Dubai seeks EPC firms for $22bn tunnels project
8 February 2024
Register for MEED's guest programme
Dubai Municipality has invited engineering, procurement and construction (EPC) companies to prequalify for the contracts to be procured under the multibillion-dollar Dubai Strategic Sewerage Tunnels (DSST) project.
The project aims to convert Dubai's existing sewerage system from a pumped system to a gravity system by decommissioning the existing pump stations and providing "a sustainable, innovative, reliable service for future generations".
Dubai Municipality has requested interested companies to submit their statements of qualifications by 26 February, according to an industry source.
It expects to announce the prequalified EPC contractors by 11 March, following which it plans to start the prequalification process for the public-private partnership (PPP) consortiums that can bid for the project.
Dubai is currently served by two major sewerage catchments. The first, located in Deira, is called Warsan, where the flow is treated by the existing Warsan sewage treatment plant (STP).
The second catchment, called Jebel Ali, is in Bur Dubai, where the wastewater is treated at the Jebel Ali STP.
The DSST project is broken down into six packages, which will be tendered separately.
The first package, J1, comprises Jebel Ali tunnels (North) and terminal pump stations (TPS). The tunnels are to extend approximately 42 kilometres with the links extending 10km.
The second package, J2, covers the southern section of the Jebel Ali tunnels, which will extend 16km, with a link stretching 46km.
W for Warsan, the third package, comprises 16km of tunnels, TPS and 46km of links.
J3, the fourth package, comprises 129km of links, which will be operated by the Dubai Municipality once completed, unlike the first three packages, which are envisaged to be operated and maintained by the winning PPP contractors.
J1, J2 and W will be procured under a design-build-finance-operate-maintain model with a concession period expected to be between 25 and 35 years.
J3 will be procured under a design-build-finance model with a concession period ranging between 25 and 35 years.
J1, J2, W and J3 will comprise the deep sewerage tunnels, links and TPS (DLT) components of the overall project.
Meed understands the remaining two packages of the project, the expansion and upgrade of the Jebel Ali and Warsan STPs, will be procured in a process separate from the four DSST-DLT components of the project.
The requests for proposals (RFPs) for the four DSST-DLT packages are likely to be issued in sequential order on a staggered basis around six to 12 months apart.
According to the prequalification document, the bidders for each of the PPP RFPs will be prequalified consortiums comprised of sponsors, EPC contractors and operation and management (O&M) contractors.
Dubai’s Executive Council approved the DSST project in June 2023 and said it would require an investment of about AED80bn ($22bn).
The Council said that the project has been designed to serve the needs of the Dubai population for the next 100 years in alignment with the Dubai Economic Agenda D33 and the Dubai Urban Plan 2040.
Dubai Municipality appointed advisers for the overall scheme last year. It selected Abu Dhabi-headquartered Tribe Infrastructure Group as lead and financial adviser, UK-based Ashurst as legal adviser and the US' Parsons as technical adviser.
Exclusive from Meed
-
Three bids submitted for Riyadh-Qassim IWTP
18 September 2025
-
Saudi Arabia seeks firms for six renewable projects
17 September 2025
-
Qatar tenders Smaisma infrastructure contract
17 September 2025
-
Dragon Oil to boost exploration and production in Egypt
17 September 2025
-
Construction launched for final major projects of Iraq’s GGIP
17 September 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends

Related Articles
-
Three bids submitted for Riyadh-Qassim IWTP
18 September 2025
Register for MEED’s 14-day trial access
State water offtaker Saudi Water Partnership Company (SWPC) has received three bids from the private sector for the development of the Riyadh-Qassim independent water transmission pipeline (IWTP) project.
The bids were submitted by two consortiums and one individual company.
The first consortium comprises Saudi firms Al-Jomaih Energy & Water, Al-Khorayef Water & Power Technologies, AlBawani Capital and Buhur for Investment Company.
The second consortium comprises Bahrain/Saudi Arabia-based Lamar Holding, the UAE's Etihad Water & Electricity and China’s Shaanxi Construction Installation Group.
The third bid was submitted by Saudi Arabia's Vision Invest.
In August, MEED exclusively reported that SWPC had extended the bid submission deadline again for a contract to develop and operate the project.
The deadline for bids was 17 September.
