Dubai seeks financial advisers for Jebel Ali STP package
4 March 2025
Dubai Municipality has invited firms to prequalify for a contract to provide financial advisory services for the procurement of the third phase of the extension of the Jebel Ali sewage treatment plant (STP) in the emirate.
The municipality expects to receive statements of qualifications by 12 March, Fahd Al-Awadhi, director of the drainage and recycled water projects department at Dubai Municipality, said in a social media post on 3 March.
Phase three of the Jebel Ali STP extension will be procured as a public-private partnership (PPP) project, and the selected financial adviser will be working closely with the technical and other advisers appointed by Dubai Municipality to provide end-to-end advisory services on the procurement of a developer for the project.
Called DS150/3, the project's concession period is expected to be 30 years.
In October last year, Dubai Municipality sought engineering consultancy companies to prequalify for a contract to provide advisory services for phases one and two of the planned expansion of the Jebel Ali STP.
The expansion and upgrade of the Jebel Ali STP is one of the six packages comprising the $22bn Dubai Strategic Sewerage Tunnels (DSST) project, which is being procured using a PPP model.
Another package comprises the rehabilitation and expansion of the existing Warsan STP, for which Dubai Municipality sought advisers in January 2024.
DSST packages
The procurement processes for the two STP packages are being run separately from those for the four tunnels, links and terminal pump stations that make up the $22bn DSST project.
MEED understands that the tenders for the Warsan and Jebel Ali STP packages are expected to be issued once the DSST project's first four components get under way.
Under the current plan, the DSST project is broken down into six packages, which will be tendered as PPP packages with concession periods lasting between 25 and 35 years.
The first package, J1, comprises Jebel Ali tunnels (North) and terminal pump stations (TPS). The tunnels will extend approximately 42 kilometres (km), and the links will extend 10km.
The second package, J2, covers the southern section of the Jebel Ali tunnels, which will extend 16km and have a link stretching 46km.
W for Warsan, the third package, comprises 16km of tunnels, TPS and 46km of links.
J3, the fourth package, comprises 129km of links.
J1, J2, W and J3 will comprise the deep sewerage tunnels, links and TPS (TLT) components of the overall project.
J1, J2 and W will be procured under a design-build-finance-operate-maintain model with a concession period of 25-35 years.
J3 will be procured under a design-build-finance model with a concession period of 25-35 years. Once completed, Dubai Municipality will operate J3, unlike the first three packages, which are planned to be operated and maintained by the winning PPP contractors.
Dubai currently has two major sewerage catchments. The first, in Deira, is known as Warsan, where the Warsan STP treats the flow.
The second catchment is in Bur Dubai, where wastewater is treated at the Jebel Ali STP.
The municipality is expected to issue the tender for the DSST's first two tunnels and links packages imminently.
READ THE FEBRUARY MEED BUSINESS REVIEW
Trump unleashes tech opportunities; Doha achieves diplomatic prowess and economic resilience; GCC water developers eye uptick in award activity in 2025.
Published on 1 February 2025 and distributed to senior decision-makers in the region and around the world, the February MEED Business Review includes:
|
> AGENDA 1: Trump 2.0 targets technology
> AGENDA 2: Trump’s new trial in the Middle East
> AGENDA 3: Unlocking AI’s carbon conundrum
> GAZA: Gaza ceasefire goes into effect
> LEBANON: New Lebanese PM raises political hopes
> WATER DEVELOPERS: Acwa Power improves lead as IWP contract awards slow
> WATER & WASTEWATER: Water projects require innovation
> INTERVIEW: Omran’s tourism strategies help deliver Oman 2040
> PROJECTS RECORD: 2024 breaks all project records
> REAL ESTATE: Ras Al-Khaimah’s robust real estate boom continues
> QATAR: Doha works to reclaim spotlight
> GULF PROJECTS INDEX: Gulf projects market enters 2025 in state of growth
> CONTRACT AWARDS: Monthly haul cements record-breaking total for 2024
> ECONOMIC DATA: Data drives regional projects
> OPINION: Between the extremes as spring approaches
|
Exclusive from Meed
-
Public Investment Fund backs Neom16 April 2026
-
Kuwait gas project worth $3.3bn put on hold16 April 2026
-
Iraq pushes to revive oil pipeline through Saudi Arabia16 April 2026
-
Algeria opens bidding for water treatment plant15 April 2026
-
WEBINAR: UAE Projects Market 202615 April 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Public Investment Fund backs Neom16 April 2026
Commentary
Colin Foreman
EditorRegister for MEED’s 14-day trial access
Saudi Arabia’s Public Investment Fund (PIF) has backed Neom by including it as one of six strategic ecosystems in its newly approved 2026-30 strategy.
