Dubai seeks EPC firms for $22bn tunnels project

8 February 2024

 

Register for MEED's guest programme 

Dubai Municipality has invited engineering, procurement and construction (EPC) companies to prequalify for the contracts to be procured under the multibillion-dollar Dubai Strategic Sewerage Tunnels (DSST) project

The project aims to convert Dubai's existing sewerage system from a pumped system to a gravity system by decommissioning the existing pump stations and providing "a sustainable, innovative, reliable service for future generations".

Dubai Municipality has requested interested companies to submit their statements of qualifications by 26 February, according to an industry source.

It expects to announce the prequalified EPC contractors by 11 March, following which it plans to start the prequalification process for the public-private partnership (PPP) consortiums that can bid for the project.

Dubai is currently served by two major sewerage catchments. The first, located in Deira, is called Warsan, where the flow is treated by the existing Warsan sewage treatment plant (STP).

The second catchment, called Jebel Ali, is in Bur Dubai, where the wastewater is treated at the Jebel Ali STP.

The DSST project is broken down into six packages, which will be tendered separately.

The first package, J1, comprises Jebel Ali tunnels (North) and terminal pump stations (TPS). The tunnels are to extend approximately 42 kilometres with the links extending 10km. 

The second package, J2, covers the southern section of the Jebel Ali tunnels, which will extend 16km, with a link stretching 46km.

W for Warsan, the third package, comprises 16km of tunnels, TPS and 46km of links.

J3, the fourth package, comprises 129km of links, which will be operated by the Dubai Municipality once completed, unlike the first three packages, which are envisaged to be operated and maintained by the winning PPP contractors.  

J1, J2 and W will be procured under a design-build-finance-operate-maintain model with a concession period expected to be between 25 and 35 years.

J3 will be procured under a design-build-finance model with a concession period ranging between 25 and 35 years.

J1, J2, W and J3 will comprise the deep sewerage tunnels, links and TPS (DLT) components of the overall project.

Meed understands the remaining two packages of the project, the expansion and upgrade of the Jebel Ali and Warsan STPs, will be procured in a process separate from the four DSST-DLT components of the project.

The requests for proposals (RFPs) for the four DSST-DLT packages are likely to be issued in sequential order on a staggered basis around six to 12 months apart.

According to the prequalification document, the bidders for each of the PPP RFPs will be prequalified consortiums comprised of sponsors, EPC contractors and operation and management (O&M) contractors.

Dubai’s Executive Council approved the DSST project in June 2023 and said it would require an investment of about AED80bn ($22bn).

The Council said that the project has been designed to serve the needs of the Dubai population for the next 100 years in alignment with the Dubai Economic Agenda D33 and the Dubai Urban Plan 2040.

Dubai Municipality appointed advisers for the overall scheme last year. It selected Abu Dhabi-headquartered Tribe Infrastructure Group as lead and financial adviser, UK-based Ashurst as legal adviser and the US' Parsons as technical adviser.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11501476/main.jpg
Jennifer Aguinaldo
Related Articles
  • Iranian drones hit Kuwait International airport’s Terminal 1

    3 June 2026

    Kuwait International airport was struck by a fresh wave of hostile drone attacks on 3 June. The drones caused significant structural damage to Terminal 1 and wounded several individuals.

    Brigadier General Saud Abdulaziz Al-Otaibi, official spokesman for the Ministry of Defence, blamed the strikes on “criminal Iranian aggression”. He confirmed that the injured had been evacuated for medical care and stated that the armed forces remain in a state of complete readiness to secure the state.

    The incident is the third major drone strike on the hub in recent months. On 1 April, a drone strike hit fuel tanks managed by Kuwait Aviation Fuelling Company, sparking massive fires. On March 28, another multi-drone raid severely damaged the airport’s primary radar systems.

    The airport is being expanded with the construction of a new terminal, and works on the project are expected to be completed by 2027. It consists of three packages.

    These are:

    • Package 1: Main works – $4,329m
    • Package 2: Multistorey car park building, connection roads, bridges and landscaping works – $550m
    • Package 3: Aircraft parking, runways and service buildings – $950m

    Turkiye’s Limak Holding is executing the main works.

    The terminal building was designed by Foster+Partners and Gulf Consult.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17089683/main.gif
    Colin Foreman
  • Consortium signs PPA for Taweelah C power plant

    3 June 2026

    Emirates Water & Electricity Company (Ewec) has confirmed it has signed a power-purchase agreement (PPA) with a developer consortium for the Taweelah C independent power producer (IPP) project.

    The agreement, which will run through to 2050, was signed with Abu Dhabi National Energy Company (Taqa), Al-Jomaih Energy & Water Company (Saudi Arabia) and Sembcorp Industries (Singapore), the utility said in a statement.

    Taqa will own a 60% stake in the project, with the international consortium holding 40%. The ADX-listed company will also own 40% of the project’s operations and maintenance company, while the international consortium will own 60%.

    Last month, MEED exclusively revealed that the winning consortium had been selected for the project, with the PPA initially expected to be signed in mid-May.

    It is understood that China Energy Engineering Corporation (CEEC) will be the engineering, procurement and construction contractor.

    The combined-cycle gas turbine plant will have a capacity of about 2.5GW. It will be located at the Al-Taweelah power and desalination complex, about 50 kilometres northeast of Abu Dhabi city.