The project will have a transmission capacity of 685,000 cubic metres a day. It will include a pipeline length of 859 kilometres (km) and a total storage capacity of 1.59 million cubic metres.
The scheme is the third IWTP contract to be tendered by SWPC since 2022.
The first two are the 150km Rayis-Rabigh IWTP, which is under construction, and the 603km Jubail-Buraydah IWTP, the contract for which was awarded to a team of Riyadh-based companies comprising Al-Jomaih Energy & Water, Nesma Group and Buhur for Investment Company.
Like the first two IWTPs, the Riyadh-Qassim IWTP project will be developed using a 35-year build-own-operate-transfer contracting model.
Commercial operations are expected to commence in the first quarter of 2030.
https://image.digitalinsightresearch.in/uploads/NewsArticle/14691078/main.jpg -
Saudi Arabia seeks firms for six renewable projects
17 September 2025
Register for MEED’s 14-day trial access
Saudi Arabia's principal buyer, Saudi Power Procurement Company (SPPC), has invited interested companies to prequalify for the contracts to develop and operate solar photovoltaic (PV) and wind independent power producer (IPP) projects with a total combined capacity of 5,300MW.
The following schemes comprise round seven of the kingdom's National Renewable Energy Programme (NREP):
- 1,400MW Tabjal 2 solar PV IPP (Tabrijal, Al-Jouf Province)
- 600MW Mawqqaq solar PV IPP (Mawqqaq, Hail Province)
- 600MW Tathleeth solar PV IPP (Tathleeth, Aseer Province)
- 500MW South Al-Ula solar PV IPP (Al-Ula, Medina Province)
- 1,300MW Bilgah wind IPP (Bilgah, Medina Province)
- 900MW Shagran wind IPP (Shagran, Medina Province)
These projects are part of the NREP, which aims to achieve an optimal energy mix and supply 50% of the kingdom's electricity from renewable energy by 2030.
Earlier rounds under the NREP have already put in place large capacities.
Round six solicited around 4,500MW of solar and wind projects:
- 1,500MW Dawadmi wind IPP (Riyadh)
- 1,400MW Najran solar PV IPP (Najran)
- 600MW Samtah solar PV IPP (Jizan)
- 600MW Al-Darb solar PV IPP (Jizan)
- 400MW Al-Sufun solar PV IPP (Hail)
In April, MEED reported that prequalified developers were forming teams to bid for the contracts to develop solar farms under the sixth round of the NREP.
A separate set of bidders were prequalified for the 1,500MW Dawadmi wind farm, with contracts due to be awarded before the end of the year.
https://image.digitalinsightresearch.in/uploads/NewsArticle/14684103/main3708.jpg -
Qatar tenders Smaisma infrastructure contract
17 September 2025
Register for MEED’s 14-day trial access
Qatar’s Public Works Authority (Ashghal) has tendered a contract inviting construction firms to bid for the remaining works on roads and infrastructure in the small seaside town of Smaisma.
The contract covers package two in the south area of Smaisma, located 52 kilometres (km) north of Hamad International airport.
The scope of work includes the completion of the remaining works and remedial works on three zones. Each zone is further divided into three sub-zones.
The scope also covers the remaining works on road C1017.
The contract duration is two years from the start of construction works.
The tender was floated on 15 September with a bid submission date of 28 October.
The latest notice follows the tendering for the construction of roads and infrastructure in Wadi Al-Banat North (Zone 70).
Market overview
After 2019, there was a consistent year-on-year decline in contract awards in Qatar’s construction and transport sectors. The total value of awards in that year was $13.5bn, but by 2023 it had fallen to just over $1.2bn.
In 2024, the value of project contract awards increased to $1.7bn, bucking the downward trend in the market in the preceding four years.
Of last year’s figure, the construction sector accounted for contract awards of over $1.2bn, while transport contract awards were about $200m.
There are strategic projects in the bidding phase in Qatar worth more than $5bn, and these are expected to provide renewed impetus to the construction and transportation market, presenting opportunities for contractors in the near term.
https://image.digitalinsightresearch.in/uploads/NewsArticle/14682452/main.jpg -
Dragon Oil to boost exploration and production in Egypt
17 September 2025
Register for MEED’s 14-day trial access
Dubai-based Dragon Oil has signed a deal with the state-owned national oil company Egyptian General Petroleum Corporation (EGPC), agreeing to increase exploration and production activities in the Gulf of Suez.