The future of the $500bn gigaproject had been thrown into doubt following the postponement of the 2029 Asian Winter Games at the Trojena mountain resort, the cancellation of construction contracts – such as the $5bn deal with Italian contractor Webuild for dam works at Trojena – and the slowdown of development at The Line, where tunnelling contracts were cancelled and staff left the project.
The backing comes as Neom’s operational focus appears to be evolving in response to shifting regional dynamics and global economic conditions. For example, on 15 April Neom posted on its official X account about a new Europe-Egypt-Neom-GCC corridor, describing it as a faster route for time-sensitive goods. It said the corridor combines trucking and ferry services to move goods quickly into the Gulf, adding that importers from several European markets are already using it to reach the UAE, Kuwait, Iraq, Oman and beyond.
Powered by Pan Marine, DFDS and regional RoPax services, the initiative is positioned as a way to add flexibility and resilience to regional supply chains. This emphasis on logistics and immediate trade utility suggests a shift away from the more speculative architectural announcements that characterised Neom’s early years, towards activity more directly tied to current market realities.
PIF’s broader 2026-30 strategy places heavy emphasis on “delivering competitive domestic ecosystems to connect sectors, unlock the full potential of strategic assets, maximise long-term returns and continue to drive the economic transformation of Saudi Arabia”.
The inclusion of Neom as a standalone ecosystem within the Vision Portfolio suggests that while the project remains part of the kingdom’s Vision 2030 goals, it will be subject to the fund's focus on working with the private sector.
That means the long-term success of Neom will increasingly depend on its ability to attract external investment and function as a viable economic hub rather than just a state-funded construction site.
MEED’s April 2026 report on Saudi Arabia includes:
> COMMENT: Risk accelerates Saudi spending shift
> GVT &: ECONOMY: Riyadh navigates a changed landscape
> BANKING: Testing times for Saudi banks
> UPSTREAM: Offshore oil and gas projects to dominate Aramco capex in 2026
> DOWNSTREAM: Saudi downstream projects market enters lean period
> POWER: Wind power gathers pace in Saudi Arabia
> WATER: Sharakat plan signals next phase of Saudi water expansion
> CONSTRUCTION: Saudi construction enters a period of strategic readjustment
> TRANSPORT: Rail expansion powers Saudi Arabia’s infrastructure pushTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16417262/main.jpeg -
Kuwait gas project worth $3.3bn put on hold16 April 2026

State-owned Kuwait Gulf Oil Company’s (KGOC’s) planned tender for the development of an onshore gas plant next to the Al-Zour refinery has been put on hold due to uncertainty created by the US and Israel’s war with Iran, according to industry sources.
The project budget is estimated to be $3.3bn, and the last meeting with contractors to discuss the project took place in Kuwait on 10 February.
Previously, it was expected to be tendered in late March, but the tendering process was delayed due to the regional conflict and disruption to shipping through the Strait of Hormuz.
One source said: “This tender is now effectively on hold while KGOC waits for increased stability in the region before it invites companies to bid for the contract.”
Under current plans, the plant will have the capacity to process up to 632 million cubic feet a day of gas and 88.9 million barrels a day of condensates from the Dorra offshore field, located in Gulf waters in the Saudi-Kuwait Neutral Zone.
Ownership of the field is disputed by Iran, which refers to the field as Arash.
Iran claims the field partially extends into Iranian territory and asserts that Tehran should be a stakeholder in its development.
It is believed that the Dorra field’s close proximity to Iran will make development difficult due to the current security environment.
The offshore elements of the project are expected to be especially difficult to protect from attacks from Iran.
In July last year, MEED reported that KGOC had initiated the project by launching an early engagement process with contractors for the main engineering, procurement and construction tender.
France-based Technip Energies completed the contract for the front-end engineering and design.
READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDFEconomic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.
Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:
> AGENDA: Gulf economies under fire> GCC CONTRACTOR RANKING: Construction guard undergoes a shift> MARKET FOCUS: Risk accelerates Saudi spending shift> QATAR LNG: Qatar’s new $8bn investment heats up global LNG race> LEADERSHIP: Shaping the future of passenger rail in the Middle EastTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16413221/main.png -
Iraq pushes to revive oil pipeline through Saudi Arabia16 April 2026
Iraq is pushing to revive an oil pipeline that passes through Saudi Arabia, allowing it to diversify export routes.
