enerbility. The peak power plant, valued at about QR1.6bn ($439.5m), is scheduled to become operational by January 2027.

Qatar’s efforts to expand both thermal and solar power generation capacity have also driven investment in its transmission and distribution network, with two contracts exceeding $100m in value.

Kahramaa awarded Elsewedy Cables Qatar the $274m main EPC contract for the construction of 132kV cables. Separately, UK-headquartered Best & Betas won the main contract for the construction of five substations and one new transformer centre, with a combined installed capacity of 1,700MVA.

Water transmission focus

Over the next 12 months, large power generation projects will take a back seat in Qatar’s utilities sector as the focus shifts towards power and water transmission infrastructure.

Qatar’s Public Works Authority, Ashghal, is expected to issue the request for proposals by mid-2025 for four construction contracts that form part of the South of Wakrah and New District of Doha pumping station scheme. Together, the four projects have an estimated combined value of about $1.1bn.

The scheme is part of Qatar’s longer-term drainage and flood-resilience strategy. In 2013, Ashghal developed the Qatar Integrated Drainage Master Plan, which set out a 50-year roadmap for foul water, groundwater, stormwater and treated sewage effluent systems across the country.

The plan identified several major groundwater and stormwater projects required to support urban expansion and climate resilience, including the South of Wakrah and New District of Doha pumping station and outfall scheme.

Progress on these projects has slowed since 2022, when Ashghal received prequalification submissions from construction companies interested in bidding for the four packages. However, with power generation capacity now largely secured in the near term, the renewed emphasis on transmission, drainage and water infrastructure will shape the next phase of activity in Qatar’s utilities market.

https://image.digitalinsightresearch.in/uploads/NewsArticle/15422255/main.jpg
Mark Dowdall
Related Articles
  • Contractor wins $197m Doha infrastructure works

    6 November 2026

     

    Register for MEED’s 14-day trial access 

    Qatar’s Public Works Authority (Ashghal) has awarded an estimated QR722m ($197m) contract to develop roads and infrastructure north of Al-Rifaa Street in Doha.

    The contract was awarded to local firm Tadmur Contracting Company.

    Six other contractors submitted bids: 

    • Qatar Trading & Contracting Group ($244m)
    • Iris Construction Tourism Industry & Trade ($259m)
    • Lotus Trading & Contracting ($260m)
    • Generic Engineering Technologies & Contracting ($261m)
    • Alghanim International / National Industrial Contracting ($268m)
    • Hamad Bin Khalid Contracting Company ($281m)

    The scope of work covers the construction of more than 34 kilometres of roads, dedicated plot developments, site clearance, backfill and earthworks.

    The package also requires the installation of surface and groundwater drainage systems, a foul-water drainage network and treated sewage effluent lines.

    In addition, the contractor will deliver a dedicated pumping station, an emergency flood area pond, 3,735 car parking spaces, road cross-sectional elements and verge parking bays.

    Secondary infrastructure works include electrical distribution, water mains, utility lines, manholes, gully pots and house connections, along with kerbing, road pavement works, landscaping, street lighting, road markings and directional signage.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21204827/main.jpg
    Yasir Iqbal
  • Stakeholders aim to sign Iraq pipeline deal by year end

    6 November 2026

     

    Stakeholders expect a key contract to be signed before the end of the year for the development of a major oil export pipeline network in Iraq, according to industry sources.

    Iraq and Syria’s governments, state-owned oil companies and a consortium led by Qatar’s UCC are currently discussing the terms.

    If all parties agree to the proposed deal, the UCC-led coalition will become the selected developer responsible for tendering engineering, procurement and construction (EPC) contracts for the project.

    The consortium includes US-based Chevron, the investment company TI Capital and France’s TotalEnergies.

    The proposed plan will use a fast-track framework to bring the pipelines online as quickly as possible.

    One source said: “The plan that is being discussed is highly unusual, because it is such a large-scale pipeline project and it would be brought online in a relatively short timeframe.”

    A team from UCC is currently in Iraq for meetings with government officials to discuss the project, one source said.

    The project will be focused on four pipeline packages:

    • Basra to Najaf
    • Najaf to Haditha
    • Haditha to Fish Khapour
    • Haditha to Banias Port in Syria

    In July, Iraq’s cabinet approved state-owned Basra Oil Company signing a ​heads of agreement and a non-disclosure agreement with the UCC-led consortium to explore possible future oil pipeline projects.