Under the terms of the agreement, Dragon Oil will make investments worth about $30m.
This will fund activities including a programme to drill at least two new wells in the East El-Hamd area.
Abdulkarim Ahmed Al-Mazmi, the acting chief executive of Dragon Oil, said: “The signing of this agreement reaffirms Dragon Oil’s commitment to strengthening its strategic presence in the Arab Republic of Egypt and supporting EGPC’s efforts to develop energy resources in the Gulf of Suez region, in line with the company’s vision for growth and sustainability.”
Dragon Oil is wholly owned by Emirates National Oil Company, which is fully owned by the Government of Dubai.
Al-Mamzi said that the new investments are part of Dragon Oil’s broader strategy to expand in regional markets and to strengthen its position in the oil and gas sector, in line with the directions of the government of the UAE, and in particular the Government of Dubai.
The agreement was signed at the EGPC headquarters in Cairo.
https://image.digitalinsightresearch.in/uploads/NewsArticle/14680456/main.png -
Construction launched for final major projects of Iraq’s GGIP
17 September 2025
Register for MEED’s 14-day trial access
Officials have announced the start of construction on Iraq’s Common Seawater Supply Project (CSSP) and the full field development of the Ratawi oil field, which is also known as the Artarwi field.
The two projects are the two last major contracts of the Gas Growth Integrated Project (GGIP).
The GGIP is led by France’s TotalEnergies, which is the operator and has a 45% stake in the project.
Its partners are Iraq’s state-owned Basra Oil Company, which has a 30% stake, and QatarEnergy, which has a 25% stake.
An event in Baghdad to mark the launch of the two projects was attended by senior officials including Patrick Pouyanne, the chairman and chief executive of TotalEnergies; and Saad Sherida Al-Kaabi, who is Qatar’s Minister of State for Energy Affairs, as well as the president and chief executive of QatarEnergy.
In a statement, TotalEnergies said: “All four parts (natural gas, solar, oil, water) of the GGIP are now in the execution phase.”
The CSSP will be built on Iraq's coast, near the town of Um Qasr. It will process and transport 5 million barrels a day (b/d) of seawater to the main oil fields in southern Iraq.
Treated seawater will be substituted for the freshwater currently taken from the Tigris, Euphrates and aquifers to maintain pressure in the oil wells.
The project is expected to help alleviate water stress in the region and free up to 250,000 cubic metres of freshwater a day for irrigation and local agriculture needs, according to TotalEnergies.
The Ratawi redevelopment was launched in September 2023. Phase one aims to increase production to 120,000 b/d of oil and is expected to come on stream by early 2026.
The launch of phase two, the full field development, will enable production to be increased to 210,000 b/d starting in 2028, with no routine flaring, according to TotalEnergies.
In a statement, it said that all 160,000 cubic feet a day (cf/d) of associated gas produced will be fully processed by the 300,000 cf/d Gas Midstream Project (GMP), the construction of which began in early 2025.
The GMP, which will also treat previously flared gas from two other fields in southern Iraq, will deliver processed gas into the national grid, where it will fuel power plants with a production capacity of approximately 1.5GW, providing electricity to 1.5 million Iraqi households.
An early production facility to process 50,000 cf/d of associated gas will start in early 2026, together with the Ratawi phase one oil production.
Pouyanne said: “We are delighted today to award the two final contracts of the GGIP, in particular the seawater treatment plant, which has been long awaited by the oil industry in Iraq.
“In less than two years since the GGIP effective date in August 2023, TotalEnergies and its partners have fully executed their commitment towards the people of Iraq and launched all projects included in the multi-energy GGIP project, the best showcase of TotalEnergies' transition strategy.
“All these projects will bring a significant contribution to the Iraq economy and employ during the construction phase 7,000 Iraqi nationals.
“Furthermore, I am proud to confirm that the first phase of the associated gas, oil and solar projects will start up as soon as early 2026.”
Turkiye’s Enka has signed a contract to develop a central processing facility at the Ratawi oil field as part of the second phase of the field’s development.
https://image.digitalinsightresearch.in/uploads/NewsArticle/14680455/main.png