Dubai seeks financial advisers for Jebel Ali STP package
4 March 2025
Dubai Municipality has invited firms to prequalify for a contract to provide financial advisory services for the procurement of the third phase of the extension of the Jebel Ali sewage treatment plant (STP) in the emirate.
The municipality expects to receive statements of qualifications by 12 March, Fahd Al-Awadhi, director of the drainage and recycled water projects department at Dubai Municipality, said in a social media post on 3 March.
Phase three of the Jebel Ali STP extension will be procured as a public-private partnership (PPP) project, and the selected financial adviser will be working closely with the technical and other advisers appointed by Dubai Municipality to provide end-to-end advisory services on the procurement of a developer for the project.
Called DS150/3, the project's concession period is expected to be 30 years.
In October last year, Dubai Municipality sought engineering consultancy companies to prequalify for a contract to provide advisory services for phases one and two of the planned expansion of the Jebel Ali STP.
The expansion and upgrade of the Jebel Ali STP is one of the six packages comprising the $22bn Dubai Strategic Sewerage Tunnels (DSST) project, which is being procured using a PPP model.
Another package comprises the rehabilitation and expansion of the existing Warsan STP, for which Dubai Municipality sought advisers in January 2024.
DSST packages
The procurement processes for the two STP packages are being run separately from those for the four tunnels, links and terminal pump stations that make up the $22bn DSST project.
MEED understands that the tenders for the Warsan and Jebel Ali STP packages are expected to be issued once the DSST project's first four components get under way.
Under the current plan, the DSST project is broken down into six packages, which will be tendered as PPP packages with concession periods lasting between 25 and 35 years.
The first package, J1, comprises Jebel Ali tunnels (North) and terminal pump stations (TPS). The tunnels will extend approximately 42 kilometres (km), and the links will extend 10km.
The second package, J2, covers the southern section of the Jebel Ali tunnels, which will extend 16km and have a link stretching 46km.
W for Warsan, the third package, comprises 16km of tunnels, TPS and 46km of links.
J3, the fourth package, comprises 129km of links.
J1, J2, W and J3 will comprise the deep sewerage tunnels, links and TPS (TLT) components of the overall project.
J1, J2 and W will be procured under a design-build-finance-operate-maintain model with a concession period of 25-35 years.
J3 will be procured under a design-build-finance model with a concession period of 25-35 years. Once completed, Dubai Municipality will operate J3, unlike the first three packages, which are planned to be operated and maintained by the winning PPP contractors.
Dubai currently has two major sewerage catchments. The first, in Deira, is known as Warsan, where the Warsan STP treats the flow.
The second catchment is in Bur Dubai, where wastewater is treated at the Jebel Ali STP.
The municipality is expected to issue the tender for the DSST's first two tunnels and links packages imminently.
READ THE FEBRUARY MEED BUSINESS REVIEW
Trump unleashes tech opportunities; Doha achieves diplomatic prowess and economic resilience; GCC water developers eye uptick in award activity in 2025.
Published on 1 February 2025 and distributed to senior decision-makers in the region and around the world, the February MEED Business Review includes:
|
> AGENDA 1: Trump 2.0 targets technology
> AGENDA 2: Trump’s new trial in the Middle East
> AGENDA 3: Unlocking AI’s carbon conundrum
> GAZA: Gaza ceasefire goes into effect
> LEBANON: New Lebanese PM raises political hopes
> WATER DEVELOPERS: Acwa Power improves lead as IWP contract awards slow
> WATER & WASTEWATER: Water projects require innovation
> INTERVIEW: Omran’s tourism strategies help deliver Oman 2040
> PROJECTS RECORD: 2024 breaks all project records
> REAL ESTATE: Ras Al-Khaimah’s robust real estate boom continues
> QATAR: Doha works to reclaim spotlight
> GULF PROJECTS INDEX: Gulf projects market enters 2025 in state of growth
> CONTRACT AWARDS: Monthly haul cements record-breaking total for 2024
> ECONOMIC DATA: Data drives regional projects
> OPINION: Between the extremes as spring approaches
|
Exclusive from Meed
-
Syria seeks interest for $1.16bn Euphrates dam7 October 2026
-
Arada launches UAE construction arm with Roberts7 October 2026
-
Expo Riyadh sets October deadline for Saudi Arabia pavilion7 October 2026
-
Kuwait on track to hit oil production target7 October 2026
-
Roshn plans new flagship development in Riyadh7 October 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Syria seeks interest for $1.16bn Euphrates dam7 October 2026
Register for MEED’s 14-day trial access
Syria’s Ministry of Energy has invited expressions of interest (EoIs) for the development of the Halabiyeh-Zalabiyeh dam project on the Euphrates River.
The project has an indicative total cost of $1.16bn, according to the ministry’s EoI document. This includes $433.7m for the dam and hydropower plant and $729.6m for the pumped-storage power plant (PSP).
The scheme includes an 81MW hydroelectric power plant and a pumped-storage facility with a capacity of up to 1,200MW. The project will also include the construction of the dam and associated water-storage infrastructure.