    Taweelah C is part of Ewec’s wider programme to support the UAE’s Net Zero by 2050 Strategic Initiative and the Abu Dhabi Department of Energy’s Clean Energy Strategic Target 2035.

    Ewec plans to raise solar power capacity to 18GW and wind capacity to 2.6GW by 2035, while reducing the carbon intensity of its power generation by more than half compared with 2019.

    The Taweelah C IPP is now expected to start commercial operations in 2029. The facility had previously been scheduled to begin commercial operations in the fourth quarter of 2028.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17089163/main.jpg
    Mark Dowdall
  • Local contractor wins Oman water transmission contract

    3 June 2026

     

    Local contractor Al-Jesr United has won the main engineering, procurement and construction contract to reinforce Oman’s Sur water transmission system.

    The contract, awarded by state-owned utility Nama Water Services (NWS), forms part of a project to improve the reliability of potable water supply to Sur, a coastal city about 200 kilometres southeast of Muscat.

    The scheme, estimated to cost $80m, is designed to strengthen the network’s resilience during peak-demand periods and emergencies.

    The scope of work includes upgrading the pumps at the Sur DP Pump Station with variable frequency drive units and replacing ductile iron pipes and fittings within the facility. It also covers about 17km of new transmission pipelines.

    According to regional projects tracker MEED Projects, at least five local firms submitted commercial bids for the contract, which was tendered in August 2025.

    These include:

    • Al-Jesr United
    • Al-Rafaa Trading & Contracting
    • Gulf Petrochemical Services & Trading
    • Professionals Trading
    • Sarooj Construction Company

    In June 2024, NWS awarded a $1.3m contract for the project’s design and construction supervision to Muscat-headquartered Ibn Khaldun Almadaen Engineering Consultants.

    Sur is home to one of the sultanate’s key desalination plants, which supplies potable water to communities across eastern Oman. 

    The water transmission project will support network expansion in areas such as Al-Aigah and Ahiae, as the existing ductile iron pipeline serving Wilayat Sur is no longer sufficient to meet current and future demand.

    Construction is expected to start in the third quarter of 2026 and take about two years to complete.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17088454/main.jpg
    Mark Dowdall
  • Syria to tender gas plant contract

    3 June 2026

     

    Syria is preparing to tender a project to rehabilitate the Conoco gas plant in Deir ez-Zor province in the east of the country within the next 10 weeks, according to a document published by the US-Syria Business Council.

    The gas plant was reclaimed by Syria’s military during an offensive in January this year.

    It is Syria’s largest gas plant, but is severely damaged and cannot be operated in its current condition.

    Before the country’s civil war, it processed 13 million cubic metres of gas a day.

    The US-based companies ConocoPhillips and Novaterra signed a memorandum of understanding with the state-owned Syria Petroleum Company (SPC) to restore the facility in November last year.

    Syria is currently in the midst of a push to ramp up oil and gas production and establish itself as a regional energy hub.

    Earlier this year, Yousef Qiblawy, chief executive of SPC, said that his organisation was aiming to double national oil production before 2027 and boost output to 800,000 barrels a day by the end of 2029, not including offshore production.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17088320/main.jpg
    Wil Crisp
  • AD Ports enters South America with $835m Brazil deal

    3 June 2026

    Abu Dhabi-listed AD Ports Group has entered the South American market by agreeing to acquire a majority stake in Corredor Logística e Infraestrutura (CLI), Brazil’s leading independent agri-bulk port terminal operator, for an enterprise value of $835m.

    The transaction represents AD Ports’ largest acquisition to date, surpassing its $720m purchase of Spain’s Noatum in 2023, and its $510m purchase of a 51% stake in Dubai-based Global Feeder Shipping in early 2024.

    Under the terms of the agreement, AD Ports will acquire CLI from joint owners Macquarie Asset Management and IG4 Capital. CLI operates two major agri-bulk export terminals under long-term concessions: CLI Norte at the Port of Itaqui, which is 100% owned by CLI, and CLI Sul at the Port of Santos, which is 80% owned. In 2025, CLI handled 17 million tonnes of cargo, generating $178m in revenue and profits of $98m.

    The deal, expected to close in the second half of 2026, subject to regulatory approvals, aligns with AD Ports’ strategy to expand its agrifood vertical. The group has recently secured similar international assets, including a 30-year concession at Jordan’s Aqaba multipurpose port, a $30m investment in Kazakhstan’s Sarzha Grain Terminal, and a clean bulk facility development at Pakistan’s Karachi Port.

    The acquisition also reflects broader economic ties between the UAE and Brazil, where UAE investments total about $5bn. The UAE is currently negotiating a Comprehensive Economic Partnership Agreement (CEPA) with the Mercosur trading bloc, which includes Brazil.

    The major capital deployment follows a period of significant financial growth and international expansion for the Abu Dhabi operator, which is 75.42% owned by sovereign wealth fund ADQ. AD Ports reported record results for 2025, with revenue rising 20% year-on-year to AED20.77bn ($5.66bn) and net profit increasing 16% to AED2.07bn.

    According to its 2025 annual report, the group plans to invest AED2.45bn in port infrastructure development during 2026 alone, alongside AED1.3bn for liquefied petroleum gas and liquefied natural gas storage terminals between 2026 and 2028. To fund higher-return projects and optimise its balance sheet, AD Ports launched an asset monetisation programme in late 2025 targeting the recycling of AED4.6bn of capital.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17087945/main.jpg
    Colin Foreman