    Under the terms of the agreement, the consortium is preparing technical and financial feasibility studies for strategic export pipeline projects.

    Also in July, US-based KBR was awarded a consultancy contract for the section of pipeline due to extend from Basra to Haditha.

    In April, Iraq announced the allocation of $1.5bn for the Basra-Haditha route, while the larger scheme is estimated at around $5bn.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21181262/main.jpg
    Wil Crisp
  • Taqa shortlists 17 contractors for Mirfa-Liwa scheme

    6 November 2026

     

    Up to 17 contractors have been invited to submit bids for a major water transmission and distribution scheme serving Mirfa, Madinat Zayed and Liwa in Abu Dhabi, a source close to the project has confirmed to MEED.

    The project, originally estimated to cost $775m, comprises a water transmission system from Mirfa, alongside distribution networks serving farms and settlements in Abu Dhabi’s western region.

    In October, MEED exclusively reported that a request for proposals had been issued, with bids due on 5 January 2027, following an extension from the initial deadline of 11 November 2026.

    The Mirfa-Liwa scheme has been in procurement for several years and was previously tendered in December 2024 as an engineering, procurement and construction scheme, divided between transmission and distribution works.

    As MEED understands, it was recently re-tendered under a design, build and operate model, extending the contractor’s responsibilities to operating the infrastructure after construction.

    According to sources, the full list of contractors invited to bid for the tender includes:

    • Afcons Infrastructure (India)
    • Alkhorayef Water & Power Technologies (Saudi Arabia)
    • China Machinery Engineering Corporation (China)
    • China National Chemical Engineering (China)
    • China Tiesiju Civil Engineering Group (China)
    • Danway Electrical & Mechanical Engineering (UAE)
    • Emarat Aloula Contracting (UAE)
    • FCC Aqualia (Spain)
    • Gulf Contractors Company (UAE)
    • Hydropower Energy & General Construction (UAE)
    • Jereh Oil & Gas Engineering Corporation (China)
    • Mapa (Turkiye)
    • Nesma & Partners Contracting Company (Saudi Arabia)
    • Orascom Construction (Egypt)
    • Power Construction Corporation of China (China)
    • Tecton Engineering & Construction (UAE)
    • Tristar Engineering & Construction (UAE)

    According to details seen by MEED, the scope includes a pumping station at Mirfa with a capacity of 128 million imperial gallons a day, approximately 125 kilometres of transmission pipelines to Muzairah, with branches to Madinat Zayed and Liwa Summit, and storage tanks at the three locations.

    The distribution network is divided into four geographic clusters covering Liwa East, Liwa West, Madinat Zayed and Seih Al-Kheir. The works include associated pipelines, pumping stations and storage facilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21181223/main.jpg
    Mark Dowdall
  • Gulf conflict cuts Emirates Group profit by 66%

    6 November 2026

    Register for MEED’s 14-day trial access 

    Dubai’s Emirates Group made a profit before tax of AED4.1bn ($1.1bn) in the first half of its 2026-27 financial year, 66% less than the AED12.2bn it made in the same period last year.

    The six months to 30 September were the group’s first full half-year since military activity disrupted commercial air traffic across the Gulf on 28 February. Group revenue fell 12% to AED66.2bn ($18bn), from AED75.4bn a year earlier. Profit after tax fell 66% to AED3.6bn ($1bn).

    Earnings before interest, tax, depreciation and amortisation (Ebitda) fell 41% to AED12.5bn ($3.4bn).

    The results follow a record 2025-26 financial year. The group made a profit before tax of AED24.4bn in that year, on revenue of AED150.5bn.

    “It has been a demanding six months, and once again our business model and our people stood up to the test,” said Sheikh Ahmed Bin Saeed Al-Maktoum, chairman and chief executive of Emirates Airline and Group. “Customer demand held firm and our cargo operations made a strong contribution, keeping revenue and cash levels healthy even as global jet fuel prices doubled against the same period last year.”

    Airline performance

    Emirates airline’s profit before tax fell 68% to AED3.7bn ($1bn), compared with AED11.4bn a year earlier. Its revenue fell 13% to AED56.9bn ($15.5bn). The airline carried 21.8 million passengers, 22% fewer than a year earlier. Capacity measured in available seat kilometres fell 17%, and the passenger seat factor dropped to 72% from 79.5%.