Saheb Bazoun, a spokesman for Iraq’s Oil Ministry, said the pipeline would help to insulate Iraq from any future blockades of the Strait of Hormuz, which has been largely closed since 28 February.
The original pipeline through Saudi Arabia has not been used for more than 30 years and would need work to be done in order to bring it online.
It is 1,568km long, extending from the city of Zubair in Iraq to the Saudi port of Yanbu on the Red Sea.
The pipeline was built in two phases during the 1980s. The first phase stretches between Zubair and Khurais, while the second extends to Yanbu. The pipeline’s operating capacity reached over 1.6 million barrels a day (b/d).
Following the Gulf War, the pipeline was shut down in August 1990. It has remained out of operation for decades, despite Iraq’s several attempts to restart it.
The original pipeline project cost over $2.6bn, including storage tanks and loading terminals.
In the wake of the US and Israel attacking Iran on 28 February, global markets have lost 11 million barrels a day (b/d) of oil supply due to the effective closure of the Strait of Hormuz.
READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDFEconomic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.
Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:
> AGENDA: Gulf economies under fire> GCC CONTRACTOR RANKING: Construction guard undergoes a shift> MARKET FOCUS: Risk accelerates Saudi spending shift> QATAR LNG: Qatar’s new $8bn investment heats up global LNG race> LEADERSHIP: Shaping the future of passenger rail in the Middle EastTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16413290/main.jpg -
Algeria opens bidding for water treatment plant15 April 2026

State-owned Cosider Pipelines, part of Algeria’s public infrastructure group Cosider, has issued a tender for the construction of a demineralisation plant in In Salah in Algeria.
The contract covers the design, supply, installation, testing and commissioning of a plant with a treatment capacity of 62,000 cubic metres a day (cm/d).
The tender is open to local and international companies specialising in the design and construction of demineralisation and reverse osmosis desalination plants.
The bid submission deadline is 26 April.
The project will be located at In Salah, a key industrial area in southern Algeria, where treated water supply is important for both municipal and industrial use.
Cosider said that individual bidders must demonstrate that they have completed at least one reverse osmosis demineralisation or desalination plant with a capacity of 20,000 cubic metres a day or more.
They must also show an average annual turnover of at least AD1bn ($7.7m) for their five best years over the past decade.
For consortium bids, all partners must share full responsibility for the contract, while the lead company must meet the technical and financial requirements.
Recent projects
In 2023, MEED reported that Riyadh-based water utility developer Wetico had won two contracts to develop water desalination plants in Algeria.
Societe Algerienne de Realisation de Projects Industriels (Sarpi) awarded the contract for the El-Tarf desalination plant, while Entreprise Nationale de Canalisations (Enac) is the client for the Bejaja facility.
Both plants were commissioned in 2025, each with a production capacity of 300,000 cm/d.
Separately, Wetico was the main contractor on a third plant commissioned last year. The Cap Dijinet 2 seawater desalination plant in Boumerdes province covers 18 hectares and also has a capacity of 300,000 cm/d.
Like many countries, Algeria is facing pressure on resources due to longer and more frequent droughts. Seawater desalination is seen as a key driver of the government’s strategy to guarantee drinking water supply.
According to previous reports, the government is planning to build up to six additional plants by 2030.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16404325/main.jpg -
WEBINAR: UAE Projects Market 202615 April 2026
Webinar: UAE Projects Market 2026
Tuesday, 28 April 2026 | 11:00 GST | Register now
Agenda:
- Overview of the UAE projects market landscape
- 2025 projects market performance
- Value of work awarded 2026 YTD
- Impact of the Iran conflict on the projects market and real estate, assessing supply chain disruptions, material cost inflation and war risk premiums
- Key drivers, challenges and opportunities
- Size of future pipeline by sector and status
- Ranking of the top contractors and clients
- Summary of key current and future projects
- Short and long-term market outlook
- Audience Q&A
Hosted by: Colin Foreman, editor of MEED
Colin Foreman is editor and a specialist construction journalist for news and analysis on MEED.com and the MEED Business Review magazine. He has been reporting on the region since 2003, specialising in the construction sector and its impact on the broader economy. He has reported exclusively on a wide range of projects across the region including Dubai Metro, the Burj Khalifa, Jeddah Airport, Doha Metro, Hamad International airport and Yas Island. Before joining MEED, Colin reported on the construction sector in Hong Kong.https://image.digitalinsightresearch.in/uploads/NewsArticle/16401868/main.gif