The ministry seeks interest from qualified local and international companies, investors and other entities. Interested parties can participate in studies, design, financing, construction, and operation and maintenance of the project.
The ministry is considering several potential development structures, including build-own-operate-transfer, build-operate-transfer and public-private partnership models, as well as an engineering, procurement and construction (EPC) structure. It has said it is also open to proposals covering consultancy and financing services.
The EoI covers several stages, including pre-feasibility and feasibility studies, financing and bankability studies, detailed and executive design, EPC execution, and operation and maintenance.
The technical specifications envisage a 23-metre-high dam with a reservoir storage capacity of about 219 million cubic metres.
The hydropower plant will have three generating units, while the 1,200MW PSP will have 3.5 hours of storage capacity and four reversible units.
The deadline for submitting EoIs is 10 November, with enquiries accepted until 26 October.
READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDFIndustry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.
Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:
> AGENDA: Oxagon takes centre stage at Neom> MARKET FOCUS: Saudi projects hold steady> INDUSTRY REPORT: MEED’s 2026 GCC power developer ranking> LEADERSHIP: The future city does not need to hang above the groundTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/20336025/main.jpg -
Arada launches UAE construction arm with Roberts7 October 2026
Register for MEED’s 14-day trial access
UAE developer Arada has integrated Australian contractor Roberts into the UAE market as part of its wider business strategy.
Arada acquired Roberts in 2025 after entering the Australian market. The tier-one contractor delivers projects in the healthcare, education, commercial, residential, hospitality, industrial, life sciences and defence sectors.
At the time of the acquisition, Arada said it planned to invest about $20m in Roberts. The investment is intended to give the developer greater control over the delivery of its Australian projects and support Roberts’ expansion into markets including the UAE.
Arada has said it could invest up to $100m in Roberts’ expansion into new sectors and markets. The company is targeting $1bn in annual revenue from Roberts by 2028.
Roberts has established a UAE office, with a head office team already in place. Arada said the contractor’s capabilities will support the delivery of its high-rise residential and social infrastructure projects.
The contractor’s first UAE project will be phase two of Arada Central Business District, a commercial development within Aljada in Sharjah. Arada is developing the AED35bn ($9.5bn) mixed-use project.
Roberts is also providing preconstruction services for several Arada projects in Dubai and Sharjah, ahead of starting site work.
READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDFIndustry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.
Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:
> AGENDA: Oxagon takes centre stage at Neom> MARKET FOCUS: Saudi projects hold steady> INDUSTRY REPORT: MEED’s 2026 GCC power developer ranking> LEADERSHIP: The future city does not need to hang above the groundTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/20334926/main.jpg -
Expo Riyadh sets October deadline for Saudi Arabia pavilion7 October 2026

Expo 2030 Riyadh Company (ERC), tasked with delivering the Expo 2030 Riyadh venue, has set a deadline of 25 October for bids for a contract to build the Saudi Arabia pavilion.
The tender was issued on 19 May, with an initial bid submission deadline of 26 August.
The pavilion is a major asset located within the KSA District on the eastern side of the Expo 2030 Riyadh masterplan, in the Loop of Nations district.
Construction activity at the Expo site is accelerating, with Riyadh moving to award its first major vertical contracts and advancing infrastructure works across the programme.
Last month, MEED reported that ERC had received contractor interest on 14 September for a contract to design and build a convention centre in the site’s Collaboration District.
ERC also tendered a contract to deliver the Souq areas within the Expo site, as MEED exclusively reported on 8 September.
These areas are divided into five precincts, with a total development area of about 300,000 square metres.
Also in September, Saudi Arabia’s Royal Commission for Riyadh City awarded a design-and-build contract to construct a new metro station serving the Expo 2030 site.
In April, ERC awarded two contracts for the next phase of infrastructure works at the site to local firm Al-Yamama Company.
The scope covered the construction of road networks and infrastructure for water, sewage, electricity, telecommunications and electric vehicle (EV) charging.
These awards followed ERC’s January award of an estimated SR1bn ($267m) contract for initial infrastructure works at the site to local firm Nesma & Partners.
That scope covered about 50 kilometres of integrated infrastructure networks, including internal roads and essential utilities such as water, sewage, electrical and communications systems, as well as EV charging stations.
The masterplan covers 6 square kilometres, making it one of the largest sites ever designated for a World Expo event. Situated north of the Saudi capital, the site will be near the future King Salman International airport and will provide direct access to Riyadh landmarks.
The Public Investment Fund, Saudi Arabia’s sovereign wealth vehicle, launched ERC – a wholly owned subsidiary – in June 2025 to build and operate facilities for Expo 2030.
READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDFIndustry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.
Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:
> AGENDA: Oxagon takes centre stage at Neom> MARKET FOCUS: Saudi projects hold steady> INDUSTRY REPORT: MEED’s 2026 GCC power developer ranking> LEADERSHIP: The future city does not need to hang above the groundTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/20334856/main.jpg -
Kuwait on track to hit oil production target7 October 2026
Kuwait is on track to meet its target of having 4 million barrels a day (b/d) of oil production capacity by 2035, according to Kuwait Petroleum Corporation (KPC) chief executive Shaikh Nawaf Al-Sabah.
Al-Sabah also said Kuwait is on course to increase non-associated gas production to 2 billion cubic feet a day by 2040.
His comments come amid an ongoing crisis in Kuwait’s oil and gas sector linked to the regional conflict that began when the US and Israel attacked Iran on 28 February.
The subsequent war has significantly disrupted shipping through the Strait of Hormuz, which is a crucial export route for Kuwaiti crude oil.
Kuwait is currently producing around 2 million b/d of oil, down from 2.6 million b/d before the US and Israel attack.
Speaking at a conference in London, Al-Sabah said: “We have the capacity to go back up to our current maximum sustainable capacity of 3 million b/d, if we have the export routes available, and this comes down to the ability to move oil through the Strait.”
KPC is investing $9bn-$10bn a year in capital expenditure to meet its oil and gas production goals, according to Al-Sabah.
He said: “We are doing this because we recognise that it is our hydrocarbons that will be most in demand a decade from now, and two decades from now – in fact, for the rest of our lifetimes.”
Project Seef
KPC is pushing ahead with the Al-Seef project, which focuses on developing three large offshore oil discoveries, Al-Sabah said.
The offshore fields are known as Nokhatha, Julaia and Jazza. The development was first announced in February this year, about two weeks before the US and Israel attack on Iran.
Al-Sabah said KPC is continuing with the project and believes the three fields collectively hold more than 3 billion barrels of recoverable oil.
He said: “We are asking international oil companies to partner with us to develop those resources under an operating services contract.
“So, we’re moving ahead according to the exact same schedule that we had put together even before the war began.”
Al-Sabah did not say which international oil companies KPC has approached to help develop the three offshore fields.
READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDFIndustry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.
Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:
> AGENDA: Oxagon takes centre stage at Neom> MARKET FOCUS: Saudi projects hold steady> INDUSTRY REPORT: MEED’s 2026 GCC power developer ranking> LEADERSHIP: The future city does not need to hang above the groundTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/20315147/main.jpg -
Roshn plans new flagship development in Riyadh7 October 2026

Saudi developer Roshn Group plans to develop its next flagship scheme in north Riyadh, spanning an area of 13.7 square kilometres.
Roshn is looking to appoint lead design consultants to deliver detailed design, tender documentation and construction documents across the scheme, known as Plot 1.
The scope covers all infrastructure, utilities, public realm works and site adaptation of Roshn’s residential prototypes, split across two work packages.
Part 1 covers phases A, B and E, which collectively span about 7.8 million square metres (sq m) and will comprise 17,000 units.
Part 2 includes phases C and D, which will span about 4.7 million sq m and comprise more than 15,000 units.
The development is bordered by Expo 2030, King Abdulaziz Park, the Sports Innovation Lab Zone and the National Housing Company-developed Khozam district.
It will be a residential-led mixed-use development, also featuring retail, offices, hospitality, education and civic facilities.
Connectivity is a core plank of the masterplan, with two metro stations planned: one at the existing Line 4/proposed Line 7 interchange and another dedicated Line 7 stop. The scheme would also be served by the future Qiddiya high-speed rail and a possible King Salman Road diversion.
Plot 1 builds on Roshn’s existing footprint in the capital, notably the multi-phase Sedra community, as the developer expands beyond single-family housing into mixed-use districts under its Roshn 3.0 strategy.
Last month, Roshn Group announced that it had signed a preliminary agreement with Talaat Moustafa Group (TMG) Saudi, the local subsidiary of Egyptian developer Talaat Moustafa Group, to establish a joint venture to explore and develop a mixed-use project in Riyadh.
Under the agreement, TMG will hold a 51% stake in the joint company, while Roshn Group will hold 49%.
The agreement sets out a framework for the two groups to assess a potential partnership for the project’s phased development, which is planned as a residential-led, mixed-use community featuring retail, commercial, hospitality, leisure, healthcare and education facilities, alongside parks and public spaces.
Roshn Group and TMG Saudi plan to conduct detailed master planning and develop the project’s business case.
Preliminary studies indicate the development could include more than 55,000 residential units across all phases.
Roshn Group did not disclose the exact project location in its announcement.
As a Public Investment Fund-owned developer, Roshn remains a key vehicle for delivering Vision 2030’s housing programme, which targets 70% Saudi home ownership, alongside the kingdom’s wider quality-of-life and economic diversification agendas.
READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDFIndustry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.
Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:
> AGENDA: Oxagon takes centre stage at Neom> MARKET FOCUS: Saudi projects hold steady> INDUSTRY REPORT: MEED’s 2026 GCC power developer ranking> LEADERSHIP: The future city does not need to hang above the groundTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19786131/main.jpg