    Cargo partly offset the drop in passenger numbers. Emirates SkyCargo carried 1.2 million tonnes, 1% less than a year earlier, but its revenue rose 52%. The conflict reduced the airfreight capacity available on the market, and disruption to shipping pushed shippers towards air transport.

    Before hedging gains, fuel costs rose 60%, even though the airline uplifted 12% less fuel. Gains of AED7.1bn ($1.9bn) from fuel hedging cut the net increase in fuel costs to 13%. Fuel accounted for 34% of operating costs.

    On 30 September, Emirates was operating 91% of its pre-disruption network, serving 150 airports in 78 countries and territories. On 31 March, it had been flying 58% of its passenger capacity to 122 destinations in 65 countries.

    Fleet investment

    The airline received nine Airbus A350s and five Boeing 777 freighters during the period. Its fleet grew to 289 aircraft, from 277 on 31 March. Emirates is continuing its cabin retrofit programme, a planned investment of more than $7bn. It refurbished 12 aircraft in the first half. In May, it broke ground on a $5.1bn engineering and maintenance, repair and overhaul (MRO) facility at Al-Maktoum International airport, which is expected to be completed in the mid-2030s.

    The group’s cash position was AED54.1bn ($14.7bn) on 30 September, down from a record AED59.6bn on 31 March. The group said it had used its reserves to make pre-delivery payments for aircraft and to service existing debt. It also paid the remaining AED2bn of the AED3.5bn dividend declared for 2025-26 to its owner, the Investment Corporation of Dubai.

    Ground services and travel company dnata made a profit before tax of AED410m ($112m), down 51%. Its revenue fell 7% to AED11bn ($3bn), and the group said dnata’s international businesses helped offset weaker traffic in the UAE.

    The group’s workforce fell 2% to 128,237 people.

    “We enter the second half of our 2026-27 financial year with measured optimism,” said Sheikh Ahmed.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21198114/main.jpg
    Colin Foreman
  • King Salman airport tenders roads and utilities package

    6 November 2026

     

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s King Salman International Airport Development Company (KSIADC) has tendered the Zone C1+C2 roads, bridges and utility networks package for King Salman International airport (KSIA) in Riyadh.

    The tender was issued on 26 October, and bids are due by 6 December.

    The request for proposals covers the procurement, construction, testing and commissioning of civil infrastructure supporting Terminal 6, alongside the existing Terminals 1-5.

    The scope includes upgrades to Airport Road 539, which runs west of Terminals 1-5, and to part of Mohamed Bin Faraj Road 5333, west of Junction 6.

    It also includes new roads, ramps, service roads, and signalised at-grade junctions. An additional access road will connect the Terminal 6 site offices to Road 5333.

    Structures will include the Junction 6 and Terminal 6 bridges, retaining walls and reinforced-soil structures.

    The contractor will also construct the central ground services equipment (GSE) bridge. Before construction begins, the contractor must validate the design, complete any outstanding elements – including mechanically stabilised earth walls, approach slabs, drainage and lighting – and secure the required authority approvals.

    Dry utilities will comprise high- and extra-high-voltage containment, a 13.8kV medium-voltage network with package substations, low-voltage distribution and street lighting, and security-surveillance systems.

    Wet utilities will include potable water, fire water, irrigation water, treated sewage effluent, district cooling and wastewater networks. Wastewater pipes will range from 200mm u-PVC gravity lines to 1,700mm glass-reinforced plastic mains.

    The stormwater network will include channels, culverts, ponds and pipes ranging from 400mm to 1,400mm in diameter. Crossings will be constructed using open-cut excavation, horizontal directional drilling or microtunneling.

    Utilities serving the operational terminals will be diverted on a design-and-build basis. Enabling works will include earthworks and the relocation of the security fence and trees. The contractor will also demolish a temporary car park, existing bridges and a sewage pumping station.

    Optional works comprise two design-and-build elements that will proceed only at the client’s instruction.

    The first is the south GSE bridge. The second is an approximately 1,400-metre, multi-lane access road to the Terminal 6 Transportation Hub, including bridges, underpasses, ramps and tunnels, as well as provisions for future Wadi Loop utilities and structures.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21176175/main.png
    Yasir Iqbal